Comprehensive Explanation
Implement precision area navigation (P-RNAV) procedures to
capitalize on the performance benefits offered by approved aircraft
This is an interim objective aimed towards establishing a global RNP
RNAV environment, and individual States, airports and aircraft operators
will need to evaluate the business need for P-RNAV procedures according
to local circumstances; Type - PCP Scope – ECAC; Applicability – All ECAC States, except Slovak Republic; Initial Operation Capability (IOC) – 01/2001; Full Operational Capability (FOC) – 31/12/2023.
ESSIP Plan 2015 / Objective NAV03 3
What is new or has changed since LSSIP 2014
The FOC of the Objective has been postponed from 31/12/2012 to 31/12/2023 to be aligned with the PCP schedule;
Also the deadline for implementation for ASP01, 02, 03, 05, 11 and USE 01, 02 have been postponed from 31/12/2012 to 31/12/2023
ESSIP Plan 2015 / Objective NAV03 4
Link to European ATM Master Plan
[AOM-0601]-Terminal Airspace Organization Adapted through Use of Best Practice;
[AOM-0602]-Enhanced terminal operations with APV using Barometric VNAV;
ESSIP Plan 2015 / Objective NAV03 5
Most important SLoA(s)
ASP01- Develop and implement RNAV arrival and departure procedures for PRNAV approved aircraft;
ASP02 - Provide appropriate terrestrial navigation infrastructure to support RNAV operations;
ASP03 - Train air traffic controllers in RNAV procedures; ASP11 - Develop a Local P-RNAV Safety Case; USE01 - Install appropriate RNAV equipment; USE02 - Train aircrews in RNAV TMA procedures;
ESSIP Plan 2015 / Objective NAV03 6
Most important Finalisation Criteria
ASP01 - RNAV arrival and departures implemented in accordance with EUROCONTROL guidance material and JAA TGL 10 and declared in national AIP, and in use;
ASP02 - Infrastructure assessed and modified if required to meet the requirements for DME/DME procedures;
ASP03 - The necessary training given to controllers responsible for the operation of RNAV terminal procedures;
ASP11 - Local P-RNAV Safety Case finalized and approved by the National Supervisory Authority;
USE01 - All civil transport aircraft operating in ECAC states are capable of P-RNAV operations;
USE02 - Training manuals have been updated to include RNAV TMA procedures. The aircrew is trained accordingly;
ESSIP Plan 2015 / Objective NAV03 7
Supporting Material
EUROCONTROL - Airspace Concept Handbook for the Implementation of Performance Based Navigation (PBN) - Edition 2.0 Url : http://www.eurocontrol.int/sites/default/files/content/documents/navigation/european-ac-handbook-pbn-implement- 2013-web.pdf
ICAO - Doc 9613 - Performance-based Navigation (PBN) Manual - Edition 4 / 03/2013 Url : http://www.icao.int/publications/Pages/catalogue.aspx
ICAO - Doc 8168-Volume II - Aircraft Operations - Volume II - Construction of Visual and Instrument Flight Procedures - Air Navigation Services - Aircraft Operations (PANS-OPS) Software - Edition 5 / 04/2012 Url : http://www.icao.int/publications/Pages/catalogue.aspx
ICAO - Doc 7030 - Regional supplementary Procedures - Edition 5 / 07/2011 Url : http://www.icao.int/publications/Pages/catalogue.aspx
EUROCONTROL - GUID-0114 - Guidelines for P-RNAV Infrastructure Assessment - Edition V1.2 / 04/2008 Url : http://www.eurocontrol.int/sites/default/files/content/documents/navigation/eg0114-p-rnav-infrastructureassessment-vweb.pdf
ESSIP Plan 2015 / Objective NAV03 8
ESSIP Report 2014
ESSIP Plan 2015 / Objective NAV03 9
Links and contacts
Objective Coordinator: Adriatik KOKONA, +32 2 729 3556