ODOT DISTRICT 6 2020 CONSTRUCTION PROGRAM MIKE DEWINE, OHIO GOVERNOR | JACK MARCHBANKS, ODOT DIRECTOR | MITCH BLACKFORD, DISTRICT DEPUTY DIRECTOR SERVING DELAWARE, FAYETTE, FRANKLIN, MADISON, MARION, MORROW, PICKAWAY AND UNION COUNTIES Delaware Pickaway Marion Morrow Union Madison Fayette Franklin Delaware Columbus 6

Transcript of ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605...

Page 1: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

    ODOT DISTRICT 6 2020 CONSTRUCTION PROGRAM

MIKE DEWINE, OHIO GOVERNOR | JACK MARCHBANKS, ODOT DIRECTOR | MITCH BLACKFORD, DISTRICT DEPUTY DIRECTOR

SERVING DELAWARE, FAYETTE, FRANKLIN, MADISON, MARION, MORROW, PICKAWAY AND UNION COUNTIES

Delaware

Pickaway

Marion

Morrow

Union

Madison

Fayette

Franklin

Delaware

Columbus6

Page 2: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

21

3

6

4

5

7

8

9

20323

521

656

3

750

257

315

745

71

42

42

4

37

37

3636 36

605

2020 DELAWARE COUNTY ODOT PROJECTS

1. U.S. Route 36 Intersection Safety Add left turn lanes on U.S. 36 and restricted crossing U-turn intersections (RCUT) at U.S. 36/Lackey Old State Rd. and at U.S. 36/North Old State Rd. RCUTs are also known as J-Turns. Start: August 2020 Complete: July 2022 Investment: $1,900,000

2. U.S. Route 36 Safety Upgrades Widen U.S. 36 at Condit Rd. to add left turn lanes, install new traffic signals, and resurface U.S. 36 from south of Condit Rd. to north of Meredith State Rd. Start: July 2020 Complete: October 2020 Investment: $1,100,000

3. State Route 37 Resurfacing Resurface SR 37 from Troy Rd. to U.S. 36 (William St.) and improve drainage on U.S. 23 south of Pennsylvania Ave. ramp. Start: April 2020 Complete: September 2020 Investment: $720,000

4. U.S. Route 42 Intersection Safety Add left turn lanes on U.S. 42 at the intersections of SR 745/SR 257 and SR 257/Klondike Rd., resurface U.S. 42 from SR 745/SR 257 to SR 257/ Klondike Rd., and upgrade guardrail. Start: February 2020 Complete: September 2020 Investment: $2,400,000

5. State Route 257 Resurfacing Repair pavement and resurface SR 257 from SR 750 to U.S. 42 (excluding Home Rd), upgrade guardrail, and bridge work. Start: April 2020 Complete: September 2020 Investment: $1,800,000

6. State Route 745 Resurfacing Resurface SR 745 from south of Glick Road to U.S. 42. Start: April 2020 Complete: October 2020 Investment: $1,200,000

7. Interstate 71 North Side Widening Widen I-71 south between Polaris/Gemini and the ramp to I-270 west, widen ramp from I-71 south to I-270 west to two lanes, construct opening in the barrier wall for Gemini traffic to merge onto I-71 south sooner. Start: April 2020 Complete: October 2020 Investment: $6,200,000

8. Interstate 71 Fiber Installation Install fiber optic cable along I-71 from I-270 to north of U.S. 36/SR 37 to communicate with various Intelligent Transportation System devices. Start: July 2019 Complete: June 2020 Investment: $1,800,000

9. Interstates 71/270 Spot Paving Resurface various locations on I-71 between Morse Rd. and I-270 on the North Side and between the Franklin/Delaware County Line and Lewis Center Rd. Resurface various locations on I-270 at I-71 on the North Side. Start: April 2020 Complete: October 2020 Investment: $1,800,000

Page 3: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

2020 FAYETTE COUNTY ODOT PROJECTS

1. District Spot Paving Repair pavement and resurface SR 207 from north of Wingate Place in Madison County to the Fayette/Pickaway County Line. Start: April 2020 Complete: September 2020 Investment: $1,750,000

4

12

2

2

3

3

4

4

5

6

7

71INTERSTATE

734

729

753

35

35

41

41

62

62

22

22

207

2. State Routes 739 and 734 Preventative Maintenance Chip seal SR 729 from the Fayette/Clinton County Line to SR 323 in Madison County. Chip seal SR 734 from I-71 to SR 38. Start: April 2020 Complete: September 2020 Investment: $1,000,000

3. U.S. Route 35 Resurfacing Resurface U.S. 35 from SR 435 to Harmony Rd. and from Palmer Rd. to SR 753, and bridge work. Start: April 2020 Complete: October 2020 Investment: $7,800,000

4. State Routes 41 and 753 Resurfacing Repair pavement and resurface SR 41 from U.S. 35 to U.S. 22. Repair pavement and resurface SR 753 from U.S. 35 to U.S. 22. Start: August 2019 Complete: August 2020 Investment: $9,300,000

5. U.S. Route 62 Bridge Replacement Replace bridge over Rattlesnake Creek between Greenfield-Sabina Rd. and Miami Trace Rd. Start: April 2020 Complete: October 2020 Investment: $1,600,000

6. U.S. Route 62 Intersection Safety Add new left turn lanes on U.S. 62 at the SR 38 intersection. Start: April 2020 Complete: October 2020 Investment: $885,000

7. Temple Street Bridge Replacement Replace Temple St. bridge over Paint Creek between Veterans Way and U.S. 22 (Clinton Ave.) Start: June 2020 Complete: October 2020 Investment: $870,000

Page 4: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

2020 FRANKLIN COUNTY ODOT PROJECTS

5. Interstate Pump System Rehabilitate the pump station near I-70 and Broad St. Start: January 2020 Complete: January 2022 Investment: $4,300,000

6. Interstate 71 Widening Replace and widen bridges on I-71 over Big Darby Creek, south of U.S. 62. Start: March 2019 Complete: November 2020 Investment: $12,000,000

7. Interstate 71 South Side Mega FIx Reconstruct and widen I-71 between downtown Columbus and Stringtown Road, replace five bridges, reconfigure interchange of I-270 and I-71 south, build new ramp from I-71 south to Stringtown Road, extend the northbound express lane from I-270 to south of Stringtown Road to remove the northbound weave, realign SR 104 (Jackson Pike) to the east to create a separate intersection at Frank Road, widen and realign the exit ramp from I-71 north to Frank Road, and construct two noise walls. Start: August 2017 Complete: December 2020 Investment: $134,000,000

1

4

3

5

6

7

89

11

12

13

20

22

1

2

10

1415

16

16

17

18

19

20

21

23

270

670315

665

62

317

16

104

71

70

33

33

161

161

23

40 40

62

270

70

1. U.S. Route 23 North Side Sign Upgrades Upgrade lane assignment signs to a larger size on U.S. 23 approaching I-270, install additional signs, modify striping on U.S. 23 south to allow a dedicated lane for each entrance ramp. Start: September 2020 Complete: December 2020 Investment: $200,000

2. U.S. Route 33 Resurfacing Resurface U.S. 33 from SR 257/SR 161 to north of Fishinger Rd, replace culvert between Lane Rd. and Henderson Rd., upgrade guardrail. Start: April 2020 Complete: September 2020 Investment: $2,500,000

3. U.S. Route 62 Resurfacing Resurface U.S. 62 from I-270 on the South Side to just north of Belmead Ave., upgrade guardrail and traffic signals. Start: May 2020 Complete: October 2020 Investment: $1,900,000

4. Interstates 70/71 Downtown Ramp Up A series of projects to reconstruct I-70/71 in downtown Columbus, widen I-71 south at Broad St. and I-70/71 between SR 315 and I-71, replace numerous bridges including Broad St., Front St., I-70 bridges over the river, and over the railroad tracks, and rebuild numerous ramps. Projects will also build new urban avenues Lester Dr. and Elijah Pierce Ave. between Spring St. and Broad St., and reconstruct Mooberry St. and Parsons Ave. Start: May 2019 Complete: October 2023 Investment: $250,000,000

8. Interstate 71 North Side Improvements Widen I-71 south between Polaris/Gemini and the ramp to I-270 west, widen ramp from I-71 south to I-270 west to two lanes, construct opening in the barrier wall for Gemini traffic to merge onto I-71 south sooner. Start: April 2020 Complete: October 2020 Investment: $6,200,000

Page 5: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

9. Interstate 71 Fiber Installation Install fiber optic cable along I-71 from I-270 to north of U.S. 36/SR 37 to communicate with various Intelligent Transportation System devices. Start: July 2019 Complete: June 2020 Investment: $1,800,000

10. State Route 104 Resurfacing Repair pavement and resurface SR 104 from the Pickaway County Line to the Columbus Corp. Limit, upgrade guardrail, bridge work. Start: April 2020 Complete: October 2020 Investment: $1,900,000

11. State Route 161 Resurfacing Resurface SR 161 from SR 257 to west of SR 315, including pavement repairs from Linworth Rd. to Olentangy River Rd. Start: August 2019 Complete: July 2020 Investment: $2,300,000

12. Claycraft Road Bridge Improvements Rehabilitate the Claycraft Rd. bridge over I-270, improve drainage, and modify signal at Claycraft Rd. and Morrison Rd. Start: October 2019 Complete: October 2020 Investment: $2,300,000

13. Interstate 270 Noise Walls Construct noise walls along I-270 from Livingston Ave. to Main St. and Main St. to Broad St. Start: October 2019 Complete: June 2021 Investment: $6,600,000

14. Interstate 270 Resurfacing Repair pavement and resurface I-270 between U.S. 23 on the South Side and Alum Creek Dr., and improve five bridges. Start: August 2020 Complete: September 2021 Investment: $7,900,000

15. Interstate 270 Spot Paving Repair pavement at I-270 and U.S. 23 on the South Side. Start: April 2020 Complete: September 2020 Investment: $754,000

16. Interstate Spot Paving Repair pavement and resurface various locations along I-270 from bridge over Big Walnut Creek to U.S. 40, and I-670 from I-70 to railroad tracks, and resurface I-270 north at Claycraft Rd. Start: May 2020 Complete: October 2020 Investment: $600,000

17. Interstate 270 Concrete Repairs Repair pavement on I-270 from I-71 to U.S. 62 on the South Side and from south of I-70 to Alum Creek Dr. on the East Side. Start: August 2020 Complete: November 2020 Investment: $2,000,000

18. Interstate 670 Resurfacing Resurface I-670 from U.S. 23 (4th St.) to I-71 including ramps. Start: September 2020 Complete: September 2021 Investment: $3,500,000

19. State Route 674 Resurfacing Resurface SR 674 from Bent Grass Rd. to Groveport Rd. and from the railroad to Gender Rd., upgrade signs, pavement markings, and traffic signals in Canal Winchester. Start: April 2020 Complete: October 2020 Investment: $900,000

20. Interstates 71/270 Spot Paving Resurface various locations on I-71 between Morse Rd. and I-270 on the North Side and between the Franklin/Delaware County Line and Lewis Center Rd. Resurface various locations on I-270 at I-71 on the North Side. Start: April 2020 Complete: October 2020 Investment: $1,800,000

21. Worthington-Galena Widening Widen Worthington-Galena Rd. to four lanes from Wilson Bridge/Huntley Rd. to Sancus Blvd. Start: July 2020 Complete: July 2021 Investment: $9,000,000

22. Bexley Traffic Signals Install or replace interconnect lines at 17 intersections in Bexley to improve communication between traffic signals. Start: January 2020 Complete: December 2020 Investment: $1,000,000

23. Whitehall Traffic Signals Install or replace interconnect lines at 26 intersections in Whitehall and 1 intersection in Columbus to improve communication between traffic signals. Start: February 2020 Complete: October 2020 Investment: $1,200,000

Page 6: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

2020 MADISON COUNTY ODOT PROJECTS

4 5

61

2

3

70

38

29

142

665

40

32341

71

42

42

3856

1. District Spot Paving Repair pavement and resurface U.S. 62 from Schadel Rd. to the Madison/Fayette County Line. Repair pavement and resurface SR 207 from north of Wingate Place in Madison County to the Fayette/Pickaway County Line. Start: April 2020 Complete: September 2020 Investment: $1,750,000

2. State Routes 729 Preventative Maintenance Chip seal SR 729 from the Fayette/Clinton County Line to SR 323 in Madison County. Start: April 2020 Complete: September 2020 Investment: $1,000,000

3. State Route 38 Resurfacing Resurface SR 38 from the Fayette County Line to Midway St. Start: April 2020 Complete: October 2020 Investment: $2,300,000

4. Interstate 70 Reconstruction Replace seven miles of existing concrete pavement on I-70 with asphalt between U.S. 42 and the Franklin County Line. Start: April 2019 Complete: October 2020 Investment: $50,000,000

5. State Route 142 Bridge Deck Replacements Replace the bridge decks and resurface SR 142 over I-70. Start: August 2020 Complete: June 2021 Investment: $3,000,000

6. State Route 323 Bridge Improvements Repair pavement and resurface bridge deck of SR 323 over Paint Creek (east of SR 729). Start: May 2020 Complete: September 2020 Investment: $430,000

Page 7: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

2020 MARION COUNTY ODOT PROJECTS

1. U.S. Route 23/State Route 203 Resurfacing Resurface and upgrade guardrail on U.S. 23 from SR 98 to SR 529. and on SR 203 from SR 4 to SR 739. Start: April 2020 Complete: October 2020 Investment: $3,900,000

3

4

4

4

11

2

2

2

5 529

984

20337 423

739

47

23

95

309

2. U.S. Route 23/State Route 231 Bridge Work Replace bridge deck on the U.S. 23 bridge over railroad tracks between SR 309 and SR 4 and the SR 231 bridge over U.S. 23. Start: February 2020 Complete: September 2020 Investment: $3,400,000

3. Village of Prospect Resurfacing Repair pavement and resurface SR 47, SR 203 and SR 257 within the village of Prospect corporation limits. Start: May 2020 Complete: September 2020 Investment: $367,000

4. State Routes 309 and 746 Bridge Work Overlay bridge deck on SR 309 west of Holland Rd., overlay bridge deck on SR 309 west of Caledonia, and overlay bridge deck of SR 746 south of SR 95. Start: June 2020 Complete: August 2020 Investment: $320,000

5. State Route 529 Pavement Repairs Repair edge of pavement on SR 529 from Mautz-Yeager Rd. to the Morrow County Line. Start: June 2020 Complete: November 2020 Investment: $1,000,000

Page 8: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

2020 MORROW COUNTY ODOT PROJECTS

314

3

1

2

3

7142

288

61

95746

229

656

42

61

95

1. Interstate 71 Crack Sealing Crackseal I-71 from south of SR 95 to the Marion County Line. Start: July 2020 Complete: August 2020 Investment: $488,000

2. State Route 95 Resurfacing Repair pavement and resurface SR 95 from I-71 to Knox County. Start: April 2020 Complete: October 2020 Investment: $1,600,000

3. State Routes 229 and 529 Resurfacing Repair pavement and resurface SR 229 from County Road 228 to east of I-71. Repair pavement and resurface SR 529 from the Marion County Line to SR 61. Start: September 2019 Complete: August 2020 Investment: $3,000,000

Page 9: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

32

1

104

207

22

22

762

316752

188

138159

7123

23

56

56

62

2020 PICKAWAY COUNTY ODOT PROJECTS

1. State Routes 316 and 752 Resurfacing Resurface SR 316 from Jefferson Ave. to Station St. in the village of Ashville. Resurface SR 752 from U.S. 23 to Fairfield County. Start: April 2020 Complete: October 2020 Investment: $2,800,000

2. State Route 674 Improvements Repair culvert and slide repair on SR 674 north of Perrill Rd. Start: May 2020 Complete: August 2020 Investment: $660,000

3. State Route 762 Bridge Deck Replacement Replace bridge deck on SR 762 over the Scioto River. Start: June 2020 Complete: August 2020 Investment: $239,000

Page 10: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

2020 UNION COUNTY ODOT PROJECTS

1. State Routes 4 and 37 Resurfacing Resurface SR 4 from Scotts Farm Blvd. to SR 37. Resurface SR 37 from Beatty Ave. to the village of Richwood Corp. Limit. Start: August 2019 Complete: June 2020 Investment: $2,000,000

2. State Route 739 Reconstruction Reconstruct SR 739 from north of Honda Pkwy. to SR 347. Start: April 2020 Complete: October 2020 Investment: $914,000

3. State Route 739 Maintenance Chip seal SR 739 from SR 31 to the Marion County Line, including a section of SR 37 that overlaps SR 739. Start: August 2020 Complete: September 2021 Investment: $856,000

1

4

5

6

12

3

739

739

47

347

31

33245

161

42

31

3336

36

4

736

4. Smart Mobility Corridor Develop smart mobility technology by installing fiber optic cable along various local roadways in Union, Franklin, and Logan Counties. Start: August 2019 Complete: July 2020 Investment: $3,700,000

5. Franklin Street Enhancements Install new benches, trash receptacles and decorative street lighting along SR 37 (Franklin St.) in the village of Richwood from north of Fisher St. to the northern Corp. Limit. Start: June 2019 Complete: June 2020 Investment: $910,000

6. U.S. Routes 42/33 Safety Improvements Install turn lanes on U.S. 33 exit ramps to U.S. 42 and add traffic signals at the interchange. Start: September 2020 Complete: November 2022 Investment: $1,800,000

Page 11: ODOT DISTRICT 6 · 2 1 3 6 4 5 7 8 9 203 23 521 656 3 750 257 315 745 71 42 42 4 37 37 36 36 36 605 2020 DELAWARE COUNTY ODOT PROJECTS 1. U.S. Route 36 Intersection Safety Add left

We will serve, innovate, and communicate with purpose. ..

We will be productive, lean, efficient and effective. ..

We will utilize the public resources entrusted to us by.. satisfying the State's transportation needs. ..

We will be the standard of excellence for winter maintenance. ..

We will create a working environment based on trust and mutual respect. ..

We will value the diversity of all ODOT people. ..

We will work together — one team: .. the Ohio Department of Transportation. ..

For more information, contact the ODOT District 6 Public Information Office at (740) 833-8268.

Like us on Facebook: www.facebook.com/ODOTColumbus

Follow us on Twitter: www.twitter.com/ODOT_Columbus

Statewide Traffic Information: www.Ohgo.com

For general information, call (740) 833-8000 or visit ODOT’s Web site at: www.transportation.ohio.gov

To provide safe and easy movement of people and goods from.. place to place, we will:..

• Improve safety; ..

• Take care of what we have; ..

• Make our system better; ..

• Enhance capacity. ..

O U R G U I D I N G P R I N C I P L E S

O U R V I S I O N A long-term, reliable, professional and highly productive organization. ..

O U R M I S S I O N