Page 1: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Concept Planning Study Northwest LRT (NAIT to NW City Limits)

September 26, 2012

1

Page 2: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Agenda

• Meeting Purpose • LRT Planning: Project Background • Urban Style LRT • Public Involvement: What We Heard • Proposed Draft concept: Stations and

Alignment • Next Steps • Question and Answer

2

Page 3: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

MEETING PURPOSE

3

Page 4: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Meeting Purpose

Our Commitment to You

• To provide you with information about the NW LRT proposed draft concept

• Make you an informed commenter • Listen to your thoughts and comments • Answer questions and clarify information

so you are as informed as possible moving forward to the City Council review

4

Page 5: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Basis for LRT 5

“The City will pursue expansion of the LRT to all sectors of the city with a goal to increase transit ridership and transit mode split, and spur the development of compact, urban communities.”

Page 6: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

LRT Network Assessment 6

Page 7: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Approved Corridor

LRT Corridor approved by City Council - July 2010

7

Page 8: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

NW LRT Project Purpose

• Builds off of policy: – Purpose: Following the

approved corridor, develop a Concept Plan to extend the existing LRT system from NAIT to Campbell Road (future park-and-ride) to serve the developed, redeveloping and new neighbourhoods in the City’s northwest.

8

Page 9: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

NW LRT Facts

• Partner with City of St. Albert • NAIT to northwest City limits • 11 km • Potentially 9 stations • Existing Edmonton style high

floor vehicle (extension of existing line)

• Anticipated travel time from Campbell Road P&R – 30 minutes to downtown – 40 minutes to University

• Urban style design

9

Page 10: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Where We Are Now

• Corridor approved in July 2010

• 2012 Concept Planning Study – Defines location of tracks – Defines stations – Identifies property

requirements – Considers auto access/traffic – Considers cyclists,

pedestrians & bus users – Provides information to begin

preliminary engineering

10

Page 11: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Project Process 11

Page 12: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

URBAN STYLE LRT

12

Page 13: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

City Council - Urban Style

• City Council policy has defined the future size, scale and operation of LRT. – Urban style design for the

existing system and new LRT lines

– NW LRT will be high floor (extension of NAIT)

13

Page 14: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

14

14 14

Page 15: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Urban Style 15

Page 16: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

16

16

Page 17: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

PUBLIC INVOLVEMENT PROCESS: WHAT WE HEARD

17

Page 18: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

CR

Key Themes

Team Meeting: Options

Dev.

Team Meeting: Options

NWLRT

JAN MR APR JUN O

Council Review

DEC

18

• Minimize traffic impacts • Minimize noise impacts • Cost – Edmonton taxpayers – City of St. Albert contribution

• No station required at 121 Street • Preserve and fence dog park • Timing - eagerness to proceed

Page 19: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

CR

Key Considerations

Team Meeting: Options

Dev.

Team Meeting: Options

NWLRT

JAN MR APR JUN O

Council Review

DEC

19

• Station locations – Provide easy access to LRT for residents – Provide easy access for LRT users to reach

destinations – Locate stations where there is available land—

avoid property impacts

• Alignment – Optimize passenger access into LRT stations – Ensure space for pedestrians and cyclists – Preserve trees and landscaping

Page 20: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

CR

Key Concerns

Team Meeting: Options

Dev.

Team Meeting: Options

NWLRT

JAN MR APR JUN O

Council Review

DEC

20

• Through traffic/neighbourhood traffic • Loss of frontage access • Noise (need for sound barriers, landscaping) • Proximity of tracks to housing • Loss of trees and landscaping

Page 21: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

CR

Conflicting Views

Team Meeting: Options

Dev.

Team Meeting: Options

NWLRT

JAN MR APR JUN O

Council Review

DEC

21

• 113 A Street alignment – Conflicting views on option to acquire

properties along east side between 129 and 130 Avenues

– Support for need to minimize impact to traffic

• 153 Avenue alignment – Residents both north and south of roadway

concerned about potential impacts • noise, safety and security, neighbourhood access,

traffic congestion and loss of green space

Page 22: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

PROPOSED DRAFT CONCEPT: STATIONS AND ALIGNMENT

22

Page 23: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Evaluation

Three components impact the decisions about the NW LRT stations and track locations

23

Page 24: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

24

Evaluation – Walk Catchment

Page 25: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

25

CCR South Station

New NAIT Station

New traffic signals to accommodate LRT and

vehicle movements

Increased potential for higher density, Transit-Oriented Development Station position that

provides equal NAIT and CCR town centre

Page 26: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

26

LRT Bridge

New pedestrian and cyclist connection to

downtown

Bridge Over Yellowhead/CN

New traffic signal to accommodate LRT and

traffic movements

Page 27: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

27

Evaluation – 113A Street

Option 1 – 113A Street

Option 2 – 113A Street

Retains local traffic Retains frontage access Increased segregation of LRT Mitigates impact on street trees Improves bicycle and pedestrian accessibility Provides space for shared use path

Impacts property

Option Development Fence and planting proposed along edge of Grand Trunk Park Mixed use path provided in place of property Landscaping proposed 130 Avenue west bound changed to Cul-de-sac

Page 28: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

28

Improved streetscape and landscape opportunities

Retained traffic access

Provided pedestrian crossings

Enhanced Shared use path

connection

New pedestrian and cyclist connection to

downtown

South of 132 Avenue Station

Minimizes impact to park

Page 29: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

29

Evaluation - 132 Avenue

Option 1 – 129 Avenue

Option 2 – Southeast

Option 3 – Northeast

Provide even catchment Good walking and cycle connectivity Connects to buses on 132 Avenue Minimizes property impact Connectivity to schools

Supports surrounding development opportunities

Option Development Traffic arrangement refined 113A Shared use path provided Cycle storage identified Stop moved west from adjacent properties Signalled pedestrian crossing on 113A

Page 30: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

132 Avenue Station 30

Pedestrian crossings

No property impact

No interference from LRT at intersection

Pedestrian and cyclist access and

facilities

Easy bus interchange

Retained traffic access

Increased accessibility for both nearby

schools and activity centres

Potential for Transit-Oriented

Development

Page 31: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

North of 132 Avenue Station 31

No LRT interference at

intersection

Retained on-street parking

Reduced traffic near school

Reduced traffic lanes focused on

local access

Shared use path Tracks located

away from homes

Local traffic connection and parking retained

Page 32: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Evaluation – 137 Avenue 32

Option 1 – Southeast

Option 2 – South centre

Option 3 – Northeast

Transit centre integration required with new Greisbach transit centre

Provides transit integration Minimizes infrastructure Aids reduction of traffic south of 137Ave Option Development Traffic arrangement refined 137 Avenue Shared use path provided Cycle storage identified

Option 4 – North Centre

Option 5 – Northeast

Page 33: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

137 Avenue Station 33

Seamless bus exchange

Removal of slip lanes New traffic signal

Pedestrian crossing

Shared use path connection and cycle facilities

Page 34: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Evaluation – 145 Avenue 34

Option 1 – East side

Option 2 – Centre

Centre running improves 153 Ave/Castle Downs arrangement Provide even catchment Good walking and cycle connectivity Minimizes property impact

Supports surrounding development opportunities

Option Development Dedicated left turns provided Shared use path provided Cycle storage identified Signalled pedestrian crossing on 113A Street

Page 35: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

145 Avenue Station 35

Minimal property impact

Provide pedestrian crossing

Shared use path connection and cycle facilities

New traffic signal intersection

Station provides equal access to

residents

Page 36: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Evaluation - Castle Downs 36

Option 1 – Northwest

Option 2 – North Centre

Provides transit integration Minimizes infrastructure Provides connectivity to park and YMCA Provide even catchment Good walking and cycle connectivity Replaces existing transit centre

Option Development Traffic arrangement refined Right slip lanes removed (improved pedestrian environment) Shared use path provided Cycle storage identified Signalled pedestrian crossing at entrances to YMCA

Option 3 – 113A Street

Page 37: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Castle Downs Station

37

Improved streetscape and

landscape opportunities

Retained traffic lanes at

intersection

Retained access

Seamless bus exchange

Supports development in

area & connects to activity centres

Provide pedestrian crossing

Shared use path connection and cycle facilities

Removal of slip lanes

Page 38: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

121 Street Station

38

Retained pedestrian crossing

Signal controlled intersection

Page 39: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Option 1 – East Centre

Provides transit integration at 127 Avenue Provide even catchment Good walking and cycle connectivity Connectivity to local housing and commercial development

Option Development Traffic arrangement refined Right slip lanes removed (improved pedestrian environment) Shared use path provided Cycle storage identified

Evaluation – 127 Street

Page 40: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

127 Street Station 40

No property impacts

Opportunity for bus

interchange

Signaled Intersection

Station provides connectivity to

community

Landscape Opportunities

Pedestrian and cyclist access to

transit Connection to activity centres

Link to existing Multi Use Trail

Retained traffic lanes

Retained access

Page 41: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Option 1 – Southwest

Provides transit integration at 137 and 139 Avenue Provide even catchment Good walking and cycle connectivity Connectivity to communities to the south and north

Option Development Sidewalk arrangement optimized Cycle storage identified

Evaluation – 137 Street

Page 42: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

137 Street Station 42

Opportunity for bus interchange

Pedestrian & cyclist access to transit

Station position provides equal access

to community

Existing Multi Use Trail

New traffic signals New traffic signal

No property impacts

Page 43: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

West of 137 Street Station

43

New pedestrian and cycle link across CN Rail tracks

Traffic signaled intersection

Page 44: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

West of 137 Street Station 44

Page 45: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Option 1 – Southwest

Provides transit integration with St. Albert

Option Development St. Albert concept layout included in design

Evaluation – Campbell Road

Page 46: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Park and Ride Terminus 46

Bus and park and ride interchange New traffic signal

Page 47: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

NEXT STEPS

47

Page 48: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

Next Steps

• Incorporate any final comments into recommended concept, if possible • Present recommended concept to you – Fall 2012 • Present recommended concept plan to Transportation Infrastructure Committee

Page 49: Northwest LRT Concept Planning Study PresentationNorthwest LRT Concept Planning Study Presentation Author Transportation Planning Subject Northwest LRT Concept Planning Study Presentation

www.edmonton.ca/lrtprojects

QUESTIONS?