NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric...

50
Subproject: Jointing 110kV line at 220kV Bim Son substation Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ------------------------------- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: DISTRIBUTION EFFICIENCY PROJECT JOINTING 110KV LINE AT 220KV BIMSON SUBSTATION PREPARED BY DONG HAI CONSULTING AND CONSTRUCTION JOINT STOCK COMPANY Hanoi, 19 April, 2012 E3035 v11 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric...

Page 1: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan

NORTH POWER CORPORATION

Electric Network Project Management Board

-------------------------------

ENVIRONMENTAL MANAGEMENT PLAN

(EMP)

SUBPROJECT:

DISTRIBUTION EFFICIENCY PROJECT

JOINTING 110KV LINE AT 220KV BIMSON SUBSTATION

PREPARED BY

DONG HAI CONSULTING AND CONSTRUCTION JOINT STOCK COMPANY

Hanoi, 19 April, 2012

E3035 v11 P

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

ed

Page 2: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 2

TABLE OF CONTENTS

I. GENERAL INTRODUCTION .................................................................................................... 4

II. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS ................................. 4

2.1. Vietnamese Legislations ...................................................................................................... 4

2.2. World Bank Safeguard Policies ........................................................................................... 5

III. SUBPROJECT DESCRIPTION AND SCOPE OF WORK ..................................................... 5

3.1. Objectives of the Subproject ................................................................................................ 5

3.2. Subproject Location ............................................................................................................. 5

3.3. Subproject Management Organization ................................................................................. 5

3.4. Project description ................................................................................................................ 6

3.5. Subproject Main Work Volume ........................................................................................... 9

3.6. Main Activities Before and During Construction ................................................................ 9

3.6.1. Main Activities Before and During Construction ......................................................... 9

3.6.2. Material and equiptment supplying source: ............................................................... 10

3.6.3. Transportation: ........................................................................................................... 10

3.7. Subproject Implementation Schedule and Total Investment ............................................. 10

3.7.1. Subproject Implementation Schedule .......................................................................... 10

3.7.2. Total investment of the project: .................................................................................. 10

IV. ENVIRONMETNAL BACKGROUND ................................................................................. 11

4.1.Geography and Geology...................................................................................................... 11

4.1.1. Geography .................................................................................................................. 11

4.1.2 Geology ........................................................................................................................ 11

4.1.3 Soil ............................................................................................................................... 11

4.1.4. Climate: ...................................................................................................................... 12

4.2. Natural resources: ............................................................................................................... 12

4.2.1. Land resources: .......................................................................................................... 12

4.2.2. Mineral resources: ...................................................................................................... 12

Page 3: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 3

4.2.3. Water Resources: ........................................................................................................ 12

4.2.4. Forest resources: ........................................................................................................ 13

4.3. Population, culture and society: ......................................................................................... 13

V. SUBPROJECT POTENTIAL IMPACTS ................................................................................ 13

5.1. Environmental screening: ................................................................................................... 13

VI. ENVIRONMENTAL MANAGEMENT PLAN: .................................................................... 19

6.1. Mitigation measures: .......................................................................................................... 19

VII.ENVIRONMENTAL MONITORING PLAN ........................................................................ 34

VIII. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING ............... 37

IX. REPORTING PROCEDURE .................................................................................................. 39

X. CAPACITY BUILDING FOR EMP IMPLEMENTATION ................................................... 40

XI.ESTIMATED COST FOR IMPLEMENTING THE EMP ...................................................... 42

XII. COMMUNITY CONSULTATION AND DISCLOSURE OF INFORMATION ................ 42

12.1 Community consultation: .................................................................................................. 42

12.2 Disclosure of information: ................................................................................................ 42

ANNEX 1. TOR for monitoring of emp implementation for construction supervising consultant

....................................................................................................................................................... 43

ANNEX 2. Report template for monitoring of EMP implementation .......................................... 45

ANNEX 3. Report template for monitoring of EMP implementation .......................................... 46

ANNEX 4. Subproject area map ................................................................................................... 47

ANNEX 5. Some pictures of project area ..................................................................................... 48

ANNEX 6. Consultancy minutes .................................................................................................. 49

ANNEX 7. List of consulted peoples ............................................................................................ 50

Page 4: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 4

I. GENERAL INTRODUCTION

The subproject “Jointing 110kV line at 220kV Bim Son substation - Thanh Hoa province”

is one of the subprojects that will be implemented in Phase I of the Distribution Efficiency

Project (DEP) of Electricity of Viet Nam Corporation funded by the World Bank. The subproject

will be implemented in Bac Son District, Bim Son Town, Thanh Hoa Province.

The activities of the subproject include: Rehabilitation and newly construction of two

110kV branches and jointing to the existing lines. The first branch is to Ninh Binh, Bim Son with

a total length of 3.537 km (4 circuit line). The second ones is to Ha Trung with a total length of

1.67km (2 circuit line). These activities can cause negative impacts on the environment and local

communities in the period of pre-construction, construction and operation.

To ensure that the potential negative impacts are identified and mitigated during project

implementation and compliance with policies on environment assessment of World Bank -

(OP/BP 4.01), Environment Management Plan (EMP) of project had been prepared in

accordance with the guidance of the Environment Management Framework (EMF) of DEP. This

EMP includes: project description, policy framework, regulations of environmental technical, the

potential negative impacts, the proposed mitigation methods will be implemented in the periods

of pre-construction, construction and operation, implementation arrangements. EMP also

includes Environmental Codes of Practice (ECOP) will be incorporated into tender documents

and contract, attached with environmental monitoring.

To comply with the government environmental management regulation the subproject

needs to prepare an Environmental Impact Assessment (EIA). The EIA of the subproject is being

prepared in parallel with the preparation of the EMP.

II. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS

2.1. Vietnamese Legislations

- Law on Protection of the Environment No. 52/2005/QH11 passed by the National

Assembly on November, 29th

, 2005 regulates the obligations of individuals, organizations

in protecting environment.

- Law on Water Resource No. 08/1998/QH10 dated 20 May, 1998

- Decree of Government No. 80/2006/ND-CP dated 9 August, 2006 on guidance for

implementation of Law on Protection of the Environment.

- Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating strategic

environmental assessment, environmental impact assessment and environment protection

commitment.

- Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree

No.29/2011/ND-CP dated 18 April, 2011.

- Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on guidance for Law

on electricity relating to the protection of high-voltage networks.

- Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending some

Article of Decree No.106/2005/ND-CP dated 17 August, 2005.

Page 5: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 5

- Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to toxic waste

management.

- Vietnam National Standard: QCVN01: 2009/BYT- national technical regulation on

drinking water quality; QCVN02: 2009/BYT- national technical regulation on domestic

water quality; QCVN08: 2008/BTNMT - national technical regulation on surface water

quality; QCVN09: 2008/BTNMT - national technical regulation on ground water quality;

QCVN05: 2009/BTNMT – air quality – Standard for ambient air quality; QCVN06:

2009/BTNMT – air quality –specified maximum allowable concentrations of certain

hazardous substances in ambient air.

- Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on

management and pollution prevention and exposure to PCBs.

2.2. World Bank Safeguard Policies

An environmental screening was undertaken in line with the guidelines provided in the

Environmental Management Framework (EMF) of the DEP project and it showed that the World

Bank’s policies on Environmental Assessment (OP 4.01) and Involuntary Resettlement (OP

4.12) will be triggered for the subproject. In addition, the Bank’s requirements on public

consultation and information disclosure will need to be followed. The implementation of policy

on involuntary resettlement (OP 4.12) will be addressed in a separate report.

III. SUBPROJECT DESCRIPTION AND SCOPE OF WORK

3.1. Objectives of the Subproject

The investment project: “Jointing 110kV line at 220kV Bim Son substation - Thanh

Hoa province” is carried out in order to meet the demand of supplying power to the loads at Bim

Son Town, VEAM auto factory, Bim Son Cement factory,… as well as the loads of Ha Trung

Town, Thanh Hoa Province and to strengthen regional grid unity in order to supply power stably

and reliably for Thanh Hoa and Ninh Binh Province.

3.2. Subproject Location

The subproject is implemented in Bac Son district, Bim Son town, Thanh Hoa province

(For position of the project communes, please refer to appendix 5)

3.3. Subproject Management Organization

- Subproject Owner: Northen Power Corporation

- Technical Design Consulting Unit: Dong Hai consulting and construction joint stock

company.

- Subproject Management Unit: Northen Project management Board - Northen Power

Corporation

Page 6: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 6

3.4. Project description

The project: “Jointing 110kV line at 220kV Bim Son substation - Thanh Hoa province”

is implemented with the scale as follows:

a. Branch 1: To Ninh Binh, Bim Son

+ Voltage level: 110kV

+ Number of circuit: four

+ The first point: The pole No.1, newly construction pole, at the position of pole No.93 of

110kV Ninh Binh – Ha Trung line, route 171.

+ The endpoint: 110kV rod of 220kV Bim Son substation.

+ The length of four circuits line: 3.537km.

+ Conductor: New conductor is ACSR240mm2.

+ Lightning conductor: Newly installing one lightning conductor TK50 and one unit

OPGW57/12.

+ Insulator: Newly installing insulator U70BS and U120B

+ Pole: Newly constructing four-circuit zinc-plate steel pole, two lightning conductors with

38m, 40m, 44m, 49m, 52m and 54m height.

+ Foundation: Newly constructing types of foundation for four-circuit line by ferro-

concrete fabricated on-site.

+ Earthing: Newly constructing earthing RC4 for all of pole positions.

b. Branch 2: To Ha Trung

+ Voltage level: 110kV

+ Number of circuit: two

+ The first point: The new pole No.1 which is far from the status pole No.102 of 110kV

Ninh Binh - Ha Trung line 171 route 20m, from pole 101 to 102 (belong to the project Bim Son

– Nui Mot).

+ The endpoint: 110kV rod of 220kV Bim Son substation.

+ The length of two circuits line: 1.67km.

+ Conductor: New conductor is ACSR240mm2.

+ Lightning conductor: Newly installing one lightning conductor OPGW57/12.

+ Insulator: Newly installing insulator U70BS and U120B

+ Pole: Newly constructing two-circuit zinc-plate steel pole, one lightning conductors with

24m, 27m, 29m, and 33m height.

+ Foundation: Newly constructing types of foundation for two-circuit line by ferro-

concrete fabricated on-site.

+ Earthing: Newly constructing earthing RC4 for all of pole positions.

c. Dismount and recovery of the status route

Page 7: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 7

+ Voltage level: 110kV

+ Number of circuit: one

+ The first point: The status pole No.93 of 110kV Ninh Binh - Ha Trung line 171 route.

+ The endpoint: The status pole No.101 of 110kV Ninh Binh - Ha Trung line 171 route.

+ Dismount and recovery of the status line: one circuit line ACSR150mm2 with 2708m

length and one lightning conductor TK50.

+ Dismount and recovery of the status pole: four concrete poles with 20m height, one

supporting steel pole D111-26, four anchor steel poles N111-25, one anchor steel pole N122-29,

one anchor steel pole N122-30

+ Dismount and recovery of conductor insulator: twenty three 110kV supporting insulator

strings, forty two 110kV anchor insulator strings.

+ Dismount and recovery of lightning conductor insulator: four 110kV supporting insulator

strings, thirteen 110kV anchor insulator strings.

The length and passing area of each route are described detailedly as follows:

Table 3.1. Description of medium voltage transmission lines

No. Poles

Distance Length (m) Route description

A Branch 1: To Ninh Binh, Bim Son: The route is from the pole No.1 that is newly

constructed at the position of the pole No.93 of 110kV Ninh Binh - Ha Trung line,

route 171

Pole No.1 to

No.5 1,309

The 110kV line with four circuits would start

from the pole No.1 that will be newly

constructed at the position of the current pole

No.93 on the pineapple planting hill and

through the perennial planting area, sugar cane,

through the positions of the poles No.2; No.3;

No.4 to the pole No.5 (G1) at the melon

planting area, on the side of the B area of the

Bim Son industrial zone.

Pole No.5 to

No.6 202

The section would pass through Tran Hung

Dao road being constructed, the new Highway

1A, North-South railway and the old Highway

1A.

Pole No.6 to

No.8 779

The section would be from the pole No.6

passes through the perennial garden to the

pole No.8 at the tea planting hill, it will pass

through the concrete road one time, one time

through 35kV line, and two times through

0,4kV line.

Pole No.8 to 292 The section passes through the valley over the

pineapple planting hill, through 0,4kV line

Page 8: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 8

No. Poles

Distance Length (m) Route description

No.9 one time.

Pole No.9 to

No.10 321

The section would be from the pole No.9

passing through the valley, crossing a lake to

the pole No.10 over the pineapple planting

hill.

Pole No.10 to

No.13 533

The section would pass through the pineapple

planting hill.

Pole No.13 to

No.14

(seperate the

1st branch)

110

The section is from the pole No.13 passes

through the valley to the pole No.14 over the

pineapple planting hill.

Pole No.14 to

220kV Bim

Son

substation

27

The section goes straight to 220kV Bim Son

substation and ends the 1st branch in the

pineapple planting hill.

Pole No.13 to

No.15

(seperate the

2nd

branch)

101

The section is from the pole No.13 passes

through the pineapple planting hill to the pole

No.15.

Pole No.15 to

220kV Bim

Son

substation

27

The section goes straight to 220kV Bim Son

substation and ends the 2nd branch in the

pineapple planting hill.

Total I 3,573

II Branch 2: To Ha Trung: The route is from the pole No.1A that is newly

constructed under the line within the pole distance between pole No.101 and No.102

of 110kV current line, route 171 to the end point at 220kV Bim Son substation.

Pole No.1 to

No.2A 418

The section follows the direction of current

line over the pineapple planting hill.

Pole No.2A to

No.3A 289

The section is from the pole No.2A through

the valley to the pole No.3A over the

pineapple planting hill.

Pole No.3A to

No.4A 330

The section is from the pole No.3A through

the valley, lake to the pole No.4A over the

pineapple planting hill.

Pole No.4A to 312 The section passed through the pineapple

Page 9: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 9

No. Poles

Distance Length (m) Route description

No.6A planting hill.

Pole No.6A to

No.8A 294

The section is from the pole No.6A through

the valley to the pole No.8A over the

pineapple planting hill.

Pole No.8A to

220kV Bim

Son

substation

27

The section goes straight from the pole No.8A

to 220kV Bim Son substation and ends at the

bar of the substation.

Total 2 1,670

3.5. Subproject Main Work Volume

Table 3.2. Work volume to be implemented in Ha Noi City

No. Construction and installation Unit Quantity Executing

methods

1 Pole foundation digging cubic

metre 17,532 Manual

2 Pole foundation filling cubic

metre 16,214 Manual

3 Concrete cubic

metre 1,804 Manual

6 Foundation steel, earthing, bolts ton 205.03 Manual

7 Erect steel pole pole 23 Manual

8 Stretching the conductors metre 53,458 Manual

9 Stretching the lightning conductors and

optical fiber metre 9,254 Manual

10 Insulation unit 512 Manual

3.6. Main Activities Before and During Construction

3.6.1. Main Activities Before and During Construction

- To implement the clearance compensation;

- To receive the site, build temporary camps;

- To mobilize manpower, machinery, material and equiptment to the constrution site;

Page 10: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 10

- To dig the pole foundation, erect poles, stretch line.

3.6.2. Material and equiptment supplying source:

- The electrical material are bought in Hanoi and transported to the construction site.

- Steel structures: is bought in domestic.

- Construction material: is bought in the local area.

3.6.3. Transportation:

- Equipment and material are transported from the receving place in Ha Noi to the store

in Bac Son Ward, Bim Son town, Thanh Hoa province by specific vehicles by land. The specific

vehicles are selected in accordance with goods packing methods that specified in the contracts.

Length of long-distance transportation is about 120 kilometres, following the Highway 1A. After

that they are transported to the site by strucks, loaded and unloaded by the automated cranes.

- Cross-arm, bracket structure, accessories are transported by five-ton strucks and loaded

manually.

- Goods that must be stored at site such as: conductors, insulators, accessories, ... are

transported intermediately from the store to the manual transporting position by mechanical and

manual combination.

- The whole material are transported manually to the site. The transmision line mainly

passes through medium high and low hill with valley of rice fields alternately, or plant corn,

potatoes, cassava, sugar cane and short-term fruits likes pineapple etc. The average

transportation distance is 150m.

3.7. Subproject Implementation Schedule and Total Investment

3.7.1. Subproject Implementation Schedule

The estimated schedule as follow:

- Establishing investment project: Quarter IV - 2011

- Establishing executing drawing design: Quarter I - 2012

- Establishing equipment and construction bidding document: Quarter II - 2012

- Providing operation time: Quarter IV-2012

3.7.2. Total investment of the project:

Table 3.3. Total investment of the project

No. Capital structure Amount (VND)

1 Constrution cost 40,566,201,916

Page 11: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 11

No. Capital structure Amount (VND)

2 Compensation cost 950,000,000

3 Project management cost 820,349,307

4 Construction investment consultancy

cost 2,687,527,377

5 Other cost 2,929,052,791

6 Provision cost 7,197,001,887

Total: 55,177,014,470

IV. ENVIRONMETNAL BACKGROUND

4.1.Geography and Geology

4.1.1. Geography

Bim Son town is the border area of Thanh Hoa province and the whole Central region,

Bim Son town is far from Thanh Hoa City 34 kilometre as North, Ha Noi Capital 120 kilometre

as South and at the coordinates of 2002 to 20

09' north latitude and 105

047' to 105

056' East

Longitude. It is on favourable transportation nework with North-South railway, 1A highway

passing. This is creat a large trade with neighbouring province and big economic central on

whole the country.

+ Its North borders on Ninh Binh province

+ Its South borders on Ha Trung district, Thanh Hoa province

+ Its East borders on Nga Son district, Thanh Hoa province

+ Its West borders on Thach Thanh district, Thanh Hoa province

4.1.2 Geology

Bim Son is lower from west to east. Geological characteristics of Bim Son belongs to

Son La structure zone, subsidiarity of Ninh Binh; Its soil and stone is formed on the medieval

period - Toriat Century, about 300 million years ago. The area is not large but Bimson has plain,

rocky, hilly and river.Hilly and mountainous area extends from NorthWest to the Northern of

Northeast with 5,097.12 ha in area, plain is 1,518.98ha in area; rock has characteristics of the

sandstone being rough sharpening stone, shale and limestone vessel ups and downs alternately,

plain is convenient for agricultural development and is also reserved land area to develop urban.

4.1.3 Soil

Bim Son Town has two main soil groups are alluvial soil, Feralit soil. Area of alluvial

soil is 999.22 ha. Area of Feralit soil is 4,193.93 ha.

Page 12: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 12

4.1.4. Climate:

Bim Son Town is influenced by three alternating climatic regions being Northeast,

Northwest of Northern and near north central part. Yearly average temperature is 23,6 degree,

average rainfall is 1,514 mm per year; average humidity is 80 percent, wind regime changes

seasonally, is sunny and rainy.

4.2. Natural resources:

4.2.1. Land resources:

Bim Son Town has two main soils is alluvial soil, gray feralit soil , specifically:

- Alluvial soil: 999.22 ha, of which:

+ Glay heavy sour alluvial soil : located six low-lying terrain area; area: 126.26 ha,

concentrated distribution in the communes: Ha Lan, Quang Trung accordance with the

development of rice cultivation, aquaculture production.

+ Glay heavy change alluvial soil: 872.96 ha, distributed in the terrain highly, favorable for

the rice cultivation, crops and anual industrial crops.

- Grey area: 4,193.93 hectares, including:

+ Rock and shallow grey feralit soil 3,535.86 ha.

+ Rock and deep grey feralit soil 658.07 ha. The thickness of soil is quite favorable for

long-time industrial plants, short development.

4.2.2. Mineral resources:

Main mineral of Bim Son: limestone, clay. Of which:

- Yen Duyen mine limestone: 3,000 million tons, distribution area: 1000 ha;

- Co Dam mine schist with reserves of 60 million tons, distribution area: 200 ha;

- Cement clay (Tam Dien mine) reserves of 240 million tons, distribution area: 200 ha;

- Leveling land (Thung Con) reserves of 3.5 million tonnes, area: 100 ha;

- Two clay mines for brick production at the Ha Lan with reserves of 19 million tons, area 30 ha.

4.2.3. Water Resources:

Bim Son Town has a network of rivers, ponds, lakes, rivers and streams short and small,

poor surface water erratic seasonal fluctuations: the rainy season flooding, dry season water

shortages.

The town's streams: Song stream, Chin Gieng, Co Dam, Go chink, 3 Voi, Khe Can are

flow Hoat river, through Tam Diep canal.

Total volume of water flooding the entire town: 1,685,000 m3/day and night, the dry

season: 9,513m3/day and night.

Town has groundwater resources very plentiful. Due to the limestone terrain, Bim Son has

many caves, underground rivers can provide water to the town, according to survey results

Page 13: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 13

56km2 Bim Son town area (Geology Group 47) the Council reserves national water through

said: Bim Son area of underground water reserve level of about 41,300m3/day and night.

4.2.4. Forest resources:

Forest of Bim Son mainly of planted forest, natural vegetation on the rocks are mainly

brushwood, area: 1,141.57 hectares.

Wild animals of Bim Son poor, mostly a few reptiles and mink, fox on the rock.

4.3. Population, culture and society:

According to information from the electronic portal of Thanh Hoa province, to 31st

December, 2008 population of Bimson 59,747 peoples ; population density: 820 people per km2

In the area of the project: the problem of culture, society has always been interested in local

government, all people have access to clean water, electric lighting. The project will contribute

directly and indirectly improve the lives of local people by providing electricity for production,

local economic development, lighting of public works.

The project is not located in area of historic, cultural - social facilities as well as security

and defense.

V. SUBPROJECT POTENTIAL IMPACTS

5.1. Environmental screening:

Table 5.1. Environmental impact assessments

Screening Question Yes No Remarks

1. Is project located near or in

sensitive area with regards to?

Cultural heritage X The project power line would not go

through the culture or history works so

it has no impact.

Reservation zone X The project’s power line would not go

through the conservation areas so it

has no impact.

Wetlands X The project’s line would mainly go

through the hill so they does not go

through the wetlands.

Forests X The project’s line would not go through

the forests so it has no impact.

Estuary X The project’s line would not go through

the estuaries so it has no impact.

Reservation buffer zone X The project’s line would not go through

Page 14: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 14

Screening Question Yes No Remarks

the buffer zone of protection areas so it

has no impact.

Rivers and reservoirs

X Line from pole No 9 to pole No 10 goes

through lake. There is no foundation

next to lake. The impact is considered

to be small.

Canaland irrigation network X The project’s line goes through some

canal but they are not the location to

build foundation for the poles so it has

no impact.

2. Potential environmental impact,

by project?

Intrusion to cultural and historical sites X The project’s line does not go through

areas that have the culture or history

works so it has no impact.

Encroachment on critical ecosystem

(e.g. sensitive or protected area,

national park, nature reserve etc....)

X The project’s line does not go through

the conservation areas so it has no

impact.

Intrusion to ecosystem (ex: nature

reserve, national park)

X Because of corridor clearance, there

will be small changes in landscape and

increase waste. However, impact is low

and mitigation measures will be

applied. .

Affecting landscape and resulting in

waste

Undermining vegetation cover or

cutting down trees for site during site

clearance for substations and along the

transmission line?

X The route mainly goes through the

average high and low hill, most land

areas are using to plant corn, potatoes,

cassava, sugar cane and short-term

fruit-tree such as pineapple, so it is

unnecessary to cut down them (the

vegetation cover is only impacted at

foundation positions)

Change surface water quality or river

course

X The route does not go through any

river, pond or lake so it has no impact.

Increase water turbidity due to

change in surface water quality

or erosion

X The excavated soil (1,318 m3) will be

given to inhabitant in subproject area

to plant tree and farm produce. There

fore, there is no excavated soil after

Page 15: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 15

Screening Question Yes No Remarks

completing the subproject.

Because the topography where the line

passes through is mainly the average

high and low hilly and mountainous

areas, while constructing if in the

raining season without projection

measure for the foundation it will cause

erosion and impact the flow.

Domestic waste water by

workers is discharged directly

into outside water bodies?

X The constructing units rent private

houses, so the wastewater is collected

into the general sewage system.

Construction waste water is

discharged directly into outside

water bodies?

X

Result in more dust? X - Dust will be generated from soil

excavation, ground leveling activities,

particularly in dry season. The affected

are people living and working around

the subproject site.

- Dust would also be generated by

transportation means that carry

materials and equipment during the

construction. The affected are people

involved in the traffic during the

transportation of construction

materials or equipment, either on

local roads or on provincial or

national roads.

- The measures described in section VI

will be implemented to minimise the

impacts of dusts.

Increase noise and/or vibration? X - Noise and vibration are generated by

operation of equipment, transportation

of materials, transportation means,

ground leveling, pole erection, and

operation of power generator (if any).

- The substations will be located on

foot hills, far from residential areas,

and hence noise and vibration during

construction would not affect local

communities.

Page 16: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 16

Screening Question Yes No Remarks

- Construction materials will be

provided and transported to the

construction sites by local suppliers.

- Base on above-mentioned reasons,

impacts on increasing the noise and/or

vibration at the subproject area are

assessed as not significant and can be

mitigated.

- Relevant measures listed in section

VI will be implemented to minimise

these impacts.

Permanent land acquisition X Permanent occupied land area is 1,828

square metre

Temporary land acquisition X Temporary occupied land area is

19,464 square metre

Resetlement of households? If yes, how

many households?

X The route mainly goes through the low

hills that plant short-term crops. The

constructing area does not impact local

household so there is not any

household to move.

Would the resettlement site is

environmentally and/or culturally

sensitive

X

Is there any risk of disease

dissemination from construction

workers to the local peoples (and vice

versa)?

X - Construction force includes one

construction team/per commune, each

team will have about 10 workers. The

total number of workers on the site at

the peak time is about 250 people but

they are in many places of the route,

not gathering in one place. Therefore,

the spread of disease will also be

limited.

-Interactions with local community

may pose the risks of STD/HIV/AIDs

diseases transmission between

workers and local community.

Relevant measures described in

section VI of this EMP will be

implemented to minimise these risks.

Page 17: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 17

Screening Question Yes No Remarks

Is there any potential for conflict

between construction workers and local

peoples (and vice versa)?

X Workers and local people are different

in income, lifestyle, custom thus it will

generate small conflict but it will be

limited.

Are explosive and hazardous chemicals

used within the Project?

X

In the past, there was any accident

incurred due to landmines or explosive

materials remaining from the war?

X

Will Project's construction cause

disturbance to the transportation in the

Project's site?

X Great impact: The transportation of

material and equiptment can cause

traffic jam. The excavation impacts the

quality of the road and cause the

traffic.

Project's construction will cause any

damage to the existing local roads,

bidges or other rural infrastructures?

X - The heavy transport vehicles can

damage the current roads.

- The impacts on traffic will also be be

managed by the measures presented in

this EMP

Will soil excavation during Project's

construction cause soil erosion?

X The constructing time for each pole

foundation is not long (maximum about

one week) and avoiding to construct in

raining seasons and constructing

definitively each item, so the erosion is

negligible.

Will Project need to open new access

roads?

X Using the current road system to

construct. These roads will be

improved for constructing and traffic of

local people.

Will Project cause fragmentation of

habitat of flora and fauna?

X In the corridor if there are crops and

trees that affect the constructing

process must be cut off.

Will Project cause impact on air

quality?

X The impact level to the environment by

exhaust fumes of traffic means during

transportation will be limited by

covering, avoid scattering.

Will Project cause accident risks for

workers and community during

X It is possible to occur transprort traffict

to worker and area community during

subproject implement. However, all

Page 18: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 18

Screening Question Yes No Remarks

construction phase? workers are disseminated implementing

process and method of safety at work.

Thus, the ocurrence of accident will be

limitted maximum.

Will Project generate hazardous wastes

including PCBs from the replacement

of transformers?

X There is no removed transformer in this

subproject. Due to there is no PCBs.

waste

Will Project cause risk to safety and

human health (electric and magnetic

fields, electric shock etc.)?

X - The transmission lines shall be

designed and constructed in

accordance with applicable standards

of power industry (in accordance with

Vietnam applicable technical

regulations, electromagnetic field

(EMF) < 5 kV/m), wherein impacts

from EMF and safety standards and

operation safety have to be taken into

due account.

- Prior to operation, all safety

indicators shall be tested and accepted

by the project owner, contractor and

operation entity therefore workers

shall not be suffering from such EMF

impacts.

- In the phase of commissioning, the

safety in power use of households of

ethinic minorities who use electricity

for the first time also needs to be paid

attention to minimize the risk of

electric shock. However, this impact is

very little and avoidable if the people

are trained well in safe power use.

- The mitigation measures in Section VI

will also be implemented to minimise

safety risks

Since implementation of the subproject would mainly cause land acquisition, increased dust

generation, air pollution, and domestic wastes. However, these impacts are not significant,

temporary, and localized, and can be mitigated available mitigation measures. Therefore, the

subproject is assessed as B environmental category and eligible for funding by the World Bank.

Page 19: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 19

VI. ENVIRONMENTAL MANAGEMENT PLAN:

6.1. Mitigation measures:

The above impacts can be mitigated by: (a) ensuring that the application and supervision

of ECOP (Table 6.1) below; and (b) implementing site specific mitigation measures.

Table 6.1. Mitigation measures description as ECOP

Preriod Protential impact Mitigation measures Responsibility

Preparation

Permanent and

temporary land

acquisition will impact

affected households and

agriculture production

To plan for construction activities

after harvesting season and try to

shorten the progress.

Inform the affected HHs about

permanent and temporary land

acquisition.

Properly compensate for land

acquisition and tree compensation

in accordance with the

Resettlement Policy Framework

of the DEP project and

Resettlement Plan of the

subproject.

PMU

Contractor

Impacts on vegetation

cover as a result of site

clearance (ROW)

Minimize land clearing by

planning for installation of

transmission/distribution lines

above existing vegetation.

Utilize hand clearing of vegetation

if possible. Save as much

vegetation as possible. Careful

manage cutting trees. Cut only

tree above 4m within the ROW.

Do not burn cleared trees and

branches;

Carry out the safety procedures to

prevent hazard of downing trees.

Dispose at established dump site.

During clearing, contact with the

affected HHs in order to mitigate

impacts and carry out

compensation.

PMU

Contractor

Page 20: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 20

Preriod Protential impact Mitigation measures Responsibility

Temporary duty roads

Use roads/trails that are available.

Any new road cause minimum

damage to the local land usage.

Contractor

Construction

Surface water,

sediment and landslides

(Leveling)

The contractor will comply with

the water drainage system design

to prevent rain drop from causing

local inundation, soil erosion in

high risk areas.

To ensure proper operation of the

drainage system.

To sustain those areas not

impacted by construction

activities.

The excavation work needs to be

done in compliance with

applicable technical construction

regulations.

To prevent the spreading of mud

into surrounding environment,

take proper measures to control

sedimentation in high risk areas.

When there is a need to dry

construction site (foundation

concrete pouring), the pumped

water containing sand will be

controlled with regards to

sedimentation before discharging

it into outside water bodies.

Use diversion techniques at

construction to prevent deposit

from being stirred up in water

bodies.

Contractor

CSC

Dust generation

The contractor is responsible for

implementing the state applicable

regulations related to air quality.

The contractor will ensure minum

dust generation and no impact on

local residents and take proper

measures to control dust

generation (for example, praying

Contractor

CSC

Page 21: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 21

Preriod Protential impact Mitigation measures Responsibility

water, covering the trucks when

carrying material).

Material will be covered up

during. transportation to prevent

scattering of material along the

way.

Material dump site and storage

yards will be covered up and

isolated from winds and located

away from schools and residential

areas.

Workers will be provided with

masks when working in high risk

areas.

Air pollution

All transportation vehicles must

comply with applicable

regulations of Vietnam with

regards to exhaust gases.

Transportation vehicles in must be

tested frequently on the waste

gases and have to show certificate

of quality, technical safety and

environmental friendliness

according to Decision

No.35/2005/QD-BGTVT.

Do not burn waste or construction

materials at the site.

Contractor

CSC

Noise and vibration level

The contractor will be responsible

for complying with applicable

regulations related to permitted

noise and vibration levels.

All transportation vehicles need to

show certificate of quality,

technical safety and environmental

friendliness according to the

Decision No.35/2005/QD-

BGTVT; to prevent excessive

noise level from machinery that is

not properly maintained, proper

noise reduction measures are

taken, including noise reducers or

Contractor

CSC

Page 22: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 22

Preriod Protential impact Mitigation measures Responsibility

arrangement of noisy machinery

in a specific noise proof area.

To prevent or reduce traffic in

residential area as well as

processing of material in

residential areas (concrete mixing)

Waste water pollution

The contractor will be responsible

for complying with applicable

regulations related to waste water

treatment and discharge.

To provide mobile toilets or

construct proper toilets for

workers at the site. Toilet waste

water and restaurants will be

treated before discharging into the

outside environment.

When construction is completed,

toilets have to be properly

destroyed and/or removed.

Contractor

CSC

Material warehouse and

material quarry

management

Material storage yards will be

predetermined in the approved

engineering design.

Material supplied by local

suppliers need to have operation

licenses for particular material

type.

To rehabilitate material storage

yard after construction is

completed.

Contractor

CSC

Waste and hazardous

waste

Prior to construction, the

contractor needs to prepare a

procedure for controlling waste

(storage, use of recycle bins, site

decommissioning, etc.) and

strictly complying during

construction phase.

Prior to construction, all necessary

licenses have to be obtained

related to waste management.

Contractor

CSC

Page 23: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 23

Preriod Protential impact Mitigation measures Responsibility

Proper measures are taken to

ensure good practices in waste

management and treatment. The

contractor will provide recycle

bins, containers and other means

to collect waste from necessary

areas.

Waste can be stored temporarily at

the site when it is approved by the

Construction Monitoring

Consultant, local authorities

before collection and treatment. If

in the absence of such authorities,

normal domestic waste can be

land filled.

Recycle bins or containers storing

waste have to be covered up from

weather impacts and intrusion by

scavengers. Do not burn waste.

Recyclable waste such as wood

form, waste steel and packing

material will be collected and

separated at the site from other

waste sources for reuse, refilling

or sale to an external company.

If it is impossible to carry away

from the site, solid waste can be

land filled at a certain place

approved by the construction

supervising consultant provide in

the waste management plan.

Under any circumstance, the

contractor has to treat all

construction waste within the site.

Waste lubricants will be taken out

from the site by an authorized

recycling company.

Waste lubricants and cleaning

solutions will be collected into

covered containers and carried

away by a contracted external

company that is permitted to treat

Page 24: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 24

Preriod Protential impact Mitigation measures Responsibility

hazardous waste

Site clearance

The contractor will prepare a plan

on site clearance and vegetation

recovery according to applicable

regulations for the construction

supervising consultant to approve.

The contractor will strictly comply

with this plan.

Do not use chemicals in clearing

vegetation.

Do not cut down any trees when it

is not provided in the vegetation

clearance plan.

If necessary, set up temporary

fence to protect valuable trees

prior to starting any construction

activities.

Contractor

CSC

Impact on cultural

property

During construction phase if the

contractor finds any cultural and

historical sites, including

commentary or tombs, the

contractor will:

- Stop construction activities in

the particular area;

- Protect the area from any

damage or loss to the sites. In case

the historical objects can be

removed or sensitive objects

assign a person to protect it until

local authorities come to confirm

and take over the issue;

- Notify the construction

supervising consultant, who will

be responsible for informing local

authorities or the state agencies of

such cultural or historical sites

(within 24 hours or less);

- Local authorities or state

agencies will be responsible for

protecting and isolating such area

Contractor

CSC

PMU

Page 25: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 25

Preriod Protential impact Mitigation measures Responsibility

before any further processing.

Decide how to process such issues

is the responsibility of the local

authorities, including change, (in

case a cultural or historical site is

found and cannot be removed),

reservation, isolation,

rehabilitation and rescue;

If the cultural or historical site are

of high value and the reservation

is recommended by relevant

agencies the project owner will

have to change project design

accordingly for the component in

that particular area;

Decisions related to the

management of found sites will be

notified in writing to relevant

authorities;

Construction work will continue

only after relevant authorities

come and take responsibility of

potential sites.

Traffic management

Prior to construction, conduct

consultation with local authorities

and traffic police.

Impacts on traffic flow needs to be

considered in the construction

plan before approval. Traffic

routes, particularly those with

heavy duty vehicles need to

consider high risk area such as

schools, hospitals or markets.

It is necessary to provide

sufficient lighting system for night

time to ensure proper traffic

conditions.

Arrange indication signs at the

construction site to inform public

people, provide instructions to

different components and

Contractor

CSC

Page 26: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 26

Preriod Protential impact Mitigation measures Responsibility

instructions and safety directions.

Take proper traffic safety

measures including sign posts and

flags to indicate danger

Do not transport material during

peak house.

Space spared for walkers and

vehicles at the site need to be

separate from the site and can be

easily accessible. Provide proper

sing posts where necessary.

Cultural property

Apply settlement procedures if

accidentally discover during

in digging activities.

Contractor, PCs

Interruption of utility

and business services

Planned or unplanned

interruptions to services such as

water, gas power supply and

internet access: The contractor

will be prepared for emergency

scenarios and any potential

failures.

Cooperate with services suppliers

(water, telecommunications, etc.)

to work out a proper construction

schedule.

During the laying out of cables

crossing over telecommunications

cable, mitigation measures have to

be taken (What are the measures?)

Notify affected households of

construction schedule as well as

expected interruptions (at least 5

days in advance)

Interruptions to water supply for

agriculture production need to be

avoided.

The contractor will ensure

alternative water supply for

affected residents in case it is

Contractor

CSC

PMU

Page 27: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 27

Preriod Protential impact Mitigation measures Responsibility

more than one day.

Any damage to the existing

service cables will be notified to

the local authorities for timely

repair.

Rehabilitation of

affected areas

Clearance areas such as soil or

rock quarries, waste treatment

areas, worker houses, warehouse

and wood forms and any other

temporary areas during

construction phase will be

rehabilitated with regards to the

landscape and vegetation cover.

Compensate the vegetation cover

at the soonest. Use proper

vegetation for such rehabilitation.

Do not use exotic or banned

vegetation for such rehabilitation

Excavated hillsides and waste

yard need to be planted with grass

to prevent soil erosion and

landslide;

All the affected areas will be

compensated with proper

landscape and there should be no

delay in doing so, including any

necessary repair or construction of

green space and other affected

areas.

Soil contaminated with chemicals

or hazardous waste will be carried

away and land filled in a proper

hazardous dump site

Rehabilitate all affected roads and

bridges due to the project

construction

Contractor

CSC

Labor and public safety

The contractor will comply with

all applicable regulations related

to labor safety.

Contractor

CSC

Page 28: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 28

Preriod Protential impact Mitigation measures Responsibility

Prepare and implement action plan

in response to risk and emergency

cases.

Prepare emergency services right

at the site.

Provide training for workers on

labor safety requirements.

Ensure to provide protective

devices for workers, including

noise protection at high risk places

In destroying existing structures,

workers and community need to

be protected from falling objects

by taking proper protection

measures

Provide protective fences and

warnings of danger at the

construction site to indicate

danger to local resident.

The contractor will provide safety

measures such as installation of

fences, provision of warning signs

at high risk areas, including pole

foundation under construction to

prevent traffic accidents as well as

other risk to local residents.

Only allow trained workers to

install, maintain or repair

electrical equipment.

Cut off and do correct earthling

for the existing power line prior to

construction work.

Comply with labor safety

procedures when working at

height and with electrical

equipment

Communications to local

community

Sustain communications to local

authorities and community; the

contractor will work with local

Contractor

CSC

Page 29: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 29

Preriod Protential impact Mitigation measures Responsibility

authorities to agree on

construction schedule for sites

near sensitive areas or at sensitive

time (regional festivals).

Enhance relationship with local

community in order to obtain

necessary information about the

project activities in the region,

progress and performance;

Keep track of the community

concerns and information required

such as project progress;

Respond to community concerns

via telephones and documents in a

timely manner;

Notify local residents of

construction schedule, work

schedule, potential interruptions to

services and detour roads and

temporary buses, any destruction

or mine explosion schedule;

Provide technical data and

drawings for community,

particularly a scheme on

construction sites and EMP;

Provide notice boards at all sites

to provide information about the

site manager, environmental

officer, medical and safety officer,

with concrete contact details and

other information so that affected

people will be able to raise their

voice and concerns.

PMU

Operations

Health and safety for

workers and local

residents

Disseminate the information on

electricity safety regulations to the

users.

Comply Decree No.

106/2005/ND-CP dated 17 August

2005 of Goverment on protecting

grid; Decree No. 81/2009/ND-CP

dated 12 October 2009 of

NPC

Page 30: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 30

Preriod Protential impact Mitigation measures Responsibility

Goverment on protecting hight

voltage grid

Regular training for local

technicians and people on safety

issues.

Use warning signs, barriers (locks,

gates, iron barriers...) around

substation or tower to prevent

people reach danger equipment;

Putting warning signs, barriers on

the ground close to electricity wire

to prevent electric shock

Fire and explosion

Periodically inspect fire

prevention and fighting facilities.

Organize training on fire

prevention and fighting for

operation workers.

NPC

Transmisison line -

Mitigation measures

related to transmission

lines

Only allow workers who have

been trained and obtained

certificates on installation,

maintenance and repair of

electrical equipment

Cut off power and provide safe

earthling before construction on

the power line or where it is near

power line

Ensure operations related to power

line will be undertaken by trained

workers with strict compliance

with safety regulations. Qualified

or trained workers to operate

power lines need to able to:

Distinguish between online

and offline power lines from

other parts of the distribution

system

Determine voltage of online

power lines

NPC

Page 31: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 31

Preriod Protential impact Mitigation measures Responsibility

Understand safety distance for

each cable types

Ensure correct and sufficient

use of safety devices and other

safety procedures or other

online parts of the distribution

system

- Even when being trained,

workers will not contact any

online parts unless:

Workers have been safely

isolated from online parts via

gloves or other insulation

devices

Online parts have been safely

isolated from workers and

other parts or

Workers have been isolated

and safely insulated from

online objects

When operations and maintenance

request minimum distance,

provide trainings on safety

measures and safety devices for

individuals and other preventive

measures identified in the health

and safety compliance plan.

(Below is the recommended safety

distance for workers:

2-15 kV: 0.6 m

15.1-35kV: 0.71 m

72.6-121 kV: 1.01 m

Safety measures when

working at height

Preventive and control measures

include:

- Check the firmness of

structures before starting work

- Take anti-fall measures

NPC

Page 32: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 32

Preriod Protential impact Mitigation measures Responsibility

including climbing skills, use

of supporting devices and first

aid toolkit

- Install supporting and anti-fall

devices

- Safety bands will not be

smaller than 16 mm, two

layers, and durable strength.

Safety bands will be replaced

before any defect or crack is

detected or if is too old

- When working with tools at

height, workers will need an

additional safely band

(backup).

- Sign posts and other obstacles

need to be removed before

starting work

- Use standard tool bag to carry

tools and materials to the

height when working on

pillars

EMF impacts

- Prevent or minimize exposure

to EMF in the working

environment by developing

and implementing a EMF

safety program with the

following components:

- Determination of potential

exposure level

- Trainings for workers on how

to identify their exposure to

EMF and its impacts

- Determination of safe areas in

order to differentiate those

areas with higher EMF

impacts than the others where

EMF impacts are small

enough not to be provided

with mitigations and minimize

NPC

Page 33: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 33

Preriod Protential impact Mitigation measures Responsibility

exposure to high EMF impact

areas

- The exposure detector for

individuals will be installed to

give warning when exposure is

below the safety limit (for

example, 50%). Action plans

for mitigating impacts

includes taking turn to work in

high risk areas, and if

necessary being provided with

protective devices.

Table 6.2. Site specific mitigation measures

Preriod Protential impact Mitigation measures Responsibility

Page 34: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 34

Preriod Protential impact Mitigation measures Responsibility

Construction

Electricity cutting

off on the crossing

over line will

influence

production and

living activities in

the electricity

cutting- off area

The replaced sections fort he upgraded and

newly connection to existing routes will

cause loss of power to the people.

With rehabilitated line, the power

management unit will cut local electricity

during the day(when people go to work on the

fields) and the contractor will carry out

construction and rehabilitation of the line

segment and at the end of the day, grid should

be resumed for power supply for people to

use.

For newly construction routes, contractors

will be resumed grid after application.

However, the construction period for each

commune is short (about a month)so that

people can overcome

However, in oder to avoid electricity cutting-

off for a long time when the line crossing over

the information line; line 35; 22; 0,4 kV;

scaffoldings must be used.

Before the setting up of the scaffoldings, the

contractors should work directly with the

electricity control team of the commune and

the hamlet for permission to cut off electricity

during the setting up of scaffoldings and avoid

electricity cutting-off during peak time. The

electricity control team of the commune and

the hamlet will inform in advance the

electricity cutting-off time to the local people

to arrange their production plan and living.

After the setting-up of scaffoldings, electricity

should be supplied again to the line. Only

after that, line extending could be conducted.

Contractor

CSC

PMU

VII. ENVIRONMENTAL MONITORING PLAN

Table 7.1: Environmental monitoring plan is shown in the below table

Impact Monitored

parameter

Monitored

point

Monitoring

equipment

/method

Timing/

frequency of

monitoring

Responsibility

Page 35: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 35

Impact Monitored

parameter

Monitored

point

Monitoring

equipment

/method

Timing/

frequency of

monitoring

Responsibility

Construction phase

I.

Vegetation

cover

clearance or

cutting

down trees

-Clearance

technique

- Disposal of

cut-down trees.

- Along the

transmission

line

- In a

centralized

place for

processing.

Observation -From

beginning to

the last

moment.

-Contractor

-Construction

supervising

consultant

I I. Rural

roads in the

project

region

- All heavy

tonnage

vehicles on the

local roads

- Along the

roads

Observation

and

consultation

with local

residents.

-Weekly basis

when material

is transported

to the region.

- Four months.

- Contractor,

-Construction

supervising

consultant

III. Surface

water

quality,

sedimentati

on and

erosion

- Not excavate

while it is

raining

- Not clear

plants

completely

- Surface

water near

the site.

Observation -During and

after heavy

rain

-Contractor,

-Construction

supervising

consultant

IV. Dust

and air

pollution

- Dust

concentration

in material

storage area

- Cover for

material during

transportation

process

- Areas with

excavation

foils and

material

storage

Observation -In presence of

strong winds

-Contractor,

-Construction

supervising

consultant

V. Noise

level

- Noise by

machinery

- Local

resident

response to

noise from the

construction

process

- The line

section

running over

residental

area

Consultatio

n with local

residents

-During

activities that

may result in

high noise

level;

Complaints by

local residents

-Contractor,

-Construction

supervising

consultant

Page 36: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 36

Impact Monitored

parameter

Monitored

point

Monitoring

equipment

/method

Timing/

frequency of

monitoring

Responsibility

VI. The

culture and

history

monuments

- The effects of

noise

-At the

construction

places close

to culture and

history

monuments

Observing

the local

residents

-During

construction,

the activities

emanate noise

-Contractors

-Construction

monitoring

consultant

VII.

Sanitation

situation at

the

construction

site,

including

the hygiene

of workers’

camps

-Garbage,

waste water at

the

construction

site and

workers’ tents

- If he tents

have been

supplied clean

water and had

sanitary

latrines

-At the tents Observing -Every week,

when official

acceptance of

work

-Contractors

-Construction

monitoring

consultant

VII. Safety

of workers

and local

presidents

- Accidents

happen

- At the sites,

local areas

- Consult,

Record the

constructio

n log of the

contractor

-Contractors

-Construction

monitoring

consultant

Operation phase

I. Maintain

and protect

the ROW

The height of

plants along

the ROW

Along the

ROW, houses

and trees

Prune trees

and ensure a

safe

distance for

the ROW

One month/

time

North High

Voltage grid

Company

II. Danger

due to

danger

-The intact

situation of

poles,

insulators,

protecting

devices of the

station

- At the pole

of the line

route, the

position of

the station

- Observing

and

assessing

3months/

time

-North high

voltage grid

Company

Page 37: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 37

VIII. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING

a) During Detailed Design and Preparation of Bidding Contract Documents

During the detailed design and bidding invitation preparation, the project management unit

will be responsible for incorporate the EMP (mitigation measures, responsibilities of the

contractor) into the attached annexes in the bidding invitation and contract signed with the

contractor. Engineers taking charge of the detailed design will also refer to findings in the EIA

and EMP to ensure environmental issues will be looked at in the final design.

During the bidding invitation preparation and the contract, it is necessary to ensure the

contractor is fully informed of its responsibilities in implementing environmental mitigation

measures and its commitment to compliance.

b) During Construction Phase

PPMU will assign the Construction Supervising Consultant (CSC) and/or field engineer to

be responsible for supervision of safeguard performance of contractor on a daily basis. A generic

Terms of Reference (TOR) is provided in Annex 1. CSC and/or field engineers will carry out,

but not limited to, the following tasks:

- Before the commencement of the construction, confirm that all compensation for land and

facilities are provided and relocation and/or land acquisition/donation has been completed.

- Closely supervise the implementation of safeguard measures throughout the construction

period.

- Confirm the compliance with the EMP and inspect for any damages caused by the

contractor. If necessary, prepare a minutes to ask the contractor to compensate or

rehabilitate as provisions of the contract. Contractor safeguard performance will be

included in the subproject progress report.

Role and responsibilities of parties in implementing EMP are summarized in the below table:

Table 8.1. Responsibility for EMP Implementation

Role Responsibility Organization

- Project

owner

- Take final responsibility with regards to the

management and implementation of project including

environmental compliance environmental

performance.

-North

Electricity

Corporation

- Environme

ntal officer

- Indicate specific responsibility and provide contact

details.

Environmental

officer of

project

Page 38: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 38

Role Responsibility Organization

- Project

manageme

nt and

implement

ation entity

Responsible for cooperating and managing the

implementation of project including providing guidance

and implementing the EMP:

- Develop plan and implement EMP activities during

construction.

- Cooperate with relevant stakeholders with regards to

environmental performance.

- Conduct internal supervision and independent audit.

- Supervise and provide budget for monitoring

activities.

- Report environmental information to relevant

stakeholders.

PMU

- Project

operation

entity

- Operating the project including environmental

management and supervision during operation phase.

North High

Voltage Grid

Company

- Contractor

supervisor

- Support the PMU in supervising project operations

with regards to environmental impacts mitigation

according to measures described in the EMP and keep

in touch with local residents.

Construction

supervising

consultant

hired by the

PMU

- Contractor Constructing and complying with technical requirements of

the EMP, including:

- Taking mitigation measures to minimize negative

impacts as described in the EMP.

- Communicating with local residents and taking action

to prevent environmental and social interruptions in

the project region during construction.

- Ensuring at least one officer supervises compliance to

EMP during construction.

- Ensuring all construction activities are given

necessary approvals from relevant authorities.

- Ensuring workers and officers understand their

responsibilities and procedures in environmental

management.

- Reporting to the construction supervising consultant

Construction

supervising

consultant

hired by the

PMU

Page 39: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 39

Role Responsibility Organization

on difficulties and solutions.

- Reporting to local authorities and PMU and

cooperating with relevant agencies to address any

issues.

IX. REPORTING PROCEDURE

Responsibility and frequency of reporting on EMP implementation are shown in

the below table.

N

o.

Report by Submitted to Frequency of reporting

1 By contractor to project owner PMU Once prior to starting

construction afterwards

every one month.

2 Construction supervisor (cum

environmental monitor)

PMU Monthly

3 Community supervisor (if any) MPU If any complaint

4 PMU EVN Quarterly

5 EVN WB Biannually

Page 40: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 40

X. CAPACITY BUILDING FOR EMP IMPLEMENTATION

Table 10.1. Estimates of capacity building for implementing EMP

Training

content Trained staff

Trainee

quantity

Training

time

Training

organizing

agency

Cost

1 2 3 4 5 6

Training about

environmental

management

Staff responsible

for environmental

management of

NPC

Six mans

January,

2012

EVN

* Cost:

2,000,000VND per man x 6 mans = 12,000,000VND

Training about

mitigation,

environmental

monitor

Staff of district

power company

Twenty mans December,

2012 EVN NPC

* Document cost: 300,000VND per man

* Subsistence cost:

300,000VND per day x 2 days = 600,000VND

* Travelling cost for trainees:

50,000VND x 2 times = 100,000VND

* Supporting cost for training lecturer: 2,000,000VND x

4 mans = 8,000,000VND

Page 41: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 41

Training

content Trained staff

Trainee

quantity

Training

time

Training

organizing

agency

Cost

Total cost 26,700,000VND

Page 42: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 42

XI.ESTIMATED COST FOR IMPLEMENTING THE EMP

Table 11.1. Table of estimate cost

No. Activity Construction

Phase Operation Phase

Total

(VND)

1 Implement

Mitigation Measures

The costs are

covered in

Contract with

Construction

Contractors

The cost is covered in

production cost of NPC

2

Environmental

monitoring during

construction phase

by Construction

Supervisor

The costs are

covered in the

contract of hiring

monitoring

consultant

3 Capacity Building 26,700,000

Total cost 26,700,000

XII. PUBLIC CONSULTATION AND DISCLOSURE OF INFORMATION

12.1 Community consultation

Public consultation was conducted on April 4, 2012. All issues and concerns raised during the

consultation have been addressed and incorporated into the final draft of the EMP.

12.2 Disclosure of information

- The EMP Vietnamese will be disclosed at Bim Son town People's Committee for the

public, organizations are able to access. The abbreviated EMP will be disclosed at the ward

People's Committee.

- The EMP in English and Vietnamese will be sent to the Vietnam Development

Information Center at 63 Ly Thai To, Hanoi for information disclosure.

- The EMP in English will be sent to the InfoShop of the World Bank in Washington DC

to be disclosed.

Page 43: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 43

ANNEX 1

TOR for monitoring of emp implementation for construction supervising consultant

Background

The construction supervising consultant will deliver technical services (“Services”) to ensure

efficient implementation of the EMP for the project.

Scope of services:

Services provided by the supervising consultant will include reviewing and monitoring of

construction activities to ensure mitigation measures described in the EMP for the project are

correctly complied with and negative environmental impacts are minimized.

On behalf of the PMU, supervising consultant undertakes the following duties:

- Conduct frequent field inspection;

- Review the implementation of environmental protection measures described in the EMP and

contract documentation;

- Review the effectiveness of the mitigation measures and environmental performance of the

project;

- If necessary, validate the acceptability of construction methods with regards to environmental

compliance (for temporary and permanent items), relevant design plans and other submitted

documents. If necessary, the supervising consultant will seek for and recommend methods

with less environmental impacts with consultation with the design consultant and the PMU;

- Validate inspection results with regards to any non-conformance to environmental

performance and effectiveness of any countermeasures;

- Provide audit results for the leading engineer of the contractor in accordance with non-

conformance handling procedure described in the EMP;

- Direct the contractor to take corrective actions within a specific time period and exercise

additional monitoring if necessary, as per the requirements of the contract in case of non-

conformance and complaints;

- Direct the contractor to take actions to mitigate impacts and comply with the EMP in case

non-conformance is found;

- Direct the contractor to stop any activity resulting negative impacts and/or in case the

contractor does not fulfill requirements of the EMP, to take corrective actions.

- For contracts that need Site Environmental Management Plan (SEMP), the supervising

consultant will conduct a final review and approve all environmental plans at the site that

may affect environment. This work includes but not limited to: dredging areas, material

quarries and dumping areas and worker houses. The supervising consultant will review and

approve such SEMP submitted by the contractor. If such plans are found non-compliant to

Page 44: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 44

the EMP, EPC or RAP, the supervising consultant will work with the PMU and contractor

for a proper solution.

- Complaint handling: Complaints from local residents will be collected by site officer of the

contractor, which may include violations to noise level, dust concentration and traffic safety

requirements. The lead consultant of the contractor and the supervising consultant will

address and work out a final solution organizes all such complaints. The supervising

consultant will provide a list of these complaints and confirm they have been properly

handled by the contractor in the same way with issued identified during site inspection.

- Confirmation of monthly payment: The supervising consultant will confirm monthly

payment for environment related activities undertaken by the contractor.

- Report: The supervising consultant will make the following reports in English:

o Report twice a week on non-conformances

o Monthly summary report will include issues and findings from the reviewing and

monitoring of construction activities

o At the end of project, the supervising consultant will make a final summary report

on findings from their work, number of violations, and solutions, etc. as well as

provide consultancy and guidance on how to implement such duties in future.

Page 45: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 45

ANNEX 2

Report template for monitoring of EMP implementation

(Used for report by supervising consultant to PMU)

Project name:

Project location: Province: District:

Commune/Town:

Supervising consultant:......Full name Date of report:……………………

No. Parameter

Assessment of

comments by

supervising

consultant and

community

Comment/

Recommenda

tion

Construction phase

1 Water turbidity and soil erosion

2 Noise level at the site and nearby

residential area

3 Dust concentration

4 Solid waste and site cleaning after

construction

5 Conflict between workers and local

residents

6 Disease spreading

7 Hygiene condition and safety for workers

8 Local traffic interruption

9 Road damage

10 Safety measure application

11 Material management

12 Remained soil and rock management

13 Evidences about loss to biodiversity (if

any)

14 Evidences about loss to cultural and

historical sites

15 Other environmental issues (if any)

….

Operation phase

16 Transmission line lobby maintenance

17 1. Health and safety for operation

workers and local residents

Page 46: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 46

ANNEX 3

Report template for monitoring of EMP implementation

(Used for reports by contractor)

Project name:

Project location:

Contractor name:

Initial or monthly report:

Date of report:

No. Impact Mitigation

measure taken Comment

Construction phase

1 Surface water pollution

2 Noise and vibration level

3 Soil erosion

4 Air pollution

5 Impacts on agriculture land due to

temporary land acquisition

6 Local traffic interruptions

7 Existing road damage

8 Solid waste from excavation

9 Remained soil management

10 Environmental impacts by workers

11 Conflict between workers and local

residents

12 Disease spreading between workers

and local residents

13 Health and safety

14 …..

Reported by :

Title :

Address :

Telephone :

Page 47: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 47

ANNEX 4

Subproject area map

Page 48: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 48

ANNEX 5

Some pictures of project area

Page 49: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 49

ANNEX 6

Consultation minutes

Page 50: NORTH POWER CORPORATION ... · Environmental Management Plan NORTH POWER CORPORATION Electric Network Project Management Board ----- ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

Subproject: Jointing 110kV line at 220kV Bim Son substation

Environmental Management Plan 50

ANNEX 7

List of consulted peoples

No. Place Local authority representative Household

representative

1 Bac Son Ward

Chairman of Ward people’s Committee:

Mr. Phan Cong Truong

Chairman Fatherland Front Committee:

Mrs. Nguyen Thi Hue

Nguyen Van Manh

Tran Hoai Nam

Duong Thi Dung

Pham Duc Ninh

Phan Van Quoc

Vu Huu Duc

Nguyen Tat Dat

Ha Quang Thiet

Mai Van Lam

Vo Duy Thang