Notes After TIG 17/7/08HF+• Move out of garage: Aug 15*• Platform+table+collars+racks+BP support (jack up for platform) = 3 days• Controls for motors = 1 day (overlap with above)• Test closing while on the floor = 1 day• Paint exposed surfaces of HF absorber = 1 day• Install BCM2 = 1 day• Remove HF lead doors = same day as BCM2• Move HF onto 2 raisers: *+6days
HF-• Move out of garage on ~Aug 25** (could be sooner)• Install CASTOR < 1 day (dedicated crane), connect+test < 1 day• (T2 will be installed in garage)• Controls for motors (in the garage)• Test closing while on the floor = 1 day• Remove HF lead doors = 1 day• Put HF onto 2 raisers AS SOON AS POSSIBLE: **+2days
Magnet tests at night• Low current > Aug 15• 1T Aug 26 3.8T Aug 29 1
17/7/2008 W. Klempt 2
Work on HF platform –z end
• Installation work ongoing in garage position We need some 3-4 days of notice to stop and prepare to move out of garage
• Foreseen date of move out of garage:– either 1/8 if no end cap e-cal installation on –z end– or 18/8 with cap e-cal installation on –z end
• Work in “floor position”• Work in height of 2 risers• Work in beam height
17/7/2008 W. Klempt 4
Garage position
• We will continue to work up to HF is moved out of the garage
• Castor:– 1. test of installation tools on 15/7. Some (small) mods on feet's
needed. Next test on Monday 28/7– Cabling will finish by 25/7– Installation of cable chain to be finished by 25/7/2008– 1 Marathon crate to be installed
• BCM– T2 rails need shimming (geometry of table pretty bad) by 21/7– Cabling finished by 25/7
17/7/2008 W. Klempt 5
Garage position (cont’d)
• TOTEM T1– Install rack’s (if possible in garage)– Equip rack’s with marathons
• Totem T2– Install marathon 17/7– Cabling and piping by 25/7– Modify 5 vertical pipes (collision with rotative shielding) 25/7– Install detector (if possible) 2 days
• Services– Connect cooling to racks (latest in week 28/7)– Install Lauda on HF and connect to
Castor, T1 and T2 cooling (31/7)– Equip all detectors with position detectors
17/7/2008 W. Klempt 7
HF close to End cap on the Floor
• We need HF open for the ease of access.• Day 1 : Install T2 (if not yet done) mechanics
• Day 2 : Install Castor mechanics (crane close to beam pipe )
• Day 3 : Cabling of Castor and T2 (in parallel)• BCM needs > 1 day of access (in parallel)• Test of closure procedure??• Install cables and pipes on YE4 for T1 (5 days)
17/7/2008 W. Klempt 9
HF lifted up 2 risers• Table in maintenance position• Collar open • Access to both sides (difficult to cross from near to
far side)• Install PT100 temp probes on beam pipe• T1 installation
– Close HF– Finalize cable and piping on YE4 (if needed)– Install truss (1 day)– Install detector (1 day)– Connect, test and de-connect(1day)– Open HF
• BCM, Castor and T2 need access