1 North Star Pre-Construction Meeting Presentation Presented by: Gas Engineering New Business March 16, 2017

Transcript of North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: •...

Page 1: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

1

North Star

Pre-Construction Meeting Presentation

Presented by: Gas Engineering New Business

March 16, 2017

Page 2: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

2

Providing Natural Gas To North Star

Page 3: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

3

North Star Project Overview

Total Feet of Pipe Installed:

• approx. 12,255’ of 2”

• approx. 750’ of 4”

• approx. 465’ of 6”

• approx. 8,135’ of 8”

Customers in project area:

• 210 directly impacted

Customers signed up for gas service line:

• 87 customers or 41% of neighborhood

• We are in need of additional applicants based on project bids received

Size of PY pipe to be installed:

• 2” , 4”, 6” & 8”

Page 4: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

4

Preliminary Design – North Star

Page 5: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

5

North Star Construction Timeline

Construction Schedule:

• Begin construction – Late March

• Complete main installation – Late July

• Complete final restoration – 10/31/2017

All work is weather dependent

Scope of work may change daily due

to unforeseen conditions

The intent is to complete final

restoration once all main and services

are complete.

Temporary restoration will be done at the end of each task or

week.

Page 6: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

6

Natural Gas Expansion Project

Project scope involves:

• Marking of utility lines – 8-1-1

• Awarding bid contractor will test hole over main

• Set up of the directional drill

• Excavation of the receiving pits, etc.

• Boring of the main

• Gas main will be tied-in (energized)

• Installation of service lines to applicable locations (bore)

• Restoration will occur once all main and services are complete

Page 7: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

7

Installation of Natural Gas

Preliminary order of Gas Main installation by street for North Star

1. Polaris Dr

2. Meteor Ct

3. Mercury Rd

4. Jupiter Rd

5. Neptune Dr

6. North Star Rd

7. Beech Hill Dr

8. Mercury Rd

9. Mars Rd

10. Meteor Ln

11. Orbit Cir

12. Saturn Dr

13. Jupiter Rd

14. Venus Dr

15. Planet Rd

16. Galaxy Dr

17. Comet Lane

Page 8: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

8

Service Installations

Services will be installed to each applicant when the customer

is ready to start receiving natural gas

Each applicant will have an on-site meeting with the field

technician and during those on-site meetings it will be

determined if the customer is ready to receive a natural gas

service line during this project.

Applicants are refunded their $200 security deposit when

natural gas is flowing to the residence for a gas-fired appliance.

Customer Converts & Gas meter is installed Security deposit refunded

Page 9: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

9

Gas Conversion Projects: Staging of Material

Locations in

neighborhood that

have been identified

as low traveled areas

are used for the

staging of materials.

Material is coned off

for safety and kept to

minimum level of

encroachment into

roadway.

Page 10: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

10

Gas Expansion Projects: Test Holes

Test holes may be performed prior to main installation by either

hand digging or possibly vacuum excavation

Page 11: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

11

Gas Conversion Projects: Test Holes

Left: Test hole areas left safe with proper coverage until

temporary restoration

Right: Completed temporary restoration with backfill

Page 12: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

12

Gas Conversion Project: Main Installation

Install new main throughout neighborhood in the state right-of-

way at the curb line utilizing a directional bore technique.

Equipment may need to encroach on private property for

perpendicular main alignments

Page 13: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

13

Gas Conversion Project: Main Installation

Right: temporary restoration on a driveway that was open cut

due to unforeseen underground conditions

Left: temporary restoration on large section of receiving pit for

main

Page 14: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

14

Gas Conversion Project: Main Installation

Final Restoration On Driveway

Page 15: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

15

Gas Conversion Project: Main Installation - Temporary

Restoration

Left: temporary restoration of test hole in roadway

Right: temporary restoration of disturbed area in right-of-way

Page 16: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

16

Service line, Riser, & Meter bar

When customer is ready to

convert to a gas-fired

appliance, they must:

• Hire a licensed contractor to

install fuel lines

• Have NCCO inspect & tag

fuel line

• Private contractor ties fuel

line into meter bar

• Call Delmarva Power to

schedule meter install

Page 17: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

17

Meter Installation

Example of Inspection Tag

Page 18: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

18

North Star Gas Project Contact Sheet

Business Development Coordinator – Mike June

• Email: [email protected]

• Phone: (302) 429-3290

Field Technician – Brent Lobley

• Email: [email protected]

• Phone: (302) 650-3067

Project Engineer – Rob Rex

• Email: [email protected]

• Phone: (302) 429-3222

Page 19: North Star - Delmarva · 3/16/2017  · North Star Construction Timeline Construction Schedule: • Begin construction – Late March • Complete main installation – Late July

19

Questions?