NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE...
Transcript of NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE...
![Page 1: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/1.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
NORTH BATTERY PARK CITYRESILIENCY PROJECT
ALL-AGENCY COORDINATION MEETING
November 22, 2019
![Page 2: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/2.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
NORTH BATTERY PARK CITY
![Page 3: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/3.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 3
1. INTRODUCTIONS
2. PROJECT OVERVIEW
3. AGENCY COLLABORATION + DISCUSSION
4. NEXT STEPS
AGENDA
![Page 4: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/4.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
NBPC CONSULTANT TEAM
4
![Page 5: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/5.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
KEY TEAM MEMBERS
5
Susan Bemis, AICPPublic Realm Design
Lead
Nora MadonickCommunity
Engagement
Mark Foster, PEEngineering Lead
Mike Seering, PEFEMA Certification
Wael Youssef, PEStructural Engineering
Andrea Rosenthal, EIT, ENV-SPEnvironmental Lead
Teresa GonzalezPartner and Stakeholder
Engagement
Ibrahim Abdul-MatinPartner and Stakeholder
Engagement
Helder De Almeida, PEHydrological Team Lead
Samara DalyPartner and Stakeholder
Engagement
Garrett Avery, ASLAProject Manager
Alim Baycora, PE, LEED APProject Executive
Serena De StefanoDeputy Project Manager
![Page 6: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/6.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 6
PROJECT OVERVIEW
![Page 7: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/7.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
RESILIENCY MEASURES | BATTERY PARK CITY
7
NORTH BATTERY PARK CITY RESILIENCY
SOUTH BATTERY PARK CITY RESILIENCY
WEST BATTERY PARK CITY RESILIENCY
BCP BALLFIELDS RESILIENCY
2050s 100-YR FLOODPLAIN
![Page 8: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/8.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
PROJECT STUDY AREA
8
NORTH BATTERY PARK CITY RESILIENCY
2050s 100-YR FLOODPLAIN
![Page 9: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/9.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
PROJECT SCOPE
9
• Conceptual design through construction documentation
• Integrate resiliency measures to improve risk-reduction for BPCA and City of New York
• Community, Partner, and Stakeholder Engagement
• Collaboratively develop long-term Operations & Maintenance Plans
• Achieve FEMA certification/accreditation
![Page 10: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/10.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 11
CONCEPTUAL ALIGNMENT DEVELOPMENT
![Page 11: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/11.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 12
TOPOGRAPHY | LOW POINT
*TOPO TO BE VERIFIED BY SURVEY
+9’
+18’
+8’
+8’
+8’
+9’
+10’
+7’
2050s 100-YR FLOODPLAIN
+14’
+17’
![Page 12: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/12.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
POTENTIAL PROJECT STAKEHOLDERS
13
STUYVESANT HIGH SCHOOL
NYC PARKS
BMCC
NYCDOT
HUDSON RIVER PARK TRUST
TRIBECA POINTE CONDOMINIUMS
2050s 100-YR FLOODPLAIN
NYSDOT
NYCDOT
![Page 13: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/13.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 14
POTENTIAL DESIGN ZONES
PEDESTRIAN AREAS
ROUTE 9A
WEST BATTERY PARK CITY RESILIENCY
STREETS
![Page 14: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/14.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
CONCEPTUAL ALIGNMENTS | EVALUATION OPTIONS
15
NORTH ESPLANADE
2050s 100-YR FLOODPLAIN
CHAMBERS STREET
HARRISON STREET
N. MOORE STREET
![Page 15: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/15.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 16
NORTH ESPLANADE
![Page 16: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/16.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 17
NORTH ESPLANADE | PROPOSED ALIGNMENT OPTIONS
![Page 17: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/17.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 18
NORTH ESPLANADE | STUDY CONDITIONS
RELIEVING PLATFORM
• Relieving platform below structural sidewalk and structural column-supported stairwells / ramp system
• Existing Seawall flush with adjacent sidewalk; existing railing with columns spaced approx. every 50’
• Option 1 – Convert relieving platform to bulkhead; elevate existing seawall and meet DFE with
vertical deployable.
• Option 2 – Retrofit existing structures (Stuyvesant High School and Tribeca Pointe
Condominium) to act as flood barrier; structurally reinforcing foundation and architectural
walls, openings (windows/doors/vents), wet-proofing basements to manage hydrostatic uplift
![Page 18: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/18.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 19
ROUTE 9A
![Page 19: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/19.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 20
ROUTE 9A | PROPOSED CONDITIONS | OPTION 1-2
WEST BPC RESILIENCY
2050s 100-YR FLOODPLAIN
ROUTE 9A / CROSSINGS
![Page 20: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/20.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
Deployable flip-up gates become Bikeway surface;
intermittent fixed wall segments where needed
21
ROUTE 9A | PROPOSED CONDITIONS | OPTION 1• Length from North Esplanade: +380 ft // Wall Height: 6’ // Width: 9’ // Gates: 8
• Likely least permanent visual impact along this segment
• Concern for significant utility conflicts, including relocations, increased separation
distances, potential loss of street trees along West Street and some located within
HRPK due to FEMA requirements
ALIGNMENT OPTIONS
FIXED WALLDEPLOYABLE
![Page 21: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/21.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 22
ROUTE 9A | PROPOSED CONDITIONS | OPTION 2
Fixed wall along east edge of Bikeway; DFE met
using vertical deployable stowed within wall
• Length from North Esplanade: +380 ft // Wall Height: 5’ // Width: 42” // Gates: 2
• Second least permanent visual impact along this segment
• Concern for significant utility conflicts, including relocations, increased separation
distances and loss of street trees along West Street due to FEMA
requirements
ALIGNMENT OPTIONS
FIXED WALLDEPLOYABLE
![Page 22: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/22.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 23
ROUTE 9A | PROPOSED CONDITIONS | OPTION 3
Fixed wall along NYS DOT right-of-way / parallel to
BMCC building façade
• Length: +365 ft // Wall Height: 3’-8’ // Width: 18” // Gates: 3
• Minimizes Potential Visual Impact to pedestrians, cyclists and vehicular viewers along
Hudson River; minimizes disruption to HRPK, provides opportunity for artist
collaboration / public art integration
• Concerns for Interference with BMCC Façade (egress, windows, venting); existing
utilities; minimal wave overtopping distance between wall and building façade; loss of
street trees along West Street due to FEMA requirements
• Would require Easement and long-term O&M coordination with DASNY / CUNY / BMCC
ALIGNMENT OPTIONS
FIXED WALLDEPLOYABLE
![Page 23: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/23.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 24
ROUTE 9A CROSSING | MULTIPLE LOCATIONS
FLIP-UP GATES
• Average Length: +160 ft // Wall Height: 8-9’ // Depth: 5’ // Gates: 3-4
• Deployable flip-up gates across Bikeway, Route 9A, with intermittent fixed wall segments
• Concern for significant utility conflicts, including relocations, increased separation distances,
operational design requirements per NYSDOT, NYCDOT, NYCDEP, OEM/DHS/JTT, etc.
ALIGNMENT OPTIONS
FIXED WALLDEPLOYABLE
![Page 24: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/24.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 25
N. MOORE STREET
![Page 25: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/25.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 26
N. MOORE STREET
N MOORE STREET ALTERNATIVE
WEST BATTERY PARK CITY RESILIENCY
2050s 100-YR FLOODPLAIN
![Page 26: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/26.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 27
N. MOORE STREET | PROPOSED CONDITIONS
FIXED WALLDEPLOYABLE
Fixed wall of variable height with deployables at
driveways, loading docks, and local street crossings• Length from Harrison: +1150 ft // Wall Height: 8’ to 6” // Width between 18”-24” // Gates: 4-6
• Deployable flip-up or roller gates at driveways, loading docks, local street crossings to reduce
deployment time and minimize coordination (storage, staffing, etc.)
• Located at back of sidewalk (NYSDOT right-of-way) along Route 9A; located along existing southern
curb line on N. Moore Street to minimize significant utility/vault conflicts; curb re-established 2’-4’ north
of existing in current parking lane
• Concern for proximity to segment of BMCC North façade; alignment parallel to utilities/ConEd steam
service; length of segment east of Greenwich into Historic District ; loss of street trees along alignment
PROPOSED ALIGNMENT
![Page 27: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/27.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 28
HARRISON STREET
![Page 28: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/28.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 29
HARRISON STREET
HARRISON STREET ALTERNATIVE
WEST BATTERY PARK CITY RESILIENCY
2050s 100-YR FLOODPLAIN
![Page 29: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/29.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 30
HARRISON STREET | PROPOSED CONDITIONS | OPTION 1
FIXED WALL
DEPLOYABLE
• Length from Route 9A: 500 ft // Wall Height: 8’ to 6” // Width between 18”-24” // Gates: 3-4
• Deployable flip-up gates at openings and crossings to reduce deployment time and minimize
coordination (storage, staffing, etc.)
• Located along street tree/parkway zone to minimize conflict with street and sidewalk operations
• Possible regrading of the intersection at Greenwich St. to avoid closure/crossing
• Concern for potential visual impact, construction (noise/vibration) impacts to Historic/Landmark
Properties, proximity to BMCC façade, and loss of street trees per FEMA requirements
Fixed wall with variable height with deployables at
openings and crossings
PROPOSED ALIGNMENT
![Page 30: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/30.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 31
HARRISON STREET | PROPOSED CONDITIONS | OPTION 2
FIXED WALL
DEPLOYABLE
• Length from Route 9A: 500 ft // Wall Height: 8’ to 6” // Width between 18”-24” // Gates: 3-4
• Deployable flip-up gates at openings and crossings to reduce deployment time and minimize
coordination (storage, staffing, etc.)
• Located along street tree/parkway zone to minimize conflict with street and sidewalk operations
• Possible regrading of the intersection at Greenwich St. to avoid closure/crossing
• Concern for potential visual impact, construction (noise/vibration) impacts to BMCC, and loss of street
trees per FEMA requirements
Fixed wall with variable height with deployables at
openings and crossings
![Page 31: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/31.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 32
CHAMBERS STREET
![Page 32: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/32.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 33
CHAMBERS STREET
CHAMBERS STREET ALTERNATIVE
WEST BATTERY PARK CITY RESILIENCY
2050s 100-YR FLOODPLAIN
![Page 33: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/33.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 34
CHAMBERS STREET | PROPOSED CONDITIONS
FIXED WALL
DEPLOYABLE
![Page 34: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/34.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 35
AGENCY COLLABORATION
![Page 35: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/35.jpg)
DRAFT FOR INTERNAL REVIEW ONLY 36
Although the alignment has not been determined, West Street (9A) must be crossed and a City sidewalk/street must be altered. Existing configuration of utilities and roadway elements are generally similar in all locations.
Configuration of proposed elements is also anticipated to be largely similar regardless of location.
Given strong typologies, our goal is to expeditiously initiate technical coordination of the following:
• Detailed Existing Conditions
• Operational Requirements
• Utility Relocations / Utilities to be Protected-in-Place
• Conduit/pipe resiliency measures
• Grading and Affected Streetscape Elements
AGENCY COLLABORATION
![Page 36: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/36.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
NEXT STEPS
37
• Direct technical coordination and additional data requests
• Continued site investigations: detailed utilities survey and geotechnical borings
• Integrated Coastal and Interior Drainage Modeling refinement
• Continued design development of flood alignment
• January 2020: Community Meeting #2 – Alignment Evaluation + Preliminary Design Concepts
![Page 37: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:](https://reader034.fdocuments.in/reader034/viewer/2022050605/5faceec0f08633304b239ed4/html5/thumbnails/37.jpg)
DRAFT FOR INTERNAL REVIEW ONLY
QUESTIONS + COMMENTS?
38