NOTICE - EXIM
Transcript of NOTICE - EXIM
NOTICEThis page appended to digital file by EXIM Bank.
The following document is an environmental assessment or supplemental environmental report (such as a remediation or mitigation plan or procedure, or related monitoring report) (“Assessment/Report”) that has been produced by a third-party and required to be submitted to the Export-Import Bank of the United States in conjunction with the referenced EXIM Bank transaction number . It is being provided here in furtherance of Section 11(a)(1) of the Export Import Bank Act of 1945, as amended (12 U.S.C. 635i-5).
Please note that the Assessment/Report is as of the date noted. Accordingly, the Bank makes no representation that it (i) is the most recent version of this document, (ii) is fully accurate and/or complete, or (iii) includes a full descrip-tion of appropriate action taken by responsible parties in response to infor-mation about environmental or social issues, if any, raised therein.
Requests for additional (including, in some cases, more current) environmen-tal or supplemental environmental Assessment/Reports regarding this project may be made using EXIM Bank’s online “Environmental and Social Project Information and Concerns” form at http://exim.gov/envsoc.
This page appended to digital file by EXIM Bank.
DUBA INTEGRATED SOLAR COMBINED CYCLE PROJECT Environmental and Social Impact Assessment 09/11/2014
Project number: 37446130 Dated: 09/11/2014 2 | 278 Revised:
Quality Management
Issue/revision Issue 1 Revision 1 Revision 2 Revision 3
Remarks Draft Draft - Revision 1 Draft - Revision 2 Draft - Revision 3
Date 15/06/2014 21/07/2014 19/10/2014 09/11/2014
Prepared by Project Team Project Team Project Team Project Team
Signature
Checked by Simon Pickup Simon Pickup Edward Crowley Edward Crowley
Signature
Authorised by Simon Pickup Simon Pickup Edward Crowley Edward Crowley
Signature
Project number 37446130 37446130 37446130 37446130
Report number 002 002 002 002
File reference 140615-37446130-002
140721-37446130-002
141019-37446130-002
141109-37446130-002
3 | 278
DUBA INTEGRATED SOLAR COMBINED CYCLE PROJECT Environmental and Social Impact Assessment
09/11/2014
Client Saudi Electricity Company
Consultant WSP Middle East Ltd P.O. Box 7497 Dubai United Arab Emirates Tel: +971 4 350 5000 Fax: +971 4 350 5001 www.wspgroup.com
Project number: 37446130 Dated: 09/11/2014 4 | 278 Revised:
Table of Contents Executive Summary............................................................................................................... 12
1 Introduction ................................................................................................................... 19 Background ............................................................................................................... 19 1.1 Overview of the Project.............................................................................................. 20 1.2 Requirement for an Environmental and Social Impact Assessment .......................... 20 1.3 The Environmental and Social Impact Assessment ................................................... 21 1.4 The Project Team ...................................................................................................... 23 1.5
2 Project Location ............................................................................................................ 24 Project Site Location .................................................................................................. 24 2.1 Existing Site Conditions ............................................................................................. 25 2.2 Site Conditions .......................................................................................................... 28 2.3 Surrounding Areas ..................................................................................................... 29 2.4 Key Sensitive Receptors............................................................................................ 29 2.5
3 Project Description ........................................................................................................ 31 Introduction ................................................................................................................ 31 3.1 Project Justification .................................................................................................... 31 3.2 Project Layout ............................................................................................................ 31 3.3 Project Specification Summary .................................................................................. 33 3.4
4 Environmental Legislation and Standards ..................................................................... 41 Regulatory Environmental Framework in KSA ........................................................... 41 4.1 Environmental Impact Assessment ........................................................................... 45 4.2 Environmental Standards Applicable to the Project ................................................... 47 4.3
5 Impact Assessment Methodology ................................................................................. 58 Methodology for the Assessment of Impacts ............................................................. 58 5.1 Sensitivity (Importance) of Receptors ........................................................................ 58 5.2 Description of Effect................................................................................................... 58 5.3 Significance of Effects ............................................................................................... 59 5.4 Evaluation of Impacts ................................................................................................ 59 5.5 Cumulative Effects ..................................................................................................... 62 5.6
6 Marine Environment ...................................................................................................... 64 Introduction ................................................................................................................ 64 6.1 Relevant Standards and Legislation .......................................................................... 64 6.2 Methodology .............................................................................................................. 66 6.3 Existing Baseline Conditions ..................................................................................... 71 6.4 Assessment of Impacts.............................................................................................. 83 6.5 Mitigation Measures, Residual/Cumulative Effects .................................................... 88 6.6 Summary and Conclusions ........................................................................................ 91 6.7
7 Air Quality ..................................................................................................................... 93 Introduction ................................................................................................................ 93 7.1 Relevant Air Quality Emission Standards .................................................................. 94 7.2 Methodology .............................................................................................................. 97 7.3 Existing Baseline Conditions ................................................................................... 106 7.4 Sensitive Receptors ................................................................................................. 108 7.5
5 | 278
Assessment of Construction phase Impacts ............................................................ 111 7.6 Assessment of Operational Phase Impacts ............................................................. 113 7.7 Mitigation Measures and Residual Impacts ............................................................. 135 7.8 Summary and Conclusions ...................................................................................... 137 7.9
8 Environmental Noise ................................................................................................... 141 Introduction .............................................................................................................. 141 8.1 Relevant Standards and Legislation ........................................................................ 141 8.2 Methodology ............................................................................................................ 145 8.3 Existing Baseline Conditions ................................................................................... 148 8.4 Assessment of Impacts............................................................................................ 151 8.5 Mitigation Measures, Residual/Cumulative Effects .................................................. 157 8.6 Summary and Conclusions ...................................................................................... 159 8.7
9 Soil, Groundwater and Contamination ........................................................................ 161 Introduction .............................................................................................................. 161 9.1 Relevant Standards and Legislation ........................................................................ 161 9.2 Methodology ............................................................................................................ 162 9.3 Existing Baseline Conditions ................................................................................... 163 9.4 Sensitive Receptors ................................................................................................. 165 9.5 Assessment of Construction and Operational Impacts ............................................ 165 9.6 Mitigation Measures, Residual and Cumulative Effects ........................................... 167 9.7 Summary & Conclusions ......................................................................................... 170 9.8
10 Waste Management .................................................................................................... 174 Introduction ........................................................................................................... 174 10.1 Relevant Standards and Legislation ..................................................................... 174 10.2 Methodology ......................................................................................................... 176 10.3 Existing Baseline Conditions ................................................................................ 177 10.4 Sensitive Receptors .............................................................................................. 178 10.5 Assessment of Construction and Operational Impacts ......................................... 179 10.6 Mitigation Measures, Residual and Cumulative Effects ........................................ 182 10.7 Summary & Conclusions ...................................................................................... 191 10.8
11 Water Resources and Wastewater.............................................................................. 194 Introduction ........................................................................................................... 194 11.1 Relevant Standards and Legislation ..................................................................... 194 11.2 Methodology ......................................................................................................... 194 11.3 Existing Baseline Conditions ................................................................................ 195 11.4 Sensitive Receptors .............................................................................................. 197 11.5 Assessment of Construction and Operational Impacts ......................................... 197 11.6 Mitigation Measures, Residual and Cumulative Effects ........................................ 199 11.7
12 Terrestrial Ecology ...................................................................................................... 206 Introduction ........................................................................................................... 206 12.1 Relevant Standards and Legislation ..................................................................... 206 12.2 Methodology ......................................................................................................... 207 12.3 Existing Baseline Conditions ................................................................................ 207 12.4 Key Sensitive Receptors....................................................................................... 209 12.5 Mitigation Measures, Residual and Cumulative Effects ........................................ 210 12.7
Project number: 37446130 Dated: 09/11/2014 6 | 278 Revised:
13 Socio Economic .......................................................................................................... 214 Introduction ........................................................................................................... 214 13.1 Relevant Standards and Legislation ..................................................................... 214 13.2 Methodology ......................................................................................................... 215 13.3 Existing Baseline Conditions ................................................................................ 216 13.4 Key Sensitive Receptors....................................................................................... 220 13.5 Mitigation Measures, Residual and Cumulative Effects ........................................ 224 13.7 Summary and Conclusions ................................................................................... 228 13.8
14 Cultural, Heritage and Archaeology ............................................................................ 234 Introduction ........................................................................................................... 234 14.1
15 Landscape and Visual ................................................................................................. 235 Introduction ........................................................................................................... 235 15.1 Relevant Standards .............................................................................................. 235 15.2 Methodology ......................................................................................................... 235 15.3 Existing Baseline Conditions ................................................................................ 236 15.4 Assessment of Construction and Operational Phase Impacts .............................. 237 15.5 Summary and Conclusions ................................................................................... 238 15.6
16 Framework Construction Environmental Management Plan ....................................... 240 Purpose of the CEMP ........................................................................................... 240 16.1 ISO 14001 Model .................................................................................................. 241 16.2 CEMP Implementation .......................................................................................... 242 16.3 Environmental Aspects and Mitigation Measures ................................................. 244 16.4 Monitoring Programmes ....................................................................................... 269 16.5
17 Framework Operational Environmental Management Plan ......................................... 271 Introduction ........................................................................................................... 271 17.1 Aims and Objectives ............................................................................................. 271 17.2 Operational Environmental Management System ................................................ 272 17.3 Operational Environmental Management System Components ........................... 272 17.4 Framework Operational Environmental Control Plans .......................................... 279 17.5 Monitoring Programmes ....................................................................................... 286 17.6 Decommissioning Plan ......................................................................................... 288 17.7
7 | 278
Appendices Appendix A – Bibliography Appendix B – Project Layout Drawings Appendix C – Fuel Specifications Appendix D - Wind Roses for Sharm El Sheikh (2009 to 2013) Appendix E – Dispersion Model Input Parameters used in the Assessment Appendix F – Air Quality Monitoring Laboratory Analytical Reports Appendix G – Modelling Results – Stack Height Analysis Appendix H – Modelling Results – Combined Cycle Appendix H – Modelling Results – Simple Cycle Appendix I – Modelling Results – Operation on Back-up Fuel (ASL) Appendix J – Recirculation Study Report
Project number: 37446130 Dated: 09/11/2014 8 | 278 Revised:
List of Figures Figure 2-1 The location of the Project Site .......................................................................................................26 Figure 3-1: General layout of the Project site (SEC, 2014) ...............................................................................32 Figure 3-2: The project layout plan overlaid onto a satellite image ...................................................................33 Figure 6-1 Location of the marine survey baseline sites ..................................................................................67 Figure 6-2 Screen Shot of the Coral Point Count Software in Operation ..........................................................69 Figure 6-3 Existing bathymetry at the project site ............................................................................................72 Figure 6-4 Typical fringing coral reef zonation pattern (image: public domain) .................................................76 Figure 6-5 Coastal habitat map .......................................................................................................................77 Figure 6-6 Substrate cover at all sites .............................................................................................................80 Figure 6-7 Percentage cover at all sites and at all depths ................................................................................80 Figure 6-8 Percentage substrate cover at each survey site ..............................................................................81 Figure 6-9 Hard coral types as a percentage of total substrate cover at all sites and all depths ........................81 Figure 6-10 Representative image of marine habitats ......................................................................................82 Figure 6-11 Temperature difference at the surface (left) and a longitudinal cross section (right) .......................86 Figure 6-12 Surface temperature contours overlaid onto the marine habitat map .............................................87 Figure 7-1 Modelling Domain ........................................................................................................................104 Figure 7-2 Diffusion Tube Monitoring Locations .............................................................................................107 Figure 7-3 Sensitive Receptor Locations .......................................................................................................109 Figure 7-4 Scenario 1A1 – Option A, Combined Cycle (OP1) – Annual Mean NO2 Concentrations (µg/m3) ....116 Figure 7-5 Scenario 1A1 – Option A, Combined Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3).....117 Figure 7-6 Scenario 1B1 – Option B, Combined Cycle (OP1) – Annual Mean NO2 Concentrations (µg/m3) ....118 Figure 7-7 Scenario 1B1 – Option B, Combined Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3).....119 Figure 7-8 Scenario 2A1 – Option A, Simple Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3) ..........122 Figure 7-9 Scenario 2B1 – Option B, Simple Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3) ..........123 Figure 7-10 Scenario 3BCC – Option B, Combined Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)127 Figure 7-11 Scenario 3BCC – Option B, Combined Cycle (OP1) – 1-hour Mean SO2 Concentrations (µg/m3) 128 Figure 7-12 Scenario 3BCC – Option B, Combined Cycle (OP1) – 24-hour Mean SO2 Concentrations (µg/m3) .....................................................................................................................................................................129 Figure 7-13 Scenario 3BSC – Option B, Simple Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3) .....130 Figure 7-14 Scenario 3BSC – Option B, Simple Cycle (OP1) – 1-hour Mean SO2 Concentrations (µg/m3) .....131 Figure 7-15 Scenario 3BSC – Option B, Simple Cycle (OP1) – 24-hour Mean SO2 Concentrations (µg/m3) ...132 Figure 8-1 Proposed location of Duba combined Cycle Power Plant (6 km north of Almuwaylih – P3)............141 Figure 8-2 Screen shot of the developed CadnaA 3D model .........................................................................146 Figure 8-3 Noise measurement locations ......................................................................................................149 Figure 8-4 Noise measurement location P1 – Future site location – 30 m from road ......................................150 Figure 8-5 Noise measurement location P2 – Fish farm ................................................................................150 Figure 8-6 Noise measurement location P3 (Almuwaylih sports field and mosque) ........................................150 Figure 8-7 Potential noise sensitive areas .....................................................................................................152 Figure 8-8 Operational Noise –Combined Cycle Noise Map ..........................................................................156 Figure 9-1 Plate Tectonics of Saudi Arabia....................................................................................................164 Figure 11-1 Site context map including wadi locations ...................................................................................196 Figure 12-1 Examples of terrestrial ecological features on the site .................................................................208 Figure 13-1 Al Muwaylih Village ....................................................................................................................220 Figure 13-2 Al Muwaylih Village ....................................................................................................................220 Figure 13-3 Tabuk Fisheries Company fish farm ...........................................................................................220 Figure 13-4 Decommissioned industrial facility ..............................................................................................220 Figure 15-1 Representative image of key site features ..................................................................................236
9 | 278
List of Tables Table 1-1 The Project Team............................................................................................................................23 Table 2-1 Key site features .............................................................................................................................27 Table 2-2 Site reference conditions .................................................................................................................28 Table 2-3 Key Sensitive Receptors .................................................................................................................29 Table 4-1 Relevant Content of the General Environmental Regulations ...........................................................43 Table 4-2 PME and IFC Ambient Air Quality Standards for SO2, NO2 and PM10 ...............................................48 Table 4-3 PME/IFC Emission Standards for SO2, NO2 and PM10 .....................................................................49 Table 4-4 PME & IFC EHS Noise Guidelines Limit Values ...............................................................................50 Table 4-5 PME General Construction – Maximum Permissible Façade Noise Limits ........................................50 Table 4-6 Examples of relevant ambient water quality and discharge limits from PME 2012 ............................52 Table 4-7 Wastewater re-use standards (MAW, 1989) ....................................................................................53 Table 4-8 Guidelines for Urban Water Reuse (US EPA Guidelines) .................................................................54 Table 5-1 Definition of Impact Type .................................................................................................................60 Table 5-2 Impact Assessment Terminology .....................................................................................................60 Table 5-3 Impact Severity Criteria ...................................................................................................................61 Table 5-4 Likelihood Categories ......................................................................................................................61 Table 5-5 Determining the Significance of Impacts ..........................................................................................62 Table 5-6 Definition of Impacts ........................................................................................................................62 Table 6-1 Examples of relevant ambient water quality and discharge limits from PME 2012 ............................65 Table 6-2 The survey scope at each of the marine survey baseline sites .........................................................68 Table 6-3 Water quality analysis results ..........................................................................................................74 Table 6-4 Percentage substrate cover .............................................................................................................79 Table 6-5 Hard coral types as a percentage of total substrate cover ................................................................79 Table 6-6 Marine ecological receptor criteria ...................................................................................................83 Table 6-7 Approximate surface area (in m2) of affected habitats ......................................................................87 Table 8-17 Impact and mitigation summary table for Marine Environment .......................................................92 Table 7-1 Air Quality Standards for SO2, NO2 and PM10 ..................................................................................94 Table 7-2 Emission Standards for SO2, NO2 and PM10 ....................................................................................95 Table 7-3 SO2, NOx and PM10 Emissions Concentrations for the Proposed Turbine at DCCPP ........................95 Table 7-4 Description of Operational Scenarios .............................................................................................100 Table 7-5 Criteria for Determination of Significance .......................................................................................105 Table 7-6 Diffusion Tube Monitoring Results .................................................................................................107 Table 7-7 Sensitive Receptors ......................................................................................................................110 Table 7-8 Maximum Ground Level Pollutant Concentrations – Combined Cycle (Natural Gas) ......................115 Table 7-9 Maximum Ground Level Pollutant Concentrations – Simple Cycle (Natural Gas) ............................121 Table 7-10 Maximum Ground Level Pollutant Concentrations – Arabian Super Light (ASL) Fuel....................125 Table 7-11 Calculation of annual carbon dioxide emissions for the Additional Turbines .................................134 Table 7-12: Impact and mitigation summary table for Air Quality....................................................................140 Table 8-1 General Construction maximum permissible facade noise levels ...................................................142 Table 8-2 Permitted free-field external noise limits for community noise, measured at any noise sensitive property within the appropriate area designation ...........................................................................................143 Table 8-3 Maximum permissible free-field noise levels ..................................................................................143 Table 8-4 Noise level guidelines....................................................................................................................144 Table 8-5 SEC Noise Requirements ..............................................................................................................144 Table 8-6 Construction Noise Emission Data ................................................................................................145 Table 8-7 Sound Power Levels of the Gas Turbine Generator .......................................................................147 Table 8-8 Sound Power Levels for the Steam Turbine package .....................................................................147 Table 8-9 Sound Power Levels for the HRSG................................................................................................147 Table 8-10 Description of noise measurement locations ................................................................................149 Table 8-11 Measured baseline noise data .....................................................................................................151 Table 8-12 Noise Sensitive Receptor Locations ............................................................................................151 Table 8-13 Noise impact for construction phases ..........................................................................................152 Table 8-14 Construction Noise –Site preparation noise map..........................................................................153 Table 8-15 Construction Noise –Civil works noise map .................................................................................154 Table 8-16 Noise impact for operational phases ............................................................................................155 Table 8-17 Impact and mitigation summary table for Environmental Noise.....................................................160
Project number: 37446130 Dated: 09/11/2014 10 | 278 Revised:
Table 9-1 Contamination Risk Assessment ...................................................................................................163 Table 9-2 Impact and mitigation summary table for soil, groundwater and contamination ...............................172 Table 10-1 Typical Construction Phase Waste Origins ..................................................................................179 Table 10-2 Waste Hierarchy..........................................................................................................................183 Table 10-3 Measures to Reduce the Waste of on-site Materials ....................................................................184 Table 0-1 Impact and mitigation summary table for waste management ........................................................192 Table 0-1 Impact and mitigation summary table for water resources and wastewater ....................................204 Table 12-1 Impact and mitigation summary table for terrestrial ecology .........................................................212 Table 13-1 Key Sensitive Receptors .............................................................................................................221 Table 13-2 Impact and mitigation summary table for socio-economic ............................................................230 Table 15-1 Impact and mitigation summary table for landscape and visual ....................................................239 Table 16-1 ISO 14001 Structure....................................................................................................................241
11 | 278
Acronyms
Abbreviation Title/ Full Description
ASL - Arabian Super Light
BOP - Balance of Plant
CEMP - Construction Environmental Management Plan
dBA - A weighted Decibel
EIA - Environment Impact Assessment
GT - Gas Turbine
GTG - Gas Turbine Generator
HRSG - Heat Recover Steam Generator
ISCC - Integrated Solar Combined Cycle Project
KSA - Kingdom of Saudi Arabia
LAeq - Equivalent Continuous A-Weighted Sound Level
NOx - Nitrogen Oxide and Nitrogen dioxide
OEM - Original Equipment Manufacturer
OEMP - Operational Environmental Management Plan
PM - Particulate Matter
RO - Reverse Osmosis
RSC - Reference Site Conditions
SEC - Saudi Electricity company
STG - Steam Turbine Generator
SOx - Sulphur Oxides
Project number: 37446130 Dated: 09/11/2014 12 | 278 Revised:
Executive Summary
Background
WSP Middle East (WSP) has been commissioned by the Saudi Electricity Company (SEC, the project
proponent) to complete an Environmental and Social Impact Assessment (ESIA) for the proposed Duba
Integrated Solar Combined Cycle Project (ISCC) located approximately 55km north of Duba on the Red Sea
coast of Saudi Arabia.
The Duba Integrated Solar Combined Cycle Project will be located in the Tabuk Region, approximately 55km
north of Duba.
The scope of the project includes:
Construction and operation of the ISCC; and
Construction and operation of a 380 kV Substation and 380 kV high voltage cables between the substation
and the turbines.
This will be the first Integrated Solar Combined Cycle project that SEC have implemented. This is the
organisation’s first step to cutting down carbon emission, increasing fuel efficiency and initiating the solar
industry in Saudi Arabia.
Project and Project Site Overview
The Project will have a net output of 485- 550 MWe with natural gas & condensate as the main operating fuel
and Arabian Super Light (ASL) fuel oil as back up fuel. 50 MWe of steam generation will be from solar energy
concentrators and its associated equipment as Integrated Solar Combined Cycle Plant.
The Project site is located on an area of approximately 160 hectares of open coastal land. The site is bordered
on the east by a main highway, from Duba to the south to the Jordanian border area to the north, and to the
west by the Red Sea coast.
The terrestrial portion of the site is undeveloped and comprises of raised areas intersected by wadi channels.
The raised areas are barren and largely devoid of vegetation with a ground surface of sandy gravel and small
dark rocks. The wadi channels have more vegetation comprised of Acacia spp. and scattered vegetation
dominated by Zygopyllum sp. growing within sandy substrate. Given the presence of vegetation and
stormwater protection infrastructure on the highway, it is likely that these wadis flood during storm events.
The majority of the coastal portion of the site is comprised of a wide sandy beach transitioning to reef flat in the
subtidal area. The reef flat, which is a shallow area less than 1 metres depth, extends between 100 and 250
metres offshore prior to the reef edge.
Approximately 0.5km north of the site there is a disused industrial facility. Approximately 1.5km north of the site
there is a coastal fish farm facility. This includes the onshore component as well as two large areas of cages
13 | 278
some 0.5km offshore. A warehouse facility associated with the fish farm is located approximately 3km north of
the site.
The nearest residential communities are Sharmaa, located 32km north east; Al Sourah, located 15km to the
north west; and AlMuwaylih, located 8km to the south west. There are no permanent residential areas on the
site or in the immediate surrounding area.
Objectives of the Report
The overarching purpose of the ESIA is to provide sufficient information to assist the PME, as the national
environmental regulator, and any parties providing financing support, in the decision making process and to
ensure compliance with all relevant regulations, standards, policies and guidance through a comprehensive
description of the following:
The existing environmental baseline;
The likely environmental impacts and significance of such impacts;
Assessment of compliance with national and international standards and guidelines;
The requirement for mitigation and compensation measures; and
The requirements for subsequent environmental management and monitoring to be implemented.
Air Quality
The impact of the Project on local air quality has been assessed for both the construction and operational
phases. For the construction phase, a qualitative assessment was undertaken based on the likely construction
activities, location of sensitive receptors and local meteorological data to assess the potential air quality im-
pacts.
For the operation phase, a complex dispersion model (Breeze Aermod) was used to predict ground level con-
centrations of NO2, SO2 and PM10 at various receptor locations, including residential locations, in the local area
and surrounding region. Operating conditions representing the plant operating during both typical and worse
case ambient conditions were modelled for the assessment. Concentrations were predicted for the plant oper-
ating on both natural gas and ASL (the latter during emergency operation resulting from gas supply interrup-
tion), as well as in Simple Cycle mode.
GHG emissions from the proposed power plant have been estimated using emission factors for CO2 and me-
thane published by the IPCC for GHG emissions
The impact of dust and fine particle emissions from construction activities and emissions associated with con-
struction plant and traffic is likely to be of negligible due to the distances to off-site locations, absence of sensi-
tive receptors nearby in the surrounding area and the likely low level of traffic associated with construction
phase.
Project number: 37446130 Dated: 09/11/2014 14 | 278 Revised:
Operational Process Contribution
The results of the dispersion modelling show that under both representative and worse-case operating condi-
tions no exceedences of the PME AQSs for the pollutants considered in the assessment were predicted to oc-
cur as a result of emissions from the proposed power plant. This is the case at both the point of maximum im-
pact and at sensitive receptors considered in the assessment and for all relevant averaging periods, under both
operational modes (combined and simple cycle).
In addition to compliance with the PME AQSs for all scenarios considered, the contribution of emissions from
the power plant (for both plant configuration options) during gas-fired operation would not contribute more than
25% to the attainment of the relevant PME AQS, which is in compliance with the relevant criteria in the IFC
EHS Guidelines for ensuring a project allows for additional, future sustainable development in the same air
shed.
GHG Emissions
The operation the turbines at DCCPP would generate GHG emissions of approximately 1,579,150 tCO2 equiva-
lents per year, based on the emission data used and assuming continuous operation of the GTs at the plant at
maximum load (8322 hours per year per GT).
Marine Environment
Six transects were surveyed including 2 control sites and 4 impact zone sites. The survey was designed in
order to document the “baseline” condition of the marine habitat present and to provide a benchmark against
which future monitoring studies can be compared.
The results of the water quality testing indicate that the water quality at the site is of a high quality with no
indicators of industrial or municipal pollution present.
At all the survey sites a high percentage of live hard coral cover (average of 40%) was present in the reef
margin and the upper outer reef slope. Seagrass was also present along two of the transects. The presence of
fish, invertebrates and other marine life was also documented during the marine baseline survey.
The coastal area north of Duba to the Gulf of Aqaba, referred to as the Tiran Area, is recognized as being an
area of special conservation importance for the wide variety of different biotopes and reef types, forming unique
reef complexes with high zoogeographic significance .
The construction phase will directly impact upon 65,000 m2 of fringing reef habitat. Secondary effects
associated with water quality impacts (suspended sediments) are also expected on the surrounding reef.
The main operational impact identified is associated with the discharge of heated cooling water from the facility
during normal plant operation. The marine modelling results have been used to determine the extent of the
area of reef likely to be affected. Taking a conservative approach we have identified the 1-2°C contour as the
area within which the coral reefs will be adversely affected and the >2°C contour where mortality will occur.
15 | 278
The 1-2°C contour affects an area of approximately 100,000 m2. Within this area we can expect to see the
corals displaying signs of physical stress, such as reduced growth rates and fecundity as a result of the
increased temperature and process chemicals. The >2°C contour impinges upon approximately 24,000 m2 of
marine habitat. Within this area coral mortality will be likely to occur.
Various mitigation and management measures have been recommended. However, the construction and
operation of a power plant in this location will inevitably have impacts upon the adjacent sensitive coral reef
habitat. It is recommended that a detailed study is undertaken to fully quantify the ecological and biodiversity
impacts of the project when suitable design information is available and identify a practical compensation
strategy for habitat losses.
Noise and Vibration
This document studies some of the potential environmental impacts of a combined Cycle Power plant 50 km
north of Duba in Saudi Arabia.
In order to fully quantify the existing baseline noise levels, measurements were under-taken at three
measurement locations around the proposed location of the Duba Power Plant site.
The potential noise and vibration impacts associated with the construction and operation of the Duba combined
Cycle Power Plant are identified using baseline measurements.
The construction phase noise impacts have been predicted based upon noise data contained in BS5228. The
results of the assessment are within the recommended limits and recommendations for the on-going monitoring
of the noise levels associated with construction activity have been made.
The operational phase noise impacts have been predicted in accordance with ISO 9613-2 based upon
historical noise data for the intended equipment. The results of the assessment are within the recommended
limits for most sensitive areas; however, they exceed the night time criteria for the company housing
compound. Therefore it was recommended that n case construction activities are scheduled to be in the night
period and if Company housing is constructed and occupied then proper mitigation measures to be taken.
Given that the nearest town is 6 km to the south of the site (Almuwaylih), it is expected that the overall residual
operation noise will have a negligible significance.
Soil and Groundwater
It is recommended that an investigation of existing contamination associated with the existing decommissioned
industrial facility is undertaken prior to any major excavation works take place on site.
It is a requirement that any existing contaminated materials on site identified during site preparation works,
including soils, are considered as hazardous waste and disposed of in a licensed landfill site prior to site
preparation works by an appropriately licensed contractor. Notwithstanding the above, intrusive investigations
will need to be enacted if additional significant pollutant sources or contaminations are identified prior to or
during the site preparation works.
Project number: 37446130 Dated: 09/11/2014 16 | 278 Revised:
In addition, during the construction and operational phases of the project, there is a potential for workers and
visitors to come into contact with contaminated land and hazardous or semi-hazardous wastes, as well as the
potential for leaks and spills to adversely affect the wider environment. The CEMP and OEMP must be
implemented to manage these risks and to reduce the likelihood of any future negative environmental and
social impacts.
It is of utmost importance that the contractor undertakes a detailed investigation of the underlying aquifer prior
to establishing deep wells. This assessment should consider all current and future abstractions.
Waste Management
Overall, with the implementation of good environmental practices through the contractor EHS policies and
guidance, together with the development of a CEMP and OEMP, the Project should be able to limit pressures
on the existing waste management facilities in the surrounding region and reduce the potential for any localised
contamination to occur.
However, it is anticipated that the quantities of hazardous and non-hazardous waste streams generated by the
Project may be substantial and therefore it is essential that the approach to waste management at the site as
highlighted above is rigidly adopted.
Water Resources and Wastewater
The construction impacts that have been identified are those that, with good on-site and off-site environmental
management practices, can be relatively easily avoided or mitigated. The key issue relates to the appropriate
management of storm water during both construction and operation. Following their implementation the residual
impacts are considered to be of negligible negative significance and therefore are considered acceptable.
Finally, and as determined within this section, a comprehensive construction environmental management plan
(CEMP) and operational environmental management plan (OEMP) are required for the facility.
Terrestrial Ecology
This chapter assesses the status of the existing terrestrial ecology on the proposed site and presents the
applicable approaches to mitigate or minimise any potential negative impacts of this development.
The site has been categorized as being of moderate ecological value and sensitivity due to the presence of
wadi and sandy beach areas which provide habitat for reptiles, rodent and bird species.
The overall construction impacts on the terrestrial ecology are considered to be of medium adverse significance
while the operational impacts (e.g. landscaping) will be of minor positive, significance.
Socio-Economics
It is generally thought that the development of the Project will have a positive impact on the local economy,
particularly in terms of local job creation, and if the mitigation measures detailed above, and within the
framework OEMP delivered as part of this ESIA are followed. In addition, it will be the responsibility of the EPC
contractor to develop a Comprehensive CEMP and SEC-Operation & Maintenance to develop an OEMP.
17 | 278
Due to the provision of additional employment opportunities during both construction and operation, the
proposed facility is expected to represent a positive employment option which may draw prospective residents
back to the region.
Key economic benefits that are thought likely to be derived from the proposed facility include:
The creation of temporary and permanent jobs during the construction and operational phases of the pro-
posed development;
The potential for labour and procurement contracts to be let locally during the construction phase and the
capital cost of the redevelopment; and
The potential for indirect increased local spending from the incoming workforce.
The potential for adverse impacts upon the existing fish farming operations associated with marine discharges
during the operational phase of the project has been noted. The detailed design of the Project should consider
means to ensure adverse effects on the fish farm are minimised.
Landscape and Visual
The proposed project site is located in a remote and undisturbed coastal landscape with limited sensitive
receptors (view points). However, the presence of a power plant in this area will have an impact upon the
visual character of the landscape. There are limited opportunities for mitigating the permanent impact of this
kind of facility. However, it recommended planting a vegetated buffer along the inland side of the power plant to
improve the aesthetic appearance.
Framework Environmental Management Plans
Framework Construction Environmental Management Plan
A framework has been provided detailing the requirements for environmental management measures which will
be implemented by the EPC Contractor prior to commencement of construction. The framework identifies
pollution control and best practice measures that should be adopted within a Project specific EHS Plan during
the construction phase of the Project in order to avoid, minimise, or offset likely impacts in the areas on and
surrounding the Site that are attributable to the Project.
Framework Operation Environmental Management Plan
A framework has been provided detailing the requirements for an OEMP which will be developed by SEC-
Operation & Maintenance prior to operation. The OEMP is a management tool used to ensure that undue or
reasonably avoidable adverse risks of the operation of a project are prevented and that any positive effects are
enhanced. The primary aim of the OEMP is to provide clear direction on the requirements of the operational
management team in the conduct of the activities, where every requirement is measurable and enforceable,
whilst any deviation can be identified and addressed swiftly.
Project number: 37446130 Dated: 09/11/2014 18 | 278 Revised:
Further Study
Detailed design information was not available at the time of the preparation of this ESIA and therefore
reasonable assumptions have been made with respect to the type of equipment to be installed based upon the
RFP issued by SEC. It is important however that the following is undertaken in detail by the EPC Contractor as
part of their detailed design to confirm adherence to national and international standards where applicable:
Dispersion modelling to confirm that ambient air quality standards are met with the actual equipment
proposed;
Investigations to understand the existence of any contamination associate with the adjacent
decommissioned industrial facility;
Detailed studies to ensure the appropriate management of storm water during both construction and
operation given that existing wadis will be heavily impacted; and
Quantification of the affected marine habitat based on the final design of the marine structures and final
marine modelling results and development of an appropriate Habitat Loss Compensation Strategy
19 | 278
1 Introduction
Background 1.1
WSP Middle East (WSP) has been commissioned by the Saudi Electricity Company (SEC), the project
proponent, to complete an Environmental and Social Impact Assessment (ESIA) for the proposed Duba
Integrated Solar Combined Cycle Project located approximately 55km north of Duba on the Red Sea coast of
Saudi Arabia.
The Duba Integrated Solar Combined Cycle Project (henceforth referred to as the Project or ISCC) will be
located in the Tabuk Region, approximately 55km north of Duba.
The scope of the project includes:
Construction and operation of the ISCC; and
Construction and operation of a 380 kV Substation and 380 kV high voltage cables between the substation
and the turbines.
This ESIA has been prepared for the Project as part of the Presidency for Meteorology (PME) approval
process. As the first step in this process, a Preliminary Environmental Assessment (PEA) has been prepared
for issue to the PME. This document sets out a clear terms of reference (ToR) for the subsequent ESIA. At this
stage a response has not yet been received from PME. However, any comments they do provide on the PEA
will be integrated into this EIA prior to submission to the PME.
At this stage an Engineering, Procurement and Construction (EPC) Contractor has not yet been appointed by
SEC. This ESIA has therefore been developed on the basis of the Request for Proposal developed by SEC.
This identifies the key characteristics of the power plant, which has been used as the basis for the assessment.
The EIA has also therefore been designed to provide information to SEC on any requirements for changes in
design to mitigate potentially significant environmental impacts and to determine the environmental
management requirements during the construction and operational phases of the project. In this regard the
ESIA has assessed compliance with the following:
The Presidency of Meteorology and the Environment’s ‘General Environmental Regulations’ (GER
2001/2006), the principal environmental legislation in Saudi Arabia, including any pertinent revised
standards released by the PME in 2012;
The Equator Principles;
The International Finance Corporation (IFC) Performance Standards (2012), General EHS Guidelines and
Sector Specific EHS Guidelines; and
The requirements of any relevant Export Credit Agencies, as set out within the OECD Common
Approaches (2012), should the project require international funding.
Project number: 37446130 Dated: 09/11/2014 20 | 278 Revised:
Therefore, this assessment and all associated modelling studies and subsequent impacts assigned should be
considered as indicative only to the expected level of impacts likely to be generated by the Project.
Whilst this ESIA provides a good indication of potential impacts, further detailed studies to include bespoke
modelling studies utilising project information relating to turbine specifications and air and noise emissions
should be undertaken once the EPC Contractor has been appointed and project technical specifications are
confirmed.
Overview of the Project 1.2
The Project will be located in the North Eastern region approximately 55 km north of Duba on the Red Sea
coast. The Project site is approximately 160 hectares.
The Project will have a net output of 485- 550 MWe with natural gas & condensate as the main operating fuel
and Arabian Super Light (ASL) fuel oil as back up fuel. 50 MWe of steam generation will be from solar energy
concentrators and its associated equipment as Integrated Solar Combined Cycle Plant.
This will be the first Integrated Solar Combined Cycle project that SEC have implemented. This is the
organisation’s first step to cutting down carbon emission, increasing fuel efficiency and initiating the solar
industry in Saudi Arabia.
Requirement for an Environmental and Social Impact Assessment 1.3
The Project is considered to be a major project with the potential for significant environmental impacts to occur
as a result of both construction and operation.
Therefore it is anticipated that PME will confirm that an EIA is required for the Project. As a result a Preliminary
Environmental Assessment and Terms of Reference (PEA and ToR) was completed by WSP in March 2014
(WSP, 2014), which has been submitted to PME for their approval.
It is also possible that the Project will attract international financial support. Therefore, the approach adopted for
compiling the scope of works for the ESIA has been designed to demonstrate if both KSA regulations and
standards and International Finance Corporation (IFC) Performance Standards and Environmental Health and
Safety Guidelines, in line with international best practice, are met.
21 | 278
The Environmental and Social Impact Assessment 1.4
Overview 1.4.1
Although this ESIA is referred to as such throughout, the contents, structure and level of assessment are also
consistent with the PME requirements for an EIA and is therefore be considered to be compliant with both
national and international requirements.
The ESIA is has been comprehensively developed to ensure compliance with the following:
Basis Law of 1992, commonly referred to as the ‘Constitution’ of Saudi Arabia;
The General Environmental Regulations, 2001;
The KSA Environmental Protection Standards, 2012;
The requirements of parties providing financing support including:
Organisation for Economic Cooperation and Development (OECD) Common Approaches;
International Finance Corporation Performance Standards, General Environmental Health and Safety
Guidelines and Sector Specific Guidelines (Thermal Power, 2008); and
The Equator Principles.
Purpose of the Environmental and Social Impact Assessment 1.4.2
The overarching purpose of the ESIA is to provide sufficient information to assist the PME, as the national
environmental regulator, and any parties providing financing support, in the decision making process and to
ensure compliance with all relevant regulations, standards, policies and guidance through a comprehensive
description of the following:
The existing environmental baseline;
The likely environmental impacts and significance of such impacts;
Assessment of compliance with national and international standards and guidelines;
The requirement for mitigation and compensation measures; and
The requirements for subsequent environmental management and monitoring to be implemented.
Report Structure 1.4.3
This section provides a summary of the contents of this ESIA document, on the basis of recommendations and
requirements of both national and international requirements, and also in line with the scope of works set out
within the PEA and ToR (WSP, 2014).
Project number: 37446130 Dated: 09/11/2014 22 | 278 Revised:
As noted above, the ESIA report has been prepared in accordance with the specific requirements of PME, and
also references IFC Performance Standards and other international best practice where appropriate. The ESIA
specifically addresses the issues determined within the PEA and ToR (WSP, 2014).
Full details of the scope of works undertaken for each technical assessment are provided within the relevant
technical chapters later in this document.
The ESIA Report is structured as follows:
Chapter 1 – Introduction
Chapter 2 – Project Location
Chapter 3 – Project Description
Chapter 4 – Environmental Legislation and Standards
Chapter 5 – Impact Assessment Methodology
Chapter 6 – Marine Environment
Chapter 7 – Air Quality
Chapter 8 – Environmental Noise
Chapter 9 – Soils, Groundwater and Contamination
Chapter 10 – Waste Management
Chapter 11 – Water Resources and Wastewater
Chapter 12 – Terrestrial Ecology
Chapter 13 – Socio-Economic
Chapter 14 – Cultural Heritage and Archaeology
Chapter 15 – Landscape and Visual
Chapter 16 – Framework Construction Environnemental Management Plan
Chapter 17 – Framework Operational Environmental Management Plan
Chapter 2 – Project Locality provide a description of Project site, details of the legislative and policy framework
and provide a detailed description of the Project, which has formed the basis for the assessment of
environmental impacts.
Chapter 3 provides the methodology for the assessment of impacts which has been undertaken in the following
technical chapters.
Chapter 6 - 15 then present the results of the impact assessment for each of the technical areas considered.
23 | 278
Chapter 16 provides a framework for the development of a Construction Environmental Management Plan
(CEMP) through the provision of appropriate environmental controls to be implemented during the construction
phase of the Project. Chapter 17 provides a framework for the development of an Environmental Management
System (EMS) once the Project becomes operational.
The Project Team 1.5
The Project team comprised the following key managers, environmental and social science experts from WSP
together with specialist sub-consultants. The key Project team members are shown in Table 1-1 below.
Table 1-1 The Project Team
Name Responsibility Company Area of Expertise
Adel Mosaad Mohamed Local EIA Manager Environmental Horizons
Company EIA Management and Regulatory
Coordination
Simon Pickup Project Director WSP Middle East EIA/ ESIA/CEMP/Terrestrial Ecology
Edward Crowley Project Manager WSP Middle East EIA
Nefertari Egara EIA Support WSP Middle East EIA
Apolline Boudier EIA Support WSP Middle East EIA
Mark Scaife Noise and Vibration WSP Middle East Acoustics, Vibration & Noise
Hassan Ktaech Waste WSP Middle East Waste Management
Paul Day Air Modelling PJD Consultants Air emissions and dispersion modelling
Project number: 37446130 Dated: 09/11/2014 24 | 278 Revised:
2 Project Location
Project Site Location 2.1
Kingdom of Saudi Arabia 2.1.1
With a total land area of 2,149,690 km2, the Kingdom of Saudi Arabia (KSA) occupies about three-quarters of
the Arabian Peninsula. Seven countries border KSA; Jordan and Iraq to the north, Kuwait to the northeast,
Qatar, Bahrain and United Arab Emirates to the east, Oman to the southeast and Yemen to the south. The KSA
coastlines (Red Sea to the west and Arabian Gulf to the east) extend over 2,640 km.
The Peninsula is a tilted plateau that slopes from the south-west towards the Arabian Gulf (Vincent, P, 2008).
However, the country has a varied geography ranging from the south-western Asir region, which includes
mountains as high as 3,000 metres and is known for having the most moderate climate in the country, to the
harsh environment of the 647,500 km2 Rub Al-Khali or “Empty Quarter”; the world’s largest contiguous sand
desert. Much of the country’s land mass consists of deserts and semi-deserts which are largely uninhabited.
With the exception of the capital city Riyadh, population centres are predominantly on the eastern (e.g.
Dammam) and western coasts (e.g. Jeddah) and at densely populated interior oases. The country supported a
population of just under 27 million in 2012 and the majority of the people live in the capital city Riyadh, which
has an estimated population of 4.7 million (CIA, 2013).
KSA is an extremely hot and arid country with summer temperatures frequently exceeding 50°C. The average
winter temperatures range from 8°C to 20°C but can drop to as low as 2°C on the high interior plateau. The
climate of the region is dry with large seasonal and daily variations in temperature; rainfall is irregular with large
variations between years. The country has limited freshwater resources and frequent sand and dust storms
occur throughout the year.
Administratively Saudi Arabia is divided into 13 provinces, which are further divided into 118 governorates.
below illustrates Project site in the context of KSA.
The Project Site Context and Features 2.1.2
The Project will be located in North Western Region, The area allocated for the Project is located in the
Tabouk Province about 55 km to the north of the City Duba, on the shore of the Red Sea in Kingdom of Saudi
Arabia. The Project has nearest access to a domestic airport within the road distance of about 140 Km to
Tabouk and within the road distance of about 195 Km to Al Wadjh airport. Railway access to Power Plant site
is not available at or near the site. The nearest sea port is in Yanbu.
25 | 278
Existing Site Conditions 2.2
The Project site is located on an area of approximately 160 hectares of open coastal land. The site is bordered
on the east by a main highway, from Duba to the south to the Jordanian border area to the north, and to the
west by the Red Sea coast.
The terrestrial portion of the site is undeveloped and comprises of raised areas intersected by wadi channels.
The raised areas are barren and largely devoid of vegetation with a ground surface of sandy gravel and small
dark rocks. The wadi channels have more vegetation comprised of Acacia spp. and scattered vegetation
dominated by Zygopyllum sp. growing within sandy substrate. Given the presence of vegetation and
stormwater protection infrastructure on the highway, it is likely that these wadis flood during storm events.
The majority of the coastal portion of the site is comprised of a wide sandy beach transitioning to reef flat in the
subtidal area. The reef flat, which is a shallow area less than 1 metres depth, extends between 100 and 250
metres offshore prior to the reef edge.
Approximately 0.5km north of the site there is a decommissioned industrial facility. Approximately 1.5km north
of the site there is a coastal fish farm facility. This includes the onshore component as well as two large areas
of cages some 0.5km offshore. A warehouse facility associated with the fish farm is located approximately 3km
north of the site.
Project number: 37446130 Dated: 09/11/2014 26 | 278 Revised:
Figure 2-1 The location of the Project Site
27 | 278
Table 2-1 Key site features
Project number: 37446130 Dated: 09/11/2014 28 | 278 Revised:
Site Conditions 2.3
The site reference conditions have been defined by the scope of works document (SEC, 2014) as follows. Table 2-2 Site reference conditions
Description Unit Particulars
SITE AMBIENT DATA
Site elevation (above sea level) m 19 m
Design ambient conditions:
Design ambient pressure mbar 1020
Design ambient temperature °C 50
Design relative humidity % 90 (at maximum dry bulb temp)
Ambient temperature:
Highest maximum (recorded) °C 46
Maximum Hourly Temperature °C 46
Design maximum temperature °C 50
Annual Mean Temperature °C 35
Lowest minimum (recorded) very rare °C 9
Design minimum temperature °C 21
Relative humidity:
Maximum % 95
Minimum Average
% %
21 50
Precipitation: Mean annual rainfall Maximum recorded rainfall in one day
mm mm
60
250
Wind speed: Max recorded wind speed
m/s
150
Air quality: Air pollution
The region of installation is subject to sand and dust storms. Usual dust in air concentration may be as high as 1 mg/m3. During sandstorms concentrations of 100 – 500 times higher may be encountered. Sand typically consists of calcium, silicon, manganese, aluminium and sodium compounds and in the presence of high humidity it can conduct electricity and corrode metal. All enclosures shall be designed and adequately pro-tected to prevent ingress of dust.
29 | 278
Description Unit Particulars
Water Supply Data: Raw water source Maximum seawater temperature Minimum sea water temperature
°C
°C
Sea water
35 19
Surrounding Areas 2.4
The nearest residential communities are Sharmaa, located 32km north east; Al Sourah, located 15km to the
north west; and Al Muwaylih, located 8km to the south west. There are no permanent residential areas on the
site or in the immediate surrounding area.
Key Sensitive Receptors 2.5
As described above the Project site is currently undeveloped and there is very limited development within the
surrounding area. The closest existing human receptors would be staff of the fish farm facility located
approximately 1.5km north of the site. Al Muwaylih is a small residential community located approximately 8km
south west of the site.
Table 2-3 Key Sensitive Receptors
Receptor Potential Construction Impacts Potential Operational Impacts
Fish farm employees and
fish farm Dust and noise impacts
Water quality impacts from marine
construction activities
Exposure to air emissions from The
Project
Water quality effects from the
marine outfalls
Marine environment
(including fringing reef
environment)
Direct impacts associated with
construction of marine components
Indirect impacts associated with
impacts upon water quality
Effects associated with the intake
and discharge of cooling water
Effects associated with the
discharge of other treated
wastewaters from the plant
Al Muwaylih Town Disturbance from construction traffic
and staff
Increased revenue for local
businesses due to presence of
construction staff
Increased demand for local services
Exposure to air emissions from the
Project
Social effects associated with the
presence of SEC labour force
Construction workers Health and safety
Working conditions and welfare N/A
Project number: 37446130 Dated: 09/11/2014 30 | 278 Revised:
Receptor Potential Construction Impacts Potential Operational Impacts
Operational staff N/A Health and safety
Working conditions
Exposure to air and noise emissions
from The Project
Terrestrial ecology Loss of native habitats
Loss of native species N/A
Soil & groundwater Potential for existing contamination
associated with decommissioned
industrial facility
Contamination events associated with
construction works
Contamination events associated
with operations
Socio-Economic Positive socio-economic impacts
through employment opportunities for
Saudi nationals and skills transfer
Positive socio-economic impacts
through employment opportunities
for Saudi nationals, skills transfer
and the supply of power
Waste management facilities Potentially significant waste arisings Potentially significant waste arisings
31 | 278
3 Project Description
Introduction 3.1All the Project design information presented below has been sourced from Construction of Duba Integrated
Solar Combined Cycle Project Project Schedule “B” Attachment III, Detailed Scope of Work (SEC, 2014). Only
the most pertinent elements of the plant are described.
Project Justification 3.2The demand for electricity in Saudi Arabia has increased dramatically over the past decade. Power
consumption is set to continue to increase with SEC forecasts indicating that power usage will increase to
75,155 MW by 2020. The power industry is a strategic industry in Saudi Arabia and has ensured the continued
economic development and industrial diversification in the Kingdom.
The total Project net output will be of 485- 550 MWe at reference site conditions (RSC). Therefore, the Duba
Integrated Solar Combined Cycle Project is a project of national importance in terms of its contribution to the
continued economic development of the Kingdom. This is also the first Integrated Solar Combined Cycle project
that will be implemented by SEC representing a positive step towards sustainability.
Project Layout 3.3
The scope of the Project includes the main components identified in the drawing as the Power Plant and all
associated facilities, the SEC housing compound, and the access road. The other main component will be the
construction of the 380 kV substation which is shown on the drawing to the north west of the plant.
Figure 3-1 below shows the general layout of the Project site in relation to the International Highway and Figure
3-2 below shows the Project layout within its surrounding environment.
Project number: 37446130 Dated: 09/11/2014 32 | 278 Revised:
Figure 3-1: General layout of the Project site (SEC, 2014)
380 kV substation
Company housing compound
Solar Collector Assemblies (SCA)
HRSG and stacks
Steam turbine building
Gas Turbine (GT) building
Intake structures
Outfall structures
33 | 278
Figure 3-2: The project layout plan overlaid onto a satellite image
Project Specification Summary 3.4
Site Preparation Works 3.4.1
In order to inform the suitability of the site for development, the appointed EPC Contractor will undertake all
required site preparation surveys, including topographic surveys and intrusive geotechnical investigations.
Site clearance and site preparation works shall include removal of all obstacles, removal of all vegetation or
unwanted materials and plantation, removal and disposal of soil, rough and final grading, excavation and back
filling with selected structural fill under and around the foundations, floor slabs and other structures.
700m
Project number: 37446130 Dated: 09/11/2014 34 | 278 Revised:
Power Plant Description 3.4.2
A detailed layout drawing for the power plant showing the location of various components is provided within
Appendix B.
The Project shall be based on commercially proven F-class and E Class gas turbines (GTs) with a total Plant
net output of 485-550 MWe at RSC with specified main operating fuel, natural gas and condensate gas fuel and
Arabia Super Light (ASL) fuel oil as back up fuel and production of equivalent to 50 MWe steam generation
from solar energy concentrators and its associated equipment as Integrated Solar Combined Cycle Plant
(ISCC).
The nominal capacity of the GTs shall be chosen to suit and meet the net power output in MW of each block
and station. The GTs shall operate initially in the simple cycle mode until construction of the combined cycle
portion is completed. The GTs shall retain the ability to operate as simple cycle units in the event there are
disturbances in the combined cycle portion.
The Project shall comprise two power blocks consisting of new, unused F- Class and/or E-Class gas turbine
generators (GTG), heat recover steam generator (HRSG) and steam turbine generator (STG) packages as
procured by the Contractor from the GTG/HRSG/STG original equipment manufacturer (OEM) supplier
including all associated auxiliary and accessory equipment. The Project will also include all associated
auxiliaries as well as Solar system equipment and the necessary Balance of Plant (BOP) equipment.
Plant Design Criteria 3.4.3
The design of the plant shall be in accordance with internationally recognised engineering standards &
practices, to ensure efficient, high reliability, maintainability and availability of the complete plant.
The gas turbine generator units shall have a net output of 485- 550 MWe at RSC. The new combined cycle
plant shall be with two blocks (Block A & Block B). Two options for the plant configuration are being examined
and are presented as follows:
Option 1 – Block A (1+1+1) will include one GTG (#1) unit Class F, one HRSG (#1), and one STG with all
associated auxiliaries and corresponding BOP. Block B (2+2+1) will include the units two GTG units (#2 &
# 3) Class E, two HRSGs (#2 & # 3) and one STG with all associated auxiliaries and corresponding power
plant BOP; and
Option 2 – Block A (2+2+1) will include the units two GTG (#1 & #2) units Class E, two HRSG (#1 & #2)
and one STG with all associated auxiliaries and corresponding BOP. Block B (2+2+1) will include the units
two GTG units (#3 & #4) Class E, two HRSGs (#3 & #4) and one STG with all associated auxiliaries and
corresponding power plant BOP.
The steam turbine generator unit shall be operating within its entire load range on a continuous basis.
35 | 278
Simple Cycle Operation
Each gas turbine unit shall be able to operate as simple cycle as soon as installation and commissioning of
each gas turbine unit has been finalised successfully. Each gas turbine shall be able to operate in the entire
load range from minimum stable load to full load on a continuous basis and under the load change rates with
the specified fuels and ambient conditions as specified.
Combined Cycle Operation
Each block shall be capable of operating in combined cycle mode in the entire load range of the gas turbine
units in all modes (cold/warm/hot) with the specified fuels and ambient conditions as specified. The plant shall
be capable of operating with any number between one and all of HRSG units in the block feeding steam to the
steam turbine. The steam turbine unit shall be capable of operating within its entire load range on a continuous
basis.
The plant shall be designed to allow the GTGs to increase load at their maximum allowable ramp rate in
combined cycle operation and under the load change rates.
The Plant shall be capable of changing from simple cycle operation to combined cycle operation without shut-
down if the purge state of the flue gas path allows. Load reduction of the gas turbines during the change from
simple cycle to combined cycle shall only be permissible as far as required for temperature matching between
gas turbine exhaust and HRSG.
Fuel Specifications 3.4.4
The main fuel for the plant is natural gas and condensate gas fuel and both shall be supplied by pipeline. The
Project scope includes the construction of a fuel gas pipeline and a condensate gas fuel pipeline from the tie-in
point with Saudi Aramco pipeline.
The backup fuel for the plant will be to Arabian Super Light (ASL). Start-up fuel shall be natural gas and
condensate gas fuel. In case of interruption of natural gas supply or condensate gas fuel, automatic switching
to ASL shall be used for start-up. The plant will include facilities for the receiving of ASL fuel unloading station
from tanker truck and storage tanks including fuel oil treatment system for ASL fuel. Facilities will be also
included for the receiving of distillate fuel from unloading station by tanker truck and day tank for Black start /
Emergency diesel generators and diesel fire pumps
Precise fuel specifications for natural gas, ASL and distillate fuel are provided in Appendix C.
Solar Field Island Equipment and Associated Auxiliaries 3.4.5
The solar island system is sized to enable the production of steam for additional 50 MW minimum net power
output at RSC by delivering steam to combined cycle steam system.
The Solar Field Island and associated equipment and auxiliaries will be designed and operated for daily cycling
following the solar irradiation profile from sunrise to sunset at all site conditions. Whereas, the Solar Field Island
shall be operated in accordance to the highest possible load conditions limited by the solar irradiation only.
Project number: 37446130 Dated: 09/11/2014 36 | 278 Revised:
The Solar Field Island will operate in such a way to minimise start-up, shut-down and change-of-operation-
mode.
The solar steam will be integrated after the combined cycle steam system and be fully dispatchable within the
emission limits at any solar steam delivery flow.
Raw Water Supply 3.4.6
The technical specifications propose that raw water be sourced from the sea water intake auxiliary cooling
water pumps to be constructed as part of the contract scope. The raw water shall be further processed through
reverse osmosis to produce service water, potable water and demineralized water in a demineralized water
treatment plant.
Water and Wastewater Treatment 3.4.7
Reverse Osmosis Plant
The reverse osmosis (RO) plant will be designed to be capable of processing water from sea water. Two RO
trains will be installed with sufficient capacity to provide water to the fire protection system, service water
system, potable water, demineralized water and water & steam cycle, make up water, wash down cycle for fuel
treatment, closed cooling water system, and water requirements for SEC housing compound but not less than
available capacity of 1500 m3/day whichever is greater value.
The RO Plant shall be a two-pass permeate staged membrane process system, based on the level of sea
water quality. The increase in efficiency and the life of the RO membrane elements shall be maximized by the
correct and effective pre-treatment of the sea water feed to the plant.
A minimum of one week of water storage will be produced by the RO plant and will be stored in two equal
capacity tanks.
It is likely that brine from the desalination plant will be mixed with cooling water and discharged to the sea.
Demineralized Water Treatment Plant
This will comprise a demineralized water treatment plant using Continuous Electro-Deionization units (CEDI)
designed for water derived from the RO plant, demineralized water storage tanks, chemical storage tanks and
pumps, chemical neutralization tanks, pipe work, controls and auxiliary components etc.
The demineralization plant capacity shall be designed to supply the requirements of all demineralized water
consumers (such as closed cooling water system, compressed air, fuel oil treatment, laboratory etc.) plus
generating unit makeup water for all HRSGs units.
Potable Water System
The potable water system shall be designed based on the number of operational staff foreseen at the power
plant and for SEC housing. Potable water storage tank will be provided at a capacity of 500 m3 for the power
plant. The system shall comprise of, but not be limited to:
37 | 278
Potable water system feed pumps;
Ultrafiltration with remote pressure drop supervision;
Food grade Sodium Hypochlorite dosing system;
Remineralisation units;
Above ground Steel Potable water tank serving only lavatories, bathrooms, safety showers, wash down
locations etc. Head Tanks for Potable Water System shall also be provided at required location of the
power plant buildings to ensure positive supply of potable water to meet the requirement;
Elevated potable water storage tower tank in the Housing Compound for minimum two days’ requirement,
considering 300 litres per person for 700 peoples plus 10 % margin;
Supply and distribution system;
Interconnection of service water and potable water tank by isolation valve;
Continuous monitoring and analyser with automatic dosing control to be provided in remineralisation plant;
and
The Potable water for personal use shall be run through the facility and branched at convenient locations to
supply facilities such as offices, meal location and site offices, living accommodation and SEC housing
compound.
Make-Up Water System
Storage tanks for the make-up water system will be provided with stair case and all required attachments such
as gauge, level indicator and nozzles, instruments, etc. The system will also comprise:
Demineralised water storage tanks of capacity to satisfy the following criteria:
1,500m3 minimum capacity;
72-hour consumption for natural and condensate gas operation of the power plant;
4 hour consumption for ASL treatment; and
Two complete fills of the steam water cycle.
Demineralised water distribution pumps; and
Demineralised water piping.
Service Water System
The service water tanks will hold a capacity equivalent to the water consumption for 72 hours of average
service water consumption, for a minimum size of 2,000m3. The service water system shall comprise of, but not
be limited to:
Service water pumps;
Project number: 37446130 Dated: 09/11/2014 38 | 278 Revised:
Supply and distribution system;
Interconnection to potable water tank with isolation valve; and
Supply and utility stations in GTG/STG building, HRSGs and in BOP buildings.
Sanitary Wastewater Treatment Plant
The sanitary waste water from toilets, showers, kitchen etc. shall be collected and treated by a sewage
treatment plant. The hydraulic design basis for this treatment facility shall be for total 700 people (150
employees at power plant, and 550 personnel at housing compound) of capacity i.e. 210 m3/day based on 300
litres per person /day, BOD of 0.08 kg/person/day and TSS of 0.09 kg/person/day. The system shall use gravity
or lift stations as required to collect and forward the sanitary waste water to the sanitary waste water treatment
plant. Each lift station shall be provided with 2 x 100% submersible pumps, pipes, valves and instruments.
The sanitary waste treatment shall be aerobic type. It shall be designed not to allow septic conditions in any
part of the plant during the collection, treatment, and storage of input sanitary waste water or product water or
thickened sludge. The treatment shall be designed to accommodate the non-constant sanitary waste water flow
on hourly, daily or annual basis.
The treated sewage water shall be collected in a separate chamber for serving the plant irrigation.
Rainwater
The final grade level throughout the site shall be selected such that rain water flooding is avoided. A stormwater
drainage system shall be provided with pipes which will drain to manholes and discharge to the storm water
drainage system.
Rainwater that falls in areas with the potential for oily residues, such as the diked area for the fuel oil tanks, will
be collected separately and directed to the oil water separator along with other industrial wastewater from the
plant.
Hazardous Wastewater / Liquid Disposal
Wastewater from gas turbine washing (which will contain detergents and other contaminants) will be stored in
the drain tanks for removal off-site by truck. Various oily wastewaters (from false starts and plant equipment
drains) will also be disposed of off-site by trucks. The disposal of hazardous liquid wastes will be undertaken by
licensed contractors only.
Evaporation Pond
Residual effluents, which cannot be re-used, shall be discharged to sea after treatment or to the evaporation
pond. The pond, which is located on the Project site, will be equipped with a sealing bottom layer and sized to
ensure complete evaporation of the produced effluents during all seasons of the year. Consequently, operation
of the combined cycle plant will not lead to any discharge of effluents to the environment. Nevertheless all
effluents shall be treated by neutralization, oil separation and solids removal before final discharge to the sea or
evaporation pond.
39 | 278
Final discharges and performance of the evaporation pond shall at least meet environmental treatment
standards recognised by industrial plants of similar nature. Dsfd
Waste Management 3.4.8
Waste materials shall be properly disposed as the requirements of local concerned authorities. The contractor
shall be responsible for the sanitation of the waste disposal area including the elimination of rodents and
insects.
Staff 3.4.9
The current stage of the plant shall be designed for an organization of 150 working persons.
SEC Housing Compound 3.4.10
The project scope includes the provision of a housing compound for a minimum of 700 people. The housing
compound will be located in an area approximately 100m north from the power plant site boundary. The
compound will include:
Ten family villa units;
100 family apartments units;
40 bachelor accommodation units;
Healthcare facility;
Mosque;
Shops;
Indoor and outdoor recreational facilities;
Open spaces and playgrounds;
Main entrance gate with gate house and security system;
Security fencing;
Roads; and
Landscaping.
All requirements for electricity, lighting, HVAC, water, sewage, drainage, telephone, internet, firefighting, fire
hydrants, fire hose cabinets, portable fire extinguishers and fire detection systems for each of the villas,
apartments, recreational and other facilities within the housing compound will also be provided.
Project number: 37446130 Dated: 09/11/2014 40 | 278 Revised:
Roads 3.4.11
New Approach Road to Power Plant
The Project scope includes designing and constructing a new four lane road access (each lane 3.5 meters
width) to provide a connection between the highway and the power plant. A separate access from existing
highway shall be provided for housing compound with two lanes each of 3.5 meters width with paved
shoulders. The road shall be provided with street lights, road markings, road signs and drainage slopes towards
the hedging and trees.
The proposed access road shall be designed for heavy duty construction in order to allow safe transport of
heavy weight equipment such as turbines, generators and transformers.
Plant Roads
Roads within the power station will be of 10m wide for the main roads and 8m wide for secondary roads. The
road network system may be constructed in asphaltic concrete but concrete paving will be provided where
petrol/oil or other chemical spillage may occur as well as in front of the transformer compounds. The road shall
be provided with bollards and/or barriers, road markings, signs and road lights and footpaths. An appropriate
width of footpath shall be provided to facilitate the safe movement of pedestrians around the site.
Patrol Roads
The internal and external asphaltic concrete patrol road shall be provided all along the perimeter of security fence and around the tank farm area. The width of petrol road shall be 4.6m with hard shoulder and gravel sur-facing.
Plant Design Life 3.4.12
All equipment and components of the Plant shall have a design life time of 262,800 operating hours as a
minimum, but at least 30 years. The civil facilities, installations and building service systems shall satisfy the
design lifetime criteria of 50 years.
41 | 278
4 Environmental Legislation and Standards
Regulatory Environmental Framework in KSA 4.1
Basis Law of 1992 4.1.1
The Kingdom of Saudi Arabia (KSA) has a suite of laws that aim to protect the environment, fauna and flora
from wilful damage or destruction. Several of these laws are embodied in the Basis Law of 1992, commonly
referred to as the ‘Constitution’ of Saudi Arabia.
Article 1 of the Basis Law defines “environment” as man’s surroundings including air, water, land and outer
space together with all matter, fauna and flora, different forms of energy, physical systems and operations and
human activities. ‘Environmental Protection’ is taken to mean the preservation of the environment and the
prevention and curbing of environmental pollution and degradation.
Article 2 defines the Law’s objectives as:
Preserve, protect and ameliorate the environment and prevent pollution;
Protect public hygiene against the dangers of activities deleterious to environment;
Conserve, develop and rationalize the use of natural resources;
Make environmental planning an integral part of comprehensive development planning in all industrial,
agricultural and urban fields, etc.; and
Enhance environmental awareness, instil a sense of individual and collective responsibility for
environmental protection and improve and encourage national voluntary efforts in this respect.
Article 2 also requires the Concerned Authority (PME) to undertake such tasks as may protect and prevent
degradation of the environment, and in particular to:
Review and assess the state of the environment, upgrade monitoring techniques and tools, collect
information and conduct environmental studies;
Document and publish environmental information;
Prepare, issue, review, develop and interpret environmental protection standards, draft environmental laws
relevant to its responsibilities;
Ensure compliance by Public Authorities and individuals with environmental laws, standards and criteria,
and take necessary measures to this end, in co-operation and co-ordination with the Competent and
Licensing Authorities;
Project number: 37446130 Dated: 09/11/2014 42 | 278 Revised:
Monitor new developments in the domain of environment and environmental management on regional and
international levels; and
Promote environmental awareness on all levels.
The General Environmental Regulations, 2001 4.1.2
Regulation and protection of the environment in Saudi Arabia is controlled and operated under the jurisdiction
of the PME. The regulatory requirements and enforcement regime for pollution control in the KSA has been
significantly strengthened in recent years by the introduction of the General Environmental Regulations (GER,
2001). These have placed specific requirements and duties on PME to apply environmental law across the
whole Kingdom and develop a system of regulation and enforcement. The GER is subdivided into the following
three sections:
General Environmental Law;
Rules for Implementation; and
Environmental Protection Standards.
Table 4-1 below provides a list of relevant environmental legislation in KSA. Further detail will be provided in
the following sections where required.
43 | 278
Table 4-1 Relevant Content of the General Environmental Regulations
Regulation Title Sub Title (if applicable) Regulator
General Environmental Regulation 2001
The ‘Act’ in 24 Articles PME
Rules for Implementation (General Environmental Regulation) 2001
The regulations in 22 Articles PME
Environmental Protection Standards (Rules for Implementation) 2001
Environmental standards for issue areas PME
GER Art 3, 4 & 10, 11, Duties and obligations
Regarding the implementation of these regulations
PME
GER Art 5 Requirement for EIA - PME
GER Art 6 Requirement for BAT -
GER Art 7 Education and communication
- PME
GER Art 8 Conservation of Natural Resources
- PME
GER Art 9 Environmental Disaster Planning
- PME
GER Art 12 Waste management and disposal
- PME/Municipalities
GER Art 13 Prevention of pollution - PME
GER Art 14 Hazardous waste management
- PME/Municipalities
GER Art 15 Implementation and timescales
- PME
GER Art 16 Project financing and development
- PME
GER Art 17, 18, 19, 20 Violations and penalties
Includes grievances and appeals. PME
Doc 1409-01 GER Air quality 1982 Ambient air and source standards PME
Doc 1409-01 GER Water quality 1982 Ambient and discharge standards to environment and wastewater treatment works.
PME
Doc 1409-01 GER Appendix 2 1982 EIA regulations PME
Doc 1423-01 GER Appendix 4 1992 Waste management regulations PME
Project number: 37446130 Dated: 09/11/2014 44 | 278 Revised:
Revised Environmental Protection Standards 4.1.3
In 2012, PME issued a revised set of Environmental Protection Standards to replace those previously referred
to within the GER (2001). These new standards are listed below and became effective as of 24th March 2012.
The results of this assessment have therefore been compared against the provisions set out within these
updated set of legislative requirements.
National Material Recovery and Recycling of Waste Guidance Document for KSA;
Standard for Control of Emissions from Mobile Sources;
General Environmental Standard for Noise;
Standards for the Control of Emissions to Air from Stationary Sources;
Protection of Major Accidents;
National Storage and Material Reclamation Facilities – Design and Operation Standard for KSA;
National Thermal Treatment and Incineration Design and Operation Standard for KSA;
Waste Acceptance Criteria Standard for KSA;
Waste Classification Standard for KSA;
Drinking Water Quality;
National Biological Treatment Design and Operations Standards for KSA;
Waste RCC Standard for KSA;
National Waste Storage Standard for KSA;
National Waste Training and Assessment of Technical Competence of Operators Standard for KSA;
National Waste Transport Standard for KSA;
National Landfill Design and Operations Standards for KSA;
Wastewater Discharge Standards for KSA;
National Best Practicable Environmental Option for Waste Disposal Guidance Note for KSA;
Ambient Air Quality Standard; and
National Ambient Water Quality Standard for KSA.
45 | 278
Environmental Impact Assessment 4.2
KSA Requirements 4.2.1
An EIA is required in KSA on the basis of the General Environmental Regulations (GER) 2001 for specific
projects.
In accordance with the industrial and development project classification guide, Appendix No. 2.1 of the GER
2001: “Guidelines for Classification of Industrial and Development Projects”, issued by PME, projects are
classified into three categories taking into consideration their environmental impacts. For projects within the first
and second categories, an initial environmental assessment report, in addition to the forms included within the
regulations themselves, is usually sufficient although an EIA may potentially be required by the PME.
Larger power plants, with capacities in excess of 30 MW, are classified as Category III projects. Projects falling
within this category, in the absence of full mitigation, could be expected to have negative effects on human
health and the environment and thus require a comprehensive EIA.
Guidelines for compiling the EIA are stated in Appendix 2.4 of the GER 2001. The regulations specify that the
EIA should include, but not be limited, to:
Justification and presentation of the project;
Description of the project and its objectives;
Baseline status of the surrounding environment including the following:
Air quality;
Soil and topography;
Oceanography;
Surface and ground water;
Land environment (fauna/flora);
Marine environment (fauna/flora);
Land use of selected site and its surroundings; and
Land ownership (original owner).
The GER 2001 further states that an EIA should include the following:
Identification of the general potential impacts of the project and suggested alternatives; and
Identification and analysis of key effects of the project on air quality, the marine and coastal
environment, surface-and-groundwater, flora and fauna, land use and urban development, residential
clusters and general scenic view.
Project number: 37446130 Dated: 09/11/2014 46 | 278 Revised:
Assessment of significant impacts, which should:
Quantify and rate the significant impacts on natural resources;
Estimate the relative damage to the area and the extent of potential damage;
Estimate the lifespan of the facilities;
Study the possible mitigation of anticipated impacts; and
Provide a summary of the significant (residual) impacts after mitigation.
International Finance Corporation Performance Standards 4.2.2
Given that the project is likely to attract private sector finance, it is assumed that an EIA would need to assess
the environmental impacts in accordance with the International Finance Corporation (IFC) Performance
Standards. For projects located in non-OECD countries (as is the case for KSA), the EIA should refer to the IFC
Performance Standards and IFC Environmental Health and Safety Guidelines, which provide general and
sector specific guidance.
All IFC projects or projects where IFC Performance Standards (updated 2012) are adhered to must meet with
the following Performance Standards on Environmental and Social Sustainability:
Performance Standard 1: Assessment and Management of Environmental and Social Risks and Impacts;
Performance Standard 2: Labour and Working Conditions;
Performance Standard 3: Resource Efficiency and Pollution Prevention;
Performance Standard 4: Community Health, Safety and Security;
Performance Standard 5: Land Acquisition and Involuntary Resettlement;
Performance Standard 6: Biodiversity Conservation and Sustainable Management of Living Natural
Resources;
Performance Standard 7: Indigenous Peoples; and
Performance Standard 8: Cultural Heritage.
In addition to meeting the requirements under the Performance Standards, projects must also comply with
applicable national laws, including those laws implementing host country obligations under international law.
The IFC has prepared a series of Environmental Health and Safety Guidelines, which provide general and
sector specific guidance. These documents provide details of the required levels and considerations when
undertaking an EIA for a project. The following would specifically be referred to as part of the preparation of an
EIA for the project:
IFC General EHS Guidelines (2007);
IFC EHS Guidelines for Water and Sanitation (2007); and
47 | 278
IFC EHS Guidelines for Thermal Power Plants (2008).
Equator Principles 4.2.3
In October 2002, the IFC convened a meeting of banks in London to discuss environmental and social issues in
project finance. It was decided to try to develop a banking industry framework for addressing environmental
and social risks in project financing. This led to the drafting of the Equator Principles. On June 4th, 2003, 10
banks from seven countries signed up to the Equator Principles, a voluntary set of guidelines for assessing and
managing environmental and social risks in project financing. To date, in excess of 60 financial institutions
operating in more than 100 countries worldwide have adopted the Equator Principles. As a result, the Equator
Principles have become the industry standard for addressing environmental and social issues. During March to
May 2006, the Equator Principles Financial Institutions (EPFIs) engaged in a substantive review of the Equator
Principles. The revised principles became effective from July 6th, 2006, although have recently been
superseded by a third revision on 4th June 2013. This revision is referred to as ‘Equator Principles III’ (EP III).
EP III ensures a strengthened framework for both social and environmental aspects and will result in benefits
for Equator Principles Financial Institutions e.g. improved transparency in reporting, and focus on emerging
social and environmental concerns. The key changes to these revised principles relate to project related
corporate loans and bridge loans. The revised EP III will not be mandatory for application to Projects until
January 2014.
The key points to note are as follows:
The Equator Principles apply to all new project financing that has a total capital cost of $10 million or more
across all industry sectors (the previous threshold was $50 million);
For projects with potentially significant social and environmental impacts (Category A and B), the borrower
must complete and disclose a Social and Environmental Assessment (EIA) (previously called an
Environmental and Social Impact Assessment). The EIA must now comprise a detailed assessment of
social and environmental impacts including labour, health and safety; and
In the context of the project, the EIA report must address the relevant potential impacts and risks.
Environmental Standards Applicable to the Project 4.3
This section details applicable environmental standards which have been specified within the technical
specification (SEC, 2014). In the absence of any specific information and/or requirements set by SEC, the
relevant IFC/PME environmental requirements that must be adhered to during the design, construction and
operational phases of the facility are presented.
Ambient Air Quality 4.3.1
Table 4-2 below provides the relevant values for each important air quality parameter for PME (and the IFC).
Project number: 37446130 Dated: 09/11/2014 48 | 278 Revised:
The PME ambient air quality standards are straightforward and apply to all circumstances. However, the IFC
standards require a certain level of interpretation due to various ‘interim’ and ‘guideline’ values being specified
rather than fixed limits. The WHO guidelines provide interim targets for countries that still have very high levels
of air pollution to encourage the gradual cutting down of emissions.
Guidelines values have the objective of minimising the health effects associated with each pollutant.
The PME and IFC air quality standards (AQSs) and emission limits for the pollutants considered are also
shown in Table 4-2 and Table 4-3, respectively.
Table 4-2 PME and IFC Ambient Air Quality Standards for SO2, NO2 and PM10
Pollutant Averaging period PME (µg/m3) IFC EHS Guidelines (µg/m3)
NO2 1-hour
Annual
660(a)
100
200
40
SO2 10-min
1-hour
24-hour
Annual
--(b)
730(a)
365(c)
80
500
--
125 (interim target 1)
50 (interim target 2)
20
--
Inhalable suspended particles (PME) or PM10 (IFC)
24-hour
Annual
340(c)
80
150 (interim target 1)
100 (interim target 2)
75 (interim target 3
50
70 (interim target 1)
50 (interim target 2)
30 (interim target 3)
20
a) Not to be exceeded more than twice per month (30 day period).
b) No 10-min standard has been set by PME.
c) Not to be exceeded more once during any 12 month period.
Stack Emissions Limits 4.3.2
SEC has not explicitly prescribed stack emission limits for the proposed facility. From an engineering point of
view, SEC does however note the following:
Stack height shall be a minimum of 60 meters above the finished floor level of the HRSG;
Bypass stacks shall be a minimum of 40 metres above the finished floor levels of the HRSG; and
49 | 278
The stack height shall conform to KSA-PME regulations and shall disperse emissions such that ground level
impacts are within regulations.
In the absence of such information, we have determined the requirements in line with international best practice
in the form of the IFC EHS Guidelines for Thermal Power Plants together with additional information in respect
to PME’s requirements with regards air pollution source standards as shown in Table 4-3 below.
Table 4-3 PME/IFC Emission Standards for SO2, NO2 and PM10
Pollutant PME (2014) IFC EHS Guidelines (Combustion Turbines >50MWth)
Non-degraded Air shed/Degraded Air shed
NOx 500 mg/Nm3(a)(b) (NDA)
350 mg/Nm3 (NDA) 74 ppm (152 mg/Nm3)(b) - Fuels other than Natural Gas
SO2 600 mg/Nm3 (NDA)
400 mg/Nm3 (DA)
Use of 1% Sulphur content or less in fuel (NDA)
Use of 0.5% Sulphur content or less in fuel (DA)
PM10 150 mg/Nm3 (NDA)
100 mg/Nm3 (DA)
50 mg/Nm3 (NDA)
30 mg/Nm3 (DA)
(a) It is assumed that mg/Nm3 is the correct unit, as stated in Article II(1)(b) of the KSA National Environmental Standards – Control of Emissions to Air from Stationary Sources (PME 2014)
(b) Nm3 – Normalised cubic metre, reference conditions 273K, 101.3 kPa, dry gas, 15% oxygen.
It should be noted that there is some confusion with the revised PME emissions standards as the units
presented within Appendix A of Control of Emissions to Air from Stationary Sources are g/Nm3, whereas
within the standard itself (Article II – General Provisions, 1 Units of Measurement) state that “Milligrams per
normal metre cubed (mg/Nm3) shall be used to indicate the concentration of gaseous, particulate and toxic
pollutants”. It is therefore assumed that mg/Nm3 is the correct unit.
Environmental Noise Standards 4.3.3
SEC (2014) stipulates a number of requirements in terms of noise emissions that, unless otherwise stated in
the Specifications, the absolute limit of any A-weighted sound pressure level measured in accordance with ISO
3746 from any equipment or plant supplied under this Contract shall not exceed 85 dB(A) at a distance of one
(1) meter from the source during normal plant or unit operation and 1.2 m above ground level or personnel
platforms.
Emissions from the Project will also need to comply with the operational noise criteria as laid out within the
PME General Environmental Standard for Noise, together with the IFC General EHS Guidelines (2007) as
illustrated in Table 4-4 below. For reference purposes, it is worth noting the IFC Guidelines criteria for noise
emissions from industrial premises stipulate that:
‘Noise impacts should not exceed the levels presented in… [Table 4-4]…or result in a maximum increase in
background levels of 3 dB at the nearest receptor location off-site’.
Project number: 37446130 Dated: 09/11/2014 50 | 278 Revised:
Table 4-4 PME & IFC EHS Noise Guidelines Limit Values
PME IFC
Receptor LAeq,T (dB) Leq,1hr (dBA)
Day-time Evening Night-time
Daytime
07:00 – 22:00
Night-time
22:00 – 07:00
Residential; Institutional; Educational. 55 50 45 55 45
Industrial;
Commercial 75 65 55 70 70
Article V – Noise from industrial units in areas set aside primarily for industrial facilities sets out a range of
permitted noise limits, classifying land uses types for which different noise limits apply. On the basis of the
descriptions provided for each category, it can be concluded that the Project can be classified as A4 – Medium
density industrial and is therefore required to adhere to the standards provided within Table 4-5 below.
The General Environmental Standard for Noise issued by PME, provide maximum permissible façade noise
limits for general construction within Article VI – Noise from Construction Activities, in addition to ambient noise
standards during operation; these are detailed below in Table 4-5 and will be applicable during the construction
phase of the project.
Table 4-5 PME General Construction – Maximum Permissible Façade Noise Limits
Water Quality Standards 4.3.4
The Government of Saudi Arabia has taken several steps and decisions to control and protect the coastal
environment. The most salient of these are listed below.
Environment Protection Standards: these are contained in Document No.1401-01, (2006), PME.
National Oil Spill and Hazardous Substances Contingency Plan: This plan is set in Decision No. 157 dated
20/11/1411 H, (June 1991) by the Council of Ministers. This decision called for the formation of a
Daytime
LAeq,12h (dB)
Evening
LAeq,12h (dB)
Night-time
LAeq,12h (dB)
5m 5m 5m
80 80 80
51 | 278
committee from five governmental bodies, to be involved in the implementation of this plan. Members of
this committee are:
1. Ministry of Defense and Aviation PME
2. Ministry of Interior Coastal Guards and Defence
3. Ministry of Petroleum and Minerals
4. Port Authority
5. Ministry of Municipalities and Rural Areas
Environmental Impact Assessment: A draft for the implementation of Environmental Protection Standards,
and Principles and Procedures for Environmental Impact Assessment (PME).
Wildlife Protection: Establishment of the National Commission for Wildlife Conservation and Development
(NCWCD) in May 1986. The main goal of this commission is to preserve, protect and develop Wildlife
within the Kingdom. Several protected areas were already established and supervised by NCWCD – Assir
National Park established in the Southern part of the Kingdom and supervised by the Ministry of
Agriculture. Wildlife protected Areas regulation. Issued under Ministerial Resolution No. 124 (26-10-1415
H), March 1995, administered by the NCWCD.
International Obligations: Saudi Arabia has also accepted its role in the international arena of
environmental protection and management by acceding to and ratifying a number of international
conventions and other agreements.
The KSA National Environmental Standard for Ambient Water Quality (2012) provides the recommended
thresholds for pollutants within marine water bodies. A sub-set of relevant limit values are shown in Table 6-1
below.
A number of additional requirements are also presented within these standards, the most relevant of which are:
Mixing zone requirements – this defines the area adjacent to an outfall where exceedances of ambient
standards are permitted. Mixing zones should not exceed 100m radius and should not impinge upon
sensitive habitats, such as coral reef. If the mixing zone requirements are determined to be unachievable
then a detailed study must be undertaken to demonstrate that the best achievable mixing zone dimensions
have been achieved using best available technology (BAT) and that environmental impacts have been
minimised.
Maintenance of background conditions – if background conditions are known to be better quality than the
ambient standards than those conditions must be maintained as a minimum requirement.
The KSA National Standards for Industrial Wastewater and Municipal Wastewater Discharges (2012) provide
limit values for discharge of pollutants into the Red Sea. A sub-set of relevant limit values are shown in Table
6-1 below.
Project number: 37446130 Dated: 09/11/2014 52 | 278 Revised:
Table 4-6 Examples of relevant ambient water quality and discharge limits from PME 2012
Parameter Unit Red Sea Ambient Criteria* Red Sea Discharge Criteria*
Temperature °C 3 7
pH pH units 0.2 6-9.5
Salinity % 0
Turbidity NTU 2 50
TSS mg/l 5 15
BOD mg/l 10 25
Ammonia mg/l 0.1 1
Aluminium mg/l 0.2 10
Lead mg/l 0.05 0.1
Zinc mg/l 0.8 3
Oil and grease mg/l 2 5
Notes:
* It has been assumed that the site would be classified as ‘Red Sea’ and ‘Marine’ or C1
International Guidelines
The IFC Guidelines for Thermal Power (IFC, 2008) specifies the following requirements in relation to the
temperature increase due to discharge from cooling systems:
Site specific requirement to be established by the local environmental regulator; and
Elevated temperature areas due to discharge of once-through cooling water (e.g., 1°C above, 2°C above,
3°C above ambient water temperature) should be minimized by adjusting intake and outfall design through
the project specific EA depending on the sensitive aquatic ecosystems around the discharge point.
Wastewater Reuse Standards 4.3.5
It is specified by the SEC (2014) that treated effluent generated by the sanitary wastewater treatment plant on
site will be reused for irrigation purposes.
The IFC Performance Standards for wastewater reuse are dependent upon the intended reuse application and
vice-versa.
53 | 278
Table 4-7 Wastewater re-use standards (MAW, 1989)
Parameter Unit Unrestricted Irrigation Restricted Irrigation Biochemical Oxygen Demand Monthly average Weekly average
mg/l mg/l
10.00 15.00
20.00 30.00
Total suspended solids (TSS) Monthly average
mg/l
10.00
20.00
Aluminium (Al) mg/l 5.00 5.00 Arsenic (As) mg/l 0.10 0.10 Beryllium (Be) mg/l 0.10 0.10 Boron (B) mg/l 0.50 0.50 Cadmium (Cd) mg/l 0.01 0.01 Chromium (Cr) mg/l 0.01 0.01 Cobalt (Co) mg/l 0.05 0.05 Copper (Cu) mg/l 0.40 0.40 Cyanide mg/l 0.05 0.05 Fluoride (F) mg/l 2.00 2.00 Iron (Fe) mg/l 5.00 5.00 Lead (Pb) mg/l 0.10 0.10 Lithium (Li) for citrus fruits mg/l 2.50 2.50 Manganese (Mn) mg/l 0.20 0.20 Mercury (Hg) mg/l 0.001 0.001 Molybdenum (Mo) mg/l 0.01 0.01 Nitrate as N mg/l 10.00 10.00 Nickel (Ni) mg/l 0.02 0.02 Selenium (Se) mg/l 0.02 0.02 Vanadium (V) mg/l 0.01 0.01 Zinc (Zn) mg/l 4.00 4.00 Phenol mg/l 0.002 0.002 Oil and grease mg/l absent Absent pH 6.0-8.4 6.0-8.4 Faecal coliforms per 100 ml Average of last seven samples Maximum of any one sample
MPN MPN
2.20 23.00
100 200
Intestinal nematodes per litre 1.0 1.0 Turbidity NTU 1.0 1.0
Table 4-7 above shows the required effluent quality for restricted and unrestricted irrigation established by the
Ministry of Agriculture and Water (MAW, 1989). The updated PME Standards (2012) for Industrial and
Wastewater Discharges’ states that wastewater destined for regulated or unregulated reuse must adhere to the
criteria specified by the relevant designated agency, which is therefore, the MAW. It should however, be noted
that WSP have concerns with these prescribed standards as they may not reflect current best practices,
particularly in regard to bacteria and viruses. In addition, as these standards are intended for agricultural reuse
they may not necessarily be applicable to landscaping.
An alternative approach could be to reference the WHO Guidelines for the Safe Use of Wastewater, Excreta
and Greywater or recognised standards such as the US Environmental Protection Agency (US EPA) Guidelines
for Water Reuse (2004).
Project number: 37446130 Dated: 09/11/2014 54 | 278 Revised:
As described earlier, the MAW standards are specifically for agricultural irrigation and it may therefore be more
suitable to apply more recognised international standards, such as the US EPA guidelines for urban water
reuse outlined in Table 4-8.
Table 4-8 Guidelines for Urban Water Reuse (US EPA Guidelines)
Type of reuse Treatment Reclaimed
Water Quality
Reclaimed Water
Monitoring Setback
Distances Comments
Urban Reuse
All types of landscape irrigation, (e.g., golf courses, parks etc) – also vehicle washing, toilet flushing, use in fire protection systems and commercial air conditioners, and other uses with similar access or exposure to the water
Secondary
Filtration
Disinfection
pH = 6-9
< 10 mg/l BOD
< 2 NTU
No detectable faecal coli/100ml
1 mg/l Cl2 residual (minimum)
pH – weekly
BOD – weekly
Turbidity – continuous
Coliforms – daily
Cl2 residual - continuous
50 ft (15 m) to potable water supply wells
At controlled-access irrigation sites where design and operational measures significantly reduce the potential of public contact with reclaimed water, a lower level of treatment, e.g., secondary treatment and disinfection to achieve < 14 faecal coli/100 ml, may be appropriate.
Chemical (coagulant and/or polymer) addition prior to filtration may be necessary to meet water quality recommendations.
The reclaimed water should be clear and odourless.
A higher chlorine residual and/or a longer contact time may be necessary to assure that viruses and parasites are inactivated or destroyed.
A chlorine residual of 0.5 mg/l or greater in the distribution system is recommended to reduce odours, slime, and bacterial growth.
55 | 278
Solid and Hazardous Waste 4.3.6
KSA Requirements
The GER (2001), updated in 2012, provides a suite of Environmental Standards relating to waste which may be
relevant to the Project. These are as follows:
Waste Acceptance Criteria Standards for KSA;
Waste Classification Standard for KSA;
Waste RCC Standards for KSA;
National Waste Storage Standard for KSA;
National Waste Transport Standard for KSA; and
National Best Practicable Environmental Option for Waste Disposal Guidance Note for KSA.
In particular, the Waste RCC Standards for KSA makes specific reference to the control of solid waste
materials and in particular waste materials which are classified as hazardous in terms of their impacts on the
environment:
Article 4 (Purpose) identifies that PME is charged with protecting the natural environment and is
therefore obliged to issue controls over waste activities in KSA’.
The Waste Classification Standard for KSA provides the following:
“A national classification system that may be employed within KSA by all waste generators, transporters, facility
operators and the relevant competent agencies and other interested parties. The standard provides
classification, coding and defining of all waste types so they can be handled treated or disposed of
accordingly".
IFC Guidelines
Section 1.6 of the IFC General Environmental, Health, Safety (EHS) Guidelines is entitled Waste Management
and is applicable to all projects that generate, store or handle any quantity of waste; whilst Section 1.5 of the
IFC EHS Guidelines covers Hazardous Materials Management.
The waste management guidelines state that facilities that generate and store wastes should practice the
following:
Establish waste management priorities at the outset of activities based on an understanding of potential
requirements;
Identify Environmental, Health, and Safety (EHS) risks and impacts and consider waste generation and its
consequences;
Establish a waste management hierarchy that considers prevention, reduction, reuse, recovery, recycling,
removal and finally disposal of wastes;
Project number: 37446130 Dated: 09/11/2014 56 | 278 Revised:
Avoid or minimize the generation waste materials, as far as practicable;
Identify where waste generation cannot be avoided but can be minimized or where opportunities exist for,
recovering and reusing waste; and
Where waste is not able to be recovered or reused, identify means of treating, destroying, and disposing of
it in an environmentally sound manner.
This section also provides guidelines for the segregation of waste into hazardous and non-hazardous and how
to manage these waste streams. The project should seek to demonstrate compliance with these principles and
the guidelines set out within this document.
International Conventions
The Kingdom of Saudi Arabia signed and ratified ‘The Basel Convention on the Control of Trans-boundary
Movement of Hazardous Wastes and their Disposal’ in 1989 and confirmed it in 1990.
This convention aims to introduce a system for controlling the export, import and disposal of hazardous wastes,
and to reduce the volume of such exchanges so as to protect human health and the environment.
The convention defines a trans-boundary movement as ‘any movement of hazardous wastes or other wastes
from an area under the national jurisdiction of one State to or through an area under the national jurisdiction of
another State, or to or through an area not under the national jurisdiction of any State, provided at least two
States are involved in the movement’.
General obligations include the following:
It is prohibited to export or import hazardous wastes or other wastes to or from a non-party State;
No wastes may be exported if the State of import has not given its consent in writing to the specific import;
Information about proposed trans-boundary movements must be communicated to the States concerned,
by means of a notification form, so that they may evaluate the effects of the proposed movements on
human health and the environment;
Trans-boundary movements of wastes must only be authorised where there is no danger attaching to their
movement and disposal;
Wastes which are to be the subject of a trans-boundary movement must be packaged, labelled and
transported in conformity with international rules, and must be accompanied by a movement document
from the point at which a movement commences to the point of disposal; and
Any party may impose additional requirements that are consistent with the provisions of the Convention.
57 | 278
Requirements for Best Available Technologies 4.3.7
Article 6 of the General Environmental Regulations (GER, 2001) outlines the requirement for the party
implementing a new project or making major modifications to existing projects to utilise the best and most
suitable technologies available for the local environment and use materials that cause the least contamination
to the environment. In order to apply further clarity to this requirement reference shall be made to international
best practice, such as the approach of the US EPA in the Clean Air Act which requires the use of the Best
Available Technology which is economically achievable or the European approach of requiring best available
techniques not entailing excessive costs (BATNEEC).
Project number: 37446130 Dated: 09/11/2014 58 | 278 Revised:
5 Impact Assessment Methodology
Methodology for the Assessment of Impacts 5.1
The assessment of the potential impacts of both the construction and operational phases associated with the
project is based on a number of criteria, which are used to determine whether or not such effects are
‘significant’. These significant criteria comprise:
Local, national and international legislation, regulations and standards;
Relationship with national planning policy;
The sensitivity of the local environment;
The reversibility/irreversibility and duration of effects;
The inter-relationship, if any, between the effects – i.e. an assessment of cumulative impacts; and
The results of consultations with the environmental regulator.
The significance of effects reflects judgements as to the importance or sensitivity of the affected receptor(s) and
the nature, magnitude and duration of the predicted changes. For example, a large adverse impact on a feature
or site of low importance will be of less significance than the same impact on a feature or site of high
importance.
Sensitivity (Importance) of Receptors 5.2
Receptors are defined as the physical resource or user group that would be affected by a proposed
development. The baseline studies identify potential environmental receptors for each topic. Certain receptors
may be more sensitive to environmental effects than others, whilst the importance of a receptor may depend,
for example, on its frequency or extent of occurrence at a local, national, regional or international scale.
Description of Effect 5.3
Effects (otherwise referred to as ‘impacts’) are defined as the physical changes to the environment as attributed
to a project. For each topic, the likely environmental effects are identified and taken into consideration,
including their magnitude, comparing the effects with and without the project in place.
Effects are defined as either ‘adverse’ or ‘beneficial’ and, depending on the discipline, either ‘direct’ (effects
directly attributable to a project action/activity), or ‘indirect’ (effects that are not directly attributed to a project
action/activity).
59 | 278
Effects are also divided into those occurring during the construction phase of a project, and those that occur
during the operational phase. Again, dependent on the discipline, this SEA may refer to such effects as
‘temporary’ (generally during the construction phase), and ‘permanent’ (generally during the operational phase).
Significance of Effects 5.4
Prediction of impacts is essentially an objective exercise to determine what could potentially happen to the
environment as a consequence of the project and its associated activities. Impacts have been categorised
according to their various characteristics (e.g. are they detrimental or beneficial, direct or indirect, etc.). The
various types of impacts that arise, and the terms used in this assessment are shown and discussed in the
following tables and associated text.
Evaluation of Impacts 5.5
In evaluating the significance (i.e. importance) of impacts, the following factors were taken into consideration:
Impact severity: The severity of an impact is a function of a range of considerations including impact
magnitude, impact duration, impact extent, and legal and guideline compliance; and
Nature and sensitivity of the receiving environment: The characteristics of the receptor / resource will be
taken into consideration with respect to its vulnerability / sensitivity to an impact / change.
In evaluation the severity of the impacts, the following factors were taken into consideration:
Impact Magnitude: The magnitude of the change that is induced (i.e. the percentage of a resource that is
lost)
Impact Duration: The time period over which the impact is intended to last;
Impact Extent: The geographical extent of the induced change; and
Regulations, Standards and Guidelines: The status of the impact in relation to regulations (e.g. discharge
limits), standards (e.g. environmental quality criteria) and guidelines.
The tables below outlines the impact criteria used within the assessment of the project.
Project number: 37446130 Dated: 09/11/2014 60 | 278 Revised:
Table 5-1 Definition of Impact Type
Impact Type Definition
Direct Impact Impacts that result from a direct interaction between a planned project activity and the receiving environment (e.g. between occupation of a plot of land and the habitats which are lost).
Secondary Impact Impacts that follow on from the primary interactions between the project and its environment as a result of subsequent interactions within the environment. (e.g. loss of part of a habitat affects the viability of a species population over a wider area).
Indirect Impacts Impacts that result from other activities that are encouraged to happen as a consequence of the project (e.g. presence of project promotes service industries in the region).
Cumulative impact
Impacts that act together with other impacts to affect the same environmental resource or receptor.
Residual Impact Impacts that remain after mitigation measures have been designed into the intended activity.
Table 5-2 Impact Assessment Terminology
Term Definition
Impact magnitude
Magnitude Estimate the size of the impact (e.g. the size of the area damaged or impacted, the % of a resource that is lost or affected etc.)
Impact Nature
Negative impact An impact that is considered to represent an adverse change from the baseline, or introduces a new undesirable factor.
Positive impact An impact that is considered to represent an improvement on the baseline, or introduces a new desirable factor.
Neutral impact An impact that is considered to represent neither an improvement nor deterioration in baseline conditions.
Impact Duration
Temporary Impacts are predicted to be of a short duration and intermittent / occasional in nature.
Short-term Impacts that are predicted to last only for a limited period but will cease on completion of the activity, or as a result of mitigation / reinstatement measures and natural recovery.
Long-term Impacts that will continue over an extended period but cease when the project stops operating. These will include impacts that may be intermittent or repeated rather than continuous of they occur over an extended period of time.
Permanent Impacts that occur once on development of the project and cause a permanent change in
61 | 278
Term Definition
the affected receptor or resources that endures substantially beyond the project lifetime.
Impact Extent
Local Impacts are on a local scale (e.g. restricted to the vicinity of the facility etc).
Regional Impacts are on a national scale (effects well beyond the immediate vicinity of the project and affect an entire region).
Global Impacts are on a global scale (e.g. global warming, depletion of the ozone layer).
Table 5-3 Impact Severity Criteria
Impact Severity Definition
Slight Effects are very small and difficult to distinguish from the baseline / within natural fluctuations.
Low Affects a specific group of localised individuals within a population over a short time period (one generation or less), but does not affect other trophic levels or the population itself.
Medium Affects a portion of a population and may bring about a change in abundance and/ or distribution over one or more generations, but does not threaten the integrity of that population or any population dependant on it.
High Affects an entire population or species in sufficient magnitude to cause a decline in abundance and / or change in distribution beyond which natural recruitment (reproduction, immigration from unaffected areas) would not return that population or species, or any population or species dependent upon it, to its former level within several generations.
The likelihood (probability) of an event occurring has been ascribed using a qualitative scale of probability
shown in the table, below:
Table 5-4 Likelihood Categories
Likelihood Definition
Extremely unlikely
The event is very unlikely to occur under normal conditions but may occur in exceptional circumstances, e.g. emergency conditions.
Unlikely The event is unlikely but may occur under normal conditions.
Low likelihood The event is likely to occur during normal conditions.
Medium likelihood The event is very likely to occur during normal conditions.
High likelihood / inevitable The event will occur during normal conditions.
Project number: 37446130 Dated: 09/11/2014 62 | 278 Revised:
The significance of each impact is determined by comparing the impact severity against the sensitivity of the
receptor in the impact significance matrix provided in Table 5-5 below:
Table 5-5 Determining the Significance of Impacts
Sensitivity of Receptor
Low (L) Low-medium (LM) Medium (M) Medium High
(MH) High (H)
Impa
ct S
ever
ity Slight (1) Negligible Negligible Negligible Minor Minor
Low (2) Negligible Negligible Minor Minor Moderate
Medium (3) Negligible Minor Minor Moderate Major
High (4) Minor Moderate Moderate Major Major
Lastly, impacts are defined according to the following criteria:
Table 5-6 Definition of Impacts
Significance Definition
Positive Impact An Impact that is considered to represent an improvement on the baseline or introduces a new desirable factor.
Negligible Impact Magnitude of change comparable to natural variation.
Minor Impact Detectable but not significant.
Moderate Impact Significant; amenable to mitigation; should be mitigated where practicable.
Major Impact Significant; amenable to mitigation; must be mitigated.
Critical Impact Intolerable; not amenable to mitigation; alternatives must be identified – Project Stopper.
Cumulative Effects 5.6
Where possible the cumulative effects of the Project are considered within the ESIA. Two types of cumulative
effects have been considered:
Type 1 Cumulative Impact: the combined effects of different environmental factors from a single
development on a particular receptor, e.g. one residential property may experience a degradation in local
air quality and an increase in noise levels as a result of construction activities; and
Type 2 Cumulative Impact: the combined effects of all developments within the area, e.g. impacts on air
quality from one development may not be significant when considered alone, but may be significant in
combination with other proposed developments.
63 | 278
The ESIA has considered Type 1 cumulative effects largely in relation to construction; whereby there is the
potential for noise impacts together with dust emissions upon sensitive residential receptors to the north and
south of the Project Site.
Project number: 37446130 Dated: 09/11/2014 64 | 278 Revised:
6 Marine Environment
Introduction 6.1
This chapter considers the marine baseline conditions on site and identifies any potential soil and groundwater
impacts associated with the development of the Project.
The assessment considers marine issues associated with both the construction and operational phases of the
development and provides appropriate pollution control best practice measures.
Relevant Standards and Legislation 6.2
Relevant Environmental Legislation 6.2.1
National Standards
The Government of Saudi Arabia has taken several steps and decisions to control and protect the coastal
environment. The most salient of these are listed below.
Environment Protection Standards: these are contained in Document No.1401-01, (2006), PME.
National Oil Spill and Hazardous Substances Contingency Plan: This plan is set in Decision No. 157 dated
20/11/1411 H, (June 1991) by the Council of Ministers. This decision called for the formation of a
committee from five governmental bodies, to be involved in the implementation of this plan. Members of
this committee are:
1. Ministry of Defence and Aviation PME
2. Ministry of Interior Coastal Guards and Defence
3. Ministry of Petroleum and Minerals
4. Port Authority
5. Ministry of Municipalities and Rural Areas
Environmental Impact Assessment: A draft for the implementation of Environmental Protection Standards,
and Principles and Procedures for Environmental Impact Assessment (PME).
Wildlife Protection: Establishment of the National Commission for Wildlife Conservation and Development
(NCWCD) in May 1986. The main goal of this commission is to preserve, protect and develop Wildlife
within the Kingdom. Several protected areas were already established and supervised by NCWCD – Assir
National Park established in the Southern part of the Kingdom and supervised by the Ministry of
65 | 278
Agriculture. Wildlife protected Areas regulation. Issued under Ministerial Resolution No. 124 (26-10-1415
H), March 1995, administered by the NCWCD.
International Obligations: Saudi Arabia has also accepted its role in the international arena of
environmental protection and management by acceding to and ratifying a number of international
conventions and other agreements.
The KSA National Environmental Standard for Ambient Water Quality (2012) provides the recommended
thresholds for pollutants within marine water bodies. A sub-set of relevant limit values are shown in Table 6-1
below.
A number of additional requirements are also presented within these standards, the most relevant of which are:
Mixing zone requirements – this defines the area adjacent to an outfall where exceedances of ambient
standards are permitted. Mixing zones should not exceed 100m radius and should not impinge upon
sensitive habitats, such as coral reef. If the mixing zone requirements are determined to be unachievable
then a detailed study must be undertaken to demonstrate that the best achievable mixing zone dimensions
have been achieved using best available technology (BAT) and that environmental impacts have been
minimised.
Maintenance of background conditions – if background conditions are known to be better quality than the
ambient standards than those conditions must be maintained as a minimum requirement.
The KSA National Standards for Industrial Wastewater and Municipal Wastewater Discharges (2012) provide
limit values for discharge of pollutants into the Red Sea. A sub-set of relevant limit values are shown in Table
6-1 below.
Table 6-1 Examples of relevant ambient water quality and discharge limits from PME 2012
Parameter Unit Red Sea Industrial Criteria*
Red Sea Ambient Criteria*
Red Sea Discharge Criteria
Temperature °C 4 3 7
pH pH units 0.3 0.2 6-9.5
Salinity % 2 0
Turbidity NTU 2 2 50
TSS mg/l 5 5 15
BOD mg/l 15 10 25
Ammonia mg/l 0.2 0.1 1
Aluminium mg/l 1 0.2 10
Lead mg/l 0.2 0.05 0.1
Zinc mg/l 2 0.8 3
Oil and grease mg/l 3 2 5
Notes:
* Ambient standards for both Red Sea ‘Industrial’ and Red Sea ‘Marine’ are provided
Project number: 37446130 Dated: 09/11/2014 66 | 278 Revised:
International Guidelines
The IFC Guidelines for Thermal Power (IFC, 2008) specifies the following requirements in relation to the
temperature increase due to discharge from cooling systems:
Site specific requirement to be established by the local environmental regulator; and
Elevated temperature areas due to discharge of once-through cooling water (e.g., 1°C above, 2°C above,
3°C above ambient water temperature) should be minimized by adjusting intake and outfall design through
the project specific EA depending on the sensitive aquatic ecosystems around the discharge point.
The IFC General EHS Guidelines states that:
Temperature of wastewater prior to discharge does not result in an increase greater than 3°C of ambient
temperature at the edge of a scientifically established mixing zone which takes into account ambient water
quality, receiving water use and assimilative capacity among other considerations.
The IFC’s Performance Standard 6: Biodiversity Conservation and Sustainable Management of Living Natural
Resources (January 1st 2012) should be applied to projects:
1. located in modified, natural, and critical habitats;
2. that potentially impact on or are dependent on ecosystem services over which the client has direct
management control or significant influence; or
3. that include the production of living natural resources (e.g., agriculture, animal husbandry, fisheries,
forestry).
Performance Standard 6 requires the following:
“The risks and impacts identification process…should consider direct and indirect project-related impacts on
biodiversity and ecosystem services and identify any significant residual impacts. This process will consider
relevant threats to biodiversity and ecosystem services, especially focusing on habitat loss, degradation and
fragmentation, invasive alien species, overexploitation, hydrological changes, nutrient loading, and pollution.
As a matter of priority, the client should seek to avoid impacts on biodiversity and ecosystem services. When
avoidance of impacts is not possible, measures to minimize impacts and restore biodiversity and ecosystem
services should be implemented’.
Methodology 6.3
Baseline Survey 6.3.1
Desktop Study
A desktop study has been made of available information in order to characterise the environmental setting in
regards to marine water quality and ecology.
67 | 278
The desktop study has also included a review of the oceanographic conditions from the marine modelling /
recirculation report.
Marine Baseline Survey
The following section describes the Marine Ecological Resources and Water Quality Baseline Study
methodology. An experienced team undertook the baseline study using recognised survey methodologies. The
survey was designed to provide an assessment of the ecology and water quality present in order to provide a
baseline for the assessment of impacts and against which further continuous monitoring surveys can be
compared.
The survey sites were selected using an overlay of the project plan onto a satellite image. The shallow sub tidal
habitat is clearly visible and identifiable as fringing reef within the satellite image.
Six survey sites were selected near to the Project site. The location of each of these sites is illustrated in Figure
6-1 and Table 6-2 below.
Figure 6-1 Location of the marine survey baseline sites
Project number: 37446130 Dated: 09/11/2014 68 | 278 Revised:
Table 6-2 The survey scope at each of the marine survey baseline sites
Site Code Survey Type
Water Quality Ecology
C1
C2
T1
T2
T3
T4
Water samples have been collected from the sea surface in duplicate at 5 locations. The collection
methodology was standardised across the site.
Once the samples had been collected, they were stored and shipped under temperature controlled conditions
until the laboratory analysis had been completed.
Samples were analysed for the following important water quality parameters:
Phenolic compounds (USEPA 625 / 8270C); Total Kjedhad Nitrogen (APHA 4500 Norg B);
Chlorinated hydrocarbons (USEPA 8270C / 3510C /
3620);
Cyanide (free) (HACH 8027);
Microbiological Analysis (APHA 9222 B); Phosphate (CHEM 1006-DXB);
Residual Chlorine (HACH 8167); Ammonia (APHA 4500 NH3-N);
Total suspended solids (APHA 2540 D); pH value @ 20°C (APHA 4500 H+B);
Oil and grease (APHA 5520B); Turbidity (NTU) (Turbidity Meter);
Biochemical Oxygen Demand (APHA 5210B); Floating particles (Visual); and
Chemical Oxygen Demand (APHA 5220B); Metals (ICP CHEM 1006-DXB / AAS-MHS).
Dissolved Oxygen (APHA 4500 O2);
Each of the survey sites were assessed by a team of experienced SCUBA divers using a combination of
Roving Diver Survey, Photographic Survey and Fixed Position Photographs.
The divers swam freely throughout each survey site and recorded every observed fish and invertebrate species
that could be positively identified. At each dive site the approximate area covered and duration of the dive was
standardised. Any sea turtle species seen during the dives were also recorded.
69 | 278
Digital underwater photographs were taken at each survey site in order to document the species and habitats
and the condition of the benthic environment (coral reef) present. Representative photographs have been
selected and presented within the Marine Ecology Survey Datasheets in Appendix 3.
In addition to a simple photographic record, each image was analysed using the software Coral Point Count
(Kohler, 2006). Coral Point Count randomly distributes a number of points onto an underwater photograph and
then the operator visually identifies the features (e.g. coral, algae, rubble, etc.) lying under each point. The
percentage of points overlying each benthic category is calculated, and statistics can be compiled to estimate
the population of biota such as stony coral, sponges, macroalgae, etc. over a region of interest. A screen shot
of Coral Point Count is presented in Figure 7-3 below.
Figure 6-2 Screen Shot of the Coral Point Count Software in Operation
For the Coral Point Count analysis, wide angle photographs were taken at each of the six transects. Six
photographs were taken at each transect arranged perpendicular to the shoreline at the following points on the
reef structure:
D – At depth (between approximately 8 to 10 metres) between the transition from the outer reef slope to the
submarine terrace;
M – Mid-depth on the outer reef slope (approximately 3-5 metres); and
S – Shallow depth of the reef crest / reef edge (approximately 2 metres depth).
The design of the survey allows data to be presented for each transect individually or for each of the five
positions on the reef structure.
Project number: 37446130 Dated: 09/11/2014 70 | 278 Revised:
Each of the 25 top down photographs was input into Coral Point Count and the total area within the field of view
calculated using a marker as a scale guide. A border was then overlaid with an internal area of 10,000 cm2.
Where the photograph or orientation of the reef allowed, the border was a 100 x 100 cm square. However, in
certain images the shape of the border was adjusted to fit the reef but the internal area was kept standard
throughout.
Within each of these borders, Coral Point Count was used to plot 25 randomly distributed points marked A to Y
(see Figure 6-2). The operator then manually designated the feature lying under each point for which a code
had been pre-assigned. Benthic organisms present within each of these photographs were identified to the
family level.
Hard and soft coral and other sessile benthic organisms present within each top down photograph serve as an
indicator of the baseline condition of the reef at each of the sites. During follow up ecological monitoring studies
throughout the construction and operational phase of the Project it will be possible to revisit each of these
transects and obtain current photographs for side-by-side comparison with these “baseline” images and
quantitative data.
Assessment of Construction Phase Impacts 6.3.2
The assessment of construction phase impacts is based on establishing the directly impacted area of marine
habitat within the footprint of the construction works. The impact of indirect aspects, such as impacts upon
water quality has been assessed based on technical judgement and experience of similar projects in similar
environments.
Assessment of Operational Phase impacts 6.3.3
The primary operational phase impact relates to the operation of the cooling water intake and outfall.
Preliminary marine modelling has been undertaken by Artelia (2014) to establish the potential for recirculation
as well as the impact of the heated water upon the marine environment. The full recirculation modelling report
can be viewed Appendix J.
A TELEMAC-3D flow model was developed to simulate the transport of thermal effluent by tide-, wind- and
density-driven currents in areas surrounding the proposed Duba Power Plant site.
The recirculation study was carried out in two stages:
Stage 1 – Regional Hydrodynamic Model. A large scale 3-D hydrodynamic model of the Red Sea was used
to establish general regional circulation patterns and provide boundary conditions for the Local Thermal
Plume Model.
Stage 2 – Local Thermal Plume Model. A local scale 3-D model of the Duba Power Plant site and surround-
ing areas was used to evaluate thermal effluent transport (advection and diffusion) and recirculation, using
hydrodynamic boundary condition input supplied by the Regional Model.
71 | 278
A total of four scenarios for the operational phase were modelled. The impact analysis focuses only on Option
1A which is the base case option under the worst mixing conditions (south easterly winds). The base case is a
300m long Intake lagoon / enclosure with submerged pipes at the natural seabed level of -14mMSL. An outfall
channel guided by breakwaters. The results of the alternative scenarios can be viewed within Appendix J.
Existing Baseline Conditions 6.4
1.1.1 Location The Red Sea is a salt water inlet of the Indian Ocean between Africa and Asia. The connection to the ocean is
in the south through Bab el Mandel and the Gulf of Aden. In the north are the Sinai Peninsula, the Gulf of
Aqaba and the Gulf of Suez (leading to the Suez Canal). Occupying a part of the Great Rift Valley, the Red Sea
has a surface area of about 438,000 km2, is approximately 2,250km long, 355 km wide at its widest point and
on average 490 m deep (with a maximum depth of 2,210m in the central median trench). The Project site is
located on the western coast of Saudi Arabia approximately 110 km south of Jeddah and 600 km north-west of
the Saudi-Yemeni border.
The coastal area north of Duba to the Gulf of Aqaba, referred to as the Tiran Area, is recognized as being an
area of special conservation importance for the wide variety of different biotopes and reef types, forming unique
reef complexes with high zoogeographic significance1.
Approximately 1.5km north of the site is a fish farm which has two batteries of cages fixed about 500m from the
shoreline. The coral reef and the existing fish farms are both sensitive receptors with a high sensitivity to the
impacts associated with the construction and operation of the Project.
Bathymetry 6.4.1
The existing bathymetry at the project site is shown in Figure 6-3. The bathymetry is based on admiralty charts
and the results of a bathymetric survey. The reef flat can be observed as the shallow nearshore area with a
depth of 0 to -1 metres extending approximately 250 m from the shoreline. Following this the reef slopes down
to depths exceeding -15 m over a distance of generally 100 to 150 m.
1 DeVantier L. & Pilcher, N (2000) The Status of Coral Reefs in Saudi Arabia – 2000. National Commission for Wildlife Conservation and Development, Saudi Arabia
Project number: 37446130 Dated: 09/11/2014 72 | 278 Revised:
Figure 6-3 Existing bathymetry at the project site
Currents 6.4.2
Based on the available information current speeds are believed to be typically low (between 0.05 and 0.1 m/s)
in the coastal area offshore from the project site. The predominant current direction in the nearshore area is to
the south.
Water Quality 6.4.3
Water quality samples were collected in duplicate from five locations along the shoreline in front of the project
site. The results of water quality testing undertaken at the project site are shown below.
Physical Parameters
The results of pH indicate the presence of alkaline medium, where the results of the samples ranged between
8.15 to 8.52. It shows the presence of very low concentrations of each of the suspended solids (ranging from
0.17 to 0.8 Mg / l) and turbidity (ranging from 0.45 and 0.08 Nephelometric units) as evidence of the lack of high
turbidity suspended matter discharge sources in the area.
73 | 278
Chemical indicators
Analyzed chemical parameters show lack of organic pollution concentrations as well Biological Oxygen
Demand (BOD) and Chemical Oxygen Demand (COD) which are used as indicators of the presence of organic
pollution less than the sensitivity limit of methods that were used in the estimation of organic pollution.
This emphasis on the fact of the lack of pollution sources and the presence of low concentrations of ammonia -
nitrogen (0.01 – 0.25 Mg / l) and phosphate - phosphorus (0.03 – 0.09 Mg / l). In addition, low concentrations of
ammonia and phosphate will not help the phenomenon of eutrophication. Also, it was found that the
concentrations of cyanide phenol, oils, grease and chlorinated hydrocarbons in the collected samples less than
the sensitivity limit of applied methods.
These results emphasis on the absence of discharge sources could contain toxic compounds or oil pollution. It
turned out the presence of low concentrations of residual chlorine (0.07 and 0.01 Mg / l). Therefore, the results
are generally ensuring the lack of contamination sources of the collected samples.
Metals
The results of elements concentrations that have been estimated, that the concentrations of most of the
elements that have been estimated, especially hazardous elements less than the sensitivity limit of the device,
which means the area not exposed to any hazardous discharge contains harmful elements, especially of
industrial activities.
Bacteriological Indicators
The results of the probabilistic count of total coliform group - as evidence of sewage pollution - were less than
the sensitivity limit of the applied method. This means that all monitored sites is not contaminated with sewage
discharge or any discharge that contains a bacterial contamination.
Project number: 37446130 Dated: 09/11/2014 74 | 278 Revised:
Table 6-3 Water quality analysis results
Parameter Unit PME Limit*
Samples T1-A T1-B T3-A T3-B T4-A T4-B C1-A C1-B C2-A C2-B
pH pH Unit 0.2 8.47 8.4 8.52 8.5 8.5 8.45 8.15 8.3 8.4 8.4 TSS mg/l 5 0.55 0.35 0.3 0.17 0.31 0.23 0.18 0.22 0.8 0.19 Turbidity NTU 2 0.35 0.19 0.2 0.08 0.25 0.11 0.1 0.1 0.45 0.1 Total BOD5 mg/l 10 >2 >2 >2 >2 >2 >2 >2 >2 >2 >2 COD mg/l 25 >10 >10 >10 >10 >10 >10 >10 >10 >10 >10 Total Chlorin-ated Hydro-carbons
µg/l 0.01 >5 >5 >5 >5 >5 >5 >5 >5 >5 >5
TKN mg/l 3 0.63 0.66 0.7 0.71 0.69 0.71 0.62 0.61 0.63 0.64 O & G mg/l 2 >1 >1 >1 >1 >1 >1 >1 >1 >1 >1 Phenols µg/l 0.05 >0.05 >0.05 >0.05 >0.05 >0.05 >0.05 >0.05 >0.05 >0.05 >0.05 Ammonia as N mg/l - 0.12 0.09 0.03 0.06 0.11 0.12 0.12 0.25 0.01 0.06 Chlorine mg/l 0.1 0.01 0.01 0.01 0.01 0.01 0.03 0.02 0.02 0.06 0.07 Phosphate as P mg/l - 0.09 0.06 0.06 0.03 0.05 0.04 0.07 0.09 0.03 0.08
Total Cyanide mg/l - <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Aluminium (Al) mg/l 0.2 >0.003 >0.003 >0.003 >0.003 >0.003 >0.003 >0.003 >0.003 >0.003 >0.003 Arsenic (As) mg/l 0.05 >0.02 >0.02 >0.02 >0.02 >0.02 >0.02 >0.02 >0.02 >0.02 >0.02 Boron (B) mg/l - >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 Barium (Ba) mg/l 0.5 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 Cadmium (Cd) mg/l 0.005 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 Chromium (Cr) mg/l 0.05 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 Cobalt (Co) mg/l 0.05 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 Copper (Cu) mg/l 0.05 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 Iron (Fe) mg/l 0.5 0.011 0.013 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 >0.01 Mercury (Hg) mg/l 0.0004 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 >0.0001 Manganese (Mn) mg/l 0.01 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001 >0.001
Nickel (Ni) mg/l 0.05 >0.005 >0.005 >0.005 >0.005 >0.005 >0.005 >0.005 >0.005 >0.005 >0.005 Lead (Pb) mg/l 0.05 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 Zinc (Zn) mg/l 0.8 <0.005 0.011 <0.005 0.011 0.005 >0.005 0.005 0.006 >0.005 >0.005 Total Coliform MPN/100ml - Negative Negative Negative Negative Negative Negative Negative Negative Negative Negative * PME ambient standards for ‘marine’ waters
75 | 278
Marine Ecology 6.4.4
The Red Sea is characterized by its rich and diverse marine life, supported by coral reefs along its coastline.
Other marine habitats include sea grass beds, salt pans, mangroves and salt marshes.
The World Wildlife Fund (WWF) lists the Red Sea as a Global 200 ecoregion. WWF has identified 867
terrestrial, freshwater and marine ecoregions with the main purpose of this classification system to ensure that
the full range of ecosystems will be represented in regional and development strategies.
The Coral Reef Environment
The physical conditions characterising the Red Sea provide an ideal environment for coral growth. The warm
water and absence of fresh water runoff provide suitable conditions for coral reef formation adjacent to the
coastline. About 74 genera and 194 species of scleractinian coral have been identified and of these, 8.5% are
endemic representing the highest diversity in any section of the Indian Ocean.
Coral reefs can be classified into four broad types: fringing reefs; barrier reefs; atolls; and platform reefs
(sometimes referred to as shelf reefs).
The reef at the Project site is a fringing reef meaning it is a reef that lies immediately adjacent and parallel to
land. In the northern Red Sea the coast is fringed by an almost continuous band of coral reef, which physically
protects the shoreline. Further south the shelf becomes much broader and shallower and the fringing reefs
gradually disappear and are replaced with shallow, muddy shorelines.
Fringing coral reefs have a typical pattern of zonation from the shore to the reef edge as shown in Figure 6-4. In
more protected areas the zonation may begin with a sandy beach. However, more typically a rocky shore
separates land from sea. Mangroves may often be associated with this transitional area, however they are
absent from the Project site.
The next zone is referred to the inner reef flat which is a shallow area typically comprised of a mosaic of sand
and rock. This shallow area is visible next to the inner reef flat and is periodically exposed to air during low tide,
but pools in the reef provide areas of permanent water. Where the inner reef flat has been heavily eroded,
lagoons provide larger and deeper areas of permanent water. A large example of such as lagoon is present to
the south of the Project Site.
The outer reef flat is the section of reef flat closest to the sea and therefore can experience considerable wave
action during storms but it is exposed to air less frequently than the inner reef flat. For these reasons the
ecology of this area of the reef can be very different compared to the inner reef flats. The area is dominated by
hard substrate with sporadic coral heads, clams and algal turfs.
The reef crest or reef margin is the next zone. It is upon this area that waves break during storms making it a
challenging environment supporting specialised coral species. Beyond the reef crest is the reef slope or reef
face. The reef slope is permanently submerged and typically supports the greatest diversity of animal life.
Project number: 37446130 Dated: 09/11/2014 76 | 278 Revised:
Figure 6-4 Typical fringing coral reef zonation pattern (image: public domain)
Figure 6-5 shows the coastal habitats present in the area surrounding the project site. The mapping has been
developed via synthesis and analysis of the baseline survey findings, satellite imagery and bathymetric maps.
Five types of habitat or “reef zones” have been identified. These are lagoon, reef flat, reef crest and reef edge,
reef slope and seagrass.
77 | 278
Figure 6-5 Coastal habitat map
Project number: 37446130 Dated: 09/11/2014 78 | 278 Revised:
Seagrass
Seagrass can be found on the reef flats or in lagoons. The lagoons provide a sheltered area with soft
sediments and a permanent source of water during low tide. Eleven species of seagrass have been recorded
from the Red Sea (Barratt et al. 1987). Seagrasses are considered to be a valuable habitat for the following key
reasons:
They are primary producers that contribute to the large quantities of fixed carbons, the basis of all food
chains to coastal ecosystems;
They play an important role in stabilising bottom sediment, supply shelter and refuge for both adult and
juvenile animals; are essential food for vulnerable and critically endangered species known to occur in
KSA, such as dugongs (vulnerable), hawksbill turtles (critically endangered) green turtles (critically
endangered), and loggerhead turtles (critically endangered); and
They play a valuable role in the life cycle of a number of commercially important fish species.
Fish and Invertebrates
More than 1,100 species of fish species have been recorded in the Red Sea, of which 10% are endemic to this
ecosystem.
Marine Mammals and Reptiles
In the Red Sea, 10 species of cetaceans have been recorded (Frazier, 1987) and these include dugong and
several other species such as dolphins, whales and porpoises. However, very little information is available on
the biology and ecology of Red Sea cetaceans. Within Saudi Arabian territorial waters, five sites have been
identified as supporting moderate populations of dugong which is the only herbivorous marine mammal. These
are: 1) TiranIsland 2) Wajh bank 3) Sharm al Khaur 4) Al-Lith and 5) Gizan. The largest Cetacean population is
centered on the Wajh Bank area. No marine mammals were seen during the marine baseline survey.
Of the five species of marine turtle that have been recorded in Saudi Arabia waters, two species dominate the
turtle population in the coastal area. These are the Green turtle Chelonia mydas and the Hawksbill turtle
Eretmochelys imbricate. Nesting areas have been mapped by PME & IUCN. Islands scattered off shore along
the whole Red Sea coast provide suitable nesting sites for sea turtles, and only a few similar sites are found on
the mainland.
Hawksbill turtles nest at scattered locations along the beaches, usually around March-April especially in the
region between Cape Baridi and Abu Madd (north of Yanbu). Green turtles nest on Cape Baridi beaches (Vine,
1987). Hawksbill turtles were sighted during the marine baseline survey at two locations.
Baseline Survey Results – Marine Ecology
Figure 6-6 to Figure 6-9 below show a summary of the quantitative data obtained via the photographic Coral
Point Count analysis. The data is presented here in terms of the percentage cover of the major groups present.
The full Coral Point Count summary data is provided in Table 6-4 and Table 6-5 for reference and comparison
with future environmental monitoring studies.
79 | 278
Figure 6-6 shows the overall composition of the reef environment which is an average of the 36 photographs
analysed across the study site. The average hard coral cover across all sites and depths was approximately
40% and ranged from 31% at site T4 to 49% at site T1. Soft coral cover was approximately 3% across all study
sites. Other groups present included macroalgae (0.6%), coraline algae (1.6%), dead coral with algae (1.05%),
other live (0.66%) and dead coral with algae (1.05%).
The non-living component of the reef, including dead coral, sand, rubble, etc. (‘sand, pavement, rubble’) totals
approximately 53%.
The summary results are also presented for each transect surveyed (Figure 6-8) and for each position on the
reef (Figure 6-7). This provides cross sections of the reef perpendicular to the shoreline at 11 locations as well
as a cross section of the reef parallel to the shoreline at the shallow, mid and deep depths. The most notable
aspect is the decrease in hard coral cover and the appearance of soft corals in deeper sections of the reef.
Table 6-4 Percentage substrate cover
% of total substrate cover
Substrate Type All Shallow Mid depth Deep C1 T1 T2 T3 T4 C2
Hard Coral 39.68 52.22 35.17 29.35 40.74 48.84 39.85 36.84 30.72 43.08
Soft Coral 2.63 0.00 0.00 9.95 2.78 0.78 9.02 0.00 0.00 3.08
Macroalgae 0.66 0.00 1.38 0.50 3.70 0.00 0.00 1.05 0.00 0.00
Coralline Algae 1.31 3.33 0.34 0.00 0.00 2.33 1.50 0.00 0.00 3.85
Sand, pavement, rubble 53.22 40.00 61.38 59.20 51.85 48.06 48.12 54.74 65.66 47.69
Other live 0.66 0.74 1.03 0.00 0.00 0.00 0.00 3.16 0.60 0.77
Dead coral with algae 1.05 2.22 0.69 0.00 0.00 0.00 1.50 0.00 3.01 0.77
Unknowns 0.79 1.48 0.00 1.00 0.93 0.00 0.00 4.21 0.00 0.77 Table 6-5 Hard coral types as a percentage of total substrate cover
% of total substrate cover
Hard Coral Types All Shallow Mid depth Deep C1 T1 T2 T3 T4 C2
Massive / Encrusting 19.58 22.22 20.34 14.93 16.67 27.91 13.53 15.79 15.66 27.69
Branching / Pillar 15.24 21.85 12.41 10.45 17.59 12.40 17.29 20.00 13.86 12.31
Leaf / Plate / Sheet 0.13 0.00 0.34 0.00 0.00 0.00 0.00 0.00 0.00 0.77
Meandroid / Brain 0.13 0.00 0.00 0.50 0.00 0.00 0.75 0.00 0.00 0.00
Flowering / Fleshy 0.39 0.00 0.69 0.50 0.00 0.78 0.00 0.00 1.20 0.00
Hydrozoan / Fire Corals 4.20 8.15 1.38 2.99 6.48 7.75 8.27 1.05 0.00 2.31
Project number: 37446130 Dated: 09/11/2014 80 | 278 Revised:
Figure 6-6 Substrate cover at all sites
Figure 6-7 Percentage cover at all sites and at all depths
81 | 278
Figure 6-8 Percentage substrate cover at each survey site
Figure 6-9 Hard coral types as a percentage of total substrate cover at all sites and all depths
Project number: 37446130 Dated: 09/11/2014 82 | 278 Revised:
The inner reef flat
Typical reef crest environment with algal turf
Seagrass
The reef edge (shallow)
The reef edge (mid depth)
The reef slope (deep)
Figure 6-10 Representative image of marine habitats
83 | 278
Assessment of Impacts 6.5
Sensitive Receptors 6.5.1
The key receptor present has been identified as being the benthic marine ecology – the fringing coral reef and
seagrass. Coral reef and seagrass are sensitive habitats of ecological importance and their protection should
be a priority. Based on an assessment of abundance, state, adaptability and value, the benthic reef habitat
within the study area has been assigned an overall level of sensitivity of Medium-High. A High score was not
assigned only because this is a well-represented habitat within the wider area. However, it should be noted that
coral reefs are under threat at a local and global level from climate change and other human induced
pressures. A summary of the assessment of sensitivity is provided in Table 6-6 below.
Table 6-6 Marine ecological receptor criteria
While a coral reef is comprised of a combination of a large number of or organisms, it is the hard corals that are
the principle “reef building” component around which all the other life flourishes. They are also the group that is
typically most vulnerable to the impacts associated with physical disturbance and water quality. The following
assessment will therefore focus on potential effects upon the reef environment with a particular emphasis upon
hard corals.
Construction Phase Impacts 6.5.2
The construction of the seawater intake and outfall structures will have resulted in impacts upon the coastal
water quality and the associated coral reef habitat. The following impacts will have occurred during the
construction phase:
Abundance State Adaptability Value
Resilient Common / abundant same everywhere
Good and robust - already experienced similar change and
fully embraced
Readily able to adapt and absorb with no
difficulty
Valued but not as unique Low
Moderately resilient
Reasonably common in surrounding area
Experienced similar change and laregly adapted / absorbed
without much difficulty
Able to absorb / adapt with only small
effort
Valued by few individuals in its
present stateLow Medium
Partially Resiliant
Range / abundance restricted to a few
locations in surrounding area
Experiencing some pressure and
responding slowly with some difficulty
May adapt / absorb change but with some difficulty
Valued locally in its present state Medium
Sensitive Rare with some unique elements
Under pressure and showing signs of
stress
Fragile to change will not adapt readily
High valued locally and regionally Medium High
Highly Vulnerable Very rare and unique
Under significant pressure and likely to
fail
Intolerable to further pressure - will
change irreparably
Significant intrinsic and extrinsic value, local, nationally and
internationally
High
Sensitivity of Receptor
Overal Level of Sensitivity
Definition
Project number: 37446130 Dated: 09/11/2014 84 | 278 Revised:
Direct loss of fringing reef habitat within the footprint of the intake structure (estimated to be 30,000 m2 of
coral reef); and
Direct loss of fringing reef habitat within the footprint of the outfall structure (estimated to be 35,000 m2 of
coral reef).
In addition to the direct impacts, impacts upon the surrounding environment are also expected. These include:
Smothering of adjacent reef habitat due to silt being generated by the construction activities;
Adverse effect on fish communities due to noise and vibration from the marine engineering activities;
Accidental spillage or release of lubricating oils or fuels during marine engineering activities;
Land-water interface impacts relating to the shoreline habitats;
Disposal sites for the deposition of rubble and dredge material;
Disturbance and/or water quality impacts on important marine and coastal species; and
Cumulative impacts associated with the construction of both intake and outfall simultaneously.
The potential construction impacts are considered to be of major negative significance in the absence of
appropriate mitigation measures. Approximately 65,000 m2 of fringing coral reef habitat will be lost within the
footprint of the works with impacts also likely to the surrounding area. Mitigation measures for habitat loss are
considered in Section 6.6.
Operational Phase Impacts 6.5.3
Entrainment and Impingement
The cooling water intake system of the plant has the potential to draw in large quantities of pelagic organisms.
Small juvenile fish, fish eggs and larvae can be drawn into the cooling water system (entrainment) and adult
fish and jellyfish can be trapped and killed by the screens protecting the intake (impingement). The pelagic
species affected are of both commercial and ecological importance including juvenile commercial fish species
as well as coral larvae. The actual severity of this impact is difficult to estimate. However, it is adequate to state
that since the project is located in an ecologically sensitive area, the impact will be adverse and therefore,
where possible, practical steps should be taken minimise it (see mitigation).
Thermal Discharges
Thermal discharges into marine waters have the potential to adversely impact ecological and fisheries
resources of receiving waters. During operation of the facility, the potential impacts of this discharge are
principally related to the ecological effects in a zone of increased temperature within and surrounding the
opening of the outfall canal. Marine organisms inhabiting tropical waters are considered to be potentially
sensitive to impacts from elevated temperatures since they live close to their upper thermal tolerance limits
(FAO 1984).
85 | 278
The thermal discharges have been modelled by Artelia (2014). The modelling assumed the following
parameters for the intake and outfall:
Outfall velocities
Depth average ranging from 0.25–0.35m/s, depending on tidal stage
Intake velocities
1.2 m/s at pipe header
Temperature of effluent at outfall
5°C above temperature of intake (ambient)
Salinity of effluent at outfall
Identical to salinity of ambient seawater at intake (i.e. negligible brine content)
15-day averaged temperature plots were presented for both pre and post development for the Surface and
Intake (-14 m) layer. The results of this preliminary modelling are presented in full within Appendix J. Figure
6-11 below shows the temperature difference at the surface and as a longitudinal cross section due to the
operation of the outfall. Discharges of warmer water tend to be buoyant spread out at the surface at illustrated
in the longitudinal plot where the plume is largely restricted to depths less than 5 m.
The PME mixing zone can be classified as a T of 4°C outside of a 60m area for zones classified and
Industrial. As this area is zoned for power generation it could be argued that the industrial classification applies.
However, given the area is currently Greenfield it could also be argued that the ‘marine’ classification applies in
which case the mixing zone would be a T of 3°C outside of a 60m area. The modelling currently
demonstrates that the plume achieves the industrial mixing zone criteria (as shown in Figure 6-11) but would
not achieve the marine criteria.
The discharge of cooling water in this location will have impacts upon the existing coral reef. The potential
impacts on the marine biota may be more pronounced in the benthic environment than the water column. This
is due to the ability of the fish, reptiles and mammals that inhabit the water column (pelagic organisms) to avoid
or escape from areas of unfavourable water quality while most of the benthic organisms (e.g., seagrass, clams,
coral, etc.) have limited or no ability to avoid such conditions. The key project “impact zone” is therefore the
shallow reef flat and the area of shelving seafloor at the edge of the reef.
Most organisms can adapt to minor deviations from optimal temperature (or other water quality factors), and
might even tolerate extreme situations temporarily, but not a continuous exposure to unfavourable conditions.
Project number: 37446130 Dated: 09/11/2014 86 | 278 Revised:
Figure 6-11 Temperature difference at the surface (left) and a longitudinal cross section (right)
The constant discharge of cooling water with higher relative temperature levels can cause a lasting change in
species composition and abundance at the discharge site (Lattemann and Hopner, 2008).
Corals are widely documented as sensitive to seawater temperature changes. Prolonged exposure to seawater
temperatures of only 1 to 3°C higher than mean averages at the warmest time of year has been linked to
bleaching events (Hoegh-Guldberg,1999). Coral bleaching results from the loss of symbiotic algae, known as
zooxanthellae, from coral tissues during times of stress. The biology of reef-building corals breaks down when
summer temperatures exceed the corals’ physiological thresholds for an extended period of time (weeks to
months).
Sea temperature increases of 1-2ºC above the long term average maximum are all that are required to trigger
mass bleaching (P.A. & Schuttenberg, 2006) and maximum summer sea temperatures that are 2-3 ºC above
normal values can kill corals.
Taking a conservative approach we can therefore consider the limit of the 1-2°C contour as the area within
which the coral reefs will be affected (i.e. reduced growth rates, decreased reproductive capacity, and
increased susceptibility to diseases) and the limit of the >2°C contour where coral mortality will be likely to
occur.
PME ‘Industrial’ Mixing Zone Area (60m)
87 | 278
Figure 6-12 shows the temperature contours from the model overlaid onto the marine habitat map. This has
been used to extrapolate the approximate areas of habitat that will be affected by the operation of the outfall.
The total area of affected habitat is estimated to be approximately 124,000 m2 (an area of approximately 25
football fields). The habitat will be adversely affected in 100,000 m2 with coral mortality expected to occur in
the remaining 24,000 m2.
Figure 6-12 Surface temperature contours overlaid onto the marine habitat map
Table 6-7 Approximate surface area (in m2) of affected habitats
Thermal impact zone (Degrees C)
Metres Squared (m2) Total plume surface area Reef flat* Reef crest
and reef edge Reef slope Seagrass Total
Habitat >4 3,597 0 2,678 919 0 3,597
3 to 4 5,792 0 1,177 4,615 0 5,792
2 to 3 15,449 5,319 1,179 8,951 0 15,449
1 to 2 111,537 45,850 3,873 38,127 11,203 99,053
Total 136,375 51,169 8,907 52,612 11,203 123,891 * Excluding area already impacted by construction of the outfall
Project number: 37446130 Dated: 09/11/2014 88 | 278 Revised:
Given the pristine nature of the existing coral reef in this area and the international value of this type of habitat
the sensitivity of this receptor is considered to be high. The impact severity is considered to be medium due to it
being localised but long-term. The significance of the impact upon the marine habitat in this area is therefore
considered to be major adverse prior to the application of any mitigation.
Other Water Quality Impacts
Chlorine will be used to treat the incoming seawater in order to minimise the negative effects of bio-fouling
within the facility. Chlorine is a broad effect anti-fouling agent and will exhibit broad effects on the environment
depending on its concentration.
The residual chlorine will need to be discharged at less than 0.2 mg/L. Assuming that this limit value is
achievable, the impact will be of negligible significance. It is assumed that all other parameters of the discharge
will meet with the PME discharge standards.
Other water quality impacts may occur as a result of wastewater and storm-water treatment and disposal.
Collection and reuse of storm-water and treated wastewater should be maximised. Sea disposal of any
effluents must only occur if they meet with the PME standards for disposal to the marine environment prior to
dilution with cooling water. Provided this requirement is satisfied, the impact is predicted to be of negligible
significance.
Impacts upon the Existing Fish Farm
Based on the results of the preliminary modelling study, the discharged cooling water from the facility is
generally expected to move in a southerly direction due to the prevailing currents in the area. The fish farm
cages are located over 3 km north of the northern extent of the thermal plume. The impact upon the fish farm is
therefore expected to be negligible and does not warrant further consideration or mitigation.
Mitigation Measures, Residual/Cumulative Effects 6.6
Construction Phase Mitigation Measures 6.6.1
The detailed design must consider opportunities to minimise the footprint of the intake and outfall structures to
avoid direct loss of habitat.
Measures for mitigating, managing and monitoring construction phase impacts are outlined in the framework
CEMP.
Regular marine monitoring should take place during the construction phase to assess the effectiveness of the
environmental management being implemented. This should include water quality monitoring, sedimentation
monitoring and an assessment of the ‘health’ of the coral reef in proximity to the construction areas and at
suitable control sites.
89 | 278
Construction Phase Residual Effects 6.6.2
The main impacts associated with the construction phase will be direct loss of coral reef habitat within the
footprint of the works and damage to surrounding reef due to water quality impacts. While the latter can be
minimised through effective management, impacts upon this sensitive habitat will be unavoidable. The residual
impact will be related to the effectiveness of the habitat loss compensation strategy (see below for further
details).
Construction Phase Cumulative Effects 6.6.3
Given the remoteness of the area and absence of other construction projects there are not expected to be
significant cumulative impacts associated with the project.
Operational Phase Mitigation Measures 6.6.4
Entrainment and Impingement
Typical measures to reduce entrainment and impingement include locating the intake in an ecologically
insensitive area, away from the littoral zone and in deeper waters. The intake for the plant is proposed to be
located at a depth of -14 metres and 300 metres away from the shoreline which will reduce the impact. Other
design measures should also be considered, such as lowering the intake velocity and the use of other low
impact intake technologies.
Thermal Discharges
The options for reducing the impact of cooling water upon the marine environment are limited. However, the
final design of the plant should be able to demonstrate that all possible measures for reducing the extent of the
area of coral habitat affected by the discharge have been considered.
Habitat Loss
The are of damaged or lost habitat associated with the construction and operation of the project is predicted to
be close to 20 hectares.
Based upon the final intake and outfall design, construction footprints and modelling results the area of affected
habitats should be fully quantified and a Habitat Compensation Strategy must be developed and implemented
by the contractor. This strategy should effectively compensate for the habitat that is lost or damaged as a
consequence of the construction and operation of the facility. The main measures available for such schemes
typically involve the acquisition of land or marine areas as reserves and/or habitat construction. These schemes
must always involve adequate management, monitoring and reporting to ensure and demonstrate their long-
term effectiveness.
Operational Environmental Management
It is recommended that an OEMP is developed by the operating company, which will include mitigation
measures to reduce the significance of impacts upon the marine environment. The key mitigation measures
during operations to prevent acute or chronic impacts on the marine environment are as follows:
Project number: 37446130 Dated: 09/11/2014 90 | 278 Revised:
Provision of on-line process monitoring for the cooling water system and associated auxiliary processes,
particularly those requiring application of chlorine or chemical additives;
Chemical monitoring of individual effluent lines prior to mixing with the cooling water and a continuous
flow/quality monitor on the final effluent channel;
The provision of balancing/evaporation ponds to receive storm water drainage or flows associated with
abnormal or emergency conditions;
Prevent planned or accidental discharge of chlorinated product water with effluent due to potential impact
on the benthic communities (i.e. coral reef) – discharge to an evaporation pond if not required;
Chemical stores to be within an enclosed structure on hard standing and with an impermeable bund
equivalent to 110% of the largest tank;
All oil storage tanks to have an impermeable bund capable of holding 110% of the largest tank;
Slow, phased, start-up of facility and discharge of effluent to facilitate a gradual acclimation of local biota
(i.e. minimise ‘shock effect’); and
Ensure that site staff are aware of the environmental management system and that there is an
Environmental Co-ordinator for the site to record training, incidents etc.
Continuous Ecological Monitoring
The key impact during the operational phase will be the potential for degradation or loss of the fringing coral
reef habitat that exists within the zone of impact of the outfall. In order to establish the actual impacts, an
operational marine ecology monitoring programme shall be implemented. If any impacts are identified these
shall be quantified in terms of their scale and severity and this information will be used to determine the
requirements for additional mitigation or compensation measures.
Operational Phase Residual Effects 6.6.5
The residual impact significance associated with entrainment and impingement are dependent on the final
design of the plant and the design measures taken to mitigate for this issue.
The residual thermal impact of the project is considered to be of minor negative significance. This is assuming
that the necessary Habitat Compensation Strategy is design and implemented.
The residual impacts associated with the residual chlorine discharges are considered to be on negligible
significance.
Operational Phase Cumulative Effects 6.6.6
Given the remote nature of the site and absence of additional facilities in the area there are not expected to be
significant cumulative impacts associated with the operation of the facility.
91 | 278
Summary and Conclusions 6.7
This section has presented an overview of the baseline environmental conditions at the site in regards to the
hydrology, water quality and marine ecology.
Six transects were surveyed including 2 control sites and 4 impact zone sites. The survey has been designed in
order to document the “baseline” condition of the marine habitat present and to provide a benchmark against
which future monitoring studies can be compared.
The results of the water quality testing indicate that the water quality at the site is of a high quality with no
indicators of industrial or municipal pollution present.
At all the survey sites a high percentage of live hard coral cover (average of 40%) was present in the reef
margin and the upper outer reef slope. Seagrass was also present along two of the transects. The presence of
fish, invertebrates and other marine life was also documented during the marine baseline survey.
The coastal area north of Duba to the Gulf of Aqaba, referred to as the Tiran Area, is recognized as being an
area of special conservation importance for the wide variety of different biotopes and reef types, forming unique
reef complexes with high zoogeographic significance .
Top down photographs and subsequent analysis using Coral Point Count software were incorporated into the
survey design in order to provide a robust and quantitative means of establishing any negative changes to the
reef environment as a consequence of the construction or operation of the facility.
The construction phase will directly impact upon 65,000 m2 of fringing reef habitat. Secondary effects
associated with water quality impacts (suspended sediments) are also expected on the surrounding reef.
The main operational impact identified is associated with the discharge of heated cooling water from the facility
during normal plant operation. The marine modelling results have been used to determine the extent of the
area of reef likely to be affected. Taking a conservative approach we have identified the 1-2°C contour as the
area within which the coral reefs will be adversely affected and the >2°C contour where mortality will occur.
The 1-2°C contour affects an area of approximately 100,000 m2. Within this area we can expect to see the
corals displaying signs of physical stress, such as reduced growth rates and fecundity as a result of the
increased temperature and process chemicals. The >2°C contour impinges upon approximately 24,000 m2 of
marine habitat. Within this area coral mortality will be likely to occur.
Various mitigation and management measures have been recommended. However, the construction and
operation of a power plant in this location will inevitably have impacts upon the adjacent sensitive coral reef
habitat. It is recommended that a detailed study is undertaken to fully quantify the ecological and biodiversity
impacts of the project when suitable design information is available and identify a practical compensation
strategy for habitat losses.
Project number: 37446130 Dated: 09/11/2014 92 | 278 Revised:
Table 6-8 Impact and mitigation summary table for Marine Environment
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Loss of habitat within the construction footprint High sensitivity Major Adverse
Consideration given to minimizing the footprint area of marine structures (intake and outfall) when preparing the final design for the plant; and
Habitat loss compensation strategy to be developed.
Moderate Adverse
Indirect impacts associated with water quality (sedimentation) High sensitivity Major Adverse
Application of stringent environment management measures during construction (refer to the Framework CEMP); and
Regular marine monitoring.
Moderate Adverse
Operational Phase
Entrainment and impingement at the intake
Moderate to high sensitivity
Moderate adverse
Incorporation of design measures to minimize Entrainment and impingement at the intake Minor Adverse
Cooling water discharge (thermal impacts) High sensitivty Major Adverse
Final design to be optimized with regards to minimizing the plume extent and interaction with sensitive marine habitats (i.e. the fringing reef);
Habitat loss compensation strategy to be developed.
Moderate Adverse
Other water quality impacts High sensitivty Negligible Adherence to PME standards and regular monitoring of cooling
water and other wastewater streams (as specified in the Framework OEMP).
Negligible
Impacts upon existing fish farm High sensitivity Negligible Preliminary marine modelling results demonstrate that there will
not be impacts upon the fish farm as a consequence of the operation of the plant.
Negligible
93 | 278
7 Air Quality
Introduction 7.1WSP carried out an assessment of the potential air quality impacts arising from the construction and operation
of the Project. The impact of the emissions from the turbines has been considered under a both typical
operating conditions and worst case conditions.
The Project site is located in the Tabouk Province, approximately 55 km to the north of the City Duba, on the
Red Sea coast in the Kingdom of Saudi Arabia. The Project will be based F-Class and/or E-Class gas turbine
(GT) technology with a total plant net output of 485-550 MWe at reference site conditions (RSC). The plant will
be designed for operation on natural gas and condensate gas fuel as the primary fuel and Arabian Super Light
(ASL) fuel oil as back-up fuel. The Project will comprise two power blocks, which will either be a combination of
one F-Class GT and two E-Class GTs (Option A) or two sets of two E-Class GTs (Option A).
The GTs will operate initially in the simple cycle mode until construction of the combined cycle portion is
completed. Once the combined cycle component of the power plant is operational, the GTs will remain capable
of operating in simple cycle mode in the event there are problems in the combined cycle component.
Sulphur dioxide (SO2), oxides of nitrogen (NOx) and fine particle (PM10) emissions from the proposed power
plant (operating at two sets of ambient conditions representative of summer or typical and winter or worse case)
have been assessed using dispersion modelling. The modelling of the power plant has been undertaken
assuming the plant operating in both Simple and Combined Cycle modes.
The following key issues are considered in this chapter:
Ambient air quality conditions at the existing the site and at sensitive receptor locations;
Emission characteristics and concentrations for key pollutants from the proposed turbines;
Dispersion modelling of the estimated emissions to establish the contribution from the Project. The data
used in the dispersion modelling (e.g. exhaust flows conditions and pollutant emission rates) have been
based emissions data held by WSP for F-Class and E-Class operating at other SEC sites and data sheets
available from the manufacturers of the these classes of turbine; and
Consideration of the discharge configurations for the proposed turbines, including number and class of GT,
stack heights and internal diameter to ensure optimal efflux velocities and adequate dispersion of exhaust
emissions.
Project number: 37446130 Dated: 09/11/2014 94 | 278 Revised:
Relevant Air Quality Emission Standards 7.2
International Standards 7.2.1
International guidelines for air emissions and ambient air quality are provided by the International Finance
Corporation (IFC) of the World Bank Group (WB) for use in environmental assessments (IFC, 2007). However,
it is stipulated in the IFC document that these guidelines are only for use in the absence of local (national)
ambient air quality standards; therefore, they have been included in their entirety, but have only been used
where national standards do not exist. The IFC ambient air quality guidelines for SO2, nitrogen dioxide (NO2)
and PM10 are shown in Table 7-1. Guidelines have also been developed by the IFC for thermal power plants
(IFC, 2008). The IFC guidelines include emissions limits for NOx, SO2, and PM10, which are shown in Table
7-2.
National Standards 7.2.2National air quality standards for Saudi Arabia are provided by PME in the General Environmental Regulations
(GER, 2006 and 2012) and emissions limits have also been produced. The superseded PME emissions
standards were based in mass of pollutant discharged per thermal input to the plant, rather than the emissions
concentration format of the 2012 emission limits and the IFC guidelines. The PME air quality standards (AQSs)
and emission limits for the pollutants considered are also shown in Table 7-1 and Table 7-2.
Table 7-1 Air Quality Standards for SO2, NO2 and PM10
Pollutant Averaging period PME (µg/m3) IFC EHS Guidelines (µg/m3) NO2 1-hour
Annual 660(a) 100
200 40
SO2 10-min 1-hour
24-hour
Annual
--(b) 730(c) 365(d)
80
500 --
125 (interim target 1) 50 (interim target 2)
20 --
Inhalable suspended particles (PME) or PM10 (IFC)
24-hour
Annual
340(e)
80
150 (interim target 1) 100 (interim target 2) 75 (interim target 3
50 70 (interim target 1) 50 (interim target 2) 30 (interim target 3)
20 (a) Not to be exceeded more than twice per month (30 day period). (b) No 10-min standard has been set by PME. (c) Not to be exceeded more than twice during any 12 month period. (d) Not to be exceeded more than once during any 12 month period. (e) Not to be exceeded more than 24 times (equivalent to the 90th percentile) during any 12 month period.
95 | 278
Table 7-2 Emission Standards for SO2, NO2 and PM10
Pollutant PME (2014) IFC EHS Guidelines (Combustion Turbines >50MWth)
Non-degraded Air shed/Degraded Air shed
NOx 500 mg/Nm3(a)(b) (NDA)
350 mg/Nm3 (NDA) 74 ppm (152 mg/Nm3)(b) - Fuels other than Natural Gas
SO2 600 mg/Nm3 (NDA)
400 mg/Nm3 (DA)
Use of 1% Sulphur content or less in fuel (NDA)
Use of 0.5% Sulphur content or less in fuel (DA)
PM10 150 mg/Nm3 (NDA)
100 mg/Nm3 (DA)
50 mg/Nm3 (NDA)
30 mg/Nm3 (DA)
(a) It is assumed that mg/Nm3 is the correct unit, as stated in Article II(1)(b) of the KSA National Environmental Standards – Con-trol of Emissions to Air from Stationary Sources (PME 2014)
(b) Nm3 – Normalised cubic metre, reference conditions 273K, 101.3 kPa, dry gas, 15% oxygen.
Turbine exhaust characteristics and pollutant emissions data for the proposed E-Class turbines have been
based on data obtained from Siemens for SGT6 2000E turbines for simple cycle and combined cycle operation
using gas and ASL as fuel and data obtained from Siemens data sheets. Emissions data for the 7F.04 (F-
Class) turbine have been based on data obtained from GE and GE data sheets. The ASL that will be utilised as
back-up fuel for the proposed turbines is assumed to have a sulphur content of up to 0.1% and the SO2 emis-
sions rates have calculated on this basis and estimated fuel usage rates for SGT6 2000E and turbines.
The concentrations of NOx, SO2 and PM10 in the emissions from the proposed turbine are shown in Table 7-3
for comparison with the emission limits presented in Table 7-2. The concentrations have been based on ex-
haust flow data obtained from Siemens and GE for the units referred to above. The emission rates for the GTs
have been based on emissions limits contained in Siemens data sheets and emissions data for Riyadh PP-11
(GE turbines). Two sets of data are shown corresponding to different ambient conditions. The emissions
shown are for the turbine at 100% load at 40ºC (ambient temperature) are typical summer conditions and are
representative of operating conditions for the majority year. The emissions shown for 0 to 10ºC are for the win-
ter period and represent worst case operating conditions.
Table 7-3 SO2, NOx and PM10 Emissions Concentrations for the Proposed Turbine at DCCPP
Pollutant
Concentration (mg/Nm3)(a)
Natural Gas ASL
Ambient tempera-ture: 40ºC
Ambient tempera-ture: 0 - 10ºC
Ambient tempera-ture: 40ºC
Ambient tempera-ture: 0 - 10ºC
SO2 -- -- 48.4/74.7 44.2/77.3
NOx 21.3/51.4 21.3/51.4 86.3/214.9 75.0/215.9
PM10 3.5/10 4.6/10 50/50 54.2/50
(a) The two values are presented for each pollutant show the emission rate for F-Class GT first and the E-Class GT second (F-Class/E-Class).
Project number: 37446130 Dated: 09/11/2014 96 | 278 Revised:
A comparison of the emissions limits and the calculated emission concentrations for the proposed turbines
show that emissions of NOx, SO2 and PM10 comply with PME emission standards for both the primary fuel and
back-up fuel, under both sets of ambient conditions.
The IFC emission guidelines that would apply to the proposed turbine operating on ASL are as follows:
Nitrogen Oxides (NOx): 152 mg/Nm3 (Degraded/Non-degraded Air shed)
Sulphur Dioxide (SO2): use of 1.0% S content or less in fuel (Non-degraded Air shed)
Total Particulate Matter: 50 mg/Nm3 (Non-degraded Air shed)
The emissions data used indicate that NOx emissions may exceed the IFC emission guideline of 152 mg/Nm3
for ASL firing; however, the NOx concentration for the E-Class GT when firing on ASL has been estimated from
the Natural gas/ASL NOx emission ratio for the F-Class GT. With respect to SO2 emissions, the sulphur content
of the ASL will be generally 0.1%, which complies with the IFC specifications. For Total Particulate Matter (as-
suming this is all PM10), emissions for the F-Class GT for 0- 10ºC ambient conditions may slightly exceed the
IFC emission limit based on emission data used. Review of compliance with PME emissions standards and IFC
emission guidelines will be required when the make and model of combustion units has been finalised and unit
specific data can be obtained from the EPC.
Projects Located in Degraded Air Sheds 7.2.3Where facilities or projects are located within an air shed of poor quality, the IFC General EHS Guidelines for air
emissions and ambient air quality require an operator to minimise incremental impacts by achieving the emis-
sions limits shown in Table 7-2 and where these emissions nevertheless result in excessive ambient impacts
relative to local regulatory standards, the project should identify and implement site-specific offsets that result in
no net increase in the total emissions of those pollutants that are responsible for the degradation of the air shed.
The IFC General EHS Guidelines (IFC, 2007) state that an air shed should be considered as having poor air
quality if nationally legislated AQSs (in this case PME standards) or WHO Air Quality Guidelines are exceeded
significantly; however, no criteria are included to determine a significant exceedence. The dispersion modelling
for this assessment has considered the baseline air quality and the influence of the existing emissions sources
at the site on the air shed.
The Project site of is essentially a Greenfield site, with no existing significant sources of combustion emissions.
It is likely that the air quality in the area of the site and surrounding areas is good and the potential for ex-
ceedences of the Kingdom of Saudi Arabia (KSA) ambient air quality standards (AQSs) for SO2, NO2 to occur is
negligible. For PM10, exceedences of the AQSs are likely to occur on occasion due to the arid nature of the ar-
ea and wind entrainment of fine particles and dust from natural sources. As such, the air shed is not considered
as degraded for any of the pollutants considered in this assessment.
97 | 278
Methodology 7.3 Scope 7.3.1
The scope of this assessment has included the following:
Review of the limited emissions data for F-Class and E-Class GTs;
Review of fuel specifications for the natural gas and ASL;
Review of the exhaust flow data and operating characteristics obtained from Siemens for SGT6 2000E and
GE 7F.04 turbine and used in previous modelling studies undertaken by WSP for the same turbine models
using natural gas and ASL;
Review of data, information and site plans and preliminary design supplied by SEC;
A desk study to confirm the locations that may be sensitive to changes in local air quality; and
Review of relevant international and national air quality regulations, standards and guidelines for emissions
to air from thermal plants and ambient air quality.
Prediction of Construction Phase Impacts 7.3.2During the construction phase, activities undertaken within the site may cause dust and particulate matter to be
emitted to the atmosphere.
Dust comprises particles typically in the size range 1-75 micrometres (µm) in aerodynamic diameter and is cre-
ated through the action of crushing and abrasive forces on materials. The larger dust particles fall out of the
atmosphere quickly after initial release and therefore tend to be deposited in close proximity (10 to 20 metres)
to the source of emission. Dust therefore, is unlikely to cause long-term or widespread changes to local air
quality. The site is in an area where there is a significant natural source of particulate material that will be readi-
ly entrained by the wind, therefore, the potential dust impacts during the construction period must be considered
within this context.
The smaller particles of dust (typically less than 10 µm in aerodynamic diameter) are known as PM10 and PM2.5
(referred to as fine particles) and represent only a small proportion of total dust released. As these particles are
at the smaller end of the size range of dust particles, they remain suspended in the atmosphere for a longer
period of time than the larger dust particles, and can therefore be transported by wind over a wider area (alt-
hough the majority are generally deposited within 100m of the source). PM10 and PM2.5 are small enough to be
drawn into the lungs during breathing, which for sensitive members of the public could cause an adverse reac-
tion. As a result of this potential impact on health, standards and objectives for PM10 and PM2.5 are defined by
PME.
A qualitative assessment of the potential impacts due to the generation and dispersion of dust and fine particles
during the construction phase has been undertaken. As there are no formal assessment criteria for dust and
fine particle generation and dispersion during construction, the significance of impacts associated with this
phase of the project has been determined qualitatively by:
Project number: 37446130 Dated: 09/11/2014 98 | 278 Revised:
Identifying the construction activities associated with the project which could generate dust and PM10/PM2.5
and their likely duration;
Identifying sensitive receptors close to the site, particularly those within 200m of the construction site bound-
ary; and
The prevailing wind direction.
Exhaust emissions from construction vehicles will have an impact on local air quality both on-site and adjacent
to the routes used by these vehicles to access the site. Information on exact numbers of vehicles associated
with the construction phase is not available; however, it is considered that vehicle movements associated with
the construction phase are not likely to be significant. Therefore, a qualitative assessment of their impact on
local air quality has also been undertaken.
Prediction of Operational Phase Impacts 7.3.3Dispersion Model Used
The operational phase of proposed turbine has been assessed using detailed dispersion modelling. The atmos-
pheric dispersion model Breeze Aermod (version 7.8.0.21) was used for quantifying the impact of emissions
from the plant at sensitive receptors in the area. Aermod is an advanced dispersion model for calculating con-
centrations of pollutants emitted continuously from point, volume and area sources and is approved by the Unit-
ed States Environmental Protection Agency (USEPA) and the Environment Agency (EA) in the UK for regulato-
ry applications. This dispersion model is also specified as appropriate for assessments of this nature in the IFC
General EHS guidelines2.
The model includes algorithms which are also able to take into account the following (where suitable input data
is available):
Effects of building downwash;
Complex terrain;
Time varying emission rates;
Chemical reactions;
Plume rise as a function of distance; and
Averaging times ranging from short-term (e.g. 10-minute or 1-hour) to annual.
Buildings and Topography
Both nearby buildings and complex topography can have a significant effect on the dispersion characteristics of
the plumes from the stacks being assessed. Buildings can cause the plume to come to ground much closer to
the stack than otherwise expected, causing higher pollutant concentrations. Plumes can also impact on
hillsides under certain weather conditions, or within a basin or hollow which may result in emissions being
trapped for low level emissions.
2 General EHS Guidelines: Environmental, Air Emissions and Ambient Air Quality, IFC (April 2007)
99 | 278
Buildings that are likely to be constructed as part of the power plant (e.g. new turbine hall and steam turbine
building), which may have an impact on the dispersion of emissions from the stacks of the proposed plant have
been identified and included in the model. The dimensions of these buildings have been estimated based on
the drawing included in the tender information supplied by SEC.
The topography of the surrounding area is essentially flat and at the same elevation across the entire study ar-
ea. Therefore, digital terrain data has not been included in the model.
Meteorological Data
Meteorological records of wind speed, direction and atmospheric stability parameters are required to predict the
pollutant concentrations which could occur under different weather conditions.
With respect to the dispersion of pollutants, the atmosphere is commonly referred to in terms of its ‘stability’.
When the atmosphere is said to be ‘stable’, there is little turbulence and vertical movement of air. These condi-
tions are almost exclusively confined to the hours between sunset and sunrise, and require light winds. Such
conditions in conjunction with wind speeds of less than 1 m/s often give rise to the highest pollutant concentra-
tions from a stack release.
‘Unstable’ atmospheric conditions are confined to the daytime when, primarily due to surface heating, there is
considerable turbulence and rapid vertical movement, thus dissipating the pollutant fairly rapidly. Hence pollu-
tant concentrations will decrease rapidly away from the source. Unstable conditions also favour light winds and
strong to moderate levels of sunshine.
‘Neutral’ stability occurs under cloudier weather conditions and is biased towards higher wind speeds. A neutral
atmosphere can persist during the day or night.
Five years (2009-2013) of sequential hourly readings of wind speed, direction and atmospheric boundary layer
conditions from the observing station at Sharm El Sheikh Airport were used in the model. This observing station
is located approximately 100km to the west northwest of the power plant site. This is the closest observing sta-
tion to the power plant site and is also in a coastal location; therefore, this observing station was considered to
be representative of meteorological conditions at the site, as far as practicable.
Review of the available data (up to 2013) indicated that the meteorological data sets for the above years were
most complete, i.e. had the fewest missing observations. Wind roses for each of the five years are shown in
Appendix D, which identifies that the predominant wind direction is from north, with winds from the north north-
east also occurring relatively frequently. Winds from all other directions occur with a very low frequency.
Concentrations of each pollutant have been predicted over the relevant averaging period of the standard (i.e. 1-
hour, 24-hour and annual mean) within the context of the individual operating conditions.
Modelling Scenarios
Scenarios have been modelled for the Project take into account the new combustion turbines operating primari-
ly in Combined Cycle operation, but Simple Cycle operation has also been considered. The tender information
issued by SEC presents two options for the number and size of the turbines on which the power plant should be
Project number: 37446130 Dated: 09/11/2014 100 | 278 Revised:
based to achieve the required power output of 485 – 550 MW. Both of the options are based on a two power
block configuration and are as follows:
Option A
Block 1: 1 x F-Class Turbine, 1 x Heat Recovery Steam Generator (HRSG) and 1 x Steam Turbine (ST)
Block 2: 2 x E-Class Turbines, 2 x HRSG and 1 x ST
Option B:
Block 1: 2 x E-Class Turbines, 2 x HRSG and 1 x ST
Block 2: 2 x E-Class Turbines, 2 x HRSG and 1 x ST
Scenarios were modelled for both potential plant configurations to provide a comparison of the impact of the two
options on local air quality. Within each of the scenarios, consideration of the turbines operating at two different
ambient temperatures has been made, reflecting the variation in emissions at different ambient conditions for
the same turbine load (this reflects operations at different times during the year). Emissions for an ambient
temperature of 40ºC (summer conditions – Operating Point 1) and a temperature of 0 to 10ºC (winter conditions
– Operating Point 2). The Operating Point 1 conditions would be indicative of the majority of the year, whereas
the Operating Point 2 conditions can be considered worse case. The twelve scenarios that have been consid-
ered in this assessment are described in Table 7-4.
Table 7-4 Description of Operational Scenarios
Scenario Description Operating Condition Details
1A1
Option A: Maximum operating
conditions (OP1) – Combined
Cycle
1 x gas-fired F-Class GT, 2 x gas-fired E-Class GTs operating at 100% load at ambient temperature of 40ºC (Operating Point 1)
Combined Cycle mode
60m Main stacks
Assumed to be operating at maximum load continuously for a full year
1A2
Option A: Maximum operating
conditions (OP2) – Combined
Cycle
1 x gas-fired F-Class GT, 2 x gas-fired E-Class GTs operating at 100% load at ambient temperature of 0 to 10ºC (Operating Point 2) (Jan to Mar, Nov & Dec only)
Combined Cycle mode
60m Main stacks
Assumed to be operating at maximum load continuously for winter period
1B1
Option B: Maximum operating
conditions (OP1) – Combined
Cycle
4 x gas-fired E-Class GTs operating at 100% load at ambient tem-perature of 40ºC (Operating Point 1)
Combined Cycle mode
60m Main stacks
Assumed to be operating at maximum load continuously for a full year
1B2 Option B: Maximum operating
conditions (OP2) – Combined
4 x gas-fired E-Class GTs operating at 100% load at ambient tem-perature of 0 to 10ºC (Operating Point 2) (Jan to Mar, Nov & Dec on-ly)
101 | 278
Scenario Description Operating Condition Details
Cycle Combined Cycle mode
60m Main stacks
Assumed to be operating at maximum load continuously for winter period
2A1
Option A: Maximum operating
conditions (OP1) – Simple Cycle
1 x gas-fired F-Class GT, 2 x gas-fired E-Class GTs operating at 100% load at ambient temperature of 40ºC (Operating Point 1)
Simple Cycle mode
40m By-pass stacks
Assumed to be operating at maximum load continuously for a full year
2A2
Option A: Maximum operating
conditions (OP2) – Simple Cycle
1 x gas-fired F-Class GT, 2 x gas-fired E-Class GTs operating at 100% load at ambient temperature of 0 to 10ºC (Operating Point 2) (Jan to Mar, Nov & Dec only)
Simple Cycle mode
40m By-pass stacks
Assumed to be operating at maximum load continuously for winter period
2B1
Option B: Maximum operating
conditions (OP1) – Simple Cycle
4 x gas-fired E-Class GTs operating at 100% load at ambient tem-perature of 40ºC (Operating Point 1)
Simple Cycle mode
40m By-pass stacks
Assumed to be operating at maximum load continuously for a full year
2B2
Option B: Maximum operating
conditions (OP2) – Simple Cycle
4 x gas-fired E-Class GTs operating at 100% load at ambient tem-perature of 0 to 10ºC (Operating Point 2) (Jan to Mar, Nov & Dec on-ly)
Simple Cycle mode
40m By-pass stacks
Assumed to be operating at maximum load continuously for winter period
3ACC
Option A: Maximum operating
conditions (OP1) – Combined
Cycle (ASL)
1 x ASL-fired F-Class GT, 2 x ASL-fired E-Class GTs operating at 100% load at ambient temperature for 45ºC (Operating Point 1)
Combined Cycle mode
60m Main stacks
Assumed to be operating at maximum load continuously for a full year
ASL assumed to have 0.1% sulphur content
3ASC
Option A: Maximum operating
conditions (OP1) – Simple Cycle
(ASL)
1 x ASL-fired F-Class GT, 2 x ASL-fired E-Class GTs operating at 100% load at ambient temperature for 45ºC (Operating Point 1)
Simple Cycle mode
40m By-pass stacks
Assumed to be operating at maximum load continuously for a full year
ASL assumed to have 0.1% sulphur content
Project number: 37446130 Dated: 09/11/2014 102 | 278 Revised:
Scenario Description Operating Condition Details
3BCC
Option B: Maximum operating
conditions (OP1) – Combined
Cycle (ASL)
4 x ASL-fired E-Class GTs operating at 100% load at ambient tem-perature for 45ºC (Operating Point 1)
Combined Cycle mode
60m Main stacks
Assumed to be operating at maximum load continuously for a full year
ASL assumed to have 0.1% sulphur content
3BSC
Option B: Maximum operating
conditions (OP1) – Simple Cycle
(ASL)
4 x ASL-fired E-Class GTs operating at 100% load at ambient tem-perature for 45ºC (Operating Point 1)
Simple Cycle mode
40m By-pass stacks
Assumed to be operating at maximum load continuously for winter period
ASL assumed to have 0.1% sulphur content
Modelling Assumptions
The make and supply of the major plant (e.g. GT/HRSGs and STs) has not yet been finalised and therefore
emissions from the turbines have been based on exhaust composition and flow data held by WSP and supplied
by Siemens and GE for previous studies involving F-Class and E-Class turbines. Pollutant emission and ex-
haust flow data for the F-Class turbine were based on data supplied by GE for Riyadh PP-11 and obtained from
data sheets available on the GE website. Exhaust flow data for the E-Class turbines were based on data sup-
plied by Siemens for DCCPP and obtained from data sheets available on the Siemens website.
The summer operating conditions were modelled for a full year of meteorological data as these conditions are
more representative of the majority of the year. The winter operating or worse case conditions were modelled
for the months of January to March, November and December because it is during these months that ambient
temperatures can drop to between 10 and 0ºC. All combustion units (GTs) were assumed to be operating 24
hours per day, seven days a week, at the maximum operating conditions in either combined cycle mode or sim-
ple cycle mode. These maximum load conditions are only likely to occur during the months of July and August
(1400 to 1640 hours per year) each year when demand on the plant would be greatest; however, the scenario
was assessed using a full year of meteorological data to allow the worse-case conditions to be identified and
when they would occur.
Emission temperatures for Combined Cycle operation for the two sets of ambient conditions were estimated
from data held by WSP for similar sized combined cycle units operating under the same ambient temperatures.
The sulphur content of the ASL has been assumed to be 0.1% based on the fuel specification issued by SEC 3.
SO2 emission rates for ASL-fired operation have been based on fuel consumption rates for the turbines. The
natural gas fuel specification supplied by SEC stated that there was no hydrogen sulphide (H2S) in the natural
gas, therefore SO2 emissions for gas-fired operation have been assumed to be negligible and not modelled.
3 Construction of Duba No.1 Combined Cycle Power Plant Project, Schedule B, Attachment III, Detailed Scope of Works; SEC
103 | 278
No minimum design stack height for the main stacks was specified in the SEC Scope of works3; therefore, a
main stack height of 60m and a bypass stack height of 40m were assumed.
Stack Parameters
The atmospheric dispersion of pollutants is affected by the efflux velocity at the stack exit point (which deter-
mines the momentum of the plume) and the temperature of the gases (which determines the thermal buoyancy
of the plume). Both momentum and buoyancy contribute to plume rise. The atmospheric conditions then gov-
ern the degree of turbulent mixing of the plume.
Engineering data (stack heights and diameters etc.), exhaust flow data, pollutant concentrations and mass
emissions rates for the proposed emission sources were based on data obtained from Siemens and GE for oth-
er SEC sites and also obtained from data sheets for Siemens and GE units. The internal stack diameter for the
proposed F-Class turbine modelled was assumed to be 5.8m for the by-bass stack (Simple Cycle) and 5.5m for
the main stack (Combined Cycle). The internal stack diameter of the E-Class turbines for the by-pass stack
was assumed to be 4.5m and 4m for the main stack. The model input parameters used for this study are sum-
marised in Appendix E. The E-Class turbines were assumed to have a NOx emission concentration of 25ppm
based on GE data sheets. The F-Class turbine was assumed to have a NOx emission concentration of 10ppm
based on data supplied by Siemens for Riyadh PP-11 Power Plant.
Modelling Domain
Pollutant concentrations have been predicted over the wider area using a regular Cartesian grid of receptor lo-
cations. The grid covers an area of 9km by 7.5km, extending out to a distance of approximately 3.5km north of
the Project site, 4km to the south, 6.5km to the east and 3.5km to the west of the site. A grid spacing of 300m
was selected for the modelling grid, which gave 806 (gridded) receptor locations in the model. In addition, 5
boundary receptors and 4161 discrete receptor points were also included in the model to ensure adequate reso-
lution of the maximum predicted concentrations in the areas of greatest impact and over areas of sensitive de-
velopment. A further 11 discrete receptors were also selected to specifically represent existing receptor loca-
tions identified as potentially sensitive to changes in air quality. The extent of the (gridded) modelling domain is
shown in Figure 7-1. It should also be noted that discrete receptor locations outside the gridded domain were
included to represent the small towns located 10 – 15km to the north (Alsourah) and south (Almuwaylih) of the
Project site.
Project number: 37446130 Dated: 09/11/2014 104 | 278 Revised:
Figure 7-1 Modelling Domain
NOx to NO2 Conversion
NOx emitted to the atmosphere as a result of combustion will consist largely of nitric oxide (NO), a relatively in-
nocuous substance. Once released into the atmosphere, nitric oxide is oxidised to NO2, which is of concern
with respect to health and other impacts. The proportion of nitric oxide converted to NO2 depends on a number
of factors including wind speed, distance from the source, solar irradiation and the availability of oxidants, such
as ozone (O3).
A study published by Janssen et al (1988) made extensive measurements of the percentage oxidation of NOx to
NO2 in power station plumes, and derived empirical relationships based on downwind distance, ozone concen-
tration, wind speed and season of the year. The findings indicated that the occurrence of NOx in the form of
NO2 within 2km of a stack will vary between 20% and 50%. An assumption that there will be 100% conversion
of NOx to NO2 for annual mean concentrations would therefore be an overestimation, thereby providing worst
case results.
In the absence of specific national guidance on detailed dispersion modelling, guidance provided by the Air
Quality and Modelling Unit (AQMAU) of the Environmental Agency in the UK on conversion ratios for NOx and
NO2 for large combustion sources has been used. The guidance sets out a phased approach to determining
the magnitude of predicted NOx concentrations. The initial phase of this approach is screening, where a worse-
case assumption of 50% and 100% oxidation is made for short-term and long-term averaging periods (respec-
tively). Where this conservative assumption leads to high predicted concentrations, the guidance advises mak-
ing a revised assumption of 35% and 70% oxidation for short-term and long-term averaging periods (respective-
ly).
105 | 278
For the purposes of this assessment, and to ensure a worst-case assessment, it has been assumed that there
will be a 50% and 100% conversion of NOx to NO2, for short (1-hour) and long -term (annual) predicted concen-
trations, respectively.
Predicted 10-Minute Mean Sulphur Dioxide Concentrations
It is not possible to predict 10-min mean pollutant concentrations directly with the EPA-approved modelling
software that has been used, namely AERMOD. To address this, a methodology for conversion of 1-hour mean
predicted concentrations to 10-minute averages published in Canada by the Ontario Ministry of the Environ-
ment4 has been used. This methodology provides a factor of 1.65 for converting a 1-hour mean predicted con-
centration to a 10-minute mean, based on the following equation:
[SO2](10-min mean) = (60min/10min)0.28 x [SO2](1-hr mean)
The factor was applied to the predicted maximum 1-hour mean SO2 concentrations. This provides an indicative
concentration for this averaging period.
Significance Criteria
The significance of the predicted concentrations for the operation of the Project has been based on the magni-
tude of the maximum predicted off-site concentration, as well as the maximum predicted at a receptor location
relative to the AQS for the pollutant and averaging period. The residual impact is based on the actual predicted
concentration, with the significance being based on the impact of the Project without any further mitigation
measures beyond those already incorporated in the design of the plant.
For the predicted pollutant concentrations, the assessment was based on the levels presented in Table 7-5
(which have been developed in the absence of any published national guidance taking into account the IFC
guidelines).
Table 7-5 Criteria for Determination of Significance
Process Contribution as Percentage of Relevant AQS Significance
0 – 5% Negligible
>5 – 25% Minor
>25 – 70% Moderate
>70 – 100% Major
>100% Critical
Impacts on pollutant concentrations will be either positive (concentrations predicted to decrease) of negative
(pollutant concentrations are predicted to increase).
Calculation of Annual Greenhouse Gas Emissions
4 Methodology For Modelling Assessments Of Contaminants With 10-Minute Average Standards And Guidelines under O. Reg. 419/05,
Ontario Ministry for the Environment (April 2008)
Project number: 37446130 Dated: 09/11/2014 106 | 278 Revised:
Data on the fuel consumption and emissions factors published by the International Panel on Climate Change
(IPCC) have been used to calculate the additional annual greenhouse gas (GHG) emissions once the proposed
power plant is operational is operational.
Existing Baseline Conditions 7.4 Local Emissions Sources 7.4.1
The Project site is located approximately 55km to the north of Duba. The site is a Greenfield site and therefore,
there are currently no other industrial point sources or sources of combustion emissions of any other type. Traf-
fic emissions from the urban area of Duba or the other nearest small settlements are unlikely to influence of pol-
lutant concentrations at the SEC site and sensitive receptors closest to the power plant to any measurable ex-
tent due to the separation distance.
Traffic using the nearby highway (Route 5), which runs roughly north-south, approximately 100m east of the
Project site will have exhaust emissions associated with it; however, emissions from the traffic is unlikely to sig-
nificantly influence background air quality in the area. The land surrounding the site is largely characterised by
sabkha, which is generally devoid of vegetation and sandy in nature. These areas and those to the north, east
and south represent a significant natural source of particulate matter, which will influence ambient particle levels
in the region of the site. Emissions from this natural source are likely to result in exceedences of the AQSs for
PM10 and PM2.5 on occasion due to wind entrainment.
The Aermod dispersion model only calculates the pollutant contribution from the stacks under consideration. It
has the capacity to allow for the contribution of background concentrations to total pollutant concentrations in
addition to those arising from the existing and the proposed sources at the facility. However, no long term air
quality monitoring data is available for the area for inclusion in the modelling. There are no significant sources
of the pollutants considered in the area; therefore, the existing air quality at the site and the surrounding area is
likely to be good.
Air Quality Monitoring Data 7.4.2A short-term air quality monitoring programme for NOx, SO2 O3
and PM10 was undertaken in the area around
the Project site in May 2014. PM10 was measured using a continuous monitoring system (laser light scattering
device) for a period of 17 hours (5th and 6th of May 2014). The average PM10 concentration for the monitoring
period was 40.2µg/m3, which is well below the PME AQS for both annual and 24-hour mean PM10 concentra-
tions SO2, NOx, and O3 (ozone) monitoring was performed using diffusion tubes at three locations. The diffu-
sion tubes were installed on 5th May and were exposed for approximately a two-week period (collected on 23rd
May). The average results for each site are shown in Table 7-6, with the locations of the diffusion tubes shown
in Figure 7-2 overleaf. Copies of the analytical results for the two diffusion tube sampling periods are presented
in Appendix F.
The monitoring results indicate low levels of NOx and (particularly) SO2, which might be expected given the lack
of major and existing sources of these primary pollutants in the area. The average concentrations of NOx and
SO2 are well below the respective PME AQS for annual mean concentrations, peaking at 20% of the NOx annu-
107 | 278
al standard and 6.5% of the SO2 annual Standard. The AQS for 1-hour mean ozone concentrations is 235
µg/m3; however, it is not possible to directly compare the monitoring results (which are time weighted averages)
with this 1-hour mean standard. Nevertheless, the highest concentration of O3 measured is below 50% of the
standard, which indicates that overall concentrations of this secondary pollutant are likely to be relatively low in
the area.
Table 7-6 Diffusion Tube Monitoring Results
Location ID Location Description
UTM Coordinates Concentration (µg/m3)(a)
Easting Northing O3 NOx SO2
AQ1 Southwest of power plant site near the coastline 740469.56 m 3071919.79 m 116.69 16.34 <1.98(b)
AQ2 Southwest of power plant site further inland. 740842.17 m 3071981.79 m 124.92 17.89 <1.98(b)
AQ3 Immediately east of the site entrance, near Route 5
741798.00 m 3073079.17 m 109.66 17.41 3.62
(a) Concentrations shown are the average of the duplicate samples deployed at each monitoring location.
(b) Concentrations are below the reporting limit (<0.03 µg S)
Figure 7-2 Diffusion Tube Monitoring Locations
Project number: 37446130 Dated: 09/11/2014 108 | 278 Revised:
Local Meteorological Data 7.4.3Site specific meteorological data is also not available for the study area. For the purposes of the modelling, five
years of hourly sequential meteorological data (wind speed and direction, ambient temperature and relative
humidity) has been obtained for Sharm El Sheikh Airport, which is the nearest monitoring station to the Project
site (closer than Tabouk) where meteorological data suitable for dispersion model input is collected and is in a
coastal location.
Inter-annual Variation in Predicted Concentrations due to Meteorological Conditions
Screening modelling for NO2 (as the pollutant with the highest mass emission rate with the primary fuel) was
undertaken, which considered both the typical ambient conditions (OP1) and worse case ambient conditions
(OP2) for each year of meteorological data (2009 to 2013), as well as both combined and simple cycle mode, to
determine the inter-annual variation in predicted concentrations (location of maximum impact) due to the effects
of meteorological conditions alone. The results of the meteorological data screening showed that 2010 general-
ly produces higher predicted ground level concentrations (in particular, annual mean concentrations); therefore,
the subsequent modelling was undertaken using 2010 meteorological data.
Sensitive Receptors 7.5The Project site is located relatively remotely from any urban development and only has a small number of po-
tentially sensitive land uses within 10km.
There are a number of future receptors, which will be introduced to the site as part of the Project including offic-
es and a company housing compound at, or adjacent to, the Project site. The power plant receptors (offices
and work areas) are effectively on-site receptors and will be located inside the boundary of the Project site, near
the south eastern corner. The company housing compound will be located immediately outside the boundary of
the site, adjacent to the northeast corner of the boundary.
These locations have been included in the model as discrete receptors due to the potential for sensitive recep-
tors to be in these locations over short and long-term periods. The locations that have been represented in the
model by a number of discrete receptors (in addition to the receptor grid and non-specific discrete receptor ar-
rays) are shown Figure 7-3. Further details of the receptor locations are in presented in Table 7-7.
109 | 278
Figure 7-3 Sensitive Receptor Locations
Project number: 37446130 Dated: 09/11/2014 110 | 278 Revised:
Table 7-7 Sensitive Receptors
Receptor Location Receptor Type
X Coordinate Y Coordinate
Central Control Building 740600.7 3073056.5 Industrial(a)
Main Administration Building 741657 3072763.9 Commercial(b)
Canteen 741678.4 3072721.1 Worker Welfare(c)
Mosque 741621.3 3072692.5 Worker Welfare
Company Housing Compound (NW) 741100.3 3073777.3 Residential)
Company Housing Compound (NE) 741193.1 3073820.2 Residential
Company Housing Compound (SE) 741235.9 3073727.4 Residential
Company Housing Compound (SW) 741143.1 3073688.1 Residential
Fish Farm (on-shore) 739340 3074614 Commercial
Alsourah 732009 3083693 Residential (Town)
Almuwaylih 744386 3067138 Residential (Town)
(a) Industrial refers to areas where workers involved directly involved in the running of the power plant may be present for a shift period; therefore, PME AQSs for annual and 24-hour mean concentrations would not apply in these locations. These receptors would gener-ally be considered lower in sensitivity.
(b) Commercial refers to locations where administration staff may be present for a shift; again, standards for annual and 24-hour mean concentrations would not apply in these locations.
(c) Worker welfare refers to places that members of the workforce are likely to be only for short periods of time; therefore only PME AQSs for averaging period of an hour or less are relevant to exposure in these locations.
(d) Residential receptors are considered of highest sensitivity due to the potential for people to be present for long periods of time. The PME AQSs for all averaging periods apply in these locations.
111 | 278
Assessment of Construction phase Impacts 7.6 Construction Sources of Dust and PM10 7.6.1
The main sources of dust and PM10 during construction activities include:
Haulage routes, vehicles and construction traffic;
Materials handling, storage, stockpiling, spillage and disposal;
Exhaust emissions from site plant, especially when used at the extremes of their capacity and during me-
chanical breakdown;
Site preparation and restoration after completion; and
Construction and fabrication processes.
The construction phase has been estimated at approximately 18 months in total duration. During this time, the
majority of the releases are likely to occur during the ‘working week’. However, for some potential release
sources, e.g. exposed soil produced from significant earthwork activities, in the absence of dust control
mitigation measures, dust generation has the potential to occur 24 hours per day over the period during which
such activities are to take place.
Distance from the Point of Generation to the Sensitive Receptor
Depending on wind speed and turbulence (notwithstanding natural events such as dust storms), it is likely that
the majority of dust will be deposited in the area immediately surrounding the source (up to 200m away). The
site of the power plant is located over 200m from the inside of the boundary of the Project site at its closest
point. Within the site itself, there are no receptor locations that are highly sensitive to dust impacts in close
proximity.
The area surrounding the Project site is essentially barren and of low sensitivity to emissions from the
construction phase. Beyond the boundary of the Project site, the closest sensitive receptor location is the
company housing compound to the immediate north of the power plant site, adjacent to Route 5; however, this
area will be under construction as part of the power plant development and therefore is effectively not a
receptor location with respect to the construction phase.
A fish farm is located some 1.7km to the north northwest of the site. Therefore, because of this very large
separation distance, the likelihood of these locations being affected by a dust nuisance during the construction
of the power plant is negligible. All other sensitive receptor locations are at least 3km from the construction site
and would, therefore, not be affected by dust emissions from the construction activities, even in the absence of
specific dust mitigation measures.
Prevailing Weather Conditions
Based on the meteorological data used in the assessment (Sharm El Sheikh) shown in Appendix D, the
strongly prevailing wind direction at the site is from the north (together with north northeast for around half the
frequency). Winds blowing from all other directions occur with a very low frequency. When applying this data
to the Project site, caution must be exercised as the climate observing station is around 100km from the site;
nevertheless, the observing station is the closest and the two sites are located a similar distance from the Red
Project number: 37446130 Dated: 09/11/2014 112 | 278 Revised:
Sea Coast and, as such, it is reasonable to assume that the prevailing winds at the Project site will have a
significant northerly component.
With the prevailing northerly winds, receptors located to the south of the construction site are most likely to be
affected by dust emissions from the site should they occur; however, there are no sensitive receptor locations
within 200m (or indeed several kilometres) of the boundary of the power plant site in this direction.
With respect to dust emissions, moderate to strong wind speeds (e.g. above 5 m/s) tend to generate dust
emissions through entrainment. On the basis of the five consecutive years of meteorological data from Sharm
El Sheikh Airport (2009 – 2013), wind speeds of this magnitude occur for only around 32% of the time for all
wind directions. Moderate to strong winds from the north occur most frequently at approximately 18% of this
time, which represents approximately 65 days per year. For the majority of wind directions however, moderate
to strong winds occur for less than 1% of the time (approximately 3.5 days per year).
The lack of sensitive receptors leads to the conclusion that the potential to be affected by dust emissions from
the construction activities is negligible.
Despite the negligible potential for giving rise to off-site dust nuisance, it will be important to ensure that any
releases of dust and other emissions to the atmosphere are controlled during the construction period. This
would not be difficult to achieve with standard mitigation measures and good working practices. Dust control
measures are presented below and in Chapter 16: Framework Construction Environmental Management Plan.
By consideration of the factors described above, the overall impact of dust nuisance would therefore be
temporary, short-term and local in effect and of negligible significance in the absence of any mitigation
measures. During construction, concentrations of PM10 in the locality will be elevated. As the magnitude of
these releases is relatively small compared to total dust, any effects resulting from them are likely to be local,
temporary, short-term and of negligible significance.
Release of Emissions to Air from Construction Traffic 7.6.2
Construction traffic associated with the construction of the Project will increase traffic levels on the Route 5.
The greatest potential for impacts on air quality from traffic associated with the construction phase of the project
will be in the areas immediately adjacent to the principal means of site access for construction traffic. However,
there are few receptor locations in close proximity to the route affected by construction traffic, and the level of
construction traffic is unlikely to be significant. Therefore, the impacts on local air quality of emissions
associated with construction traffic would to be localised, temporary, and of negligible significance.
113 | 278
Assessment of Operational Phase Impacts 7.7
Introduction 7.7.1The IFC General EHS guidelines for air emissions2 state that for projects with significant sources of air
emissions, and potential for significant impacts to ambient air quality (which is relevant to DCCPP), impacts
should be prevented or minimized by ensuring:
emissions do not result in pollutant concentrations that reach or exceed relevant ambient quality guidelines
and standards by applying national legislated standards, or in their absence, the current WHO Air Quality
Guidelines; and
emissions do not contribute a significant portion to the attainment of relevant ambient air quality guidelines
or standards. As a general rule, this Guideline suggests 25% of the applicable air quality standards to allow
additional, future sustainable development in the same air shed.
The PME has published Environmental Standards for stationary sources5 which include emission limits (see
Table 7-2) that have been set to:
i) contribute to the maintenance of ambient air quality.
ii) control the wider spatial and trans-boundary effects of air pollution; and
iii) recognise the importance of international air quality agreements.
The assessment of the impacts of the Project has been undertaken within the context of the above
requirements, using the significance criteria presented in Table 7-5.
Stack Heights 7.7.2
The PME Environmental Standards for stationary sources states that stack heights should be equal to or greater than:
H + 1.5L
Where:
H is the height of nearby structure(s) above the base of the stack (e.g. turbine hall);
L is the lesser of dimension, height or width, of the nearby structure; and
where a nearby structure is classed as anything within 5L (but less than 800m).
The turbine hall is likely to be the largest structure near the main stacks and by-pass stacks. Currently, the
height of the turbine hall has not been finalised; however, if the turbine hall was assumed to be 20m (as in the
modelling), then the appropriate minimum stack height would be 50m (although this calculation would apply to
both main stacks and by-pass stacks, the main stacks would be the emphasis, as emissions would be from
these stack under normal operation). The SEC minimum main stack height specification of 60m would clearly
meet with PME requirement for a 20m tall turbine building and would continue to meet the requirement for a
5 Kingdom of Saudi Arabia National Environmental Standard, Control of Air Emissions from Stationary Sources (March 2012)
Project number: 37446130 Dated: 09/11/2014 114 | 278 Revised:
turbine building of up to 25m in height. This issue may require further review and assessment once the power
plant building and structure dimensions have been finalised by the EPC and SEC; however, the PME
Environmental Standards also state that stack height should ultimately be determined using dispersion
modelling.
It must also be remembered that the dispersion modelling undertaken for this assessment is based on general
plant descriptions and typical emissions for F-Class and E-Class turbines and, as such, several assumptions
were required regarding turbine exhaust flows, discharge temperatures and pollutant emission rates to
complete the assessment. Although, the assumptions are aimed, as far as practicable, at producing
conservative results, the results of the assessment would need to be reviewed once an EPC has been selected
and the exact combustion units that will be installed (and the associated emissions under the ambient
conditions considered herein) are known. This would determine whether further dispersion modelling may be
needed to characterise the impacts of the power plant on local air quality and confirm proposed stack heights.
Combined Cycle Operation Scenarios – Natural Gas 7.7.3A full set of results for the combined cycle operation scenarios is provided in Appendix G, with a summary
provided in Table 7-8. Dispersion modelling results for Option A and Option B plant configurations have been
presented for emissions from natural gas-firing and under both sets of ambient conditions (OP1 and OP2).
The results show that when considering both the typical and worse case operating conditions for gas-fired
combined cycle operation, the highest predicted process contributions (concentrations due to emissions from
the Project only) at the maximum point of impact (which occurs on-site) and at sensitive receptor locations are
well below the respective PME AQSs for NO2 and PM10. The results also show that the minimum assumed
design stack height of 40m for the main (HRSG) stacks is likely to ensure the exhaust plume under gas-fired
operation will be adequately dispersed prior to coming to ground. Figure 7-4 to Figure 7-7 are contour plots of
annual and 1-hour mean NO2 concentrations for the OP1 scenarios for each plant configuration option.
115 | 278
Table 7-8 Maximum Ground Level Pollutant Concentrations – Combined Cycle (Natural Gas)
Scenario Pollutant Concentration (µg/m3) Maximum NO2
Concentrations Annual Mean 24-hr Mean 1-hr Mean
Air Quality Standard 100
No 24-hour Standard or Guideline Applicable
660
Scenario 1A1 (OP1) 3.7 (4%)(a) 12.8 (2%)
Scenario 1A2 (OP2) NA(b) 12.6 (2%)
Scenario 1B1 (OP1) 6.5 (6%) 20.9 (3%)
Scenario 1B2 (OP2) NA 22.0 (3%)
Maximum PM10 Concentrations Annual Mean 24-hr Mean 1-hr Mean
Air Quality Standard 80 340(c)
No 1-hour Standard or Guideline Applicable
Scenario 1A1 (OP1) 0.7 (<1%) 1.1 (<1%)
Scenario 1A2 (OP2) NA 1.2 (<1%%)
Scenario 1B1 (OP1) 1.3 (2%) 2.0 (1%)
Scenario 1B2 (OP2) NA 2.2 (1%)
(a) The value shown in the parentheses is the percentage of the PME AQS or IFC guideline the concentration represents. (b) NA means not applicable. The annual averaging period is not relevant to these scenarios because these operating conditions would
not prevail for an entire year. OP2 represents worse-case conditions which would occur during the winter months. (c) As the 90th percentile of 24-hour means.
The results show that Option B plant configuration gives rise to a greater impact than the Option A
configuration. This is mainly due to the additional turbine in the design of the Option B configuration, but also
relates to the lower NOx emission concentration assumed for the F-Class turbine compared to the E-Class
turbines. The ground level concentrations resulting from the plant are proportional to the NOx emission rate
(e.g. kg/hr) and the additional turbine (Option B) result in a greater mass emission rate from the plant and
higher predicted pollutant concentrations. The higher concentrations and geographical extent of impact for
Option B can be clearly seen in the figures above; as can the influence of the prevailing northerly wind
(particularly for the annual mean concentrations).
When considering the ambient conditions, the impacts for the winter or worse case operating conditions (OP2)
are very similar to those predicted for the operating conditions which are more representative of the emissions
associated with the summer or typical operating conditions (OP1).
The highest predicted annual mean NO2 concentration at the point of maximum impact is 6.5µg/m3 (6% of the
PME AQS), which is well below the standard. The concentration occurs for the Option B power plant
configuration at an on-site location, to the south of the turbine building (740450, 3072250).
Project number: 37446130 Dated: 09/11/2014 116 | 278 Revised:
Figure 7-4 Scenario 1A1 – Option A, Combined Cycle (OP1) – Annual Mean NO2 Concentrations (µg/m3)
117 | 278
Figure 7-5 Scenario 1A1 – Option A, Combined Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)
Project number: 37446130 Dated: 09/11/2014 118 | 278 Revised:
Figure 7-6 Scenario 1B1 – Option B, Combined Cycle (OP1) – Annual Mean NO2 Concentrations (µg/m3)
119 | 278
Figure 7-7 Scenario 1B1 – Option B, Combined Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)
Project number: 37446130 Dated: 09/11/2014 120 | 278 Revised:
The highest predicted 1-hour mean NO2 concentration is 20.9µg/m3 (3% of the PME AQS) and also occurs on-
site, in a similar location to the maximum annual mean (740600, 3072400). This concentration is also well
below the PME AQS. The location of the highest concentrations can be seen in the contour plots and that the
NO2 concentrations reduce rapidly with distance from the maximum point of impact.
The highest predicted annual mean NO2 concentration at a sensitive receptor location is 0.2µg/m3 (<1% of the
AQS), which occurs at the company housing compound for OP2 (plant configuration Option B). For 1-hour
mean NO2 concentrations, the highest predicted concentration at a sensitive receptor location is 11.9µg/m3 (2%
of the PME AQS), which occurs at the Central Control Building (CCB) under OP1 conditions for Option B and is
again well below the AQS.
For PM10 concentrations, the predicted concentrations are all well below those predicted for NO2. The highest
predicted concentrations at the point of maximum impact are a maximum of 2% of the PME AQS for all
averaging periods, plant configurations and ambient conditions (i.e. OP1 and OP2). At the sensitive receptor
locations, the highest predicted annual and 24-hour mean PM10 concentrations are considerably lower than the
concentration predicted at the maximum point of impact for both plant configurations
Summary of Results and Significance of Impact
For natural gas-fired, combined cycle operation, the results of the modelling presented in Table 7-8 and
Appendix G for the two plant configuration options and sets of operating conditions show that:
the highest predicted pollutant concentrations for either plant configuration or set of operating conditions oc-
cur on-site and are all well below the relevant PME AQS for NO2 and PM10;
the Option B plant configuration gives rise to higher predicted ground level concentrations at the point of
maximum impact and sensitive receptor locations than Option A for all averaging periods;
the highest predicted pollutant concentrations for the two sets of operating conditions (OP1 and OP2) are
very similar in magnitude and location at both the point of maximum impact and sensitive receptor locations
for both plant configuration options; generally slightly higher concentrations are predicted for OP1;
at the point of maximum impact, the significance of the impact of the emissions from the plant during com-
bined cycle operation is minor negative to negligible for NO2 concentrations and negligible for PM10 con-
centrations according to the significance criteria used in the assessment; and
at sensitive receptor locations, the significance of the impact of the emissions is considered to be negligible
for both NO2 and PM10 concentrations for both plant configurations and operating conditions.
Simple Cycle Operation Scenarios – Natural Gas 7.7.4A full set of results for the simple cycle operation scenarios is provided in Appendix H, with a summary
provided in Table 7-9. Dispersion modelling results for Option A and Option B plant configurations have been
presented for emissions from natural gas-firing and under both sets of ambient conditions (OP1 and OP2).
Similar to the results seen for combined cycle operation, the modelling results show that when considering both
the typical and worse case operating conditions for gas-fired simple cycle operation, the highest predicted
121 | 278
concentrations due to emissions from the Project remain below the respective PME AQSs for NO2 and PM10 at
both the maximum point of impact and sensitive receptor locations. This is despite the concentrations being
much greater (relatively speaking) for all averaging periods and locations than the respective concentrations
predicted for combined cycle operation.
It can be seen from Table 7-9 that the minimum assumed design stack height of 30m for the by-pass stacks is
likely to ensure the exhaust plume from the Project during gas-fired simple cycle operation will be adequately
dispersed prior to coming to ground.
Table 7-9 Maximum Ground Level Pollutant Concentrations – Simple Cycle (Natural Gas)
Scenario Pollutant Concentration (µg/m3)
Maximum NO2 Concentrations Annual Mean 24-hr Mean 1-hr Mean
Air Quality Standard 100
No 24-hour Standard or Guideline Applicable
660
Scenario 2A1 (OP1) 25.8 (26%)(a)(b) 97.3 (15%)
Scenario 2A2 (OP2) NA(c) 94.3 (14%)
Scenario 2B1 (OP1) 27.0 (27%) 105.0 (16%)
Scenario 2B2 (OP2) NA 101.1 (15%)
Maximum PM10 Concentrations Annual Mean 24-hr Mean 1-hr Mean
Air Quality Standard 80 340(d)
No 1-hour Standard or Guideline Applicable
Scenario 1A1 (OP1) 5.0 (6%) 11.8 (3%)
Scenario 1A2 (OP2) NA 10.8 (8%)
Scenario 1B1 (OP1) 5.3 (7%) 12.5 (4%)
Scenario 1B2 (OP2) NA 11.3 (3%)
(a) The value shown in the parentheses is the percentage of the PME AQS or IFC guideline the concentration represents. (b) The annual mean averaging period is not relevant to simple cycle operation because these operating conditions would
not occur for long periods of time; however, the annual mean concentration for OP1 has been presented for compari-son against the results for OP1 for combined cycle operation.
(c) NA means not applicable. The annual averaging period is not relevant to this scenario because these operating condi-tions would not prevail for an entire year. OP2 represents worse-case conditions which would occur during the winter months.
(d) As the 90th percentile of 24-hour means.
The annual mean concentrations are just over 25% of the relevant PME AQS for NO2; however, operation of the
Project in simple cycle mode would not occur for an entire year, therefore the AQS does not apply and the
figures are included in the table for comparative purposes only. The short-term concentrations are all less than
25% of the relevant AQS.
Figure 7-8 and Figure 7-9 are contour plots of 1-hour mean NO2 concentrations for the OP1 scenarios for each
plant configuration option.
Project number: 37446130 Dated: 09/11/2014 122 | 278 Revised:
Figure 7-8 Scenario 2A1 – Option A, Simple Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)
123 | 278
Figure 7-9 Scenario 2B1 – Option B, Simple Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)
Project number: 37446130 Dated: 09/11/2014 124 | 278 Revised:
The results in Table 7-9 and the contour plots show that the impact of the emissions arising from simple cycle
operations are (relatively speaking) much greater than predicted for combined cycle operation in the area of
maximum impact. However, the concentrations reduce more quickly with distance from this point than for
combined cycle operation, such that emissions during combined cycle operation affect a wider area (albeit at
very low levels relative to the AQSs). This will be primarily due to the lower stacks, but the different discharge
characteristics are also likely to influence this outcome to some extent.
Again, the results show that the Option B plant configuration gives rise to higher pollutant concentrations at the
point of maximum impact and at sensitive receptor locations compared with Option A. This is likely to be due to
the same reasons as presented for combined cycle operation (i.e. higher pollutant mass emissions rates for
Option B), despite the differing discharge conditions (e.g. temperature and flow rate). Once again, there is little
difference between the highest pollutant concentrations predicted for OP1 and OP2 for each of the plant
configuration options.
The highest predicted 1-hour mean NO2 concentration is 105.0µg/m3 (15% of the PME AQS), which occurs on-
site, to the immediate north of the turbine building (740600, 3072850). This concentration is also well below the
PME AQS.
The highest predicted 1-hour mean NO2 concentrations at a sensitive receptor location is 57.0µg/m3 (9% of the
PME AQS), which occurs at the CCB (Receptor 1) under OP1 conditions for Option B and is again well below
the AQS.
For PM10 concentrations, the predicted concentrations are again all well below those predicted for NO2,
although slightly higher than those predicted for combined cycle operation. The highest predicted
concentrations at the point of maximum impact are a maximum of 7% of the relevant PME AQS for both plant
configurations and sets of ambient conditions (i.e. OP1 and OP2). At the sensitive receptor locations, the
highest predicted 24-hour mean PM10 concentrations are less than 1% of the PME AQS for both configuration
Option A and Option B.
Summary of Results and Significance of Impact
For natural gas-fired, simple cycle operation, the results of the modelling presented in Table 7-9 and Appendix H for the two plant configuration options and operating conditions show that:
the highest predicted pollutant concentrations for either plant configuration or set of operating conditions are
all below the relevant PME AQS for NO2 and PM10;
the Option B plant configuration gives rise to higher predicted ground level concentrations at the point of
maximum impact and sensitive receptor locations than Option A for all averaging periods;
the highest predicted pollutant concentrations for the two sets of operating conditions (OP1 and OP2) are
very similar in magnitude and location at both the point of maximum impact and sensitive receptor locations,
with generally slightly higher concentrations predicted for OP1;
at the point of maximum impact, the significance of the impact of the emissions from the plant during simple
cycle operation is minor negative for NO2 concentrations and negligible for PM10 concentrations (annual
125 | 278
mean concentrations are not relevant to this scenario) according to the significance criteria used in the as-
sessment; and
at sensitive receptor locations, the significance of the impact of the emissions is minor negative at one loca-
tion (Receptor 1 – CCB) for 1-hour mean NO2 concentrations for Option B. For all other sensitive receptor
locations, the impact is considered to be negligible for both NO2 and PM10 concentrations for both plant
configurations and operating conditions.
Abnormal Operation Scenarios – Operation on Back-up Fuel (ASL) 7.7.5The full set of results for the modelling of NO2, SO2 and PM10 concentrations at the selected receptors for
operation of the plant on ASL are shown in Appendix I with a summary given in Table 7-10 below. Dispersion
modelling results for Option A and Option B plant configurations have been presented for emissions from ASL-
firing under typical ambient conditions (OP1).
The proposed GT/HRSGs have been assumed to be continuously operating at maximum load conditions across
the entire year (worse-case) utilising ASL as fuel in combined cycle mode and simple cycle mode. OP2
conditions have not been modelled for this scenario because the earlier modelling had showed that predicted
concentrations were generally slightly lower for OP2 operating conditions compared to OP1 conditions. SO2
concentrations have been predicted due to the 0.1% sulphur content of the ASL compared with the negligible
content in the natural gas and condensate.
Table 7-10 Maximum Ground Level Pollutant Concentrations – Arabian Super Light (ASL) Fuel
Scenario Pollutant Concentration (µg/m3) Maximum SO2
Concentrations Annual Mean 24-hr Mean 1-hr Mean 10-minute Mean
Air Quality Standard 80 365 730 500 3ACC 5.0 (6%) 11.7 (3%) 38.4 (5%) 65.8 (13%) 3ASC NA 25.3 (7%) 76.0 (10%) 184.3 (37%) 3BCC 6.5 (8%) 15.0 (4%) 41.9 (6%) 74.9 (15%) 3BSC NA 25.5 (7%) 130.0 (18%) 350.0 (70%)
Maximum NO2 Concentrations Annual Mean 1-hr Mean
Air Quality Standard 100
No 24-hour Standard or Guideline Applicable
660
No 10-min Standard or Guideline Applicable
3ACC 12.3 (12%) 43.7 (7%) 3ASC NA 109.2 (17%) 3BCC 18.6 (19%) 60.3 (9%) 3BSC NA 186.9 (28%)
Maximum PM10 Concentrations Annual Mean 24-hr Mean
Air Quality Standard 80 340
No 1-hour Standard or Guideline Applicable
No 10-min Standard or Guideline Applicable
3ACC 4.1 (5%) 9.5 (3%) 3ASC
8.08 (2%)
3BCC 4.3 (5%) 6.9 (2%) 3BSC
12.3 (4%)
Project number: 37446130 Dated: 09/11/2014 126 | 278 Revised:
These scenarios represent a short-term set of operating conditions which would only occur if the natural gas
supply was interrupted. As such, the annual averaging period is not relevant; however, the scenario has been
run for a full year of meteorological data to ensure the worse-case conditions are identified and annual mean
concentrations have been presented for combined cycle operation for comparative purposes.
The results of the modelling for emissions associated with ASL-fired operation show that the highest predicted
process contributions at the point of maximum impact are all below the respective PME AQS. As would be
expected from the higher mass emission rates for the turbines when operating on ASL, the highest predicted
process contributions at the point of maximum impact are markedly higher than those predicted for gas-fired
operation. The difference varies for pollutant and averaging period, with 1-hour and 24-hour means ranging
between 2 and 28% of the respective PME AQS, compared with 2 and 6% for gas-fired operation.
Figure 7-10 to Figure 7-15 are contours plots showing 1-hour mean NO2 concentrations and 1-hour and 24-hour
mean SO2 concentrations for plant configuration Option B (as the Option with the greater impact) for both
combined and simple cycle operations. Comparing the plots for ASL with the short-term plots for natural gas-
fired operation clearly illustrates the greater impact on local air quality of emissions associated with ASL-fired
operation. Similar to the results for gas-fired operation, the highest concentrations are predicted to occur on-
site, with concentrations reducing rapidly with distance from the point of maximum impact, such that highest
predicted concentrations at sensitive receptor locations are no higher than 10% of the relevant PME AQS for
both combined cycle and simple cycle operation (with the exception of the CCB, where the highest 1-hour mean
NO2 concentration is 13% of the PME AQS).
Overall, the results of the modelling presented in Table 7-10 and Appendix I show that when the plant is
operating on ASL (abnormal operating conditions), no exceedences of the PME AQSs for NO2, SO2 and PM10
concentrations (or IFC Guideline for SO2) are predicted to occur with the minimum design stacks (main and by-
pass). It is also important to remember that in order for the highest predicted short-term concentrations
presented in Table 7-10 and Appendix I to occur, the short-term operation of the plant on ASL would have to
coincide with the worse-case meteorological conditions; therefore, there is a very low probability of the
predicted maximum impacts occurring.
127 | 278
Figure 7-10 Scenario 3BCC – Option B, Combined Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)
Project number: 37446130 Dated: 09/11/2014 128 | 278 Revised:
Figure 7-11 Scenario 3BCC – Option B, Combined Cycle (OP1) – 1-hour Mean SO2 Concentrations (µg/m3)
129 | 278
Figure 7-12 Scenario 3BCC – Option B, Combined Cycle (OP1) – 24-hour Mean SO2 Concentrations (µg/m3)
Project number: 37446130 Dated: 09/11/2014 130 | 278 Revised:
Figure 7-13 Scenario 3BSC – Option B, Simple Cycle (OP1) – 1-hour Mean NO2 Concentrations (µg/m3)
131 | 278
Figure 7-14 Scenario 3BSC – Option B, Simple Cycle (OP1) – 1-hour Mean SO2 Concentrations (µg/m3)
Project number: 37446130 Dated: 09/11/2014 132 | 278 Revised:
Figure 7-15 Scenario 3BSC – Option B, Simple Cycle (OP1) – 24-hour Mean SO2 Concentrations (µg/m3)
133 | 278
Summary of Results and Significance of Impacts
For ASL-fired and both combined cycle and simple operation, the results of the modelling presented in Table
7-10 and Appendix I for the two plant configuration options show that for these short-term abnormal operating
conditions:
the highest predicted pollutant concentrations predicted for either plant configuration or set of operating
conditions are well below the relevant PME AQS for NO2 and PM10;
the Option B plant configuration gives rise to higher predicted ground level concentrations at the point of
maximum impact and sensitive receptor locations than Option A for all averaging periods;
at the point of maximum impact, the significance of the impact of the emissions from the plant during ASL-
fired operation is at worst (i.e. Option B, simple cycle) moderate negative for 1-hour mean NO2 concentra-
tions, minor negative to negligible for SO2 concentrations and negligible for PM10 concentrations accord-
ing to the significance criteria used in the assessment; and
at sensitive receptor locations, the significance of the impact of the NO2 and SO2 emissions is minor nega-tive at one location (Receptor 1) for 1-hour mean concentrations (Option A and B, simple cycle). For all
other sensitive receptor locations and all relevant averaging periods (e.g. 1-hour and 24-hour), the impact is
considered to be negligible for NO2, SO2 and PM10 concentrations for both plant configurations and opera-
tional modes.
Greenhouse Gas Emissions 7.7.6Natural gas and gas condensate will be used as the primary fuel for the Project. The power plant will also have
the capability of operating on ASL as a back-up if the gas supply is interrupted. The combustion of these fossil
fuels will produce CO2 emissions and, to a lesser extent, methane (CH4) emissions (as a result of incomplete
combustion). CO2 and methane emissions are accepted as contributing to global warming and known as
Greenhouse Gases (GHG). Calculation of global warming potential (GWP) allows comparison with other
sources and provides some context for the plant. GWP is measured in terms of equivalent emissions of CO2;
hence the GWP factor of CO2 is 1. CH4 has a GWP factor of 21 - i.e. an emission of 1kg of CH4 is defined as
having 21 times the GWP of an emission of 1kg of CO2.
The use of emission factors in combination with fuel consumption or power generated is a widely accepted
method for calculating GHG emissions from a range of industrial activities including power generation. GHG
emissions from the power plant have been calculated using the default Intergovernmental Panel on Climate
Change (IPCC) emission factors for CO2 and methane emissions from natural gas (IPCC 2006). The data
used for the calculation of annual CO2 emissions from the Project is presented in Table 7-11 below.
Project number: 37446130 Dated: 09/11/2014 134 | 278 Revised:
Table 7-11 Calculation of annual carbon dioxide emissions for the Additional Turbines
Parameter Option A Option B Units
Fuel Calorific Value 46.4 MJ/kg
Fuel Consumption (Total Plant)
72.56 72.80 t/h
72,560 72,800 kg/hour
3,370,049 3,381,196 MJ/hour
Average Operational Hours (per GT) 8,322 8,322 hours/year
Annual Fuel Consumption (for Plant) 28,046 28,138 TJ/year
IPCC Guidelines CO2 Emission Factor (2006) 56,100 56,100 kg CO2/TJ
IPCC Guidelines CH4 Emission Factor (2006) 1 1 kg CH4/TJ
Duba CCPP No.1 Annual CO2 Emissions 1,573,355 1,578,559 tCO2 per annum
Duba CCPP No.1 Annual CH4 Emissions 28 28 tCH4 per annum
Duba CCPP No.1 Annual GHG Emissions (GWP) 1,573,944 1,579,150 tCO2 equivalents per
annum
The data in Table 7-11 shows that assuming maximum load (OP1) for the proposed turbines over the two plant
configurations and operation of 8,322 hours per year, the annual GHG emissions would be similar for the two
plant configurations, with 1,573,944 tonnes CO2 equivalents being emitted per year for Option A and 1,579,150
being emitted for Option B. It is worth noting that the IPCC emission factors for natural gas liquids are higher
for both CO2 (64,200 kg CO2/TJ) and methane (3 kg CH4/TJ). If these emissions factors are used, the
corresponding tonnes of CO2 equivalents emitted per year are 1,802,291 for Option A and 1,808,252 for Option
B.
The GHG emissions are indicative at this point because the exact design of the plant has not been finalised
and therefore the emission data has been based on fuel consumption rates and assumed operating conditions
for turbines of the classes specified on the SEC scope of works. More accurate emission calculation will be
possible when the exact make and model of turbines has been finalised and the manufacturers can provide
emission data based on an anticipated annual operating profile.
135 | 278
Mitigation Measures and Residual Impacts 7.8 Construction Phase Mitigation Measures 7.8.1
The location of the construction area on the site benefits from a large separation distance to any sensitive
receptors and therefore, activities associated with the construction of the power plant to the plant have a
negligible impact off-site even with no specific dust control measures.
Nevertheless, mitigation measures representing best practice for construction sites should be employed during
the construction of the power plant to ensure dust emissions and construction traffic/plant exhaust emissions
are minimised to an extent where adverse impacts beyond the boundary of the site would be prevented. Dust
mitigation measures and monitoring provisions are included in Chapter 16: Framework Construction Environmental Management Plan. A full Construction Environmental Management Plan (CEMP) for the
project would be prepared in the basis of this framework. The mitigation measures which will be implemented
during construction include the following:
Measures to reduce dust arising through appropriate stockpile management;
Controlling dust arising through management of vehicle movements and speeds;
Appropriate materials handling (e.g. minimising drop heights);
Measures to reduce dust impacts when grading:
Correct use of cement batching:
Reducing exposed areas of open ground:
Preventing certain types of work in windy conditions;
Controls of excavation, piling and sandblasting works (where relevant); and
Minimising emissions from construction vehicles and plant through regular servicing and maintenance.
Construction Phase Residual Effects 7.8.2Residual impacts, should they occur, following the implementation of mitigation measures would be temporary,
of limited duration and negligible in impact.
Construction Phase Cumulative Effects 7.8.3The construction of the power plant and associated infrastructure will be the only construction works on the
larger area, therefore there will be no cumulative impacts beyond those associated with the power plant com-
plex; therefore, potential impacts would remain the same as above: temporary, of limited duration and negligi-
ble effect.
Operational Phase Mitigation Measures 7.8.4Operational Emissions
All combustion units and associated plant on-site will be subject to a regular inspection, servicing and mainte-
nance programme to ensure optimal efficiency and ensure, as far as practicable, all equipment is in good work-
ing order at all times, which will minimise pollutant emissions.
Project number: 37446130 Dated: 09/11/2014 136 | 278 Revised:
Emissions of NOx, SO2 and PM10 from the turbines at the facility will be continuously monitored. This monitor-
ing would provide data to confirm assumptions made for the dispersion modelling. This would accurately de-
termine pollutant concentrations in the emissions and provide an indication of any temporal variation in emis-
sions from the plant and further assist in verifying the modelling predictions and/or allow further, more accurate
modelling to be undertaken in the future to determine potential air quality impacts. This will be important if fur-
ther development of power generation capability is considered at the site.
The results of this assessment indicate that a minimum main stack height 60m will not lead to any exceedences
of the PME AQSs under normal operation. For the by-pass stacks, a minimum design stack height of 40m will
also ensure emissions are dispersed adequately and exceedences of short-term AQSs avoided during these
abnormal, short-term operating conditions.
Further assessment of the adequacy of the suggested minimum design stack heights may be necessary when
the design of the plant and the combustion units have been finalised and more accurate emission data is avail-
able; however, the fact that predicted maximum concentrations are all well below the relevant PME AQSs (and
IFC Guideline) provides confidence that impact of the power plant of either configuration on local air quality will
not be significant.
GHG Emissions
The use of natural gas has significant advantages over other fossil fuels:
Each unit of energy provided by the combustion of natural gas results in less global warming emissions than
other fossil fuels; and
Its energy content can be converted to electricity in efficiencies in the order of 60% within CCGT power sta-
tions. This is significantly more efficient than other combustion based electricity production technologies,
particularly heavy fuel oil or coal.
The combination of low emissions per unit of released energy in combination with efficient technologies for the
conversion into electricity and ready transportability of natural gas allows the production of electricity from natu-
ral gas with considerably less greenhouse gas emissions than other fossil fuels.
The plant will incorporate leading combustion technology and will be operated to a high standard to ensure the
efficiency of the combustion plant is maximised as far as practicable to prevent incomplete combustion and
minimise methane emissions from this source. The design will be to a high specification and the facilities will
be maintained to a standard which will control the unnecessary emission of natural gas (methane) from leaks.
Minimising fugitive releases is a priority for the site to control associated risks to safety and the loss of product.
Leak detection and repair procedures will be implemented at the site as part of the larger service and mainte-
nance programme for the plant, which will ensure that fugitive emissions of natural gas are prevented or mini-
mised as far as practicable.
137 | 278
Operational Phase Residual Effects 7.8.5The Scenarios modelled for this assessment have considered optimal design characteristics for the height of
the stacks for the Project to ensure the impact of the plant on local air quality is not significant. Therefore the
significance of the predicted concentrations referred to in the assessment of impacts above and presented in
Appendices G to I represent the residual effects of the emissions from the proposed power plant in the opera-
tional phase.
In addition to this, it should be noted that the emission data used in the assessment was based on assumptions
regarding the proposed combustion units at the site. Therefore, the predicted impacts must be considered
within this context. Every effort has been made to utilise representative input data and conservative assump-
tions to ensure the impacts have not been underestimated. Plant specific pollutant emission data would pro-
vide assistance with determining the level of conservatism and confirming the adequacy of the main and by-
pass stack heights.
Detailed emission data from the proposed combustion units would allow for more accurate modelling of the
proposed plant to be undertaken and provide more confidence of the accuracy of the predicted impacts. Nev-
ertheless, the modelling results show that even if the impact of the power plant operating normally were dou-
bled, it is still likely exceedences of the standards would occur for combined cycle or simple cycle operation.
Summary and Conclusions 7.9 Summary 7.9.1
The impact of the Project on local air quality has been assessed for both the construction and operational
phases. For the construction phase, a qualitative assessment was undertaken based on the likely construction
activities, location of sensitive receptors and local meteorological data to assess the potential air quality im-
pacts.
For the operation phase, a complex dispersion model (Breeze Aermod) was used to predict ground level con-
centrations of NO2, SO2 and PM10 at various receptor locations, including residential locations, in the local area
and surrounding region. Operating conditions representing the plant operating in combined cycle mode during
both typical and worse case ambient conditions were modelled for the assessment. Concentrations were pre-
dicted for the plant operating on both natural gas and ASL (the latter during emergency operation resulting from
gas supply interruption), as well as in simple cycle mode.
GHG emissions from the proposed power plant have been estimated using emission factors for CO2 and me-
thane published by the IPCC for GHG emissions.
Conclusions 7.9.2Construction Phase
The impact of dust and fine particle emissions from construction activities and emissions associated with con-
struction plant and traffic is likely to be of negligible due to the distances to off-site locations, absence of sensi-
Project number: 37446130 Dated: 09/11/2014 138 | 278 Revised:
tive receptors nearby in the surrounding area and the likely low level of traffic associated with construction
phase.
Operational Process Contribution
The results of the dispersion modelling show that under both representative and worse-case operating condi-
tions no exceedences of the PME AQSs for the pollutants considered in the assessment were predicted to oc-
cur as a result of emissions from the proposed power plant. This is the case at both the point of maximum im-
pact and at sensitive receptors considered in the assessment and for all relevant averaging periods, under both
operational modes (combined and simple cycle).
The significance of the residual air quality impacts associated with the proposed power plant when operating on
natural gas and in combined cycle mode range from minor negative to negligible at the point of maximum
impact, according to the significance criteria used. For all sensitive receptor locations the significance of the
impact of the emissions is negligible when operating on natural gas and in combined cycle mode.
In simple cycle mode and utilising natural gas, the residual impacts are minor negative at the point of maxi-
mum impact and minor negative (at one on-site receptor location) to negligible for sensitive receptor loca-
tions. The summary of significance of the residual impacts for natural gas fired operation applies to both power
plant configurations (Option A and Option B) and sets of ambient conditions (OP1 and OP2). Significance has
only been assigned to short-term impacts (e.g. 1-hour and 24-hour), as an annual averaging period is not rele-
vant to simple cycle operation.
As with the power plant operating in simple cycle mode, operation on ASL would also only be a short-term oc-
currence and therefore, only short-term mean pollutant concentrations were considered.. The residual impacts
for emissions from ASL firing in combined cycle mode are of minor negative to negligible significance at the
point of maximum impact and minor negative (one on-site receptor only. Option B configuration) to negligible
significance at sensitive receptor locations. For simple cycle operation, the significance of the impact was
moderate negative to negligible at the point of maximum impact and of minor negative (at one on-site recep-
tor location) to negligible significance at sensitive receptor locations. The summary of significance of the re-
sidual impacts for ASL-fired operation applies to both power plant configurations (Option A and Option B). Im-
pacts were not modelled for OP2 conditions as the earlier modelling had shown impacts to be similar to, but
lower than, OP1.
With respect to the two potential plant configuration options, Option B (4 x E-Class GTs) was predicted to have
a greater impact on local air quality compared to Option A for all scenarios considered. This is primarily due to
the lower total plant mass emission (e.g. kg/hr) of the pollutants considered for Option A. Although the F-Class
turbine is considerably larger than the E-Class, the modelling results indicate that its impact is lower than the
combined impact of two E-Class turbines.
In addition to compliance with the PME AQSs for all scenarios considered, the contribution of emissions from
the power plant (for both plant configuration options) during gas-fired operation would not contribute more than
25% to the attainment of the relevant PME AQS, which is in compliance with the relevant criteria in the IFC
139 | 278
EHS Guidelines for ensuring a project allows for additional, future sustainable development in the same air
shed.
GHG Emissions
The operation the turbines at DCCPP would generate GHG emissions of approximately 1,579,150 tCO2 equiva-
lents per year, based on the emission data used and assuming continuous operation of the GTs at the plant at
maximum load (8322 hours per year per GT).
Further Impact Assessment
Detailed design information is not currently available for the Project, only that the plant will be based on F-class
and/or E-Class turbines. Therefore, a number of assumptions were required for the dispersion modelling and
GHG emission estimations undertaken for this assessment. Where assumptions were required to develop the
necessary modelling input and emissions data, these were conservative so as ensure worse-case predictions
and prevent, as far as practicable, under estimation of potential air quality impacts or global warming potential.
Therefore, once more detail becomes available on plant design and technology, any proposed emissions miti-
gation and emissions data for the proposed DCCPP (i.e. when an EPC has been appointed for the project), this
should be compared against the input data used and assumptions made for this assessment to determine
whether further detailed assessment (e.g. re-modelling of emissions) is required to fully characterise the poten-
tial impacts of the plant on air quality and determine whether further mitigation measures are required.
Project number: 37446130 Dated: 09/11/2014 140 | 278 Revised:
Table 7-12: Impact and mitigation summary table for Air Quality
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Release of dust and PM10 associated with construction activities.
Low sensitivity Negligible Development of a CEMP which include the following measures (for example):
Measures to reduce dust arising through appropriate stockpile management;
Controlling dust arising through management of vehicle movements and speeds;
Measures to reduce dust impacts when grading; and
Minimising emissions from construction vehicles and plant through regular servicing and maintenance.
Negligible
Release of air pollutants associated with construction traffic Low sensitivity Negligible Negligible
Operational Phase
Emissions of NO2 associated with the plant operation.
Low to high sensitivity
Negligible to moderate adverse
All combustion units and associated plant on-site will subject to a regular inspection, servicing and maintenance programme to ensure optimal efficiency and ensure, as far as practicable, all equipment is in good working order at all times;
Emissions of NOx, SO2 and PM10 from the turbines at the facility will be continuously monitored;
Further assessment of the adequacy of the suggested minimum design stack heights may be necessary when the design of the plant and the combustion units have been finalised and more accurate emission data is avail-able; and
On-going ambient air monitoring NOx, SO2 and PM10 using a continuous air quality monitoring station should be considered to verify the current baseline and impact of the proposed power plant on the air shed.
Negligible to minor adverse
Emissions of SO2 associated with the plant operation.
Low to high sensitivity
Negligible to minor adverse
Negligible to minor adverse
Emissions of PM10 associated with the plant operation.
Low to high sensitivity Negligible Negligible
Green House Gas (GHG) Emissions
Low to high sensitivity
Minor to critical adverse
The plant will incorporate leading combustion technology and will be operated to a high standard to ensure the efficiency of the combustion plant is maximised as far as practicable to prevent incomplete combustion and minimise methane emissions from this source.
Negligible to moderate adverse
141 | 278
8 Environmental Noise
Introduction 8.1
The potential noise and vibration impacts associated with the construction and operation of the Project are
identified and discussed within this chapter. A review of the relevant standards, legislation and Project specific
noise requirements has been undertaken in order to establish the required criteria used to determine the noise
and vibration effects. The baseline environmental conditions within the vicinity of the power plant are
established and the effects of the construction and operational phases are analysed.
Figure 8-1 Proposed location of Duba combined Cycle Power Plant (6 km north of Almuwaylih – P3)
Where appropriate, during both construction and the operation of the Project, mitigation measures are
specified that will minimise any noise or vibration impact.
Relevant Standards and Legislation 8.2
Construction Phase Impacts 8.2.1The Kingdom of Saudi Arabia National Environmental Standard sets out General Construction maximum
permissible façade noise limits depending on the designated area type in Article VI – Noise from construction
activities. The permissible noise levels are presented in Table 8-1.
Project number: 37446130 Dated: 09/11/2014 142 | 278 Revised:
Table 8-1 General Construction maximum permissible facade noise levels
Area Classification Daytime LAeq, 12h dB 5 m
Evening LAeq, 12h dB 5 m
Night-time LAeq,12h dB 5 m
A, B, C 75 65 45
D 80 80 80
The area classification is as follows:
A: Quiet areas – These areas are designated quiet areas as they hold value in terms of being places of
worship, important tourist attractions, recreational park land and those areas surrounding hospitals,
schools and noise sensitive natural habitats.
B: Sensitive – Areas designated in this category will typically be dominated by residential properties
(including hostels and hotels) and may range from sparse population densities to suburban districts of
cities.
C: Mixed – This designation applies to mixed areas often within cities where there is a mix of residential
and commercial activities. This designation will also apply to retail and financial districts.
D: Non-Sensitive – The final classification of district is a predominantly industrial area where there are few
residential properties and commercial premises. This classification also applies to industrial cities and land
that is generally unpopulated.
It should be noted that the table as taken from the Kingdom of Saudi Arabia National Environmental Standard
indicates LAeq,12h indices for the evening as well as the night time periods. This is generally a day time index
and the evening and night times are usually measured in terms LAeq,4h and LAeq,8h respectively. The 24
hour day is split into three segments; 0700-1800 for the day time period, 1800-2200 for the evening period, and
2200-0700 for the night time period. Our assessment is based on 12 hour days, 4 hour evenings and 8 hour
nights.
In the absence of any national environmental noise calculation methodology guidance with respect to Saudi
Arabia and where detailed information is available, it is appropriate to estimate the levels of noise and vibration
at local noise sensitive receptors in accordance with British Standard (BS) 5228:2009 Code of practice for
noise and vibration control on construction and open sites – Part 1: Noise.
This document details a methodology for estimating construction noise levels from a site based on the type of
plant, usage, and distance to receiver, barriers and ground conditions. The assessment is carried out for
multiple sources and multiple receivers.
Operational Phase Impacts 8.2.2Criteria for permitted free field external noise limits for given activities are provided within the Kingdom of Saudi
Arabia National Environmental Standards in Article IV – Community noise and presented in Table 8-2.
143 | 278
Table 8-2 Permitted free-field external noise limits for community noise, measured at any noise sensitive property within the appropriate area designation
Designation Daytime LAeq, T dB Evening LAeq, T dB Night-time LAeq, T dB
A 50 45 40
B 55 50 45
C 60 55 50 T- This is understood to be 12 hours for Day, 4 hours for Evening and 8 hours for Night time periods.
The area designations are as follows:
A: Sensitive – These areas are designated quiet areas as they hold value in terms of them being places of
worship, important tourist attractions, recreational park land and those areas surrounding hospitals,
schools and noise sensitive natural habitats.
B: Mixed – Areas designated in this category will typically be dominated by residential properties (including
hostels and hotels) and may range from sparse population densities to suburban districts of cities.
C: Non-Sensitive – This designation applies to mixed areas often within cities where there is a mix of
residential and commercial activities. This designation will also apply to retail and financial districts.
In addition criteria for noise from industrial units in areas set aside primarily for industrial activities are given in
Article V – Noise from industrial units in areas set aside primarily for industrial facilities and presented in
Table 8-3.
Table 8-3 Maximum permissible free-field noise levels
Site Daytime LAeq, T dB Evening LAeq, T dB Night-time LAeq, T dB
A1 55 50 45
A2 55 50 45
A3 55 50 45
A4 65 60 50
A5 75 65 55 T- This is understood to be 12 hours for Day, 4 hours for Evening and 8 hours for Night time periods.
The site classification is as follows:
A1 – Retail refers to areas that are entirely dominated by retail, dining and recreational properties.
A2 – Warehousing refers to areas where units predominantly store products or goods for distribution and
there are no or very limited process activities.
Project number: 37446130 Dated: 09/11/2014 144 | 278 Revised:
A3 – Light industrial refers to those areas which may be mixed with or adjacent to residential properties
where minor manufacturing processes take place.
A4 – Medium density industrial areas are those when a range of manufacturing processes including
combustion take place on small to medium size sites and there is an absence of residential properties.
A5 – High density industrial refers to designated industrial cities and complexes where large scale
manufacturing, refining and petrochemical processes exist. Cement manufacture is specifically included.
In addition to the Local Environmental Standards, the IFC World Bank General EHS Guidelines are presented
in Table 8-4.
Table 8-4 Noise level guidelines
Receptor Daytime 0700-2200 LAeq, 1h dB
Nigh-time 2200-0700 LAeq, 1h dB
Residential; institutional; educational 55 45
Industrial; commercial 70 70
In addition to the absolute standards provided in Table 8-4 above, it is also a requirement of the IFC that noise
impacts should not result in a maximum increase in background levels of 3dB at the nearest receptor location
off-site.
Finally, the SEC technical specifications provided sets out the noise level criteria for both indoor and outdoor
equipment as presented in Table 8-5.
Table 8-5 SEC Noise Requirements
Location Measurement Location Sound Pressure Level dB(A)
From any equipment or plant item 1 m from the source 85
Steam turbine 1 m from the steam turbine or its
acoustical enclosure and 1.2 m above ground level of personnel platforms
85
Outside diesel generator buildings for diesel generators and pumps 1 m from equipment 85
Site boundary (Day-time) 1 m outside boundary line and 1.2 m above ground level 70
Site boundary (Night-time) 1 m outside boundary line and 1.2 m above ground level 55
145 | 278
Methodology 8.3
This section describes the different assumptions and methods used to construct each sound propagation
models necessary to evaluate impacts in sensible areas during both construction and operating phases.
Construction Phase 8.3.1Construction noise has been assessed using the methodology set out in BS 5228 Part 1. It is assumed that the
main construction phases are as follows:
Site preparation;
Civil works;
Supply and installation of plant and equipment; and
MEP works.
Noise predictions have been undertaken utilising the Datakustic CadnaA noise modelling software and based
on the source noise levels presented in Table 8-6, which are in accordance with BS5228.
Table 8-6 Construction Noise Emission Data
Equipment
Sound Pressure Level, LAeq dB @10m
Site Preparation
Civil Works
Plant and Equipment
MEP Works
Dozer (41 t) 80 80 - - Tracked Excavator (40t) 79 79 - - Wheeled Loader 80 80 - - Articulated dump truck (tipping fill) 81 - - - Lorry 80 80 80 80 Vibratory Roller 74 74 - - Large Rotary Bored piling rig 83 - - - Cement Mixer truck - 75 - - Tracked Mobile Crane - 77 77 - Lifting Platform - - 67 67 Tower Crane - 77 77 77 Power for site cabins 66 66 66 66 Water pump (diesel) 68 68 - - Angle Grinder - 80 80 -
The noise predictions are based on the following assumptions:
There is one of each item of equipment on the site;
The ground is hard and reflective;
The works are spread mainly across the turbine and HRSG sectors.
Project number: 37446130 Dated: 09/11/2014 146 | 278 Revised:
Operational Noise 8.3.2Operational noise levels have been assessed using the methodology set out in ISO 9613:2. This methodology
uses the following parameters to estimate environmental noise levels:
Noise source sound power level;
Geometric spreading;
Screening and ground effect;
Air absorption (temperature and humidity).
The ISO standard also considers downward winds: in other words, noises are pushed toward sensible areas
and favourable sound propagation weather conditions are therefore considered. This worst case scenario is
used to evaluate if mitigation measures are necessary.
The main noise sources are related to the gas turbines and other associated systems. There are 6 turbines
proposed (4 gas turbines and 2 steam turbines). Noise models for the steady state base load were developed
and the following scenario was considered:
Combined cycle for Turbines – Proposed plant operation;
There was no noise data available for the proposed units at the time of the report, therefore historic data from
previous work with SEC was utilised and can be seen in Table 8-7, Table 8-8 and Table 8-9.
Figure 8-2 Screen shot of the developed CadnaA 3D model
No cooling system is mentioned in this report since the power plant is working under an open loop system
(sea water). Therefore a water pump was placed as described in the power plant general layout.
147 | 278
Table 8-7 Sound Power Levels of the Gas Turbine Generator
Section
Sound Power Level
Overall
dB(A)
Octave Band Centre Frequencies Hz, dB
63 125 250 500 1000 2000 4000 8000
Inlet Ducting (including filter house) 88 101 94 93 82 74 82 54 26 Inlet Filter Face 99 111 104 100 95 93 90 84 76 Accessory Module 103 107 101 98 97 97 99 93 88 Inlet Plenum 103 93 90 92 91 92 101 92 80 Turbine Compartment 113 115 110 108 106 104 109 104 99 GT Exhaust Diffuser Enclosure 112 121 115 111 108 104 104 103 100 GT Load Compartment 105 109 109 104 99 97 100 97 90 GT Generator 107 105 105 101 104 102 101 96 87 Cooling Water Module 107 99 113 105 104 104 94 89 91
Table 8-8 Sound Power Levels for the Steam Turbine package
Section
Sound Power Level
Overall
dB(A)
Octave Band Centre Frequencies Hz, dB
63 125 250 500 1000 2000 4000 8000
STG Summary 107 112 108 107 106 101 96 94 93 STG Generator 108 106 105 102 104 103 102 97 88 95 kV transformer (fans on) 75 71 72 72 72 70 68 65 60
Table 8-9 Sound Power Levels for the HRSG
Section
Sound Power Level
Overall
dB(A)
Octave Band Centre Frequencies Hz, dB
63 125 250 500 1000 2000 4000 8000
HRSG Wall 96 84 89 92 88 83 79 55 20 Stack Wall 91 84 88 86 79 66 71 29 20 Stack Exit (90-degrees) 95 91 92 77 75 80 70 46 24 Salt water pump 104 97 97 98 99 98 98 94 89
The sound pressure levels for the gas turbine step-up transformer, steam turbine step-up transformer as well
as the auxiliary transformer were assumed to have a diffuse sound field pressure of 75 dB(A). Furthermore
85 dB(A) at 1 m was utilized for the sound pressure levels of all pumps used at the plant (except for the salt
water pump).
In addition it has been assumed that the building fabric of all buildings including Gas Turbine Generators
(GTG), Heat Recovery Steam Generators (HRSG), Steam Turbine Generator (STG) enclosures and pump
enclosures will provide a minimum weighted sound reduction index of 30 dB Rw. This is typically achieved
using an aluminium cladding panel.
Project number: 37446130 Dated: 09/11/2014 148 | 278 Revised:
The stated assumptions and noise data were used to create a noise model for the steady state base load,
however this model did not include:
Start-up/shut down of the power plant;
Commissioning phase;
Failure conditions;
Emergency conditions; and
Other abnormal operating conditions.
The predicted results from the noise model are given in Section 8.5
Vibration 8.3.3Operational vibration can be an issue with power station developments within a 200 m radius of vibration-
sensitive properties but extremely unlikely beyond a distance of 500 m. Site visits and a review of the
topographical drawings have indicated that the nearest affected premises are beyond this zone of influence (a
fish farm is located approximately 1 km north-west of the main generators – P2 on Figure 8-1). As such,
operational vibration impacts have not been assessed. Any source of vibration significant enough to be
perceived at or beyond the boundary would be potentially destructive close to the source and it is therefore not
considered that this condition would be allowed to occur.
Existing Baseline Conditions 8.4
In order to fully quantify the existing baseline noise levels, measurements were under-taken at three
measurement locations around the Project site. The measurement locations are presented in Figure 8-3 and
described in Table 8-10.
149 | 278
Figure 8-3 Noise measurement locations
Table 8-10 Description of noise measurement locations
Location Description
P1 NE corner of plant site. The site is situated approximately 30 metres from the highway and 5 metres from an ungraded track.
The highway traffic was light but includes a high proportion of HGVs. A single car passed close by on the ungraded track. Wind was light and steady throughout the measurement period.
P2 NW of the site near to disused industrial facility. Fish farm about 500 m further north.
The site is situated quite close to the sea; However, the sea conditions were calm so unlikely to have affected noise levels significantly. No real source of noise at this location with the excep-tion of the distant road and some very infrequent off-road traffic in the area.
P3 Northern edge of Almuwaylih (the closest town) near to sports field and mosque. A paved road and unpaved road were also adjacent with very infrequent traffic movements (perhaps two or three vehicles passed nearby). However, there was some concrete mixing and loading activi-ties taking place nearby which was quite consistently noisy. Construction stopped during the night period.
Project number: 37446130 Dated: 09/11/2014 150 | 278 Revised:
Figure 8-4 Noise measurement location P1 – Future site location – 30 m from road
Figure 8-5 Noise measurement location P2 – Fish farm
Figure 8-6 Noise measurement location P3 (Almuwaylih sports field and mosque)
151 | 278
The noise survey was undertaken between the 20th of May and the 24th of May 2014. A total of ten, fifteen
minute measurements were completed and were averaged at each location (day and night). The results of the
noise survey are presented in Table 8-11. Please see the acronym table for a short explanation of each sound
index.
Table 8-11 Measured baseline noise data
Position LAeq Lmax LA10 LA90
Day Night Day Night Day Night Day Night
P1 57.7 53.8 72.8 71.4 61.2 54.0 39.0 20.7 P2 52.8 35.5 71.0 41.2 49.0 36.7 35.0 33.9 P3 52.0 37.3 68.6 49.6 52.2 41.2 42.0 27.9
It should be noted that during the survey period winds conditions were acceptable and therefore are
considered to be representative of the typical noise environment.
Assessment of Impacts 8.5
In this section the different construction and operational phases of the Project will be studied to detect potential
noise overshoot and recommend mitigation measures where necessary.
Sensitive Receptors 8.5.1The Project site is located approximately 6 km to the north of Almuwaylih. There are currently no noise
sensitive receptors within the Project site, although the fish farm is located approximately 1 km away. In the
future however, noise sensitive receptors will be introduced to the Project site and immediate surrounds as part
of the Project, which include an administrative building and housing compound. Evaluation points renamed with
a “b” are in the same area as the baseline measurements, but are directly positioned at the sensitive receptor
(closest residence for example).
Table 8-12 Noise Sensitive Receptor Locations
Noise Sensitive Receptor Location
P0 Administrative Building 27°45'27.17"N, 35°27'07.06"E
P1b Company housing compound 27°45'58.40"N, 35°26'52.12"E
P2b Fish Farm 27°46'06.90"N, 35°26'02.30"E
P3 Town of Almuwaylih (mosque and sports centre) 27°42'14.73"N, 35°28'34.95"E
The noise sensitive receptors in the vicinity of the proposed works site are shown in Figure 8-7.
Project number: 37446130 Dated: 09/11/2014 152 | 278 Revised:
Figure 8-7 Potential noise sensitive areas
Construction Phase Impacts 8.5.2The construction phase impact assessment has been undertaken based on the principles described in
Section 8.3.1. A noise map has been created for two worst case construction stage scenarios based on the
levels provided for the site preparation and civil works stage, which demonstrate the impacts to existing
sensitive receptors.
The predicted noise levels for the two construction phases as shown in Table 8-13.
Table 8-13 Noise impact for construction phases
Evaluation point
Area Classification
Recommended maximum night time noise levels Site preparation Civil work
P2b Fish Farm B 45 39 39
P3 Almuwaylih village A 45 13 11
Simulations indicate that the noise levels will be negligible in Almuwaylih village given the distance between the
plant and Almuwaylih, which causes any noise to dissipate before reaching any receptor in that location.
The fish farm, being closer to the Project site, will receive a greater noise contribution. The modelling however
predicts that the noise levels will be in conformity with the applicable noise regulations.
153 | 278
Table 8-14 Construction Noise –Site preparation noise map
1250 m
0
Project number: 37446130 Dated: 09/11/2014 154 | 278 Revised:
Table 8-15 Construction Noise –Civil works noise map
1200 m
0
155 | 278
Operational Phase Impacts 8.5.3The operational phase assessment has been undertaken based on the principles described in Section 8.3.2
and the results are presented in the form of noise maps in Figure 8-8.
Table 8-16 Noise impact for operational phases
Evaluation point Area Classification
Noise Limit (Night-time)
dB LAeq, T Combined
cycle Single cycle
P0 (Admin. Building) C 50 49 47
P1b (Housing Compound) B 45 46 43
P2b (Fish farm) B 45 45 43
P3 (Almuwaylih) A 40 23 20
The predicted noise levels mainly meet the IFC requirements set out in Table 8-4 and are typical for major
industrial developments. There is only one sensitive receptor that is exceeding IFC standards by 1dBA.
Furthermore the results indicate that the predicted sound pressure levels will meet the PME and SEC daytime
and night time criteria to the exception of the company housing compound. Night time levels are 1 dBA higher
than the regulations recommends for this sensitive receptor.
Noise levels generated by Duba power plant will not be heard in Almuwaylih village.
The Administrative building being mainly for work purposes has a greater sound limit. The noise level
simulated for both operational phase comply with Saudi Arabia noise regulations. Nevertheless, noise levels
are sufficiently high to consider this aspect when constructing the outer envelope of the administrative building.
A good working environment where concentration is required has noise levels of approximately 45 dBA.
Therefore, the outer envelope of the building should provide sufficient sound insulation to meet that criterion.
Project number: 37446130 Dated: 09/11/2014 156 | 278 Revised:
Figure 8-8 Operational Noise –Combined Cycle Noise Map
1350 m
0
157 | 278
Mitigation Measures, Residual/Cumulative Effects 8.6
Construction Phase Mitigation Measures 8.6.1The predicted construction noise levels during the construction phase are below the criteria therefore no
additional mitigation measures are required.
It is however recommended to follow ‘As Low as Reasonably Practicable’ methods of noise and vibration
control such as:
It is recommended that regular noise monitoring is undertaken within close proximity of noise sensitive
locations, if future works include activities which are known to cause significant levels of noise;
In order to control the duration of noise and vibration from the construction activities, no noise from the
works will be audible at the boundary of any occupied residential property outside the hours of:
Saturday to Thursday 07:00 - 19:00; and
No working on Friday or Public Holidays.
If noise exceeds the required standards the use of acoustic screens or noise attenuation measures will be
implemented;
Stationary machinery such as generators must be kept in enclosed structures during the night;
Items of plant on site operating intermittently will be shut down in the intervening periods between use;
Electrically powered plant should be preferred, where practicable, to mechanically powered alternatives.
All mechanically powered plant should be fitted with suitable silencers;
Use of vibratory hammer for piling rather than impact hammer to reduce noise levels;
High frequency vibrator hammer to be used rather than low frequency based on the type of piling;
Moveable acoustic sound barriers for the hammer and piling equipment to be provided near to receptors
such as the adjacent staff accommodation and other facilities;
Delivery vehicles should be prohibited from waiting within or near the construction site with their engines
running. The movement of heavy vehicles during the night will be avoided wherever practical;
Noisy equipment and machinery will be replaced with less noisy alternatives or provide equipment that is
specifically designed with noise inhibitors, such as generators and compressors with silencers and muffled
jackhammers; and
It is recommended that a grievance procedure be implemented by the EPC Contractor. This will provide a
mechanism for adjacent staff or nearby residents to make representations if significant noise disturbance
occurs.
Project number: 37446130 Dated: 09/11/2014 158 | 278 Revised:
Construction Phase Residual Effects 8.6.2Given the nature of the locality of sensitive receptors and the baseline noise survey, it is anticipated that the
overall residual impact for construction works will be temporary and of negligible significance.
Construction Phase Cumulative Effects 8.6.3Construction noise has been assessed within the construction noise section above. It is considered that the
cumulative effects of these noise sources are negligible on account of the temporary nature of construction
activities and the considerable distance of the nearest off-site noise sensitive location.
Operational Phase Mitigation Measures 8.6.4Using historical noise data for the plant equipment, the predicted noise emissions from the Duba Power Plant
during the operational phase have a negligible effect on the noise environment. However, the predicted results
are exceeding the night time noise criteria at the company housing compound.
Therefore, the following noise mitigation measures are recommended:
Move the equipment further into the site
Use plant equipment with lower noise levels
Use screens/ enclosures or an acoustic berm to achieve the recommended limits
Ensure that the buildings housing the equipment provide adequate sound insulation
It is also important to note that there are also occupational noise standards that need to be maintained as part
of the Health and Safety of the employees at the facility. It is therefore important that noise levels in working
areas are limited to less than 85 dB(A) at 1 m from any noise generating equipment.
It is recommended that as part of the Operational Management Plan regular noise monitoring is undertaken at
the site boundary to show compliance with PME noise standards. It is further recommended that a full
occupational noise survey is undertaken in the interests of the health and safety of the site employees.
Operational Phase Residual Effects 8.6.5Due to the distance of the power plant to the nearest town, it is expected that the overall impact of the residual
operational noise has a negligible significance.
It is anticipated that the overall residual impact for operational works at the accommodation building will be
1dBA above the night time criteria. However, this is in accordance with IFC guidelines and is typical for major
industrial processes.
Operational Phase Cumulative Effects 8.6.6Operational noise has been assessed within the section above. The assessment has indicated that the noise
from the different plant equipment will elevate the existing noise climate. However, it is considered that the
cumulative effects of these noise sources are minor due to the relative importance of the nearest noise
159 | 278
sensitive receptor. Housing compound should be constructed according the site proximity and the town
Almuwaylih should not be impacted by the power plant noise contribution.
There is the potential for further developments in the area, but there is insufficient information to enable an
assessment at this time.
Summary and Conclusions 8.7
An assessment of the potential noise and vibration effects for the Proect during both construction and operation
has been undertaken.
The construction phase noise impacts have been predicted based upon noise data contained in BS5228. The
results of the assessment show that noise levels are within the recommended limits and recommendations for
the on-going monitoring of the noise levels associated with construction activity have been made.
The operational phase noise impacts have been predicted based upon historical noise data for the intended
equipment. The results of the assessment are within the recommended limits for most sensitive areas;
however, they exceed the night time criteria for the company housing compound. Given that the nearest town is
6 km to the south of the site, it is expected that the overall residual operation noise will have a negligible
significance at this location (Almuwaylih).
Project number: 37446130 Dated: 09/11/2014 160 | 278 Revised:
Table 8-17 Impact and mitigation summary table for Environmental Noise
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Noise associated with construction activities. Low sensitivity Negligible
No mitigation measures are required but it is however recommended to follow ‘As Low As Reasonably Practicable’ methods of noise and vibration control such as:
It is recommended that regular noise monitoring is undertaken within close proximity of noise sensitive locations, if future works include activities which are known to cause significant levels of noise;
In order to control the duration of noise and vibration from the construction activities, no noise from the works will be audible at the boundary of any occupied residential property outside the hours of:
- Saturday to Thursday 07:00 - 19:00; and
- No working on Friday or Public Holidays.
If noise exceeds the required standards the use of acoustic screens or noise attenuation measures will be implemented.
Negligible
Operational Phase
Noise from the plant operation. Low to high sensitivity Negligible
Development of an OEMP which include the following measures (for example):
Move the equipment further into the site;
Use plant equipment with lower noise levels;
Use screens / enclosures to achieve the recommended limits;
Ensure that the buildings housing the equipment provide adequate sound insulation;
Regular noise monitoring shall be undertaken at the site boundary to show compliance with PME noise standards; and
A full occupational noise survey shall be undertaken in the interests of the health and safety of the site employees.
Negligible
161 | 278
9 Soil, Groundwater and Contamination
Introduction 9.1
This chapter considers the soil and geological conditions on site together with an appreciation of contamination
issues. The aim is to identify any potential soil and groundwater impacts associated with the development of
the Project.
The assessment considers potential contamination issues associated with both the construction and
operational phases of the development and provides appropriate pollution control best practice measures.
These measures are summarised below and set out in full in Chapter 16: Framework Construction
Environmental Management Plan and Chapter 17: Framework Operational Environmental Management Plan.
Relevant Standards and Legislation 9.2
National Legislation and Standards 9.2.1
The General Environmental Regulations (2001) specifies the following requirements in regards to protecting
soil and groundwater from environmental harm:
Article 13.2:
‘To preserve the soil and land and limit is deterioration or contamination’.
Article 13.2.1:
‘To take all precautions required to prevent and control contamination and degradation of soil and land,
remediate degraded and contaminated soil and use best available means and technologies for this purpose in
accordance with the standards and criteria’.
IFC Standards and International Best Practice 9.2.2Sector-specific guidance documents on pollution prevention good practices produced by the IFC are relevant,
which includes:
IFC ‘EHS Guidelines for Thermal Power Plants’ (2008); and
IFC ‘Environmental Health and Safety (EHS) Guidelines: Contaminated Land’ (2007).
This assessment also considers the likely impacts upon soils and geology as a result of Project activities in
relation to the updated IFC Performance Standards; namely:
Performance Standard 3: Resource Efficiency and Pollution Prevention.
Project number: 37446130 Dated: 09/11/2014 162 | 278 Revised:
For reference, the International Finance Corporation (IFC, 2007) defines land as being contaminated when ‘it
contains hazardous materials or oil concentrations above background or naturally occurring levels’. Further,
‘contaminated lands may involve surficial soils or subsurface soils that, through leaching and transport may
affect groundwater, surface water, and adjacent sites’.
Additional sector-specific guidance documents on pollution prevention best practice guidance developed by the
UK Government and others have been used to inform the assessment, where relevant. These include:
Integrated Pollution Prevention and Control (IPPC) Technical Guidance Note S3 1.01 ‘Combustion
Processes Supplementary Guidance Note’;
The Environment Agency (UK) Pollution Prevention Guideline 6 (PPG6) Working at Construction and
Demolition Sites (2003);
The Environment Agency (UK) Pollution Prevention Guideline 11 (PPG11) Preventing Pollution on
Industrial Sites (2003);
The Environment Agency (UK) Pollution Prevention Guideline 21 (PPG21) Pollution Incident Response
Planning (2003); and
Environmental Protection Agency (US) Office of Compliance (1997) ‘Sector Notebook project - Profile of
Fossil Fuel Electric Power Generation Industry’.
Methodology 9.3
The methodology used to conduct this assessment is described below:
Desktop Information Review 9.3.1
A review of available information was made in order to provide a background to the geological and
hydrogeological (groundwater) conditions within the region and the study site.
Site Visit 9.3.2
A Phase I (non-intrusive) Assessment was undertaken to provide an initial appreciation of existing ground
conditions and contamination status of the site. The Phase I Assessment comprised visiting certain areas of the
site and making a visual assessment with regards to, inter alia:
Potential soil and surface water contamination;
Bulk chemical storage, focusing on bulk above and below ground storage tanks and associated piping
equipment;
Hazardous and non-hazardous wastes;
Signs of groundwater abstraction;
163 | 278
Polychlorinated biphenyls (PCBs) and the presence of equipment with the potential to contain PCBs;
The presence of ozone depleting substances, e.g. chlorofluorocarbons; and,
The presence of asbestos containing materials.
Current best practice guidance in Western Europe and the USA advocates the use of a conceptual risk
assessment model to establish the potential links between a hazardous source and a sensitive receptor via an
exposure pathway, as illustrated by Table 9-1 below.
The concept behind this approach is that, without each of the three fundamental elements (source, pathway,
and receptor) there can be no potential contamination risk. Thus, the presence of a contamination hazard at a
particular site does not necessarily imply the existence of associated risks.
Table 9-1 Contamination Risk Assessment
The IFC (2007) is also instructive in providing a useful definition of ‘exposure pathway(s)’; as ‘A combination of
the route of migration of the contaminant from its point of release (e.g. leaching into potable groundwater) and
exposure routes (e.g. ingestion, transdermal absorption), which would allow receptor(s) to come into actual
contact with contaminants.’
Existing Baseline Conditions 9.4
The Project site lies along the coast in an area classified throughout as coastal plain and lowlands, running
almost the entire length of the Red Sea. The plains’ surfaces comprise of raised Quartenary coralline reef, up to
30m above sea level, but these are observed to go up to 300m asl. Inland from these plains, the pediments and
promontories lead to the adjacent mountains.
The soil of the Project area is characterized by strongly saline, highly permeable soils with high concentration of
salts in the surface layer, forming a dry crust. This type of soil is typical of low lying coastal sands where the
water table is high, often within 50 cm of the surface, more or less throughout the year.
The soils of this coastal area are classed under the Calciorthid-Camborthid soil association, mainly found on
gently undulating plains along the western edge of Saudi Arabia. This soil association comprises 50 percent
Calciorthids, 30 percent Camborthids and 20 percent other soil types.
Project number: 37446130 Dated: 09/11/2014 164 | 278 Revised:
Local Seismicity 9.4.1
The site is located within the seismically active Arabian tectonic plate, which for the last twenty million years
has been colliding with the Eurasian plate. The western boundary of the Arabian plate is known as a ‘transform
fault zone’ where the two plates grind past each other, and include the Dead Sea Zone (Ref. NASA Johnson
Space Centre); whilst rifts of the Red Sea and Gulf of Aden constitute the southern boundary, and the Zagros
and Makran mountain ranges mark the present collision zone. Figure 9-1 below provides a graphical
representation of the main plate tectonic features within the Kingdom.
Figure 9-1 Plate Tectonics of Saudi Arabia
[Ref. Saudi Aramco World – Volcanic Arabia (www.saudiaramcoworld.com/issue/200602/volcanic.arabia.htm)]
As per the Saudi Geological Survey, National Centre for Earthquakes and Volcanoes, the most active area for
seismic activity within the Kingdom is along the Gulf of Aqaba (known as the Dead Sea transform fault), and is
an area where large and damaging earthquakes can occur quite regularly, with the last major event taking
place in 1995 (the ‘Haql Earthquake’ which had a magnitude of 7.3 and which caused significant damage on
both sides of the Gulf). Earthquakes of magnitude 6 are common along the spreading axis of the Red Sea but
they are generally not felt onshore and appear to pose little risk.
Whilst the wider area is regarded as seismically active, it is thought that the general environs of the proposed
facility is located within a relatively quiet zone, typically without locally significant seismicity. Indeed, as the
165 | 278
Saudi Geological Survey pronounce, the ‘risk of damage from earthquakes is quite low over most of Saudi
Arabia, the main areas of risk being near the Gulf of Aqaba and Jizan, with lower risk in the west near the Red
Sea and in some of the harrats (Saudi Geological Society).’
The caution is that, whilst major advances have been made in the prediction of the location and magnitudes of
earthquakes and other acts of nature, the field remains an inexact science and further clarification should be
sought as required.
Groundwater 9.4.2
The Project site is coastal with an elevation of approximately 19m above sea level. The groundwater at the site
is therefore expected to be shallow and strongly influenced by the marine environment. Freshwater runoff from
the mountainous area inland is also likely to have an influence. Groundwater is expected therefore expected to
be brackish.
Existing Contamination 9.4.3
No evidence of existing soil contamination was observed on site during the site visit on the 5th May 2014. A
decommissioned industrial facility is present approximately 500m to the north of the Project site which is a
potential source of contamination.
Sensitive Receptors 9.5
The soil strata within and adjoining the site and groundwater are considered as sensitive receptors for the
purposes of this assessment, which may be subject to impacts, including the mobilisation of existing
contamination during construction and spillages of hazardous materials during construction and operation.
During construction the most critical sensitive receptors would be construction staff that may be exposed to any
existing contamination at the site, particularly associated with ground preparation works and excavations.
During operation the site staff and residents of the SEC Housing Area will be the key receptors.
Assessment of Construction and Operational Impacts 9.6
Construction Phase Impacts 9.6.1
The primary source for potential contamination is considered to be existing soil contamination, which if present
could be mobilised through site construction activities and surface water run-off during the infrequent periods of
rainfall. However, since no obvious signs of contamination were identified during the Phase I Investigation, the
potential for such mobilisation is considered minimal, although if present, may result in a moderate negative
impact prior to the implementation of appropriate mitigation measures.
Project number: 37446130 Dated: 09/11/2014 166 | 278 Revised:
Some aqueous effluents from temporary construction facilities, including dewatering, washing down, dust
damping activities and concrete work, may lead to the contamination of soil. This impact is likely to be
temporary in nature and will only be applicable during the construction phase. Prior to mitigation, it is
considered that the impact will be of minor negative significance.
The remainder of the potential impacts are associated with the management of waste and hazardous materials.
These impacts will generally be associated with poor storage or handling arrangements of these materials
resulting in chronic or acute spillages of contaminants to land. Prior to the implementation of mitigation
measures, it is considered that the impact will be of minor negative significance.
During construction, there is a potential for construction workers to come into contact with contaminated soils
and hazardous materials. It is therefore important that appropriate measures are taken to protect construction
contractors during site clearance, excavation and general construction activities. It is considered that this may
result in a moderate negative impact prior to mitigation.
The improper storage and use of other hazardous materials during the construction phase such as chemical
solvents, cleaning fluids, fuels and oils etc., may lead to spillages and leaks that may result in soil and/or
surface water contamination. The above issues may result in a moderate negative impact prior to the
implementation of appropriate mitigation measures.
If applicable, cement batching plants require large amounts of “wash-out” water which has a high pH and high
concentration of suspended solids. In addition, plant and equipment wash water may contain some
contaminants such as hydrocarbons although traces of other contaminants may be present. These two waste
water processes can affect the quality of groundwater if discharged to land. The generation of wastewater
during the construction phase is a direct, temporary minor negative impact prior to the implementation of
mitigation measures.
Operational Phase Impacts 9.6.2
During the operation of the plant, the key contamination issues are likely to be associated with potential leaks
and spills associated with the plant operations and storage of hazardous materials on-site. The materials with
potential to cause contamination include: fuels (such as associated with diesel generator operation); oils (such
as associated with the maintenance and repair of equipment); lubricants (such as those associated with plant
equipment maintenance and repair): and a variety of chemicals.
Prior to mitigation measures being implemented, the use and storage of materials on site with hazardous
properties and the potential to cause contamination is likely to result in a moderate negative impact. However,
adequate handling and storage arrangements complemented by appropriate procedural control measures
would diminish such an impact substantially.
There is the potential for contaminants to be mobilised during periods of rainfall, which may then be discharged
into the wider environment, such as the recharge area of an underlying aquifer. This is considered to be an
impact of moderate negative significance.
167 | 278
Mitigation Measures, Residual and Cumulative Effects 9.7
Construction Phase Mitigation Measures 9.7.1
There will be no discharge or overflow of sanitary waste on site. Modular wastewater storage tanks will be
introduced to the site to provide adequate containment facilities for the construction workforce.
Hazardous materials such as fuel oils and chemicals used during the construction phase that have the potential
to cause contamination will be managed through the CEMP, to be developed by the EPC Contractor. This
CEMP would provide detailed Environmental Control Plans for construction workers and personnel and sub-
contractors including personnel safety, site conduct, security, storage of hazardous material and emergency
preparedness.
The contractor shall be fully responsible that all demolitions and removal of any abandoned facilities are
undertaken in a safe way.
The key control measures incorporated in to the CEMP to promote on-site environmental good practice during
the construction process in relation to the storage of fuels, chemicals and oils on-site must include:
Substitution of any hazardous substances with safer alternatives;
Changing work methods in order to prevent the production or release of potentially contaminative materials;
Enclosing the process or handling system as far as reasonably practicable;
Using a potentially hazardous material away from high risk areas;
Limiting the quantities of hazardous substances during the construction process to reduce the risk of
spillages;
Ensuring that all substances are stored in suitable, undamaged, containers that are clearly marked with the
type, nature and content of the material. This will ensure that all staff are aware of the material and its
properties;
Appropriate storm water management procedures to ensure that contaminants are not mobilised into the
wider environment;
Where practicable, retaining substances during the construction process in a centrally controlled storage
compound in accordance with World Bank Group guidance, and appropriate risk assessment based on the
material safety data sheet provided by manufacturer (the Control of Substances Hazardous to Health
[COSHH Regulations 2002] which provides a similar framework in the UK);
The storage area should: prevent damage to containers by any means; prevent the unauthorized use of
material (e.g. responsible person to sign materials in and out of the compound); can contain any spillage
from materials / substances (by the use of an impermeable surface and walls); and, separate any materials
that may become a hazard if combined;
Project number: 37446130 Dated: 09/11/2014 168 | 278 Revised:
Returning any unused materials, spent containers, contaminated clothing, rags and tools to the central
compound for appropriate disposal;
As part of the CEMP, emergency clean-up procedures will need to be in place in the event of any potential
spillages; and,
Staff and personnel will need to be briefed through toolbox talks and training on the control of substances
and informing them of all control measures and location of spill response equipment on-site.
In addition the CEMP will also contain control measures to be adopted during the construction stage to
minimise potential impacts associated with leaks and spills from on-site activities. Such measures will include
the following:
All plant should be regularly maintained and appropriate drip-trays should be located below mobile plant
such as generators;
Washout from concrete mixing plant or from cleaning ready-mix concrete lorries is contaminated with
cement and therefore is highly alkaline. This should not be allowed to enter any watercourse/drainage
channel and should be re-used on site where possible; and,
All vehicle/plant re-fuelling should be closely supervised and appropriate spill trays utilised where
appropriate.
The on-going evolution of the site CEMP will need to be agreed with the client, the EPC contractor, and with
PME in order to ensure that any potential environmental and health and safety issues are adequately managed.
This will ensure good working procedures are followed and will decrease the potential risk of pollution incidents
occurring. In addition, appropriate precautions will be implemented to prevent construction workers from having
contact with potentially contaminated soils. Construction workers will be required to wear appropriate personal
protective clothing and be subject to adequate training / awareness.
Construction Phase Residual Effects 9.7.2
The implementation of a detailed CEMP for the construction phase of the development is imperative in order to
ensure that appropriate measures are implemented to minimise any potential risks from contamination to the
workforce and the environment during the construction phase, including any groundwater sources, during the
construction phase. Once these measures are followed, the assessment is of a minor negative residual effect.
Construction Phase Cumulative Impacts 9.7.3
The potential for cumulative effects to occur, as a result of the construction phase, is negligible. Type I
cumulative effects – i.e. impacts associated with other construction related impacts - are not expected. Site
investigation work, which will be undertaken at the project site in advance of the commencement of the
construction phase, will however determine if there are any existing issues at the project site associated with
past or current uses.
169 | 278
Operational Phase Mitigation Measures 9.7.4
The key measures for preventing contamination during the operational phase will be designed into the project.
This includes appropriate designs in relation to the following:
Appropriate containment systems around storage tanks (e.g. fuels, oils etc.);
Leak detection facilities;
Fire prevention measures; and
Appropriate storm water management systems.
An OEMP will also be developed which will contain the key operating procedures that are to be implemented
for the project to prevent contamination of the ground and surface water. Such measures will include:
Hazardous chemicals and materials to be appropriately stored on-site in secure, bunded compounds and
located on an impervious surface. The storage areas will need to be clearly labelled with material safety
data sheets (MSDS) maintained as part of the on-site record keeping;
Details and properties for each material should be clearly detailed which include its nature (poisonous,
corrosive, flammable), prohibitions on its disposal (dumpster, drain, sewer) and the recommended disposal
method (recycle, sewer, burn, storage, landfill). A signed checklist should be developed for users of
hazardous materials detailing amount taken, amount used, amount returned and disposal of spent material;
All contaminated effluent shall receive appropriate treatment at the source of pollution before being
collected and discharged. Please note that further measures relating to water and wastewater resources
appear in the pertinent chapter of this report; and
Further, the Client dictates that every ‘effort shall be taken to ensure that the risk of pollution is eliminated.
Provisions shall be made to bund all oil storage facilities. All delivery areas shall have suitable drainage
gully provisions to all sides to prevent spillages to spreading to the surrounding ground.
Other measures in relation to personnel safety, housekeeping and security, on-site awareness training and
emergency preparedness policies are also essential. Such measures will form part of the OEMP with the
overall aim of avoiding incidences which may lead to potential contamination issues. Such measures will
include, inter alia:
To protect and promote health and safety issues to all staff and personnel on-site;
To minimise exposure to potential hazards and safety issues and reduction in risk from injury and health
risk;
To minimise impacts on the environment from the plant activities taking into account the necessary balance
between economic efficiency, energy requirements and environmental protection;
Promote good practice measures in terms of health and safety to comply, as a minimum, with KSA law and
policy requirements;
Project number: 37446130 Dated: 09/11/2014 170 | 278 Revised:
Provide appropriate security measures to ensure that any potential issues that may result in contamination
are avoided;
Promote appropriate safety zoning to the hazards that may be present and to ensure that any spillages or
incidents are avoided;
Provide emergency response procedures to any potential incidents to ensure that contamination incidents
are controlled if they occur;
Provision of written standard operating procedures for all processes and appropriate document control;
Provision of awareness training for all employees including management, office staff and technical staff on
pollution prevention and control techniques and best practices;
The establishment of daily checklists for plant and office areas to confirm cleanliness and adherence to
proper storage and security. Specific employees should be assigned specific inspection responsibilities and
given the authority to remedy any problems found;
Continuous monitoring and reporting of the plants’ performance should be undertaken in order to establish
baseline conditions and whether conditions are improving or deteriorating; and,
Regular reviews of emergency response procedures should be undertaken, including a contingency plan
for spills, leaks, weather extremes etc.
Operational Phase Residual Effects 9.7.5
It is anticipated that the detailed OEMP for the site will dictate good on-site working practices the risk of
pollution incidents will be minimised resulting in a minor negative residual effect.
Operational Phase Cumulative Effects 9.7.6
It is anticipated that the risk of cumulative impacts during the operational phase is low. Best practice measures
implemented as part of the OEMP will reduce the risk of contamination events occurring at the Project site.
Summary & Conclusions 9.8
It is recommended that an investigation of existing contamination associated with the decommissioned
industrial facility is undertaken prior to any major excavation works take place on site.
It is a requirement that any existing contaminated materials on site identified during site preparation works,
including soils, are considered as hazardous waste and disposed of in a licensed landfill site prior to site
preparation works by an appropriately licensed contractor. Notwithstanding the above, intrusive investigations
will need to be enacted if additional significant pollutant sources or contaminations are identified prior to or
during the site preparation works.
171 | 278
In addition, during the construction and operational phases of the project, there is a potential for workers and
visitors to come into contact with contaminated land and hazardous or semi-hazardous wastes, as well as the
potential for leaks and spills to adversely affect the wider environment. The CEMP and OEMP must be
implemented to manage these risks and to reduce the likelihood of any future negative environmental and
social impacts.
Project number: 37446130 Dated: 09/11/2014 172 | 278 Revised:
Table 9-2 Impact and mitigation summary table for soil, groundwater and contamination
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Impacts associated with mobilisation of existing contamination.
Medium to high sensitivity
Negligible to major adverse
An investigation of existing soil and groundwater contamination associated with the decommissioned industrial facility should be undertaken prior to excavation works taking place on site.
Negligible to minor adverse
Discharge of aqueous effluents from temporary construction facilities and activities e.g. dust damping activities, sanitary wastewater.
Low to medium sensitivity
Minor adverse
Adherence to the CEMP ensuring good working practices are followed, thereby decreasing the risk of pollution incidents occurring. The CEMP will include the following measures includes (for example):
There will be no discharge or overflow of sanitary waste on site. Modular wastewater storage tanks will be introduced to the site to provide adequate containment facilities for the construction workforce;
Changing work methods in order to prevent the production or release of potentially contaminative materials;
Substitution of any hazardous substances with safer alternatives; and
Limiting the quantities of hazardous substances during the construction process to reduce the risk of spillages.
Negligible
Impacts associated with management of waste and hazardous materials resulting from poor on-site management.
Low to medium sensitivity Minor adverse Negligible
Potential for construction workers to come into contact with contaminated soils and hazardous materials.
Medium to high sensitivity
Moderate adverse
The CEMP shall provide detailed Environmental Control Plans for construction workers and personnel and sub-contractors including personnel safety, site conduct, security, storage of hazardous material and emergency preparedness; and
Staff and personnel will need to be briefed through toolbox talks and training on the control of substances and informing them of all control measures and location of spill response equipment on-site.
Negligible to minor adverse
Improper use and storage of hazardous materials such as solvents, cleaning fluids, fuels and oils.
Low to medium sensitivity
Moderate adverse
Adherence to the CEMP ensuring good working practices are followed, thereby decreasing the risk of pollution incidents occurring. The CEMP will include the following measures includes (for example):
Ensuring that all substances are stored in suitable, undamaged, containers that are clearly marked with the type, nature and content of the material. This will ensure that all staff are aware of the material and its properties; and
Negligible to minor adverse
173 | 278
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Impacts upon groundwater resulting from improper discharge of wastewater e.g. ‘wash out’ water from cement batching plants.
Low to medium sensitivity
Minor adverse
Washout from concrete mixing plant or from cleaning ready-mix concrete lorries is contaminated with cement and therefore is highly alkaline. This should not be allowed to enter any watercourse/drainage channel and should be re-used on site where possible;
Negligible
Operational Phase
Contamination resulting from the use and storage of hazardous materials on-site.
Low to medium sensitivity
Moderate adverse
The key measures for preventing contamination during the operational phase will be designed into the project. An OEMP will be also developed which include the following measures (for example):
Hazardous chemicals and materials to be appropriately stored on-site in secure, bunded compounds and located on an impervious surface. The storage areas will need to be clearly labelled with material safety data sheets (MSDS) maintained as part of the on-site record keeping;
Details and properties for each material should be clearly detailed which include its nature (poisonous, corrosive, flammable), prohibitions on its disposal (dumpster, drain, sewer) and the recommended disposal method (recycle, sewer, burn, storage, landfill). A signed checklist should be developed for users of hazardous materials detailing amount taken, amount used, amount returned and disposal of spent material;
Provide emergency response procedures to any potential incidents to ensure that contamination incidents are controlled if they occur; and
Continuous monitoring and reporting of the plants’ performance should be undertaken in order to establish baseline conditions and whether conditions are improving or deteriorating.
Negligible to minor adverse
Impacts upon the wider environment e.g. recharge area of an underlying aquifer resulting from contamination potentially mobilised during periods of rainfall.
Low to medium sensitivity
Moderate adverse
Negligible to minor adverse
Project number: 37446130 Dated: 09/11/2014 174 | 278 Revised:
10 Waste Management
Introduction 10.1
This chapter presents the results of a solid waste assessment for the Project. The potential impacts that may
arise from waste generated during the construction and operational phases are identified.
The chapter also details opportunities for implementing mitigation measures together with good practice for the
storage, transfer and disposal of waste in order to reduce the potential impacts arising during each phase of the
development. These measures are summarised below and set out in full in Chapter 16: Framework
Construction Environmental Management Plan and Chapter 17: Framework Operational Environmental
Management Plan.
Relevant Standards and Legislation 10.2
National Legislation and Standards 10.2.1
The GER, 2001 makes specific reference to the control of solid waste materials and, in particular, waste
materials which are classified as hazardous in terms of their impacts on the environment. The following are of
particular note:
Article 14 (Hazardous Waste Management) identifies the Presidency of Meteorology and the Environment
(PME) as the responsible authority for the regulation of waste materials; and
GER Appendix 4 “Hazardous Waste Control Rules and Procedures” provides details regarding the
classifications of waste and the obligations placed on producers, transporters and waste disposal
authorities to ensure environmental pollution is avoided. Prior to shipping any hazardous waste outside the
facility, the generator of hazardous waste shall comply with the requirements for packaging, record keeping
and duty of care obligations.
Further, the revised PME environmental standards issued in 2012 include the following, which are of relevance
to this assessment:
Environmental Standard 8 - Waste Acceptance Criteria;
Environmental Standards 9 - Waste Classification;
Environmental Standard 12 - Waste Control;
Environmental Standard 13 – Waste Handling and Storage;
Environmental Standard 14 – Waste Training and Operators; and
175 | 278
Environmental Standard 15 – Waste Transport.
In particular, the Environmental Standard 12 makes specific reference to the control of solid waste materials
and in particular waste materials which are classified as hazardous in terms of their impacts on the
environment:
Article 4 (Purpose) identifies that PME is charged with protecting the natural environment and is
therefore obliged to issue controls over waste activities in KSA’.
The Waste Classification Standard for KSA provides the following:
“A national classification system that may be employed within KSA by all waste generators, transporters, facility
operators and the relevant competent agencies and other interested parties. The standard provides
classification, coding and defining of all waste types so they can be handled treated or disposed of
accordingly".
IFC Standards 10.2.2
The IFC Environmental, Health and Safety (EHS) Guidelines for Thermal Power Plants (December, 2008)
requires:
“Management of ash disposal and reclamation so as to minimize environmental impacts – especially the
migration of toxic metals, if present, to nearby surface and groundwater bodies, in addition to the transport of
suspended solids in surface runoff due to seasonal precipitation and flooding. In particular, construction,
operation, and maintenance of surface impoundments should be conducted in accordance with internationally
recognized standards.”
Section 1.5 of the IFC General EHS Guidelines covers Hazardous Materials Management and Section 1.6
deals with Waste Management and is applicable to all projects that generate, store or handle any quantity of
waste. The waste management guidelines state that facilities that generate and store wastes should practice
the following:
Establish waste management priorities at the outset of activities based on an understanding of potential
Environmental, Health, and Safety risks and impacts;
Establish a waste management hierarchy that considers prevention, reduction, reuse, recovery, recycling,
removal and finally disposal of wastes;
Avoid or minimize the generation waste materials, as far as practicable;
Where waste generation cannot be avoided but has been minimized then options for recovering and
reusing waste should be developed; and
Where waste cannot be recovered or reused, identify means of treating, destroying, and disposing of it in
an environmentally sound manner.
Project number: 37446130 Dated: 09/11/2014 176 | 278 Revised:
This assessment also considers the likely impacts upon soils and geology as a result of Project activities in
relation to the updated IFC Performance Standards; namely:
Performance Standard 3: Resource Efficiency and Pollution Prevention.
It is a requirement of this performance standard to implement measures to ensure the following:
‘Avoid the generation of hazardous and non-hazardous waste materials. Where waste generation cannot
be avoided, the client will reduce the generation of waste and recover and reuse waste in a manner that is
safe for human health and the environment. Where waste cannot be recovered or reused, the client will
treat, destroy or dispose of it in an environmentally sound manner that includes the appropriate control of
emissions and residues resulting from the handling and processing of the waste material’;
‘When hazardous waste disposal is conducted by third parties, the client will use contractors that are
reputable and legitimate enterprises licensed by the relevant government regulatory agencies and obtain
chain of custody documentation to the final destination’;
‘The client will avoid or, when avoidance is not possible, minimise and control the release of hazardous
materials….The client will avoid the manufacture, trade and use of chemicals and hazardous materials
subject to international bans or phase-outs due to their high toxicity to living organisms, environmental
persistence, potential for bio accumulation or potential for depletion of the ozone layer’; and
‘This section also provides guidelines for the segregation of waste into hazardous and non-hazardous
streams and how to manage these waste streams. The Project should seek to demonstrate compliance
with the principles and guidelines set out within this document’.
Methodology 10.3
The principal aim of this assessment is to consider the key waste management issues associated with the
construction and operational phases of the proposed Project with particular reference to identifying
opportunities for the reduction of the severity or likelihood of significant environmental impacts.
The methodology adhered to comprised of a number of tasks including:
Site visit in May 2014 to gain an understanding of any issues regarding waste;
A desk top review to collate existing information relevant to waste generation and disposal within the Tabuk
area and the Kingdom;
A review of the current project and past projects in relation to waste storage and transfer requirements; and
A review of available and accessible waste guidance and policy information.
177 | 278
Existing Baseline Conditions 10.4
Introduction 10.4.1
The existing baseline conditions on site have been assessed based on a site visit undertaken in May 2013 as
well as a desktop analysis of the waste situation in KSA and implications of these for the Project.
Waste Management in KSA 10.4.2
Responsible management of solid waste materials, both hazardous and inert, has become a pressing need for
all developing and modern economies, including the Kingdom of Saudi Arabia. There are strong economic and
environmental reasons for tackling the growing quantity of solid waste.
Waste management sites and facilities in the Kingdom are typically operated and managed by private
companies or local municipalities, with PME as the competent environmental regulator. When new sites are
proposed and constructed, PME plays an important role in advising the operators on the environmental
protection requirements for the facility.
The economic growth in Saudi Arabia, in addition to correlating urbanisation and population growth has
resulted in a significant increase in the quantities of solid waste generated. It is estimated that 15 million tons of
solid waste are generated annually, which equates to a per capita waste generation rate of between 1.5 to
1.8kg per person per day (Zafar, 2013). The vast majority of municipal solid waste is sent directly to landfill,
with an estimated 10-15% recycled. Although both recycling and composting activities are undertaken on a
small scale in comparison to the amounts of waste generated nationally, increasing interest is being placed in
these sectors, with the Saudi government being acutely aware of the pressing need to identify solutions to the
existing waste management issues facing the country (SEC, 2014).
Efforts are also underway to deploy waste-to-energy technologies in the Kingdom. The Saudi government is
aware of the critical demand for waste management solutions, and is investing heavily to solve this problem.
The 2011 national budget allocated SR 29 billion for the municipal services sector, which includes water
drainage and waste disposal. The Saudi government is making concerted efforts to improve recycling and
waste disposal activities. Recently the Saudi Government approved new regulations to ensure an integrated
framework for the management of municipal wastes. The Ministry of Municipal and Rural Affairs will be
responsible for overseeing the tasks and responsibilities of the solid waste management system.
However, more serious efforts are required to improve waste management scenario in the Kingdom. A
methodical introduction of modern waste management techniques like material recovery facilities, waste-to-
energy systems and recycling infrastructure can significantly improve waste management scenario and can
also generate good business opportunities.
Project number: 37446130 Dated: 09/11/2014 178 | 278 Revised:
The design of any new facility should take into account the types of waste being produced within a given area
or region and the environmental setting in which it will be placed. The needs and concerns of the local
population should be considered within the decision process.
Existing Site Conditions 10.4.3
The proposed Project site is located by the Al-Muwaylih Village within the Tabouk Province. This north western
region of the Kingdom is characterized by agricultural activities reflecting on the availability of natural resources
including water, both from rain and ground sources.
Currently, there is only one industrial zone located in Tabouk with few industrial facilities, the most significant of
which are related to cement and steel manufacturing.
For this reason, the majority of waste produced in Tabouk is agricultural waste rather than industrial.
Agricultural waste is commonly burned in open spaces near their farms representing significant environmental
concern. A single waste facility exits within boundaries of the Tabouk Province. However, the facility is merely a
dump site, located south from Tabouk City, which lacks in design and maintenance and is not in line with waste
management standards of PME.
It is understood that the Tabouk municipality is in the early stages of planning for a new sanitary landfill facility
which would be developed in accordance with the PME standards.
No facility designed specifically for hazardous waste material exists in Tabouk, therefore each industrial facility
generating hazardous wastes must individually contract a certified contractor approved by PME in order to
establish an appropriate hazardous waste management procedure.
Sensitive Receptors 10.5
The main sensitive receptor relating to hazardous and non-hazardous waste generated by the proposed Project
will be the waste infrastructure utilised for the treatment and storage of wastes produced from the facility, both
during the construction and operational phases e.g. city landfills operated by the local municipalities (in this
instance, Northern Borders Municipality). These receptors have been assessed as low to medium in terms of
sensitivity.
Potentially sensitive receptors also include the soil within the site which could be adversely affected in the event
of a contamination event due to inadequate storage provisions. Additionally, operational workers may also
represent sensitive receptors and could be exposed to hazardous materials if adequate procedures have not
been implemented to ensure the abatement, correct storage and transport of these materials and
contamination of the environment resulting from releases of hazardous substances. These are discussed below
and dealt with in Chapter 9: Soils, Geology and Contamination and Chapter 13: Socio-Economic.
179 | 278
Assessment of Construction and Operational Impacts 10.6
Construction Phase Impacts 10.6.1
A summary of the potentially significant effects associated with the construction phase waste management is
presented below.
The construction of the facility is likely to generate significant quantities of waste; Table 10-1 below outlines the
waste types and sources expected during the construction phase. At this stage, however, it is not possible to
fully quantify the amounts of wastes produced.
Table 10-1 Typical Construction Phase Waste Origins
Excavation and Demolition Waste
Spoil;
Demolition waste
Other Solid Wastes
Residual general waste
Construction wastes
Concrete and cement
Brick / Block/ Ceramics
Metals including steels from fabrication, iron aluminium etc.
Glass and Cladding
Timber and plaster board
Insulation materials including fibreglass
Plastics from packaging and construction materials
Hazardous wastes
Oil both liquid and sludge
Paint, thinners contaminated painting equipment
Chemicals
Excavation and Demolition Waste
A qualitative impact assessment cannot be undertaken at this stage due to limited data regarding the expected
quantities of excavation material generated through excavation works on site.
It is anticipated that a significant quantity of excavation waste will be generated, through the construction of
foundations across all parts of the site, pile arisings and the construction of service trenches.
It is expected that the majority of excavated material will comprise of natural ground, which is likely to be
classified as non-hazardous waste due to the absence of historical sources of contamination within the area.
This issue has been covered in detail within Chapter 9: Soil and Geology.
However, any excavated material that does require disposal to landfill due to likely contamination renders the
impact from excavation waste to be of moderate negative significance upon landfill and other local waste
facilities, prior to the implementation of mitigation measures.
Project number: 37446130 Dated: 09/11/2014 180 | 278 Revised:
Whilst a qualitative impact assessment cannot be undertaken to ascertain the levels of excavation and
demolition waste generation, it is thought that this may result in a minor negative impact.
Management of Construction Waste
Waste material from the construction of buildings and plant infrastructure will require off-site disposal.
Additionally, the high number of construction workers expected to be required at the site during the construction
phase is likely to result in an increase in waste generation.
Licensed waste management facilities must be used for disposal and therefore the waste generation is likely to
result in a minor negative impact.
Uncontrolled or unlicensed dumping of waste is common in the region and steps should be taken to ensure this
does not happen in order to prevent significant environmental damage in the local area.
Storage of Construction Waste
The impacts associated with the poor storage of construction materials on-site may result in the potential
wastage of large volumes of raw materials. It is anticipated that prior to the implementation of appropriate
mitigation measures that this will result in a minor negative impact.
Contamination issues associated with the poor storage of construction wastes are dealt with in Chapter 11:
Soils, Geology and Contamination.
Generation of Hazardous Wastes
Hazardous wastes likely to be produced will include oil (both liquid and sludge), paint, thinners, contaminated
painting equipment and chemicals associated with construction activities.
It is anticipated that potential impacts of hazardous waste streams generated from construction activities of the
facility are likely to be of moderate negative significance due to the potential to cause contamination if not
managed or disposed of properly. It is also noted that not all landfills in the Kingdom are lined which suggests
that the leaching of hazardous materials to the surrounding soil strata and groundwater may occur.
Operational Phase Impacts 10.6.2
The types of solid waste materials generated during the operational phase may be expected to include:
Waste associated with operation and maintenance works of the plant equipment; and,
General waste streams generated from the administration buildings, site canteen and worker accommoda-tion.
181 | 278
It should be noted that the use of natural gas as the primary fuel is beneficial with regards to solid waste gener-
ation. Unlike other fuels, such as coal and heavy fuel oil, the use of natural gas to create electricity does not
produce substantial amounts of solid waste6.
Generation of Hazardous Wastes
Hazardous wastes likely to be produced will include hydrocarbons and oils, solvents, contaminated rags, steel
and plastic drums, filters, paints and greases. Periodically it may also include pipe work, metals and plastics
associated with plant maintenance or filter media and sludge arising from treatment works.
It is anticipated that potential impacts of hazardous waste streams generated from the maintenance works and
plant processes of the Project are likely to be of moderate negative significance due to their potential to cause
contamination if not managed or disposed of properly. Uncontrolled or unlicensed dumping of waste is also
common in the region and steps should be taken to ensure this does not happen in order to prevent significant
environmental damage.
Sludge generated from the sanitary waste treatment plant will need to be disposed of by an appropriately
licensed contractor. It has been assumed that the storm drains will not be connected to the sewage system.
Should there be any interconnectivity between these systems, sanitary sludge would need to be disposed of as
hazardous waste, since the potential exists for hazardous substances such as chemicals through accidental
spills, to enter and contaminate this system. The issue of liquid wastes from wastewater treatment processes is
considered in Chapter 10: Water Resources and Waste Water.
General Solid Wastes
Based on natural gas operation, the only waste stream from the power plant itself will be a small amount of
spent catalyst which is generated every one to five years.
The waste from the operational administration area and any worker’s accommodation included within the site
boundary of the plant will be general waste streams of a predominately non-hazardous nature and may include:
Paper – waste paper may be generated during the general administration process and on site record
keeping;
Organic food waste – leftover food and preparation waste from canteen areas;
Cardboard – waste cardboard may be generated from deliveries of material to the site;
Green waste – from on-site landscaping; and
Plastic packaging – waste plastic packaging in the form of shrink and bubble wrap.
6 USEPA (Last updated on 9/25/2013) http://www.epa.gov/cleanenergy/energy-and-you/affect/natural-gas.html
Project number: 37446130 Dated: 09/11/2014 182 | 278 Revised:
The Project is unlikely to result in a significant generation of general solid waste during operation and the
impact is therefore predicted to be of minor negative effect, due in the main to the impact on depleting landfill
space in the region.
Mitigation Measures, Residual and Cumulative Effects 10.7
The mitigation measures applicable to waste management are set out within this section and are summarised
in Chapter 16: Framework Construction Environmental Management Plan and Chapter 17: Framework
Operational Environmental Management Plan.
Construction Phase Mitigation Measures 10.7.1In accordance with Environmental Standard 8 – Waste Acceptance Criteria, a waste generator must undertake
a detailed audit of their waste to establish whether the waste:
i. is prohibited from disposal to landfill;
ii. is hazardous and suitable for landfill in its current condition;
iii. is hazardous and would meet the Waste Acceptance Criteria (WAC) for dedicated hazardous landfill;
iv. is hazardous and regarded as stable and non-reactive;
v. will be classified as inert, appears on the WAC lists and does not require testing;
vi. requires testing prior to being certain as to which class of landfill it can go to; or
vii. has, or may be subject to treatment of some sort.
Details of the waste classification process are set out in Environmental Standard 9 – Waste Classification.
Once the waste is characterised, the Generator must then consider the ways in which the waste might be
managed and disposed, in accordance with the waste hierarchy of minimisation, reuse, recovery or ultimate
disposal. This is illustrated in Table 10-2, below.
183 | 278
Table 10-2 Waste Hierarchy
If disposal is the only option, the Generator must select the disposal option that avoids or reduces any impact
on the environment. Where landfill is the only disposal option identified for all or part of the waste, the
Generator must consider the appropriate treatment options as follows:
i. Identify the landfill that may be able to accept the treated waste; and
ii. Establish whether the waste will meet the relevant WAC.
During the construction phase, the EPC contractor and their sub-contractors will be required to minimise the
impacts on the environment that may arise as a result of construction works. This is normally implemented via
the development of a Construction Environmental Management Plan (CEMP), and adherence to such a plan.
The construction contractor will also promote the commitment to continual improvement and the identification of
appropriate opportunities to reduce waste and where practicable, promote recycling and the potential reuse of
materials. This will be implemented by ensuring increased awareness among construction workers of more
sustainable working practices, for example through ‘Tool Box Talks’ to ensure that all workforce and sub-
contractors are adequately informed.
The EPC contractor and their sub-contractors will be required to identify the types and quantities of waste that
can be minimised or effectively segregated for recycling/re-use and the materials that require disposal to
landfill. As part of this process, clearly labelled waste skips should be provided for the separation of specific
waste materials such as metal, wood, cardboard and polythene for recycling. Separate skips or containers will
also be provided for residual waste streams generated during the construction phase which cannot be reused
or recycled.
Any waste fuels, oils and chemicals will be stored separately in a bunded compound situated on an
impermeable surface in order to prevent any potential spillage and contamination issues prior to collection for
appropriate disposal.
Project number: 37446130 Dated: 09/11/2014 184 | 278 Revised:
In addition, and in accordance with the IFC EHS Guidelines (Waste Management), waste minimisation should
be encouraged among suppliers. This is likely to involve suppliers committing to reducing surplus packaging
associated with any construction materials; particularly common packaging materials such as plastics (shrink
wrap and bubble wrap), cardboard and wooden pallets. This may also involve improved procurement and
consultation with selected suppliers regarding commitments to waste minimisation, recycling and the emphasis
on continual improvements in environmental performance. Table 10-3, below, summarises the most important
mitigation measures that will be implemented to minimise the potential waste of on-site materials during
construction.
Table 10-3 Measures to Reduce the Waste of on-site Materials
Ordering Delivery
Avoid: Over ordering (order ‘just in time’);
Ordering standard lengths rather than lengths
required;
Ordering for delivery at the wrong time (update
programme regularly).
Avoid: Damage during unloading;
Delivery to inappropriate areas of the site;
Accepting incorrect deliveries, specifications, or
quantities.
Storage Handling
Avoid: Damage to materials from incorrect storage;
Loss, theft, or vandalism through secure storage
and on-site security.
Avoid: Damage or spillage through incorrect or repeti-
tive handling.
Additionally, in order to ensure that such a system of reuse and recycling is effective a set of measures should
be set out which encourages a programme of auditing at each stage of the construction process. This will assist
in achieving appropriate on-site waste targets and focus upon:
Quantifying raw material wastage;
Quantifying the generation of each waste stream;
Methods by which the waste streams are being handled and stored;
Quantifying the material disposed of off-site to landfill facilities; and,
Identifying responsibilities.
Setting waste targets and undertaking future measurement and monitoring will assist in determining the
success of waste management initiatives employed at the Project site during construction. This will ultimately
lead to continual improvement as the construction process progresses.
185 | 278
Environmental Standard 12 – Waste Control sets out a Duty of Care on waste generators, transporters and
disposers to ensure that:
a) Waste is not illegally disposed of or dealt with without a licence or in breach of a licence or in a way that
causes pollution or harm;
b) Waste does not escape from a Waste Handler’s control;
c) Waste is transferred only to an ‘authorised person’, such as the relevant Competent Agency, registered
transporter or licensed disposer;
d) When the waste is transferred, it is accompanied by a full written description so that each person who has it
knows enough to deal with it properly and thus avoids committing an offence under GER 2001.
Waste Generators shall be responsible for identification of the types of waste and hazardous waste they
generate, as well as for ensuring that such wastes are stored, treated and disposed of in an environmentally
sound manner that does not cause its dispersal and also does not cause any detrimental effect on human
health, safety and welfare or the environment and the natural resources.
To this end, The Generator shall be required to:
i. classify and identify their waste;
ii. refrain from delivering or transferring wastes to a waste transporter or to a Treatment, Storage or
Disposal (TSD) facility which are either not registered, not licensed or who do not have a site ID
number from the Competent Agency;
iii. refrain from delivering consignments of waste for transportation outside the TSD Facility without being
accompanied by a Waste Tracking Form, obtained from the Competent Agency, where relevant;
iv. comply with segregation and storage requirements as specified in the Waste Segregation and Storage
Standard; and
v. prepare the waste for transportation.
It is also a responsibility of Waste Generators to prepare a Waste Tracking Form. The Generator must give the
prescribed information to the Transporter and, within fourteen days of the transfer, give the information to the
Competent Agency on the completed form. The following information must be provided on the form:
i. the Generator’s name, address, municipality and contact details;
ii. the name, address, and contact details of the person to whom the waste is to be transported;
iii. the day and time the Generator gives the waste to the transporter for transporting;
iv. the type and number of containers if the waste is hazardous; and
v. the following waste details:
The type of waste;
Project number: 37446130 Dated: 09/11/2014 186 | 278 Revised:
The amount in kilograms, tonnes, cubic metres or litres;
Its physical nature (liquid or solid);
Its hazardous waste code, if relevant (see Waste Classification Standard);
The waste origin code for the activity that produced the waste.
The Generator is required to record and keep for a minimum period of five years the following information:
i. the information detailed in the waste tracking form; and
ii. the Transporter’s name, address and contact details.
Environmental Standard 14 – Waste Handling and Storage sets out that all stored wastes must be segregated
as follows:
a) Segregation reduces the risk of waste being incorrectly classified and ensures that the correct procedures
are followed from the point of generation through to final disposal.
b) Liquids must be kept separate from solid wastes, and non-hazardous and inert waste must be segregated
from hazardous wastes, so as to create effective segregation systems to:
i. prevent unwanted or potentially dangerous reactions;
ii. reduce the rate of accidental exposure to potentially hazardous substances;
iii. ease handling and disposing of wastes;
iv. increase the diversion of waste for the purposes of recycling.; and
v. keep the cost of waste disposal to a minimum.
Environmental Standard 14 – Waste Handling and Storage requires that waste storage areas are managed as
follows:
a) Storage areas must be located to eliminate or minimise the double handling of waste.
b) Storage areas must be clearly marked and signed with regard to the quantity and hazardous characteristics
of the wastes stored therein.
c) The waste Generator using satellite storage areas and the designated waste manager of the main waste
storage are responsible for the proper accumulation, maintenance and housekeeping of their storage
areas. They must ensure that:
i. Waste streams do not get mixed and that no waste other than the normal waste stream, approved for
the container, is placed in the collection container.
ii. The waste components are correct and complete for each waste container.
iii. Accurate records are maintained to ensure compliance with onward transportation of the waste and to
minimize analytical costs associated with disposal.
187 | 278
iv. All leaks, spills, and releases are recorded.
v. Major leaks, releases or spills sufficient to pose a threat to human health or the environment are
brought to the attention of the Competent Agency.
vi. All major hazardous spills (>25 litres) are reported immediately to the Competent Agency and the
appropriate evacuation action taken.
d) Storage areas must be constructed such that any spillage or loss of containment of a particular waste type
cannot spread to other waste types. This is particularly important where flammable materials are involved.
e) The total maximum storage capacity of the storage areas must be clearly and unambiguously stated in
writing, accompanied with details of the method used to calculate the volumes held against this maximum.
The stated maximum capacity of storage areas must not be exceeded.
f) The storage arrangements must be marked on a site plan which clearly shows:
i. waste types to be stored in particular areas;
ii. separation arrangements;
iii. any fire breaks proposed; and
iv. the maximum storage capacity of each storage area.
g) Storage area drainage infrastructure must ensure all contaminated runoff is contained and that drainage
from incompatible wastes cannot come into contact with each other.
h) There must be vehicular, for example, forklift, and pedestrian access at all times to the whole of the storage
area such that the transfer of containers is not reliant on the removal of impediments which may be
blocking access, other than drums in the same row.
i) Containers must be stored in such a manner that leaks and spillages cannot escape over bunds or the
edge of the sealed drainage areas.
Construction Phase Residual Effects 10.7.2
Waste management must be included within the EPC contractor’s EHS plan and CEMP. These should provide
the necessary framework for the management of waste on-site during the construction process. This should
include encouraging waste minimisation practices during the construction process, setting waste diversion
targets and segregating waste streams for reuse/recycling. It will also help to ensure that waste is disposed of
at suitable licensed facilities and reduce the amount of waste disposed of thereby reducing the associated
traffic impact. It is anticipated that the implementation of best practice measures highlighted above and in
accordance with the aforementioned IFC guidelines, will reduce the possibility of contamination occurring. Such
an approach will result in the impact of construction waste reducing from being of minor negative significance to
a negligible impact.
Project number: 37446130 Dated: 09/11/2014 188 | 278 Revised:
Following the implementation of appropriate controls such as testing for contaminants, and subsequent
remediation if required, it is considered that the residual impacts associated with excavation and demolition
waste will be negligible.
Assuming that hazardous waste streams are handled by a locally registered waste contractor and transferred to
an appropriately licensed hazardous waste facility, and control measures are implemented to prevent
accidental spillages and ensure appropriate storage, the residual impact of the generation of hazardous waste
is considered to be of negligible significance.
Storage of Construction Waste
It is anticipated that implementation of the best practice measures highlighted above and in accordance with
the aforementioned IFC guidelines, will reduce the possibility of contamination occurring. The potential for
contamination to occur associated with the storage of construction waste is assessed in the chapter on soils,
geology, and contamination. It is anticipated that such an approach will result in a reduced effect although
construction waste remains of minor negative concern.
Construction Phase Cumulative Effects 10.7.3
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Operational Phase Mitigation Measures 10.7.4
The operational phase of the Project will result in the generation of waste streams associated with the plant
operation, maintenance works and administration functions. Once the plant is in operation, it is important that a
comprehensive OEMP is developed by the appointed O&M Company and that waste management is
considered a priority.
A formal and structured way of monitoring and recording waste and associated impacts shall be developed. A
schedule of monitoring and periodic audits to inform the OEMP process shall be established. Procedures for
waste management will be clearly defined. Plans will be drawn up for waste generated due to emergencies and
accidents. Responsibilities of individuals relating to waste management shall be clearly assigned. The financial
resources necessary to implement and operate a suitable waste management system shall be specified, as
well as those people responsible for making those resources available. Capacity building and training needs
shall be identified to ensure that waste can be properly managed and controlled. Staffing requirements and
other supporting arrangements shall be identified to demonstrate capacity to manage waste generated at the
site. A framework for the development of an OEMP is presented in Chapter 16: Framework Operational
Environmental Management Plan.
189 | 278
Waste Strategy
Current international best practice, including the IFC guidelines, advocates the need to operate sustainable
waste management practices for major industrial developments. Such guidance sets out scenarios for dealing
with waste in a preferential order from waste prevention and reduction through to re-use, recovery (energy and
materials) and disposal via landfill. The waste hierarchy can be expressed as in Table 10-2 above.
Therefore, waste management practices at the Project site should involve consideration of the following:
Ensuring compliance with national and international best practice guidance;
Encouraging opportunities to minimise waste;
Providing good on-site storage practices;
Providing suitable waste receptacles for the segregation of waste streams for recycling and general waste
for disposal to landfill;
Providing fully covered waste storage areas; and
Appointing dedicated personnel responsible for waste management issues.
Management of General Waste – Industrial Facilities
Industrial wastes that do not leach toxic substances or other contaminants of concern to the environment may
be disposed by suitably licensed contractors in landfills or at other disposal sites provided they do not impact
nearby water bodies.
Management of Hazardous Waste
The hazardous waste generated from maintenance works and plant operations are likely to include waste oils,
fuels, chemicals, empty containers and filters and replaced parts which may have associated hazardous
properties. Hazardous waste streams should be handled by a locally registered waste contractor and
transferred either to an appropriately licensed hazardous waste facility for disposal or an on-site waste
incinerator should be established for the treatment of hazardous waste.
The GER Appendix 4 (2006) “Hazardous Waste Control Rules and Procedures” details the requirements for
managing hazardous waste. A few of the key requirements are included below, which will need to be complied
with during the operation of the Project:
Containerise and pack hazardous waste in a proper and environmentally sound manner placing warning
labels on each package in accordance with the specifications and standards applicable in the Kingdom;
Accurately fill up the product data on the appropriate section of the hazardous waste transportation docu-
ment in accordance with the instructions provided in the document;
Confirm with the PME, that the storage, treatment or disposal facility designated in the transportation doc-
ument is capable of managing the waste that will be sent to it;
Project number: 37446130 Dated: 09/11/2014 190 | 278 Revised:
Make the necessary arrangements with both the transporter who will carry the waste and the receiving fa-
cility designated in the transportation documents as the destination for the waste (such as providing the fa-
cility with full and detailed information on the waste and samples for analysis);
Provide the transporter with the transportation document and copy of the safety data sheets for each type
of hazardous waste being transported; and
Comply with the hazardous waste transportation instructions provided in the transportation document.
The hazardous waste generator shall comply with the following for keeping of records and reports:
Keep one copy of each transport document it has generated pending receipt of the signed copy from the
facility designated in the document. It shall also keep the signed copy for at least 5 years as of the date of
receipt of the waste by that facility;
Retain copies of the results of all tests and analysis performed on the hazardous waste as well as copies of
all pertinent reports, correspondence and documents for at least five years from the last date of handling of
such waste;
Submit to the PME an annual report on all hazardous waste generated during the year. Copies of such re-
ports shall be retained for at least five years from the date of completion;
Submit on demand to the PME or the agencies designated by it, all documents, records and reports related
to the waste; and
Hazardous Waste Transporters and Hazardous Waste Management Facilities are required to have both a
valid identification code and a work permit from the PME.
Non-Hazardous Solid Waste Management
The administration buildings and offices on-site are likely to generate quantities of non-hazardous waste
streams including waste paper, cardboard, plastic packaging that have the potential to be segregated for
recycling. Therefore suitable waste receptacles will need to be provided at central locations on-site for the
segregation of waste streams for recycling and residual general waste. The segregated waste will be
transferred to the central storage area on-site for non-hazardous waste which will consist of dedicated
containers for recyclable waste and general waste. The storage area for non-hazardous waste will be located
on an impermeable hard-standing surface and located under cover.
Operational Phase Residual Effects 10.7.5
The negative effects associated with waste generation during the operational phase will be reduced through the
application of best practice waste management measures.
191 | 278
The implementation of the above good practice waste management measures will not however eliminate the
waste and it is anticipated that there will be a negligible residual effect associated with the management of
hazardous wastes on site.
Operational Phase Cumulative Effects 10.7.6
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Summary & Conclusions 10.8
Overall, with the implementation of good environmental practices through the contractor EHS policies and
guidance, together with the development of a CEMP and OEMP, the Project should be able to limit pressures
on the existing waste management facilities in the surrounding region and reduce the potential for any localised
contamination to occur.
However, it is anticipated that the quantities of hazardous and non-hazardous waste streams generated by the
Project may be substantial and therefore it is essential that the approach to waste management at the site as
highlighted above is rigidly adopted.
Project number: 37446130 Dated: 09/11/2014 192 | 278 Revised:
Table 0-1 Impact and mitigation summary table for waste management
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Increased pressure on local landfill and other local waste facilities due to disposal of contaminated excavated material and demolition waste.
Low to medium sensitivity
Minor to moderate adverse
It is anticipated that the majority of excavated material will require off-site disposal. If there is a potential presence of contaminants, the excavated material must be tested prior to offsite removal and disposed of to an appropriate hazardous waste facility.
Negligible to minor adverse
Generation of raw material waste. Low to medium sensitivity Minor adverse
Development of a CEMP which include the following measures (for example):
Identification of the types and quantities of waste that can be minimised or effectively segregated for recycling/re-use; and
Identification of the materials requiring disposal to landfill.
Negligible
Poor storage of construction materials on-site resulting in the wastage of large volumes of raw materials.
Low to medium sensitivity
Minor adverse
Good working practices are encouraged on-site within the CEMP, particularly in relation to the storage and disposal of waste materials; and
All on-site workers should be aware of the location of storage areas and the requirements of such areas.
Negligible
Contamination associated with generation and disposal of hazardous wastes.
Low to medium sensitivity
Moderate adverse
Adherence with the CEMP ensuring good working practices are followed;
A waste generator must ensure that hazardous wastes are stored, treated and disposed of in an environmentally sound manner without dispersal or detrimental effects; and
All hazardous wastes should be classified and delivered to a registered Competent Agency.
Negligible to minor adverse
Operational Phase
Generation of hazardous waste streams.
Low to medium sensitivity
Moderate adverse
Hazardous waste streams shall be handled by a locally registered waste contractor and transferred either to an appropriately licensed hazardous waste facility for disposal or an on-site waste incinerator should be established for the treatment of hazardous waste. Control measures regarding hazardous waste stream shall be developed within the OEMP.
Negligible to minor adverse
193 | 278
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Generation of solid waste. Low to medium sensitivity Minor adverse
Suitable waste receptacles shall be provided at central locations on-site for the segregation of waste streams for recycling and residual general waste;
The segregated waste shall be transferred to the central storage area on-site for non-hazardous waste which will consist of dedicated containers for recyclable waste and general waste; and
The storage area for non-hazardous waste will be located on an impermeable hard-standing surface and located under cover.
Negligible
Project number: 37446130 Dated: 09/11/2014 194 | 278 Revised:
11 Water Resources and Wastewater
Introduction 11.1
This Chapter discusses the baseline information relating to water resources and wastewater at the Project Site
and in the surrounding area. In particular, it considers the sources of water and the effective management of
waste water streams during construction and operational phases of the Project.
Where significant impacts are identified, appropriate avoidance and mitigation measures are provided, which
are summarised below and set out in full in Chapter 16: Framework Construction Environmental Management
Plan and Chapter 17: Framework Operational Environmental Management Plan.
Relevant Standards and Legislation 11.2
Wastewater Standards 11.2.1
The IFC Guidelines for Thermal Power Plants (2008) provide environmental guidance for effluents from power
plants, including thermal discharges, wastewater effluents and sanitary wastewater. Furthermore, relevant
standards exist within KSA for discharges e.g. PME 2012 standards, which include discharge standards to
marine waters and to municipal collection systems. Standards for the re-use of waste waters have also been
developed by the Ministry of Agriculture and Water (1989).
The PME stipulate a series of standards for direct discharge, as specified within the Industrial and Municipal
Wastewater Discharges Standards (2012). Of potential relevance are discharge standards to Municipal
collecting systems, although it is understood that the majority of wastewater streams will be treated on site or
removed by tanker for treatment and disposal at a wastewater treatment plant. In the event that any discharges
to a municipal system are made, all wastewater effluents will be required to comply with the standards identified
within Chapter 3: Environmental Legislation and Standards.
Methodology 11.3
An overview of the existing conditions on site is presented below based on information provided by the Client
and a site walkover undertaken in May 2014. The key sources of information are listed within the references
section at the end of the chapter.
An assessment of potential impacts has been made for the construction and operation phases of the project
using the project planning and project design information available. For details of the relevant waste water
quality standards and guidelines please refer to Chapter 3, Section 1.5.
195 | 278
Existing Baseline Conditions 11.4
Overview of Water and Wastewater in Saudi Arabia 11.4.1
Given Saudi Arabia’s desert climate, rapidly growing population, large agricultural requirements, and recent
substantial infrastructure and industrial development, the supply of water is a significant challenge.
Saudi Arabia is fourth highest in the world in average water use per citizen. It is estimated that 70% of the
Kingdom’s water requirements are provided for by desalination. Indeed, at present, Saudi Arabia is the largest
producer of desalinated water in the world accounting for 30% of total world capacity. A 2,300-mile pipe
distribution network supplies potable water to major urban and industrial centres, with approximately 70% of the
desalinated water subsequently used for agricultural purposes, 25% for drinking water, and 5% for industrial
use.
The remaining 30% of current water needs are supplied by groundwater abstraction. Given the low
precipitation, the groundwater in many of the country’s aquifers has taken centuries to accumulate and cannot
recharge at the same rate as current rates of abstraction. In parts of the country reliant on groundwater it has
been estimated that there may be less than twenty years remaining reserves of non-renewable resources at
current rates of usage.
Less than one half (47%) of the current population of the Kingdom has a connection to a piped water supply.
The shortfall is made up of supplies delivered in trucks and containers, which may be considerably more
expensive than an equivalent amount delivered by pipe, or from private wells. There is a national tariff for water
supply to the public, which has been in force since 1994. Before that all water was provided free of charge. The
tariff applies everywhere in the Kingdom, regardless of the cost of production and delivery.
Existing Site Conditions 11.4.2
No permanent surface freshwater features were identified during the site reconnaissance undertaken by WSP
in May 2014. The site is intersected by a number of dry wadi beds which are likely to flood during winter rainfall
events, as shown in the site context map in Figure 11-1. This will be a key consideration during both
construction and operation to ensure that the Project site is not flooded and that surrounding areas are
protected from flood.
The western edge of the site borders the Red Sea.
Project number: 37446130 Dated: 09/11/2014 196 | 278 Revised:
Figure 11-1 Site context map including wadi locations
197 | 278
Sensitive Receptors 11.5
The primary water source for the Project will be desalinated water from the sea. Therefore there will be no
abstraction from freshwater aquifers.
The land within and surrounding the Project site is a potentially sensitive receptor to the release, accidental or
otherwise, of wastewater and a concern does remain with regards to the depth of any aquifer/s in the region –
whilst it is expected that groundwater beneath the project site will be brackish, major, pollution instances may
have a significant deleterious effect. It is therefore contingent on the responsible body to take all necessary
precautions when such extraction takes place to ensure that no contamination of local water bodies takes
place.
The construction site area and the subsequent operational facility and staff are considered to be sensitive
receptors with respect to flooding.
Further, construction and operational staff are therefore thought to be one of the more sensitive receptors as
they will require a continuous supply of safe drinking and washing water throughout the construction and
operation period. There is also the possibility of staff coming in contact with non-potable water.
Assessment of Construction and Operational Impacts 11.6
Construction Phase Impacts 11.6.1
Provision of Potable and Other Water
As noted earlier, it is understood that the Client is to provide the source of potable water and from an
appreciation of the information that has been received, it is anticipated the source of potable water for the
construction phase will be via tankers.
Large amounts of potable and utility water will need to be brought to the Project Site to serve the needs of
construction personnel and construction processes. Provided that this water is obtained without impacting upon
other consumers or depleting unsustainable sources than the impact significance is considered to be negligible.
Discharge of Wastewater Streams
Whilst it is understood that there will be no direct discharges to the environment in terms of wastewater
streams, some aqueous effluents from temporary construction facilities, including washing down, dust damping
activities and concrete work, may lead to the contamination of soil, underlying groundwater and the marine
environment. This impact is likely to be temporary in nature and will only be applicable during the construction
phase. Prior to mitigation, it is considered that the impact will be of minor negative significance.
The potential does exist, however, for contamination of the soil and groundwater in the event of any accidental
spillages or leaks of fuels, oils and other hazardous materials. Depending on the scale of the event this impact
could range from medium to major negative significance.
Project number: 37446130 Dated: 09/11/2014 198 | 278 Revised:
During the construction phase, a large number of staff, including labourers and sub-contractors, will be working
on the site, generating a large volume of sanitary waste. As the contractor is to provide a sewage treatment
system in order to achieve the additional requirements of the new facility, and the fact that the any/all collected
sanitary waste water will be directed to this sewage treatment system, it is thought that any effects will be of a
negligible, negative impact.
Storm Water Run-Off and Erosion from the Construction Site
There is the potential for controlled and uncontrolled emissions associated with the construction of the Project
which could result in contamination of groundwater and the marine environment. The primary source for
potential contamination is considered to be existing soil contamination, which if present could be mobilised
through site construction activities and surface water runoff during the infrequent periods of rainfall. Following
the Phase I Site Walkover Survey, it has been determined that the likelihood of contamination on site is minimal
and this is impact is therefore considered to be of negligible significance.
Construction activities such as any ground excavation and piling for building foundations will result in ground
compaction and, ultimately, reduce the permeability of the underlying soils and reduce the amount of water
infiltrating the ground. Therefore, in the event of a storm, the volume and the rate of surface water run-off will
be increased, which may pose a localised flood risk. The Kingdom receives very little annual rainfall; however,
when rainfall occurs this can be very heavy and can result in rapid flushing of surfaces and high levels of
surface runoff in a short time period. The topography of the site and presence of wadis suggests that high
volumes of runoff and flooding could be an issue. This will have to be confirmed by during detailed design.
Increasing the volume and rate of surface water run-off at certain times of the year, as a result of an increase in
the impermeable areas across the project site and altering ground levels will affect local drainage patterns and
may result in temporary ‘ponding’ of water in certain parts during the construction phase during times of rainfall.
The groundwork and excavation of the site should be carefully phased to ensure that surface (or flood) water
conveyance is maintained.
Therefore, temporary changes to the drainage regime as a result of construction, including the increase in the
volume and rate of surface water run-off, are likely to result in a direct, temporary, minor negative impact on the
drainage regime, prior to the implementation of mitigation measures. However, it must also be noted that
periods of heavy rainfall are rare and the project site is not thought to be located within a known flood risk area
and therefore the overall risk of significant changes to the drainage regime is not thought to be significant.
Operational Phase Impacts 11.6.2
Provision of Potable, Utility and Fire Fighting Water
Potable water, utility water and fire-fighting water will be supplied from seawater via reverse osmosis plant. The
key impact will be the production of brine effluents which will need to be disposed.
It is not possible at this stage to fully determine the significance of the impacts associated with brine
discharges.
199 | 278
Wastewater Streams
It is understood that there will be no direct discharges to the environment of wastewater. The majority of treated
effluents will be treated on-site and recycled for reuse within the power plant or for irrigation purposes. Oily
water will be treated using an oil separator prior to discharge to the evaporation pond along with brine from the
reverse osmosis units. Such impacts are therefore considered to be negligible.
The liquid wastes that are to be collected by a mobile vacuum truck will need to be collected by an authorised
contractor and subsequent specialist (PME licensed contractor) off-site disposal. Without mitigation measures,
this is considered to be negligible.
Storm Water Generation and Management
Rainwater falling on areas where there is a risk of mixing with oils will be channelled as oily water to the oil
separator. All other rainwater considered to be clean will be captured in the waste water pond for reuse on site
for irrigation. The main risk associated with this process would be for a long-term build-up of contaminants
within irrigated soils. However, as there will be an on-site laboratory responsible for ensuring the quality of the
treated effluents prior to reuse the likelihood of this is considered to be low. The impact associated with
stormwater contamination is therefore considered to be negligible.
Significant storm water management will be required as part of the Project design to ensure that sufficient water
conveyance is maintained. In the absence of appropriate management this is considered to be an impact of
major significance.
Mitigation Measures, Residual and Cumulative Effects 11.7
Construction Phase Mitigation Measures 11.7.1
A facility-specific Construction Environmental Management Plan (CEMP) will be developed by the EPC
Contractor prior to any construction.
Provision of Potable and Other Water
As referenced earlier, it is understood that potable water and utility water will be supplied from tankers. It is
imperative that appropriate sources of water are used and that water minimisation measure are implemented
and fully conveyed to all construction staff.
Potable water should not be used for any other purpose than drinking water and, if required, for washing
facilities. Signs should be clearly placed next to sinks and in bathrooms encouraging staff to minimise the
amount of water used. If possible, push taps which automatically cut-off water should be used in preference to
turning taps.
Storm Water Run-Off and Erosion from the Construction Site
To protect the environment from flooding during heavy downpours, a localised run-off management system will
be employed by the EPC Contractor. This should comprise temporary surface water run-off facilities, which in
Project number: 37446130 Dated: 09/11/2014 200 | 278 Revised:
addition to containing contaminants will provide on-site attenuation for surface water flows, thereby reducing
the flood risk.
It is recommended that the EPC Contractor undertakes a detailed topographic survey and drainage pattern
analysis to determine the existing conditions on site and estimate storm water collection at the Site and
surrounding area. Information which could be considered in further assessments includes:
Slope information;
Drainage pattern interpreted from high resolution satellite imagery or field surveys;
Historic information regarding rainfall patterns;
Investigation of storm water runoff and direction;
Demarcation of catchment area within watershed.
Mitigation measures with respect to surface water run-off and contamination are dealt with comprehensively in
Chapter 8: Soils, Geology and Contamination.
Generation of Sanitary Wastewater from On-Site Facilities
All sanitary waste water will be collected and disposed of at a sewage treatment system.
Mitigation measures with respect to the potential for the contamination of the soil and groundwater in the event
of any accidental spillages or leaks associated with collection, storage and collection are dealt with
comprehensively in Chapter 8: Soils, Groundwater and Contamination.
Potential for Contaminated Waters to be Released to the Environment
Adequate infrastructure should be installed on the construction site for the collection and storage of all
contaminated wastewaters generated during the construction phase e.g. plant washdown water or chemical
wastewater streams. The wastewater must then be collected by a suitably qualified and PME approved
hazardous liquid waste contractor. Duty of care records should be maintained for all potentially contaminated
wastewater throughout the construction phase.
Mitigation measures to prevent releases of contaminated waters to the environment are dealt with
comprehensively in Chapter 8: Soils, Geology and Contamination.
Construction Phase Residual Effects 11.7.2
Provision of Potable and Other Water
It is assumed that significant amounts of potable and other sources of water will be required during the
construction phase. The extraction from ground-well sources remains of concern given the nationally perilous
state of the aquifer source. This therefore remains of moderate negative significance despite the
implementation of water conservation measures.
201 | 278
Storm Water Run-Off and Erosion from the Construction Site
Following implementation of the proposed mitigation measures, the residual impacts associated with storm
water run-off will be negligible.
Generation of Sanitary Wastewater from On-Site Facilities
The assessment remains of negligible impact, providing all safety measures are followed, such as the checking
of pipelines for leakages.
Potential for Contaminated Waters to be released to the Environment
The residual impacts associated with releases of contaminated waters to the environment are dealt with
comprehensively in Chapter 8: Soils, Geology and Contamination.
Construction Phase Cumulative Effects 11.7.3
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Operational Phase Mitigation Measures 11.7.4
It is anticipated that there will be no direct discharges to the environment in terms of wastewater streams. It is
further understood that all effluents will be either transferred for treatment at the sewage treatment plant, or
disposed of at separation pits, evaporation ponds, and/or waste water holding ponds. All such facilities will be
required to match or exceed the engineering requirements of the Client, and to comply with national and inter-
national best practice and standards.
An over-arching recommendation is that a facility-specific operational environmental management plan (OEMP)
is developed prior to the operation of any part of the facility. The delivery of and adhered to the OEMP is
normally the responsibility of the EPC Contractor.
Provision of Potable and Utility Water
Measures to reduce the requirements for reverse osmosis water should be fully investigated by the EPC and
detailed within a site-specific environmental management plan. Furthermore, there is an opportunity to limit the
consumption of potable water through the introduction of water efficient faucets, urinals, showerheads and
toilets together with a programme of workforce education.
Generation and Disposal of Wastewater Streams
Oily water and waste drainage from such areas as the GT building and crude oil treatment plant are to be
collected in local sumps and then forwarded to an oil-water separator which is to be periodically emptied via
suction pump to a mobile vacuum truck, and subsequent specialist (PME licensed contractor) off-site disposal.
The chemical waste water drainage system must be properly designed to ensure the proper collection, treat-
ment, storage, and final disposal of any chemically contaminated or potentially contaminated liquids.
Project number: 37446130 Dated: 09/11/2014 202 | 278 Revised:
If on-site disposal, then all separation pits, evaporation ponds, and waste water holding ponds must be appro-
priately designed, constructed and managed.
If off-site disposal, then such waste must be collected by an authorised contractor and the procedures noted
above followed.
All sanitary waste water is to be collected and treated at a sewage treatment plant prior to reuse for irrigation
purposes. The use of treated wastewater for irrigation represents a beneficial reuse of a waste product from the
facility. However, it will be necessary to implement adequate quality control measures to ensure that no impacts
upon the environment or health and safety are realised. The United States Environmental Protection Agency
(USEPA) Guidelines for Water Reuse (2004) provide guidance on the safe reuse of wastewater for irrigation. It
is recommended that these guidelines, or a suitable recognised alternative, are adhered to when implementing
this element of the project.
Storm Water Generation and Management
The alteration of ground levels and the introduction of additional areas of impermeable hard standing will have
a permanent effect on local drainage patterns. It is therefore important that a site wide stormwater management
system is designed and implemented.
All industrial process areas and hazardous material areas will be contained under roof structures to ensure any
rain is directed away from these areas. In addition, all industrial process areas and hazardous material storage
areas will be either walled or bunded to ensure no storm water interacts with the hazardous materials. All storm
water should then only have contact with the roofs and hard standing areas of the facility.
Rainwater captured from areas where there is a risk of it mixing with oils will be captured separately and chan-
nelled to the oil separator prior to discharge to the evaporation pond. Clean rainwater will be channelled to the
wastewater storage pond for reuse as irrigation water or recycling to the plant’s cooling water cycle.
Operational Phase Residual Effects 11.7.5
Provision of Potable and Utility Water
The impact significance associated with the use of reverse osmosis to provide potable water cannot be estab-
lished until after a detailed marine modelling study including the brine effluents has been undertaken.
Generation and Disposal of Wastewater Streams
As referred to earlier, it is understood that there will be no direct discharges to the environment in terms of
wastewater streams.
It is expected that chemicals (typically, ammonia, phosphate, and oxygen scavengers) will be delivered to the
facility in drums or similar containers before being transferred to mixing and dilution vessels. Providing good
practice is adhered to, detailed mitigation measures and procedures detailed within a site-specific environmen-
tal management plan, and frequent tool-box talks are arranged, this become of minor negative significance.
203 | 278
Other liquid wastes will be stored on-site for collection by road tanker and subsequent specialist (PME licensed
contractor) off-site disposal. The following information must be recorded by the licensed contractor. Providing
good practice in site management and transportation is adhered to, the residual effect is thought to be of negli-
gible negative concern.
Any off-site disposal remains of minor negative concern, again attributed to any leakages in the system or
spillages from the tankers.
The generation and treatment of sanitary wastewater streams remains of negligible concern.
Storm Water Generation and Management
Captured stormwater will either be recycled on site or treated and discharge to the evaporation pond. As there
will be no off-site discharges the impact is considered to be negligible.
Operational Phase Cumulative Effects 11.7.6
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Summary and Conclusions 11.7.7
The construction impacts that have been identified are those that, with good on-site and off-site environmental
management practices, can be relatively easily avoided or mitigated. Following their implementation the
residual impacts are considered to be of negligible negative significance and therefore are considered
acceptable.
The residual operational impacts related to the facility are considered to be of moderate to negligible negative
significance.
Recommendations and mitigation detailed within this assessment are designed to ensure compliance with EPA
and IFC effluent discharge guidelines, in addition to guidance set out within the IFC Environmental Health and
Safety Guidelines for Water and Sanitation (2007).
Finally, and as determined within this section, a comprehensive construction environmental management plan
(CEMP) and operational environmental management plan (OEMP) are required for the facility.
Project number: 37446130 Dated: 09/11/2014 204 | 278 Revised:
Table 0-1 Impact and mitigation summary table for water resources and wastewater
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Increased pressure on local water resources due to an increase in water demand for potable and utility water requirements on-site.
Low to medium sensitivity
Negligible to Major adverse
Use of appropriate water sources;
Water minimisation measures conveyed to staff; and
Potable water should be used for only drinking and if required fo washing facilities.
Minor to moderate adverse
Contamination of the soil as a result of sanitary and construction related effluents.
Low to high sensitivity
Negligible to minor adverse
All sanitary waste water will be collected and disposed of at a sewage treatment system;
Adequate infrastructure should be installed on the construction site for the collection and storage of all contaminated wastewaters generated during the construction phase e.g. plant washdown water or chemical wastewater streams;
The wastewater must then be collected by a suitably qualified and PME approved hazardous liquid waste contractor;
Duty of care records should be maintained for all potentially contaminated wastewater throughout the construction phase; and
Mitigation measures with respect to the potential for the contamination of the soil and groundwater in the event of any accidental spillages or leaks associated with collection, storage and collection are dealt with comprehensively in Chapter 8: Soils, Groundwater and Contamination.
Negligible
Potential for uncontrolled and controlled emissions resulting in groundwater contamination from surface water run-off or existing contamination sources.
Low to high sensitivity Negligible
A localised run-off management system will be employed by the EPC Contractor;
It is recommended that the EPC Contractor undertakes a detailed topographic survey and drainage pattern analysis to determine the existing conditions on site and estimate storm water collection at the Site and surrounding area; and
Mitigation measures with respect to surface water run-off and contamination are dealt with comprehensively in Chapter 8: Soils, Geology and Contamination.
Negligible
Increased volume and rate of surface run-off and erosion causing on-site flooding.
Low to medium sensitivity
Minor adverse Negligible
205 | 278
Operational Phase
Discharges of wastewater streams: oily water and liquid wastes.
Low to high sensitivity Negligible
The chemical waste water drainage system must be properly designed to ensure the proper collection, treatment, storage, and final disposal of any chemically contaminated or potentially contaminated liquids;
If on-site disposal, then all separation pits, evaporation ponds, and waste water holding ponds must be appropriately designed, constructed and managed;
If off-site disposal, then such waste must be collected by an authorised contractor; and
All sanitary waste water is to be collected and treated at a sewage treatment plant prior to reuse for irrigation purposes. The use of treated wastewater for irrigation shall follow the USEPA Guidelines for Water Reuse (2004).
Negligible
Storm water management: potential risk of a long-term build-up of contaminants within irrigated soils due to the use of rainwater and risk of inundation due to flooding events.
Low to high sensitivity
Negligible - Major
A site wide stormwater management system shall be designed and implemented;
All industrial process areas and hazardous material areas will be contained under roof structures to ensure any rain is directed away from these areas. In addition, all industrial process areas and hazardous material storage areas will be either walled or bunded to ensure no storm water interacts with the hazardous materials; and
Rainwater captured from areas where there is a risk of it mixing with oils will be captured separately and channeled to the oil separator prior to discharge to the evaporation pond. Clean rainwater will be channeled to the wastewater storage pond for reuse as irrigation water or recycling to the plant’s cooling water cycle.
Negligible
Project number: 37446130 Dated: 09/11/2014 206 | 278 Revised:
12 Terrestrial Ecology
Introduction 12.1
This chapter assesses the status of the existing terrestrial ecology on the Project site and presents the
applicable approaches to mitigate or minimise any potential negative impacts of this development.
Where significant impacts are identified, appropriate avoidance and mitigation measures are provided, which
are summarised below and set out in full in Chapter 16: Framework Construction Environmental Management
Plan and Chapter 17: Framework Operational Environmental Management Plan.
Relevant Standards and Legislation 12.2
The IFC’s Performance Standard 6: Biodiversity Conservation and Sustainable Management of Living Natural
Resources (2012) should be applied to projects:
(i) located in modified, natural, and critical habitats;
(ii) that potentially impact on or are dependent on ecosystem services over which the client has direct
management control or significant influence; or
(iii) that include the production of living natural resources (e.g., agriculture, animal husbandry, fisheries,
forestry).
Performance Standard 6 requires the following:
“The risks and impacts identification process…should consider direct and indirect project-related
impacts on biodiversity and ecosystem services and identify any significant residual impacts. This
process will consider relevant threats to biodiversity and ecosystem services, especially focusing on
habitat loss, degradation and fragmentation, invasive alien species, overexploitation, hydrological
changes, nutrient loading, and pollution.
As a matter of priority, the client should seek to avoid impacts on biodiversity and ecosystem services.
When avoidance of impacts is not possible, measures to minimize impacts and restore biodiversity and
ecosystem services should be implemented’.
There are no specific requirements within KSA that protect terrestrial ecology and biodiversity. However, since
terrestrial flora and fauna form part of the definition of “The Environment”, they should be afforded adequate
protection from unnecessary damage and deterioration.
The National Commission for Wildlife Conservation and Development (NCWCD), which has now been renamed
the Saudi Wildlife Commission (SWC) assisted by its two prominent research centres, the King Khalid Wildlife
Research Centre (KKWRC) and the National Wildlife Research Centre (NWRC) run a chain of fifteen wildlife
207 | 278
reserves comprising about 4% of the country land area where conservation of certain wildlife species is a major
priority.
Methodology 12.3
This assessment has been undertaken with due consideration of Performance Standard 6 (Biodiversity
Conservation and Sustainable Natural Resource Management) of the IFC Performance Standards on Social
and Environmental Sustainability.
The terrestrial ecology assessment comprised a desktop review of existing, accessible information relating to
the site and its surrounding area and was supported by a terrestrial ecology site investigation. A review of The
ESIA for the Umm Wu’al Phosphate Project (Jacobs, 2013) was also carried out.
Existing Baseline Conditions 12.4
The Word Wide Fund for Nature (WWF, 2014) classifies the area in which the site is located as Arabian Desert
and East Sahero- Arabian Xeric Shrublands. This is the largest desert ecoregion which holds relatively little
biodiversity. The primary biomes in this region are deserts and xeric shrublands. Many species, such as the
striped hyena, jackal and honey badger have become extinct in this area due to hunting, human encroachment
and habitat destruction. Other species have been successfully re-introduced, such as the endangered white
(Arabian) oryx and the sand gazelle, and are protected at a number of reserves. Overgrazing by livestock, off-
road driving, and human destruction of habitat are the main threats to this desert ecoregion.
During the site visit for the project location, it was observed that vegetation scattered across the site were of
common species, typical to the area. While no wildlife was observed, small burrows, tracks and droppings seen
on site elude to the presence of fauna.
Project number: 37446130 Dated: 09/11/2014 208 | 278 Revised:
Figure 12-1 Examples of terrestrial ecological features on the site
209 | 278
Key Sensitive Receptors 12.5
With regards to terrestrial ecology, the site has been deemed to be of a moderate ecological diversity and
therefore generally medium sensitivity to impacts. The wadis provide relatively lush vegetation compared to the
more arid raised areas. The sandy beach and associated dune vegetation is also a notable habitat for bird
species in particular.
Specific receptors may include the vegetation within the wadis, burrowing rodents and lizards as well as
occasional large mammals.
Assessment of Construction and Operational Impacts 12.6
Construction Phase Impacts 12.6.1
There are a range of construction impacts which could affect the terrestrial ecology of the site during the
construction of the facility. However, the baseline terrestrial ecology survey on site indicates that the value in
terms of ecological diversity is moderate. The following impacts are notable:
Areas of terrestrial habitat, such the wadis and sandy beach, will be lost as a consequence of the project;
Site clearance and grading may disturb or destroy flora and fauna such as burrowing rodents or reptiles;
Removal of the top layer of sand due to levelling and grading of the site may reduce the seed bank for fu-
ture flora growth;
Wastes from construction have a potential to pollute the natural environment if not adequately managed;
There is a potential for damage to the vegetation of adjacent areas and lay-down areas at the construction
stage; and
Roads and pathways carry the potential to attract both contamination from littering and fugitive materials
and dusts. This could be particularly important where fly ash is being transported. The fringes of these
roads, particularly in the downwind direction may become contaminated from windblown ash residue. The
potentially toxic nature of these compounds may affect nearby vegetation.
The construction phase impacts are deemed to be of moderate, negative significance without the
implementation of mitigation measures.
Operational Phase Impacts 12.6.2
There are potentially positive impacts associated with any site landscaping. Within the fence line, the terrestrial
vegetation will be provided a refuge from heavy grazing from animals such as camels and goats. This could
Project number: 37446130 Dated: 09/11/2014 210 | 278 Revised:
promote significant growth of plants which will in turn provide a habitat for invertebrates and birds, potentially
increasing the biodiversity of the site.
Exotic weed and pest control may be desired by the operator; however these activities may represent a threat
to any indigenous favourable species that are growing naturally and which provide ecological value to the area.
The operational phase impacts (i.e. landscaping) are deemed to be of minor, positive significance without the
implementation of mitigation measures.
Mitigation Measures, Residual and Cumulative Effects 12.7
Construction Phase Mitigation Measures 12.7.1
Where significant site levelling and re-grading is expected, the productive top surface layer should be re-
moved separately and either spread back within the site once the re-grading has been completed, or
spread on the adjacent environment. This will give seeds that exist in the top surface layer a chance to
germinate.
Wastes from construction must be adequately managed in terms of a waste management regime so that
the waste does not end up in the terrestrial environment. An adequately enforced waste management plan
will also serve to reduce the attraction of pest species such as rats and flies to the site.
During construction, unnecessary movement of machinery around the site should be avoided where possi-
ble. Dedicated transport access ways should be designated to avoid damage to the existing natural vegeta-
tion. Construction activities should be limited to the proposed site and measures should be taken to avoid
damage to adjacent areas.
Vehicles carrying potentially toxic, friable materials such fly ash, should be covered at all times so that
these materials are not accidentally deposited into the natural environment, causing harm to flora and fau-
na. Littering from construction vehicles must be prohibited.
Construction Phase Residual Effects 12.7.2
The residual effect of the construction works is considered to be of moderate negative significance.
Construction Phase Cumulative Effects 12.7.3
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Operational Phase Mitigation Measures 12.7.4
The principal mitigation measures during the operational phase are as follows:
211 | 278
Any landscape planting should be designed to provide some ecological benefit in attracting bird and insect
species. Native species should be favoured over exotic species.
Where practicable, naturally growing vegetation within the fence-line should be protected and/or encour-
aged, i.e. ensuring that vehicles and members of staff keep to maintained roads and pathways would pro-
tect the onsite vegetation from trampling. This will encourage native species which will be free from grazing
pressure of livestock animals which would in turn attract fauna species such as birds and insects, increas-
ing the biodiversity of the site.
The land within the fence-line boundary should be kept clear of any municipal or industrial waste arising
from facility processes (other than designated areas where appropriate controls should be applied), staff
and staff housing and offsite sources. This would improve the general “environmental quality” and amenity
value of the site and reduce potential attraction of pest species such as rats and flies to the site.
Operational Phase Residual Effects 12.7.5
Following mitigation from operational impacts, the residual impact will be minor, positive significance.
Operational Phase Cumulative Effects 12.7.6
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Summary 12.8
This chapter assesses the status of the existing terrestrial ecology on the proposed site and presents the
applicable approaches to mitigate or minimise any potential negative impacts of this development.
The site has been categorized as being of moderate ecological value and sensitivity due to the presence of
wadi and sandy beach areas which provide habitat for reptiles, rodent and bird species.
The overall construction impacts on the terrestrial ecology are considered to be of medium adverse significance
while the operational impacts (e.g. landscaping) will be of minor positive, significance.
Project number: 37446130 Dated: 09/11/2014 212 | 278 Revised:
Table 12-1 Impact and mitigation summary table for terrestrial ecology
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Site clearance and grading may disturb or destroy flora and fauna; and removal of the top layer of sand may reduce the seed bank for future flora growth.
Medium sensitivity
Moderate adverse
Where significant site leveling and re-grading is expected, the productive top surface layer should be removed separately and either spread back within the site once the re-grading has been completed, or spread on the adjacent environment. This will give seeds that exist in the top surface layer a chance to germinate.
Moderate adverse
Wastes from construction have a potential to pollute the natural environment.
Medium sensitivity
Moderate adverse
Wastes from construction must be adequately managed in terms of a waste management regime so that the waste does not end up in the terrestrial environment; and
An adequately enforced waste management plan will serve to reduce the attraction of pest species such as rats and flies to the site.
Moderate adverse
Potential damage to the vegetation of adjacent areas and lay-down areas.
Medium sensitivity
Moderate adverse
Unnecessary movement of machinery around the site should be avoided where possible;
Dedicated transport access ways should be designated to avoid damage to the existing natural vegetation; and
Construction activities should be limited to the proposed site and measures should be taken to avoid damage to adjacent areas.
Moderate adverse
Roads and pathways carry the potential to attract both contamination from littering and fugitive materials and dusts.
Medium sensitivity
Minor adverse
Vehicles carrying loose materials should be covered at all times so that these materials are not accidentally deposited into the natural environment, causing harm to flora and fauna; and
Littering from construction vehicles must be prohibited.
Negligible
213 | 278
Operational Phase
Within the fence line, the terrestrial vegetation will be provided a refuge from heavy grazing from animals. This could promote growth of plants which will in turn provide a habitat for invertebrates and birds, potentially increasing the biodiversity of the site.
Low sensitivity Minor positive Any landscape plantings should be designed to provide some ecological benefit in attracting bird and insect species. Native species should be favoured over exotic species;
Where practicable, naturally growing vegetation within the fence-line should be protected and/or encouraged;
The land within the fence-line boundary should be kept clear of any municipal or industrial waste arising from facility processes, staff and staff housing and offsite sources.
Minor positive
Exotic weed and pest control desired by the operator. Low sensitivity
Minor to moderate adverse
Negligible
Project number: 37446130 Dated: 09/11/2014 214 | 278 Revised:
13 Socio Economic
Introduction 13.1
This chapter of the ESIA considers the potential socio-economic impacts (both positive and negative) of the
proposed facility on its environs during both the construction and operational phases. Where appropriate,
mitigation measures and residual effects have been included and assessed respectively.
The Interorganisational Committee on Guidelines and Principles for Social Assessment (US NOAA , 2003)
provides a broad definition of a Social Impact Assessment as the:
‘systematic…appraisal of the impacts on the day to day quality of life for people and communities when the
environment is affected by development.’
This chapter highlights the methodology used to conduct this study and is followed by a brief examination of
Saudi Arabia’s macro socio-economic situation. From this, the baseline conditions of the proposed site and the
surrounding area are presented followed by an assessment of the social and economic effects of the proposed
development.
Where significant impacts are identified, appropriate avoidance and mitigation measures are provided, which
are summarised below and set out in full in Chapter 15: Framework Construction Environmental Management
Plan and Chapter 16: Framework Operational Environmental Management Plan.
Relevant Standards and Legislation 13.2
International Standards 13.2.1
The International Finance Corporation (IFC, part of the World Bank Group) ‘performance standards’ place a
significant emphasis on ensuring that the likely social and economic impacts of a project are identified and
minimised and that this is clearly demonstrated within the ESIA documentation. The specific IFC Performance
Standards appropriate to this assessment are:
Performance Standard 1: Assessment and Management of Environmental and Social Risks and Impacts;
Performance Standard 2: Labour and Working Conditions; and
Performance Standard 4: Community Health, Safety and Security.
Performance Standard 1 requires that a project proponent should identify the range of stakeholders that may
be interested in their actions and consider how external communications might facilitate a dialog with all
stakeholders. Furthermore, Performance Standard 1 states that “The client will develop and implement a
215 | 278
Stakeholder Engagement Plan that is scaled to the Project risks and impacts and development stage, and be
tailored to the characteristics and interests of the Affected Communities”.
Performance Standard 2 (Labour and Working Conditions) in particular, determines the standard of care that
must be taken with regards to workers during the construction and operational phase of the proposed facility.
SEC and the appointed EPC and associated parties must ensure that the objectives are achieved and to
promote the fair treatment of workers and safe and healthy working conditions.
Performance Standard 4 places an emphasis on the avoidance or minimisation of impacts upon community
health, safety, and security that may arise from a proposed project.
IFC’s EHS Guidelines for Thermal Power Plant (2008) also address industry-specific impacts on the social and
economic aspects of the site and surrounding context, specifically:
Occupational Health and Safety; and,
Community Health and Safety.
National Standards 13.2.2
The Labour Law (by Royal Decree No. M/51, 2005) defines the regulation of employment, labour relations,
worker contracts and work place conditions in the Kingdom.
The law contains provisions intended to protect the interests of both employers and employees with the aim of
establishing a stable, equitable and sustainable work environment. This law will therefore provide a minimum
legal basis for the engagement of the Project workforce, the working conditions and worker housing. The law
also specifically addresses such issues as protection against occupational hazards; major industrial accidents
and work injuries; and health and social services.
The law will apply to the construction and operational workforce as well as applying to both the project
company staff and all contractors.
Methodology 13.3
An assessment of the Project’s social and economic impacts has been conducted using a range of research
techniques. The objective of this section is to identify the baseline social and economic characteristics of both
the site and the surrounding local area (approximately 50km radius of the site).
This baseline review focused upon the area’s demographics, infrastructure (roads, transportation and
communication levels) potable water and sanitation facilities, education and healthcare services, economic
activity, social organisation, land ownership patterns, and land use patterns.
However, due to the inherent difficulties in assessing the significance of socio-economic issues, it is inevitable
that there will be a degree of subjectivity in assessing the nature of the impacts described. Nevertheless, this
chapter has described the principal impacts on the local social and economic climate in terms of whether the
Project number: 37446130 Dated: 09/11/2014 216 | 278 Revised:
impact and residual effects are positive or negative; permanent (long-term) or temporary (short-term); and
major, moderate, minor, or negligible.
Desk Study 13.3.1
A desktop study review has been undertaken for the proposed project and the key information has been
incorporated into the social and economic assessment and decision making process.
Information sources considered as part of the desk study include, inter alia:
Information provided by the Client;
CIA – The World Factbook website: www.cia.gov/library/publications/the-world-factbook/;
World Bank’s web-site: www.worldbank.org;
International Financial Corporation’s website: www.ifc.org;
UNESCO Institute for Statistics: www.uis.unesco.org; and;
The International Labour Organisation (ILO) website: www.ilo.org.
Existing Baseline Conditions 13.4
Introduction 13.4.1
The Kingdom of Saudi Arabia as we know it today came into being in the early part of the 20th century. Under
the Basic Ruling Law, the King is the ultimate source of authority for the executive, judicial and organisational
powers of the State. The King appoints the Council of Ministers, which he also leads as Prime Minister. Saudi
Arabia’s political and judicial apparatus is bound to Islamic principles, with the sharia (Islamic law) the basis for
all legislation.
Population and Demography 13.4.2Saudi Arabia is the largest country in the Arabian Peninsula covering an area of 2.15 million square kilometres.
Its population was estimated to be 26.54 million in 2012, including 5.6 million non-nationals (CIA, 2013).
From 1981 to 2001, the population grew from 9.9 million to 21.4 million, a total increase of 54%, averaging out
at a per annum increase of about 3.67%. The United Nations Department of Economic and Social Affairs
(2010) has estimated that the rate of population growth in Saudi Arabia in the years 1975-1999 was at an even
higher rate of 4.2%, making it one of the highest in the world.
There are several causes for this tremendous population growth. The first being the reduction in infant death
rates over the past 20 years. From 65 deaths per 1000 live births in 1980, Saudi Arabia had dropped to 19 per
1000 by 1999, and 15.61 per 1000 in 2012. However, whilst this is one of the lowest in the Arab world, and less
217 | 278
than half the regional average, KSA ranks 111 out 223 countries in the world (CIA, 2013). Likewise, life
expectancy in Saudi Arabia, which was 61 in 1980, had risen to 72 by 1999 and 74.35 in 2012 (CIA, 2013).
The population is comprised of approximately 75% Saudi citizens and 25% non-Saudi residents. Of these, 4.7
million people live in the capital Riyadh. The age structure of the kingdoms population was estimated in 2012
to be (CIA, 2013):
0-14 years: 28.8% (male 3,913,775/female 3,727,767);
15-24 years: 19.8% (male 2,811,407/female 2,439,978);
25-54 years: 44.2% (male 6,769,529/female 4,971,415);
55-64 years: 4.1% (male 604,722/female 494,497); and
65 years and over: 3% (male 416,673/female 384,741).
Health Care 13.4.3
The increased life expectancy of both infants and the elderly has been largely due to the Saudi Government’s
investment in the health care system. In 2009 (CIA, 2013), the Kingdom spent 5% of GDP on health
expenditure and healthcare provisions within KSA have been widely cited by the World Health Organisation
(WHO) as being an exemplar model for the development of healthcare infrastructure within third world
countries.
Education 13.4.4
Saudi Arabia’s educational policy aims to ensure that education becomes more efficient, to meet the religious,
economic and social needs of the country and to eradicate illiteracy.
General education in the Kingdom consists of kindergarten, six years of primary school and three years each of
intermediate and high school. The Ministry of Education sets overall standards for the country's educational
system and also oversees special education for the handicapped. Early in 2003 the General Presidency for
Girls' Education was dissolved and its functions taken over by the Ministry, to administer the girls' schools and
colleges, supervise kindergartens and nursery schools and sponsor literacy programs for females. The first
government school for girls was built in 1964; by the end of the 1990s there were girls' schools in every part of
the Kingdom. Of the nearly 5 million students enrolled in Saudi schools for the academic years 2003-04, it is
thought about half of these were female.
In addition to the dramatic quantitative growth of the educational system since the introduction of the First
Development Plan in 1970, there has also been an improvement in the quality of education. One measure of
this emphasis is that while the number of students in the educational system increased six-fold between the
1970s and the 1990s, the number of full-time teachers grew more than nine-fold. The Kingdom's ratio of 15
students to every teacher is one of the lowest in the world. The government, however, continues to work to
improve educational standards. This has been achieved by raising the quality of teacher training programs,
Project number: 37446130 Dated: 09/11/2014 218 | 278 Revised:
improving standards for evaluation of students and increasing the use of educational technology. One aspect of
this is the introduction of computer science at the secondary level. In 2000, an ambitious school computer
project was named after Deputy Prime Minister and Commander of the National Guard Crown Prince Abdullah.
In addition, the administration of the educational system has also been enhanced by delegating greater
authority to the Regional Boards.
Employment and Labour Market 13.4.5
In 2012, it was estimated that Saudi Arabia had a total work force of 8 million (CIA, 2013) albeit, approximately
80% of the workforce was comprised of non-nationals (CIA, 2013). Despite having a high unemployment rate,
especially amongst the younger generations (estimates for the Kingdom range between 14% and 25%),
employment in the Kingdom can be divided into the following sectors:
Government 40%;
Industry, construction and oil 25%;
Services 30%; and,
Agriculture 5%.
Saudi Arabia has enacted a policy known colloquially as ‘Saudiisation’ the goal of which is to increase
employment of Saudi citizens by replacing 60% of the estimated 5.6 million foreign workers in the country. To
do this, the Saudi government has stopped issuing work visas for certain jobs and has moved to increase the
training of Saudi nationals and has minimum requirements for the hiring of Saudi nationals by private
companies.
The labour market of Saudi Arabia is subject to significant challenges, with considerable unemployment and
skills shortages in key sectors. Official records estimate unemployment of Saudi males as 10.7% (CIA, 2013)
(2012, est.) however, numerous sources recognise this as a significant underestimate, with some placing
unemployment as high as 25%. This is particularly acute in the large youth population, which generally lacks
the education and technical skills the private sector needs.
Economic Overview 13.4.6
Saudi Arabia has an oil based economy with strong government controls over major economic activities. The
petroleum sector accounts for roughly 75% of budget revenues, 45% of Gross Domestic Product (GDP), and
90% of export earnings. About 40% of GDP comes from the private sector. Saudi Arabia has the largest
reserves of petroleum in the world (26% of proven reserves). Saudi Arabia’s GDP was estimated in 2012 to be
$657 billion, with a real GDP growth of 6% on the previous year (CIA, 2013).
In spite of the recent surge in its oil income, Saudi Arabia continues to face long term economic challenges
including high rates of unemployment, as highlighted above. It has a rapidly growing population, around
1.523% (2012, est.) a year (CIA, 2013), which verifies the government’s consequent need for increased public
219 | 278
spending. Saudi Arabia’s young population has increased, while oil export revenues have sharply decreased.
Saudi Arabia has also moved towards subsidy cuts, tax increases and financial sector reforms.
While the government is expanding the country’s oil and gas industry, it is also diversifying the economy into
non-oil sectors, including manufacturing and services. Although the state retains a dominant role in the
economy, the government is seeking to encourage the development of the private sector, particularly in areas
such as utilities and services.
Since 1970, economic development in Saudi Arabia has been organised through five-year development plans,
which establishes infrastructure development targets and an overall framework for public spending. The
primary objective of this plan is to increase the Saudi employment through economic growth, new investments
education, and the development of national capabilities and skills.
Social Development 13.4.7
In the context of the Arab world, the welfare of Saudi Arabia’s citizens ranks reasonably highly. The 2011
United Nations Human Development Index (HDI) gives Saudi Arabia a score of 0.777, placing it within the High
Human Development category and above the average level for the Arab States data grouping. Graphical
analysis of the change in HDI in the Kingdom over the past 30 years also indicates that the growth of the HDI in
Saudi Arabia has outstripped the average rate for the Arab world.
The Project Site 13.4.8
The Project is located in area dominated by agricultural activity, but has begun to see industrial developments.
The movement of trade is flourishes in this region with the help of proximity to various ports the closest of which
is Duba Port, only 40 km to the south, allow for the import and export of goods.
Al Muwaylih Village is a growingly popular destination for visitors seeking a access to the Red Sea. Beach,
desert and unique cultural heritage offer visitors a diverse combination of opportunities. The region is also
known for its variety of plants and animals, and diverse locations like sandy deserts, hills, and unique rock
formations.
Project number: 37446130 Dated: 09/11/2014 220 | 278 Revised:
Figure 13-1 Al Muwaylih Village
Figure 13-2 Al Muwaylih Village
The coastal range is also a key resource for fisheries; approximately 5 km north from the Project site, a fish
farm of the Tabuk Fisheries Company exists, using cages for fishing process. Adjacent to the project border
remains an old mining site which belongs to the Ministry of Petroleum and Mineral Resources.
Figure 13-3 Tabuk Fisheries Company fish farm
Figure 13-4 Decommissioned industrial facility
Key Sensitive Receptors 13.5
A number of key sensitive receptors have been identified (existing and proposed) which will be the core focus
of the assessments undertaken within the ESIA technical chapters. These are considered to be the most
sensitive receptors within the potential zone of influence of the Project. The great majority are human receptors.
Specifically, Table 13-1 below described the following sensitive receptors in terms of socio-economic impacts.
221 | 278
Table 13-1 Key Sensitive Receptors
Receptor Potential Construction Impacts Potential Operational Impacts
The fish farm Disturbance associated with the
construction work (noise, dust,
access)
Impacts to farming activties
associated with operational
discharges from the plant;
Exposure to air emissions from the
Project; and
Exposure to noise emissions from
the Project.
Duba Construction
workers
Health and safety;
Working conditions and welfare;
Exposure to air emissions from
existing facility.
Not Applicable
Residents of Al Muwaylih
Disturbance or nuisance due to
increased activities asscoiated with
construction; and
Increased pressure on local
facilities due to presence of the
construction labour force.
Exposure to air emissions from the
Project; and
Exposure to noise emissions from
the Project.
Operational staff at
existing Duba facility Not Applicable
Health and safety;
Working conditions;
Exposure to air emissions from the
Project; and
Exposure to noise emissions from
the Project.
Economic Positive economic impacts through
employment opportunities for Saudi
nationals and skills transfer.
Positive economic impacts through
employment opportunities for Saudi
nationals, skills transfer and the
supply of power.
Project number: 37446130 Dated: 09/11/2014 222 | 278 Revised:
Assessment of Construction and Operational Impacts 13.6
Construction Phase Impacts 13.6.1
Construction Worker Welfare
The main issues to be considered are associated with the labour force during the construction phase, which
includes the following:
Health and safety at work;
Access to medical facilities where required;
Reasonable working hours, wages and other benefits;
Provision of suitable and safe accommodation and sanitation; and
Access to welfare and recreation facilities.
With respect to health and safety at work, construction sites are considered to be a relatively dangerous
working environment and without proper health and safety controls there is a considerable risk of serious injury
or fatalities. Access to medical facilities is also crucial with respect to accidents and illness either in the
workplace or outside. In the absence of mitigation measures, the potential impacts are therefore considered to
be of major negative significance.
Other working conditions such as reasonable working hours, wages and other benefits are considered to be
good working practices and should be employed at all times. In the absence of mitigation measures, this has
the potential to be an impact of moderate negative significance.
In addition, a large number of labourers may be housed temporarily near the site. It must be ensured that the
labour and working conditions are of an acceptable standard. Housing must be adequately designed with
adequate sanitary and safety facilities such as fire suppressants. Issues such as retrenchment policies must be
clearly defined prior to work beginning.
Impacts on Surrounding Communities
It is considered that the potential for dust to impact upon any sensitive receptors is likely to be of negligible
significance given their distance from the Project site.
No impacts for dust and noise nuisance are likely in terms of the residents of Al Muwaylih due to the distance
separating them from the Project site.
Impact on Local Business
The influx of professional workers into the area, whilst expected to the relatively low, will generate economic
opportunities and rewards for the local population of Al Muwaylih, enhancing social and economic
development. This is deemed to be a minor positive impact.
223 | 278
Additional impacts may be associated with local employment created during the construction phase. Taken in
consideration, the high level of unemployment in the Kingdom, any additional creations for jobs and for Saudi
nationals is likely to prove beneficial for the local economy.
The construction of the proposed facility will create direct and indirect opportunities for various support service
providers including guards, cleaners, catering and other site management, prior to mitigation to be a minor
positive impact on a short term basis.
Social Issues
As above, the proposed facility will introduce a certain number of professional workers (including expatriates) to
the local area. However, in addition to the potential benefits that this may represent, this influx may also result
in social and cultural tensions, albeit this is deemed unlikely and thus thought to be a minor negative impact on
a short term basis.
Operational Phase Impacts 13.6.2
Operational Worker Welfare
One of the key issues is ensuring that operational staff and contractors are protected from workplace incidents
and illness through appropriate health and safety systems both during normal operation and other tasks such
as maintenance and repair. Appropriate safety systems such as fire protection and emergency procedures will
also be required. The potential health and safety impacts are considered to be of moderate negative
significance in the absence of suitable control measures.
Noise Nuisance upon Local Residents/Receptors
The results of the noise modelling assessment (Chapter 7) indicate that the predicted sound pressure levels will
meet the 70dB(A) criteria at the boundaries of the site. No noise impacts are expected at any sensitive
receptors or at Al Muwaylih itself. The impact is therefore determined to be negigible.
Air Quality Impacts on Human Health
A full assessment of air quality impacts associated with the operation of the Project has been undertaken within
Chapter 6: Air Quality.
The primary operational impact on air quality relates principally to stack emissions and their potential effect on
ground level concentrations (GLCs) of key airborne pollutants, such as SO2, NOx and particulates.
The results of the dispersion modelling show that under both typical and worst-case operating conditions no
exceedences of the PME AQSs for the pollutants considered in the assessment were predicted to occur as a
result of emissions from the Project at sensitive receptors in this area over all averaging periods. The impact is
therefore determined to be negigible.
Impacts on Local Businesses and Social Issues
As intimated above, the influx of professional workers, labourers, and other staff members into the area will
generate economic opportunities and rewards for the local population of Al Muwaylih, enhancing social and
economic development. This is deemed to be a minor positive impact on a long-term basis.
Project number: 37446130 Dated: 09/11/2014 224 | 278 Revised:
Indirect opportunities for various support service providers including guards, cleaners, catering and other site
management will provide employment and a further source of income for these services giving a minor to
moderate positive impact.
The employment of local workers on such a project of national importance with the requisite training which will
be included within their contracts will improve their capabilities and skill. This will also result in improving their
employability should they move on from the Project. This is deemed to be a negligible to minor positive impact;
The additional employees required for the operation of the proposed facility will put additional pressure on local
services which is deemed to be a negligible negative impact.
Similar to the construction phase, a potentially positive economic impact will result from any local employment
created by the operational phase of the Project. Whilst the likely nature of these impacts, and the effect of
expatriate workers, is largely unchanged from the construction phase, they are likely to be amplified by the
greater time-scales involved in the operation of the site.
The relatively small workforce required during the operational phase means that potential impacts are likely to
be less significant. However, all relevant labour and working condition laws and guidelines must still be adhered
to during this phase.
The marine modelling has demonstrated that the existing fish farming operations will not be adversely impacted
by the operational phase of the project due to water quality impacts associated plant outfall.
Mitigation Measures, Residual and Cumulative Effects 13.7
Construction Phase Mitigation Measures 13.7.1
Construction Worker Welfare
Construction activities undertaken for the proposed facility will be managed in such a way as to minimise
construction impacts through the Construction Environmental Management Plan (CEMP); to be developed by
the EPC. Such measures are to include:
The development of a Health and Safety and Environmental Policy would provide detailed health and safety
guidelines for staff, personnel and sub-contractors, including personal safety, site conduct, security, site
safety zoning and emergency procedures;
In common with Performance Standard 2, on site medical facilities must be made available throughout the
construction phase for the use of workers. Trained health and safety and first aid personnel must be identi-
fied to workers as part of their training schedule;
Suitably qualified personnel must be chosen for potentially hazardous activities such as for the installation
and testing of specialist electrical equipment;
225 | 278
Appropriate action must be taken for outbreaks of illnesses amongst workers, minimising the transmission
as far as is possible;
The EPC contractor must establish a Human Resources Policy which will be communicated to employees
with information including, but not limited to, their rights under national labour and employment laws, salary,
and other associated information, such as medical care and insurance. The Human Resources Policy will
ensure an approach of non-discrimination is followed with equal opportunities for all. No child labour or
forced labour will be used for the proposed facility;
In common with Performance Standard 1 (Section 23), the establishment of a ‘grievance mechanism’ for
workers and local residents, will involve the identification of a local environmental co-ordinator, identified by
the EPC within the management structure, to identify and log all concerns. This contact information will be
provided to the public via appropriate transparent measures and a placard left on the perimeter of the site
with further details of contact arrangements. The resultant procedure to address these concerns will be
made clear to the complainant and a set process followed, as identified within the CEMP, and within a suit-
ably prompt period;
Throughout the construction and operation of the proposed facility, a long term training programme should
be implemented to ensure adequate training and qualification of all staff employed within the IPP and its as-
sociated facilities. The aim of this programme would be to ensure that personnel acquire and maintain the
combination of knowledge and demonstrated skills as required to safely and adequately fulfil their responsi-
bilities. The objective of the long term training plan will be to ensure that the facility is operated safely and
efficiently, while also guaranteeing the long term economic success of the project; and,
In common with Performance Standard 4, all components of, and infrastructure associated with, the project
will be constructed in accordance with industry best practice and by qualified engineers.
Impacts on Surrounding Communities
Construction activities undertaken for the Project will be managed in such a way as to minimise construction
impacts through the EHS Plan which will be implemented and monitored by the Contractor and any sub-
contractors, to include an update of existing EHS documentation. The EHS Plan will also be required to
incorporate all the mitigation measures identified within this ESIA, which is presented in Chapter 15. This will
ensure that the effects of construction works upon the local community is minimised.
In addition, a grievance procedure needs to be established for local residents to ensure that any issues are
resolved to the satisfaction of all parties. This will include the following:
Clear contact numbers for key construction management staff who can be contacted in the case of
complaints, which could be posted on signage near to the site access gates or in leaflets distributed to the
local community; and
A clear grievance procedure which involves studying the basis of complaints, identifying corrective actions
and communicating the response to the complainant.
Project number: 37446130 Dated: 09/11/2014 226 | 278 Revised:
Construction Phase Residual Effects 13.7.2
With the implementation of the CEMP it is considered that health and safety risks for construction site workers,
particularly the risks of serious injury, illness or fatalities are significantly reduced and therefore the residual
significance is predicted to be minor negative significance.
With the implementation of the mitigation measures set out above it is predicted that the residual impacts upon
construction staff in relation to their working conditions and welfare will be negligible significance.
Nuisance to nearby landuses due to increased dust, noise, emissions, traffic and increased levels of activity will
be kept to a minimum with the use of construction corridors and low-noise producing equipment, where
possible. These mitigation measures will be identified and implemented through a CEMP. Following the
implementation of such techniques, the impact is deemed to be a negligible impact on a short-term basis,
although concerns from residents will be iterative. As such, the CEMP must be viewed as an ‘organic’
document which will require constant updating in view of new concerns coming to light, and allowing the
addressing of such concerns.
The residual effects of the construction of the Plant on the local businesses will be a minor positive effect.
The residual effects related to potential social issues relating to the presence of a construction workforce will be
negligible.
The residual impacts of indirect employment opportunities and influx of professional workers during the
construction are both of minor positive significance.
Construction Phase Cumulative Effects 13.7.3
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Operational Phase Mitigation Measures 13.7.4
It is recommended that the following measures are adopted during the operational phase of the Project, ideally
within an Operational Environmental Management Plan (OEMP), a framework for which is provided in Chapter
16:
Operational Worker Welfare
To provide the employees with a safe and risk free environment, it is recommended that a comprehensive
EHS plan is developed and implemented. This framework, in line with Performance Standard 2, will
address measures for accident prevention, identification, mitigation and management of hazards (including
physical, chemical, and radiological hazards), training of workers and reporting of accidents and incidents;
Occupational noise standards need to be maintained as part of the Health and Safety of the employees at
the facility. It is therefore important that noise levels in working areas are limited to less than 85 dB(A) at
227 | 278
1m from any noise generating equipment. It is further recommended that a full occupational noise survey is
undertaken in the interests of the health and safety of the site employees;
In accordance with Performance Standard 2, the Project should develop and implement a human resource
policy outlining the management approach towards working conditions, entitlement to wages and any
benefits and terms of employment. This policy must be disseminated and accessible for all employees,
clearly defining the employees’ legal rights and the management’s statement on child labour, forced labour
and on non-discrimination and equal opportunities. This policy will also provide the mechanism through
which employees can express and register their concerns and the system through which these grievances
will be addressed;
Expatriate staff must be provided with an induction course (as part of their training), which will highlight
local customs, cultures and living conditions in KSA. The objective of this course will be to familiarise the
expatriate staff with knowledge of their host country and provide an understanding and respect for other
cultures. The aim will be to reduce, prevent and mitigate against social and cultural tensions and potential
hostility between workers and the residents of surrounding communities;
The provision of facilities for workers, such as kitchen facilities, dining areas, washrooms, and a mosque,
will minimise the placing of undue pressure on existing local services;
Where feasible, staff will be of local origin where suitably qualified applicants are available. This will ensure
a degree of balance between the use of non-Saudi Arabian workers and locally employed personnel during
the operational phase, and limit the impact on the local economy;
In common with Performance Standard 4, all components of and infrastructure associated with the Project
will be operated in accordance with industry best practice by qualified staff; and
In line with IFC Performance Standard 1, it is also recommended that a grievance mechanism is
established for local residents, giving them a platform to raise any concerns.
Noise Nuisance
The predicted environmental noise emissions from the Project during the operational phase are below the noise
criteria based on the supplied noise data, therefore no significant noise nuisance upon nearby sensitive
receptors is expected and no additional mitigation measures are required.
However, it is important to note that there are also occupational noise standards that need to be maintained as
part of the Health and Safety of the employees at the facility. It is therefore important that noise levels in
working areas are limited to less than 85 dB(A) at 1m from any noise generating equipment.
Air Quality Impacts on Human Health
The key mitigation requirement which can be implemented relates to the stack design of the Project. SEC
requirements are for the HRSG stacks to be a minimum of 60m which has been shown to be more than
adequate to ensure acceptable ground level concentrations.
Project number: 37446130 Dated: 09/11/2014 228 | 278 Revised:
All combustion units and associated plant on-site will be subject to a regular inspection, servicing and
maintenance programme to ensure optimal efficiency and ensure, as far as practicable, all equipment is in
good working order at all times and will minimise pollutant emissions.
Emissions of NOx, SO2 and PM10 from the Project will be continuously monitored using a Continuous
Emissions Monitoring System (CEMS).
Ambient air monitoring of NOx, SO2 and PM10 using a continuous air quality monitoring station should be
considered to verify the current baseline and impact of the existing facilities in the airshed.
Impacts on Local Businesses
The detailed design of the Project must consider measures to minimise or avoid any impacts upon the existing
fish farming operations.
Operational Phase Residual Effects 13.7.5
Given the remote location of the project site and lack of developments (existing or proposed) in the surrounding
area cumulative impacts are not expected to be a major concern.
Operational Phase Cumulative Effects 13.7.6
It is not considered that there will be any Type 1 significant cumulative effects during the operational phase of
the Project. Type 2 cumulative impacts will be related to the
Summary and Conclusions 13.8
It is generally thought that the development of the Project will have a positive impact on the local economy,
particularly in terms of local job creation, and if the mitigation measures detailed above, and within the
framework OEMP delivered as part of this ESIA are followed. In addition, it will be the responsibility of the EPC
contractor and Operations and Maintenance Company to develop comprehensive Environmental Management
Plans specific to the construction and operation of the proposed facility.
Due to the provision of additional employment opportunities during both construction and operation, the
proposed facility is expected to represent a positive employment option which may draw prospective residents
back to the region.
Key economic benefits that are thought likely to be derived from the proposed facility include:
The creation of temporary and permanent jobs during the construction and operational phases of the pro-
posed development;
The potential for labour and procurement contracts to be let locally during the construction phase and the
capital cost of the redevelopment; and,
229 | 278
The potential for indirect increased local spending from the incoming workforce.
The main negative impact would be associated with impacts upon the existing fish farm to the north of the site.
Discharges from the facility during operation have the potential to affect the farming operations.
Project number: 37446130 Dated: 09/11/2014 230 | 278 Revised:
Table 13-2 Impact and mitigation summary table for socio-economic
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Workers health and safety: Construction sites are considered to be a relatively dangerous working environment and without proper health and safety controls there is a considerable risk of serious injury or fatalities.
High sensitivity Negligible to major adverse
Development of a CEMP which include the following measures (for example):
The development of a Health and Safety and Environmental Policy shall provide detailed health and safety guidelines for staff, personnel and sub-contractors, including personal safety, site conduct, security, site safety zoning and emergency procedures;
On-site medical facilities must be made available throughout the construction phase for the use of workers. Trained health and safety and first aid personnel must be identified to workers as part of their training schedule; and
Suitably qualified personnel must be chosen for potentially hazardous activities such as for the installation and testing of specialist electrical equipment.
Minor adverse
Working and accommodation conditions such as working hours, wages and housing.
High sensitivity Moderate adverse All relevant labour and working condition laws and guidelines
must be adhered. Negligible
Dust and noise nuisance upon surrounding communities. Low sensitivity Negligible
Construction activities undertaken for the Project will be managed in such a way as to minimise construction impacts through the EHS Plan which will be implemented and monitored by the Contractor and any sub-contractors, to include an update of existing EHS documentation; and
A grievance procedure needs to be established for local residents to ensure that any issues are resolved to the satisfaction of all parties.
Negligible
231 | 278
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Influx of professional workers into the area generating economic opportunities and rewards for the local population of Al Muwaylih.
Low to medium sensitivity Minor positive
As the impacts are considered to be positive there is no requirement for any mitigation measures to be implemented.
Minor positive
Indirect employment opportunities for various support service providers including guards, cleaner etc.
Low to medium sensitivity Minor positive Minor positive
Influx of professional workers causing social and cultural tensions in the community.
Low to medium sensitivity Minor adverse
Clear grievance procedure and ease of contact maintained between the local residents and businesses. Negligible
Operational Phase
Workers health and safety. High sensitivity Moderate adverse
Development of an OEMP which include the following measures (for example):
Implementation of a comprehensive EHS plan; and
It is therefore important that noise levels in working areas are limited to less than 85 dB(A) at 1m from any noise generating equipment. It is further recommended that a full occupational noise survey is undertaken in the interests of the health and safety of the site employees.
Minor adverse
Noise nuisance upon local receptors.
Low to high sensitivity Negligible
The predicted environmental noise emissions from the Project are below the noise criteria based on the supplied noise data, therefore no significant noise nuisance upon nearby sensitive receptors is expected and no additional mitigation measures are required.
Negligible
Project number: 37446130 Dated: 09/11/2014 232 | 278 Revised:
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Potential health impacts upon the employees as a result of SO2, NOx and particulates exceedences.
High sensitivity Negligible
The key mitigation requirement which can be implemented relates to the stack design of the Project;
All combustion units and associated plant on-site will be subject to a regular inspection, servicing and maintenance programme;
Emissions of NOx, SO2 and PM10 will be continuously monitored using a Continuous Emissions Monitoring System (CEMS); and
Ambient air monitoring of NOx, SO2 and PM10 using a continuous air quality monitoring station should be considered to verify the current baseline and impact of the existing facilities in the airshed.
Negligible
Influx of professional workers into the area generating economic opportunities and rewards for the local population of Al Muwaylih.
Low to medium sensitivity Minor positive
As the impacts are considered to be positive there is no requirement for any mitigation measures to be implemented.
Minor positive
Indirect opportunities for various support service providers and other site management providing employment and a further source of income for these services.
Low to medium sensitivity
Minor to moderate positive
Minor to moderate positive
Improvement of the workers capabilities and skills thanks to the training received for this type of Project.
Low to medium sensitivity
Negligible to minor positive
Negligible to minor positive
233 | 278
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Additional pressure on local services due to the additional employees required.
Low to medium sensitivity
Negligible
Development of an OEMP which include the following measures (for example):
The provision of facilities for workers, such as kitchen facilities, dining areas, washrooms, and a mosque, will minimise the placing of undue pressure on existing local services;
Where feasible, staff will be of local origin where suitably qualified applicants are available. This will ensure a degree of balance between the use of non-Saudi Arabian workers and locally employed personnel during the operational phase, and limit the impact on the local economy;
The Project should develop and implement a human resource policy outlining the management approach towards working conditions, entitlement to wages and any benefits and terms of employment; and
Expatriate staff must be provided with an induction course (as part of their training), which will highlight local customs, cultures and living conditions in KSA.
Negligible
Labour and working conditions. High sensitivity Minor adverse Minor negative
Impacts upon the existing fish farming operations associated with the plant sea outfall
High sensitivity Negligible The plant is not expected to have adverse impacts upon the
existing fish farm based on the results of the preliminary marine modelling study.
Negligible
Project number: 37446130 Dated: 09/11/2014 234 | 278 Revised:
14 Cultural, Heritage and Archaeology
Introduction 14.1
The Tabouk region is recognised to be rich in its antiquities and archaeological sites such as petroglyphs, forts,
and Syrian-Egyptian pilgrimage route. The Al-Muwaylih Fort, which dates back to the sixteenth century AD, is
located approximately8km south of the Project site.
Despite this, no features of archaeological or cultural significance were identified on or near to the site.
Management measures have been defined in Chapter 16 to ensure chance archaeological finds are dealt with
appropriately during construction.
235 | 278
15 Landscape and Visual
Introduction 15.1
This chapter determines the significance of the project in terms of visual impact by defining the character of the
existing landscape and locating potentially significant viewpoints. The purpose of this chapter is to describe,
determine and assess the existing character and visual resources of the Project site and its immediate
surroundings.
This chapter also evaluates the likely visual impacts of the development on the landscape during the
construction and operational phases and, where appropriate, pertinent mitigation measures are proposed.
Although landscape impacts and visual impacts are interrelated, it is instructive to briefly explain the difference
between ‘landscape’ and ‘visual’ impacts:
‘Landscape’ refers to the appearance of the land (its shape and colour for example). It is not just a visual
resource but is also shaped by a number of factors, such as the topography, geology and ecology of the ar-
ea. Generally, landscape impacts are changes that affect the character and quality of a landscape, due pri-
marily to development.
Whilst, ‘visual’ impacts relate solely to changes in the available view or views of the landscape, and, im-
portantly, the effect of such changes on people.
Relevant Standards 15.2
There is no legislation in Saud Arabia concerning the landscape and visual impacts of a project.
Methodology 15.3
The methodology used follows and incorporates accepted international best practice, such as information
detailed within the ‘Guidelines for Landscape & Visual Impact Assessment (2002), produced from a combined
venture between the UK’s Institute of Environmental Management and Assessment, the Landscape Institute;
and Morris and Therivel (2001), particularly in relation to. Including a site survey undertaken in May 2014 to
establish the character of the existing site and its surroundings and the relationships of the site to adjacent
areas and public views points towards the site.
Project number: 37446130 Dated: 09/11/2014 236 | 278 Revised:
Existing Baseline Conditions 15.4
The project site is coastal with sandy and rocky beaches on the seaward side. Behind are raised flat gravel
areas intersected by dry wadi beds with relatively lush vegetation. The site could be described as being a
natural remote and scenic coastal area. Figure 15-1 shows representative images of the project site.
View towards the coast across the project site
The sandy beach on the coastal side of the site
View inland from the project site
Typical feature wadi on site
Figure 15-1 Representative image of key site features
The main viewpoint of the site would be vehicles passing on the road parallel to the inland side of the site or
boats viewing the site from offshore. There are no other significant viewpoints.
237 | 278
Assessment of Construction and Operational Phase Impacts 15.5
Construction Phase Impacts 15.5.1
During the construction phase, plant and equipment, including large cranes, will be present on the site. Prior to
mitigation, such structures are likely to have a temporary impact of minor negative significance.
Operational Phase Impacts 15.5.2
The proposed project will be visible during the operational phase, since the facility is expected to cover an area
of approximately 1.5 km by 1.0 km. However, the presence of a power plant in this area will have an impact
upon the visual character of the landscape. This is assessed as being a permanent impact of moderate
negative significance.
14.6 MITIGATION MEASURES, RESIDUAL AND CUMULATIVE EFFECTS
Construction Phase Mitigation Measures 15.5.3
Implementation of site hoardings in strategic areas and general good site management practices related to
material stockpiling and waste management will be the main mitigation measures during construction.
Construction Phase Residual Effects 15.5.4
Given the temporary nature of the construction operations and the site location, the residual effects will be
temporary and of negligible significance.
Construction Phase Cumulative Effects 15.5.5
Impacts relating to the landscape and visual aspects of proposed development are unlikely to contribute to
cumulative impacts associated with construction works at the site.
Operational Phase Mitigation Measures 15.5.6
The surrounding area is remote with limited existing human influences. It is considered that the visual impact on
the areas will be of moderate significance and limited mitigation will be required. It is proposed within the
Landscaping Plan that a vegetated buffer is planted around the inland side of the site.
Operational Phase Residual Effects 15.5.7
Given the nature of the locality and lack of sensitive receptors, it is anticipated that the overall residual impact
will be of permanent but moderate negative significance.
Project number: 37446130 Dated: 09/11/2014 238 | 278 Revised:
Operational Phase Cumulative Effects 15.5.8
Impacts relating to the landscape and visual aspects of proposed development are unlikely to contribute to
cumulative impacts associated with operations at the site.
Summary and Conclusions 15.6
The proposed project site is located in a remote coastal landscape with limited sensitive receptors (view
points). However, the presence of a power plant in this area will have an impact upon the visual character of
the landscape. There are limited opportunities for mitigating the permanent impact of this kind of facility.
However, it recommended planting a vegetated buffer along the inland side of the power plant to improve the
aesthetic appearance.
239 | 278
Table 15-1 Impact and mitigation summary table for landscape and visual
Impact Overview Receptor Sensitivity
Impact Significance Key Mitigation Residual
impact
Construction Phase
Construction activities (cranes, excavations, etc.) will have a temporary adverse impact on the landscape character of the surrounding area.
Medium sensitivity Minor adverse
Site hoardings; and
Good site management – material stockpiling, waste management etc.
Minor adverse
Operational Phase
The permanent presence of the project will have an adverse effect on the natural, remote and scenic nature of the surrounding environment.
Medium sensitivity
Moderate adverse
Using vegetation to act as a visual buffer in strategic areas. Moderate adverse
Project number: 37446130 Dated: 09/11/2014 240 | 278 Revised:
16 Framework Construction Environmental Management Plan
Purpose of the CEMP 16.1
This chapter proposes a framework for pollution control and best practice measures that should be adopted
during the construction phase of the Project in order to avoid, minimise, or offset likely impacts in the areas on
and surrounding the site that are attributable to the project.
It is recommended that the mitigation requirements set out within this Framework Construction Environmental
Management Plan (CEMP) chapter will be included in full within any Project Environmental, and Health and
Safety (EHS) Plan or CEMP established by the construction contractor and other associated standalone
documents where relevant.
The updated Project EHS Plan or CEMP will therefore provide a logical extension of the ESIA process and will
ensure that recommendations contained within the ESIA are implemented, assuring that the Project does not
deviate from the environmental and social profile that formed the basis of this document.
In a similar vein the Project EHS Plan or CEMP will serve to ensure that requirements of the General
Environmental Regulations (GER, 2006) and, where relevant, the IFC Operational Standards and Guidelines
are also met and serve as a clear and auditable indication as to how those requirements are implemented
during the construction phase.
The primary objective of the Project EHS Plan or CEMP will be to provide a clear direction on the requirements
of the construction contractor and all subcontractors in their activities: each requirement is measurable and
enforceable; hence any non-compliance can be identified and addressed swiftly.
The objectives of the Project EHS Plan or CEMP are defined as follows:
Prescribe an overall management structure with clearly defined accountabilities and responsibilities;
Ensure an environmental management structure responsible for implementing the relevant measures within
the Framework CEMP;
Ensure adequate and relevant environmental induction training for all contractors and subcontractors
(including construction workers);
Incorporate Emergency Planning into the management system;
Stipulate a programme of deliverables, meetings, audits, communication protocols and reporting
requirements to monitor and manage the construction works;
241 | 278
Define objectives and targets for environmental and social management on the construction activities
(these objectives and targets will be captured in the detailed Environmental Control Plans of the full Project
EHS Plan or CEMP);
Implement Mitigation Measures and Monitoring Programmes;
Prescribe a mechanism for recording and reporting environmental and social concerns, improvement,
complaints or incidents;
Define the communications protocols for liaison with local communities and regulatory authorities on
environmental and social matters;
Ensure compliance with all regulatory requirements of the GER 2006 and with all IFC operational standards
and Guidelines, where relevant; and
Stipulate a mechanism for periodical review for the Project EHS Plan or CEMP.
ISO 14001 Model 16.2
One of the most widely used environmental management systems, developed by the International Standards
Organisation (ISO), is the ISO14001 standard for environmental management of activities. The standard
provides a logical framework within which to prepare and develop the Project Environmental Health and Safety
Plan and subsequent formal EMS (if applicable). The structure of a typical EMS certified to ISO 14001 is shown
in Table 16-1.
Table 16-1 ISO 14001 Structure
Project number: 37446130 Dated: 09/11/2014 242 | 278 Revised:
CEMP Implementation 16.3
Resources, Roles, Responsibility 16.3.1Environmental governance will be clearly set out and maintained as a stand-alone document by the
Construction Project Director for the duration of the project. This structure will be agreed prior to and during the
construction phases. Although individual sub-contractors may have adequate controls in place when reviewed
independently, the Construction Project Director is the lead contractor for EHS in the proposed scheme and
has the authority to update, replace or approve them as appropriate to ensure its responsibilities are met.
These relationships will be set out in an organisational chart which will be supported by a more detailed
description of the roles and responsibilities of the organisations such as Construction Project Director, Site
Manager, Site EHS Manager, Subcontractors Site EHS representatives etc. All construction teams with a
significant project involvement should be consulted as part of the development process.
Clear roles and responsibilities for internal staff will also be specified for the construction phase which will
include responsibility for both environmental as well as health and safety issues. The definition of roles and
responsibilities is an important part of environmental governance and allows for discreet management of tasks
and involvement throughout the project team.
It is everyone’s responsibility to ensure that the Project EHS Plan or CEMP policies and applicable Client’s
procedures are adhered to.
Training and Induction Procedure 16.3.2Competence, training and awareness are critical to the effective implementation of the Project EHS Plan or
CEMP, and therefore all site personnel and visitors must attend an EHS induction course which includes
environmental awareness in order to gain an understanding of the environmental aspects and associated
environmental mitigation measures related to the construction phase.
An Induction and Training Procedure will be developed to cover aspects of training involving those personnel
and activities likely to have a significant effect on the environment, including: Induction Training for New Site
Personnel including General Site Induction, Supervisors Site EHS Training, Visitor Induction and Toolbox
Talks.
In addition, the Project EHS Plan or CEMP will be updated in order to include Specialist Training for individuals
with specific roles and responsibilities, including but not limited to: Chemical and fuel handling, Hot Work,
Handling or organic solvents, Handling of toxic materials etc.
Environmental Incident Procedure 16.3.3A site specific emergency procedure for all foreseeable eventualities that pose significant risks to site
personnel, local communities and the environment will be developed and will need to be implemented and
adequately communicated to all involved parties during the construction phase of the project. These emergency
243 | 278
plans will be supported by planned simulated training exercises in order to test their robustness and
practicability.
CEMP Compliance 16.3.4The Project EHS Plan or CEMP will set out how the compliance of construction activities will be periodically
inspected and audited through:
Routine inspections:
Areas Supervisor’s Weekly Inspections;
Site Managers Weekly EHS Tour;
Site EHS Managers Inspections; and
Routine daily Surveillance Inspections.
EHS Audits:
Subcontractor Audits, undertaken within the first month of the arrival of the subcontractor, then
subsequently on a 6 monthly basis;
EHS Road map Self-Assessment;
EHS Road map Verification Assessments; and
Internal Site Audits.
Client and Third Party Audit.
Non-conformances Management Procedure 16.3.5Any deviations from the Project EHS Plan or CEMP identified by site personnel or other parties through formal
site inspections, audits, visual observations or other mechanisms, would need to be documented and
associated corrective action and preventative action implemented by competent individuals in order to mitigate
the environmental impacts and to prevent re-occurrence.
Complaints Management Procedure 16.3.6A Complaint Procedure will be established in order to effectively address all complaints received by the project
management team and construction contractor; outlining roles and responsibilities, and timeframes for
investigation and resolution of complaints.
Environmental Review Procedure 16.3.7A review of any Project EHS Plan or CEMP will be required in order to ensure that all requirements of this
Framework CEMP are included and to ensure continual improvement, suitability and effectiveness of the
overall management system.
Project number: 37446130 Dated: 09/11/2014 244 | 278 Revised:
Environmental Control Plans 16.3.8Specific Environmental Control Plans (ECP) detailing mitigation measures which must be implemented during
the construction phase of a project in order to minimise potential environmental and social impacts. This will
include as minimum all mitigation measures identified within the ESIA.
Typically the structure of an ECP will be as follows:
1. Environmental Impacts;
2. Responsibilities;
3. IFC Guidelines;
4. Standards; and
5. Environmental or Social Issue(s):
a. Objective;
b. Target;
c. Responsibilities;
d. Mitigation measures;
e. Monitoring Activities;
f. Reporting; and
g. Records Management.
Environmental Aspects and Mitigation Measures 16.4
An assessment of construction activities will be conducted to determine the significant environmental aspects
and resulting impacts, taking into consideration normal, abnormal and emergency operation, together with the
location of the sensitive receptors identified.
The environmental aspects will be determined and ranked based on an approved methodology, which will be
consistent with the ISO 14001:2004 Standard for Environmental Management Systems and detailed within the
Project EHS Plan or CEMP.
Each contractor and sub-contractor will be required to undertake their own review of the Environmental Aspect
Register, which includes the potential environmental impacts of the project during the construction phase. This
sets out the construction activities where mitigation measures will be implemented. They will also be required to
use the same approach provided in the methodology detailed within the Project EHS Plan or CEMP to
determine the significance of any new aspects and impacts resulting from a new construction activity if the
methodology differs significantly from what has been assumed in advance of the appointment of the
245 | 278
construction contractor. This will therefore identify any additional environmental aspects and impacts which
would need to require additional mitigation measures.
The ESIA has identified the following aspects that require control during the construction phase:
Marine Environment;
Air Quality;
Noise and Vibration;
Solid Waste Management;
Socio Economic;
Soils, Geology and Contamination;
Water Resources and Wastewater;
Marine Environment 16.4.1During the construction phase, the following mitigation measures shall be implemented:
A marine construction and dredging plan will be developed to avoid, or substantially reduce and / or mitigate
the potential impacts upon identified receptors, including:
– A justification for the selection of the dredging technology will be utilised;
– Details of all mitigation and management measures proposed for dredging and marine construction;
– The plan for disposing of the dredge material; and
– Environmental monitoring requirements.
If a cetacean or other sensitive species is spotted within the surrounding area, the work will not commence.
Observations will continue during work and works will cease as a response to any sightings and will begin
again only 30 minutes after last sighting;
Marine construction will not be undertaken during inclement weather conditions;
Suitable dredging methods will be used to minimise the loss of sediments into the neighbouring water col-
umn and cause minimum disturbance to the marine ecology of the area;
Marine construction areas shall be bunded where possible.
Fences will be erected for near water construction areas to minimise rock and soil fall or waste materials
migrating into the marine environment;
Fuels, oils, hazardous chemicals and hazardous wastes shall be stored in covered, bunded areas to ensure
that spillages are isolated from the storm water system and therefore cannot discharge into the sea;
Project number: 37446130 Dated: 09/11/2014 246 | 278 Revised:
Dewatering effluents must not be discharged directly to the marine environment – settlement basins and silt
screens will be used and the turbidity of the resultant water measured frequently;
Silt screens will be employed where practicable in order to reduce the dispersion of sediments; and
Total Suspended Solids (TSS) in sea water will be monitored continuously at various locations in and
around the dredging/construction work areas in order to assess the sediment transport and the resultant im-
pacts.
Air Quality 16.4.2
Mitigation Measures by construction activities
Stockpiling of friable materials
Minimize stock pile heights (circa. 3m);
Pile surfaces will be as smooth as possible to reduce wind erosion. An irregular pile surface will create
turbulence that aggravates dust;
When reclaiming from stockpiles, loaders will work on the lee side (sheltered side) of the pile where its
activity is sheltered from the wind;
Stockpiled materials shall be covered with tarpaulin type materials to prevent wind blowing off dust from
these areas; and
Good housekeeping to make sure that unnecessary stockpiled waste material does not accumulate and
become airborne pollution.
Vehicle movement
Vehicles and vessels carrying loose aggregate should be covered at all times;
Vehicles should not be overloaded while transporting sand, as this may lead to spillage and littering of
roads;
Keep vehicles equipment as free from dust as possible; and
Make sure tailgates of trucks are secured properly to prevent spillage of aggregate and clean up
spillages immediately;
Temporary site roads and any unpaved areas will be watered to avoid excessive dust. The frequency of
watering will be determined by weather conditions (wind, humidity, temperature) and the erodibility of
the soil;
Existing roads to be utilized to the maximum extent;
The contractors will ensure that adequate supply and storage of water is available on site for dust
suppression;
247 | 278
Speed of vehicles will be restricted to 15 km/h along the temporary site roads and any unpaved areas of
the site to avoid creating excessive dust;
Fencing of construction area to prevent external vehicle movement on site;
Any machinery which is intermittent in use will be shut off during periods of non-use, or if not practical to
be throttled back to a minimum;
Washing of vehicle tyres to prevent dust emissions during movement outside the Project site; and
Provision of covers on vehicles transporting soil or other loose materials.
Unpaved Roads
New direct access roads would be constructed providing clearly designated haul routes;
Existing tracks would either be compacted and/or water sprayed;
Designated working corridors would assist in controlling the routes for vehicle access across the site
and reducing airborne dust;
Regular non-potable water spraying (dust suppression) of the haul roads with water sprinklers;
Regular inspection and, if necessary, cleaning of surrounding roads to check for dust deposits (and
removal if necessary);
Keep speed limit to 15km/hr on site, with signs erected to this effect; and
Paving of roads will stop dust emissions from these surfaces, which has already been undertaken for
the site access road.
Materials handling
Operators must exercise caution to maintain minimum height for dropping of aggregate materials;
Loader operators should be trained to avoid overfilling their bucket and spilling aggregate on the carry
over to the trucks; and
Operators must be trained to observe potential problem conditions. For example, the loader takes a cut
from a pile just to see how dusty it is. If it looks like a problem, wet the pile down.
Grading
Grading of material is potentially a source of dust. It is envisaged that such operations will not generally
be undertaken during periods of high wind and will be subject to stringent application of dust
suppression sprays.
Cement batching
On-site cement and concrete batching, where required, will be undertaken in suitable areas, with wind
shielding to avoid wind-blown dry cement.
Project number: 37446130 Dated: 09/11/2014 248 | 278 Revised:
Exposed areas
Plant naturally occurring (endemic), desert adapted trees and shrubs around the perimeter of the site to
act as a wind and dust screen;
Do not remove any existing site vegetation unless absolutely necessary; and
Cover exposed dust generating areas with shade cloth materials until needed.
Climatic conditions
During extremely windy conditions, activities should be temporarily ceased to prevent excessive dust
generation.
Demolition
Dust suppression using spraying of treated water on land and buildings;
Water spraying will prevent dust generation due to demolition of buildings and other facilities;
Demolition to be avoided during high wind speeds; and
Screens to be provided for each demolition activity to prevent dust emissions to nearby receptors.
Excavation
Spraying of water on the ground before excavation to moist the area and prevent dust emissions; and
Loading of materials into the trucks by excavators to be carried out from minimum height to prevent dust
generation.
Piling
Spraying of water on the ground before piling to moist the area and prevent dust emissions.
Sand blasting
Barriers or protective screens to be installed around any sand blasting areas to avoid the dispersion of
fugitive dust.
Sand blasting of materials, if required, to be conducted in offsite locations prior to shipment to site based
on the feasibility.
Construction Vehicles and Plant Air Emissions
Exhaust emissions from Vehicle and Machinery
Heavy machinery will be serviced prior to commencement of construction. Any emission filters or
catalytic converters (in the case of petrol engines) will be tested for compliance with supplier’s
specifications. In the case of non-compliance, they will be replaced;
249 | 278
Motor vehicles and plant equipment are to be fitted with appropriate exhaust equipment to minimise
emissions;
The contractor shall inspect the machinery, vehicles and vessels every morning for defects (indicator
lights, oil leaks) and excessive emissions;
All vehicles and machinery including diesel power generators will be frequently maintained and serviced
to manufacturer specifications with at least a major service every 6 months;
Clean fuel, i.e. low sulphur diesel will be used.
Black smoke will not be allowed from construction equipment.
Idling of vehicles will be avoided at site. Vehicles will be switched off when not in use.
Proactive liaison with the PME and local residents for any complaints;
All complaints pertaining to the construction vehicles and plant machinery will be recorded as well as
immediate actions taken to rectify the situation;
Unnecessary journeys will be avoided;
The combustion of any waste materials including waste oils on site will not permitted under any
circumstances;
When possible the use of mains powered electrical equipment should be used in preference to using
generators to provide power; and
Ensure limited escape of gases during maintenance works.
Gaseous Substances
Gaseous Hazardous Substances
These substances must be appropriately stored with the necessary warning signage, in accordance with
the MSDS;
Personnel using such substances must be trained in the safe handling of such substances; and
Personnel must be provided with the necessary safety equipment to protect against any possible
harmful emissions.
Noise Management 16.4.3
General
It is recommended that regular noise monitoring is undertaken within close proximity of noise sensitive
locations, especially if future works include activities which are known to cause significant levels of noise;
Project number: 37446130 Dated: 09/11/2014 250 | 278 Revised:
In order to control the duration of noise and vibration from the construction activities, no noise from the
works will be audible at the application site boundary of any occupied residential property outside the hours
of:
Saturday to Wednesday 08:00 - 18:00
Thursday 08:00 - 13:00; Or
No working on Friday or Public Holidays.
If noise exceeds the required standards the use of acoustic screens or noise attenuation measures will be
implemented (refer to standards below);
Stationery machinery such as generators must be kept in enclosed structures for noise control during the
night;
Items of plant on site operating intermittently will be shut down in the intervening periods between uses;
Electrically powered plant should be preferred, where practicable, to mechanically powered alternatives.
All mechanically powered plant should also be fitted with suitable silencers;
Proper PPE to be provided to all personnel working in high noise areas;
Appropriate breaks to be provided to personnel working in high noise areas;
High noise sign boards to be placed in high noise areas such as piling, excavation, cutting, grinding, etc.
Backfilling
Backfilling activities will be restricted to day time hours.
Excavation and material handling
Loading of materials into the trucks by excavators to be carried out from a minimum height to prevent high
noise; and
Excavations to be restricted to day time hours.
Piling
Piling activities to be conducted during the day time;
Use of vibratory hammer rather than impact hammer to reduce noise levels;
High frequency vibrator hammer to be used rather than low frequency based on the type of piling; and
Moveable acoustic sound barrier for the hammer and piling equipment to be provided near to receptors
such as accommodation and other facilities.
Cutting, bending and welding
Cutting of steel rods and other building materials to be conducted in separate areas; and
251 | 278
Machinery used for cutting to be adequate to ensure low noise generation.
Sand blasting
Sand blasting, if required will be conducted during day time and in closed environment with temporary
noise barriers.
Vehicle movement
Speed restriction of 15 kmph to be enforced on internal roads to minimise noise from vehicle movement;
Vehicle movement and delivery of materials will be avoided at night time (6pm to 6am) to ensure minimum
disturbances to the nearby receptors;
Vehicle deliveries will be organised in order to avoid pile of delivery trucks leading to high noise levels; and
Deliveries will be routed so as to minimise disturbance to nearby communities. Delivery vehicles will be
prohibited from waiting within or near the site with their engines running. The movement of heavy vehicles
during the night will be avoided wherever practical.
Construction equipment
Noise from vehicles, machinery and equipment used on site will not exceed the manufacturer’s
specifications, based on the installation of adequate noise reduction systems;
Equipment and machinery will be regularly serviced to ensure that they are kept in good condition, with
attention given to muffler maintenance and noise reduction systems;
Noisy equipment and machinery will be replaced with less noisy alternatives or provide equipment that is
specifically designed with noise inhibitors, such as generators and compressors with silencers and muffled
jackhammers;
Acoustic covers and barriers must be used on all machine engines that generate excessive noise levels;
Any machinery will be shut off during periods of non-use or, if not practical to do so, will be throttled back to
a minimum; and
Where possible, ensure that operation times of noisy equipment, machinery and activities are carried out
during daytime hours.
Solid Waste Management 16.4.4The aim of the proposed mitigation measures during the construction phase is to ensure adherence to the
waste management hierarchy of the ‘3 Rs’: “Reduce – Reuse – Recycle”, and to present procedures for the
correct segregation and disposal of the waste streams. Waste streams will be collected by locally registered
waste contractors and transferred to appropriately licensed waste facilities for recycling or disposal. A chain of
custody relating to the waste will be implemented with the aim of ensuring the waste is handled and disposed of
correctly by suitable qualified contractors.
Project number: 37446130 Dated: 09/11/2014 252 | 278 Revised:
Non Hazardous Solid Waste Management 16.4.5
Waste Storage
Damage to materials from incorrect storage will be avoided;
Loss, theft, or vandalism will be avoided through secure storage and on-site security;
Effective segregation of waste streams will be undertaken to facilitate onsite reuse and offsite recycling
where possible;
Construction workers will be informed and trained with regards to waste minimisation throughout toolbox
talks;
Dedicated containers for segregated waste streams for reuse/recycling/disposal will be located under cover
on an impermeable hardstanding surface and will be located at strategic locations in the onsite compound;
These containers will be stored in a covered and enclosed area when practicable to provide protection from
the elements and scavengers;
Dedicated skips for any residual construction waste that requires off-site disposal will be located under
cover on an impermeable hardstanding surface in a designated area. Key waste streams will include any
excavated soil from building foundations and waste chemicals / oils will be located in the on-site
construction compound;
Waste storage on site will be in designated and appropriately signed area(s). Skips will be clearly labelled
to specify the waste streams which can be recycled or disposed of;
Waste that is generated during construction will be classified as hazardous or non-hazardous and stored
appropriately;
Domestic solid waste generated within workers accommodation areas will be stored in specified areas prior
to removal and disposal by the specifically appointed waste management sub-contractor;
Food waste will be collected and stored within an allocated skip and disposed of by a specifically appointed
waste management sub-contractor; and
Storage practices will be implemented across the site in order to ensure that any wastage is kept to a
minimum.
Waste Minimisation and Waste Recycling
Over ordering will be avoided;
Ordering standard lengths rather than lengths required will be avoided;
Ordering for delivery at an inadequate time (update programme regularly) will be avoided;
Conventional dry recyclable materials (paper, cardboard, plastic etc.) will be either reused on site or
removed by licensed contractors for recycling;
253 | 278
The following dry recyclable materials will be reused or recycled; Glass, papers and cardboard, metals
(other than aluminium), aluminium, organic waste and plastic could be recycled;
Containers will be suitably marked and stored in a covered and enclosed area to ensure that the weather
and/or scavengers cannot access them;
Recyclable materials will be collected by recycling contractors registered with the PME;
Excavated material from the construction activities will be reused for backfilling and other activities,
wherever possible;
Welding rods will be used to the maximum extent prior to disposal only certified welders will be employed
for welding purposes;
Metal waste from cutting will be reused on site to the maximum extent possible;
Waste metal scrap will be collected in separate bins or skips and disposed to waste metal recyclers;
Leftover concrete after casting will be reused for the construction of temporary works;
Where possible, materials will be ordered in bulk to reduce packaging;
Suppliers will be requested to use minimal packaging or take back packaging such as plastic drums;
Dedicated skips for segregated waste streams for re-use/recycling will be located under cover on an
impermeable hardstanding surface in the onsite construction compound(s);
Dedicated skips for any residual construction waste that requires off-site disposal will be located under
cover on an impermeable hardstanding surface. Key waste streams will include any excavated soil from
building foundations and waste chemicals / oils will be located in the on-site construction compound;
Suppliers will be required to reduce surplus packaging associated with any construction raw materials;
particularly common packaging materials such as plastics (shrink wrap and bubble wrap), cardboard and
wooden pallets. This will also involve improved procurement and consultation with selected suppliers
regarding commitments to waste minimisation, recycling and the emphasis on continual improvements in
environmental performance;
Concrete/cement will be purchased from local ready mix works, where possible, to allow materials to be
generated in close proximity to the site, thereby allowing for ‘just-in-time’ resource ordering and minimising
transport costs associated with haulage of raw and finished or semi-finished products;
Material deliveries will be efficiently planned in order to avoid damage to the materials and the unnecessary
generation of waste;
Coordination between local contractors and suppliers will be effective in order to avoid the excessive
purchase of raw materials and to prevent the risk of materials being lost, stolen or damaged;
Handling and storage of delivered materials will be effective in order to prevent loss or damage through
exposure to the weather, mud and onsite vehicles through:
Project number: 37446130 Dated: 09/11/2014 254 | 278 Revised:
Ensuring well-timed deliveries to the site;
Providing on-site security; and
Installing temporary site security fencing.
Conventional wastes (paper, cardboard, plastic etc.) will be either reused by approved firms or removed
from site by licensed contractors preferably for recycling;
Any construction waste materials will be reused where feasible, for example, timber and other scrap
material representing commercial value shall be separated and stored in a segregated area prior to reuse
or recycling (including selling of products to third parties);
Damage during unloading operations will be avoided through careful handling;
Damage to materials from incorrect storage or handling will be avoided;
Temporarily site security fencing will be installed; and
On-site 24h security will be provided and together with temporary site security fencing.
Waste Handling and Transport
Damage during unloading operations will be avoided;
Delivery to inappropriate areas of the site will be avoided;
Acceptance of incorrect deliveries, specifications or quantities will be avoided;
PME approved certified waste contractors will be sourced in order to regularly remove the separated waste
streams;
All relevant consignments of waste (waste manifests) for disposal or recycling will be specify: type,
destination and name of the carrier. This will indicate whether the waste is to be treated, recycled or
disposed of to a landfill site and discharge liability from the waste producer by ensuring that disposal
activities are in accordance with local regulations;
On site waste auditing at each stage of the construction process is required as part of the audit programme
in order to develop and to allow reporting on waste management targets and to ensure that the Project
EHS plan or CEMP is being adhered to;
The segregated materials for recycling will be collected on an agreed basis with a local waste recycling
contractor;
The construction contractor will perform biannual inspection of all waste management facilities for their
areas of assignment and based on this audit, contracts will be renewed or rejected;
Industrial / domestic waste containers will be checked prior to leaving the PROJECT site to ensure that:
The waste containers are clean on the outside, sealed, and not leaking;
255 | 278
The required forms for wastes and other documents required for shipment are completed and correct;
and
Waste separation will be undertaken by staff wearing suitable PPE such as gloves and dust masks.
Waste Disposal
All non-hazardous waste generated on site, if it is not suitable for reuse either on site or off-site, must be
disposed of at a landfill site, which is licensed by PME;
A licensed waste management contractor will be appointed for all removal of waste from site and delivery to
the PME licensed landfill; and
Collection of all non-hazardous construction waste will be undertaken at least daily.
Staff Training
Training will be provided to educate all construction workers regarding best practice waste management
practices and recycling initiatives, and to encourage more sustainable working practices. Emphasis will be
placed on the waste minimisation hierarchy: “Reduce, Reuse, and Recycle”;
All workers will be provided with a comprehensive induction awareness program outlining which wastes
must be segregated in adequately labelled containers;
Specific PPE and training will be provided; and
PPE must be worn by employees at all times.
Hazardous Waste Management 16.4.6
Identification
All identified contamination areas, generated by historical or existing incidents and hazardous waste (e.g.
chemical/fuel drums) will need to be appropriately stored, removed and diverted to a licensed hazardous
waste landfill site prior the development of the area.
Storage
The construction contractor will nominate EHS representatives to manage hazardous wastes on site. These
individuals will be responsible for ensuring the correct placing, construction, maintenance and
housekeeping of the hazardous waste storage areas;
Accurate record keeping of hazardous waste types and amounts will be undertaken. This will take place on
a monthly basis or as new hazardous waste stream is produced. The following information shall be kept up
to date for each hazardous waste stream:
Name and description of the hazardous waste stream;
Project number: 37446130 Dated: 09/11/2014 256 | 278 Revised:
Classification (e.g. code, class or division) of the hazardous waste stream;
Quantity of the hazardous waste stream produced per month;
Characteristic(s) of the hazardous waste stream (e.g. flammability, toxicity);
Hazardous Waste Responsibility Details; and
Inventory of all hazardous wastes on site, which should be updated daily. This should be available for
Emergency crews in case of an event.
Any waste fuels, oils and chemicals will be stored separately in a bunded compound situated on an
impermeable surface in order to prevent any potential spillage and contamination issues prior to collection
for appropriate disposal;
Storage areas will be clearly marked and signed with regard to the quantity and hazardous characteristics
of the hazardous waste streams materials stored therein;
Hazardous wastes will be stored in a container which has sufficient strength and structural integrity to
ensure that it is unlikely to burst or leak in its ordinary use;
Any unused materials, spent containers, contaminated clothing, rags and tools will be returned to a central
compound, where practicable, for appropriate disposal;
For liquid hazardous waste streams, the waste container will be situated within a secondary containment
system which will satisfy the following requirements:
It must have a capacity of not less than 110% of the container’s storage capacity or, if there is more
than one container within the system, of not less than 110% of the largest container’s capacity or 25% of
their aggregate capacity, whichever is the greater;
It must be positioned, or other steps must be taken, so as to minimise any risk of damage by impact so
far as is reasonably practicable;
Its base and walls must be impermeable to water and oil;
Its base and walls must not be penetrated by any valve, pipe or other opening which is used for draining
of the system; and
If any fill pipe, or draw off pipe, penetrates its base or any of its walls, the junction of the pipe with the
base or walls must be adequately sealed to prevent hazardous wastes escaping from the system.
Each individual drum, package or container will be clearly labelled. Internationally recognised warning
signage shall be used to indicate the hazards of the individual hazardous waste materials;
Where any drum is used for storage in conjunction with a drip tray as the secondary containment system, it
is sufficient if the tray has a capacity of not less than 25% of:
The drum’s storage capacity; or
257 | 278
If there is more than one drum used at the same time with the tray, the aggregate storage capacity of
the drums.
Incompatible hazardous wastes will be segregated and stored separately. For example, flammable liquids
and other organics must be segregated from acidic and caustic materials;
Where there is risk of a spill of hazardous wastes, a spill control, prevention, and countermeasure plan will
be established as a specific component of the Site Emergency Preparedness Plan;
Storage areas will be constructed such that any spillage or loss of containment of a particular hazardous
waste type cannot spread to other material types. This is particularly important where flammable materials
are involved;
Covered plastics containers will be provided in the first aid area (for waste syringes, suturing kits and
needles) and also clearly identified bagging for infectious or contaminated items;
Containers holding hazardous wastes will be clean, in good condition, not leaking, and compatible with the
waste being stored within;
Regular inspection and maintenance of storage areas including drums, vessels, pavements and bunds will
take place;
The stated maximum capacity of waste storage areas will not be exceeded; and
There will be vehicular and pedestrian access at all times to the whole of the waste storage area such that
the transfer of containers is not reliant on the removal of impediments which may be blocking access, other
than drums in the same row.
Handling
Staff members will be assigned to manage hazardous wastes on site, to make sure that hazardous wastes
are handled in the correct manner in order to reduce the risk of accidents;
Prior to commencing work involving handling waste materials, all personnel will be familiar with the relevant
hazardous properties and instructed on the relevant emergency plan;
Personnel will wear appropriate PPE according to the type of hazardous waste they are working with;
The use of drip trays for liquid hazardous waste will be compulsory in order to contain any spills;
Any spillage of fuel or oils waste into the marine environment will be efficiently contained with oil booms
and pumps will be readily available to pump out any spillages; and
Emergency procedures will be put in place in case of spills.
Transportation
Contractors responsible for transporting hazardous wastes from the site will be suitably qualified and
possess a license from the PME to perform such work;
Project number: 37446130 Dated: 09/11/2014 258 | 278 Revised:
The vehicles will be in a good condition and will be suitable for the material being conveyed;
A transportation document will be created in order to establish a chain-of-custody, using multiple signed
copies to demonstrate that the hazardous waste stream has been transported and received by the disposal
facility in the correct manner (such as intact, non-leaking labelled containers, licensed transporter, correct
handling);
Employees involved in the transportation of hazardous waste will be trained regarding proper transport
procedures and emergency procedures;
Hazardous wastes will be labelled, and external signs on transport vehicles will be appended;
Competent individual(s) will be available for emergency response on call 24 hours/day;
Hazardous wastes will be transported outside of peak traffic hours;
A material safety data sheet shall be filled in for each item of hazardous waste. These forms will be kept on
record for at least 5 years following completion of the construction phase; and
Any spillages during transport will be removed and disposed of in a manner decided by the PME and the
Civil Defence.
Social Aspects 16.4.7
Construction Workers Welfare Management
The implementation of Project EHS Plan or CEMP will ensure that all health and safety guidelines for
construction workers, personnel and sub-contractors are followed and any potential risk is mitigated and
managed. The Project EHS Plan or CEMP will include detailed practices on undertaking safe work in relation to
the following:
The use of PPE will be mandatory;
Control measures will be implemented with regards to the use and the storage of hazardous substances;
A permit to work system for potentially hazardous work will be established;
Control measures will be established in relation to:
Crane operation;
Working at heights;
Using scaffolding;
Using ladders and steps;
Barricading;
Electrical safety;
259 | 278
Welding, cutting and grinding;
Working in confined spaces;
Excavations; and
Working over and near water.
Emergency response procedures will be developed;
First aid procedures (including the provision of first aid kits);
Provision of an ambulance service; and
Disciplinary action for non-compliance.
Local Communities Management 16.4.8
Grievance Mechanisms for Local Communities
Contact details and nominated individuals will be provided to local communities through the following
means:
Project Notice Board; and
Newsletter.
All complaints and claims will be acknowledged within 48 hours of receipt by being reported to the
construction contractor;
The construction contractor will assign and dispatch an Investigation team following a complaint;
Investigation tasks will be agreed, delegated and actioned by the investigation team;
Remedial actions recommended by the investigation team will be implemented and finalised;
Complainant will be contacted by the construction contractor and advised on the outcome of the
investigation within one week unless additional information or clarifications are needed;
Complaints and actions taken will be discussed on a monthly basis between the relevant parties;
Recording will involve:
Date and time of the complaint;
Method by which the complaint was made;
Personal details of the complainant;
Nature of the complaint;
The action to be taken; and
Details of the response provided to the complainant.
Project number: 37446130 Dated: 09/11/2014 260 | 278 Revised:
Project Notice Board
To ensure visible and clear notification, the construction contractor will erect notice boards with key
contacts (e.g. nominated environmental representative) at specific positions, and pro-actively communicate
with members of the public; and
The site notice board will display information on the construction activities, as well as contact numbers, all
of which could be used to contact responsible staff members or lodge specific complaints.
Project Newsletters
Project Newsletters would be disseminated to the relevant parties in order to ensure that ongoing feedback
is provided on the progress and environmental and social management performance of the project to a
broad group of parties affected by construction activities.
Contamination 16.4.9
Hazardous Materials Management
Sourcing of Hazardous Materials
The procurement manager will look at substitution of any hazardous substances with safer alternatives and
limit the quantities of hazardous substances during the construction process to reduce the risk of spillages.
Storage
The construction contractor and nominated staff members will have responsibility to ensure the correct
management of hazardous materials on site. These individuals will be responsible for ensuring the correct
placing, construction, maintenance and housekeeping of the hazardous materials storage areas, in addition
to provide toolbox talks and training on the control of substances and informing relevant employees of all
control measures, health and safety issues and location of spill response equipment on-site;
The storage area will be designed as to prevent damage to containers by any means, the unauthorized use
of material and contain any spillage from hazardous materials (e.g.: by the use of an impermeable surface
and walls).
Types, nature, characteristic of the hazardous materials will be recorded on site, and available to all
personnel;
The unauthorised use of hazardous materials will be prevented by requiring a responsible person to sign
materials in and out of a compound;
Where practicable, substances during the construction process will be retained in a central controlled
storage compound in accordance with World Bank guidance and appropriate risk assessment based on
the material safety data sheet provided by the supplier;
Storage areas will be clearly marked and signed with regard to the quantity and hazardous characteristics
of the materials stored within;
261 | 278
The storage areas will be designed in order to prevent damage to containers by any means and the
unauthorized use of material.
Hazardous materials will be stored in a container which is sufficient strength and structural integrity to
ensure that it is unlikely to burst or leak in its ordinary use;
The container will be situated within a secondary containment system;
Any valve, filter, sight gauge, vent pipe or other equipment ancillary to the container (other than a fill pipe or
draw off pipe or, if the oil has a flashpoint of less than 32oC a pump) will be situated within the secondary
containment system;
Where a fill pipe is not within the secondary containment system, a drip tray will be used to catch any spills
when the container is being filled;
Each individual drum, package or container will be clearly labelled. Internationally recognised warning
signage shall be used to indicate the hazards of the individual hazard materials;
Where any drum is used for storage in conjunction with a drip tray as the secondary containment system,
the drop tray will have a capacity of not less than 25% of:
The drum’s storage capacity; or
If there is more than one drum used at the same time with the tray, the aggregate storage capacity of
the drums;
Incompatible, hazardous materials will be segregated and stored separately. For example, flammable
liquids and other organics must be segregated from acidic and caustic materials;
Where there is risk of a spill of hazardous materials, responsible parties will prepare a spill control,
prevention, and countermeasure plan as a specific component of the Site Emergency Plan;
Storage areas will be constructed such that any spillage or loss of containment of a particular hazardous
material type cannot spread to other material types. This is particularly important where flammable
materials are involved;
The storage area will prevent damage to containers by any means;
Covered plastics containers will be provided in the first aid area (for syringes, suturing kits and needles)
and also clearly identified bagging for infectious or contaminated items;
Containers will be stored in such a manner that leaks and spillages cannot escape over bunds or the edge
of the sealed drainage areas;
Regular inspection and maintenance of storage areas including drums, vessels, pavements and bunds will
be undertaken;
The stated maximum capacity of storage areas will not be exceeded;
Project number: 37446130 Dated: 09/11/2014 262 | 278 Revised:
The use of hazardous substances during the construction process will be reviewed and when feasible
decreased in order to reduce the risk of spillages;
There will be vehicular and pedestrian access at all times to the whole of the storage area such that the
transfer of containers is not reliant on the removal of impediments which may be blocking access, other
than drums in the same row; and
Washout from concrete mixing plant or from cleaning ready-mix concrete vehicles is highly alkaline. This
will not be allowed to enter the marine environment and will be re-used on site where possible or stored
appropriately and removed by a licensed contractor to a PME approved facility.
Handling
All identified contamination areas will need to be appropriately removed and diverted to a licensed
hazardous waste landfill site prior to the development of the area;
Work methods will be updated if the production or release of potentially contaminative materials occur;
All vehicle/plant re-fuelling will be closely supervised and appropriate spill trays utilised where appropriate;
Competent staff member(s) will be assigned to manage hazardous materials on site, in order to ensure that
that hazardous materials are handled in the correct manner to reduce potential accidents;
Prior to commencing work involving handling materials, all personnel will be familiar with the relevant
hazardous properties and instructed on what to do in case of an emergency and location of spill response
equipment on-site;
Personnel must wear appropriate PPE according to the type of hazardous materials they are working with;
Machinery will be situated on sealed surfaces to prevent contamination of soil and groundwater below with
oils, chemicals or fuels;
Use of drip trays will be compulsory to contain spills;
Vehicle and plant refuelling will be closely supervised and spill trays utilised;
Refuelling areas and hazardous materials usage areas must be set back at least 50m from any water
drainage system;
All vehicle/plant re-fuelling will be closely supervised;
The use of potentially hazardous material will be away from high risk areas;
Enclosing the process or handling system as far as reasonably practicable; and
Emergency procedures will be put in place in case of spills.
Fixed tanks
Any fixed tank used for storing oil shall satisfy the following requirements:
263 | 278
Any sight gauge will be properly supported and fitted with a valve which must be closed automatically when
not in use;
Any fill pipe, draw off pipe or overflow pipe will be positioned, or other steps must be taken, so as to
minimise any risk of damage by impact so far as is reasonably practicable;
Fixed tanks will be adequately protected from physical damage;
Fixed tanks will have adequate facilities for detecting any leaks;
If fitted with a leakage detection device which is used continuously to monitor for leaks, the detection device
will be maintained in working order and tested at appropriate intervals to ensure that it works properly;
If not fitted with such a device, Fixed tank must be tested for leaks before it is first used and further tests for
leaks must be performed, in the case of pipes which have mechanical joints, at least once in every 5 years
and, in other cases, at least once in every 10 years;
Fixed tanks will be adequately protected against corrosion;
Fixed tanks will be fitted with an automatic overfill prevention device if the filling operation is controlled from
a place where it is not reasonable practicable to observe the tank and any vent pipe;
Where Hazmat is delivered through a flexible pipe which is permanently attached to the container;
The pipe must be fitted with a tap of valve at the delivery end which closes automatically when not in
use;
The tap or valve must not be capable of being fixed in the open position unless the pipe is fitted with an
automatic shut off device;
The pipe must be enclosed in a secure cabinet which is locked shut when not in use and is equipped
with a drip tray or the pipe must have a lockable valve where it leaves the container which is locked shut
when not in use; and
Be kept within the secondary containment system when not in use.
Any pump will be:
Fitted with a non-return valve in its feed line;
Positioned, or other steps must be taken, so as to minimise any risk of damage by impact so far as is
reasonable practicable; and
Protected from unauthorised use.
Mobile Bowsers
Any mobile bowser used for storage must satisfy the following requirements:
Any tap or valve permanently fixed to the unit through which oil can be discharged to the open will be fitted
with a lock and locked shut when not in use;
Project number: 37446130 Dated: 09/11/2014 264 | 278 Revised:
Where oil is delivered through a flexible pipe which is permanently attached to the unit:
The pipe must be fitted with a manually operated pump or with a valve at the delivery end which closes
automatically when not in use;
The pump or valve will be provided with a lock and locked shut when not in use; and
The pipe must be fitted with a lockable valve at the end where it leaves the container and must be
locked shut when not in use.
Transportation
Contractors responsible for transporting hazardous materials to the site will be suitably qualified and
possess a license from the PME to perform such work;
The vehicle will be in a good condition and will be suitable for the material being conveyed. Compartments
must also be cleaned prior to being filled;
A transportation document will be created to establish a chain-of-custody using multiple signed copies in
order to demonstrate that hazardous materials have been transported and received by the disposal facility
in the correct manner (such as intact, non-leaking labelled containers, licensed transporter, correct
handling);
The volume, nature, integrity and protection of packaging and containers used for transport will be
appropriate for the type and quantity of hazardous material and modes of transport involved;
Employees involved in the transportation of hazardous materials will be trained regarding proper transport
procedures and emergency procedures;
All hazardous materials to be transported will be labelled and external signs on transport vehicles will be
appended;
Competent individual(s) will be available for emergency response on call 24 hours/day;
The transportation of hazardous materials outside of peak traffic hours will be forbidden; and
Any spillages during transport will be removed and disposed of in a manner decided by the PME and the
Civil Defence.
Emergency Preparedness and Response
Procedures for the handling of hazardous materials will be established in order to ensure quick and efficient
responses to accidents that may result in injury or environmental damage;
An detailed Emergency Preparedness and Response Plan supporting will be developed as soon as possible
to cover:
Informing the public and emergency response agencies;
265 | 278
Documenting first aid and emergency medical treatment;
Taking emergency response actions;
Reviewing and updating the emergency response plan to reflect changes and ensuring that the
employees are informed of such changes;
Emergency Equipment: The plan should include procedures for using, inspecting, testing, and
maintaining emergency response equipment; and
Training: Employees should be trained in any relevant procedures.
Where there is risk of a spill of uncontrolled hazardous materials, the construction contractor will prepare a
spill control, prevention, and countermeasure plan as a specific component of their Emergency Prepared-
ness and Response Plan. The plan will be tailored to the hazards associated with the Project, and includes:
Training of operators on release prevention, including drills specific to hazardous materials as part of
emergency preparedness response training;
Implementation of inspection programs to maintain the mechanical integrity and operability of pressure
vessels, tanks, piping systems, relief and vent valve systems, containment infrastructure, emergency
shutdown systems, controls and pumps, and associated process equipment;
Preparation of written Standard Operating Procedures (SOPs) for filling containers or equipment as well
as for transfer operations by personnel trained in the safe transfer and filling of the hazardous material,
and in spill prevention and response;
SOPs for the management of secondary containment structures, specifically the removal of any
accumulated fluid, to ensure that the system remains structurally intact;
Identification of locations of hazardous materials and associated activities on an emergency plan site
map;
Documentation of availability of specific personal protective equipment (PPE) and training needed to
respond to an emergency;
Documentation of availability of spill response equipment sufficient to handle at least initial stages of a
spill and a list of external resources for equipment and personnel, if necessary, to supplement internal
resources; and
Description of response activities in the event of a spill, release, or other chemical emergency including:
Internal and external notification procedures;
Specific responsibilities of individuals or groups;
Decision process for assessing severity of the release, and determining appropriate actions;
Facility evacuation routes; and
Project number: 37446130 Dated: 09/11/2014 266 | 278 Revised:
Post-event activities such as clean-up and disposal, incident investigation, employee re-entry, and
restoration of spill response equipment.
Contaminated Soil Handling
Contaminated soil will be stored separately on hard standing area to prevent soil and groundwater
/seawater contamination; and
Contaminated soil will not be stored along with uncontaminated material and will be bunded and covered to
prevent any run off.
Construction Equipment
Vehicles and equipment will be regularly inspected and maintained to confirm they are not leaking or drip-
ping;
All stationary diesel and petrol operated construction equipment will have impervious drip trays placed be-
neath them during operation;
Operators will also be instructed to notify their supervisors if there are any problems with their vehicles and
equipment;
Refuelling of construction equipment will only be carried out in designated areas not at machinery work loca-
tions, in order to avoid potential spills of fuel to the ground;
Refuelling areas will be sealed to contain any spills or leaks that may occur and will be communicated to all
site personnel by signs and notice boards; and
Washing of vehicles to be undertaken in specific locations and wastewaters to be routed to separate holding
tanks.
Fuel and Chemical Handling and Storage
Fuels and chemicals must be stored on non-permeable surfaces with sufficient bund wall with a 110% ca-
pacity of the fuel tank or chemical;
Diesel dispensing tanker to be used for refuelling construction equipment to the maximum extent possible;
Fuel tanks and chemical storage area to be provided with covered roof;
Reduce the quantities of hazardous materials (fuel) stored on site to minimum practical levels. Infrequently
used chemicals will be ordered just before they are needed;
Different types of chemicals will be stored separately according to their Material Safety Data Sheets
(MSDS), in order to avoid adverse chemical reactions;
Hazardous materials will be handled only by operators trained in spill response procedures; and
All vehicle/plant re-fuelling will be closely supervised.
267 | 278
Piling
Piling accompanied with hazardous drilling fluids will not be used; and
Soil contaminated during piling activities to be removed and disposed of as hazardous waste through con-
tractors authorised by the PME.
Sand Blasting
Sand blasting areas will be concreted or provided with non-permeable membrane.
Painting areas
Paint drums will be stored on non-permeable membrane / concrete flooring to prevent seepage into soil in
case of accidental spillage; and
Painting area will be concreted to ensure no contamination of soil in the area.
Concrete Batching
Concrete agitator bowls and chutes must not be washed out to any stormwater system or roadways;
All process waste water will be drained to a collection pit for recycling or disposed;
Wastewater stored within the recycling system will be used at the earliest possible opportunity; and
No discharges of used process water will be allowed to the stormwater drainage system or the marine envi-
ronment.
General
Water will not be extracted from any borehole installations for construction purposes;
Domestic wastewater tanks will be regularly checked for leakages and emptied at periodic intervals;
Maintenance workshops for construction equipment will to be concreted and placed with spill control sys-
tems;
There will be no discharge or overflow of sanitary waste on site. Modular wastewater storage tanks will be
introduced to the site to provide adequate containment facilities for the construction workforce; and
Work methods will be updated in order to prevent the production or release of potentially contaminative ma-
terials.
Project number: 37446130 Dated: 09/11/2014 268 | 278 Revised:
Water Resources and Waste Water 16.4.10
Storm Water Run-Off and Erosion from the Construction Site
To protect the environment from flooding during heavy downpours, a localised run-off management system will
be employed by the Contractor. This will include temporary surface water run-off facilities, which in addition to
containing contaminants will provide on-site attenuation for surface water flows, thereby reducing the flood risk.
Best practice recommendations for the prevention of impacts associated with storm water runoff during the
construction phase include the following controls:
Areas where erosion may occur will be identified in order to ensure that they are appropriately protected by
installing the necessary temporary and/or permanent drainage works as soon as possible;
Any erosion channels which develop during the construction period will be suitably backfilled, compacted
and restored to a proper condition;
Where excavation takes place, the affected area will be properly stabilised to minimise erosion risk;
Appropriate storm water management measures will be established in order to ensure that contaminants are
not mobilised into the wider environment;
Stormwater control measures to control sediment will include:
Use of silt screens;
In the case of high volumes of stormwater flows, retention must be provided;
All erosion protection measures have to be maintained on a continual basis.
Limit disturbance when excavating;
Install sediment fences prior to rain events;
Wash equipment in designated area, where wastewater will be diverted to a sump or holding tanks;
Place sands and soils stockpile behind a sediment fence;
Store all hard waste and litter in designated area(s); and
Restrict vehicle movement to stabilised road access.
Generation of Sanitary Wastewater
There will be no discharge or overflow of sanitary waste on site. Modular wastewater storage tanks will be
introduced to the site to provide adequate containment facilities for the construction workforce;
Sanitary wastes generated during the construction phase will be collected and disposed of by a licensed
contractor;
269 | 278
Wastewater storage tanks will be introduced to the site to provide adequate containment facilities for the
construction workforce.
Functional and well maintained sanitary facilities will be available on site at all times;
Where there are temporary toilet facilities located on site, these will be placed on concrete bunds;
Adequate removal of sanitary liquid wastes from temporary toilet facilities, in conjunction with periodic in-
spections will avoid any overflow and create a zero leakage site; and
Removal of liquid sanitary waste from the septic system will be undertaken by a licensed waste manage-
ment sub-contractor.
Potentially Contaminated Wastewater
Any potentially contaminated water generated by construction activities including concrete washout and
plant washdown water will be diverted to a sump or a holding tank;
Any potentially contaminated wastewater will be removed by an appropriately licensed waste management
sub-contractor; and
A Chain of Consent System will be implemented to ensure that disposal of potentially contaminated liquid
waste is correctly undertaken and delivered to the correct, allocated treatment and disposal facilities.
Monitoring Programmes 16.5
An environmental monitoring programme will be developed and implemented by the construction contractor as
part of the Project EHS plan or CEMP.
The monitoring programme will include the ongoing review of emissions which will be reported to PME on an
annual basis and more frequently if there are abnormal conditions (e.g. uncontrolled emissions or spillages) or
changes which may affect the environmental quality of the emissions.
Marine Survey 16.5.1The condition of the marine environment at the site should be surveyed regularly at defined intervals during the
construction phase. This should include water quality and sedimentation measurements as well as assessing
the ‘health’ of coral reef areas adjacent to the works and at suitable control sites. The minimum recommended
interval for marine surveys is every six months.
Third Part Audits 16.5.2Third party audits should be undertaken by a suitably qualified professional to assess the implementation of the
CEMP on site during the construction phase. This should include a site inspection as well as review of
paperwork and records relating to environmental management on site. Third party audits should be undertaken
a minimum of once every six months.
Project number: 37446130 Dated: 09/11/2014 270 | 278 Revised:
Waste Management 16.5.3As part of the Project EHS or CEMP, all paperwork and records of waste management activities on-site will
need to be maintained including records of off-site disposal to landfill as follows:
SEC will maintain the following records and reports:
Keep one copy of each transport document it has generated pending receipt of the signed copy from the
facility designated in the document. It shall also keep the signed copy for at least 5 years as of the date
of receipt of the waste by that facility;
Retain copies of the results of all tests and analysis performed on the hazardous waste as well as
copies of all pertinent reports, correspondence and documents for at least five years from the last date
of handling of such waste;
Submit to the PME an annual report on all hazardous waste generated during the year. Copies of such
reports shall be retained for at least five years from the date of completion; and
Submit on demand to the PME or the agencies designated by it, all documents, records and reports
related to the waste.
Hazardous Waste Transporters and Hazardous Waste Management Facilities are required have both a
valid identification code and a work permit from the PME. The management of the Project should maintain
an up to date list of local contractors who can satisfy their requirements for the responsible handling and
disposal of hazardous waste.
271 | 278
17 Framework Operational Environmental Management Plan
Introduction 17.1
This chapter presents a Framework Operational Environmental Management Plan (OEMP), which aims to
manage environmental impacts and, to a lesser degree, the health and safety risks that may arise during the
operational phase of the Project.
It is highly recommended that SEC prepare a full OEMP on the basis of this framework to ensure that all
environmental controls, identified within this ESIA, are implemented. In this regard, an overall OEMP aims to
bridge the gap between the completion of the ESIA and the full implementation of the operational phase of the
project, with a key focus for implementing the mitigation measures as described within the ESIA in order to
minimise disturbance to the surrounding environment and sensitive receptors.
The proposed OEMP approach is based on the management philosophy of the ISO 14001 Environmental
Management System and OHSAS Occupational Health and Safety Assessment 18001 series; ensuring,
therefore, that the environmental and health and safety requirements of the Project during its operational phase
are not only planned, but that a robust mechanism for implementation is also ensured.
It is intended that this document provides a framework for the development of the full OEMP by SEC, which
would be fully established in consultation with all stakeholders, and adequately implemented by the operator.
Aims and Objectives 17.2
An OEMP is a management tool used to ensure that undue or reasonably avoidable adverse risks of the
operation of a project are prevented and that any positive effects are enhanced. The primary aim of the OEMP
is to provide clear direction on the requirements of the operational management team in the conduct of the
activities, where every requirement is measurable and enforceable, whilst any deviation can be identified and
addressed swiftly.
The main purpose of the OEMP is:
To ensure compliance with the General Environmental Regulations and Rules for Implementation in the
Kingdom of Saudi Arabia (2006); IFC Performance Standards (2006); and IFC General Environmental, and
Health, and Safety Guidelines (2007);
To ensure that all mitigation measures detailed within the ESIA are adequately implemented;
To verify environmental performance through information on impacts as they occur;
Project number: 37446130 Dated: 09/11/2014 272 | 278 Revised:
To ensure that there is sufficient allocation of resources within the project budget so that the scale of the
OEMP related activities are consistent with the significance of project impacts;
To respond to changes in project implementation not considered in the ESIA; and
To provide feedback for continual improvement in environmental and social performance.
Operational Environmental Management System 17.3
ISO 14001 provides a logical framework within which to prepare an OEMP, even for organisations not intending
to obtain certification. If effectively implemented, the methodology detailed below would lead to:
Compliance with legislative and other requirements;
Pollution Prevention; and
Continual Improvement.
An appropriate environmental management structure should be planned and agreed between all operating
parties and the relevant regulatory authorities. The structure should allow for the effective implementation of the
Environmental Management System (EMS) and the appropriate interaction with regulatory authorities.
Due regard should be paid to the building of relationships with regulators including the establishment of points
of contact for planned monitoring and environmental assessment. These contacts will be useful to assist in
developing a trusting and productive partnership that generates tangible benefits for environmental
management.
In this regard SEC should seek to involve relevant stakeholders in the development and implementation of an
environmental management system. These stakeholders may involve all parties from the client, PME and the
local community.
Operational Environmental Management System Components 17.4
Planning Phase 17.4.1Planning involves identifying and defining the various environmental aspects and associated environmental
impacts that can result from the operational phase of the project. In the case of the Project, the major potential
environmental and social impacts are as defined through the ESIA. The planning phase would typically include
the following requirements:
Environmental Policy
The development of an Environmental Policy would be aligned with other existing policies so that it can be
adopted as part of ‘business as usual’, provided this policy meets the expectations of all stakeholders, including
users and communities affected by the operational phase of the project.
273 | 278
The environmental policy will:
Include a commitment from top management to continual Environmental, Health and Safety (EHS)
improvement;
Commit to setting objectives and targets for key operational areas;
Be appropriate to the nature, scale and potential EHS impacts of its activities, products or services;
Include a commitment to continual improvement of the management system, enhance health and safety
controls and the prevention of pollution;
Include a commitment to comply with relevant EHS legislation and regulations, and with other requirements
to which the organisation subscribes;
Provide the framework for setting and reviewing EHS objectives and targets;
Be documented, implemented and maintained and communicated to all employees; and
Be available to the public.
Environmental Aspects
The EMS will set out the detailed process for the identification of significant EHS aspects and assess the level
of risk associated with each of those aspects, where a quantitative method would be used to determine the
significance of aspects. Those which are significant must be included in the setting of objectives and targets.
All EHS aspects (significant or not) shall be documented in a register along with method statements regarding
the assessment of significance; and aspects that are identified should be appropriate to the scale and nature of
the activities that are relevant to the project. They will include any impacts that the organisation can be
expected to have influence over.
Legal and Other Requirements
A site register will be compiled which details the relevant legislation that applies to EHS issues on site. This
register will include an assessment of the key requirements of the legislation and set out the specific actions
that must be undertaken to meet these requirements.
Where possible, further information sources should be specified or provided to staff should they need further
guidance. Other obligations refer to the formal and informal obligations regarding the local community and
society at large, including voluntary agreements.
Objectives, Targets and Programmes
A series of EHS objectives and targets should be developed which draw from the commitments of the EHS
policy, the legal requirements placed upon the organisation and the significant aspects identified.
The objectives and targets will however be set in the context of technological scenarios that are available, the
financial implications and the requirements of other stakeholders;
Project number: 37446130 Dated: 09/11/2014 274 | 278 Revised:
The organisation shall establish and maintain a programme for achieving its objectives and targets which shall
include:
Designation of responsibility for achieving objectives and targets at each relevant function and level of the
organisation; and
The means and time frame by which they are to be achieved.
If a project relates to new developments and new or modified activities, products or services, programme(s)
shall be amended where relevant to ensure that sound environmental management practices are applied to
such projects.
Implementation Phase 17.4.2Implementation and operation is the heart of the environmental management function, because it is in
implementation that the true efficacy of environmental management lies. Even the best planned environmental
management approach will fail to achieve its desired outcome if the implementation of that planning is weak.
Implementation and operation consists of two key components, namely: Management Structure, Roles and
Responsibility; and Operational Control.
Management Structure, Roles and Responsibilities 17.4.3Roles, responsibilities and authorities shall be defined, documented and communicated in order to facilitate
effective environmental management. Management shall provide resources essential to the implementation
and control of the EHS management system. Resources include human resources and specialised skills,
technology and financial resources.
The organisation’s top management shall appoint specific management representative(s) who, irrespective of
other responsibilities, shall have defined roles, responsibilities and authority for:
Ensuring the EHS management system requirements are established, implemented and maintained; and
Reporting on the performance of the EHS management system to top management, for review and as a
basis for improvement of the system.
Competence, Training and Awareness 17.4.4There must be processes for the assessment of competence within the workforce and a documented system
for managing competence and training records. Activities and competencies should be mapped to identify any
shortfalls or areas of potential risk. This will comprise details of all training programmes pertinent to the core
training processes, and schedules will be central to the success of the programme and should include:
Document controls for training;
Induction and toolbox talks;
Training plans for management and specialist skills;
275 | 278
Internal communication methods; and
Management of external communication on environmental issues.
As a minimum, all staff are required to be aware of the Environmental Policy and the responsibilities they have
with regards to contributing to this. In addition, staff with more specific roles may require more detailed
environmental awareness training as set out in the training programme. Training records must be maintained
appropriately including attendances and competency identification assessments.
Communication 17.4.5The organisation shall establish and maintain procedures for internal communication between the various
levels and functions of the organisation; receiving, documenting and responding to relevant communication
from interested parties. Internal communication is important to:
Raise staff awareness of the EHS management system;
Inform staff of progress towards objectives and targets;
Promote proactive participation in EHS activities, including feedback and ideas from staff on environmental
management; and
To allow effective action to be taken by qualified personnel if incidents occur.
The organisation shall establish and maintain information, in paper or electronic form, to:
Describe the core elements of the management system and their interaction; and
Provide direction to related documentation aspects.
Control of Documents 17.4.6The operator would set out a detailed procedure in order to:
Approve documents for adequacy prior to issue;
Review and update as necessary and re-approve documents;
Ensure that changes and the current revision status of document are identified;
Ensure that relevant versions of applicable documents are available at point of use; and
Ensure that document remain legible and readily identifiable.
Environmental Operational Control Plans 17.4.7Operational controls are an essential part of the operational environmental management system as it is at the
operational level at which many impacts can occur. It is therefore very important that the correct working
procedures and protocols are developed and followed.
Project number: 37446130 Dated: 09/11/2014 276 | 278 Revised:
The operational controls should be documented where they address any significant environmental aspects
identified at an earlier stage. This will include the discussion of mitigation procedures that should be addressed
within these protocols. Each effect will be considered in terms of relevant legislation and guidance, potential
impacts, sensitive receptors, baseline conditions and procedures and, where necessary, recommendations for
further monitoring will be provided.
When considering the requirement for procedures to be documented and communicated, the following should
be taken into account:
Extent of environmental risk represented by activity(ies) under consideration;
Potential for legal non-compliance and/or reputational impact to result;
The number and turnover of people responsible for implementation of the procedure;
The importance of ensuring a consistent approach to managing activities;
The complexity and technical detail to be taken into account when managing an activity; and
Value of documentation to communicate procedural requirements.
Emergency Preparedness and Response 17.4.8The nature of the project requires that strong emergency procedures are put in place. The operational EHS will
include an emergency management plan which will detail and maintain plans to identify the potential for, and
the responses to major site incidents including equipment failures, natural phenomenon and major pollution
incidents.
The organisation shall establish and maintain procedures to identify the potential for, and response to,
accidents and emergency situations and for preventing and mitigating the environmental impacts that may be
associated with them. Evacuation procedures will also be included.
Plans for all foreseeable eventualities that pose significant risks to staff or the local community or environment
must be drafted, communicated and made available. The appropriate training for such events should be
included within the training programme.
Planned simulated training exercises should be deployed at reasonable intervals to test the plans that have
been developed. The results should be recorded and fed into action plans for improvement.
Specific plans must be developed for major hazardous materials stores, fire and electrical safety as a minimum.
The organisation shall review and revise, where necessary, its emergency preparedness and response
procedures, in particular, after the occurrence of accidents or emergency situations. The organisation shall also
periodically test such procedures where practicable.
277 | 278
Checking Phase 17.4.9Checking and corrective action forms the fourth component of the environmental management function and is
aimed at ensuring that both the necessary environmental management activities are being implemented and
that the desired outcomes are being achieved. This component consists of a series of key activities including
monitoring selected environmental quality variables and continued inspections of the various operational
activities. This would also be supplemented by inspections and audits.
Monitoring and Measurement 17.4.10The organisation shall establish and maintain documented procedures to monitor and measure, on a regular
basis, the key characteristics of its operations and activities that can have a significant impact on the
environment or pose risk to health and safety. This shall include the recording of information to track
performance, relevant operational controls and conformance with the organisation’s environmental objectives
and targets.
Monitoring equipment shall be calibrated and maintained and records of this process shall be retained
according to the organisation's procedures.
Operational controls will detail the required monitoring for individual aspects and the results should be reported
in line with an appropriate programmed schedule. The organisation shall also establish and maintain a
documented procedure for periodically evaluating compliance with relevant environmental legislation and
regulations.
The operation controls for monitoring should consider the suggested monitoring scope as detailed below and at
a minimum to the level as required by pertinent environmental regulations and guidelines.
Evaluation of Compliance 17.4.11Comprehensive procedures will be deployed for the management of complaints, accidents and pollution
incidents. These procedures will include:
A process for handling the investigation of accidents, incidents, near misses and non-conformances;
Response activity coordination as a result of any of the above including preventative actions, mitigation and
corrective actions; and
The development and documentation of logging, reporting and progress tracking processes including a
change log of core EHS documentation.
Nonconformity, Corrective Action and Preventive Action 17.4.12Any deviations from the OEMP identified by site personnel or other interested parties through formal site
inspection, audit, visual observation (or other means) should be documented, and associated corrective action
and preventative action implemented by competent individuals in order to mitigate the environmental impacts
and to prevent re-occurrence.
Project number: 37446130 Dated: 09/11/2014 278 | 278 Revised:
Control of Records 17.4.13The organisation shall establish and maintain procedures for the identification and maintenance of EHS
records. These records shall include training records and the results of audits and reviews.
EHS records shall be legible, identifiable and traceable to the activity, product or service involved. EHS records
shall be stored and maintained in such a way that they are readily retrievable and protected against damage,
deterioration or loss. Their retention times shall be established and recorded.
Internal Audits 17.4.14The organisation shall establish and maintain programme(s) and procedures for periodic environmental
management system audits to be carried out, in order to:
Determine whether or not the EHS management system conforms to planned arrangements for EHS man-
agement and that is has been properly implemented and maintained; and
To provide information on the results of audits to management.
The organisation’s audit programme, including any schedule, shall be based on the environmental importance
of the activity concerned and the results of previous audits. In order to be comprehensive, the audit procedures
shall cover the audit scope, frequency, and methodologies, as well as responsibilities and requirements for
conducting audits and reporting results.
The audit programme will provide opportunities to ensure that the contents of the Environmental Policy and
other commitments are being duly satisfied.
The audit programme should be developed on the basis of the risk posed by various activities i.e. high risk
activities will receive more regular checking.
In addition the programme will:
Check on the performance of the EHS management plan;
Ensure document compliance;
Contribute to education and awareness of employees;
Share best EHS practice; and
Report findings, non-conformances, corrective actions and preventative measures.
Management Review Phase 17.4.15The project team’s top management shall, at intervals that are predetermined, review the EHS management
system to ensure its continuing suitability, adequacy and effectiveness. The management review process shall
ensure that the necessary information is collected to allow management to carry out this evaluation. This review
shall be fully documented.
279 | 278
The management review shall address the possible need for changes to policy, objectives and other elements
of the system in the light of the audit results, changing circumstances, and the commitment to continual
improvement.
Framework Operational Environmental Control Plans 17.5
Marine Environment 17.5.1The key impact during the operational phase will be the potential for adverse environmental impacts upon the marine
and coastal environment resulting from the operation of the cooling water intake and outfall.
It is recommended that the following key mitigation measures are implemented:
Provision of on-line process monitoring for the cooling water system and associated auxiliary processes,
particularly those requiring application of chlorine or chemical additives;
Chemical monitoring of individual effluent lines prior to mixing with the cooling water and a continuous
flow/quality monitor on the final effluent channel;
The provision of balancing/evaporation ponds to receive storm water drainage or flows associated with ab-
normal or emergency conditions;
Prevent planned or accidental discharge of chlorinated product water with effluent due to potential impact on
the benthic communities (i.e. coral reef) – discharge to an evaporation pond if not required;
Chemical stores to be within an enclosed structure on hard standing and with an impermeable bund equiva-
lent to 110% of the largest tank;
All oil storage tanks to have an impermeable bund capable of holding 110% of the largest tank;
Slow, phased, start-up of facility and discharge of effluent to facilitate a gradual acclimation of local biota
(i.e. minimise ‘shock effect’); and
Ensure that site staff are aware of the environmental management system and that there is an Environmen-
tal Co-ordinator for the site to record training, incidents etc.
A marine ecology marine monitoring programme will be implemented during the operational phase of the
Project to ensure that the impacts of the project are fully understood and offset where possible.
The monitoring programme should cover the affected area as well any areas considered part of the Habitat
Loss Compensation Strategy.
Air Quality 17.5.2 All plant on-site will be regularly maintained to ensure optimal efficiency and ensure, as far as practicable,
all equipment will be in good working order at all times.
Project number: 37446130 Dated: 09/11/2014 280 | 278 Revised:
The proposed facility will incorporate a Continuous Emissions Monitoring System (CEMS) for NOx, SO2 and
PM10. This would accurately determine pollutant concentrations in the emissions and provide an indication
of any exceedences in emissions from the plant against the PME and IFC air pollution standards.
Ambient air quality monitoring of NOx, SO2 and PM10 will be undertaken using a continuous air quality
monitoring station to verify the current baseline and impact of the existing facilities upon the air shed.
Operating instructions to be provided to ensure that machines do not operate above the allowed limits; and
A periodic calibration and maintenance programme will be implemented to maintain the monitoring systems
in place.
Noise and Vibration Management 17.5.3It is recommended that as part of the Operational Management Plan regular noise monitoring is undertaken at
the site boundary to show compliance with PME noise standards. It is further recommended that a full
occupational noise survey is undertaken in the interests of the health and safety of the site employees.
Occupational noise standards need to be maintained as part of the Health and Safety of the employees at the
facility. It is therefore important that noise levels in working areas are limited to less than 85 dB(A) at 1m from
any noise generating equipment.
In addition, to ensure the above noise levels are adhered to, procedures will be implemented to ensure that,
where appropriate, staff requiring Personal Safety Equipment to prevent impacts from noise will be provided as
part of the Health, Safety and Environment Programme.
Waste Management 17.5.4It is anticipated that the operational phase will generate waste streams associated with the plant operation,
maintenance works and administration functions. Once the plant is in operation it is important that waste
management is considered as a priority within the OEMP. Furthermore, waste recording and monitoring
requirements are set out in Section 16.5.1.
Management of Hazardous Waste 17.5.5The hazardous waste generated from maintenance works and plant operations are likely to include waste oils,
fuels, chemicals, empty containers and filters and replaced parts which may have associated hazardous
properties. Sludge from the water evaporation ponds, where toxic or other contaminants are expected to leach
out, should be treated before disposal by, for example, a stabilisation process.
Hazardous waste streams will be collected by a locally registered waste contractor and transferred to an
appropriately licensed hazardous waste facility for disposal. As part of the OEMP, all paperwork and records of
hazardous waste management activities on-site will need to be maintained including records of off-site disposal
to landfill.
281 | 278
The GER Appendix 4 (2006) “Hazardous Waste Control Rules and Procedures” details the requirements for
managing hazardous waste. A few of the key requirements are included below, which will need to be complied
with during the operation of the Project:
Containerise and pack hazardous waste in a proper and environmentally sound manner placing warning
labels on each package in accordance with the specifications and standards applicable in the Kingdom;
Accurately fill up the product data on the appropriate section of the hazardous waste transportation
document in accordance with the instructions provided in the document;
Confirm with the PME, that the storage, treatment or disposal facility designated in the transportation
document is capable of managing the waste that will be sent to it;
Make the necessary arrangements with both the transporter who will carry the waste and the receiving
facility designated in the transportation documents as the destination for the waste (such as providing the
facility with full and detailed information on the waste and samples for analysis);
Provide the transporter with the transportation document and copy of the safety data sheets for each type
of hazardous waste being transported; and
Comply with the hazardous waste transportation instructions provided in the transportation document;
The hazardous waste generator shall comply with the following for keeping of records and reports:
Keep one copy of each transport document it has generated pending receipt of the signed copy from the
facility designated in the document. It shall also keep the signed copy for at least 5 years as of the date of
receipt of the waste by that facility;
Retain copies of the results of all tests and analysis performed on the hazardous waste as well as copies of
all pertinent reports, correspondence and documents for at least five years from the last date of handling of
such waste;
Submit to the PME an annual report on all hazardous waste generated during the year. Copies of such
reports shall be retained for at least five years from the date of completion;
Submit on demand to the PME or the agencies designated by it, all documents, records and reports related
to the waste; and
Hazardous Waste Transporters and Hazardous Waste Management Facilities are required have both a
valid identification code and a work permit from the PME. The management of the Project should maintain
an up to date list of local contractors who can satisfy their requirements for the responsible handling and
disposal of hazardous waste.
In addition, adherence to the guidance set out within the IFC General EHS Guidelines: Community Health and
Safety, relating to the on-site and off-site transportation of waste is recommended. These guidelines require
that transportation of waste should be undertaken so as to prevent or minimise spills, releases, and exposures
to employees and the public. All waste containers designated for off-site shipment should be secured and
Project number: 37446130 Dated: 09/11/2014 282 | 278 Revised:
labelled with the contents and associated hazards, be properly loaded on the transport vehicles prior to leaving
the site, and be accompanied by a shipping paper that describes the load and its associated hazards.
Non-Hazardous Solid Waste Management 17.5.6
Solid wastes, including sewage treatment plant sludge, that do not leach toxic substances or other
contaminants of concern to the environment, may be disposed by suitably licensed contractors in landfills or
other disposal sites provided they do not impact nearby water bodies.
The administration buildings and offices on-site are likely to generate quantities of non-hazardous waste
streams including waste paper, cardboard, plastic packaging that have the potential to be segregated for
recycling. Therefore suitable waste receptacles will need to be provided at central locations on-site for the
segregation of waste streams for recycling and residual general waste. The segregated waste will be
transferred to the central storage area on-site for non-hazardous waste which will consist of dedicated
containers for recyclable waste and general waste. The storage area for non-hazardous waste will be located
on an impermeable hardstanding surface and located under cover.
The waste streams segregated for recycling and the general waste will be collected by a suitably qualified and
licensed waste contractor. As part of the OEMP, all paperwork and records of non-hazardous waste
management activities on-site and off-site disposal will be maintained for monitoring purposes.
Socio Economic 17.5.7
The operation of the Project will create economic opportunities for the local area. This is likely to include
increased business for services with the additional SEC workers and contractors. There will also be
opportunities for various support service providers including guards, cleaners, catering and other site
management facilities, which will provide employment and a further source of income.
However, one of the key issues is ensuring that operational staff employed by SEC and contractors, are
protected from workplace incidents and illness through appropriate health and safety systems both during
normal operation and other tasks such as maintenance and repair. Appropriate safety systems such as fire
protection and emergency procedures will also be required.
Operational Worker Welfare
It is recommended that the following measures are adopted during the operational phase of the Project:
Implementation of Saudi Arabian Labour Law;
To provide the employees with a safe and risk free environment, it is recommended that a comprehensive
EHS plan is developed and implemented. This framework, in line with Performance Standard 2, will
address measures for accident prevention, identification, mitigation and management of hazards (including
physical, chemical, and radiological hazards), training of workers and reporting of accidents and incidents;
283 | 278
In accordance with Performance Standard 2 SEC should develop and implement a human resource policy
outlining the management approach towards working conditions, entitlement to wages and any benefits and
terms of employment. This policy must be disseminated and accessible for all employees, clearly defining
the employees’ legal rights and the management’s statement on child labour, forced labour and on non-
discrimination and equal opportunities. This policy will also provide the mechanism through which
employees can express and register their concerns and the system through which these grievances will be
addressed;
Expatriate staff must be provided with an induction course (as part of their training), which will highlight
social and cultural trends in practice in Saudi Arabia. The objective of this course will be to familiarise the
expatriate staff with knowledge of their host country and provide an understanding and respect for other
cultures. The aim will be to reduce, prevent and mitigate against social and cultural tensions and potential
hostility between workers and the residents of surrounding communities;
Where feasible, staff will be of local origin where suitably qualified applicants are available. This will ensure
a degree of balance between the use of non-Saudi Arabian workers and locally employed personnel during
the operational phase, and limit the impact on the local economy;
In common with Performance Standard 4, all components of and infrastructure associated with the Project
will be operated in accordance with industry best practice by qualified staff; and
In line with Performance Standard 1 it is also recommended that a grievance mechanism is established for
local residents, giving them a platform to raise any concerns.
Noise Nuisance to Adjacent Land Uses
The assessment undertaken in Chapter 7: Noise and Vibration has determined that there will be no
exceedance of IFC or PME noise criteria at any noise sensitive locations. Therefore, there is no need for any
mitigation measures to be implemented. However, it is important to note that there are also occupational noise
standards that need to be maintained as part of the Health and Safety of the employees at the facility. It is
therefore important that noise levels in working areas are limited to less than 85 dB (A) at 1m from any noise
generating equipment.
It is recommended that as part of the OEMP, regular noise monitoring is undertaken at the site boundary to
show compliance with PME noise standards. It is further recommended that a full occupational noise survey is
undertaken in the interests of the health and safety of the site employees.
Air Quality Impacts on Human Health
All plant on-site will be regularly maintained to ensure optimal efficiency and ensure, as far as practicable,
all equipment will be in good working order at all times.
Project number: 37446130 Dated: 09/11/2014 284 | 278 Revised:
The proposed facility will incorporate a Continuous Emissions Monitoring System (CEMS) for NOx, SO2 and
PM10. This would accurately determine pollutant concentrations in the emissions and provide an indication
of any exceedences in emissions from the plant against the PME and IFC air pollution standards.
Ambient air quality monitoring of NOx, SO2 and PM10 will be undertaken using a continuous air quality
monitoring station to verify the current baseline and impact of the existing facilities upon the air shed.
Operating instructions to be provided to ensure that machines do not operate above the allowed limits; and
A periodic calibration and maintenance programme will be implemented to maintain the monitoring systems
in place.
Impacts on Local Businesses
As the impacts are considered to be positive there is no need for any mitigation measures to be implemented.
Economic Impacts
As the impacts are considered to be positive there is no need for any mitigation measures to be implemented.
Soils, Geology and Contamination 17.5.8In order to avoid any contamination during the operational phase of the Project, the following mitigation
measures will be implemented:
The Material Safety Data Sheets (MSDS) of all chemicals used during operation will be retained on site;
Procedures will be implemented to ensure the safe storage and disposal of hazardous and waste
chemicals;
Hazardous chemicals and materials will be appropriately stored on-site in a secure, bunded compound and
located on an impervious surface. The storage areas will need to be clearly labelled with MSDS maintained
as part of the on-site record keeping;
Details and properties for each material will be clearly noted and will include the nature (poisonous,
corrosive, flammable), prohibitions on disposal (dumpster, drain, sewer) and the recommended disposal
method (recycle, sewer, storage, landfill). A signed checklist should be developed for users of hazardous
materials detailing amount taken, amount used, amount returned and disposal of spent material;
Good practice measures in terms of health and safety to comply, as a minimum, with KSA law and policy
requirements would be proactively promoted;
Appropriate security measures will be provided in order to ensure that any potential issues that may result
in contamination are avoided;
Appropriate safety zoning to the hazards will be provided in order to ensure that any spillages or incidents
are avoided;
285 | 278
Written standard operating procedures (SOPs) for all processes and appropriate document control will be
provided;
Awareness training will be provided for all employees including management, office staff and technical staff
on pollution prevention and control techniques and best practices;
Daily checklists for plant and office areas will be established in order to confirm cleanliness and adherence
to proper storage and security. Specific employees will be assigned specific inspection responsibilities and
given the authority to remedy any problems found;
Emergency response procedures will be provided in order to avoid any potential incidents to ensure that
contamination incidents are controlled if they occur;
Regular reviews of emergency response procedures will be undertaken, including a contingency plan for
spills, leaks, weather extremes etc.;
Continuous monitoring and reporting of the plants’ performance should be undertaken in order to establish
baseline conditions and whether conditions are improving or deteriorating; and
To reduce the risk of wind-blown residue contaminating the site or adjacent areas, the evaporation ponds
should either have all residue removed on a regular basis or have a continuous supply of water to keep the
tanks damp. The residue left in the evaporation ponds will be collected and disposed of as a hazardous
waste by a PME licensed hazardous waste contractor.
Terrestrial Ecology 17.5.9Chapter 11: Terrestrial Ecology outlines that as there is limited terrestrial ecology in the area this has not been
considered within the ESIA as the impact of the operation of the project is likely to be of negligible significance,
however the following key mitigation measures will be implemented:
Any additional landscape planting should be proposed and designed to provide some ecological benefit in
attracting bird and insect species. Native species should be favoured over exotic species;
Where practicable, naturally growing vegetation within the site boundary should be protected and/or
encouraged, e.g. ensuring that vehicles and members of staff keep to maintained roads and pathways
would protect the onsite vegetation from trampling. This will encourage native species which will be free
from grazing pressure of livestock animals which would in turn attract fauna species such as birds and
insects, increasing the biodiversity of the site;
The land within the site boundary should be kept clear of any municipal or industrial waste arising from
facility processes (other than designated areas where appropriate controls should be applied), staff and
staff housing and offsite sources. This would improve the general “environmental quality” and amenity
value of the site and reduce potential attraction of pest species such as rats and flies to the site; and
Vehicles carrying potentially toxic, friable materials should be covered at all times so that these materials
are not accidentally deposited into the natural environment, causing harm to flora and fauna.
Project number: 37446130 Dated: 09/11/2014 286 | 278 Revised:
Wastewater and Water Resources 17.5.10The Project will not result in any direct discharges to the environment.
Wastewater Process 17.5.11The process wastewater will be discharged to an evaporation pond following onsite treatment e.g.
demineralisation, and therefore no further mitigation is required. The removal of oils and hydrocarbons from
waste waters will be undertaken, which will generate waste materials. Furthermore, when the waste process
water evaporates it will leave behind a residue. These wastes will need to be collected and disposed of as a
hazardous waste by a PME licensed hazardous waste contractor (see Section 17.5.4 for appropriate controls).
Sanitary Wastewater Effluent 17.5.12It is understood that treated sewage effluent is proposed for re-use for irrigation and it will therefore be
necessary to implement adequate quality control measures to ensure that no impacts upon the environment or
health and safety are realised. The United States Environmental Protection Agency (USEPA) Guidelines for
Water Reuse (2004) provide guidance on the safe reuse of wastewater for irrigation. It is recommended that
these guidelines, or a suitable recognised alternative, are adhered to when implementing this element of the
project.
Local Water Resources 17.5.13The source of potable water for the site will be via deep wells from aquifers with limited recharge. It is therefore
recommended that potable water reduction measures are implemented such as water efficient faucets, urinals,
showerheads and toilets.
Storm Water Generation and Management 17.5.14 Runoff from areas without potential sources of contamination should be minimised by the development of
appropriate storm-water and run-off control measures within the design of the Project which could include,
for example, reduction in peak discharge rates by using swales and retention ponds;
Oil water separators and grease traps should be installed and maintained as appropriate at refuelling
facilities workshops, parking areas, fuel storage and containment areas; and
Sludge or other solid wastes arising from storm water catchments or collection and treatment systems may
contain elevated levels of pollutants and should be disposed in compliance with local regulatory
requirements, in the absence of which disposal has to be consistent with protection of public health and
safety, and conservation and long term sustainability of water and land resources.
Monitoring Programmes 17.6
An environmental monitoring programme will be developed and implemented as part of the OEMP. The
monitoring programme will include the ongoing review of emissions which will be reported to the PME on an
287 | 278
annual basis and more frequently if there are either abnormal operating conditions, or changes which may
affect the environmental quality of the emissions.
Air Quality 17.6.1 The proposed facility will incorporate a Continuous Emissions Monitoring System (CEMS) for NOx, SO2 and
PM10. This would accurately determine pollutant concentrations in the emissions and provide an indication
of any exceedences in emissions from the plant against the PME and IFC air pollution standards.
Ambient air quality monitoring of NOx, SO2 and PM10 will be undertaken using a continuous air quality
monitoring station to verify the current baseline and impact of the existing facilities upon the air shed.
Noise 17.6.2The following aspects relating to noise will be monitored during the operational phase of the Project by the
O&M Company:
Regular noise monitoring will be undertaken within close proximity of noise sensitive locations, if future
works include activities which are known to cause significant levels of noise;
A full occupational noise survey should be undertaken in the interests of the health and safety of Site
employees; and
Periodic monitoring of operational areas where workers are expose to noise to ensure appropriate working
practices and protection for O&M staff and contractors. Noise levels in working areas must be less than
85dB(A) at 1m from any noise generating equipment.
Waste Management 17.6.3As part of the OEMP, all paperwork and records of hazardous waste management activities on-site will need to
be maintained including records of off-site disposal to landfill as follows:
SEC will maintain the following records and reports:
Keep one copy of each transport document it has generated pending receipt of the signed copy from the
facility designated in the document. It shall also keep the signed copy for at least 5 years as of the date
of receipt of the waste by that facility;
Retain copies of the results of all tests and analysis performed on the hazardous waste as well as
copies of all pertinent reports, correspondence and documents for at least five years from the last date
of handling of such waste;
Submit to the PME an annual report on all hazardous waste generated during the year. Copies of such
reports shall be retained for at least five years from the date of completion; and
Submit on demand to the PME or the agencies designated by it, all documents, records and reports
related to the waste.
Project number: 37446130 Dated: 09/11/2014 288 | 278 Revised:
Hazardous Waste Transporters and Hazardous Waste Management Facilities are required have both a
valid identification code and a work permit from the PME. The management of the Project should maintain
an up to date list of local contractors who can satisfy their requirements for the responsible handling and
disposal of hazardous waste.
Groundwater 17.6.4 A monitoring programme should also be established by SEC to determine any detrimental impacts upon
water levels and water quality as a result of long-term abstraction for use within the Project.
If significant groundwater impacts are identified, alternative sources of water should be sourced where
possible.
Decommissioning Plan 17.7
A comprehensive plan for decommissioning the facility should be compiled at the end of its 30+ year design
life. All decommissioning and restoration activities must adhere to the requirements of appropriate governing
authorities and will be in accordance with all applicable local and international regulation and guidance. The
decommissioning and restoration process is likely to include:
The removal of above-ground structures;
The removal of below-ground structures (turbine foundations);
The restoration of topsoil; and
The implementation of a monitoring and remediation period.
Successful decommissioning will only be complete when all buildings, equipment, materials, wastes or any
other materials, which could result in environmental pollution, are removed from the site and recycled,
recovered or disposed of.
289 | 278
Appendices
Project number: 37446130 Dated: 09/11/2014 290 | 278 Revised:
Appendix A – Bibliography CIA. (2013). The World Factbook - Middle East: Saudi Arabia. . Retrieved 04 28, 2013, from
CIA: https://www.cia.gov/library/publications/the-world-factbook/geos/sa.html#top
IFC. (2007). Environmental, Health, and Safety (EHS) Guidelines – General EHS Guidelines.
Jacobs. (2013). Umm Wu'al Phosphate Project Environmental and Social Impact
Assessment.
Nader, I. A. (1995). Harrat Al-Harra, First National Reserve in Saudi Arabia. Arabian Wildlife
Vol 2.
P.A., M., & Schuttenberg, H. (2006). A Reef Manager’s Guide to Coral Bleaching. Australia:
Great Barrier Reef Marine Park Authority.
Saudi Geological Society. (n.d.). Saudi Geological Survey: National Centre for Earthquakes
and Volcanoes - Earthquake Seismology . Retrieved 03 27, 2014, from
http://www.sgs.org.sa/English/NaturalHazards/Pages/Earthquakes.aspx
SEC. (2014). Construction of Duba Integrated Solar Combined Cycle Project Project
Schedule “B” Attachment III, Detailed Scope of Work.
UN-ESCWA and BGR . (2013). Inventory of Shared Water Resources in Western Asia.
Beirut.
United Nations Department of Economic and Social Affairs. (2010). Resource Abundance - A
curse or a Blessing .
US NOAA . (2003). Guidelines and Principles for Social Impact Assessment .
Vincent, P. (2008). Saudi Arabia: An Environmental Overview. London: Taylor & Francis.
WSP. (2014). Duba Solar Thermal Power Project, Preliminary Environmental Assessment
and Terms of Reference.
WWF. (2014). Desert and Xeric Shrublands. Retrieved 04 10, 2014, from World Wildlife Fund
Terrestrial Ecoregions: https://worldwildlife.org/ecoregions/pa1303
Zafar, S. (2013). Solid Waste Management in Saudi Arabia. . Retrieved 04 25, 2013, from
EcoMENA: Powering Sustainable Development in MENA: www.ecomena.org/solid-
waste-management-in-saudi-arabia/
291 | 278
Appendix B – Project Layout Drawings
Project number: 37446130 Dated: 09/11/2014 292 | 278 Revised:
Appendix C – Fuel Specifications
293 | 278
Natural gas specifications
Gas Specification
Component Unit Current (RFP Reference Gas) Low High
CH4 Methane mole-% 83.00 80.85 80.7
C2H6 Ethane mole-% 6.60 2.28 16
C3H8 Propane mole-% 0.07 0.47 2.8
C4H10 Butane mole-% 0.50 0.14 -
C5H12 Pentane mole-% 0.50 0.04 -
C6H14 Hexane mole-% 0.50 - -
N2 Nitrogen mole-% 6.40 13.77 0.5
CO2 Carbon dioxide mole-% 2.50 2.41 -
H2S -
Specific Gravity @ 600F, Air = 1
- 0.6098 0.55 0.65
Water Dew Point C0 - -75 -55
Hydro Carbon Dew Point @ 39.2 bar (a)
C0
- - -5
HHV Higher Heating Value
MJ/m³ 40.215 34.529 46.217
MJ/kg 46.445 40.841 53.843
BTU/SCF 1080 *) ~ 930**) 1240
LHV Lower Heating Value
MJ/m³ 36.367 31.154 41.865
MJ/kg 42.001 36.85 48.772
BTU/SCF 976 836 1124
P Gas Gas Pressure bar (g) 35 21 66
T Gas Gas Temperature C0 50 15 65
Project number: 37446130 Dated: 09/11/2014 294 | 278 Revised:
Arabian Super Light (ASL) Fuel Oil Specifications
Property Limit Heating Value, Gross, BTU/Lb. 19145
Kin. Viscosity, cSt, (20 0C)
Kin. Viscosity, cSt, (37.8 0C).
Kin. Viscosity, cSt, (40 0C).
Kin. Viscosity, cSt, (50 0C).
2.09
1.8
1.58
1.5 Gravity , API 49.1
Specific Gravity , 60 0F (15.6 0C) 0.7835
Flash Point, (0C) < 0 0C
Distillate Temp. 90% Point, 0F(0C) N/A
Pour Point, 0F(0C), -31 0F
Cold Filter Plugging Point 20 0F
Ash , ppm 3
Sodium plus Potassium ppm 2.1
Lead ppm 1
Vanadium ppm 0.5
Calcium, max 10
Nitrogen ppm 62
Carbon residue Wt. % 0.8
Nickel ppm 0.1
Reid Vapour pressure psi 7.8
Salt as NaCl, PPTB <1
Hydrogen, Wt. %, min 11 %
Carbon Residue, Wt. % (100% Sample) max
Air automixation, Low Pressure
1 Sulphur, Wt. % 0.1
Wax, (%), max 1.43
295 | 278
Distillate Fuel Oil Specifications.
ARAMCO SPECIFICATION AL – 18
DIESEL OIL FOR LOCAL USE
TEST GUARANTEE METHOD
Acid No.mg KOH/gm ASTM D 974 Strong Nil
Total 0.25 Max Ash ,Wt. ,% 0.005 Max ASTM D 482
Carbon Residue, 10% Bottoms ,wt. %
0.2 Max ASTM D 524
Cloud Point. 0F (-1.1 c)+30 Max ASTM D 2500 Colour 3 Max ASTM D 1500
Composition 100% Virgin Distillate
Corrosion, On Strip 3 hrs @212 0F
# 2 Strip or better
ASTM D 130
Diesel Index 55min IP - 21 ASTM D 86
Distillation (% Recovered) (357.2 0c) 675 Max
90% Point, 0F (385 0c) 725 Max
End Point, 0F Flash, P.M. Closed, 0F (60 0c) 140 Min ASTM D93
ASTM D287 Gravity
0 API 34.0 – 42.0 Specific, 60/60 0F 0.8155 – 0.8550
Pour Pont, 0F (-666 0c) + 20 Max
ASTM D97
Sulphur, wt. % 1.0 Max ASTM D2622/ ASTM D1522
Viscosity ,S.U.S @ 100 0F,Seconds
33 – 45 ASTM D88
Water: Sediment by Centrifuge %
Trace Max ASTM D1796
Water by Distillation, Vol % 0.05
ASTM D95
MHV (mj/KG 45.57
Project number: 37446130 Dated: 09/11/2014 296 | 278 Revised:
Appendix D – Wind Roses for Sharm El Sheikh (2009 to 2013)
297 | 278
Wind Rose for 2009
Wind Rose for 2010
Project number: 37446130 Dated: 09/11/2014 298 | 278 Revised:
299 | 278
Wind Rose for 2011
Wind Rose for 2012
Project number: 37446130 Dated: 09/11/2014 300 | 278 Revised:
301 | 278
Wind Rose for 2013
Project number: 37446130 Dated: 09/11/2014 302 | 278 Revised:
Appendix E – Dispersion Model Input Parameters used in the Assessment
303 | 278
Emission Data for E-Class Turbines
Parameter Units Siemens (SGT6-2000E)
OP1 OP2 OP1 OP2 OP1 (ASL) OP2 (ASL)
Ambient Temperature °C 40 0 40 0 40 0
Fuel Type NG (Simple Cycle) NG (Combined Cycle) ASL (Combined Cycle)
Internal stack diameter m 4.5 4 4
Stack Height m 40 60 60
Flue gas temperature °C 540.0 506.0 176.0 141.0 180.0 145.0
flue gas velocity m/s 30.5 34.5 21.3 23.2 22.1 26.0
Actual flue gas flow rate ( per stack) Am3/s 484.8 548.8 267.7 291.6 351.6 413.2
Normalised flue gas flow rate ( per stack) Nm3/s 209.7 222.7 209.7 222.7 151.0 203.9
Emissions NG (Simple Cycle) NG (Combined Cycle) ASL (Combined Cycle)
OP1 OP2 OP1 OP2 OP1 OP2
NOx ppmv 25 25 25 25 105 105
NOx mg/Nm3 51.4 51.4 51.4 51.4 214.9 214.9
SO2 mg/Nm3 NA NA NA NA 74.7 77.3
PM10 mg/Nm3 10.0 10.0 10.0 10.0 50.0 50.0
NOx g/s 10.8 11.4 10.8 11.4 32.5 43.8
SO2 g/s NA NA NA NA 11.3 15.8
PM10 g/s 2.1 2.2 2.1 2.2 7.5 10.2
Project number: 37446130 Dated: 09/11/2014 304 | 278 Revised:
Emission Data for F-Class Turbines
Parameter Simple Cycle Combined Cycle
OP1 OP1 OP1 OP1
Fuel Type NG NG NG ASL ASL
Fuel Consumption Rate (t/hr) 36.2 36.16 30.47 40.37 34.02
Oxygen content (% at actual stack condition) 11.98 11.02 12.60 10.64 10.00
Water content (% at actual stack condition) 10.29 11.11 7.68 12.91 12.50
Flue Gas exhaust Temperatures (°C) 615 183 171 201 190
Flue Gas exhaust Temperatures (K) 888 456 444 474 463
Flue Gas exhaust flow (t/h) 1417.00 1421.35 1221.20 1466.00 1259.56
Flue Gas specific volume (Am3/kg) 2.58 1.33 1.28 1.38 1.32
Flue Gas exhaust flow (Am3/s) 1016.23 524.40 433.63 562.37 461.84
Normalized Exhaust flow rate (Nm3/s)(*) 358.46 402.18 302.51 415.13 382.51
Exhaust efflux velocity (m/s); 39.13 22.07 18.25 23.67 19.44
Stack Height (m) 40 60
Internal stack diameter (m) 5.75 5.50 5.50 5.50 5.50
Emissions
NOx concentration (mg/Nm3) 21.2 21.3 18.5 86.3 75.0
SO2 Concentration (mg/Nm3) NA NA NA 48.4 44.2
PM10 concentration (mg/Nm3) 3.9 3.5 4.6 50.0 54.2
NOx emission (g/s) 7.59 8.56 5.59 35.81 28.68
305 | 278
SO2 emission (g/s) NA NA NA 20.09 16.91
PM10 emission (g/s) 1.39 1.39 1.39 20.75 20.75
Project number: 37446130 Dated: 09/11/2014 306 | 278 Revised:
Stacks and Structures included in the model
Option A and Option B Stack Locations
Source Coordinates
Option A Easting Northing
Main Stacks
MS11 740615.0 3072878.1
MS21 740586.4 3072945.9
MS22 740565.0 3072981.6
By-pass Stacks
BS11 740654.2 3072894.1
BS21 740622.1 3072963.7
BS22 740604.3 3072999.4
Option B
Main Stacks
MS11 740615.0 3072878.1
MS12 740604.3 3072910.2
MS21 740586.4 3072945.9
MS22 740565.0 3072981.6
By-pass Stacks
BS11 740654.2 3072894.1
BS12 740640.0 3072928.0
BS21 740622.1 3072963.7
BS22 740604.3 3072999.4
On-site Building Locations and Dimensions
Structure Coordinates Height
(m) Width(m) Length (m)
Radius (m) Easting Northing
Turbine Hall (tall) 740668.5 3072881.7 20 36 155
Central Control Room 1 740600.7 3073020.8 12 25 43
Condensate Tank 1 740672.1 3073256.3 15
14
Condensate Tank 2 740714.9 3073277.8 15 14
ASL Tank 1 740850.5 3073277.8 15 14
ASL Tank 2 740914.7 3073306.3 15 14
ST Building 740522.2 3072849.5 18 28 126
307 | 278
Appendix F – Air Quality Monitoring Laboratory Analytical Reports
2187
(A division of Gradko International Ltd.)
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:[email protected]
LABORATORY ANALYSIS REPORT
The Diffusion Tubes have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures calculations and assessments
involving the exposure procedures and periods provided by the client are not within the scope of our UKAS accreditation. Those results obtained
using exposure data shall be indicated by an asterisk. Any queries concerning the data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 4 – September 2012 Report Number I02047R Page 1 of 1
DETERMINATION OF SULPHUR DIOXIDE IN DIFFUSION TUBES BY ION CHROMATOGRAPHY
REPORT NUMBER I02047R
BOOKING IN REFERENCE No I02047
DESPATCH NOTE No SOR015778
CUSTOMER WSP Middle East Environmental Attn: Simon Pickup
P.O. Box 7497 Monarch Office Tower Buildin 1 Sheikh Sayed Road '20 Dubai United Arab Emirates
DATE SAMPLES RECEIVED 30/05/2014
Date Date Exposure µg S µg S - SO2 SO2
Location Sample Number
Exposed Finished Hours Total Blank µg/m3* ppb*
Waad Al Shamal 1A 343246 05/05/2014 23/05/2014 431.25 <0.03 <0.02 <1.98 <0.74
Waad Al Shamal 1B 343247 05/05/2014 23/05/2014 431.25 <0.03 <0.02 <1.98 <0.74
Waad Al Shamal 2 343248 05/05/2014 23/05/2014 430.72 <0.03 <0.02 <1.98 <0.74
Waad Al Shamal 3A 343249 05/05/2014 23/05/2014 428.45 <0.03 <0.02 <1.99 <0.75
Waad Al Shamal 3B 343250 05/05/2014 23/05/2014 428.45 0.06 0.06 5.24 1.97
Laboratory Blank 0.003
Comment: Results are blank subtracted
Results reported as <0.03µg S are below the reporting limit.
Overall M.U. ±6.0% Reporting Limit 0.03µg S
Analysed on Dionex ICS3000 ICU5
Analyst Name Katya Paldamova
Date of Analysis 09/06/2014 Date of Report 10/06/2014
Analysis has been carried out in accordance with in-house method GLM1
2187
(A division of Gradko International Ltd.)
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:[email protected]
LABORATORY ANALYSIS REPORT
The Diffusion Tubes have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures calculations and assessments
involving the exposure procedures and periods provided by the client are not within the scope of our UKAS accreditation. Those results obtained
using exposure data shall be indicated by an asterisk. Any queries concerning the data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 4 – September 2012 Report Number X1257A Page 1 of 1
DETERMINATION OF OZONE IN DIFFUSION TUBES BY ION CHROMATOGRAPHY
REPORT NUMBER X1257AR
BOOKING IN REFERENCE No X1257A
DESPATCH NOTE No SOR015778
CUSTOMER WSP Middle East Environmental
P.O. Box 7497, Monarch Office Tower Building
1 Sheikh Sayed Road 20
DATE SAMPLES RECEIVED 30-May
GRADKO LAB REF GIO2497-2502
Location Bar Code Date On Date Off Exposure µg on Tube µg - Blank O3* O3*
(hrs) Total
µg/m
3 ppb
1A 05/05/2014 23/05/2014 431.25 0.82 0.80 107.06 53.53
1B 05/05/2014 23/05/2014 431.25 0.96 0.94 125.77 62.88
2A 05/05/2014 23/05/2014 430.72 1.02 1.00 134.52 67.26
2B 05/05/2014 23/05/2014 430.72 0.88 0.86 115.32 57.66
3A 05/05/2014 23/05/2014 428.45 0.77 0.75 101.76 50.88
3B 05/05/2014 23/05/2014 428.45 0.89 0.87 117.55 58.77
Lab Blank 0.02
(RESULTS ARE BLANK CORRECTED)
Overall M.O.U
±10.0% Reporting Limit 0.096µg O3
Analysed on ICS3000 ICU05
K. Paldamova
Date of Analysis
04/06/2014 Date of Report 10/06/2014
Analysis has been carried out in accordance with in-house method GLM 2
2187
(A division of Gradko International Ltd.)
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:[email protected]
LABORATORY ANALYSIS REPORT
The Diffusion Tubes have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures calculations and assessments involving the exposure procedures and periods provided by the
client are not within the scope of our UKAS accreditation. Those results obtained using exposure data shall be indicated by an asterisk. Any queries concerning the data in this report should be directed to the
Laboratory Manager Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32c Issue 4 – September 2012 Report number X1257R Page 1 of 2
NITROGEN DIOXIDE IN DIFFUSION TUBES BY U.V.SPECTROPHOTOMETRY
REPORT NUMBER X1257R
BOOKING REFERENCE No X1257
DESPATCH NOTE No SOR015778
CUSTOMER WSP Middle East Environmental
P.O. Box 7497, Monarch Office Tower Building
1 Sheikh Sayed Road 20
Dubai, UAE
DATE SAMPLES RECEIVED 30/05/2014
Exposure Data
NO2 NOX NO NO2 NOX NO TOTAL TOTAL
NO2 Tube Number NOx Date On Date Off Time (hr.) ppb * ppb * ppb * + µµµµg/m
3 µµµµg/m
3 µµµµg/m
3 + µµµµG NO2 µµµµG NOx
Waad Al Shamal 1A 295375 05/05/2014 23/05/2014 431.25 7.28 13.94 0.44 Waad Al Shamal 1B 295376 05/05/2014 23/05/2014 431.25 9.77 18.73 0.59 Waad Al Shamal 2A 295377 05/05/2014 23/05/2014 430.72 9.99 19.13 0.60 Waad Al Shamal 2B 295378 05/05/2014 23/05/2014 430.72 8.69 16.64 0.52 Waad Al Shamal 3A 295379 05/05/2014 23/05/2014 428.45 8.45 16.19 0.50 Waad Al Shamal 3B 295373 05/05/2014 23/05/2014 428.45 9.72 18.63 0.58
2187
(A division of Gradko International Ltd.)
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:[email protected]
LABORATORY ANALYSIS REPORT
The Diffusion Tubes have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures calculations and assessments involving the exposure procedures and periods provided by the
client are not within the scope of our UKAS accreditation. Those results obtained using exposure data shall be indicated by an asterisk. Any queries concerning the data in this report should be directed to the
Laboratory Manager Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32c Issue 4 – September 2012 Report number X1257R Page 2 of 2
Lab Blanks 431.25 0.07 0.33 0.27 0.13 0.64 0.51 0.004 0.020
Comment: Results are not blank subtracted
+NO results are derived by subtracting NO2 from NOx.
Results have been corrected to a temperature of 293K (20C) Overall M.O.U. 5.2% +/- Limit of Detection 0.029ug NOx, 0.01ug NO2 on tube Tube Preparation: 20%TEA/Water Analysed on UVS05 Camspec M550
Analyst Name L. Digby
Date of Analysis 05/06/2014 Date of Report 10/06/2014
Analysis carried out in accordance with documented in-house Laboratory Method GLM7
Appendix G – Modelling Results – Combined Cycle
Project number: 37446130 Dated: 09/11/2014 310 | 278 Revised:
Modelling Results: Combined Cycle Mode
Fuel: Natural Gas
Predicted Concentrations: Maximum point of Impact – Option A (OP1)
Table A5-1: NO2 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 12.83 2% NEGLIGIBLE 740550 3072350
Annual Mean 100 3.69 4% NEGLIGIBLE 740450 3072200
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-2 PM10 Concentrations
Predicted Concentrations: Maximum point of Impact – Option A (OP2)
Table A5-3: NO2 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 12.64 2% NEGLIGIBLE 740500 3072400
Annual Mean 100 3.74 4% NEGLIGIBLE 740450 3072200
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-4 PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 1.22 <1% NEGLIGIBLE 740450 3072200
Annual Mean 80 0.76 <1% NEGLIGIBLE 740450 3072200
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 1.12 <1% NEGLIGIBLE 740450 3072200
Annual Mean 80 0.69 <1% NEGLIGIBLE 740450 3072200
Predicted Concentrations: Maximum point of Impact – Option B (OP1)
Table A5-5: NO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 20.94 3% NEGLIGIBLE 740600 3072400
Annual Mean 100 6.45 6% MINOR 740450 3072250
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-6 PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 2.03 1% NEGLIGIBLE 740500 3072250
Annual Mean 80 1.25 2% NEGLIGIBLE 740450 3072250
Predicted Concentrations: Maximum point of Impact – Option B (OP2)
Table A5-7: NO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 22.03 3% NEGLIGIBLE 740500 3072350
Annual Mean 100 6.90 7% MINOR 740450 3072250
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-8 PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 2.15 <1% NEGLIGIBLE 740450 3072200
Annual Mean 80 1.33 2% NEGLIGIBLE 740450 3072250
Project number: 37446130 Dated: 09/11/2014 312 | 278 Revised:
Predicted Concentrations: Maximum at Sensitive Receptors – Option A (OP1) Table A5-9: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.05 <1% NEGLIGIBLE 7.11 1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.11 <1% NEGLIGIBLE 5.57 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.11 <1% NEGLIGIBLE 5.33 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.11 <1% NEGLIGIBLE 5.02 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.12 <1% NEGLIGIBLE 4.95 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.11 <1% NEGLIGIBLE 5.12 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.11 <1% NEGLIGIBLE 4.66 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.12 <1% NEGLIGIBLE 5.01 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.10 <1% NEGLIGIBLE 3.14 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NEGLIGIBLE 0.64 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.07 <1% NEGLIGIBLE 1.99 <1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-10 PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.01 <1% NEGLIGIBLE 0.02 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.02 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NEGLIGIBLE 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.01 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 314 | 278 Revised:
Predicted Concentrations: Maximum at Sensitive Receptors – Option A (OP2) Table A5-11 NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.05 <1% NEGLIGIBLE 7.54 1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.12 <1% NEGLIGIBLE 5.62 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.11 <1% NEGLIGIBLE 5.35 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.12 <1% NEGLIGIBLE 5.12 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.12 <1% NEGLIGIBLE 4.76 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.11 <1% NEGLIGIBLE 5.20 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.11 <1% NEGLIGIBLE 4.83 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.12 <1% NEGLIGIBLE 5.09 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.11 <1% NEGLIGIBLE 3.17 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NEGLIGIBLE 0.72 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.08 <1% NEGLIGIBLE 2.03 <1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-12: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.01 <1% NEGLIGIBLE 0.02 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.02 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.02 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.02 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.02 <1% NEGLIGIBLE 0.08 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NEGLIGIBLE 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.02 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 316 | 278 Revised:
Predicted Concentrations: Maximum at Sensitive Receptors – Option B (OP1) Table A5-13: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.09 <1% NEGLIGIBLE 11.94 2% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.18 <1% NEGLIGIBLE 8.82 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.18 <1% NEGLIGIBLE 8.50 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.18 <1% NEGLIGIBLE 8.28 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.19 <1% NEGLIGIBLE 7.34 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.17 <1% NEGLIGIBLE 7.98 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.17 <1% NEGLIGIBLE 7.11 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.19 <1% NEGLIGIBLE 8.15 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.16 <1% NEGLIGIBLE 4.76 1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.02 <1% NEGLIGIBLE 1.09 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.12 <1% NEGLIGIBLE 3.14 <1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-14 PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.02 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.03 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.03 <1% NEGLIGIBLE 0.06 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.03 <1% NEGLIGIBLE 0.06 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.03 <1% NEGLIGIBLE 0.11 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NEGLIGIBLE 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.02 <1% NEGLIGIBLE 0.08 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 318 | 278 Revised:
Predicted Concentrations: Maximum at Sensitive Receptors – Option B (OP2) Table A5-15 NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.10 <1% NEGLIGIBLE 13.42 2% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.20 <1% NEGLIGIBLE 9.56 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.20 <1% NEGLIGIBLE 9.21 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.20 <1% NEGLIGIBLE 8.98 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.21 <1% NEGLIGIBLE 7.90 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.19 <1% NEGLIGIBLE 8.61 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.19 <1% NEGLIGIBLE 7.79 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.21 <1% NEGLIGIBLE 8.94 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.17 <1% NEGLIGIBLE 5.31 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.02 <1% NEGLIGIBLE 1.29 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.13 <1% NEGLIGIBLE 3.41 <1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A5-16 PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.02 <1% NEGLIGIBLE 0.05 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.04 <1% NEGLIGIBLE 0.08 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.04 <1% NEGLIGIBLE 0.08 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.04 <1% NEGLIGIBLE 0.07 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.04 <1% NEGLIGIBLE 0.08 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.03 <1% NEGLIGIBLE 0.12 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NEGLIGIBLE 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.03 <1% NEGLIGIBLE 0.09 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 320 | 278 Revised:
Appendix H – Modelling Results – Simple Cycle
Modelling Results: Simple Cycle Mode
Fuel: Natural Gas
Predicted Concentrations: Maximum point of Impact – Option A (OP1)
Table A6-1: NO2 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 97.33 15% MINOR 740600 3072850
Annual Mean 100 25.76 26% NA 740600 3072850
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Table A6-2 PM10 Concentrations
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Predicted Concentrations: Maximum point of Impact – Option A (OP2)
Table A6-3: NO2 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 94.31 14% MINOR 740600 3072850
Annual Mean 100 23.01 23% NA 740600 3072850
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 11.78 3% MINOR 740600 3072850
Annual Mean 80 5.01 6% NA 740600 3072850
Project number: 37446130 Dated: 09/11/2014 322 | 278 Revised:
Table A6-4 PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 10.79 3% NEGLIGIBL
E 740450 3072200
Annual Mean 80 4.44 6% 740600 3072850
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Predicted Concentrations: Maximum point of Impact – Option B (OP1)
Table A6-5: NO2 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 105.03 16% MINOR 740600 3072850
Annual Mean 100 27.01 27% NA 740600 3072850
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Table A6-6: PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 12.47 4% NEGLIGIBLE 740600 3072850
Annual Mean 80 5.25 7% NA 740600 3072850
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Project number: 37446130 Dated: 09/11/2014 324 | 278 Revised:
Predicted Concentrations: Maximum point of Impact – Option B (OP2)
Table A6-7: NO2 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 101.14 15% MINOR 740600 3072850
Annual Mean 100 24.14 24% NA 740600 3072850
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Table A6-8: PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 11.25 3% NEGLIGIBLE 740600 3072850
Annual Mean 80 4.66 6% NA 740600 3072850
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Predicted Concentrations: Maximum at Sensitive Receptors – Option A (OP1) Table A6-9: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact Significance
1 Central Control Building 740600.7 3073056.5 0.16 <1% NA 23.63 4% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.06 <1% NA 5.00 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.06 <1% NA 4.57 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.06 <1% NA 3.89 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.07 <1% NA 3.92 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.06 <1% NA 4.43 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.06 <1% NA 4.54 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.07 <1% NA 6.20 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.06 <1% NA 1.71 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 0.42 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.04 <1% NA 1.19 <1% NEGLIGIBLE
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Project number: 37446130 Dated: 09/11/2014 326 | 278 Revised:
Table A6-10: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.03 <1% NEGLIGIBLE 1.30 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.01 <1% NEGLIGIBLE 0.25 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.01 <1% NA 0.02 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.01 <1% NA 0.02 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.01 <1% NA 0.02 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.01 <1% NA 0.02 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.01 <1% NA 0.02 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.01 <1% NA 0.02 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.01 <1% NA 0.02 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NA 0.02 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.01 <1% NA 0.04 <1% NEGLIGIBLE
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Predicted Concentrations: Maximum at Sensitive Receptors – Option A (OP2) Table A6-11: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean Percentage
of PME AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.14 <1% NA 22.52 3% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.05 <1% NA 4.35 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.05 <1% NA 4.00 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.05 <1% NA 3.64 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.06 <1% NA 3.90 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.06 <1% NA 4.19 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.06 <1% NA 4.30 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.06 <1% NA 5.87 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.05 <1% NA 1.65 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 0.40 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.04 <1% NA 1.18 <1% NEGLIGIBLE
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Project number: 37446130 Dated: 09/11/2014 328 | 278 Revised:
Table A6-12: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.03 <1% NA 0.03 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.01 <1% NA 0.02 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.01 <1% NA 0.02 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.01 <1% NA 0.02 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.01 <1% NA 0.02 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.01 <1% NA 0.02 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.01 <1% NA 0.02 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.01 <1% NA 0.02 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.01 <1% NA 0.04 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NA 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.01 <1% NA 0.02 <1% NEGLIGIBLE
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Predicted Concentrations: Maximum at Sensitive Receptors – Option B (OP1) Table A6-13: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean Percentage
of PME AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.30 <1% NA 56.97 9% MINOR
2 Main Administration Building 741657 3072763.9 0.11 <1% NA 8.74 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.10 <1% NA 8.07 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.11 <1% NA 7.43 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.11 <1% NA 7.37 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.10 <1% NA 6.90 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.10 <1% NA 7.86 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.11 <1% NA 9.89 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.09 <1% NA 2.70 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 0.66 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.06 <1% NA 2.07 <1% NEGLIGIBLE
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Project number: 37446130 Dated: 09/11/2014 330 | 278 Revised:
Table A6-14 PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.06 <1% NEGLIGIBLE 0.06 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.02 <1% NEGLIGIBLE 0.06 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NEGLIGIBLE 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.01 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Predicted Concentrations: Maximum at Sensitive Receptors – Option B (OP2) Table A6-15 NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance 1-hour Mean Percentage
of PME AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.25 <1% NA 49.67 8% MINOR
2 Main Administration Building 741657 3072763.9 0.10 <1% NA 8.36 1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.10 <1% NA 7.77 1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.10 <1% NA 7.36 1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.11 <1% NA 7.18 1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.10 <1% NA 6.04 1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.10 <1% NA 6.55 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.11 <1% NA 8.32 1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.09 <1% NA 2.74 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 0.67 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.06 <1% NA 2.08 <1% NEGLIGIBLE
NB:
1. 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
2. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Project number: 37446130 Dated: 09/11/2014 332 | 278 Revised:
Table A6-16: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.05 <1% NEGLIGIBLE 0.06 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.02 <1% NEGLIGIBLE 0.03 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.02 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.02 <1% NEGLIGIBLE 0.06 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.00 <1% NEGLIGIBLE 0.01 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.01 <1% NEGLIGIBLE 0.04 <1% NEGLIGIBLE
NB:
1. NA - Annual mean concentrations are not relevant to Simple Cycle mode
Appendix I – Modelling Results – Operation on Back-up Fuel (ASL)
Project number: 37446130 Dated: 09/11/2014 334 | 278 Revised:
Modelling Results: Operation on ASL – Combined and Simple Cycle (OP1) Notes: 1. Annual mean concentrations have been predicted and included in the tables below; how-
ever, this averaging period does not apply the operation of the power plant on ASL as op-erations under these conditions would only be short-term.
2. Only the OP1 operating conditions were predicted for ASL operation because earlier mod-elling indicated that impacts predicted for OP1 conditions were slightly higher than the re-sults for OP2.
Fuel: ASL
Predicted Concentrations: Maximum point of Impact – Option A (Combined Cycle) Table A7-1: SO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
10-min mean 500 65.77 13% NA 740450 3072400
Highest 1-hr Mean 730 38.42 5% MINOR 740650 3072350
99.7th Percentile of 24-hr Means 365 11.71 3% NEGLIGIBLE 740600 3072000
Annual Mean 80 5.03 6% NA 740450 3072200
Table A7-2: NO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 43.71 7% MINOR 740450 3072350
Annual Mean 100 12.27 12% NA 740450 3072200
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A7-3: PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 9.48 3% NEGLIGIBLE 740550 3072000
Annual Mean 80 4.08 5% 740450 3072200
Predicted Concentrations: Maximum point of Impact – Option B (Combined Cycle)
Table A7-4: SO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
10-min mean 500 74.85 15% NA 740675 3072975
Highest 1-hr Mean 730 41.92 6% MINOR 740450 3072400
99.7th Percentile of 24-hr Means 365 15.03 4% NEGLIGIBLE 740550 3072150
Annual Mean 80 6.46 8% NA 740450 3072250
Table A7-5: NO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 60.29 9% MINOR 740450 3072400
Annual Mean 100 18.57 19% NA 740450 3072250
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A7-6: PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 6.90 2% NEGLIGIBLE 740450 3072200
Annual Mean 80 4.29 5% NA 740450 3072250
Project number: 37446130 Dated: 09/11/2014 336 | 278 Revised:
Predicted Concentrations: Maximum at Sensitive Receptors – Option A (Combined Cycle) Table A7-7: SO2 Concentrations
Receptor
UTM Grid Ref SO2 Concentrations (µg/m3)
Easting Northing Annual Mean
Percentage of PME
AQS Impact
Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
99.7th Percentile
of 24-hour
Means
Percentage of PME AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.08 <1% NA 18.86 3% NEGLIGIBLE 1.71 <1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.15 <1% NA 15.22 2% NEGLIGIBLE 1.14 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.15 <1% NA 14.73 2% NEGLIGIBLE 0.97 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.15 <1% NA 14.25 2% NEGLIGIBLE 0.86 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.16 <1% NA 12.92 2% NEGLIGIBLE 1.33 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.14 <1% NA 14.09 2% NEGLIGIBLE 1.09 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.15 <1% NA 12.29 2% NEGLIGIBLE 1.50 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.16 <1% NA 13.89 2% NEGLIGIBLE 1.33 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.14 <1% NA 8.64 1% NEGLIGIBLE 1.32 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 1.74 <1% NEGLIGIBLE 0.19 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.10 <1% NA 5.58 1% NEGLIGIBLE 1.24 <1% NEGLIGIBLE
Table A7-8: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.17 <1% NA 23.51 4% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.38 <1% NA 18.51 3% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.37 <1% NA 17.78 3% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.38 <1% NA 16.99 3% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.39 <1% NA 16.27 2% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.35 <1% NA 17.09 3% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.37 <1% NA 15.05 2% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.40 <1% NA 16.76 3% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.35 <1% NA 10.43 2% NEGLIGIBLE
10 Alsourah 732009 3083693 0.03 <1% NA 2.14 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.24 <1% NA 6.73 1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Project number: 37446130 Dated: 09/11/2014 338 | 278 Revised:
Table A7-9: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance
90th Percentile of 24-hour
Means
Percentage of PME
AQS Impact
Significance
1 Central Control Building 486394.2 3501816.3 0.07 <1% NA 0.19 <1% NEGLIGIBLE
2 Main Administration Building 486450.0 3501827.7 0.12 <1% NA 0.23 <1% NEGLIGIBLE
3 Canteen 486471.7 3501798.7 0.12 <1% NA 0.23 <1% NEGLIGIBLE
4 Mosque 486584.4 3501812.2 0.13 <1% NA 0.25 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 486315.7 3501820.4 0.13 <1% NA 0.26 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 486411.8 3501771.9 0.12 <1% NA 0.22 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 486409.2 3501869.5 0.12 <1% NA 0.23 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 486225.0 3499915.0 0.13 <1% NA 0.26 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 486345.0 3504020.0 0.12 <1% NA 0.42 <1% NEGLIGIBLE
10 Alsourah 486595.0 3504020.0 0.01 <1% NA 0.04 <1% NEGLIGIBLE
11 Almuwaylih 486595.0 3503820.0 0.08 <1% NA 0.26 <1% NEGLIGIBLE
Predicted Concentrations: Maximum at Sensitive Receptors – Option B (Combined Cycle)
Table A7-10: SO2 Concentrations
Receptor
UTM Grid Ref SO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
99.7th Percentile
of 24-hour
Means
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.09 <1% NA 23.88 3% NEGLIGIBLE 2.15 1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.18 <1% NA 18.03 2% NEGLIGIBLE 1.30 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.18 <1% NA 17.38 2% NEGLIGIBLE 1.10 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.19 <1% NA 16.91 2% NEGLIGIBLE 0.98 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.19 <1% NA 15.02 2% NEGLIGIBLE 1.67 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.17 <1% NA 16.38 2% NEGLIGIBLE 1.29 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.18 <1% NA 14.47 2% NEGLIGIBLE 1.86 1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.19 <1% NA 16.56 2% NEGLIGIBLE 1.53 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.16 <1% NA 9.70 1% NEGLIGIBLE 1.47 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.02 <1% NA 2.13 <1% NEGLIGIBLE 0.22 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.12 <1% NA 6.48 1% NEGLIGIBLE 1.57 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 340 | 278 Revised:
Table A7-11: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.27 <1% NA 34.33 5% MINOR
2 Main Administration Building 741657 3072763.9 0.53 1% NA 25.92 4% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.52 1% NA 25.00 4% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.54 1% NA 24.32 4% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.54 1% NA 21.59 3% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.49 <1% NA 23.55 4% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.50 1% NA 20.80 3% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.55 1% NA 23.82 4% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.49 <1% NEGLIGIBLE 13.94 2% NEGLIGIBLE
10 Alsourah 732009 3083693 0.05 <1% NEGLIGIBLE 3.06 0% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.45 <1% NEGLIGIBLE 9.31 1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A7-12: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage of PME AQS
Impact Significance
90th Percentile of 24-hour
Means
Percentage of PME
AQS Impact
Significance
1 Central Control Building 486394.2 3501816.3 0.06 <1% NA 0.16 <1% NEGLIGIBLE
2 Main Administration Building 486450.0 3501827.7 0.12 <1% NA 0.23 <1% NEGLIGIBLE
3 Canteen 486471.7 3501798.7 0.12 <1% NA 0.22 <1% NEGLIGIBLE
4 Mosque 486584.4 3501812.2 0.12 <1% NA 0.24 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 486315.7 3501820.4 0.13 <1% NA 0.25 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 486411.8 3501771.9 0.11 <1% NA 0.21 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 486409.2 3501869.5 0.12 <1% NA 0.22 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 486225.0 3499915.0 0.13 <1% NA 0.25 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 486345.0 3504020.0 0.11 <1% NA 0.39 <1% NEGLIGIBLE
10 Alsourah 486595.0 3504020.0 0.01 <1% NA 0.03 <1% NEGLIGIBLE
11 Almuwaylih 486595.0 3503820.0 0.08 <1% NA 0.27 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 342 | 278 Revised:
Predicted Concentrations: Maximum point of Impact – Option A (Simple Cycle) Table A7-13: SO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
10-min mean 500 184.27 37% NA 740750 3072875
Highest 1-hr Mean 730 76.00 10% MINOR 740675 3073075
99.7th Percentile of 24-hr Means 365 25.32 7% MINOR 740600 3072850
Annual Mean 80 4.59 6% NA 740550 3072700
Table A7-14: NO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 109.24 17% MINOR 740675 3073075
Annual Mean 100 13.18 13% NA 740575 3072800
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A7-15: PM10 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 8.08 2% NEGLIGIBLE 740600 3072850
Annual Mean 80 3.05 4% NA 740575 3072800
Predicted Concentrations: Maximum point of Impact – Option B (Simple Cycle)
Table A7-16: SO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
10-min mean 500 350.01 70% NA 740750 3072875
Highest 1-hr Mean 730 129.97 18% MINOR 740750 3072875
99.7th Percentile of 24-hr Means 365 25.52 7% NEGLIGIBLE 740600 3072850
Annual Mean 80 5.72 7% NA 740550 3072450
Table A7-17: NO2 Concentrations
Averaging Period Air Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
Highest 1-hr Mean 660 186.91 28% MODERATE 740750 3072875
Annual Mean 100 16.45 16% 740550 3072450
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A7-18: PM10 Concentrations
Averaging Period Air
Quality Standard
Concentration (µg/m3)
Percentage of AQS
Impact Significance
Location
Easting Northing
90th Percentile of 24-hr Means 340 12.30 4% NEGLIGIBLE 740575 3072775
Annual Mean 80 5.72 7% NA 740550 3072450
Project number: 37446130 Dated: 09/11/2014 344 | 278 Revised:
Predicted Concentrations: Maximum at Sensitive Receptors – Option A (Simple Cycle) Table A7-19: SO2 Concentrations
Receptor
UTM Grid Ref SO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS
Impact Significance
99.7th Percentile
of 24-hour
Means
Percentage of PME
AQS
Impact Significance
1 Central Control Building 740600.7 3073056.5 0.12 <1% NA 43.65 6% MINOR 2.73 1% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.08 <1% NA 10.06 1% NEGLIGIBLE 0.87 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.08 <1% NA 9.82 1% NEGLIGIBLE 0.71 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.08 <1% NA 9.31 1% NEGLIGIBLE 0.61 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.09 <1% NA 11.08 2% NEGLIGIBLE 1.16 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.08 <1% NA 8.23 1% NEGLIGIBLE 0.71 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.09 <1% NA 8.47 1% NEGLIGIBLE 1.21 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.09 <1% NA 9.48 1% NEGLIGIBLE 0.93 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.08 <1% NA 4.76 1% NEGLIGIBLE 0.95 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 1.25 <1% NEGLIGIBLE 0.15 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.06 <1% NA 3.47 <1% NEGLIGIBLE 0.56 <1% NEGLIGIBLE
Table A7-20: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.32 <1% NA 62.77 10% MINOR
2 Main Administration Building 741657 3072763.9 0.21 <1% NA 13.57 2% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.20 <1% NA 12.36 2% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.21 <1% NA 11.72 2% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.23 <1% NA 15.03 2% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.21 <1% NA 10.91 2% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.22 <1% NA 11.42 2% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.23 <1% NA 13.54 2% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.21 <1% NA 5.93 1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.03 <1% NA 1.60 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.14 <1% NA 4.43 1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Project number: 37446130 Dated: 09/11/2014 346 | 278 Revised:
Table A7-21: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance
90th Percentile of 24-hour
Means
Percentage of PME AQS
Impact Significance
1 Central Control Building 486394.2 3501816.3 0.09 <1% NA 0.19 <1% NEGLIGIBLE
2 Main Administration Building 486450.0 3501827.7 0.06 <1% NA 0.11 <1% NEGLIGIBLE
3 Canteen 486471.7 3501798.7 0.06 <1% NA 0.11 <1% NEGLIGIBLE
4 Mosque 486584.4 3501812.2 0.06 <1% NA 0.12 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 486315.7 3501820.4 0.07 <1% NA 0.13 0% NEGLIGIBLE
6 Company Housing Compound (NE) 486411.8 3501771.9 0.06 <1% NA 0.11 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 486409.2 3501869.5 0.06 <1% NA 0.12 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 486225.0 3499915.0 0.07 <1% NA 0.13 0% NEGLIGIBLE
9 Fish Farm (on-shore) 486345.0 3504020.0 0.07 <1% NA 0.24 <1% NEGLIGIBLE
10 Alsourah 486595.0 3504020.0 0.01 <1% NA 0.03 <1% NEGLIGIBLE
11 Almuwaylih 486595.0 3503820.0 0.04 <1% NA 0.14 <1% NEGLIGIBLE
Predicted Concentrations: Maximum at Sensitive Receptors – Option B (Simple Cycle)
Table A7-22: SO2 Concentrations
Receptor
UTM Grid Ref SO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact
Significance
99.7th Percentile of 24-hour
Means
Percentage of PME
AQS Impact
Significance
1 Central Control Building 740600.7 3073056.5 0.20 <1% NA 60.07 8% MINOR 11.55 3% NEGLIGIBLE
2 Main Administration Building 741657 3072763.9 0.12 <1% NA 17.00 2% NEGLIGIBLE 1.15 <1% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.12 <1% NA 15.35 2% NEGLIGIBLE 0.94 <1% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.12 <1% NA 14.83 2% NEGLIGIBLE 0.82 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.12 <1% NA 14.39 2% NEGLIGIBLE 1.71 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.11 <1% NA 11.23 2% NEGLIGIBLE 1.05 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.12 <1% NA 11.04 2% NEGLIGIBLE 1.57 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.13 <1% NA 13.03 2% NEGLIGIBLE 1.20 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.11 <1% NA 6.03 1% NEGLIGIBLE 1.18 <1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.01 <1% NA 1.72 <1% NEGLIGIBLE 0.18 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.08 <1% NA 4.88 1% NEGLIGIBLE 0.85 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 348 | 278 Revised:
Table A7-23: NO2 Concentrations
Receptor
UTM Grid Ref NO2 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance 1-hour Mean
Percentage of PME
AQS Impact Significance
1 Central Control Building 740600.7 3073056.5 0.58 <1% NA 86.39 13% MINOR
2 Main Administration Building 741657 3072763.9 0.34 <1% NA 24.44 4% NEGLIGIBLE
3 Canteen 741678.4 3072721.1 0.33 <1% NA 22.08 3% NEGLIGIBLE
4 Mosque 741621.3 3072692.5 0.35 <1% NA 21.32 3% NEGLIGIBLE
5 Company Housing Compound (NW) 741100.3 3073777.3 0.36 <1% NA 20.70 3% NEGLIGIBLE
6 Company Housing Compound (NE) 741193.1 3073820.2 0.32 <1% NA 16.16 2% NEGLIGIBLE
7 Company Housing Compound (SE) 741235.9 3073727.4 0.34 <1% NA 15.88 2% NEGLIGIBLE
8 Company Housing Compound (SW) 741143.1 3073688.1 0.36 <1% NA 18.74 3% NEGLIGIBLE
9 Fish Farm (on-shore) 739340 3074614 0.32 <1% NA 8.67 1% NEGLIGIBLE
10 Alsourah 732009 3083693 0.04 <1% NA 2.48 <1% NEGLIGIBLE
11 Almuwaylih 744386 3067138 0.22 <1% NA 7.01 1% NEGLIGIBLE
NB - 50% oxidation of NOx to NO2 assumed for 1-hour mean concentrations; 100% oxidation for annual means
Table A7-24: PM10 Concentrations
Receptor
UTM Grid Ref PM10 Concentrations (µg/m3)
Easting Northing Annual Mean Percentage
of PME AQS
Impact Significance
90th Percentile of
24-hour Means
Percentage of PME
AQS Impact
Significance
1 Central Control Building 486394.2 3501816.3 0.20 <1% NA 0.34 <1% NEGLIGIBLE
2 Main Administration Building 486450.0 3501827.7 0.12 <1% NA 0.21 <1% NEGLIGIBLE
3 Canteen 486471.7 3501798.7 0.12 <1% NA 0.21 <1% NEGLIGIBLE
4 Mosque 486584.4 3501812.2 0.12 <1% NA 0.21 <1% NEGLIGIBLE
5 Company Housing Compound (NW) 486315.7 3501820.4 0.12 <1% NA 0.23 <1% NEGLIGIBLE
6 Company Housing Compound (NE) 486411.8 3501771.9 0.11 <1% NA 0.20 <1% NEGLIGIBLE
7 Company Housing Compound (SE) 486409.2 3501869.5 0.12 <1% NA 0.20 <1% NEGLIGIBLE
8 Company Housing Compound (SW) 486225.0 3499915.0 0.13 <1% NA 0.23 <1% NEGLIGIBLE
9 Fish Farm (on-shore) 486345.0 3504020.0 0.11 <1% NA 0.41 <1% NEGLIGIBLE
10 Alsourah 486595.0 3504020.0 0.01 <1% NA 0.04 <1% NEGLIGIBLE
11 Almuwaylih 486595.0 3503820.0 0.08 <1% NA 0.27 <1% NEGLIGIBLE
Project number: 37446130 Dated: 09/11/2014 350 | 278 Revised:
Appendix J – Recirculation Study Report
Recirculation Study Report
Saudi Electricity Company
Recirculation Studies for Various Power Plant
Sites - Duba Power Plant October 2014
Revision 0
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 i
DOCUMENT INFORMATION
Project Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Report Title Recirculation Study Report
Client Saudi Electricity Company
Location Saudi Arabia
Author Abdelhadi Mehdi Ghozali
Project Manager Avni Buyukozer
Project Director Jorge Trindade
Report No. SGF11129-RPT-MRN-052-00
Format Code SGF09-FMT-QMS-008-03-rev00
DOCUMENT HISTORY
Rev Date Description Issued Reviewed Approved
0 27/10/2014 AGI ABR JWR
SOGREAH GULF FZCO
P.O. Box 18271
Jebel Ali, Dubai, United Arab Emirates
Phone: +971 (0)4 886 56 90
Fax : +971 (0)4 886 56 91
Email: [email protected]
ح م ش الخليج سوجرية
17281ص.ب:
، دبي ، الامارات العربية المتحدة جبل علي
: 90 56 886 4(0) 971+تليفون
: 91 56 886 4(0) 971+فاكس
[email protected] ايميل
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 ii
EXECUTIVE SUMMARY
Sogreah Gulf - Artelia Group was appointed by Saudi Electricity Company (SEC)
to carry out data collection and numerical modelling of thermal effluent transport
(recirculation studies) for the Duba Thermal Power Plant project on the Red Sea
coast of Saudi Arabia.
This report deliverable documents the numerical modelling studies undertaken to
assess various intake / outfall configurations, for the environmental conditions at
the project site.
A detailed TELEMAC-3D model was developed, making use of available field
data, and used to assess thermal effluent transport at the project site.
Direct access to cooler water from deep areas outside the reef is necessary to
comply with plant operational criteria (maximum intake temperature of 31°C),
since water temperatures inside the reef are expected to reach 33°C in late
summer. A numerical simulation of a base case layout (Option 1) proposed by
SEC incorporating an intake basin and an outfall channel both extending to the
edge of the reef was carried out.
The base case layout was found to comply with the PME, plant intake and
temperature criteria. Two other configurations (Option 2 and Option 3) with
different length intake basins were also investigated. Option 2 and Option 3 also
comply with the PME criteria. It is anticipated that the construction costs for Option
2 and Option 3 layouts will be lower than the base case layout.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 iii
TABLE OF CONTENTS
Executive Summary ........................................................................................ ii
1 Introduction ...................................................................................... 1
1.1 Project Location and Site Characteristics .......................................... 1
1.2 Study Objectives ........................................................................... 2
1.3 Report Structure ............................................................................ 3
2 Intake / Outfall Design Criteria and Layout Concepts ............................ 4
2.1 Design Criteria ............................................................................. 4
2.2 Environmental (Mixing Zone) Criteria .............................................. 4
2.3 Layout Concepts ........................................................................... 5
3 Field Data and Survey Campaign ....................................................... 9
3.1 Field Surveys ................................................................................ 9
3.2 Other Available Data .................................................................. 11
3.2.1 Seawater Temperature .................................................... 11
3.2.2 Air Temperature ............................................................. 12
3.2.3 Wind ............................................................................ 13
3.2.4 Tides ............................................................................. 15
4 Thermal Plume and Hydrodynamic Modelling ..................................... 16
4.1 Numerical Modelling Software ..................................................... 16
4.2 Overview of Modelling Approach ................................................. 17
4.3 Regional Hydrodynamic Model (Red Sea) ...................................... 17
4.3.1 Regional Model Set-Up ................................................... 17
4.3.2 Regional Model Calibration............................................. 18
4.3.3 Regional Model Validation .............................................. 21
4.4 Local Thermal Plume Model (Duba) ............................................... 24
4.4.1 Model Set-Up ................................................................. 24
4.4.2 Modelling Scenarios ....................................................... 26
5 Results ............................................................................................ 28
5.1 Option 1 Layout .......................................................................... 28
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 iv
5.1.1 Scenario 1A: SE Winds .................................................. 28
5.1.2 Scenario 1B: NW Winds ................................................ 36
5.2 Scenario 2 (Option 2 Layout) ....................................................... 44
5.3 Scenario 3 (Option 3 Layout) ....................................................... 52
6 Discussion And Summary ................................................................. 60
7 References ...................................................................................... 61
LIST OF FIGURES
Figure 1. Project site location plan. Image by Stamen Design, data by
OpenStreetMap (2014). ................................................................................ 1
Figure 2. Extract from Admiralty Chart 159 [1] showing bathymetry in areas
surrounding the project site. ........................................................................... 2
Figure 3. Duba Power Plant proposed layout ................................................... 6
Figure 4. Model Option 1 layout (Base Case). ................................................. 6
Figure 5. Model Option 2 layout. ................................................................... 7
Figure 6. Model Option 3 layout. ................................................................... 7
Figure 7. Regional extent of data collection components ................................... 9
Figure 8. Bed-mounted ADCP current speed time series ................................... 11
Figure 9: Climatic air temperature data for Hurghada Airport [8] ..................... 13
Figure 10: Wind roses for Hurghada Airport [8] ............................................ 13
Figure 11: Wind rose at Duba power Plant site for south-easterly winds (August
2000)........................................................................................................ 14
Figure 12: Wind rose at Duba Power Plant site for north-westerly winds (August
1995)........................................................................................................ 15
Figure 13. Red Sea Hydrodynamic Model computational mesh (left) and
bathymetry (right). ....................................................................................... 18
Figure 14. Admiralty tide predictions and modelled tidal elevations at Suez (top),
Um Qusur (middle) and Port Sudan (bottom). ................................................. 19
Figure 15. Admiralty tide predictions and modelled tidal elevations at Yanbu (top),
Jizan (middle) and Djibouti (bottom). ............................................................. 20
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 v
Figure 16. Admiralty tide predictions and modelled tidal elevations at Aqaba (top),
Jazirat Shakhir (middle) and Rabigh (bottom). ................................................ 22
Figure 17. Admiralty tide predictions and modelled tidal elevations at Jeddah (top)
and Al Hudaydah (bottom). ......................................................................... 23
Figure 18. Local Model computational mesh and bathymetry. .......................... 25
Figure 19. Schematic diagram of 3D local model, its boundary conditions and
heat transport processes. ............................................................................. 26
Figure 20. 15-day average seawater temperatures at the surface (Scenario 1A). 29
Figure 21. 15-day average seawater temperatures at the intake level (-14 mMSL)
(Scenario 1A). ............................................................................................ 30
Figure 22. Intake section showing 15-day average seawater temperatures
(Scenario 1A) ............................................................................................. 31
Figure 23. Plume section showing 15-day average seawater temperatures
(Scenario 1A) ............................................................................................. 32
Figure 24. 15-day averaged ∆T at the surface (Scenario 1A)........................... 33
Figure 25. 15-day averaged ∆T at the intake layer (Scenario1A) ..................... 34
Figure 26. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 1A. .................................................. 35
Figure 27. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 1A. ................................................................ 35
Figure 28. 15-day average seawater temperatures at the surface (Scenario 1B). 37
Figure 29. 15-day average seawater temperatures at the intake level (-14mMSL)
(Scenario 1B). ............................................................................................ 38
Figure 30. Intake section showing 15-day average seawater temperatures
(Scenario 1B) ............................................................................................. 39
Figure 31. Plume section showing 15-day average seawater temperatures
(Scenario 1B) ............................................................................................. 40
Figure 32. 15-day averaged ∆T at the surface (Scenario 1B) ........................... 41
Figure 33. 15-day averaged ∆T at the intake (Scenario 1B) ............................. 42
Figure 34. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 1B. .................................................. 43
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 vi
Figure 35. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 1B. ................................................................ 43
Figure 36. 15-day average seawater temperatures at the surface (Scenario 2). . 45
Figure 37. 15-day average seawater temperatures at the intake level (-14mMSL)
(Scenario 2). .............................................................................................. 46
Figure 38. Intake section showing 15-day average seawater temperatures
(Scenario 2) ............................................................................................... 47
Figure 39. Plume section showing 15-day average seawater temperatures
(Scenario 2) ............................................................................................... 48
Figure 40. 15-day averaged ∆T at the surface (Scenario 2) ............................. 49
Figure 41. 15-day averaged ∆T at the intake (Scenario 2) .............................. 50
Figure 42. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 2. .................................................... 51
Figure 43. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 2. .................................................................. 51
Figure 44. 15-day average seawater temperatures at the surface (Scenario 3). . 53
Figure 45. 15-day average seawater temperatures at the intake level (-14mMSL)
(Scenario 3). .............................................................................................. 54
Figure 46. Intake section showing 15-day average seawater temperatures
(Scenario 3) ............................................................................................... 55
Figure 47. Plume section showing 15-day average seawater temperatures
(Scenario 3) ............................................................................................... 56
Figure 48. 15-day averaged ∆T at the surface (Scenario 3) ............................. 57
Figure 49. 15-day averaged ∆T of the intake layer (Scenario 3) ...................... 58
Figure 50. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 3. .................................................... 59
Figure 51. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 3. .................................................................. 59
LIST OF TABLES
Table 1. Intake / outfall design criteria. ........................................................... 4
Table 2: Typical summer ambient seawater temperature profile (deep water) ..... 12
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 vii
Table 3: Typical summer ambient seawater salinity profile (deep water) ............ 12
Table 4: Umm Qusur tidal planes ................................................................. 15
Table 5: Summary of modelling scenarios ...................................................... 27
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 1
1 INTRODUCTION
Sogreah Gulf - Artelia Group ("ARTELIA", or "the Consultant") was appointed by
Saudi Electricity Company ("SEC", or "the Client") to carry out data collection and
numerical modelling of thermal effluent transport (recirculation studies) for the Duba
Power Plant project on the Red Sea coast of Saudi Arabia.
The project ("the WORKS") involves the construction of a thermal power plant at a
location approximately 90km south east of the entrance of the Gulf of Aqaba.
This document describes the numerical modelling undertaken to evaluate thermal
recirculation at the project site.
1.1 Project Location and Site Characteristics
The Duba Power Plant site will be constructed on a 1.5km by 1.2km plot (with
marine works extending west of the plot), located approximately 90km south east
of the entrance to the Gulf of Aqaba on the Red Sea coast of Saudi Arabia (Figure
1).
Figure 1. Project site location plan. Image by Stamen Design, data by
OpenStreetMap (2014).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 2
The project site is situated between the Ra’s Wadi Tarim to the north and Al
Muwaylih to the south (Figure 2). The nearshore bathymetry features shallow and
exposed reefs together with very deep (>300m) water close to the shoreline [1].
Figure 2. Extract from Admiralty Chart 159 [1] showing bathymetry in areas
surrounding the project site.
1.2 Study Objectives
The objectives of the recirculation study are to:
– Determine the impact of the thermal discharge from the power plant (i.e. the
extent of temperature increases above ambient seawater temperature);
– Assess the potential of thermal recirculation which could impede the
efficiency the power plant operations; and to
– Recommend suitable layout concepts for the intake / outfall channels.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 3
1.3 Report Structure
The report is structured as follows:
– Section 1 - Introduction.
– Section 2 - Intake / Outfall Design Criteria and Layout Concepts. This section
sets the basis for the assessment of the intake / outfall configuration and
presents the layout concepts.
– Section 3 - Available Data. This section briefly describes the data collection
activities and identifies the various datasets and information used as input to
the study.
– Section 4 - Thermal Plume and Hydrodynamic Modelling. This section
describes the numerical modelling methodology.
– Section 5 - Results (Thermal Plume Modelling). This section presents the results
for the numerical modelling scenarios.
– Section 6 – Discussion and Summary. This section discusses the key findings
of the thermal plume modelling.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 4
2 INTAKE / OUTFALL DESIGN CRITERIA AND LAYOUT
CONCEPTS
2.1 Design Criteria
Basic (non-exhaustive) plant design criteria for the intake / outfall system were
provided by SEC and are reproduced in Table 1.
Table 1. Intake / outfall design criteria.
Intake discharge 80,000m3/hr (continuous)
Maximum permissible velocity of
seawater in intake / pipes
1.5m/s
Maximum permissible velocity of
seawater at entrance to pumping
station
0.3m/s
Maximum permissible seawater
temperature at intake pipes
31°C
Outfall discharge 80,000m3/hr (continuous)
Temperature of effluent (at outfall) 5°C above temperature of intake
Salinity of effluent (at outfall) Identical to salinity of ambient seawater
at intake (i.e. negligible brine content)
2.2 Environmental (Mixing Zone) Criteria
Environmental criteria for power plant discharges in Saudi Arabia are regulated
by the Presidency of Meteorology and Environment (PME), under the recently
published National Environmental Standard for Ambient Water Quality [2]. This
standard revises the General Standards for the Environment [3].
The new standard [2] specifies changes in ambient seawater temperatures (ΔT) not
to be exceeded outside the effluent mixing zone, which is defined based on the
local water depth and on whether the site is classified as “Marine” (the default),
“High Value”, or “Industrial”. As confirmed by SEC, the site will be classified as
"Industrial". The "Industrial" classification allows for a maximum ΔT = 4°C outside
the mixing zone.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 5
Based on typical water depths less than 5m and an "Industrial" site classification,
the horizontal extent of the mixing zone for an outfall located near the shore is
40m [2]. This increases to 100m (the maximum permissible) for an outfall located
in 13m water depths.
According to Article I 5 of the standard, the specified value of ΔT (4°C) may be
exceeded inside the mixing zone provided that other criteria are met, including:
– Acutely toxic conditions are not reached (based on testing for Whole Effluent
Toxicity);
– The mixing zone does not impinge on sensitive areas, such as coral reefs,
recreational areas or important spawning or nursery areas for aquatic
organisms; and
– The mixing zone does not impinge the mean low water spring (MLWS)
shoreline.
Assuming all other requirements for the effluent are met (e.g. with regard to
toxicity, etc.), the target for compliance with mixing zone criteria is to ensure
ambient seawater temperatures do not increase by more than 4°C at (i) distances
greater than 40m from end of the outfall, (ii) coral reef areas, or (iii) the MLWS
shoreline.
2.3 Layout Concepts
Three different layout concepts were investigated:
- Option 1 (Base Case) – 300m long Intake lagoon / enclosure with submerged
pipes at the natural seabed level of -14mMSL. An outfall channel guided by
breakwaters. This layout was based on SEC’s proposed layout [4] (Figure 3
and Figure 4).
- Option 2 – 200m long intake lagoon with a 100m long dredged channel
at -15mMSL. This layout was based on the results of Option 1 and was
proposed by the Consultant (Figure 5)
- Option 3 – 100m long intake lagoon with a 200m long dredged channel
at -15mMSL. This layout was based on the results of Option 1 and Option 2
and was proposed by the Consultant (Figure 6)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 6
Figure 3. Duba Power Plant proposed layout
Figure 4. Model Option 1 layout (Base Case).
Intake Lagoon
Breakwater
Outfall Channel
dredged to -1.5 mMSL
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 7
Figure 5. Model Option 2 layout.
Figure 6. Model Option 3 layout.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 8
The options above are listed in order of decreasing capital constructions cost.
Option 1 was developed to investigate the potential for a submerged array of
pipes set at approximately -14mMSL to convey cooler water from near the seabed
(-15mMSL) to an enclosed intake basin (Figure 4). The outfall channel located at
the southern end of the site and flanked by two 300m long breakwaters is to be
dredged to -1.5mMSL.
Option 2 is similar to Option 1 but with a 200m long intake basin (100m shorter
than Option 1) and a trapezoidal channel dredged to -15mMSL to convey cooler
water from the edge of the reef to the intake pipes set at approximately -14mMSL.
Option 3 is a variant of Option 2, with a 100m long intake basin (200m shorter
than Option 1) and a similar trapezoidal channel dredged to -15mMSL to convey
cooler water from the edge of the reef to the intake pipes set at
approximately -14mMSL.
Shortening of the outfall breakwaters was not considered as an option because of
the potential impact of the outflow on the coral reef area.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 9
3 FIELD DATA AND SURVEY CAMPAIGN
3.1 Field Surveys
The data collection programme was completed during a 3 week period that
encompasses a spring and neap tide cycle [5]. A weather station was
commissioned on the 25th June 2014 at the nearby Coast Guard base. On the
same date, a bed mounted ADCP (Fixed ADCP in approximately 19m water
depth) was deployed for a 3 week period (Figure 7). A non-vented tide gauge was
also deployed for the same time period.
ADCP transects were conducted on subsequent days along Transect 1 and
Transect 2 (Figure 7). Thermistor strings to measure conductivity and temperature
were deployed at strategic locations within the study area.
Figure 7. Regional extent of data collection components
Measured currents were typically less than 0.2m/s, as shown in Figure 8 for the
fixed (bed-mounted) ADCP.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 10
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 11
Figure 8. Bed-mounted ADCP current speed time series
3.2 Other Available Data
3.2.1 Seawater Temperature
No long-term measurements of ambient seawater temperature or salinity were
available for the project site. "Typical" summer ambient profiles were estimated
based on the Journal of Geophysical Research, 2007 [6]. The paper includes data
collected along a transect in the northern Red Sea during August 2001. The survey
indicates spatially uniform seawater temperatures and salinity. The temperature
profile is reasonably consistent with the sea surface temperature contours in the
Red Sea and Gulf of Aden Pilot [4] and profiles available within the NOAA World
Oceanographic Database (WOD) [7]. The majority of the CTD casts were in deep
water and it is noted that temperatures may be higher in the reef areas. The
resulting simplified typical (deep water) summer temperature and salinity profiles
are shown in Table 2 and Table 3 respectively.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 12
Table 2: Typical summer ambient seawater temperature profile (deep water)
Approximate Water Depth (m) Temperature (°C)
Less than 30 31
30 to 40 26
40 to 50 25
50 to 60 24
60 to 80 23
Greater than or equal to 100 22
Table 3: Typical summer ambient seawater salinity profile (deep water)
Approximate Water Depth (m) Salinity (PSU)
Less than 50 40
50 to 60 40.1
60 to 80 40.2
Greater than or equal to 100 40.5
3.2.2 Air Temperature
A statistical summary of climatic air temperature data is provided in the Red Sea
and Gulf of Aden Pilot [8] for the nearby World Meteorological organization
station number 62463 (Hurghada Airport), which is approximately 170 km west
of the Duba Power Plant site. The climate information is based on data spanning
an 18 year period (1990-2007). The mean daily maximum and minimum air
temperature are approximately 37.5 °C and 27.5 °C, respectively (Figure 9).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 13
Figure 9: Climatic air temperature data for Hurghada Airport [8]
3.2.3 Wind
Wind roses are provided in the Red Sea and Gulf of Aden Pilot [8] for Hurghada
Airport (Figure 10). The roses indicate strong prevailing winds, predominantly from
the westerly to northerly sectors, with less frequent south-westerly winds. Wind
speeds are typically less than 10 m/s in summer months.
Figure 10: Wind roses for Hurghada Airport [8]
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 14
10m elevation 10-minute average wind speed data was obtained from the
European Centre for Medium-Range Weather Forecasts (ECMWF) [9]. ECMWF is
an intergovernmental organisation supported by 34 states, which provides
operational medium- and extended-range forecasts. The data, which includes
atmospheric parameters (e.g. wind speeds) on a global 2.5° grid at 6-hourly
intervals for the period 1992 to 2002, was analysed to identify "typical"
representative wind conditions for use in the recirculation study (Section 4). Two
relatively calm summer periods, one between 29th of July to 31st of August 2000
(hereafter referred to as south-easterly winds) and another between 29th of July to
31st of August 1995 (hereafter referred to as north-westerly winds) were selected
for further analysis.
The wind roses at the project site for south-easterly (SE) winds (August 2000) and
north-westerly (NW) winds (August 1995) are shown in Figure 11 and Figure 12.
Figure 11: Wind rose at Duba power Plant site for south-easterly winds (August
2000)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 15
Figure 12: Wind rose at Duba Power Plant site for north-westerly winds (August
1995)
3.2.4 Tides
The tidal range at the project site is small (MHWS – MLWS = 0.5m). Tides are
predominantly semi-diurnal. Characteristic tidal planes at Umm Qusur (an
admiralty station located at 30km north Duba Power Plant site) are listed in Table
4 [10].
Table 4: Umm Qusur tidal planes
Characteristic Tidal Plane Elevation (mCD) Elevation (mMSL)
Highest Astronomical Tide (HAT) +1.0 +0.5
Mean High Water Spring (MHWS) +0.8 +0.3
Mean High Water Neap (MHWN) +0.7 +0.2
Mean Sea Level (MSL) +0.5 +0.0
Mean Low Water Neap (MLWN) +0.4 -0.1
Mean Low Water Spring (MLWS) +0.3 -0.2
Lowest Astronomical Tide (LAT) +0.13 -0.37
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 16
4 THERMAL PLUME AND HYDRODYNAMIC MODELLING
4.1 Numerical Modelling Software
A TELEMAC-3D flow model was developed to simulate the transport of thermal
effluent by tide-, wind- and density-driven currents in areas surrounding the
proposed Duba Power Plant site. TELEMAC-3D is part of TELEMAC (Hervouet,
2007) , a finite element-based hydrodynamic modelling system under development
since 1987 by Laboratoire National d’Hydraulique (LNHE) of Electricite de France
(EDF). The system is widely used (over 150 commercial licenses issued worldwide
prior to the open source distribution era, which commenced in 2010) and has
been extensively documented and validated in accordance with the
recommendations of the International Association of Hydraulic Research (IAHR).
TELEMAC-3D solves the Navier-Stokes equations of free surface flow in three
dimensions (with or without the hydrostatic pressure assumption) and the transport-
diffusion equations of intrinsic quantities (temperature, salinity, concentration). The
equations are solved using finite element (or alternatively, finite volume) methods,
which allow for discretization of the domain on flexible, multi-layered, unstructured
meshes (typically consisting of triangular prisms). The principle advantage of this
approach is that it enables accurate representation of complex coastlines and
detailed bathymetry with maximum computational efficiency.
TELEMAC-3D accounts for the following phenomena, many of which are important
in assessing flow and transport in rivers, lakes, coastal embayments and seas:
– Influence of temperature or salinity on density;
– Bottom friction;
– Coriolis force;
– Atmospheric pressure and wind effects;
– Heat exchange with atmosphere;
– Fluid and momentum sources and sinks within the domain;
– First order (constant diffusivity) or complex (k-epsilon) turbulence models
including effects of Archimedes’ force (buoyancy);
– Wetting and drying (e.g. tidal flats and floodplains); and
– Tracer (conservative or decaying) transport and diffusion by currents.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 17
4.2 Overview of Modelling Approach
The recirculation study was carried out in two stages:
– Stage 1 – Regional Hydrodynamic Model. A large scale 3-D hydrodynamic
model of the Red Sea (Section 4.3) was used to establish general regional
circulation patterns and provide boundary conditions for the Local Thermal
Plume Model.
– Stage 2 – Local Thermal Plume Model. A local scale 3-D model of the Duba
Power Plant site and surrounding areas (Section 4.4) was used to evaluate
thermal effluent transport (advection and diffusion) and recirculation, using
hydrodynamic boundary condition input supplied by the Regional Model.
4.3 Regional Hydrodynamic Model (Red Sea)
A TELEMAC-3D model of the Red Sea was developed, calibrated and validated
against tidal constituents at various locations throughout the region. The Regional
Model establishes general circulation patterns around the Red Sea due to tides and
wind, including along the Duba Power Plant site coast, and provides boundary
conditions to the nested Local Thermal Plume Model (Section 4.4).
4.3.1 Regional Model Set-Up
The computational domain of the TELEMAC-3D Regional Hydrodynamic Model
extends from Suez in the north of the Red Sea to the open sea boundary between
Aden and Berbera in the Gulf of Aden. The model bathymetry and computational
mesh are shown in Figure 13. The mesh consists of more than 590,000 triangular
prismatic elements and 12 layers, with increased resolution at areas of steep
bathymetry and the Bab-el-Mandeb Strait, which connects the Red Sea to the Gulf
of Aden.
The coastline and bathymetry of the model were generated from:
– Digitized Admiralty charts;
– The GEBCO_08 Grid [11], a global continuous terrain (land and sea) model
with a spatial resolution of 30 arc-seconds.
The open boundary between Aden and Berbera was forced using Admiralty tide
predictions [10]. Wind boundary conditions were applied as spatially varying
wind fields, based on 10m elevation (10-min average) wind speeds output at 6-
hourly intervals from the ECMWF database (Dee et al., 2011) and linearly
interpolated to the Red Sea model mesh.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 18
Figure 13. Red Sea Hydrodynamic Model computational mesh (left) and
bathymetry (right).
4.3.2 Regional Model Calibration
The Red Sea hydrodynamic model was calibrated against Admiralty tides at the
following locations / stations (Figure 13):
– Suez;
– Um Qusur;
– Port Sudan;
– Madinat Yanbu as Sinaiyah;
– Jizan; and
– Djibouti.
Based on the final calibrated model parameters, Admiralty tide predictions and
model-predicted free surface elevations are shown in Figure 14 and Figure 15 for
the calibration period (7th January to 4th February 2001). The model captures the
variation in tidal range throughout the Red Sea, with peak values (greater than
2m) occurring in the north and near the Bab el Mandeb strait in the south. Tidal
Jeddah
Aqaba Suez
Yanbu
Port Sudan
Jizan
Djibouti
Jeddah
Aqaba Suez
Yanbu
Port Sudan
Jizan
Djibouti
Um Qusur Um Qusur Jazirat Shakhir
Al Hudaydah
Rabigh
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 19
ranges decrease to less than 0.1m at mid-latitudes (i.e. in the region between
Jeddah and Port Sudan).
Figure 14. Admiralty tide predictions and modelled tidal elevations at Suez (top),
Um Qusur (middle) and Port Sudan (bottom).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 20
Figure 15. Admiralty tide predictions and modelled tidal elevations at Yanbu (top),
Jizan (middle) and Djibouti (bottom).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 21
4.3.3 Regional Model Validation
Once the final Red Sea model parameter values were established through
calibration, goodness-of-fit between the model-predicted values and field
measurements was reassessed (validated) at the following locations / stations
(Figure 13):
– Aqaba;
– Jazirat Shakhir;
– Rabigh;
– Jeddah; and
– Al Hudaydah.
The spatial variation in tidal range is captured by the model for the locations listed
above. In particular, and of relevance to the present study, the small modelled tidal
range at Umm Qusur station matches the harmonic predictions.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 22
Figure 16. Admiralty tide predictions and modelled tidal elevations at Aqaba (top),
Jazirat Shakhir (middle) and Rabigh (bottom).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 23
Figure 17. Admiralty tide predictions and modelled tidal elevations at Jeddah (top)
and Al Hudaydah (bottom).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 24
4.4 Local Thermal Plume Model (Duba)
For the purpose of investigating transport and mixing of thermal effluent at the
power plant site, a local scale TELEMAC-3D model was developed to cover the site
and surrounding areas. The Local Model was driven (forced) by boundary
conditions extracted from the Regional (Red Sea) Hydrodynamic Model (Section
4.3).
4.4.1 Model Set-Up
A three-dimensional hydrodynamic and temperature model (TELEMAC-3D) was
developed for the Duba Power Plant site. The model bathymetry was based on
digitized Admiralty charts, GEBCO data (described in Section 3.1) and the
bathymetry collected on site (which only covers the area near the plant). The model
mesh was refined in areas surrounding the Duba Power Plant site to provide better
resolution of coastal and bathymetric features affecting local hydrodynamics (such
as the shallow reef areas). The model computational mesh, layer structure and
bathymetry are shown for the future (post-development) scenario in Figure 18. The
number and position of the model layers were selected to provide a suitable
compromise in terms of resolving ambient temperature and salinity gradients,
intake / outfall flow structure and to ensure compliance with Courant numerical
stability criteria (Figure 19). The ambient seawater temperature in the model was
initialized to 31°C based on the discussion in Section 3.2.1. The mesh consists of
around 360,000 triangular prismatic elements and 10 layers, with increased
resolution at the project site (characteristic element edge lengths around 10m).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 25
Figure 18. Local Model computational mesh and bathymetry.
The open boundary conditions used to drive the hydrodynamic model consisted of:
– Temporally and spatially varying water levels and currents extracted directly
from the Regional Hydrodynamic Model (Section 4.3);
– Prescribed seawater temperature and salinity at the open sea boundary
(Section 3.2.1);
– Diurnally varying air temperature (Section 3.2.2)
– Temporally varying wind fields (Section3.2.2);
– Specified outfall flow rates, temperature and salinity for post-development
scenarios (Section 2.1); and
– Specified intake flow rates for post-development scenarios (Section 2.1).
These boundary conditions and the key processes affecting seawater temperatures
computed by the model are shown schematized in Figure 19.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 26
Figure 19. Schematic diagram of 3D local model, its boundary conditions and
heat transport processes.
4.4.2 Modelling Scenarios
For the purpose of investigating transport, dilution and recirculation of thermal
effluent at the power plant site, a continuous discharge at both the intake and
outfall was simulated
After an initial "spin-up" period of approximately 3 days, the flow at the intake
and outfall were initialised based on the criteria described in Section 2.1. An
increase in temperature of 5°C (above the ambient at the intake head) was applied
to the outfall discharge.
Two periods were investigated for Option 1 Layout:
– A calm weather period with south-easterly winds; and
– A calm weather period with north-westerly winds.
Simulation results indicated that the south-easterly wind period marginally
represents the most critical condition for plant operations. Therefore, Option 2 and
Option 3 layouts were simulated only for the south-easterly wind period.
Open boundary
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 27
A summary of the full set of modelling scenarios is provided in Table 5.
Table 5: Summary of modelling scenarios
Scenario Layout Predominant Wind
Conditions
Scenario 1A Option 1 south-east
Scenario 1B Option 1 north-west
Scenario 2 Option 2 south-east
Scenario 3 Option 3 south-east
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 28
5 RESULTS
Pre- and post-development cases were modelled to investigate the thermal plume
dispersion and recirculation characteristics of the project development. This section
provides the results of the three layout options that were modelled.
5.1 Option 1 Layout
5.1.1 Scenario 1A: SE Winds
Option 1 layout driven by a calm weather period with south-easterly winds was
simulated for Scenario 1A. 15-day average seawater temperatures at the surface
and intake level (intake pipes at -14mMSL) are shown in Figure 20 and Figure 21.
Sections through the thermal plume and at the intake showing 15-day averaged
seawater temperatures are provided in Figure 22 to Figure 23.
To indicate the extent of the actual mixing zone (based on an "Industrial" site
classification, which uses a temperature criterion of ∆T = 4°C), plots of ∆T (the
difference between the 15-day average temperature for the post-development and
the pre-development) are presented at the surface and intake layer (Figure 24 and
Figure 25). The extent of the mixing zone does not impinge beyond the maximum
regulatory length of 40m, within which this temperature criterion may be
exceeded.
Time series plots of seawater temperature at the seaward end of the intake
enclosure, at the elevation of the submerged pipe inlet (-14 mMSL), and at the
seaward end of the outfall at the surface are provided in Figure 26 and Figure 27.
The temperature at the intake is not influenced by the thermal plume released from
the outfall and the temperature remained below the plant intake temperature
criteria of 31°C.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 29
Figure 20. 15-day average seawater temperatures at the surface (Scenario 1A).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 30
Figure 21. 15-day average seawater temperatures at the intake level (-14 mMSL)
(Scenario 1A).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 31
Figure 22. Intake section showing 15-day average seawater temperatures
(Scenario 1A)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 32
Figure 23. Plume section showing 15-day average seawater temperatures
(Scenario 1A)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 33
Figure 24. 15-day averaged ∆T at the surface (Scenario 1A)
T2
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 34
Figure 25. 15-day averaged ∆T at the intake layer (Scenario1A)
T1
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 35
Figure 26. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 1A.
Figure 27. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 1A.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 36
5.1.2 Scenario 1B: NW Winds
Option 1 layout driven by a calm weather period with north-westerly winds was
simulated for Scenario 1B. 15-day average seawater temperatures at the surface
and intake level (intake pipes at -14mMSL) are shown in Figure 28 and Figure 29.
Sections through the thermal plume and at the intake showing 15-day averaged
seawater temperatures are provided in Figure 30 and Figure 31.
To indicate the extent of the actual mixing zone, where ∆T may exceed 4°C, plots
of ∆T are presented at the surface and intake layer (Figure 32 and Figure 33). The
extent of the mixing zone does not impinge beyond the maximum regulatory length
of 40m, within which this temperature criterion may be exceeded.
Time series plots of seawater temperature at the seaward end of the intake
enclosure, at the elevation of the submerged pipe inlet (-14 mMSL), and at the
seaward end of the outfall at the surface are provided in Figure 34 and Figure 35.
The temperature at the intake is not influenced by the thermal plume released from
the outfall and the temperature remained below the plant intake temperature
criteria of 31°C.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 37
Figure 28. 15-day average seawater temperatures at the surface (Scenario 1B).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 38
Figure 29. 15-day average seawater temperatures at the intake level (-14mMSL)
(Scenario 1B).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 39
Figure 30. Intake section showing 15-day average seawater temperatures
(Scenario 1B)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 40
Figure 31. Plume section showing 15-day average seawater temperatures
(Scenario 1B)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 41
Figure 32. 15-day averaged ∆T at the surface (Scenario 1B)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 42
Figure 33. 15-day averaged ∆T at the intake (Scenario 1B)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 43
Figure 34. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 1B.
Figure 35. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 1B.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 44
5.2 Scenario 2 (Option 2 Layout)
Option 2 layout driven by a calm weather period with south-easterly winds was
simulated for Scenario 2. 15-day average seawater temperatures at the surface
and intake depth (intake pipes at -14mMSL) are shown in Figure 36 and Figure
37.
Sections through the thermal plume and the dredged intake channel showing
15-day average seawater temperatures are provided in Figure 38 and Figure 39.
To indicate the extent of the actual mixing zone, where ∆T may exceed 4°C, plots
of ∆T are presented at the surface and intake layer (Figure 40 and Figure 41). The
extent of the mixing zone does not impinge beyond the maximum regulatory length
of 40m, within which this temperature criterion may be exceeded.
Time series plots of seawater temperature at the seaward end of the intake
enclosure, at the elevation of the submerged pipe inlet (-14 mMSL), and at the
seaward end of the outfall at the surface are provided in Figure 42 and Figure 43.
The temperature at the intake is not influenced by the thermal plume released from
the outfall and the temperature remained below the plant intake temperature
criteria of 31°C.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 45
Figure 36. 15-day average seawater temperatures at the surface (Scenario 2).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 46
Figure 37. 15-day average seawater temperatures at the intake level (-14mMSL)
(Scenario 2).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 47
Figure 38. Intake section showing 15-day average seawater temperatures
(Scenario 2)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 48
Figure 39. Plume section showing 15-day average seawater temperatures
(Scenario 2)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 49
Figure 40. 15-day averaged ∆T at the surface (Scenario 2)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 50
Figure 41. 15-day averaged ∆T at the intake (Scenario 2)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 51
Figure 42. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 2.
Figure 43. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 2.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 52
5.3 Scenario 3 (Option 3 Layout)
Option 3 layout driven by a calm weather period with south-easterly winds was
simulated for Scenario 3. 15-day average seawater temperatures at the surface
and intake depth (intake pipes at -14mMSL) are shown in Figure 44 and Figure
45.
Sections through the thermal plume and the dredged intake channel showing 15-
day average seawater temperatures are provided in Figure 46 and Figure 47.
To indicate the extent of the actual mixing zone, where ∆T may exceed 4°C, plots
of ∆T are presented at the surface and intake layer (Figure 48 and Figure 49). The
extent of the mixing zone does not impinge beyond the maximum regulatory length
of 40m, within which this temperature criterion may be exceeded.
Time series plots of seawater temperature at the seaward end of the intake
enclosure, at the elevation of the submerged pipe inlet (-14 mMSL), and at the
seaward end of the outfall at the surface are provided in Figure 50 and Figure 51.
The temperature at the intake is not influenced by the thermal plume released from
the outfall and the temperature remained below the plant intake temperature
criteria of 31°C.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 53
Figure 44. 15-day average seawater temperatures at the surface (Scenario 3).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 54
Figure 45. 15-day average seawater temperatures at the intake level (-14mMSL)
(Scenario 3).
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 55
Figure 46. Intake section showing 15-day average seawater temperatures
(Scenario 3)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 56
Figure 47. Plume section showing 15-day average seawater temperatures
(Scenario 3)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 57
Figure 48. 15-day averaged ∆T at the surface (Scenario 3)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 58
Figure 49. 15-day averaged ∆T of the intake layer (Scenario 3)
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 59
Figure 50. Time series of 15-day average of seawater temperatures at the seaward
end of the intake enclosure for Scenario 3.
Figure 51. Time series of 15-day average of seawater temperatures at the seaward
end of the outfall for Scenario 3.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 60
6 DISCUSSION AND SUMMARY
A detailed TELEMAC-3D hydrodynamic model was developed and used to
quantitatively assess thermal effluent transport and dispersion for a number of
layouts, and environmental conditions at the Duba Power Plant site.
The numerical modelling results presented in Section 5 for various intake/outfall
configurations are discussed herein, in relation to compliance/non-compliance
with:
– Plant intake temperature criterion (i.e. T < 31°C) and
– PME environmental criterion (i.e. 15-day average ΔT < 4°C outside of the
mixing zone)
The layout of the base case (Option 1) comprises a 300m long intake enclosure
with submerged pipes at the natural seabed level of -14mMSL and an outfall
channel constrained by breakwaters. Option 1 complies with all of the criteria of
the project. An economical alternative (Option 2) was investigated by reducing the
intake lagoon length by 100m and providing a dredged channel at a bed level
of -15mMSL to convey cool water from offshore. Option 2 also complies with all
the criteria of the project. A third option (Option 3) investigated a further reduction
in the lagoon length by 200m and an increase in the length of the dredged
channel. Option 3 also complies with all of the criteria of the project. Shortening of
the outfall breakwaters was not considered as an option because of the potential
impact of the outflow on the coral reef area.
At the project site, the ambient tide- and wind-generated currents are weak
(typically less than 0.2m/s) both inside and outside the reef areas, confirming
initial field observations. The prevailing wind has little influence on the thermal
plume transport and mixing, with the predominant south-easterly wind condition
being only slightly more unfavourable for all layouts investigated.
The plant operational criteria (maximum intake temperature of 31°C), is satisfied
for all scenarios modelled and there is negligible recirculation observed during the
simulations.
PME mixing zone criteria are satisfied for all scenarios modelled (∆T < 4°C)
outside the 40m mixing zone – maximum allowable for industrial classification of
power plants. All three options presented comply with all the criteria discussed in
this report.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 61
7 REFERENCES
[1] U.K.H.O, "Admiralty Chart 159 – Suez (as Suways) to Berenice
(Barnis). Edition Number: 3," 2013.
[2] Presidency and Rules of Meteorology and Environment. National
Environmental Standard – Water Quality. Kingdom of Saudi Arabia,
Presidency of Meteorology and Environment, 2012.
[3] PME. General Environmental Regulations and Rules for
Implementation. Kingdom of Saudi Arabia, Presidency of
Meteorology and Environment, 2001.
[4] Saudi Electricity Company, "Duba No. 1 Combined Cycle Power
Plant Preliminary Comceptual Layout - GESDRW-DP-G-01 Rev. 2
Dated 12-06-2014," 2014.
[5] Sogreah Gulf - Artelia Group, "Data Collection Report - SGF11129-
RPT-MRN-055-00," 2014.
[6] S. Sofianos and W. Johns, "Observation of the summer Red Sea
circulation, C06025," Journal Of Geophysical Research, vol. 112,
2007.
[7] "NOAA, World Ocean Database (WOD09). National
Oceangraphic Data Center, Uited States Department of Commerce,"
2009. [Online]. [Accessed June 2014].
[8] U.K.H.O. Red Sea and Gulf of Aden Pilot. 16th Edition, 2009.
[9] D. Dee, S. Uppala, A. Simmons, P. Berrisford, P. Poli, S. Kobayashi,
U. Andrae, M. Balmaseda, G. Balsamo, P. Bauer, P. Bechtold, A.
Beljaars, L. Van de Berg, J. Bidlot, N. Bormann, C. Delsol, R.
Dragani, M. Fuentes, A. Geer, L. Haimberger, S. Healy, H.
Hersbach, E. Holm, L. Isaksen, P. Kallberg, M. Kohler, M.
Matricardi, A. McNally, B. Monge-Sanz, J. Morcrette, B. Park, C.
Peubey, P. de Rosnay, C. Tavolato, J. Thepaut and F. Vitart, "The
ERA-Interim reanalysis: configuration and performance of the data
assimilation system. Q. J. R. Meteorol. Soc. 137: 553-597.," 2011.
Saudi Electricity Company
Recirculation Studies for Various Power Plant Sites - Duba Power Plant
Recirculation Study Report
SGF11129-RPT-MRN-052-00 62
[Online]. [Accessed May 2014].
[10] U.K.H.O, Admiralty Chart 159. Volume 3 – Indian Ocean and South
China Sea, 2011.
[11] "General Bathymetric Chart of the Oceans web site : Gridded
bathymetry data," 2008. [Online]. [Accessed May 2014].
WSP Middle East Ltd P.O. Box 7497 Dubai United Arab Emirates Tel: +971 4 350 5000 Fax: +971 4 350 5001