O’Donnell-Jones 1 Running head: CAPSTONE PROJECT · O’Donnell-Jones 3 Project 1: U.S....
Transcript of O’Donnell-Jones 1 Running head: CAPSTONE PROJECT · O’Donnell-Jones 3 Project 1: U.S....
O’Donnell-Jones 1
Running head: CAPSTONE PROJECT
MGT6960: Enterprise Project Management- Capstone Project
Jennifer O’Donnell-Jones, #164625
Madonna University
Prof. Thomas Schoenfeldt
July 20, 2008
O’Donnell-Jones 2
Abstract
This paper will discuss five different projects I have worked on throughout my
career and how the various elements I have learned through my education seeking the
Project Management degree can be applied to each of these projects. Each project will
be outlined with the project charter, scope and management plan, and will be analyzed
to show how improvements could have possibly been implemented to make the project
more successful. A matrix will be presented as well to illustrate what elements of the
classes I have taken applied to each project.
O’Donnell-Jones 3
Project 1: U.S. Manufacturing Corporation
Project Charter: U.S. Manufacturing Corporation is a
“leading manufacturer of highly specialized axle
housings for the automotive industry.” (US Mfg., n.d.)
It is a privately owned corporation, founded in 1964 by
Joseph Simon and run today by the founder’s sons.
The sons made all the final decisions and contractual arrangements regarding the
scope of the project and what was purchased for the project. (US Mfg., 2006)
Project Scope: The project was initiated in 2001 due to the company relocating its
world headquarters from Frasier, Michigan to a new facility in Warren, Michigan. The
company I was working for at the time, Creative Office Interiors, Inc., handled the
specifications of finishes, furniture and lighting, as well as the coordination of the move
of their existing furniture and equipment from the Frasier location. From the original
contract (COI, Inc., 2001) the work provided included:
Space planning for approximately 30,000 square feet for the first and second floor offices, including a furniture plan for all areas. (72 hours)
An electrical and lighting plan for all areas. (6 hours)
A room finish specification package, to include flooring, wallcoverings, window treatments and anything else as deemed necessary. We worked within the allocations provided by the architect and general contractor for each of the areas. (38 hours)
Furniture inventory of the existing space and coordination of the existing furniture move to the new location. (3 hours)
The project was initiated in 2001 with the design
component and ended in 2003 when the client
received the certificate of occupancy and was able
to move in.
O’Donnell-Jones 4
Project Management Plan:
Scope Management: With a project this large, it was
difficult to keep to the number of hours that were originally
quoted for the job. We provided additional services for the
client including additional re-configurations, additions and
changes as the project went on, and would charge as appropriate for the additional
services provided. We also purchased the new furniture the client needed for the
facility, and made additional revenue from the sales of the furniture.
Schedule Management: The initial schedule was set by the general contractor we
were working with on the project. From their schedule, we had an approximation of
when we would be installing the furniture and could order the new furniture based on
the manufacturer lead times, and set up installation dates with the movers and furniture
installers. Communication was instrumental with the scheduling of the project- we
would have to call the contractor weekly and visit the site to make sure that the project
was on schedule, and could make adjustments as necessary. When we would have to
make any changes, we would have to contact the manufacturers to adjust shipping
dates (for furniture and accessories) and the movers and furniture installers so they
could make sure there was an opening in their schedule. The installers were critical as
they had to be on site to receive the furniture from the freight companies. We were also
responsible for scheduling the individual freight companies to arrive on site at staggered
times so someone was available to receive and inspect the orders.
Cost and Quality Management: The client was a prior client and had existing furniture
that we had to match, so cost management was not difficult for this project. We had to
O’Donnell-Jones 5
quote new furniture to match the existing for both the systems furniture and office
furniture, and were able to negotiate pricing and discounts with the manufacturers
based on the volume of furniture purchased, the client and prospect of future business.
The quality of the furniture used was mid-to-high end furniture that was appropriate for
the use and area being used. Some areas were used 24-hours, and the furniture had to
be specified to handle extended use. Costs for the finishes were determined by the
architect and general contractor, who gave us a grade or range to work within when
specifying. We selected the finishes based on the use of the area, building codes and
aesthetics desired by the client. The quality of the finishes was dictated by the grade
that was given to us by the contractor. We selected appropriate finishes within the
prices allocated to stay within budget and meet the client’s needs.
Risk Management: Risk was managed through communication with all parties
involved. There is always an elevated risk when working with a general contractor and
when delivering furniture directly to site. When working with a contractor, making sure
the correct finishes are ordered, and that changes in schedule are communicated is
crucial to the success of the project. Furniture delivery to site reduces the risk of
furniture being damaged if it is received at the warehouse by the installer and
transported, but there is an elevated risk of having the manpower at site to receive the
delivery and that the freight companies arrive when they are scheduled. Another risk
that was a challenge in this job was the use of existing and new furniture used together,
and that I came in on the job after it had been started. The furniture plans and
individual cubicles had existing and new pieces in each, making it difficult to track what
furniture was coming from where. When I came in to the project, I had to go through the
O’Donnell-Jones 6
existing inventories and new furniture order to make sure everything was accounted for.
If we had been missing even a few small pieces, it could have held up the installation
until we were able to get in the needed parts from the manufacturer and get the
installers out to the site to finish the installation. Fortunately, the installation went well
the client had relatively little “down-time” with the move of their offices.
Procurement Management: Procurement of all furniture was conducted through
purchase orders faxed to the individual manufacturers. Purchase orders were
completed by the designers who worked on the jobs because they were the most
familiar with the project and what needed to be ordered. We would also have to call
each of the manufacturers to obtain the lead time until shipment for the items so we
could gauge what needed to be ordered based on the project schedule furnished by the
general contractor. Once the furniture order was placed, the manufacture sends an
acknowledgement stating the details of the order as entered and the estimated ship
date. The acknowledgement would be checked against the purchase order for
correctness and any changes that needed to be made were documented in writing.
Ship dates were recorded on the general calendar so everyone was aware when
products were scheduled to ship.
Conclusions: The overall outcome of the project was successful, but there are tools
that could have been employed for management of the project and the time spent on
the design and tracking of different elements. There are furniture specification
programs that work with the drawings with libraries of furniture that create specification
lists based on the furniture used from the libraries in the drawings. This would have
been an invaluable tool in regards of time spent doing inventory and checking for
O’Donnell-Jones 7
correctness whenever a change was made, and eliminated some of the margin for
error. Creation of a database or use of a tool such as MS Project would have helped to
track the project deliverables and to make changes in the project schedule as
necessary; cut down on time spent on tracking and increased the overall job profits.
Project 2: Century 21 Town & Country- Commerce Office
Project Charter: Century 21 Town & Country is one
of the largest Century 21 offices in the state. The
company is privately owned by Mr. John Kersten,
who began his business in 1980 with one office,
eventually expanding to include more than sixteen
offices. (Century 21, 2008) Since, the company has downsized to now having ten
offices in the metro Detroit area. Mr. Kersten was the primary decision maker regarding
all design decisions. Creative Office Interiors, Inc. provided the interior design for Mr.
Kersten on this and several other projects for his real estate offices.
Project Scope: For this project, my firm was contracted to provide the space planning
and furniture drawings for an approximately 20,000 square foot building for one hundred
real estate agents, specifications for all furnishings, purchasing and installation of the
flooring, wallcoverings, window treatments and all furniture. We worked with the
general contractor to provide the specifications for all of the finishes, and had to
coordinate the scheduling for the finishes we were installing (flooring, wallcovering and
window treatments). We had worked with the contractor on prior projects, which helped
in the coordination to get everything installed by the projected occupancy date. This
project began in late 2001, and was finally completed at the beginning of 2003.
O’Donnell-Jones 8
Project Management Plan:
Scope Management: The scope of what we were to provide
was managed through the contract agreements between my
firm and the client. It was clearly outlined what we were
providing and what was the responsibility of the general
contractor. The client was not charged for design time (for providing the space planning
and specifications), so time management in regards to the hours spent on revisions and
contractual changes was not tracked. Any additional services or addendums that were
made to the original contract were handled with new contracts.
Schedule Management: The schedule for overall construction was handled by the
general contractor, who provided us with a Gantt chart at the beginning of the project to
show the different parts of the construction process. From their schedule, we were able
to schedule preliminary dates for finish and furniture installation. As with US
Manufacturing, coordination and communication with the general contractor was
instrumental. We would contact the contractor weekly to make sure everything was on
schedule, and were out at the site frequently when installation was taking place to make
sure we were meeting the allotted time from the given schedule. We ordered the
furniture based on the time frame given and based on the lead times quoted by the
various manufacturers for both the finishes and furnishings.
Cost and Quality Management: The client was very
particular about the styling of the finishes and furniture
selected for his offices. The styling of the furniture and
finishes is traditional, and he used the same finishes for
O’Donnell-Jones 9
most of his offices, especially with new construction. Many of the items were custom
because we were matching items that had been discontinued that he wanted to use
from prior projects, and cost was not much of an issue because the quality of the
finishes was at the level he desired, and would last for years because they were of
better construction. The client was aware that the life-cycle costs of what he was
purchasing outweighed the initial cost investment for the higher quality items.
Risk Management: Risk management for the project was not a primary concern. We
made sure to communicate with the contractor weekly to eliminate any scheduling
issues that would arise. The risk involved with the purchasing of custom items was
minimized by having samples presented prior to ordering that we had to approve, so
there was no risk of something turning out differently that what we had envisioned or
ordered. As with US Manufacturing, we had the larger furniture orders delivered to site,
and had to coordinate the freight companies to have the manpower available at site to
receive their deliveries.
Procurement Management: Prior to ordering anything, we solicit a signed contract for
all items to be purchased from the client. Similar to US Manufacturing, procurement
was completed through the faxing of orders to the various manufacturers, who would
provide us with an order acknowledgement after it was entered, and an estimated ship
date. The acknowledgement would be checked for correctness, and ship dates entered
on a calendar and adjusted as necessary for scheduling changes.
Conclusions: This project overall went well, and was installed with little to no issues.
As with US Manufacturing, and due to the scope of the project, this could also have
benefited from the use of a furniture specification system that worked with the drawings
O’Donnell-Jones 10
to create an itemized list of furniture. This would have cut down on time spent verifying
the quantities of furniture to be ordered. A project management software or creation of
a database would also have helped to track the deliverables for the project in the
ordering and scheduling process. Also, the client is not charged for any of the time that
is spent creating the drawings, which can be hours of work depending on the size of the
building and number of revisions that are required to come to a final solution for the
space. The costs that are involved with this process aren’t associated with the job very
well, and many “gray” areas arise when negotiating costs with the client and justifying
profit margins. A different method could be negotiated with the client to ensure that
both parties come to a reasonable agreement.
Project 3: Century 21 Town & Country- Grosse Pointe Office
Project Charter: This was another project for Mr. Kersten and
his Century 21 offices, but was quite different from the other
project we had completed for him. The office was obtained
through an acquisition of several real estate offices, which he
merged with his own. The Grosse Pointe office was one of the
acquisitions, and was larger than any other office he owned in
the vicinity. He chose to make this location the primary office for this area, and
combined his office with the one that existed. This project was smaller scale, and took
about three months to complete. Time was a factor because the client was paying rent
on the other offices and wanted to get them out as soon as possible to the property he
owned (the new office).
O’Donnell-Jones 11
Project Scope: The Grosse Pointe office needed to have space for fifty to sixty real
estate agents. For this project, my firm was responsible for providing the space
planning, flooring, millwork, window treatments and some of the furnishings. We were
also responsible for the inventory and move of existing furniture, and specifications for
the finishes we were not providing (paint and bathroom finishes). The client was using
furniture from his existing Grosse Pointe office, from storage and purchasing some new
as well.
Project Management Plan:
Scope Management: This project was a little
complicated due to the logistics of the furnishings and
coordinating the scheduling. Because we were using
furniture from multiple locations, it was difficult to
determine sometimes what would work in certain areas
and we did several addendums to the original contract for
additional items as we proceeded through the project.
The client was aware of the conditions and the
possibility, so there were no surprises for any of the involved parties.
Schedule Management: This was another example of a project where we worked with
a general contractor regarding the scheduling and construction of the project. It was a
different contractor than we normally worked with, but communication was still essential.
The painting was complex in this interior because the styling of the building and finishes
was more contemporary and different than what is used in the other offices, so we were
on site much more often to reinsure that the plans were correct and easily understood
O’Donnell-Jones 12
by the painters and contractor. Once the construction and painting was completed, we
had the flooring and millwork installed. The move of the furnishings had to be well
communicated to the employees because everything had to be packed and
disconnected on a Friday so it would be ready to use the following Monday. Overall the
move went smoothly and the office experienced little to no down-time.
Cost and Quality Management: The cost of the interior furnishings was moderate; the
carpeting selected was a contemporary floor tile, so there were no custom design fees
as with Mr. Kersten’s other offices (which use a custom carpet) and installation is less
because of the ease of installing carpet tiles vs. broadloom. The cost of window
treatments was moderate as well as the building shared a common wall with the
neighbors to the west and windows were only along two sides of the building. The
quality of the items was still moderate-to-high to meet the client’s life-cycle expectations
for the interior finishes and furnishings, but because we weren’t purchasing an
exorbitant amount, the costs seemed significantly less than normal. The one place
where costs were high in this project was the installation, because of overtime costs and
the project having to take place on the weekend, there was a fifty percent increase over
the standard installation charges.
Communication and Risk Management: Communication once the project started was
handled in the same manner. Weekly calls weren’t necessary due to the proximity of
the site to our office (within five miles) and that we were involved early in the process
with the painting, we were able to clearly identify if the project was going to experience
any lag and notify the required parties. Fortunately, the project was completed in a
timely manner, and the client was able to move his office within the three month target
O’Donnell-Jones 13
date. Risks in this project were nominal, aside from the unknown working with a
different contractor. We were fortunate to have developed an agreeable working
relationship and future resource for construction projects. The other risk would be in the
matching of existing furniture to new furniture. We minimized the risk by retaining the
prior contracts to refer to for some of the furniture, and were able to work with the
manufacturer’s representative to match to some of the discontinued items.
Procurement Management: We obtained a signed contract after showing the client
samples of all interior elements for the finishes and furniture we were providing. Once
we have the signed contract and deposit, we proceed with contacting the manufacturers
to determine the lead times for all items we have to order. After receiving a schedule
from the contractor, it’s determined when the orders have to be submitted to the various
manufacturers based on when we need the item for installation. Acknowledgements
are sent from the manufacturer to verify the entered order, and checked to confirm they
match the purchase order. Items for smaller jobs such as this were sent directly to the
installer, and it would be our responsibility to correspond all ship dates, manufacturer
and freight company installation to them.
Conclusions: This project would have definitely benefited from the inclusion of design
time into the overall project scope for charging the client. Several hours were spent on
space planning of this building, and it changed several times due to the logistics of
merging several offices. Also, I believe a better system could be employed or initiated
to correspond with the installation companies. Everything was sent gradually as we
received acknowledgements from the various companies. They would have a listing of
the items from what was sent to them to get the initial quote, but sometimes changes
O’Donnell-Jones 14
were not communicated and there was no real outline to keep all parties on the same
page. I think that the database would have worked well in this application- once the
acknowledgements had been received from all manufacturers, a query could be run that
had all relevant information for the warehouse/installation company, sorted by date,
cross referenced with the installation plan, so they knew exactly when they were to
receive everything and where it was to be installed. This is especially crucial in projects
similar to this one, where existing and new furniture is used together.
Project 4: Automotive Youth Educational Systems (AYES)
Project Charter: The Automotive Youth Educational Systems is a non-profit partnership
among participating automotive manufacturers, participating dealers, and selected high
schools/tech prep schools. It's designed to encourage young people to consider
satisfying careers in retail automotive service, and prepare them for entry-level career
positions or advanced studies in automotive technology (AYES, 2008). AYES
contacted my firm in 2003 to provide space planning for their relocation to a new, larger
suite in their office building. I worked primarily with the director and her assistant of the
Troy, MI branch.
Project Scope: The project began with a contract for a total of fifteen hours of space
planning and design work to include:
Furniture plan with systems furniture reconfiguration
Existing furniture inventory
Installation plans for furniture move
Blueprint copies for the client
Furniture and electrical specifications
Revisions to furniture/space plan as necessary After filling the above contractual agreement, the client retained our services for
additional time, including the tagging of existing furniture and coordinating the move to
O’Donnell-Jones 15
the new office. We also helped with the selection and specifications of finishes for the
new suite, and provided a few new pieces of furniture as required for the systems
furniture reconfiguration (cubicles).
Project Management Plan:
Scope Management: Because there was no furniture and little furnishings purchased
for this project and it was primarily based on contracted design services, it was relatively
easy to track the number of hours worked and keep the time used within the scope of
the contract. Some of the “gray” areas were in regards to meeting time and trips to the
site- these were usually not included in the quoted hours to the client. The client was
understanding and agreeable when a new contract had to be signed because the time
in the prior one had been exhausted.
Schedule Management: During this project, we had to rely on communication with the
client to schedule the installation and move of the furniture. The move was based on
the projected construction completion date given by the building owner/management
company. The delivery of furniture was not a factor due because there were only a few
parts that were needed, and they had a short lead time from the manufacturer. Once
the construction was completed, we only had to schedule the move date with the
installation company.
Cost and Quality Management: Cost and quality were not much of an issue with this
project. The costs were mostly design-related, and the client was charged at a
competitive hourly rate for all services provided. The installation company’s charges
were also competitive with other companies in the area. The installation took place on
the weekend, so the cost was fifty percent above the standard rates. Quality was not
O’Donnell-Jones 16
much of an issue on this project. The installation company we had worked with on
several prior projects and were confident in the level of work they provided. The quality
of the furniture we were working with was good, and the re-configuration of the systems
furniture went smoothly and without any issues.
Communication and Risk Management: The main risk was in communication with
this project, because we did not have direct contact with the construction manager and
had to rely on the client to communicate the schedule and any changes that may have
arisen. There is also always some risk when executing a systems furniture re-
configuration, because each manufacturer is a little different in their joinery and
allocations, and I was not familiar with the systems furniture the client had. I was able
to rely on the installation company and to assist with the identification of the systems
furniture and the manufacturer’s representative in ordering the additional parts needed.
Procurement Management: The procurement procedure was straightforward and
simple on this project, being primarily for design services and with the installation
company for the move. The only area we had to work with an outside vendor was for
the purchase of the systems furniture component, and the delivery of these to the
warehouse was not an issue because they were easily stored parts.
Conclusions: This project overall was one of the easier and straightforward of all the
projects I worked on when in the design industry. There was minimal risk involved, and
the amount of work done in the office was almost all billed directly to the client. A
project management tool would have been beneficial for inventory of the client’s
furnishings, and all the parts that were used in the systems furniture configuration, as
O’Donnell-Jones 17
the client continued to come to us for additional design services and re-configurations
as their business and needs grew.
Project 5: Park Rite- St. Clair Shores Office
Project Charter: The Park Rite Corporation was founded in 1975 by three brothers and
provides parking services in Detroit, Ann Arbor and Dearborn. We became referred to
Park Rite after one of the brother’s businesses moved in to our firm’s neighboring suite.
Park Rite had purchased a small office building in St. Clair Shores to run some of their
operations from. We worked with two of the three owners, and one of their sons who
would be working in the building, on the project. (Park Rite, n.d.)
Project Scope: This project was smaller in scope, and the client had purchased the
building. My firm was contracted to create all necessary drawings for construction, as
well as supply the finishes and furniture for the client to occupy the space. Construction
for the space was contracted by the client to be completed by a family member. We
provided the demolition drawings for the contractor that showed what existing walls
needed to be removed, and where new walls should be installed.
Project Management Plan:
Scope Management: The building was small, and we did not charge for the design of
the space planning for the construction documents because the client was purchasing
all of the finishes and furniture from us, and the profit for the project was built into their
prices. Any items that were added after the initial contract was signed were done as an
addendum to the original contract. The client later added flooring for one of the storage
rooms and reconfigured one of the offices’ systems furniture when they added another
person to their staff.
O’Donnell-Jones 18
Schedule Management: There were some conflicts with the scheduling of the
installation of furniture due to construction delays. The client was a little laissez-faire
because they owned the building, family was completing the construction at a
discounted rate, and they had signed our contract and given us a deposit for the items
to be purchased. The client in this case was also our liaison for information regarding
the construction schedule and when we could plan to install the finishes and furnishings.
The project ended up taking a few months longer than the original completion date. We
had ordered the finishes and furniture based on the original date, as changes in the
construction schedule were not corresponded with us. As a result, our installation
company wanted to charge storage fees for the furniture it was holding in their
warehouse, waiting to install. We had to negotiate with the installers and the client to
get a commitment to the completion of the project or would have had to pass on storage
fees to the client for their new furniture that was sitting in storage.
Cost and Quality Management: The client had requested a traditional to transitional
style at a competitive price point. We selected a transitional furniture style for the office
furnishings, and used systems furniture for the other areas. The furniture selected was
a medium-level quality, well-constructed that will serve the client well for its purpose.
The finishes selected were commercial-grade quality based on the aesthetics the client
desired with the quality needed for the applied use.
Communication and Risk Management: Communication proved to be the main
source of risk in this project. Dealing with a contractor that is related to the client proved
problematic. To circumvent this, we should have had a solid line of communication for
scheduling changes. There were not many other risks related with this project aside
O’Donnell-Jones 19
from having to negotiate with the installation company to hold the furniture longer than
they should have.
Procurement Management: Procurement of deliverables was handled in the same
manner as other projects. When we received the signed agreement from the client,
manufacturers were contacted to determine the lead times for all elements to be
ordered. From this information and the construction schedule provided, we scheduled
the purchase orders to be submitted as needed based on the lead times and scheduled
installation dates. This could have been managed more effectively though better
communication with the client and construction company.
Conclusions: The end result of the project was positive. Once everything was
installed, the client was pleased with their new office building. As noted above, better
lines of communication would have proved beneficial, but the overall results were
positive and the client did return for more work in the future. As with other projects, a
project management tool for scheduling and tracking of orders would eliminate some of
the time spent when changing elements and being able to project due dates.
O’Donnell-Jones 20
Below is a matrix that maps the elements I have learned in the MS Project Management
courses to the projects I have explored as part of this assignment (information for matrix
was obtained from http://www.madonna.edu/pages/mspromgtrc.cfm):
O’Donnell-Jones 21
References Automotive Youth Educational Systems. (2008). General Information. Retrieved June
10, 2008 from https://www.ayes.org/about/general_information. Century 21 Town & Country. (2008). Our History. Retrieved June 5, 2008 from
http://www.century21town-country.com/aboutus/history.asp. Kerzner, PhD., H. (2006). Project Management: A Systems Approach to Planning,
Scheduling and Controlling. (9th ed.). John Wiley & Sons: New Jersey. Meredith, J. R. & Mantel, Jr., S. (2006). Project Management: A Managerial Approach.
(6th ed.). John Wiley & Sons: New Jersey. Park Rite. (n.d.) Company information retrieved June 10, 2008 from
http://www.park-rite.com/index.html. Photos for Century 21 and U.S. Manufacturing retrieved June 21, 2008 from Creative
Office Interiors, Inc. (2008). http://www.creativeofficeinteriorsinc.com. Project Management Institute. (2004). A Guide to the Project Management Body of
Knowledge. (3rd ed.). Project Management Institute: Pennsylvania. U.S. Manufacturing Corporation. (2006). About Us. Retrieved June 1, 2008 from
http://www.usmfg.com/aboutus.aspx.