Novel waste water treatement
-
Upload
harshaanne -
Category
Education
-
view
503 -
download
5
Transcript of Novel waste water treatement
Commercial Application of an innovative membrane
bioreactor for waste water treatment at Glanbia Ingredients
Ltd. Ballyragget Site
Presented by: Karen Kennedy
Product Portfolio 2001
Butter 32,833
Cheese 14,628
Rennet Casein 9,845
Acid Casein 6,097
Lactose 16,922
Whey Powders 25,386
105,711
Tonnes
Glanbia was faced with two major challenges following the issue of our IPC Licence in December 1998.
i. Following the merger of the Avonmore Foods Plc. and Waterford Foods Plc. to form Glanbia Group, it was decided to close the Dungarvan site and process up to 60% additional milk and whey on the Ballyragget site. At the same time, the emission limit values in the new IPCL were being reduced.
ii. The type of emission values outlined in this license could not be delivered by conventional technology.
Glanbia carried out research on what technology was available in the latter half of 1998 with the objective of upgrading its waste water treatment plant for the 1999
peak season.
Development of the New Process
Technology
OPTIONS CONSIDERED FOR PLANT EXPANSION
• Remain with proven conventionaly technology
• Extend existing biotower, increase clarification capacity
• Or deviate from the norm and rewrite the rules of water
treatment.
Waste Water Treatment
Inputs• Milk per annum - 201M gallons• Whey per annum - 203M gallons
Outputs520 million Gallons Wastewater To Be Treated• 490 million Gallons Treated Permeate To River Nore• 3.5 million gallons of Sludge
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Average Loss kg COD/m3
Intake Cream Sep Whey Casein Cheese Butter Oil
Plant
1998
1999
2000
2001
Loss Minimisation
Disposal Costs/annum £464,000
Landbank Maintenance
Costs/annum
£54,000
Total Costs £518,000
Income from Pig
farmers/annum
£100,000
Waste Minimisation:Delactosed Permeate
800-850m3/day
Diverted from effluent to Cooling Line
<50mg/l COD
Rennet Casein
RO2
UF2
Lactose WPC
Acid Whey
Acid Whey Wash Water
UO
UF3
RO1 Gemini
P R
100m3/day
Off Site Treatment
P
R
P
P
Waste Minimisation:Whey Gemini Plant
100m3/hr
5 Evaporators
Recycled as Boiler Feed Make Up Water
Recover & use as pre-rinse for membrane CIP
PreRinse in Whey CIP’s, evaps, tanks, silos etc.
General Cleaning
RO Polisher
Retentate
to Effluent
Waste Minimisation:2nd Stage Condensate Polishing
OPTION CHOSEN
• To expand treatment capacity from 15,000Kgs COD to
30,000kgs/Day, 2 limiting factors:
• Oxygen Transfer in aeration basin
• And the inability of settlement in final clarifiers at MLSS
above 2,000.
• Solution – Suprafilt fine bubble air diffusers and Kubota
membranes.
• Operating now at 8,000 mg/l MLSS in the oxidation ditch
BOD ReductionBOD Reduction
BOD IN
20,000kg/day
Conventional Technology 98.6%
Kubota Technology 99.5%
WWTP
BOD OUT
Principle of Operation
Screened Effluent ex oxidation
Ditch
Air in
In
Waste Sludge(to further treatment)
A Crap Commitment
Treated &disinfected
effluent
Out
The Kubota membrane bioreactor is essentially a high MLSS activated sludge process where the Kubota membrane treatment units are submerged within the extended activated sludge tanks. Typically, the activated sludge is maintained in the range 15 – 20,000 mg/l MLSS.
Specific Innovative ElementsSpecific Innovative Elements
Specific Innovative ElementsSpecific Innovative Elements
In operation, the treated effluent through the membrane units is controlled by available gravity head (typically 1 – 1.5 metres).
The number of units installed is dependant on the maximum flow rate required. The plant at Ballyragget comprises 74 packs for a guarantee flow rate of 7,300 m3 per day. However, it is hoped that flow rates of 9,0003 per day will be achieved.
0.4 microns
The Filtration SpectrumThe Filtration Spectrum
0
10
20
30
mg/l
Traditional Technology v's Kubota Membranes Results to Date
KubotaMembranes2001 Limit
TraditionalTechnology
SS BOD Ortho-P
River Nore (Downstream) = Q4 Unpolluted
Improvements in Suspended Solids Improvements in Suspended Solids
Conventional Technology: Feb- Mar 1999 Suspended Solids EPA 2001 limit
01020304050607080
25-Jan 04-Feb 14-Feb 24-Feb 05-Mar 15-Mar 25-Mar 04-Apr
Date
SS
mg/
l
SS
Limit 2001
Kubota Plant: Feb- Mar 2000 Suspended Solid 2001 EPA Limit 2001
0
2
4
6
8
10
12
14
16
25/01/00 04/02/00 14/02/00 24/02/00 05/03/00 15/03/00 25/03/00 04/04/00
Date
Su
spen
ded
Sol
ids
SS
Limit 2001
1999 2000
Improvements in Biological Oxygen Improvements in Biological Oxygen
Demand Demand
1999 2000
Conventional Technology: Feb Mar 1999 BOD Results EPA 2001 limit
0
5
10
15
20
25
30
35
25-Jan 04-Feb 14-Feb 24-Feb 05-Mar 15-Mar 25-Mar 04-Apr
Date
BO
D m
g/l
BOD
Limit 2001
Kubota Plant: Feb-Mar 2000 BOD EPA Limits 2001
0
2
4
6
8
10
12
25/01/00 04/02/00 14/02/00 24/02/00 05/03/00 15/03/00 25/03/00 04/04/00
Date
BO
D m
g/l
BOD
Limit 2001
Improvements in Ortho P Improvements in Ortho P
1999 2000
Conventional Technology: 1999 Ortho P Results EPA 2000 and 2001 limits
0
2
4
6
8
10
12
25-Jan 04-Feb 14-Feb 24-Feb 05-Mar 15-Mar 25-Mar 04-Apr
Date
Ort
ho
P m
g/l
Ortho P
Limit 2001
Limit 2000
Kubota Plant: Feb- Mar 2000 Ortho Phosphate EPA 2000 and 2001 limits
0
0.2
0.4
0.6
0.8
1
1.2
1.4
31-Dec 05-Jan 10-Jan 15-Jan 20-Jan 25-Jan 30-Jan
Date
Ort
ho
P m
g/l
Ortho P
Limit 2001
Limit 2000
WWTP FlowWWTP Flow
DenitrificationtankExisting Oxidation ditch (13000 m3)
Preliminary treatment:- Screen- DAF- Biofilters
Existing settlement tanks
Outfall to river
Feed 7-9000 m3/d
Recycle/returnsludge
Future capacity
Re-use
16 t/d BOD
Kubota membrane units
Energy Requirements for new plant
• Upgrading and Expansion of the Treatment plant cost IR£3
Million, with the Kubota membranes costing IR£1.6 Million
and the installation of a new aeration system, Suprafilt Fine
bubble diffusers.
• Aerzen fine bubble diffusers – 50-60% increase in Oxygen
Transfer when compared with surface rotors.
• Energy usage.
• Conventional plant would not achieve the 10:15, BOD:SS
standard
Operational Difficulties Encountered
• 150% Of design airflow was required to maintain flux.
• No Standby blower.
• Membrane scaling incidents.
• Membrane sliming.
• Sludging between membrane plates, reduces flux.
• Wear on plates.