Ocean General is a semi-submersible rig owned by Diamond Offshore Drilling. It was used for Nam Côn Sơn Basin as there is a deep water area (245m), out of jack-up rig range.

Tension leg Production Platform Drilling vessel Semi-submersible rig

Jack-up rig

Jacket Production Platform Onshore rig

Page 3: Ocean General Overview-part 1

3

Main parts of Ocean General

Cranes

Derrick

Helideck

Main deck

Anchor Controllers

Life boat

Tensioners

Page 4: Ocean General Overview-part 1

4

1. DerrickIt is 50m high, can load 250 tons drill string.

Page 5: Ocean General Overview-part 1

5

Derrick’s function is to support rotating systems loading and drilling equipments’ traveling.

Page 6: Ocean General Overview-part 1

6

Drill floor is under derrick, it is the place where floormen and driller work.

Page 7: Ocean General Overview-part 1

7

2. Main deckFor units, equipments occupied and workers do their jobs.

Page 8: Ocean General Overview-part 1

8

3. Helideck deckSupports taking off and landing of helicopter. Its diameter is 22m.

Page 9: Ocean General Overview-part 1

9

4. CraneThere are always 2 cranes on each rig. They are for transporting containers, equipments and people within the rig and to supply boat.

Page 10: Ocean General Overview-part 1

10

5. Ballasts

A typical part of a semi-sub rig, they are floatable buoys with occupied water inside.

Ballasts

Page 11: Ocean General Overview-part 1

11

6. Tensioners

It is available on a semi-sub rig only. It consist of hydraulic cylinders and cables system.

Tensioners work automatically and continously to minimize the rig’s heave due to sea wave.

Page 12: Ocean General Overview-part 1

12

7. Anchors and anchor controllers

Each semi-sub rig has 8-12 anchors. They keep the rig’s stability and were handled by Anchor Handling Vessel.

The anchor controllers were controlled automatically by Dynamic Balance System to balance the tension of each opposite anchor cables.

Page 13: Ocean General Overview-part 1

13

8. Generators and Power supply systemThere are 4 engines use diesel to ensure the power for system operation and other life activities.

Page 14: Ocean General Overview-part 1

14

9. Circulating system

Circulates the drill mud into the bore hole and support mud logging job.

This system will be regarded with more details in following section.

Page 15: Ocean General Overview-part 1

15

10. Transportationa. Helicopter:

For personnel changeout and moving small items. It takes 1.5 hour from Vũng Tàu Airport to Ocean General by helicopter.