NUOL Campus Intranet (Team 5) Final presentation 2004-05-24 NUOL Intranet Project Final Presentation Team 5 E-mail: [email protected] http://csd.ssvl.kth.se/~csd2004-team5

Transcript of NUOL Campus Intranet (Team 5) Final presentation 2004-05-24 NUOL Intranet Project Final Presentation...

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

NUOL Intranet Project

Final Presentation

Team 5E-mail: [email protected]://csd.ssvl.kth.se/~csd2004-team5

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Agenda

• Introduction

• Goals

• Working Methodology

• Results

• Future plan

• Summary + Video

• Questions

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

INTRODUCTION

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Introduction

Team members:

• Khamphanh Sithavong, NUOL, Laos

• Virasack Rajpho, NUOL, Laos

• Manivone Dokdouangnary, NUOL, Laos

• Sahar Moosavi, KTH, Sweden

• Rafic Dalle, KTH, Sweden

´

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Introduction

• Cooperation between NUOL and KTH

• Sponsored by Sida

• Part of a 2-year ICT-development plan for NUOL

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

GOALS

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

2 – year goalBuild computer rooms with LANs at 15 faculties, to enable students and staff to use computers and Internet for educational purposes.

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

• Build computer room with LAN in 5 faculties- 15-20 computers- 1 DHCP- 1 print server- 1 network printer

• Software for the computers:- Linux RedHat 8- Lao fonts

Main goal

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Sub goal

• Train 2 administrators from each faculty- To have sufficient knowledge for maintaining the computer rooms

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Working

Methodology

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Two main phases

• Sweden 10 weeks – theoretical part- Preparing for the implementation

• Laos 6 weeks– practical part- The actual implementation

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Sweden phase

• Training- Links and LANs- DHCP- User manuals

• Research- Print server- Software installation

• Simulation - Similar scenario

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Laos phase

• Prepare the computer room- Cable installation

• Install and configure computers- Install Linux and Lao fonts

- Configure DHCP and Print server

• Train local administrators

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Results

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Requirements for the computer rooms

• Room requirements

-Power supply (power sockets and APS for power backup)

-Cooling

-Security locks and fence

When all the requirements were met the team started with the installation

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Installation

• The first step of the installation was to draw all UTP cable.For safety reason all the cables in the computer room where run through wire ways.

• The Second step was to install socket into both end of the UTP cables.

• Third step was to install the hardware (workstation, server and printer) in there final position.

• Step four was to load all software and configure the servers and computers

• And the last Step was the final test. -Check that the hardware was working properly-Verify that all the clients had Lao font and the operating system Red hat working properly. -Try to print from the client machine-Make sure that all the client can access the internet

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

• 13 computers

• 1 DHCP & Printer server

• 1 network printer

• UTP cables (wire ways )

• Software: Red hat 8 and Lao font

• Internet connection

Faculty of Letters

24 port

NAT

DHCP & Printer server

Network Printer

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

• 14 computers• 1DHCP and printer server• 1 Network printer• UTP cables (wire ways), outdoor cable• Software: Red Hat 8 and Lao font• Internet connection

School of Foundation studiesDHCP and

Printer server

24 port

NAT

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

• 15 computers• 1DHCP and printer server• 1 Network printer• UTP cables (wire ways), outdoor cable• Software: Red Hat 8 and Lao font• Internet connection

Faculty of Law

24 port

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

• 15 computers• 1DHCP and printer server• 1 Network printer• UTP cables (wire ways)• Software: Red Hat 8 and Lao font• Not installed yet: 24 port switch

DHCP & printer server

NATFaculty of Education

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Faculty of Irrigation

• UTP cables (wire ways) and outdoor cable

• 4 computersNot installed yet: - DHCP and Printer server - Network printer-11 computers-24 port switch

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Training

• Links and LANs

• DHCP

• All training documents were translated into the Lao language

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Problems

• Hardware-Long delay-Faulty hardware

• Samba server

• Software -License problem

• Different hardware

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Future Plan

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Future Plan

• Training

• Software

• Computer

• Power cut

• Financial situation

• Maintenance of the computer rooms

• Network plan

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Follow up

• ITCenter

• 3 administrators

• 10 faculties

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

I would like to thanks all the team member for

their high contribution and the hard work they have

provide making this project a success.

And hopefully all our recommendation will be

implemented so in the future no problems will be

faced during future activities.

Conclusion

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Summary• Main goals

• 6 weeks in Vientiane

• 4 of 5 computer rooms

• Hardware delay

• Administrators (ITCenter)

• More computers

• Training

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

VIDEO

NUOL Campus Intranet (Team 5) Final presentation 2004-05-24

Questions?

Team 5: Intranet([email protected]://csd.ssvl.kth.se/~csd2004-team5)