NBC FORM 8-01 NEW RENEWAL AMENDATORY OCCUPANCY CLASSIFIED TOTAL ESTIMATED COST P. NUMBER OF UNITS PROPOSED DATE OF CONSTRUCTION TOTAL FLOOR AREA PROPOSED DATE OF COMPLETION whose signature appear herein above known to me to be the same persons who executed this standard prescribed form and acknowledged to me that the same is their free and voluntary act and deed WITNESS MY HAND AND SEAL on the date and place above written Doc no. Page no. Book no. Series No. REPUBLIC OF THE PHILIPPINES ) CITY/MUNICIPALITY OF ) BEFORE ME , at the City/Municipality of DATE_______________________ PLACE ISSUED TIN BOX 3 BOX 4 APPLICANT/OWNER WITH CONSENT : LOT OWNER BOX 5 (SIGNATURE OVER PRINTED NAME) DATE (SIGNATURE OVER PRINTED NAME) DATE ADDRESS: ADDRESS: CTC NO. DATE ISSUED PLACE ISSUED CTC NO. DATE ISSUED PLACE ISSUED OTHERS AGRICULTURAL USE OR CHARACTER OF OCCUPANCY GROUP A RESIDENTIAL DWELLINGS GROUP F INDUSTRIAL OTHERS (specify) GROUP C EDUCATIONAL RECREATIONAL GROUP H RECREATIONAL ASSEMBLY OCCUPANT LOAD LESS THAN 1000 USE OR OCCUPANCY OF BUILDING / STRUCTURE COMMERCIAL RESIDENTIAL OTHERS (SPECIFY) ALTERATION MOVING INSTITUTIONAL INDUSTRIAL RAISING BY AN ENTERPRISE SCOPE OF WORK : DATE OF APPLICATION DATE ISSUED DO NOT FILL-UP (NSO USE ONLY) BOX 1 (TO BE ACCOMPLISHED IN PRINT BY THE APPLICANT) OWNER LAST NAME APPLICATION NO. Republic of the Philippines Davao City Province of Davao Del Sur OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING PERMIT AREA NO. FIRST NAME M.I. TAX ACCT. NO. FORM OF OWNERSHIP FOR CONSTRUCTION OWNED ADDRESS : NO. STREET BARANGAY CITY/MUNICIPALITY ZIP CODE TELEPHONE NO. LOCATION OF CONSTRUCTION : NEW CONSTRUCTION RENOVATION ERECTION CONVERSION ACCESSORY BUILDING STRUCTURE ADDITION REPAIR GROUP B RESIDENTIAL HOTEL APARTMENT GROUP G INDUSTRIAL STORAGE AND HAZARDOUS GROUP I RECREATIONAL ASSEMBLY OCCUPANT LOAD 1000 OR MORE GROUP E BUSINESS AND MERCANTILE GROUP J AGRICULTURAL ACCESSORY GROUP D INSTITUTIONAL BOX 2 FULL-TIME INSPECTOR AND SUPERVISOR OF CONSTRUCTION WORKS (REPRESENTING THE OWNER) ADDRESS PRC NO. VALIDITY ARCHITECT OR CIVIL ENGINEER PTR NO. DATE ISSUED (SIGNED AND SEALED OVER PRINTED NAME) personally apreared APPLICANT NAME C.T.C. No. DATE ISSUED PLACE ISSUED LICENSED ARCHITECT/CIVIL ENGINEER C.T.C. No. DATE ISSUED PLACE ISSUED on FULL TIME INSPECTOR AND SUPERVISOR OF CONSTRUCTION NOTARY PUBLIC (until December________) TCT NO.

Transcript of OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING … · 2020. 2. 4. · DENR ECC for...

Page 1: OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING … · 2020. 2. 4. · DENR ECC for Environmentally Critical Project [Sec. 302.12.b.vi] Engineer/Architect [Sec. 302.3.b-c,

NBC FORM 8-01

NEW RENEWAL AMENDATORY

OCCUPANCY CLASSIFIED TOTAL ESTIMATED COST P.

NUMBER OF UNITS PROPOSED DATE OF CONSTRUCTION

TOTAL FLOOR AREA PROPOSED DATE OF COMPLETION

whose signature appear herein above known to me to be the same persons who executed this standard prescribed form and acknowledged to methat the same is their free and voluntary act and deed

WITNESS MY HAND AND SEAL on the date and place above written

Doc no.Page no.Book no.Series No.

REPUBLIC OF THE PHILIPPINES )

CITY/MUNICIPALITY OF )

BEFORE ME , at the City/Municipality of

DATE_______________________ PLACE ISSUED TIN

BOX 3 BOX 4APPLICANT/OWNER WITH CONSENT : LOT OWNER

BOX 5

(SIGNATURE OVER PRINTED NAME) DATE (SIGNATURE OVER PRINTED NAME) DATE

ADDRESS: ADDRESS:

CTC NO. DATE ISSUED PLACE ISSUED CTC NO. DATE ISSUED PLACE ISSUED

OTHERSAGRICULTURAL

USE OR CHARACTER OF OCCUPANCY

GROUP A RESIDENTIAL DWELLINGS GROUP F INDUSTRIAL OTHERS (specify)

GROUP C EDUCATIONAL RECREATIONAL GROUP H RECREATIONAL ASSEMBLY OCCUPANT LOAD LESS THAN 1000

USE OR OCCUPANCY OF BUILDING / STRUCTURECOMMERCIALRESIDENTIAL

OTHERS (SPECIFY)

ALTERATION MOVING

INSTITUTIONALINDUSTRIAL

RAISING

BY AN ENTERPRISE

SCOPE OF WORK :

DATE OF APPLICATION DATE ISSUEDDO NOT FILL-UP (NSO USE ONLY)

BOX 1 (TO BE ACCOMPLISHED IN PRINT BY THE APPLICANT)OWNER LAST NAME

APPLICATION NO.

Republic of the PhilippinesDavao City

Province of Davao Del SurOFFICE OF THE BUILDING OFFICIAL

APPLICATION FOR BUILDING PERMITAREA NO.

FIRST NAME M.I. TAX ACCT. NO.

FORM OF OWNERSHIPFOR CONSTRUCTION OWNED

ADDRESS : NO. STREET BARANGAY CITY/MUNICIPALITY ZIP CODE TELEPHONE NO.

LOCATION OF CONSTRUCTION :

NEW CONSTRUCTION RENOVATION

ERECTION CONVERSION ACCESSORY BUILDING STRUCTURE

ADDITION REPAIR

GROUP B RESIDENTIAL HOTEL APARTMENT GROUP G INDUSTRIAL STORAGE AND HAZARDOUS

GROUP I RECREATIONAL ASSEMBLY OCCUPANT LOAD 1000 OR MORE

GROUP E BUSINESS AND MERCANTILE GROUP J AGRICULTURAL ACCESSORY

GROUP D INSTITUTIONAL

BOX 2FULL-TIME INSPECTOR AND SUPERVISOR OF CONSTRUCTION WORKS (REPRESENTING THE OWNER)

ADDRESS

PRC NO. VALIDITY

ARCHITECT OR CIVIL ENGINEERPTR NO. DATE ISSUED

(SIGNED AND SEALED OVER PRINTED NAME)

personally apreared

APPLICANT NAME C.T.C. No. DATE ISSUED PLACE ISSUED

LICENSED ARCHITECT/CIVIL ENGINEER C.T.C. No. DATE ISSUED PLACE ISSUED

on

FULL TIME INSPECTOR AND SUPERVISOR OF CONSTRUCTION

NOTARY PUBLIC (until December________)

TCT NO.

Page 2: OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING … · 2020. 2. 4. · DENR ECC for Environmentally Critical Project [Sec. 302.12.b.vi] Engineer/Architect [Sec. 302.3.b-c,

BOX 6 (TO BE ACCOMPLISHED BY THE BUILDING OFFICIAL)

BOX 7 (TO BE ACCOMPLISHED BY THE DIVISION / SECTION CONCERNED)

NOTED

CHIEF,PROCESSING, DIVISION/SECTION

RECEIVING and RECORDING

LAND USE and ZONING

GEODETIC (Line and Grade)

ARCHITECTURAL

STRUCTURAL

SANITARY / PLUMBING

ELECTRICAL

MECHANICAL

Permit is issued to for the proposed

Under , of Group , located at

subject to the following

1) THAT UNDER ARTICLE 1723 OF THE CIVIL CODE OF THE PHILIPPINES, THE ENGINEER OR ARCHITECT WHO DREW UP THE PLANS AND SPECIFICATIONS FOR ABUILDING/STRUCTURE IS LIABLE FOR DAMAGES IF WITHIN FIFTEEN (15) YEARS FROM THE COMPLETION OF THE BUILDING/STRUCTURE, THE SAME SHOULDCOLLAPSE DUE TO DEFECT IN THE PLANS OR SPECIFICATIONS OF DEFECTS IN THE GROUND. THE ENGINEER OR ARCHITECT WHO SUPERVISES THECONSTRUCTION SHALL BE SOLIDARILY LIABLE WITH THE CONTRACTOR SHOULD THE EDIFICE COLLAPSE DUE TO DEFECT IN THE CONSTRUCTION OR THE USEOF INFERIOR MATERIALS.

2). THIS PERMIT ACCOMPANIED BY THE VARIOU S APPLICABLE ANCILLARY AND ACCESSORY PERMITS,PLANS AND SPECIFICATIONS SIGNED AND SEALEDBY THE CORRESPONDING DESIGN PROFESSIONALS WHO SHALL BE RESPONSIBLE FOR THE COMPREHENSIVE AND CORRECTNESS OF THE PLANS INCOMPLIANCE TO THE CODE AND ITS IRR AND TO ALL APPLICABLE REFERAL CODES AND PROFESSIONAL REGULATORY LAWS.

3). THAT THE PROPOSED CONSTRUCTION/ERECTION/ADDITION/ALTERATION/RENOVATION/CONVERSION/REPAIR/MOVING/DEMOLITION, ETC. SHALL BE INCONFORMITY WITH THE PROVISIONS OF THE NATIONAL BUILDING CODE AND ITS IRR.

A. THAT PRIOR TO COMMENCEMENT OF THE PROPOSED PROJECTS AND CONSTRUCTIONS AN ACTUAL RELOCATION SURVEY SHALL BE CONDUCTED BY ADULY LICENSED GEODETIC ENGINEER.

B. THAT BEFORE COMMENCING THE EXCAVATION THE PERSON MAKING OR CAUSING THE EXCAVATION TO BE MADE SHALL NOTIFY IN WRITING TO THEOWNER OF ADJOINING PROPERTY . NOT LESS THAN TEN (10) DAYS BEFORE SUCH EXCAVATION IS TO BE MADE AND SHOW THE ADJOINING PROPERTYSHOULD BE PROTECTED.

C. THAT NO PERSON SHALL USE OR OCCUPY A STREET ALLEY OR PUBLIC SIDEWALK FOR THE PERFORMANCE OF WORK COVERED BY A BUILDING PERMIT.D. THAT NO PERSON SHALL PERFORM ANY WORK ON ANY BUILDING OR STRUCTURE ADJACENT TO A PUBLIC WAY IN GENERAL USE FOR PEDESTRIAN

TRAVEL, UNLESS THE PEDESTRIANS ARE PROTECTED.E. THAT THE SUPERVISING ARCHITECT/CIVIL ENGINEER SHALL KEEP THE JOBSITE AT ALL TIMES A LOGBOOK OF DAILY CONSTRUCTION ACTIVITIES

WHEREIN THE ACTUAL DAILY PROGRESS OF CONSTRUCTION INCLUDING TEST CONDUCTED, WEATHER CONDITION AND OTHER PERTINENT DATE ARE TOINSPECTION PURSUANT TO SECTION 207 OF THE NATIONAL BUILDING CODE.

F. THAT UPON COMPLETION OF THE CONSTRUCTION, THE SAID LICENSED SUPERVISING ARCHITECT/CIVIL ENGINEER SHALL SUBMIT TO THE BUILDINGOFFICIAL DULY SIGNED AND SEALED LOGBOOK, AS-BUILT PLANS AND OTHER DOCUMENTS AND SHALL ALSO PREPARE AND SUBMIT A CERTIFICATE OFCOMPLETION OF THE PROJECT STATING THAT THE CONSTRUCTION OF THE BUILDING/STRUCTURE CONFORM TO THE PROVISION OF THE CODE, ITS IRR ASWELL AS THE PLANS AND SPECIFICATIONS.

G. ALL SUCH CHANGES,MODIFICATIONS AND ALTERATIONS SHALL LIKEWIS E BE SUBMITTED TO THE BUILDING OFFICIAL AND THE SUBSEQUENTAMENDATORY PERMIT THEREFORE ISSUED BEFORE ANY WORK ON SAID CHANGES,MODIFICATIONS AND ALTERATIONS SHALL BE STARTED. THE AS-BUILTPLANS AND SPECIFICATIONS MAYBE JUST AN ORDERLY AND COMPREHENSIVE COMPILATION OF ALL DOCUMENTS WHICH INCLUDE THE ORIGINALLYSUBMITTED PLANS AND SPECIFICATIONS OF ALL AMMENDMENTS THERETO AS ACTUALLY BUILT OR THEY MAY BE AN ENTIRELY NEW SET OF PLANS ANDSPECIFICATIONS ACCURATELY DESCRIBING AND/OR REFLECTING THEREIN THE BUILDING AS ACTUALLY BUILT.

4). THAT NO BUILDING/STRUCTURE SHALL BE USED UNTIL THE BUILDING OFFICIAL HAS ISSUED A CERTIFICATE OF OCCUPANCY THEREFORE AS PROVIDED IN THECODE. HOWEVER, A PARTIAL CERTIFICATE OF OCCUPANCY MAY BE ISSUED FOR USE/OCCUPANCY OF A PORTION(S) OF A BUILDING/STRUCTURE PRIOR TO THECOMPLETION OF THE ENTIRE BUILDING/STRUCTURE.

5). THAT THIS PERMIT SHALL NOT SERVE AS AN EXEMPTION FROM SECURING WRITTEN CLEARANCES FROM VARIOUS GOVERNMENT AUTHORITIES EXERCISINGREGULATORY FUNCTION AFFECTING BUILDING/STRUCTURES.

6). WHEN THE CONSTRUCTION IS UNDERTAKEN BY CONTRACT, THE WORK SHALL BE DONE BY DULY LICENSED AND REGISTERED CONTRACTOR PURSUANT TO THE PROVISIONS OF THE CONTRACTORS LICENSE LAW (RA 4566).

7). THE OWNER/PERMITTEE SHALL SUBMIT A DULY ACCOMPLISHED PRESCRIBED 'NOTICE OF CONSTRUCTION' TO THE OFFICE OF THE BUILDING OFFICIAL PRIORTO ANY CONSTRUCTION ACTIVITY.

8). THE OWNER/PERMITTEE SHALL PUT A BUILDING PERMIT SIGN WICH COMPLIES WITH THE PRESCRIBED DIMENSIONS AND INFORMATION, WHICH SHALL REMAINPOSTED ON THE CONSTRUCTION SITE FOR THE DURATION OF THE CONSTRUCTION.

PERMIT ISSUED BY:

loymi_lapuz_2000

ONE HALF (1/2) OF FIRE SERVICE FUND (FSF)

OTHERS(SPECIFY)

TOTAL

LINE AND GRADE (Geodetic)

FILING FEE

BUILDING FEE

TIME DATE

WE HEREBY AFFIX OUR HANDS SIGNIFYING OUR CONFORMITY TO THE INFORMATION HEREIN ABOVE SETFORTH

BOX 8 (TO BE ACCOMPLISHED BY THE BUILDING OFFICIAL)

BUILDING PERMIT NO. OFFICIAL RECIEPT NO.

ASSESSED FEE ASSESSED BY AMOUNT DUE DATE PAID O.R. NUMBER NSO

LOCATIONAL/ZONING OF LAND USE

PROGRESS FLOWIN OUT

ACTION/REMARKS

BUILDING PERMIT

ELECTRICAL FEE

MECHANICAL FEE

SANITARY/PLUMBING FEE

ELECTRONICS FEE

(Owner/Applicant) (Type of Project)

ENGR. CIRINIA GRACE L. CATUBIGOfficer-In-Charge

Date:___________________NOTE: THIS PERMIT MAY BE CANCELLED OR REVOKED PURSUANT TO SECTIONS 305 AND 306 OF THE NATIONAL BUILDING CODE.

DATE ISSUED DATE PAID

M M D D Y Y M M D D Y Y

PROCESSED BYTIME DATE

Page 3: OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING … · 2020. 2. 4. · DENR ECC for Environmentally Critical Project [Sec. 302.12.b.vi] Engineer/Architect [Sec. 302.3.b-c,

Name of Applicant:

Address:

Use or Type of Occupancy:

Project location:

Name of Authorized Representative:

Contact Numbers of the Authorized Representative:

A. PRE-REQUISITE DOCUMENTS: Subdivision

Approved Development permit (from SP/HLURB)

A.1 Clearances/Certificates (from other Offices)- original with photo copy Building plans should be stamped approved by subdivisionAdministrator (if applicable)1 Zoning Location clearance (CPDO) [sec.302.12.a] 5. other Legal Requirements

2 BFP Fire Safey Evaluation Certificate (FSEC) [Sec.303.10] Photo copy of Owners/Applicants valid I.D with three (3)

3 CSHP (DOLE) D.O. No. 13, 1998; NBC MC no. 02, 2011. specimen signatures.

> up to 2-storey residential or minor repair works: stamped Photocopy of PRC IDs and current PTR and TIN of all the

receive by DOLE Signing professionals [NBC MC No.01, 2005; Item 4]

> construction of commercial bldg.: should be dule B] Technical Documents (by Owner and Hired Professionals)

Approved by DOLE 1 Application letter with duly filled up forms of the following:

4. Others (as deemed applicable) - original with photo copy [Sec. 302]

DPWH clearance (if along National Highway) [Sec.302.12.b.i] 2 Building Permit Form with 6-7 sets of Civil/Architectural

CAAP (ATO) clearance (if applicable) [Sec. 302.12.b.ii] Plans duly signed and sealed by a licensed Civil

DENR ECC for Environmentally Critical Project [Sec. 302.12.b.vi] Engineer/Architect [Sec. 302.3.b-c, Sec. 302.4-5]

Drainage Clearance (from DPWH/CEO) if required in the ECC 3 Sanitary/Plumbing Permit Form with 6-7 sets Plumbing plans

and if there is existing drainage/waterway affected duly signed and sealed bt licensed Sanitary Engineer/Master

Traffic Impact Assessment (TIA) for major Development such as, Plumber [Sec.302.3.g, Sec.302.9]

Malls, Convention Centers, Sports Complex, etc. duly approved 4 Electrical Permit Form with 6-7 sets Electrical Plans Duly signed

by the Traffic Management and Control Board (TMCB) and sealed by a licensed (Registered Professional) Electrical

> Submit approved Site Development plan and parking lay-out Engineer/Electronic Engineer [Sec.302.3.d, Sec.302.6]

and tabulation signed by technical working group. 5 Sketch/lot plan with vicinity map drawn to scale signed and

CEO RROW Clearance (if along City/Brgy/Subd Road) sealed by a licensed geodetic engineer (Sec.302.3.a,Sec.32.11)

A.2] Legal Documents (original with photo copy) and relocation survey plan and reports. (4 copies)

1 Certified True Copy of Land Title (from the Land Registrtion 6 Mechanical permit form with 6-7 sets mechanical plans signed

Authority) [section 302.a.2.ii] and sealed by a licensed mechanical engineer.

2 Certified True Copy of Tax Declaration of the property (from 7 Project Technical Specification (signed and sealed)[Sec.302] (2 copies)

the City Assessor's Office) [Sec.302.a.2.ii] 8 Bill of materials and cost estimates (signed and sealed)[Sec.302] (4 copies)

3 Certified True Copy of Current Real Property Tax 9 Boring and plate load test result/report by licensed civil/

Reciept (from the City Treasurer's Office) [Sec.302.2.a.iii] geotechnical engineer (for Building three storeys and above)

4 Barangay clearance of NO SITE CONFLICT [Sec.302.5] if extending building for additional storey; submit

5 If Applicant is: affidavit that the foundation can carry the proposed additional

Not the Owner of the lot (whichever is applicable) [Sec.302.2.b] floors. (2 copies)

Notarized Deed of Absolute Sale Structural Design analysis for all building (except one storey

Notarized Contract of Lease building and single dettached structure with total floor area of

Notarized Contract of Sale 20sq.m or less)[Sec.302.5.c] (2 copies)

Notarized Authority to Construct from the Lot Owner Seismic analysis [Sec.302.5.3]

And, Notarized Special Power of Attorney (SPA) Picture on Site with landmarks

Corporation: Note: INCOMPLETE DOCUMENTS WILL NOT BE ACCEPTED

Notarized Secretary Certificate appointing the authorized (dili dawaton kung kulang ang mga dokumento)

person who will sign for and in behalf of the company all forms must be filled-up properly, use black ink

only and write legibly

Association Board resolution Received/pre-evaluated as to checklist by:

Applicants Certificate of membership in that community

association Name/Position:City Housing Clearance (if Gov't housing project)a. if City; Box9 should be signed by the City Administrator Date/Time:

b. If NHA: Box9 should be signed by the regional manager

Signature:

loymi_lapuz_2000

Community Association: (for residential buildings)

12

11

Republic of the PhilippinesOFFICE OF THE CITY BUILDING OFFICIAL

City of Davao

CHECKLIST OF GENERAL REQUIREMENTS FOR BUILDING APPLICATIONS

10

Page 4: OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING … · 2020. 2. 4. · DENR ECC for Environmentally Critical Project [Sec. 302.12.b.vi] Engineer/Architect [Sec. 302.3.b-c,

Date :

ENGR. CIRINIA GRACE L. CATUBIG

Officer-In-Charge

Davao City

Sir/Maam:

I(First Name) (Middle Name) (Family Name)

would like to aplply for for my

located at(Complete Address)

I also authorize to(Authorized Representative of the Company)

transact the application with your Office in my behalf.

I/We hereby certify that the documents submitted herein are all true and correct, therefore

falsification on the supporting document in any way will cause disapproval of the permit

application without prejudice t further action that may be undertaken pursuant to Articles 171 &

172 of R.A. 3815, otherwise known as the Revised Penal Code of the Philippines.

Address: Address:

Contact Number: Contact Number:

loymi_lapuz_2000

APPLICATION LETTER

(Signature over Printed Name of Owner) (Signature over Printed Name of Authorized Representative)

Page 5: OFFICE OF THE BUILDING OFFICIAL APPLICATION FOR BUILDING … · 2020. 2. 4. · DENR ECC for Environmentally Critical Project [Sec. 302.12.b.vi] Engineer/Architect [Sec. 302.3.b-c,

NBC Form No. B-17

TO : CITY/MUNICIPAL FIRE MARSHALL

Bureau of Fire Protection, DILG

SUBJECT : APPLICATION FOR BUILDING PERMIT

Pursuant to the provision of Section 303 10 of the Revised Implementing Rules and

Regulation of PD 1093, I have the honor to endorse to your three (3) sets of plans and specification

for the building to be constructed at

for your evaluation, review and/or

recommendation with respect to fire safety and control requirements.

Quoted hereunder is the pertinent provision of Section 303 10 of the Revised

Implementing Rules and Regulations of PD 1096:

Date referred to C/MFM :

Date referred by C/MFM :

Date returned to Building Official :

Date returned by Building Official :

loymi_lapuz_2000

ENGR. CIRINIA GRACE L. CATUBIGOfficer-In-Charge

“The Building Official shall refer three (3) sets of plans and specifications to the

City/Municipal Fire Marshall (C/MFM), Bureau of Fire Protection (BFP), for his review and

recommendations with respect to fire safety and control requirements. The C/MFM

shall submit his report and recommendations to the Building Official within Five (5)

working days from the date referral. Failure of the C/MFM to act within said period

shall mean that the plans and specifications of non-issuance, suspension or

revocation of the said requirements by the C/MFM, he shall so state in writing the

reasons or grounds therefor”.