NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE...

37
DRAFT FOR INTERNAL REVIEW ONLY NORTH BATTERY PARK CITY RESILIENCY PROJECT ALL-AGENCY COORDINATION MEETING November 22, 2019

Transcript of NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE...

Page 1: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

NORTH BATTERY PARK CITYRESILIENCY PROJECT

ALL-AGENCY COORDINATION MEETING

November 22, 2019

Page 2: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

NORTH BATTERY PARK CITY

Page 3: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 3

1. INTRODUCTIONS

2. PROJECT OVERVIEW

3. AGENCY COLLABORATION + DISCUSSION

4. NEXT STEPS

AGENDA

Page 4: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

NBPC CONSULTANT TEAM

4

Page 5: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

KEY TEAM MEMBERS

5

Susan Bemis, AICPPublic Realm Design

Lead

Nora MadonickCommunity

Engagement

Mark Foster, PEEngineering Lead

Mike Seering, PEFEMA Certification

Wael Youssef, PEStructural Engineering

Andrea Rosenthal, EIT, ENV-SPEnvironmental Lead

Teresa GonzalezPartner and Stakeholder

Engagement

Ibrahim Abdul-MatinPartner and Stakeholder

Engagement

Helder De Almeida, PEHydrological Team Lead

Samara DalyPartner and Stakeholder

Engagement

Garrett Avery, ASLAProject Manager

Alim Baycora, PE, LEED APProject Executive

Serena De StefanoDeputy Project Manager

Page 6: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 6

PROJECT OVERVIEW

Page 7: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

RESILIENCY MEASURES | BATTERY PARK CITY

7

NORTH BATTERY PARK CITY RESILIENCY

SOUTH BATTERY PARK CITY RESILIENCY

WEST BATTERY PARK CITY RESILIENCY

BCP BALLFIELDS RESILIENCY

2050s 100-YR FLOODPLAIN

Page 8: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

PROJECT STUDY AREA

8

NORTH BATTERY PARK CITY RESILIENCY

2050s 100-YR FLOODPLAIN

Page 9: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

PROJECT SCOPE

9

• Conceptual design through construction documentation

• Integrate resiliency measures to improve risk-reduction for BPCA and City of New York

• Community, Partner, and Stakeholder Engagement

• Collaboratively develop long-term Operations & Maintenance Plans

• Achieve FEMA certification/accreditation

Page 10: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 11

CONCEPTUAL ALIGNMENT DEVELOPMENT

Page 11: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 12

TOPOGRAPHY | LOW POINT

*TOPO TO BE VERIFIED BY SURVEY

+9’

+18’

+8’

+8’

+8’

+9’

+10’

+7’

2050s 100-YR FLOODPLAIN

+14’

+17’

Page 12: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

POTENTIAL PROJECT STAKEHOLDERS

13

STUYVESANT HIGH SCHOOL

NYC PARKS

BMCC

NYCDOT

HUDSON RIVER PARK TRUST

TRIBECA POINTE CONDOMINIUMS

2050s 100-YR FLOODPLAIN

NYSDOT

NYCDOT

Page 13: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 14

POTENTIAL DESIGN ZONES

PEDESTRIAN AREAS

ROUTE 9A

WEST BATTERY PARK CITY RESILIENCY

STREETS

Page 14: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

CONCEPTUAL ALIGNMENTS | EVALUATION OPTIONS

15

NORTH ESPLANADE

2050s 100-YR FLOODPLAIN

CHAMBERS STREET

HARRISON STREET

N. MOORE STREET

Page 15: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 16

NORTH ESPLANADE

Page 16: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 17

NORTH ESPLANADE | PROPOSED ALIGNMENT OPTIONS

Page 17: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 18

NORTH ESPLANADE | STUDY CONDITIONS

RELIEVING PLATFORM

• Relieving platform below structural sidewalk and structural column-supported stairwells / ramp system

• Existing Seawall flush with adjacent sidewalk; existing railing with columns spaced approx. every 50’

• Option 1 – Convert relieving platform to bulkhead; elevate existing seawall and meet DFE with

vertical deployable.

• Option 2 – Retrofit existing structures (Stuyvesant High School and Tribeca Pointe

Condominium) to act as flood barrier; structurally reinforcing foundation and architectural

walls, openings (windows/doors/vents), wet-proofing basements to manage hydrostatic uplift

Page 18: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 19

ROUTE 9A

Page 19: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 20

ROUTE 9A | PROPOSED CONDITIONS | OPTION 1-2

WEST BPC RESILIENCY

2050s 100-YR FLOODPLAIN

ROUTE 9A / CROSSINGS

Page 20: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

Deployable flip-up gates become Bikeway surface;

intermittent fixed wall segments where needed

21

ROUTE 9A | PROPOSED CONDITIONS | OPTION 1• Length from North Esplanade: +380 ft // Wall Height: 6’ // Width: 9’ // Gates: 8

• Likely least permanent visual impact along this segment

• Concern for significant utility conflicts, including relocations, increased separation

distances, potential loss of street trees along West Street and some located within

HRPK due to FEMA requirements

ALIGNMENT OPTIONS

FIXED WALLDEPLOYABLE

Page 21: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 22

ROUTE 9A | PROPOSED CONDITIONS | OPTION 2

Fixed wall along east edge of Bikeway; DFE met

using vertical deployable stowed within wall

• Length from North Esplanade: +380 ft // Wall Height: 5’ // Width: 42” // Gates: 2

• Second least permanent visual impact along this segment

• Concern for significant utility conflicts, including relocations, increased separation

distances and loss of street trees along West Street due to FEMA

requirements

ALIGNMENT OPTIONS

FIXED WALLDEPLOYABLE

Page 22: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 23

ROUTE 9A | PROPOSED CONDITIONS | OPTION 3

Fixed wall along NYS DOT right-of-way / parallel to

BMCC building façade

• Length: +365 ft // Wall Height: 3’-8’ // Width: 18” // Gates: 3

• Minimizes Potential Visual Impact to pedestrians, cyclists and vehicular viewers along

Hudson River; minimizes disruption to HRPK, provides opportunity for artist

collaboration / public art integration

• Concerns for Interference with BMCC Façade (egress, windows, venting); existing

utilities; minimal wave overtopping distance between wall and building façade; loss of

street trees along West Street due to FEMA requirements

• Would require Easement and long-term O&M coordination with DASNY / CUNY / BMCC

ALIGNMENT OPTIONS

FIXED WALLDEPLOYABLE

Page 23: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 24

ROUTE 9A CROSSING | MULTIPLE LOCATIONS

FLIP-UP GATES

• Average Length: +160 ft // Wall Height: 8-9’ // Depth: 5’ // Gates: 3-4

• Deployable flip-up gates across Bikeway, Route 9A, with intermittent fixed wall segments

• Concern for significant utility conflicts, including relocations, increased separation distances,

operational design requirements per NYSDOT, NYCDOT, NYCDEP, OEM/DHS/JTT, etc.

ALIGNMENT OPTIONS

FIXED WALLDEPLOYABLE

Page 24: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 25

N. MOORE STREET

Page 25: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 26

N. MOORE STREET

N MOORE STREET ALTERNATIVE

WEST BATTERY PARK CITY RESILIENCY

2050s 100-YR FLOODPLAIN

Page 26: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 27

N. MOORE STREET | PROPOSED CONDITIONS

FIXED WALLDEPLOYABLE

Fixed wall of variable height with deployables at

driveways, loading docks, and local street crossings• Length from Harrison: +1150 ft // Wall Height: 8’ to 6” // Width between 18”-24” // Gates: 4-6

• Deployable flip-up or roller gates at driveways, loading docks, local street crossings to reduce

deployment time and minimize coordination (storage, staffing, etc.)

• Located at back of sidewalk (NYSDOT right-of-way) along Route 9A; located along existing southern

curb line on N. Moore Street to minimize significant utility/vault conflicts; curb re-established 2’-4’ north

of existing in current parking lane

• Concern for proximity to segment of BMCC North façade; alignment parallel to utilities/ConEd steam

service; length of segment east of Greenwich into Historic District ; loss of street trees along alignment

PROPOSED ALIGNMENT

Page 27: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 28

HARRISON STREET

Page 28: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 29

HARRISON STREET

HARRISON STREET ALTERNATIVE

WEST BATTERY PARK CITY RESILIENCY

2050s 100-YR FLOODPLAIN

Page 29: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 30

HARRISON STREET | PROPOSED CONDITIONS | OPTION 1

FIXED WALL

DEPLOYABLE

• Length from Route 9A: 500 ft // Wall Height: 8’ to 6” // Width between 18”-24” // Gates: 3-4

• Deployable flip-up gates at openings and crossings to reduce deployment time and minimize

coordination (storage, staffing, etc.)

• Located along street tree/parkway zone to minimize conflict with street and sidewalk operations

• Possible regrading of the intersection at Greenwich St. to avoid closure/crossing

• Concern for potential visual impact, construction (noise/vibration) impacts to Historic/Landmark

Properties, proximity to BMCC façade, and loss of street trees per FEMA requirements

Fixed wall with variable height with deployables at

openings and crossings

PROPOSED ALIGNMENT

Page 30: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 31

HARRISON STREET | PROPOSED CONDITIONS | OPTION 2

FIXED WALL

DEPLOYABLE

• Length from Route 9A: 500 ft // Wall Height: 8’ to 6” // Width between 18”-24” // Gates: 3-4

• Deployable flip-up gates at openings and crossings to reduce deployment time and minimize

coordination (storage, staffing, etc.)

• Located along street tree/parkway zone to minimize conflict with street and sidewalk operations

• Possible regrading of the intersection at Greenwich St. to avoid closure/crossing

• Concern for potential visual impact, construction (noise/vibration) impacts to BMCC, and loss of street

trees per FEMA requirements

Fixed wall with variable height with deployables at

openings and crossings

Page 31: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 32

CHAMBERS STREET

Page 32: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 33

CHAMBERS STREET

CHAMBERS STREET ALTERNATIVE

WEST BATTERY PARK CITY RESILIENCY

2050s 100-YR FLOODPLAIN

Page 33: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 34

CHAMBERS STREET | PROPOSED CONDITIONS

FIXED WALL

DEPLOYABLE

Page 34: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 35

AGENCY COLLABORATION

Page 35: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY 36

Although the alignment has not been determined, West Street (9A) must be crossed and a City sidewalk/street must be altered. Existing configuration of utilities and roadway elements are generally similar in all locations.

Configuration of proposed elements is also anticipated to be largely similar regardless of location.

Given strong typologies, our goal is to expeditiously initiate technical coordination of the following:

• Detailed Existing Conditions

• Operational Requirements

• Utility Relocations / Utilities to be Protected-in-Place

• Conduit/pipe resiliency measures

• Grading and Affected Streetscape Elements

AGENCY COLLABORATION

Page 36: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

NEXT STEPS

37

• Direct technical coordination and additional data requests

• Continued site investigations: detailed utilities survey and geotechnical borings

• Integrated Coastal and Interior Drainage Modeling refinement

• Continued design development of flood alignment

• January 2020: Community Meeting #2 – Alignment Evaluation + Preliminary Design Concepts

Page 37: NORTH BATTERY PARK CITY RESILIENCY PROJECT · OPTION 2. Fixed wall along east edge of Bikeway; DFE met using vertical deployable stowed within wall • Length from North Esplanade:

DRAFT FOR INTERNAL REVIEW ONLY

QUESTIONS + COMMENTS?

38