NuMI Operation Summary: 2005-2012

16
1 NuMI Operation NuMI Operation Summary: Summary: 2005-2012 2005-2012 Sam Childress - Fermilab 7 Nov. 2012 CERN NBI 2012 1 NuMI Beam Layout: 735 km baseline to Soudan, MN. far detector -> beam pitch angle = 58 mrad. •Optimized for medium – high energy neutrino beam and tunability (designed before oscillation parameters were known)

description

NuMI Operation Summary: 2005-2012. NuMI Beam Layout:. Sam Childress - Fermilab. 735 km baseline to Soudan, MN. far detector -> beam pitch angle = 58 mrad. Optimized for medium – high energy neutrino beam and tunability (designed before oscillation parameters were known). 1. - PowerPoint PPT Presentation

Transcript of NuMI Operation Summary: 2005-2012

Page 1: NuMI Operation Summary: 2005-2012

1

NuMI Operation Summary:NuMI Operation Summary:2005-20122005-2012

Sam Childress - Fermilab

7 Nov. 2012 CERN NBI 2012 1

NuMI Beam Layout:

• 735 km baseline to Soudan, MN. far detector -> beam pitch angle = 58 mrad.

•Optimized for medium – high energy neutrino beam and tunability (designed before oscillation parameters were known)

Page 2: NuMI Operation Summary: 2005-2012

22CERN NBI 2012

120 GeV protons

Focusing Horns

2 m

675 m15 m 30 m

Target Decay Pipe

π-

π+

νμ

νμ

• Neutrino energy tuned by moving target (usually Low Energy)

• Change horn polarity to select νμ or νμ

7 Nov. 2012

NuMI Neutrino BeamNuMI Neutrino Beam

Page 3: NuMI Operation Summary: 2005-2012

3

Primary Proton LinePrimary Proton Line

Total length ~ 350 m

MI tunnel

bringing the protons to the correct pitch of 58 mrad

bending down by 156 mrad

final focus

trim magnets

carrier tunnel~70 m

beam pipe 12” Ø

Main Injector

NuMI line

Recycler

7 Nov. 2012 CERN NBI 2012 3

Page 4: NuMI Operation Summary: 2005-2012

47 Nov. 2012 CERN NBI 2012 4

Graphite TargetGraphite Target

Graphite Fin Core

2 interaction lengths

Water cooling tube

provides mechanical support

Low Energy Target fits in

horn without touching

Page 5: NuMI Operation Summary: 2005-2012

57 Nov. 2012 CERN NBI 2012 5

Horn System – 2 HornsHorn System – 2 Horns(Shown in work cell, hanging from support module)(Shown in work cell, hanging from support module)

Page 6: NuMI Operation Summary: 2005-2012

6

Other NBI 2012 Presentations Other NBI 2012 Presentations Covering Details of NuMI Beam

Operation

• Proton Beam Monitoring & Control - S. Childress• Secondary Beam Monitoring - L. Loiacono• Recent Experience with NuMI Targets & Dumps – J. Hylen• Horn Design - J. Hylen• NuMI Experience with Tritium - J. Hylen

7 Nov. 2012 CERN NBI 2012 6

Here, will provide a brief summary of the 7 years of NuMI beam operation – some challenges & successes, along with key lessons learned. Our beam data is summarized by Fiscal years (Oct – Sept).

Page 7: NuMI Operation Summary: 2005-2012

7

• But… Target after 1 week of beam operation, March 2005

• Very successful beam commissioning!

• Photos after day 1, Dec. 2004. Thanks, Malika ! for working

with us.

F Y 2005: Commissioning & F Y 2005: Commissioning & Beginning OperationsBeginning Operations

7 Nov. 2012 CERN NBI 2012 7

And the serious work of operating a high power neutrino beam begins!

Total POT in FY 2005 = 6.56 x10**19

Page 8: NuMI Operation Summary: 2005-2012

8

FY 2006 : Horns, Target & FY 2006 : Horns, Target & TritiumTritium

• Oct: Horn 2 ground fault• Dec: Find Tritium in lab ponds -> from

NuMI. Initial mitigation.• Feb: Tritium analysis in decay tunnel &

dehumidification mitigation• July: Horn 1, DI bottle beads• Aug: Horn 1 water leak Target Z drive stuck; Replace NT01 with

NT02

Total POT in FY 2006 =1.02 x10**20

Horn Water Line Ceramic IsolatorFracture at Geometry Change-Thin Wall-Stress Concentration Area-Shear Failure Appearance

7 Nov. 2012 CERN NBI 2012

Page 9: NuMI Operation Summary: 2005-2012

9

FY 2007 : PB Dipole, Horns FY 2007 : PB Dipole, Horns & Tritium& Tritium

• Feb: Primary beam dipole water leak.

• July – Aug: Horn water leak.• Aug - Sep: Target chase

dehumidification for tritium mitigation.

Replacing a primary beam 3 meter dipole. Ceramic isolator water leak.Total POT in FY 2007 =1.91 x10**20

Commission multi-batch slip-stackingin Main Injector! K. Seiya

7 Nov. 2012 CERN NBI 2012

Page 10: NuMI Operation Summary: 2005-2012

10

FY 2008 : Horns, FY 2008 : Horns, Decay WindowDecay Window & PB Quad. & PB Quad.Implement Multi-batch Slip-stackingImplement Multi-batch Slip-stacking

• Nov: Horn 2 water leak.• Oct – Nov: Change from vacuum

to He in decay pipe. • Jan – Implement multi-batch slip-

stacking. Increase from 5 to 9 Booster batch normal operation.

• Feb – Mar: Horn 2 water leak. Replace ceramic isolators with new design.

• Mar: PB Quad failure. • June – July: Horn 1 water leak;

replace Horn 1.

7 Nov. 2012 CERN NBI 2012 10

Decay window inspection shows oxidation beam profile. Change from vacuum to He in decay to mitigate pressure on window.

Total POT in FY 2008 =1.99 x10**20

Page 11: NuMI Operation Summary: 2005-2012

11

FY 2009 : Horn Stripline, Target FY 2009 : Horn Stripline, Target & Tritium& Tritium

• Nov – Dec: Replace Horn 2; strip-line failure

• May – PB tunnel flood due to blockage under target hall.

• June – Change target NT02 to NT03. Graphite “depletion”

• June – Add dehumidification to Beam Dump region.

Water backup in PB Pretarget tunnel.

Total POT in FY 2009 =2.18 x10**20

7 Nov. 2012 CERN NBI 2012

Page 12: NuMI Operation Summary: 2005-2012

12

FY 2010 : FY 2010 : Tritium Mitigation Tritium Mitigation && Great UptimeGreat Uptime

• Oct: NT04 -> NT05• Mar: NT05 -> NT06• May: NT06 -> NT01• July: NT01 -> NT02• July: PB Dipole cables ground

fault; Sump pump & alarm failure.

• Sep: NT02 -> NT07

Total POT in FY 2010 = 3.19 x10**20

FY 2011 : Year of the Targets (Five) & PB CablesFY 2011 : Year of the Targets (Five) & PB Cables

Total POT in FY 2011 = 2.21 x10**20

7 Nov. 2012 CERN NBI 2012

Page 13: NuMI Operation Summary: 2005-2012

13

FY 12: FY 12: Great Uptime.Great Uptime. Seven Month Operation before Seven Month Operation before NOvA Shutdown 30 Aoril.NOvA Shutdown 30 Aoril.

NuMI Downtime SummaryNuMI Downtime Summary• Primary Beam ~ 1%Primary Beam ~ 1%• Neutrino beam ~ 13%Neutrino beam ~ 13%• Accelerator (including Accelerator (including

scheduled M&D) ~ 13%scheduled M&D) ~ 13%

• Fraction up since May Fraction up since May 2005 ~ 73%2005 ~ 73%

Total POT in FY 2012 = 2.55 x10**20

7 Nov. 2012 CERN NBI 2012

Page 14: NuMI Operation Summary: 2005-2012

14

Some NuMI Lessons Learned – Primary BeamSome NuMI Lessons Learned – Primary Beam

• We refurbished existing dipoles and quads (30-40 years old magnets) for NuMI to save $$.– Worked okay -> 99% uptime for PB. But, probably fortunate for quads.

We lost many during refurbishment, and had few spares. For NOvA shorter cycle time, have replaced highest current quads with new design.

• Did not skimp on instrumentation, and greatly enhanced beam control.– Great payoff here. Prior to operation, control of primary beam losses to

avoid ground water activation as unshielded intense beam passes through a protected aquifer region was a great concern.

– This worked extremely well. > 60 million targeted beam pulses, and ZERO with large beam loss.

– Many side benefits also, with no activation issues for PB components, and consistently robust targeting precision.

7 Nov. 2012 CERN NBI 2012

Page 15: NuMI Operation Summary: 2005-2012

15

Some NuMI Lessons Learned – Neutrino BeamSome NuMI Lessons Learned – Neutrino BeamJim Hylen probably has many more.Jim Hylen probably has many more.

• Tritium is VERY mobile in moist air– Our major problem is transfer of tritium produced in target hall chase [smaller effect

from absorber] to wet decay tunnel walkway which then transferred to large volume of “clean” water designed to come in to NuMI tunnel from regions external to system shield. Produces effective shield short circuit

• Began operations with no spares for target or horns, with first spares many months away

– Not the best approach!– BUT, our people learned by necessity to repair highly activated components

efficiently and safely.– Still, would have been much better to begin beam operation with spares.

• Need good control over critical component production.

– 1st targets produced by IHEP worked well. Major quality control problems with later ones.

• Hydrogen embrittlement of high strength steel in high radiation field is VERY REAL.– Horn 2 Strip-line failure.

7 Nov. 2012 CERN NBI 2012 15

Page 16: NuMI Operation Summary: 2005-2012

16

NuMI 2005 - 2012NuMI 2005 - 2012

Shutdown begins 30 April 2012 for 700 kW NOvA Upgrade

and 1.57 Sextillion (1.57 × 1021 )

Protons on Target for NuMI

LE neutrino beamLE antineutrino beamSpecial Runs

7 Nov. 2012 CERN NBI 2012 16