Katy Börner and the NWB Team @ IUB Victor H. Yngve Professor of Information Science
Nunavut Water Board (NWB) Community Presentation Type “A” Water Licence Process for Baffinland...
-
Upload
silvester-hudson -
Category
Documents
-
view
213 -
download
1
Transcript of Nunavut Water Board (NWB) Community Presentation Type “A” Water Licence Process for Baffinland...
Community Session – January 16, 2013
Nunavut Water Board (NWB)
Community Presentation
Type “A” Water Licence Process
for
Baffinland Iron Mines Corporation’s (BIMC)
Mary River Project
1
Background Information about the NWB
An institution of public government established under Article 13 of the Nunavut Land Claims Agreement (NLCA)
The objects of the NWB are to provide for the conservation and utilization of waters in Nunavut, except in a national park, in a manner that will provide the optimum benefit from those waters for Nunavut’s resident in particular and Canadians in general
NWB has the responsibilities and powers over the regulation, use and management of freshwater in the Nunavut Settlement Area
2Community Session – January 16, 2013
Community Session
Application before the BoardBIMC’s Type “A” Water Licence Application
Twenty-Five (25) year licence (2013-2038) for the use of water and the deposit of waste in support of the Mary River Project
Water use, including water crossings, and waste disposal activities are planned for three project sites: Milne Port Site, the Mine Site and Steensby Inlet Site
Estimated water use is 1585 cubic metres/day the during the peak construction period
Estimated water use is 625 cubic metres/day during the peak operation period
3
BIMC’s Type “A” Water Licence Application Cont.
Existing or proposed water sources are as follows: Milne Port – Phillips Creek, 32 km Lake Mine site – Camp Lake Steensby Inlet – 3km and 10 km Lakes Railway Camps – Cockburn Lake, Nivek Lake, and
Raven Camp Lake Construction activities (bridges, etc.) – mostly
unnamed sources
Types of waste disposal activities anticipated include but are not limited to waste rock, sewage and sewage sludge, fuel/oil contaminated water, solid waste, contaminated soil and/or water, hazardous waste storage, and bulky items/scrap metal disposal
4Community Session – January 16, 2013
Type “A” Water Licence ApplicationProcedural History
March 2, 2012 – NWB acknowledged receipt of BIMC’s Type “A” water licence application
March 9, 2012 – BIMC provided an errata document in support of its Type A water licence application
April 13. 2012 – NWB issued its completeness review for BIMC’s Type “A” water licence application and requested that interested parties begin their completeness check and technical review of the application
April 25, 2012 – BIMC provided its response to the relevant Final Environmental Impact Statement IRs, some of which pertained to the Type A water licence application
5Community Session – January 16, 2013
Procedural History of BIMC’s Type “A” Water Licence Application Cont.
October 12, 2012 – BIMC Provided its response to technical review comments submitted by interveners in June 2012 for the Type “A” water licence application
October 18, 2012 – NWB held a Pre-Technical Meeting for the BIMC’s Type “A” water Licence Application
October 31, 2012 – BIMC provided its response to relevant issues raised during the Pre-Technical Meeting held in October 2012
6Community Session – January 16, 2013
Procedural History of BIMC’s Type “A” Water Licence Application Cont.
December 14, 2012 – NWB distributed correspondence, which included a draft agenda, informing interested parties of the location/dates for the Technical Meeting and Pre-Hearing Conference planned for the Mary River Project
January 7, 2013 – NWB issued updated information pertaining to the Technical Meeting and Pre-Hearing Conference scheduled for the Mary River Project
January 11, 2013 – NWB distributed the agenda and list of confirmed representatives for the Mary River Project Technical Meeting & Pre-Hearing Conference
7Community Session – January 16, 2013
NWB Type “A” Water Licensing Process
8
NWB receives application and confirms classification of undertaking and type of licence as type A.
NWB conducts concordance review
If required, applicant provides
additional information.
NWB issues notice of application (minimum 30 days).
Next Slide
Community Session – January 16, 2013
NWB Type “A” Water Licensing Process
9
NWB holds TM and PHC
NWB issues notice of Public Hearing (minimum
60 days).
If required, applicant provides
additional information.
If directed in PHC decision, applicant provides additional
information.
.
TechnicalReview Phase
We are at this stage
NWB Issues PHC Decision
Next Slide
Parties submit written representations.
.
Community Session – January 16, 2013
NWB Type “A” Water Licensing Process
10
Parties exchange written interventions.
Parties prepare for public hearing.
Minister approves of the issuance
of the licence.
Minister does not approve
of the issuance of the licence.
Minister approves of
NWB decision.
Minister does not approve
of NWB decision.
NWB holds Public Hearing.
NWB issues decision not to approve of application with
reasons to Minister.
NWB issues decision to approve of application and
licence to Minister.
Community Session – January 16, 2013
Next Steps in the Water Licensing Process for the Application
Technical Meeting (TM) was held earlier today and the Pre-Hearing Conference (PHC) will be held tomorrow
One of the main objectives of the Technical Meeting and Pre-hearing Conference is to help the Board determine whether all substantive issues have been or are being addressed prior to any Board decision to a schedule a Public Hearing
Following the TM-PHC, the NWB will issue a PHC report, which will include a decision on if and when a Public Hearing for the Application will be scheduled
Following the Public Hearing, should a licence be issued, a licence and decision will be submitted to the Minister of AANDC for approval
11Community Session – January 16, 2013
Objectives of Tonight’s Meeting
Promote community awareness of and participation in the type “A” water licensing process for the Mary River Project
Provide the opportunity for community members to meet face-to-face with other stakeholders as well as provide feedback on the application that is before the Board
Listen and note the concerns and views that community members may have with respect to BIMCs Application and the water licensing process for the application and to answer relevant questions that community members may have
To provide consultation opportunity and information, as well as invite participation in the formal Public Hearing process when scheduled
12Community Session – January 16, 2013
Objectives of Tomorrow’s Pre-Hearing Conference
Formal meeting with the Applicant and intervening parties, including, AANDC, EC, DFO, QIA and interested community members, to discuss various matters in preparation for a potential future Public Hearing for the Application including:
Who will participate in the hearing Issues to be addressed during the hearing Schedules and timelines for participation Exchange of information prior to a hearing
13Community Session – January 16, 2013
How can the Community Participate?
Attendance at this community session on the Application
Attend tomorrow’s Pre-Hearing Conference
Contact the Nunavut Water Board
Visit the NWB’s ftp site
Attend any Public Hearing held for the Application
14Community Session – January 16, 2013
NWB Staff Damien A. Côté, Exécutive Director
Email: [email protected]
David Hohnstein, Director of Technical Services
Email: [email protected]
Ben Kogvik, Interpreter and Board Secretary
Email: [email protected]
Sean Joseph, Technical Advisor
Email: [email protected]
Megan Porter, Licensing Administrative Assistant
Email: [email protected]
15Community Session – January 16, 2013
Contact InformationNunavut Water Board
P.O. Box 119
Gjoa Haven, NU
X0B 1J0
Tel: 867-360-6338
Fax: 867-360-6369
Web Site: www.nunavutwaterboard.org/en/home
Ftp site: http://nunavutwaterboard.org/ftp/
16Community Session – January 16, 2013