NORTHAMPTON NORTH-WEST RELIEF ROAD · 1.3 scope of report 2 1.4 biodiversity net gain policy 2 2...
Transcript of NORTHAMPTON NORTH-WEST RELIEF ROAD · 1.3 scope of report 2 1.4 biodiversity net gain policy 2 2...
BNG MAY 2019 CONFIDENTIAL
Northampton County Council
NORTHAMPTON NORTH-WEST
RELIEF ROAD
Biodiversity Net Gain Assessment
Northampton County Council
NORTHAMPTON NORTH-WEST RELIEF ROAD
Biodiversity Net Gain Assessment
CONFIDENTIAL
TECHNICAL APPENDIX (V1) CONFIDENTIAL
PROJECT NO. 70045931
OUR REF. NO. BNG
DATE: MAY 2019
WSP
Kings Orchard
1 Queen Street
Bristol
BS2 0HQ
Phone: +44 117 930 6200
WSP.com
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
QUALITY CONTROL
Issue/revision First issue Revision 1 Revision 2 Revision 3
Remarks First Issue
Date 30/05/2019
Prepared by Laura Homfray
Signature
Checked by Sarah Scott
Signature
Authorised by Jenny Merriman
Signature
Project number 70045931
Report number BNG
File reference
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
CONTENTS
1 INTRODUCTION 1
1.1 BIODIVERSITY NET GAIN 1
1.2 PROJECT BACKGROUND 1
1.3 SCOPE OF REPORT 2
1.4 BIODIVERSITY NET GAIN POLICY 2
2 METHODOLOGY 4
2.1 OVERVIEW 4
2.2 BASELINE BIODIVERSITY UNIT CALCULATION 5
2.3 POST-DEVELOPMENT BIODIVERSITY UNIT CALCULATION 7
2.4 TEMPORAL RISK 9
2.5 CALCULATING THE CHANGE IN BIODIVERSITY UNITS AS A CONSEQUENCE OF THE
PROPOSED SCHEME 10
3 ASSUMPTIONS AND LIMITATIONS 12
3.1 BASELINE BIODIVERSITY AND LINEAR UNIT CALCULATION 12
3.2 POST-DEVELOPMENT BIODIVERSITY AND LINEAR UNIT CALCULATION 12
3.3 LIMITATIONS 13
4 RESULTS OF BASELINE BIODIVERSITY AND LINEAR UNIT
CALCULATIONS 14
4.1 OVERVIEW 14
4.2 AREA-BASED HABITATS 14
4.3 IRREPLACEABLE HABITATS 15
4.4 LINEAR HABITATS 16
5 RESULTS OF THE POST DEVELOPMENT BIODIVERSITY AND LINEAR
UNIT CALCULATIONS 17
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
6 SUMMARY OF RESULTS AND RECOMMENDATIONS 22
6.1 SUMMARY OF RESULTS 22
6.2 RECOMMENDATIONS 22
7 REFERENCES 24
TABLES
Table 2-1 – Habitat distinctiveness bands and scores 6
Table 2-2 – Habitat condition bands and scores 7
Table 2-3 – Defra spatial risk factor 8
Table 2-4 - Defra delivery risk factors 9
Table 2-5 – Delivery risk of created habitats 9
Table 2-6 - Temporal risk factors 10
Table 2-7 - Temporal risk for created habitats 10
Table 4-1 - Baseline BU of the Proposed Scheme: habitat lost 14
Table 4-2 - Baseline BU of the Proposed Scheme: habitat retained 15
Table 4-3 – Baseline hedgerow LU lost 16
Table 4-4 – Baseline hedgerow LU retained 16
Table 4-5 – Baseline watercourse LU lost 16
Table 4-6 – Baseline watercourse LU retained 16
Table 5-1 – Post-development – retained habitats 17
Table 5-2 – Post-development – created habitats 18
Table 5-3 – BU results summary 19
Table 5-4 – Hedgerow LU created post-development 19
Table 5-5 –Hedgerow LU retained from baseline 19
Table 5-6 – Hedgerow LU results summary 20
Table 5-7 – Watercourse LU created post-development 20
Table 5-8 –Watercourse LU retained from baseline 20
Table 5-9 – Watercourse LU results summary 21
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
Table 6-1 – Summary of results 22
APPENDICES
CIEEM, CIRIA AND IEMA UK BIODIVERSITY NET GAIN GOOD PRACTICE
PRINCIPLES FOR DEVELOPMENT
WSP BIODIVERSITY NET GAIN PROCESS
PHASE 1 MAPS:BASELINE AND POST-DEVELOPMENT
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
EXECUTIVE SUMMARY
Biodiversity Net Gain (BNG) is a quantitative, stepwise process which is applied to development and
results in an overall net gain in biodiversity after development. The principle behind it is that any
impacts from development to biodiversity need to be accounted for and compensated with equivalent
and additional gains. Applying the biodiversity net gain process to a development project provides
clear, quantifiable outcomes for biodiversity which are backed up by a robust evidence base.
WSP UK Ltd (‘WSP’) was commissioned in April 2018 to carry out ecology surveys, in support of the
planning application for a proposed relief road to the north-west of the town of Northampton, known
as the Northampton North-West Relief Road (NNWRR). This will involve the construction of a new
single carriageway that will connect the A5199 Welford Road to a proposed junction adjacent to
Dallington Grange Farm, hereafter referred to as the ‘Proposed Scheme’.
The Proposed Scheme has adopted the Defra metric to calculate baseline and preliminary post-
development biodiversity units (BU) and linear units (LU), to quantify biodiversity lost to the Proposed
Scheme and to provide an indication of the biodiversity which will be replaced through onsite
compensation. This information will be used to indicate whether the Proposed Scheme is likely to
meet no net loss or net gain for biodiversity.
This report aims to:
Establish the total number of baseline BU and LU at the Site of the Proposed Scheme;
Establish the total number of BU and LU which will be created, retained and/or enhanced under
landscape and ecological mitigation proposals at the Site of the Proposed Scheme; and
Determine whether the Proposed Scheme will result in a net loss, no net loss or a net gain for
biodiversity.
Results
The Proposed Scheme design will result in a net gain for biodiversity for area-based habitats (an
increase of 31.78 BU which equates to 34% net gain), a net loss for linear hedgerow habitats (a
decrease of 1337 LU which equates to a 46% net loss) and a net gain of linear watercourse habitats
(an increase of 1838m which equates to a 353% net gain). The results of the BNG assessment are
summarised in the table below.
Although there is a significant biodiversity net gain of BU and watercourse LU, the Proposed
Scheme cannot claim that it will deliver a net gain in biodiversity within the site boundary due
to the loss of Hedgerow LU.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
Area
(Hectares) BU
Hedgerow Length (m)
Hedgerow LU
Length (m) or Watercourse
LU
TOTAL AREA-BASED HABITAT OR LINEAR
FEATURE AT BASELINE
41.10 93.82 1060 2900 520
TOTAL AREA-BASED HABITAT OR LINEAR
FEATURE POST-DEVELOPMENT
41.16 125.60 1543 1563 2358
OUTCOME NET GAIN OF 34%
(+31.78 BU)
NET GAIN OF 46% (+483m)
NET LOSS OF 46%
(1337 LU)
NET GAIN OF 353% (+1838m)
Although there is a net increase in length of hedgerows of approximately 483m, there is an overall
loss of 1337 LU. Using the current metric it is difficult to deliver significant gains for even relatively
limited loss of linear units, without providing considerably more habitat (by length) than is lost. This is
because the current hedgerow metric does not have any weighting for habitat condition when hedges
are created post-development and the condition assessment for hedgerows does not account for
different levels of species richness. The metric for linear units is currently under review by Natural
England.
Due to the limitations of the current metric, enhancements of linear habitats that have been proposed
as part of the Proposed Scheme are not captured. Biodiversity enhancement of hedgerows as part of
the Proposed Scheme include increasing the species-richness of existing hedgerows and providing
species-rich hedgerow to replace species-poor hedgerow.
It is important to recognise that the quantification of biodiversity units is one of a number of factors to
be considered when assessing the impact of each stage on biodiversity.
WSP recommends the following next steps for the BNG assessment of NNWRR:
The BNG assessment is re-run once the temporary works layout information is available to ensure
that any impacts resulting from the construction of the Proposed Scheme are captured and
quantified.
The BNG assessment is re-run based on the final landscape plan for the Proposed Scheme.
To avoid re-running the BNG calculations multiple times, the calculations should be re-run once
when the final landscape plan and temporary works layout information is available.
The client should continue to explore any other options to avoid impacts to and create more
hedgerow habitats.
Contact name Laura Homfray
Contact details +44 1179 306195 | [email protected]
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 1 of 25
1 INTRODUCTION
1.1 BIODIVERSITY NET GAIN
1.1.1 Biodiversity net gain (BNG) is the end result of a process applied to infrastructure development so
that overall, there is a positive outcome for biodiversity. The process itself follows the mitigation
hierarchy, which sets out that everything possible must be done to first avoid and then minimise and
restore / rehabilitate losses of biodiversity on site. Only as a last resort, residual losses are
compensated for using biodiversity offsets, which are distinguished from other forms of mitigation in
that they are off the development site and require measurable conservation outcomes.
1.1.2 Adopting a BNG approach can account for biodiversity losses not fully covered by legal and planning
systems. Whilst some species are extensively protected, many are not; with the consequence that
development can be ‘legally compliant’ but still result in biodiversity loss. The BNG approach guards
against this, enabling development to contribute towards the national and global target of halting
biodiversity loss by 2020 and towards local and national strategies for conserving and enhancing
wildlife.
1.1.3 For BNG to be used appropriately and to generate long-term gains for nature, the good practice
principles established by the Business and Biodiversity Offset Programme (BBOP) can be used.
These principles have been established in the context of UK development by the Construction Industry
Research and Information Association (CIRIA), the Chartered Institute for Ecology and Environmental
Management (CIEEM) and the Institute of Environmental Management and Assessment (IEMA) (see
Appendix A). The BNG process for the Northampton North-West Relief Road (NNWRR) assessment
adheres to these principles.
1.2 PROJECT BACKGROUND
1.2.1 WSP UK Ltd (‘WSP’) was commissioned in April 2018 to carry out ecology surveys, in support of the
planning application for a proposed relief road to the north-west of the town of Northampton, known
as the Northampton North-West Relief Road (NNWRR). This will involve the construction of a new
single carriageway that will connect the A5199 Welford Road to a proposed junction adjacent to
Dallington Grange Farm, hereafter referred to as the ‘Proposed Scheme’.
1.2.2 The Proposed Scheme comprises an approximately 1.6km single two-lane carriageway (Route Option
‘11’) connecting two proposed junctions, the Dallington Grange Roundabout (in the south) and the
Sandy Lane Roundabout (in the north). Furthermore, the development will include the construction of
a new bridge crossing the River Nene that will connect the Sandy Lane Roundabout to a third
proposed junction, the Brampton Lane Roundabout.
1.2.3 The Proposed Scheme will also encompass approximately 30ha of surrounding land required to
facilitate construction and is hereafter referred to as the ‘Site’. This area will include construction work
areas, borrow pits, and flood mitigation, as well a shared cycle/footway along the west of the proposed
road and flood and drainage provisions.
1.2.4 It is understood the planning application for the Proposed Development will be submitted in June 2019.
1.2.5 The Proposed Scheme has adopted the Defra metric 2012 to undertake baseline and preliminary
post-development biodiversity unit (BU) and linear unit (LU) calculations to quantify the biodiversity
which will be lost to the Proposed Scheme and provide an indication of the biodiversity which will be
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 2 of 25
replaced through onsite compensation once the Proposed Scheme has been built. This information
will be used to indicate whether the Proposed Scheme is likely to meet no net loss or net gain for
biodiversity.
1.2.6 The Defra metric will be used to assess the biodiversity impacts and opportunities of the Proposed
Scheme. This assessment will inform avoidance, mitigation and compensation measures designed to
mitigate for habitat loss due to the Proposed Scheme. This includes informing habitat restoration and
reinstatement proposals as well as new habitat creation. The Defra metric is also required to evaluate
progress towards achievement of the target of net gain or no net loss. This information will provide a
quantitative benchmark to inform the size and type of habitat compensation requirements as a result
of habitat lost to the Proposed Scheme
1.3 SCOPE OF REPORT
1.3.1 This report aims to:
Establish the total number of baseline BU and LU at the Site of the Proposed Scheme;
Establish the total number of BU and LU which will be created, retained and/or enhanced under
landscape and ecological mitigation proposals at the Site of the Proposed Scheme; and
Determine whether the Proposed Scheme will result in a net loss, no net loss or a net gain for
biodiversity.
1.3.2 Please note that the BNG report does not cover requirements of the Proposed Scheme arising from
potential impacts on protected species and designated sites. This information will be covered within
the ecology chapter of the Environmental Statement (ES) for the Proposed Scheme.
1.4 BIODIVERSITY NET GAIN POLICY
1.4.1 The appraisal has been compiled with reference to the following relevant nature conservation
legislation, planning policy and the UK Biodiversity Framework from which the protection of sites,
habitats and species is derived in England.
The Natural Environment and Rural Communities (NERC) Act 2006;
The UK Post-2010 Biodiversity Framework (2011-2020) (JNCC and DEFRA, 2012);
Biodiversity 2020: A strategy for England’s wildlife and ecosystem services (DEFRA, 2011);
UK Biodiversity Action Plan (UKBAP)1;
The National Planning Policy Framework (NPPF) 2019 (DCLG, 2012);
NATIONAL PLANNING POLICY FRAMEWORK
1.4.2 Although not currently a legal obligation, the revised National Planning Policy Framework (NPPF)
(2019) refers to biodiversity and environmental net gains in the following paragraphs:
Transport Infrastructure
1 The UK BAP has now been replaced by the UK Post-2010 Biodiversity Framework, however, it contains useful
information on how to characterise important species assemblages and habitats which is still relevant.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 3 of 25
• Paragraph 102. “Transport issues should be considered from the earliest stages of plan-making
and development proposals, so that:
d) the environmental impacts of traffic and transport infrastructure can be identified assessed
and taken into account – including appropriate opportunities for avoiding and mitigating any
adverse effects, and for net environmental gains.”
Planning decisions
• Paragraph 118 “Planning decisions and planning policy should a) encourage multiple benefits
from both urban and rural land … and taking opportunities to achieve net environmental gains
- such as developments that would enable new habitat creation.”
• Paragraph 170 “Planning policies and decisions should contribute to and enhance the natural
and local environment by: … d) minimising impacts on and providing net gains for biodiversity”
• Paragraph 174 “To protect and enhance biodiversity and geodiversity plans should b) ... identify
and pursue opportunities for securing measurable net gains for biodiversity.”
• Paragraph 175 “When determining planning applications, local planning authorities should apply
the following principles: d) … opportunities to incorporate biodiversity improvements in and
around developments, especially where this can secure measurable net gains for
biodiversity.”
LOCAL POLICY
1.4.3 Northamptonshire County Council has the following target within the Northamptonshire Biodiversity
Action plan (BAP) 2015-2020 (p38) “Ensure that all relevant new developments lead to a net gain in
biodiversity through on or off site mitigation with consideration of BAP targets”.
1.4.4 The Northamptonshire BAP 2015-2020 states that “The BAP should guide the planning decision
process to ensure priority habitats and species are conserved, and that development leads to a net
gain in biodiversity in accordance with the National Planning Policy Framework”.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 4 of 25
2 METHODOLOGY
2.1 OVERVIEW
2.1.1 The method applied followed the six steps of WSP’s BNG process (see Appendix B for the full six step
process). The work set out in this report is covered by step two. The relevant sections of step two are
provided below:
STEP 2 INITIAL BIODIVERSITY ASSESSMENT
i. Survey baseline habitats and their condition. Ideally, a habitat condition assessment is
undertaken during Phase 1 Habitat survey. If Phase 1 Habitat data has been collected prior to
initiating the BNG process, condition assessment can be undertaken either:
a. Retrospectively through interpretation of Phase 1 target notes, consultation with
surveyors, or employing a number of assumptions; or
b. During an additional site visit.
ii. Identify irreplaceable habitat. Following Defra guidance, irreplaceable habitats within the
Proposed Scheme boundary must be identified and excluded from the biodiversity unit
calculations.
iii. Calculate baseline biodiversity units using the biodiversity metric. This calculation
includes all habitats (minus irreplaceable habitats) within the Proposed Scheme boundary prior
to development and is informed by Phase 1 Habitat data and results of the condition
assessment. The baseline biodiversity unit calculation may be run on a number of scheme
options if the scheme is at options appraisal stage.
iv. Calculate post-development biodiversity units using the biodiversity metric. This
calculation accounts for all of the proposed habitats (including retained habitats and habitats
lost or created as a result of the development) within the Proposed Scheme boundary post-
development. The calculation excludes irreplaceable habitats. The calculation is informed by
scheme design, landscape plans, and proposed ecological mitigation. The assessment is
based upon the target state (type, size and condition) of habitats being created.
v. Produce an ‘Initial Biodiversity Assessment’ report. The report sets out the BNG process
in the context of the Proposed Scheme and includes the method and results of initial baseline
and post-development biodiversity unit calculations.
IRREPLACEABLE HABITATS
2.1.2 Following Defra guidance, irreplaceable habitats have been excluded from this biodiversity unit
calculation. It is important to note that BNG or no net loss cannot be achieved for the scheme as a
whole if there is a negative impact on an irreplaceable habitat.
LINEAR HABITATS
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 5 of 25
2.1.3 Defra recognise that hedgerows are a very important feature in terms of biodiversity value: ‘‘Their
contribution, by area, to biodiversity in the landscape is far greater than even the most biodiversity
rich habitats’’ (Defra, 2012a). Hedgerows and watercourses therefore cannot be treated as other area-
based habitats and are considered in terms of LU rather than BU; both are arbitrary units which are
not directly comparable with each other.
2.2 BASELINE BIODIVERSITY UNIT CALCULATION
EXTENT AND SOURCES OF BASELINE HABITAT DATA
2.2.1 Identification of baseline habitats was based on a digitised Phase 1 Habitat layer (WSP, 2019). The
BNG calculation covered all habitats (linear and non-linear) within the Scheme footprint (for a map of
the Proposed Scheme extent and Phase 1 Habitat survey data please see Appendix C of this report).
The following Phase 1 Habitat typologies present within the Scheme footprint which, in the context of
BNG, are not considered ‘habitats’ were excluded:
→ Fence; and
→ Hardstanding/buildings.
2.2.2 Although these habitat typologies do not generate BU, they have been included within the tables
presented in subsequent sections to understand the area in hectares that they occupy relative to the
Proposed Scheme as a whole.
2.2.3 Rivers, streams and dry ditches are included in the BNG assessment as linear features. For the
baseline and post-development biodiversity unit calculation, running water or ditches are expressed
simply as a length in metres.
2.2.4 For area-based habitats, hectares are reported to two decimal places. However, for linear habitats,
length is reported to the nearest metre. The reason for this is that 0.01 of a linear unit is equivalent to
reporting to 1cm. This level of detail is superfluous for the purposes of a preliminary BNG assessment.
2.2.5 The Phase 1 Habitat survey was undertaken following Joint Nature Conservation Committee (JNCC,
2010) survey methodology, and are reported in full within the NNWRR Preliminary Ecological
Assessment report.
DEFRA BIODIVERSITY UNIT CALCULATION
2.2.6 A baseline biodiversity unit calculation was completed for all areas of permanent and temporary land
take within the operational footprint of the Scheme. Habitat area or length, distinctiveness and
condition were used to calculate baseline BU and LU, providing a measure of the biodiversity on site
before development. This calculation is in accordance with Defra’s technical paper, guidance for
developers and guidance for offset providers (Defra 2012 a, b and c). This is the standard metric
used for calculating BU and LU in the UK.
2.2.7 Distinctiveness and condition are given numerical ‘scores’ which are multiplied, together with hectares
(ha) or length in metres (m) of habitat to give the number of baseline BU or LU:
Distinctiveness x Condition x Area (ha) = BASELINE BIODIVERSITY UNITS
Length (m) x Condition = BASELINE LINEAR UNITS
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 6 of 25
DISTINCTIVENESS
2.2.8 Habitat distinctiveness is defined as a collective measure of biodiversity and includes parameters such
as the number and variety of species found within the habitat (richness and diversity), how rare the
species are, and how many species the habitat supports that are not common elsewhere.
2.2.9 To determine habitat distinctiveness, Phase 1 Habitat types were transposed into the standard habitat
distinctiveness typology and bands issued by Defra (‘the Defra habitat type’). For some habitat types,
multiple distinctiveness bands can apply, depending on the quality of the habitat. Decisions on which
distinctiveness band to assign were based on criteria listed in Appendix C of the Building Research
Establishment’s (BRE) Guidance Note 36: BREEAM, CEEQUAL and HQM Ecology Calculation
Methodology – Route 2.
2.2.10 Appendix C of the BRE Guidance Note 36 spreadsheet contains information which can be used to
match each Phase 1 Habitat type to a Defra habitat type, enabling consistent assessment of
distinctiveness for all habitat parcels
2.2.11 The Defra distinctiveness bands and associated scores are described in Table 2.1.
Table 2-1 – Habitat distinctiveness bands and scores
DISTINCTIVENESS BAND
DISTINCTIVENESS SCORE
HABITAT TYPES INCLUDED
High 6
Habitats of principle importance or habitats which meet the criteria to qualify as habitats of principle importance (JNCC, 2011). This excludes ancient woodland and other habitats
which are irreplaceable.
Medium 4
Other semi-natural habitats that do not fall within the scope of habitats of principle importance definitions, i.e. all other areas
of woodland (e.g. non-native coniferous plantation), other grassland (e.g. species poor semi-improved), uncultivated
field margins, road verge and railway embankments (excluding those that are intensively managed).
Low 2
Improved grassland, arable fields (excluding any uncultivated margins), built up areas, domestic gardens, regularly disturbed
bare ground (e.g. quarry floor, landfill sites etc.), verges associated with transport corridors.
2.2.12 For some habitat types, multiple distinctiveness bands can apply, depending on the quality of the
habitat. Decisions on which distinctiveness band to assign were based on criteria listed in Appendix
C of the BRE Guidance Note 36.
2.2.13 All hedgerows are assumed to be of High distinctiveness because the vast majority of hedgerows will
meet Habitat of Principle Importance (HPI) criteria. For this reason, distinctiveness is not included as
part of the linear unit calculation. This follows the approach set out by Defra.
CONDITION
2.2.14 Condition, in the context of BNG, is defined as the quality of a particular habitat. For example, a
habitat is in poor condition if it fails to support the rare or notable species for which it is valued, or if it
is degraded as a result of pollution, erosion, invasive species or other factors.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 7 of 25
2.2.15 The Defra metric requires habitat condition to be assessed using the system presented in Natural
England's Farm Environment Plan (FEP) manual.
2.2.16 Habitat condition scores were assigned based on the criteria in Table 2.2.
Table 2-2 – Habitat condition bands and scores
CONDITION BAND CONDITION SCORE CRITERIA FOR
ASSIGNING CONDITION
Good 3 Any habitat which passes
all the FEP criteria.
Moderate 2 Any habitat which fails
one FEP criterion.
Poor 1 Any habitat which fails
two or more FEP criteria.
2.2.17 As primary habitat condition assessment data was not available, habitat condition was assigned
through interviews with the Phase 1 surveyor who undertook a retrospective condition assessment of
the site.
DERIVING THE TOTAL NUMBER OF BASELINE BIODIVERSITY UNITS
2.2.18 Following the scoring of all habitat parcels for habitat distinctiveness and condition, the total number
of baseline BU will be calculated for each area-based habitat (including those assumed for arable field
margins).
2.2.19 The scores generated by each individual habitat parcel will then be summed to provide the total
number of BU generated by the baseline habitat parcels. It is important to set out the BU for the
individual habitats so that these can be compared with the post-development BU for the same habitat
type.
2.2.20 The number of baseline LU present should be calculated for linear habitats (keeping hedgerows and
watercourses separate).
2.3 POST-DEVELOPMENT BIODIVERSITY UNIT CALCULATION
2.3.1 BU and LU resulting from landscape and ecological mitigation designs for the scheme, including newly
created and retained habitats, are referred to as post-development BU / LU.
LINEAR HABITATS
2.3.2 In the post-development unit calculation, linear habitats have been kept separate from units calculated
for area-based habitats; this mirrors the approach for baseline unit calculations. The risk factors
described below are only applicable to the area-based habitat calculation. They are not included in
the calculation for linear habitats. This is because the risks associated with creating linear features
are considered to be taken into account within the condition multiplier used to calculate the baseline
LU.
2.3.3 The post-development LU from the hedgerows and watercourses created are expressed simply as a
length in metres.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 8 of 25
Length (m) = POST-DEVELOPMENT LINEAR UNITS
APPLYING RISK FACTORS TO THE POST-DEVELOPMENT CALCULATION
2.3.4 Post-development BU are calculated in a similar way to baseline BU. However, in addition to area,
condition and distinctiveness of the proposed habitats, the key risks to delivery are taken into account
through incorporation of risk factors. The Defra metric sets out three risk factors: distance from scheme
(spatial risk); time taken for created or enhanced habitats to reach target condition (temporal risk);
and how difficult it is to create or enhance any given habitat (delivery risk).
SPATIAL RISK
2.3.5 The spatial risk is the risk associated with delivering compensation for the loss of a habitat at a
distance from that loss. The further from the site of the loss, the greater the risk. Spatial risk has not
been included in the preliminary post-development calculation as it is assumed that habitat
compensation and retention will be delivered within the Proposed Scheme’s footprint or within the
same ecological network as the loss occurs.
Table 2-3 – Defra spatial risk factor
LOCATION OF HABITAT CREATION OR ENHANCEMENT
RISK FACTOR
Habitat being created or enhanced is within 500m of the area of loss or in the same ecological network identified in a local (county or equivalent) biodiversity, green infrastructure or offsetting strategy.
1
Habitat type being created or enhanced contributes to and is in a location identified within a local (county or equivalent) biodiversity, green infrastructure or offsetting strategy.
0.67
Habitat being created or enhanced is not making a contribution to local (county or equivalent) biodiversity, green infrastructure or offsetting strategy.
0.50
DELIVERY RISK
2.3.6 Delivery risk is the risk associated with the difficulty to create or restore any specific habitat. Appendix
1 of Defra’s Technical Paper (2012a) provides an indicative guide to broad categories of risk for
different habitats. For habitat types not listed in Defra’s guidance, Appendix C of the BRE Guidance
Note 36 was used to determine the appropriate level of delivery risk. This was informed by delivery
risk levels assigned to similar habitat types by Defra. Tables 2.4 and 2.5 show risk factors assigned
to each level of delivery risk and type of habitat on this scheme.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 9 of 25
Table 2-4 - Defra delivery risk factors
DIFFICULTY OF RECREATION OR RESTORATION
DELIVERY RISK FACTOR
Very High 0.10
High 0.33
Medium 0.67
Low 1.00
Table 2-5 – Delivery risk of created habitats
JNCC HABITAT TYPE DIFFICULTY OF RECREATION
DELIVERY RISK FACTOR
A1.1.1 Broadleaved woodland – semi-natural Medium 0.67
A1.1.2 Broadleaved woodland – plantation Low 1
B2.2 Neutral grassland – semi-improved Low 1
B5 Marsh/marshy grassland Medium 0.67
F2.1 Marginal vegetation Low 1
G1 Standing water Medium 0.67
J1.2 Cultivated/disturbed land – amenity grassland Low 1
J4 Bare ground Low 1
2.4 TEMPORAL RISK
2.4.1 In delivering compensation for loss of habitats, the timing of impact may not coincide with the new
habitat reaching the required quality or level of maturity which could result in loss of biodiversity for a
period of time. This risk is accounted for by applying a ‘temporal risk’ multiplier to the biodiversity unit
calculations.
2.4.2 Defra has no set guidance on the time taken to reach a specific condition for each habitat type.
Therefore, this information was taken from Appendix C of the BRE Guidance Note 36 as outlined in
Tables 2.6 and 2.7.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 10 of 25
Table 2-6 - Temporal risk factors
Table 2-7 - Temporal risk for created habitats
HABITAT TYPE YEARS TO TARGET
CONDITION
TEMPORAL RISK FACTOR
A1.1.1 Broadleaved woodland – semi-natural 32+ 0.33
A1.1.2 Broadleaved woodland – plantation 20 0.71
B2.2 Neutral grassland – semi-improved 10 0.71
B5 Marsh/marshy grassland 5 0.83
F2.1 Marginal vegetation 2 0.93
G1 Standing water 0 1
J1.2 Cultivated/disturbed land – amenity grassland 2 0.93
J4 Bare ground 0 1
2.5 CALCULATING THE CHANGE IN BIODIVERSITY UNITS AS A
CONSEQUENCE OF THE PROPOSED SCHEME
2.5.1 The following formula is used to calculate the change in BU as a consequence of the Proposed
Scheme:
POST-DEVELOPMENT BIODIVERSITY UNITS – BASELINE BIODIVERSITY UNITS = CHANGE
IN BIODIVERSITY UNITS
2.5.2 If this resulting score is negative there is a net loss in biodiversity for area-based habitats. If the score
is close to zero (with the post-development units being within 95%-104% of the baseline units) there
YEARS TO TARGET CONDITION
TEMPORAL RISK FACTOR
Under 1 year 1
1 0.97
2 0.93
3-5 0.83
6-10 0.71
11-15 0.59
16-20 0.50
21-25 0.42
26-30 0.35
32+ 0.33
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 11 of 25
is no net loss of biodiversity for area-based habitats. If there is an increase in the BU of 5% or more
the project is capable of delivering net gain for biodiversity for area-based habitats. The percentage
should be rounded to the nearest whole percentage point.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 12 of 25
3 ASSUMPTIONS AND LIMITATIONS
3.1 BASELINE BIODIVERSITY AND LINEAR UNIT CALCULATION
3.1.1 The following assumptions were made for the baseline biodiversity unit and linear unit calculations.
DISTINCTIVENESS
All G1 Standing water is assumed to be of High distinctiveness, in line with Appendix C of the BRE
guidance.
All hedgerows are assumed to be of High distinctiveness because the vast majority of hedgerows
will meet the Habitat of Principal Importance criteria. For this reason, distinctiveness is not included
as part of the linear unit calculation. This follows the approach set out by Defra.
CONDITION
3.1.2 Where no primary condition information was available, the following assumptions were made:
All hedgerows with the exception defunct hedgerows were assigned a condition rating of Good.
Defunct hedgerows were assigned a condition rating of Moderate because by nature of being
defunct will fail one criterion of the FEP condition assessment.
3.2 POST-DEVELOPMENT BIODIVERSITY AND LINEAR UNIT CALCULATION
3.2.1 The following assumptions were made for the post-development biodiversity unit and linear unit
calculations.
STANDING WATER
All G1 Standing water is assumed to be of Medium distinctiveness, this is a deviation from Appendix
C of the BRE guidance because not all G1 Standing water will be created for the purpose of ecological
mitigation and therefore may not be a High distinctiveness habitat.
TARGET CONDITION
It is assumed that Low distinctiveness habitats will reach Poor condition.
Target conditions for Medium and High distinctiveness habitat types have been assigned using
expert judgment and knowledge of the Proposed Scheme.
• It is assumed that created A1.1.1 Broadleaved semi-natural woodland and F2.1 Marginal
vegetation will reach Moderate condition.
• It is assumed that created G1 Standing water is a drainage feature for the Proposed Scheme.
The drainage will not be designed for the purpose of ecological mitigation. Therefore, it is
assumed that the created G1 Standing water will reach Moderate condition.
• It is assumed that created A1.1.2 Broadleaved woodland – plantation and B2.2 Neutral
grassland – semi-improved will reach Good condition.
BARE GROUND
An area of 12.54 hectares of habitat has been categorised as J4 Bare ground post-development. This
is because it is currently unknown what will happen to this habitat area because it falls within the
boundary of another proposed development as well as the footprint of the Proposed Scheme. It is
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 13 of 25
likely that the area will be cleared for construction or creation of new habitat. Although other areas of
J4 Bare ground are assigned units in the baseline, this area is not assigned any post-development
units. The reason for this decision is that undisturbed J4 Bare ground has some biodiversity value, but
it is likely that this habitat will be disturbed due to construction and will therefore not be a suitable
habitat.
TEMPORARY CONSTRUCTION IMPACTS
There are currently no temporary compound locations or site plans for the construction areas. It is
assumed, as a precautionary approach, that any area of habitat which is proposed within the
landscape plan is cleared during construction and then created from scratch. Therefore, all proposed
post-development habitats which are not retained are created from scratch rather than enhanced.
SPATIAL RISK FACTOR
It is assumed that habitat compensation, enhancement or retention will be delivered within the
Proposed Scheme’s footprint or within the same ecological network as the loss occurs. Therefore, the
spatial risk factor is not included within the post-development biodiversity unit calculations.
3.3 LIMITATIONS
3.3.1 The BU and LU calculations do not account for indirect impacts that may happen to habitats outside
of the Proposed Scheme footprint. Given all required construction compounds and accesses are
included in the Proposed Scheme, this limitation is unlikely to have any effect on the BNG calculations.
3.3.2 The baseline BNG calculations are based on the Phase 1 Habitat survey data whereas the post-
development BNG calculations are based upon the detailed landscape plan. Therefore, it is possible
that minor discrepancies exist between the areas of retained habitat post-development and the
baseline habitats. Any discrepancies will not change the overall outcome of the BNG assessment.
3.3.3 The post-development habitat map was drawn up from the CAD plan into GIS and as a result there is
a minor discrepancy of 0.06 hectares between the area of the baseline and post-development footprint
of the Proposed Scheme.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 14 of 25
4 RESULTS OF BASELINE BIODIVERSITY AND LINEAR UNIT
CALCULATIONS
4.1 OVERVIEW
4.1.1 Tables 4.1, 4.2 and 4.3 show the baseline habitat types and the number of BU and LU attributed to
existing habitats within the Proposed Scheme footprint. For a Phase 1 map of the Proposed Scheme’s
baseline habitats, please refer to Appendix C.
4.2 AREA-BASED HABITATS
Table 4-1 - Baseline BU of the Proposed Scheme: habitat lost
JNCC HABITAT TYPE DISTINCTIVENESS
SCORE CONDITION
SCORE AREA (HA
to 0.01) BU
A1.1.1 Broadleaved woodland – semi-natural
High (6) Poor (1) 0.01 0.06
A1.1.2 Broadleaved woodland – plantation
Medium (4) Poor (1) 0.02 0.08
A2.1 Dense scrub Medium (4) Poor (1) 0.37 1.48
A2.2 Scattered scrub Medium (4) Poor (1) 0.03 0.12
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Good (3) 0.21 2.52
A3.3 Mixed parkland/ scattered trees
Medium (4) Good (3) 0.04 0.48
A3.3 Mixed parkland/ scattered trees
Medium (4) Moderate (2) 0.04 0.32
B6 Poor semi-improved grassland Low (2) Poor (1) 11.14 22.28
C3.1 Other tall herb or fern – Ruderal/ ephemeral
Low (2) Poor (1) 2.02 4.04
F2.1 Marginal vegetation High (6) Moderate (2) 0.05 0.6
J1.1 Arable land Low (2) Poor (1) 15.34 30.68
J1.3 Ephemeral/ short perennial Low (2) Moderate (2) 0.05 0.2
J1.3 Ephemeral/ short perennial Low (2) Poor (1) 0.23 0.46
J4 Bare ground Low (2) Poor (1) 0.16 0.32
J5 Hardstanding N/A N/A 1.04 0.00
TOTAL 30.75 63.64
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 15 of 25
Table 4-2 - Baseline BU of the Proposed Scheme: habitat retained
JNCC HABITAT TYPE DISTINCTIVENESS
SCORE CONDITION
SCORE AREA (HA
to 0.01) BU
A1.1.1 Broadleaved woodland – semi-natural
High (6) Moderate (2) 0.00 0.00
A1.1.2 Broadleaved woodland - plantation
Medium (4) Poor (1) 0.33 1.32
A2.1 Dense scrub Medium (4) Poor (1) 1.29 5.16
A2.2 Scattered scrub Medium (4) Poor (1) 0.24 0.96
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Good (3) 0.03 0.36
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Moderate (2) 0.42 3.36
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Poor (1) 0.03 0.12
A3.3 Mixed parkland/ scattered trees
Medium (4) Moderate (2) 0.40 3.20
B6 Poor semi-improved grassland Low (2) Poor (1) 4.29 8.58
C3.1 Other tall herb or fern – Ruderal/ ephemeral
Low (2) Poor (1) 1.39 2.78
F2.1 Marginal vegetation High (6) Good (3) 0.04 0.72
F2.1 Marginal vegetation High (6) Moderate (2) 0.05 0.6
G1 Standing water High (6) Moderate (2) 0.04 0.48
G1 Standing water High (6) Poor (1) 0.04 0.24
J1.1 Arable land Low (2) Poor (1) 0.30 0.60
J1.2 Amenity grassland Low (2) Poor (1) 0.01 0.02
J1.3 Ephemeral/ short perennial Low (2) Poor (1) 0.03 0.06
J4 Bare ground Low (2) Poor (1) 0.81 1.62
J5 Hardstanding N/A N/A 0.61 0.00
TOTAL 10.35 30.18
4.3 IRREPLACEABLE HABITATS
4.3.1 No irreplaceable habitats were identified within the red line boundary of the Proposed Scheme.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 16 of 25
4.4 LINEAR HABITATS
4.4.1 Tables 4.3 and 4.4 show that there is a total of 2900 LU (1060m) of hedgerow on site of which 30 LU
(10m) will be retained and 2870 LU will be lost.
Table 4-3 – Baseline hedgerow LU lost
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
J2.1.1 Hedges – intact – native species-rich
Good (3) 275 825
J2.1.2 Hedges – intact - native species-poor
Good (3) 429 1287
J2.2.1 Hedges – defunct – native species-rich
Moderate (2) 280 560
J2.3.2 Hedges – with trees – native species-poor
Good (3) 66 198
TOTAL 1050 2870
Table 4-4 – Baseline hedgerow LU retained
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
J2.1.2 Hedges - intact - native species-poor
Good (3) 10 30
TOTAL 10 30
Table 4-5 – Baseline watercourse LU lost
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
G2 Running water N/A 107 N/A
TOTAL 107 N/A
Table 4-6 – Baseline watercourse LU retained
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
G2 Running water N/A 413 N/A
TOTAL 413 N/A
4.4.2 There is a total of 520m of watercourse on site. Of which, 413m will be retained and 107m will be lost.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 17 of 25
5 RESULTS OF THE POST DEVELOPMENT BIODIVERSITY AND
LINEAR UNIT CALCULATIONS
5.1.1 Tables 5.1 and 5.2 show the BU of retained baseline habitats and the BU generated from created
habitats post-development. Table 5.3 shows a summary of the results of the area-based habitat BNG
assessment. Post-development there will be 125.60 BU within the Proposed Scheme’s footprint. Of
which, 95.42 BU is generated by newly created habitat and 30.18 BU by retaining baseline habitat.
Table 5-1 – Post-development – retained habitats
JNCC HABITAT TYPE DISTINCTIVENESS
SCORE CONDITION
SCORE AREA (HA
to 0.01) BU
A1.1.1 Broadleaved woodland – semi-natural
High (6) Moderate (2) 0.00 0.00
A1.1.2 Broadleaved woodland – plantation
Medium (4) Poor (1) 0.33 1.32
A2.1 Dense scrub Medium (4) Poor (1) 1.29 5.16
A2.2 Scattered scrub Medium (4) Poor (1) 0.24 0.96
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Good (3) 0.03 0.36
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Moderate (2) 0.42 3.36
A3.1 Broadleaved parkland/ scattered trees
Medium (4) Poor (1) 0.03 0.12
A3.3 Mixed parkland/ scattered trees
Medium (4) Moderate (2) 0.40 3.20
B6 Poor semi-improved grassland Low (2) Poor (1) 4.29 8.58
C3.1 Other tall herb or fern – Ruderal/ ephemeral
Low (2) Poor (1) 1.39 2.78
F2.1 Marginal vegetation High (6) Good (3) 0.04 0.72
F2.1 Marginal vegetation High (6) Moderate (2) 0.05 0.6
G1 Standing water High (6) Moderate (2) 0.04 0.48
G1 Standing water High (6) Poor (1) 0.04 0.24
J1.1 Arable land Low (2) Poor (1) 0.30 0.60
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 18 of 25
J1.2 Amenity grassland Low (2) Poor (1) 0.01 0.02
J1.3 Ephemeral/ short perennial Low (2) Poor (1) 0.03 0.06
J4 Bare ground Low (2) Poor (1) 0.81 1.62
J5 Hardstanding N/A N/A 0.61 0.00
TOTAL 10.35 30.18
Table 5-2 – Post-development – created habitats
JNCC HABITAT TYPE DISTINCTIVENESS TARGET
CONDITION DIFFICULTY
RISK TEMPORAL
RISK AREA (ha)
POST-DEVELOPMENT
BU
A1.1.1 Broadleaved woodland – semi-natural
High (6) Moderate (2) Medium (0.67)
32+ yrs (0.33)
2.82 7.48
A1.1.2 Broadleaved woodland –plantation
Medium (4) Good (3) Low (1) 20 yrs
(0.5) 0.00 0.00
B2.2 Neutral grassland – semi-improved
Medium (4) Good (3) Low (1) 10 yrs
(0.71) 8.94 76.17
B5 Marshy grassland
Low (2) Poor (1) Medium (0.67)
5 yrs
(0.83) 0.86 0.96
F2.1 Marginal vegetation
High (6) Moderate (2) Low (1) 2 yrs
(0.93) 0.47 5.25
G1 Standing water Medium (4) Moderate (2) Medium (0.67)
0 yrs
(1) 1.73 5.36
J1.2 Cultivated/ disturbed land – amenity grassland
Low (2) Poor (1) Low (1) 2 yrs
(0.93) 0.14 0.2
J4 Bare ground Low (2) N/A Low (1) 0 yrs
(1) 12.54 N/A
J5 Hardstanding N/A N/A N/A N/A 3.33 N/A
TOTAL
fhafohaofh
30.83 95.42
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 19 of 25
Table 5-3 – BU results summary
Area (Hectares)
BU
BASELINE HABITAT LOST
30.75 63.64
BASELINE HABITAT RETAINED
10.35 30.18
TOTAL BASELINE AREA 41.10 93.82
POST-DEVELOPMENT HABITAT CREATED
30.83 95.42
TOTAL AREA POST-DEVELOPMENT
41.16 125.60
5.1.2 Tables 5.4 and 5.5 show the length of hedgerow created post-development and the hedgerow LU
retained in the baseline respectively. Table 5.6 provides a summary of the linear results of this
assessment. Post-development there will be 1563 hedgerow LU (1543m) within the Proposed
Scheme’s footprint. 1533 LU of watercourses will be created and 30 LU will be retained.
Table 5-4 – Hedgerow LU created post-development
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
J2.1.1 Hedges – intact – native species-rich
N/A 1148 1148
J2.3.1 Hedges – with trees – native species-rich
N/A 385 385
TOTAL 1533 1533
Table 5-5 –Hedgerow LU retained from baseline
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
J2.1.2 Hedges - intact - native species-poor
Good (3) 10 30
TOTAL 10 30
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 20 of 25
Table 5-6 – Hedgerow LU results summary
Length (m) Hedgerow
LU
TOTAL HEDGEROWS AT BASELINE
1060 2900
BASELINE HEDGEROWS LOST
1050 2870
BASELINE HEDGEROWS RETAINED
10 30
HEDGEROWS CREATED
1533 1533
TOTAL HEDGEROWS POST-DEVELOPMENT
1543 1563
5.1.3 Tables 5.7 and 5.8 show the length of watercourse created post-development and retained in the
baseline respectively. Table 5.9 provides a summary of the results of the watercourse assessment
Post-development there will be 2358m of watercourse habitats within the Proposed Scheme’s footprint
of which 55m will be culverted. The culverted area will result in a loss of biodiversity value of the linear
feature but this loss is not captured by the current linear metric which simply presents the watercourse
LU as a length in m. 1945m of watercourses will be created and 413m will be retained.
Table 5-7 – Watercourse LU created post-development
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
G2 Running water N/A 1945 N/A
TOTAL 1945 N/A
Table 5-8 –Watercourse LU retained from baseline
JNCC HABITAT TYPE CONDITION SCORE LENGTH (to nearest m)
LU
G2 Running water (55m culverted) N/A 413 N/A
TOTAL 413 N/A
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 21 of 25
Table 5-9 – Watercourse LU results summary
Length (m) or
Watercourse LU
TOTAL WATERCOURSES AT BASELINE
520
BASELINE WATERCOURSES LOST
107
BASELINE WATERCOURSES RETAINED
413
WATERCOURSES CREATED
1945
TOTAL WATERCOURSES POST-DEVELOPMENT
2358
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 22 of 25
6 SUMMARY OF RESULTS AND RECOMMENDATIONS
6.1 SUMMARY OF RESULTS
6.1.1 Table 6.1 demonstrates that the Proposed Scheme design will result in a net gain for biodiversity for
area-based habitats (an increase of 31.78 BU which equates to 34% net gain), a net loss for linear
hedgerow habitats (a decrease of 1337 LU which equates to a 46% net loss) and a net gain of linear
watercourse habitats (a net gain of 1838 m which equates to a 353% net gain).
Table 6-1 – Summary of results
Area
(Hectares) BU
Hedgerow Length (m)
Hedgerow LU
Length (m) or Watercourse
LU
TOTAL AREA-BASED HABITAT OR LINEAR
FEATURE AT BASELINE
41.10 93.82 1060 2900 520
TOTAL AREA-BASED HABITAT OR LINEAR
FEATURE POST-DEVELOPMENT
41.16 125.60 1543 1563 2358
OUTCOME NET GAIN OF 34%
(+31.78 BU)
NET GAIN OF 46% (+483m)
NET LOSS OF 46%
(1337 LU)
NET GAIN OF 353% (+1838m)
6.1.2 Although there is a very significant biodiversity net gain of area-based habitats and
watercourse LU, the Proposed Scheme cannot claim that it will deliver a net gain in biodiversity
within the site boundary due to the loss of Hedgerow LU.
6.1.3 Although there is a net increase in length of hedgerows of approximately 483m, there is an overall
loss of 1337 LU. Using the current metric it is difficult to deliver significant gains for even relatively
limited loss of linear units, without providing considerably more habitat (by length) than is lost. This is
because the current hedgerow metric does not have any weighting for habitat condition when hedges
are created post-development and the condition assessment for hedgerows does not account for
different levels of species richness. The metric for linear units is currently under review by Natural
England.
6.1.4 Due to the limitations of the current metric, enhancements of linear habitats that have been proposed
as part of the Proposed Scheme are not captured. Biodiversity enhancement of hedgerows as part of
the Proposed Scheme include increasing the species-richness of existing hedgerows and providing
species-rich hedgerow to replace species-poor hedgerow.
6.1.5 It is important to recognise that the quantification of biodiversity units is one of a number of factors to
be considered when assessing the impact of each stage on biodiversity
6.2 RECOMMENDATIONS
6.2.1 WSP recommends the following next steps for the BNG assessment:
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 23 of 25
The BNG assessment is re-run once the temporary works layout information is available to ensure
that any impacts resulting from the works are captured and quantified.
The BNG assessment is re-run based on the final landscape plan for the Proposed Scheme.
To avoid re-running the BNG calculations multiple times, the calculations should be re-run once
when the final landscape plan and temporary works layout information is available.
The client should continue to explore any other options to avoid impacts and create more linear
habitats. The client should also continue to emphasise the enhancements of linear habitats that
have been proposed as part of the ES in the BNG report and that these are not captured by the
current metric.
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 24 of 25
7 REFERENCES
Business and Biodiversity Offsets Programme (BBOP). (2012). BBOP Principles on
Biodiversity Offsets. Available: http://bbop.forest-trends.org/documents/files/bbop_principles.pdf
BRE Group. (2018). GN36 BREEAM, CEEQUAL and HQM Ecology Calculation Methodology –
Route. Available: https://bregroup.com/brebreeam/wp-content/uploads/sites/3/2018/06/GN36-
v0.0-BREEAM-CEEQUAL-HQM-Ecology-Calculation-Methodology-Route-2.pdf
CIEEM, CIRIA & IEMA. (2016). Biodiversity Net Gain: Good practice principles for development.
https://www.iema.net/assets/newbuild/documents/IEMA%20Biodiversity%20Net%20Gain.pdf
Department for Communities and Local Government. (2018). Revised National Planning
Policy Framework. Available:
https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/fil
e/740441/National_Planning_Policy_Framework_web_accessible_version.pdf
Department for Environment, Food and Rural Affairs (Defra). (2011). Biodiversity 2020: A
strategy for England's wildlife and ecosystem services. Available:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/69446/pb13583-
biodiversity-strategy-2020-111111.pdf .
Department for Environment, Food and Rural Affairs (Defra). (2012a). Technical Paper: the
metric for the biodiversity offsetting pilot in England. Available:
https://www.gov.uk/government/publications/technical-paper-the-metric-for-the-biodiversity-
offsetting-pilot-in-england
Department for Environment, Food and Rural Affairs (Defra). (2012b). Biodiversity Offsetting
Pilots: Guidance for offset providers. Available:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/69530/pb13742-
bio-guide-offset-providers.pdf
Department for Environment, Food and Rural Affairs (Defra). (2012c). Biodiversity Offsetting
Pilots: Guidance for developers. Available:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/69528/pb13743-
bio-guide-developers.pdf
Department for Transport. (2014). National policy statement for national networks. Available:
https://www.gov.uk/government/publications/national-policy-statement-for-national-networks
Highways England. (2015). Our plan to protect and increase biodiversity. Available:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/441300/N150146_-
_Highways_England_Biodiversity_Plan3lo.pdf
JNCC. (2010). Handbook for Phase 1 Habitat Survey: a Technique for Environmental Audit.
Natural England. (2010). Higher Level Stewardship Farm Environment Plan (FEP) Manual
Technical Guidance on the completion of the FEP and identification, condition assessment and
recording of HLS FEP features. Third Edition. NE. Peterborough.
Northamptonshire Local Nature Partnership (2016) Northamptonshire Biodiversity Action Plan
2015 -2020 (3rd Edition). Available:
https://www3.northamptonshire.gov.uk/councilservices/environment-and-
planning/planning/planning-policy/archaeology-biodiversity-and-
landscape/documents/PDF%20Documents/Northamptonshire%20BAP%202015-2020.pdf
NORTHAMPTON NORTH-WEST RELIEF ROAD CONFIDENTIAL | WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council Page 25 of 25
The European Commission. (2011). Our life insurance, our natural capital: an EU biodiversity
strategy to 2020. Available:
http://ec.europa.eu/environment/nature/biodiversity/strategy/index_en.htm
Internal References
WSP (2017). North-west relief road. Preliminary Ecological Appraisal. WSP UK Limited.
Birmingham, UK.
WSP (2018a). NNWRR Bat Crossing Point Survey Report. WSP UK Limited. Birmingham, UK.
WSP (2018b). NNWRR Breeding Bird Mitigation Report. WSP UK Limited. Birmingham, UK.
WSP (2018c). NNWRR Hedgerow Survey Report. WSP UK Limited. Birmingham, UK.
WSP (2018d). NNWRR. Preliminary Ecological Appraisal. WSP UK Limited. Birmingham, UK.
WSP (2018e). NNWRR Protected Species Survey Report - Badger Survey Report. WSP UK
Limited. Birmingham, UK.
WSP (2018f). NNWRR Protected Species Survey Report - Barn Owl Survey Report. WSP UK
Limited. Birmingham, UK.
WSP (2018g). NNWRR Protection Species Survey Report – Bat Surveys. WSP UK Limited.
Birmingham, UK.
WSP (2018h). NNWRR Protection Species Survey Report – Bat Surveys Summary. WSP UK
Limited. Birmingham, UK.
WSP (2018i). NNWRR Protected Species Survey Report - Great Crested Newt Survey Report.
WSP UK Limited. Birmingham, UK.
WSP (2018j). NNWRR Protected Species Survey Report - Kingfisher Site Appraisal Report. WSP
UK Limited. Birmingham, UK.
WSP (2018k). NNWRR Protected Species Survey Report - Otter and Water Vole Survey Report.
WSP UK Limited. Birmingham, UK
WSP (2018l). NWRR Protected Species Survey Report - Reptile Survey Report. WSP UK
Limited. Birmingham, UK.
Confidential
CIEEM, CIRIA AND IEMA UK
BIODIVERSITY NET GAIN GOOD
PRACTICE PRINCIPLES FOR
DEVELOPMENT
NORTHAMPTON NORTH-WEST RELIEF ROAD WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
NORTHAMPTON NORTH-WEST RELIEF ROAD WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
Confidential
WSP BIODIVERSITY NET GAIN
PROCESS
NORTHAMPTON NORTH-WEST RELIEF ROAD WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
Step 1 – Set the Scope
i. Produce a biodiversity net gain (BNG) strategy. A short memo report setting out client
commitments to BNG, scope of the BNG work, and the proposed steps required.
ii. Workshop 1 or 1-2-1 meetings – strategy meetings. Early engagement with key
stakeholders, likely to include local conservation NGOs, local authorities and government
agencies such as Natural England. Early engagement is essential to present, discuss and
develop the BNG strategy; including setting the BNG good practice principles into a scheme
context and agreeing local priorities for biodiversity.
Step 2 – Initial Biodiversity Assessment
i. Survey baseline habitats and their condition. Ideally, a habitat condition assessment is
undertaken during Phase 1 Habitat survey. If Phase 1 Habitat data has been collected prior
to initiating the BNG process, condition assessment can be undertaken either a)
retrospectively through interpretation of Phase 1 target notes, consultation with surveyors, or
employing a number of assumptions; or b) during an additional site visit.
ii. Identify irreplaceable habitat. Following Defra guidance, irreplaceable habitats within the
scheme boundary must be identified and excluded from the biodiversity unit calculations. It is
important to note that biodiversity net gain or no net loss cannot be achieved for the scheme
as a whole if there is a negative impact on an irreplaceable habitat
iii. Calculate baseline biodiversity units using the biodiversity metric. This calculation
includes all habitats (minus irreplaceable habitats) within the scheme boundary prior to
development, and is informed by Phase 1 Habitat data and results of the condition
assessment. The baseline biodiversity unit calculation may be run on a number of scheme
options if the scheme is at options appraisal stage.
iv. Calculate post-development biodiversity units using the biodiversity metric. This
calculation accounts for all of the proposed habitats (including retained habitat and habitat lost
or created as a result of the development) within the scheme boundary post-development. The
calculation is informed by scheme design, landscape plans, and proposed ecological
mitigation. The assessment is based upon the target state (type, size and condition) of habitats
being created.
v. Produce an ‘Initial Biodiversity Assessment’ report. The report sets out the BNG process
in the context of the scheme, and includes the method and results of initial baseline and post-
development biodiversity unit calculations.
Step 3 – Detailed Scheme Assessment
i. Inform options appraisal. If baseline biodiversity units have been calculated for a number of
scheme options, results will be used to inform options appraisal.
NORTHAMPTON NORTH-WEST RELIEF ROAD WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
ii. Inform the mitigation proposals. Results of biodiversity unit calculations performed under
Step 2 are used to inform the extent and habitat type of on-site ecological mitigation and
compensation land required for the scheme to meet no net loss or net gain targets.
iii. Update biodiversity unit calculations. Following finalisation of the scheme design and
ecological mitigation proposals, the biodiversity units are updated to reflect any changes.
Calculations may also be re-run if updated Phase 1 Habitat data becomes available.
iv. Estimate the biodiversity compensation required. The difference between baseline and
post-development biodiversity units indicates the number of units required for the scheme to
deliver no net loss or net gain for biodiversity. This in turn can be used to identify the extent
and habitat type of compensation required. A rough cost estimate for potential compensation
can be provided at this stage.
v. Workshop 2 – compensation/offset workshop. Work with stakeholders to gather
suggestions to identify candidate compensation sites and providers. These sites could be
offset sites, which are compensation sites that are situated outside the project boundary. This
workshop also provides an opportunity to update stakeholders on BNG progress.
Step 4 – Assessment of Candidate Offset Sites
i. Initial assessment of feasibility. Any candidate offset sites which are considered not feasible
for any reason are scoped out at this stage.
ii. Survey candidate offset sites to identify existing habitat type, extent and condition.
iii. Calculate potential biodiversity units deliverable by each candidate offset. Using the same
methods employed for calculating baseline and post-development biodiversity units for the
scheme as a whole, calculate baseline and post-development biodiversity units for offset sites
to determine potential biodiversity units deliverable.
iv. Hold one-to-one meetings with potential offset providers to:
a) Identify suitable locations for candidate offset sites and determine what habitats and
species they could support;
b) Determine how offsets can contribute to local biodiversity objectives and fit within
ecological networks;
c) Set out the type of agreement that would be acceptable to offset providers (e.g. long
term agreement for management of the land); and
d) Collate information to feed in to offset scoring templates and offset summary sheets.
v. Score candidate offsets using the offset scoring template. This takes into account ecological
factors, financial factors, and wider benefits and opportunities.
NORTHAMPTON NORTH-WEST RELIEF ROAD WSP Project No.: 70045931 | Our Ref No.: BNG MAY 2019 Northampton County Council
vi. Produce offset summary sheets describing each offset site in its present state and the
habitats and species the proposed offsets will support. Details of land ownership, access
provisions and proposed management agreements are also included in summary sheets.
vii. Panel review of potential offset sites to include relevant stakeholders. Decisions are made
as to which candidate offset sites to take forward.
Step 5 – Completion of Biodiversity Assessment
i. Final update of biodiversity unit calculations. If there have been changes to the scheme
design (including environmental mitigation proposals) since calculations were last updated,
biodiversity units are updated to reflect any changes.
ii. Workshop 3 – final workshop. A third stakeholder engagement workshop is recommended
to update all stakeholders on BNG progress since the last workshop, and inform them of any
decisions made.
iii. Produce a ‘Full Biodiversity Assessment’ report and associated GIS data. This will detail
the approach and outcomes of Steps 1 to 4, importantly, how the project has met the BNG
good practice principles. It will set out candidate offset sites and enable the client to decide
which offsets to support and whether to aim for no net loss or net gain.
Step 6 – Delivering Biodiversity Net Gain
i. Implement BNG during the construction phase. This will involve: updating the biodiversity
baseline; including BNG within construction documents; training key staff; reducing the time-
lag between losses and gains; acting on risks and opportunities; and collecting evidence and
data.
ii. Set up offsets. Once offset sites to be delivered have been selected, and fine details of the
scope of each offset agreed, legal agreements will be set up with offset providers to manage
offsets over a set time frame (generally between 15 and 30 years). Further information on the
agreement types can be provided on request.
iii. Monitor and report to ensure the offsets are delivered to the standard required. Monitoring
and reporting is undertaken at key points throughout the management agreement (e.g. once
every two or three years).
Confidential
PHASE 1 MAPS: BASELINE AND
POST-DEVELOPMENT
CONFIDENTIAL
Kings Orchard
1 Queen Street
Bristol
BS2 0HQ
wsp.com