Noise and Vibration assessment

43
Appendix J Noise and vibration assessment Snowy 2.0 Transmission Connection Project Environmental Impact Assessment ( February 2021)

Transcript of Noise and Vibration assessment

Page 1: Noise and Vibration assessment

Appendix J Noise and vibration assessment Snowy 2.0 Transmission Connection Project Environmental Impact Assessment

( February 2021)

Page 2: Noise and Vibration assessment

Snowy 2.0 Transmission Connection Project

Noise and Vibration assessment

Rev 5

December 2020

TransGrid Limited

Client Reference

Noise and Vibration assessment TransGrid Limited

Page 3: Noise and Vibration assessment

Noise and Vibration assessment

ii

Contents Executive Summary ............................................................................................................................................................. v

1. Introduction ............................................................................................................................................................ 1

1.1 Overview ................................................................................................................................................................................ 1

1.2 Purpose of this report ....................................................................................................................................................... 1

2. Project description ................................................................................................................................................. 2

2.1 Project components .......................................................................................................................................................... 2

2.2 Project location ................................................................................................................................................................... 2

2.3 Project area .......................................................................................................................................................................... 3

2.4 Construction activities ...................................................................................................................................................... 6

2.4.1 Construction staging and timing .................................................................................................................................. 8

2.4.2 Construction working hours ........................................................................................................................................... 9

2.4.3 Construction traffic movements ................................................................................................................................... 9

2.4.3.1 Primary construction transport routes ....................................................................................................................... 9

2.5 Operation and maintenance ........................................................................................................................................ 10

2.6 Primary noise and vibration-related risks ................................................................................................................ 10

3. Existing environment ......................................................................................................................................... 11

3.1 Surrounding sensitive receivers .................................................................................................................................. 11

3.2 Meteorology ...................................................................................................................................................................... 13

3.3 Background noise levels ................................................................................................................................................ 13

4. Policy setting and criteria ................................................................................................................................. 15

4.1 Construction noise ........................................................................................................................................................... 15

4.1.1 Noise management levels ............................................................................................................................................. 15

4.1.2 Construction traffic noise impacts ............................................................................................................................. 16

4.1.3 Sleep disturbance during construction .................................................................................................................... 16

4.2 Operational noise ............................................................................................................................................................. 17

4.2.1 Overview .............................................................................................................................................................................. 17

4.2.2 Intrusiveness noise level ................................................................................................................................................ 17

4.2.3 Amenity noise level ......................................................................................................................................................... 17

4.2.4 Project operational noise criteria ............................................................................................................................... 18

4.2.5 Sleep disturbance during operations ........................................................................................................................ 18

4.3 Vibration .............................................................................................................................................................................. 18

4.3.1 Overview .............................................................................................................................................................................. 18

4.3.2 Human comfort ................................................................................................................................................................ 18

4.3.3 Buildings and structures ................................................................................................................................................ 20

4.3.4 Construction Noise and Vibration Guideline .......................................................................................................... 20

4.4 Blasting ................................................................................................................................................................................ 21

4.5 Other policy considerations .......................................................................................................................................... 21

5. Estimation of emissions .................................................................................................................................... 22

Page 4: Noise and Vibration assessment

Noise and Vibration assessment

iii

5.1 Noise emissions during construction ........................................................................................................................ 22

5.2 Noise emissions during construction blasting activities ..................................................................................... 24

5.3 Noise emissions during operation .............................................................................................................................. 25

5.4 Vibration-generating plant and equipment ........................................................................................................... 25

5.5 Cumulative impacts ......................................................................................................................................................... 26

6. Assessment of impacts ...................................................................................................................................... 27

6.1 Assessment approach .................................................................................................................................................... 27

6.2 Predicted construction noise impacts ....................................................................................................................... 27

6.3 Predicted construction traffic noise impacts .......................................................................................................... 29

6.4 Predicted construction vibration impacts ................................................................................................................ 29

6.5 Predicted construction blasting impacts ................................................................................................................. 29

6.6 Predicted operation noise impacts ............................................................................................................................ 30

6.6.1 Substation........................................................................................................................................................................... 30

6.6.2 Transmission line ............................................................................................................................................................. 31

6.7 Predicted cumulative impacts ..................................................................................................................................... 31

7. Mitigation and management ........................................................................................................................... 32

8. Conclusion ............................................................................................................................................................ 33

9. References ............................................................................................................................................................ 34

List of figures Figure 2-1: Project location .................................................................................................................................................................... 4 Figure 2-2: Project overview................................................................................................................................................................... 5 Figure 2-3: Indicative timing for the construction of key project components ................................................................. 9 Figure 3-1: Sensitive receivers ............................................................................................................................................................ 12 Figure 6-1: Estimated effective mass charges to minimise annoyance .............................................................................. 30

List of tables Table 1-1: Secretary’s environmental assessment requirements – Noise and vibration ............................................... 1 Table 2-1: Project construction overview .......................................................................................................................................... 6 Table 2-2: Indicative timing for the construction of key project components ................................................................... 8 Table 2-3: Estimated project-related vehicle movements during construction ................................................................ 9 Table 3-1: Nearby noise sensitive receivers ................................................................................................................................... 11 Table 3-2: Non-Aboriginal heritage items identified within the project area .................................................................. 11 Table 3-3: EIS background noise monitoring results summary (EMM, 2019) .................................................................. 13 Table 3-4: Adopted background noise levels dB(A) ................................................................................................................... 14 Table 4-1: ICNG guidance for establishing construction NMLs at residential receivers ............................................... 15 Table 4-2: ICNG NMLs for residential receivers ............................................................................................................................ 16 Table 4-3: ICNG NMLs for non-residential receivers .................................................................................................................. 16 Table 4-4: NPI intrusiveness noise levels ........................................................................................................................................ 17 Table 4-5: NPI amenity noise criteria, residential receivers .................................................................................................... 17 Table 4-6: NPI amenity noise criteria, other receivers ............................................................................................................... 18 Table 4-7: Project operational noise criteria ................................................................................................................................. 18 Table 4-8: Preferred and maximum weighted root mean squared (rms) values for continuous and impulsive vibration acceleration (m/s2) 1-80 Hz ............................................................................................................................................. 19 Table 4-9: Preferred and maximum VDVs for intermittent vibration (ms-1.75), (DECC, 2006) .................................. 19

Page 5: Noise and Vibration assessment

Noise and Vibration assessment

iv

Table 4-10: Transient vibration guideline values for cosmetic damage ............................................................................ 20 Table 4-11: Recommended safe setback distances .................................................................................................................... 20 Table 4-12: Airblast overpressure criteria ...................................................................................................................................... 21 Table 4-13: Peak particle velocity criteria ...................................................................................................................................... 21 Table 5-1: Construction stages and equipment sound power levels ................................................................................... 22 Table 5-2: Noise emissions inventory, operations ...................................................................................................................... 25 Table 5-3: Recommended safe working distances for vibration intensive plant ............................................................ 26 Table 6-1: Construction noise assessment details ...................................................................................................................... 27 Table 6-2: Predicted worst-case Leq 15 min dB(A) noise levels, construction ....................................................................... 28 Table 6-3: Predicted construction traffic noise impacts ........................................................................................................... 29 Table 6-4: Predicted operational noise levels, substation ....................................................................................................... 30 Table 6-5: Worst-case cumulative construction noise review ................................................................................................. 31 Table 7-1: Proposed construction noise management, standard measures ..................................................................... 32 Table 7-2: Proposed vibration management, standard measures ........................................................................................ 32 Table 7-3: Proposed vibration management, additional measures ..................................................................................... 32

Page 6: Noise and Vibration assessment

Noise and Vibration assessment

v

Executive Summary

Background

TransGrid is seeking approval under Part 5 Division 5.2 of the NSW Environmental Planning and Assessment Act 1979 (EP&A Act) for the construction and operation of a transmission line connection and substation to enable the grid connection of the Snowy 2.0 pumped hydro generation project. As part of the Environmental Impact Statement (EIS) being prepared for the project, an assessment was completed in accordance with the “Interim Construction Noise Guideline” (ICNG) (Department of Environment and Climate Change [DECC], 2009), the “Noise Policy for Industry” (NPI) (NSW Environment Protection Authority, 2017), Assessing Vibration: a technical guideline (NSW Department of Environment and Conservation [DEC], 2006) and other relevant State, National and International policies and guidelines to identify and evaluate the potential for noise and vibration-related impacts during the construction and operation of the project.

Key features of the existing environment

A review of available information was completed to characterise key features of the existing environment. Aerial imagery was reviewed to identify sensitive receivers around the project. Nearby heritage structures that can be more sensitive to vibration were identified by reviewing the Snowy 2.0 Transmission Connection Project Non-Aboriginal Heritage Assessment (Jacobs, 2020) prepared for the project. Noting that certain meteorological conditions can enhance the propagation of noise, information presented in Appendix R: Noise and Vibration Impact Assessment Snowy 2.0 Main Works’, (EMM, 2019) were reviewed which identified that noise-enhancing meteorological effects required consideration as part of the assessment. Background noise levels established in Appendix R: Noise and Vibration Impact Assessment Snowy 2.0 Main Works’, (EMM, 2019) were also reviewed to confirm the suitability of adopting the minimum rating background levels (RBLs) from the NPI.

Estimation of emissions

Construction staging and operational noise emissions information provided by TransGrid were used to develop emissions inventories. Reference sound power levels (SWLs) from various standards and guidelines were used to estimate overall noise emissions from different phases of construction. These inventories were cross-referenced against recommended safe setback guidance for avoiding vibration-related building cosmetic structural and human health impacts to identify vibration-generating plant/equipment to be used. Potential airblast overpressure and vibration levels from blasting activities were estimated using guidance presented in Australian Standard AS2187.2 – 2006 Explosives – Storage and use Part 2: Use of explosives. Cumulative construction noise impacts were evaluated by considering worst-case predictions from the project and Snowy 2.0 as presented in Appendix R: Noise and Vibration Impact Assessment Snowy 2.0 Main Works’, (EMM, 2019).

Assessment of impacts

Potential noise, vibration and airblast overpressure levels at identified surrounding receiver locations were quantitatively assessed using various predictive methods. Results were evaluated by comparing the predictions against limits established based on guidance from relevant NSW, National and international standards and guidelines.

Using this approach, the following potential for impacts were determined:

Predicted worst-case noise levels during construction were predicted to remain below project noise management levels (NMLs) at the identified receiver locations. Levels up to 59 dB(A) were predicted at receiver A16 (Snowy 2.0 works accommodation) although this is not considered to be a sensitive receiver given its association with Snowy 2.0. It is expected that the Snowy 2.0 accommodation facility would meet relevant requirements to provide adequate levels of amenity.

Sleep disturbance impacts were not predicted during construction or operation

Additional traffic movements from project construction activities are not expected to result in unacceptable changes in traffic noise levels at sensitive receivers along the intended haulage routes

Page 7: Noise and Vibration assessment

Noise and Vibration assessment

vi

Building cosmetic damage and human comfort impacts from vibration generated from the use of hydraulic rock breakers and vibratory rollers at identified receiver locations would be unlikely. Care would need to be taken if this equipment is required within 50 m of heritage items R45 and R49

Airblast overpressure and vibration impacts from blasting activities were not anticipated at the identified sensitive receiver locations. Care would be required to avoid damage to R45 and R49 if blasting is required around these locations

Operational noise from the substation and transmission lines would not result in unacceptable impacts at the identified sensitive receivers

The potential for cumulative noise impacts during the construction of the project and Snowy 2.0 was also determined to be negligible with cumulative levels remaining below NMLs at the identified sensitive receiver locations.

Conclusion and recommendations

Considering these outcomes, it was determined that the potential for noise and vibration impacts during the project would be limited. Measures to minimise construction noise and vibration from the project in line with best practice were recommended as required, with specific measures recommended regarding vibration. No noise impacts were determined during operation and therefore no measures have been recommended.

Page 8: Noise and Vibration assessment

Noise and Vibration assessment

vii

Important note about your report

The sole purpose of this report and the associated services performed by Jacobs is to assess potential noise and vibration impacts associated with the Snowy 2.0 Transmission Connection Project (the project) in accordance with the scope of services set out in the contract between Jacobs and TransGrid. That scope of services, as described in this report, was developed with the Client.

In preparing this report, Jacobs has relied upon, and presumed accurate, any information (or confirmation of the absence thereof) provided by TransGrid and/or from other sources. Except as otherwise stated in the report, Jacobs has not attempted to verify the accuracy or completeness of any such information. If the information is subsequently determined to be false, inaccurate or incomplete then it is possible that our observations and conclusions as expressed in this report may change.

Jacobs derived the data in this report from information sourced from TransGrid (if any) and/or available in the public domain at the time or times outlined in this report. The passage of time, manifestation of latent conditions or impacts of future events may require further examination of the project and subsequent data analysis, and re-evaluation of the data, findings, observations and conclusions expressed in this report. Jacobs has prepared this report in accordance with the usual care and thoroughness of the consulting profession, for the sole purpose described above and by reference to applicable standards, guidelines, procedures and practices at the date of issue of this report. For the reasons outlined above, however, no other warranty or guarantee, whether expressed or implied, is made as to the data, observations and findings expressed in this report, to the extent permitted by law.

This report should be read in full and no excerpts are to be taken as representative of the findings. No responsibility is accepted by Jacobs for use of any part of this report in any other context.

This report has been prepared on behalf of, and for the exclusive use of TransGrid, and is subject to, and issued in accordance with, the provisions of the contract between Jacobs and TransGrid. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance upon, this report by any third party.

Page 9: Noise and Vibration assessment

Noise and Vibration assessment

1

1. Introduction

1.1 Overview

TransGrid is the manager and operator of the major high-voltage electricity transmission network in New South Wales (NSW) and the Australian Capital Territory (ACT).

TransGrid is seeking approval under Part 5 Division 5.2 of the NSW Environmental Planning and Assessment Act 1979 (EP&A Act) for the construction and operation of an overhead transmission connection and substation to enable the grid connection of the Snowy 2.0 pumped hydro generation project (Snowy 2.0).

The Snowy 2.0 Transmission Connection Project (the project) has been declared critical State Significant Infrastructure (SSI) under the State Environmental Planning Policy (State and Regional Development) 2011 and is subject to assessment and determination by the Minister for Planning and Public Spaces. This noise and vibration assessment has been developed in support of the Environmental Impact Statement (EIS) for the project.

1.2 Purpose of this report

This noise and vibration assessment has been prepared in accordance with the Secretary’s Environmental Assessment Requirements (SEARs) issued for the project on 1 November 2019 by the Planning Secretary of the NSW Department of Planning, Industry and Environment (DPIE).

The SEARs relating to noise and vibration impacts are outlined in Table 1-1, along with a reference to where these requirements are addressed in this report.

Table 1-1: Secretary’s environmental assessment requirements – Noise and vibration

Requirement Where addressed

Amenity – an assessment of the construction, operational and road noise impacts of the project.

Section 6

In meeting these requirements, the objectives of this assessment were to:

Describe the project setting, details and potential noise and vibration-related risks (Section 2)

Outline key features of the existing environment including surrounding receivers, meteorology andbackground noise levels (Section 3)

Establish suitable assessment criteria (Section 4)

Estimate noise and vibration-related emissions associated with the construction and operational phases ofthe Project (Section 5)

Predict the potential for noise and vibration-related impacts (including the potential for cumulativeimpacts) (Section 6)

Recommend mitigation and management measures (Section 7).

Page 10: Noise and Vibration assessment

Noise and Vibration assessment

2

2. Project description

2.1 Project components

The project involves the construction and operation of an overhead transmission connection and substation to connect Snowy 2.0 to the National Electricity Market.

The key elements of the project would include:

A new 500/330 kilovolt (kV) substation located within Bago State Forest and adjacent to TransGrid’s existing Line 64, which forms a 330 kV connection between Upper Tumut and Lower Tumut switching stations. The substation would occupy a footprint of approximately 300 metres (m) wide by 600 m long inclusive of an approximate 25 to 45 m wide cleared asset protection zone (APZ) surrounding the switchyard. Key noise-generating equipment at the new substation include three 500 kV transformers, two 500 kV reactors, three auxiliary transformers and two voltage transformers

Upgrade and widening of an existing access road off Elliott Way to the new substation including the construction of a new driveway into the 330 kV and 500 kV switchyards

Two new 330 kV overhead double-circuit transmission lines from the Snowy 2.0 cable yard to the new substation:

- Total length of each line is approximately nine kilometres (km)

- Located in a corridor ranging in width from approximately 120 m to 200 m

- Each line would comprise approximately 21 steel lattice structures up to 75 m in height

Short overhead 330 kV transmission line connection (approximately 300 metres in length) comprising both steel lattice structures and pole structures as required between the substation and Structure 43 on Line 64

Construction of approximately 10 km of new access tracks (Option A) or 8 km (Option B) to the transmission structures and upgrade to existing access tracks where required. Option A minimises disturbance within a mapped high risk naturally occurring asbestos (NOA) zone. The access tracks would remain following the completion of construction to service ongoing maintenance activities along the transmission lines

Establishment of a helipad (approximately 30 m wide by 30 m long) to support the transmission line construction activities carried out at higher elevations and steep terrain

Ancillary activities, including the establishment of tensioning and pulling sites for conductor and earth wire stringing, crane pads, site compounds, and equipment laydown areas.

The project location and key components of the project are shown Figure 2-1 and in Figure 2-2 respectively.

A complete project description which includes a consolidated summary and discussion of the construction and operation of the project is provided in Chapter 5 of the EIS.

2.2 Project location

The eastern extent of the project is defined by the location of Snowy 2.0 cable yard at Lobs Hole in Kosciuszko National Park (KNP). The cable yard serves as the transition point between the underground cables carrying electricity generated by Snowy 2.0 to the overhead transmission connection. The cable yard forms part of Snowy 2.0.

From the cable yard, the transmission connection extends west through KNP and up Sheep Station Ridge which is characterised by steep, mountainous terrain before traversing Talbingo Reservoir. The transmission connection then continues west, passing over Elliott Way at three locations before entering Bago State Forest to the proposed substation site. The location of the project is shown in Figure 2-1.

Page 11: Noise and Vibration assessment

Noise and Vibration assessment

3

The nearest large town to the project is Tumut, which is located approximately 55 km to the north west Other townships near the project include Talbingo, Tumbarumba, Cabramurra and Adaminaby. Talbingo and Cabramurra were built to provide accommodation for the original Snowy Scheme workers and their families.

2.3 Project area

For the purposes of predicting environmental impacts of the project, a disturbance area has been defined. The disturbance area encompasses the extent of physical disturbance likely to be required to accommodate construction activities and infrastructure needed to build the overhead transmission line, the permanent substation and access roads and vegetation clearing along the transmission corridor.

A broader project area has also been defined. The project area represents the limits of where disturbance may occur during construction to allow for flexibility for the final siting of project infrastructure. Final siting of the infrastructure (i.e. the disturbance area) can move within the assessed project area subject to recommended environmental management measures and provided it does not exceed the limits defined by the project area.

The project traverses Talbingo Reservoir, which naturally splits the project area into two. When defining the area of works, the terms ‘project area east’ and ‘project area west’ have been used where required for the purpose of the EIS. These are defined as follows:

Project area east: includes the project area and existing surrounding access roads in the area east ofTalbingo Reservoir

Project area west: includes the project area and existing surrounding access roads in the area west ofTalbingo Reservoir.

The existing landscape character of much of the project area consists of undisturbed and mountainous terrain, forested valleys, and is the only true alpine environment in NSW (NPWS 2003). This landscape contains limited human disturbance, however existing transmission line easements, minor access tracks, and infrastructure associated with the Talbingo Reservoir occur within and in the vicinity of the project area.

The project area and disturbance area shown in Figure 2-1.

Page 12: Noise and Vibration assessment

D AO

E RNI

LOBS

HOLE

RAV

SNOW

Y MOU

NTAIN

S HIG

HWAY

GOBILLY RIVER

NA K R ERAY

TAILRACE TUNNEL

TANT

A

TUMUT RIVER

LO

NUNG

ARCR

EEKBS HOLE RAVINE

ROAD

Line 64

Line 2

SNOW

Y MONA

RORE

GIONA

L COU

NCIL

L ICN

SNOW

Y VAL

LEYS

COU 1

neiLELLIOTT WAY

NSW

TALBINGO ACT

RAVINE KOSCIUSZKO RULES POINT

NATIONAL PARK MARAGLE CABRAMURRA

SA

LOBS HOLE

TALBINGO RESERVOIR

RAVINE BAYEMPLACEMENT AREA

TANTANGARARESERVOIR

NGAR

A CRE

TALBINGO INTAKE BAGOSTATE HAINS HUT

ACCOMMODATIONCAMP TANTANGARA

INTAKE FOREST

RAVINE HEADRACE TUNNEL EMERGENCY

EGRESS, CABLE AND VENTILATION

TUNNEL MILK SHANTY TRACES

HUT SUE CITY MARAGLE

STATEFOREST

0 1.5 3 km 1:140,000 @ A4

Imagery: Aerometrex 2020 and © Department of Customer Service 2020

Project area Snowy 2.0 cable yard Electricity transmission line State forestProposed transmission line Snowy 2.0 element Local Government boundary NPWS estateProposed 500kV substation Waterway

Water body

JACO

BSNS

WSP

ATIA

L-GI

SMA

Pfile

:IA1

9990

0_GI

S_EI

S_F0

01_r2

v2_L

ocali

ty |

30/09

/2020

Data source:Jacobs 2020, TransGrid, EMM 2020 Figure 2-1 | Project location © Department Finance, Services and Innovation 2018

Page 13: Noise and Vibration assessment

Line 64

LOBS

HOLE

RAV

INE R O AD

TALBINGORESERVOIR

KOSCIUSZKO NATIONAL PARK

YARRANGOBILLY RIVER

TUMUT RIVER

MARAGLESTATE FOREST

BAGOSTATE FOREST

Line 2

MINE TRAIL

BLACK JACK LOGGING ROAD

BOUNDARY ROAD

APRIL TRAIL

EAST BAGO POWERLINE ROAD

TOLBAR TRAIL

ELLIOTT WAY

PLAIN CREEK

YORKERS CREEK

JACO

BS N

SW S

PATIA

L -GI

S MA

P file

: IA

1999

00_G

IS_EI

S_F0

02_r2

v2_S

tudy_

area

| 30

/09/20

20

Line 64

Line 2

RAVINE

MARAGLE

CABRAMURRA

0 1.5 3 km 1:50,000 @ A4

Imagery: Aerometrex 2020

KOSCIUSZKO NATIONAL PARK

BAGOSTATE

FOREST

MARAGLESTATE

FOREST

MINE TRAIL

INSET

SEE INSET

Project area Snowy 2.0 cable yard Electricity transmission line Disturbance area Snowy 2.0 element Waterway Proposed 500kV substation Ravine Bay Emplacement Area Water body Potential helipad location Snowy 2.0 Disturbance footprint State forestProposed structure NPWS estateProposed transmission line Proposed access track - Option A Proposed access track - Option B

Data source:Jacobs 2020, TransGrid, EMM 2020,

Figure 2-2 | Project overview © Department Finance, Services and Innovation 2018

Page 14: Noise and Vibration assessment

Noise and Vibration assessment

6

2.4 Construction activities

The construction works would commence with the construction of the access tracks to the substation and transmission structure locations. Construction of the helipad is also expected to commence in the initial stages. Once suitable access has been established, construction of the substation and transmission line would commence and occur concurrently. Table 2-1 below summarises the key construction activities associated with each of the of the project elements above.

Table 2-1: Project construction overview

Construction activity

Description

Pre-construction, site establishment

Site mobilisation once relevant approvals have been granted, property acquisitions havebeen finalised with Forestry Corporation of NSW (FCNSW) and National Parks andWildlife Service (NPWS) and agreements with construction contractors has beenachieved

Surveying and marking out the approved disturbance area and any environmentalavoidance areas

Installation of appropriate stormwater and diversion drainage and erosion andsedimentation control works prior to ground disturbance and vegetation clearing

Inform recreational users of KNP, Bago State Forest and Talbingo Reservoir of theconstruction activities, the extent of work areas and the locations of environmentalexclusion areas with project notifications, including warning signs of constructionactivities and notifications of access restrictions

Establishment of the construction compound and equipment laydown areas at thesubstation site and at Lobs Hole*.

Access tracks Vegetation clearing within the approved corridor. This is expected to be carried out bothmanually in the areas of steeper slopes and machine clearing where access can be safelyachieved

Grubbing and bulk earthworks (cut and fill) using an excavator

Installation of suitable drainage structures and sediment retention basins where required

Laying and compaction of a suitable rock aggregate/road base

Grading and/or reshaping of existing tracks where required, within the existing accesstrack width (no road widening)

Minor excavations followed by laying and compaction of crushed rock or gravel, toimprove the existing track surface and drainage.

Substation Vegetation clearing across the substation site and surrounding APZ. This would involvethe stripping and stockpiling of topsoil for later use. Vegetation clearing is expected tobe carried out utilising a bulldozer equipment with a tree pusher, however would beconfirmed in consultation with FCNSW

Establishment of a site compound and laydown area within the cleared APZ. The sitecompound would be in placed throughout the construction period and is expected tocontain a demountable office, meal room, and toilet/shower facilities, equipmentlaydown areas, vehicle and equipment storage, maintenance sheds, chemical/fuel storesand stockpile areas

Minor earthworks to establish the site amenities; which would include cut and fill toestablish a level area for the site facilities and temporary storage areas andestablishment of the permanent site access road

Page 15: Noise and Vibration assessment

Noise and Vibration assessment

7

Construction activity

Description

Earthworks:

- Excavation works to remove excess material, provide a level surface, and createthe required trenches for drainage, earthing, and electrical conduits. Some spoilfrom the excavation may be reused on site for filling and compaction (includingbenching areas of the site where required). Excavation works would be carried outusing equipment such as excavators, dozers and crushing plant. Furthermore,depending on the underlying geology, blasting may be required to facilitate thebreak-up of rock, should it be present

- Bulk earthworks to establish the level surface for the substation bench

- Approximately 11,300 cubic metres of excess spoil would be generated from thelevelling of the substation site and construction of the access road. Any soil whichcannot be reused onsite as fill material, landscaping or other means would bedisposed of off-site at a suitably licenced facility and/or at a location(s) as agreedwith FCNSW

- Where excavated spoil is not appropriate for reuse on site, additional spoil wouldbe imported to site

Civil and building works:

- Civil works involving the establishment of concrete footings for the high voltageequipment and buildings, construction of stormwater drainage and oilcontainment infrastructure and cable trenches and subsurface cables

- Construction of onsite buildings (e.g. control room) and services installedincluding general lighting, power and ventilation.

Transmission corridor

Vegetation clearing within the approved transmission corridor where the overheadconductors would not meet safe clearance heights above the underlying vegetation

Grading and/or reshaping of existing access tracks where required

Vegetation clearing and bulk earthworks to establish the level helipad

Establishment of the transmission structure work sites involving:

- Clearing of an approximate 40 m by 60 m area around each transmissionstructure location to allow for the laydown of materials and equipment andfacilitate access for vehicles, plant and machinery during structure construction

- Bulk earthworks (cut and fill) to establish level construction benches within theworksite to allow for the safe operation of plant and equipment (namely elevatedworks platforms and cranes) during structure construction

- Geotechnical investigation works using a mobile drill rig at each structure locationto determine the most appropriate footing design

- Bulk earthworks and excavations to establish the structure footings involving theinstallation of steel framework and backfilling with concrete or pile type footingsinvolving boring four boreholes at each structure leg location and backfilling withconcrete

- Steel lattice structures would be transported to each structure location via heavyvehicle in parts and assembled on site using mobile cranes

Stringing of conductor and overhead earth wire which would involve:

- Establishment of level tensioning and pulling sites within the approximate 40 mby 60 m structure worksite or at suitable locations within the transmission corridor

Page 16: Noise and Vibration assessment

Noise and Vibration assessment

8

Construction activity

Description

- Attachment of sheaves (or pulleys) to the top of the structures in readiness forstringing work using an elevated work platform

- Pulling out a light weight draw wire across the section of line being strung using adrone or vehicle/machine (such as dozer), followed by the placement of the drawwire through the sheaves

- Attachment of the draw wire to the earth wire or conductor drum (depending onwhich is being strung) and pulling it through the sheaves under tension usingspecialised tensioning and pulling equipment

- Termination of the conductor/earth wire at each end clipping it into positionfollowed by the removal of the sheaves.

Commissioning Testing of all high voltage equipment at the substation and ensuring all protection,control and metering equipment is operating correctly

Completion of all necessary cut-in works to Line 64 and relevant testing undertaken

Placement of the new transmission lines and substation into standby in readiness forSnowy 2.0 to be completed

Once Snowy 2.0 becomes operational, energisation of the high voltage equipment andthe project placed into service

Rehabilitation and demobilisation

Removal of all non-permanent infrastructure and equipment from the work sites andsite compounds

Decommissioning and dismantling of the site compounds at the substation and LobsHole

Site stabilisation and landscaping involving:

- Stabilisation of exposed areas and slopes

- Installation and maintenance of erosion and sediment controls at the work sites tomanage impacts post-construction

- Seeding soil slopes to assist stabilisation

- Planting vegetation on any higher risk slopes

- Mulching of stabilised and revegetated areas where required.

*The site compound at Lobs Hole would be located within the approved disturbance footprint of Snowy 2.0.

2.4.1 Construction staging and timing

These works are anticipated to commence in early 2022 and take approximately 39 months to complete. An indicative is program is presented below in Figure 2-3. Further details on the estimated timing and staging of the main project activities is described in Section 5.3 of the EIS.

Construction works 2022 2023 2024 2025

Quarter Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

Access tracks, roads and

helipad

330 kV Switchyard

500 kV Substation

Transmission connection

Figure 2-3: Indicative timing for the construction of key project components

Page 17: Noise and Vibration assessment

Noise and Vibration assessment

9

2.4.2 Construction working hours

Given the isolated location and the construction of Snowy 2.0 occurring in parallel, construction works are expected to be carried out 12 hours per day, seven days per week between the hours of 6 am and 6 pm.

2.4.3 Construction traffic movements

Construction vehicle movements have the potential to generate temporary adverse noise impacts along access routes which use public roads as vehicles deliver materials to and from the project site. Construction vehicle movements would comprise vehicles transporting equipment, waste, materials and spoil, as well as vehicles driven by the construction workforce accessing the work locations. Estimated light and heavy vehicle movements on a typical day and during the peak construction period is outlined in Table 2-3.

Table 2-3: Estimated project-related vehicle movements during construction

Vehicles Movement type Estimated movements / day

Substation

Light vehicles Indicative daily movements (typical day) 50

Maximum daily movements (critical/peak construction period) 80

Heavy vehicles Indicative daily movements (typical day) 30

Maximum daily movements (critical/peak construction period) 75

Transmission line

Light vehicles Indicative daily movements (typical day) 30

Maximum daily movements (critical/peak construction period) 60

Heavy vehicles Indicative daily movements (typical day) 50

Maximum daily movements (critical/peak construction period) 75

* Indicative daily movements are based on current program of work and may change as a result of detailed constructionplanning with one vehicle movement referring to one inbound and outbound trip.

It is anticipated that the maximum predicted daily heavy vehicle movements would occur during:

Bulk earthworks and civil works during the substation construction

Bulk earthworks and civil works during access track construction and establishment of the transmissionstructure footings

Transmission connection corridor vegetation clearing works.

The high volume of heavy vehicle movements during the above activities is attributed to heavy vehicles transporting large volumes of spoil, vegetative matter and debris from the project area.

Light personnel vehicle movements would be generally attributed to the construction workforce accessing the substation site for work each day and accessing the work locations along the transmission connection corridor.

2.4.3.1 Primary construction transport routes

The values in Table 2-3 above are based on current program of works. The anticipated haulage routes for heavy vehicles carrying materials and equipment to and from the project area are outlined below.

Project area west: It is expected that majority of materials and equipment would travel along HumeHighway, Snowy Mountains Highway, Batlow Road, Tooma Road and Elliott Way.

Page 18: Noise and Vibration assessment

Noise and Vibration assessment

10

Project area east: It is expected that the majority of materials and equipment would travel along SnowyMountains Highway (from both Tumut and Cooma), Link Road and Lobs Hole Ravine Road.

It is expected that all heavy transport would occur between 5am and 7pm and be limited to daylight hours to avoid sleeping hours.

2.5 Operation and maintenance

The substation and transmission connection would be inspected by field staff on a regular basis. Key activities undertaken during operation would include:

Regular inspection and maintenance of electrical equipment at the substation including structural integrityof all footings and support structures

General inspection and maintenance of other components within the substation including the stormwatermanagement system, fire detection system, onsite buildings and drainage infrastructure

Regular inspection and maintenance of the transmission structures, footings, fittings, conductors andoverhead earth wires

Vegetation removal and trimming along the transmission easement and APZ surrounding the substation tomaintain appropriate clearances between ground vegetation and the overhead transmission lines andaround the substation to manage bushfire risk

Removal of trees which have the potential to strike the overhead conductors if they were to fall (referred toas hazard trees) as required.

It is expected that only light vehicles and small to medium plant would need to access the substation site and the transmission corridor for these activities. The substation would not accommodate full-time staff or contractors, and the regular collection of waste would not be required. Any waste generated during operation of the substation would be minimal and disposed of on an ‘as need’ basis.

Given that only 40 traffic movements per year are estimated to be generated during operations, the potential for noise impacts from additional traffic generated by the operation of the project is not expected and has not been considered further in the assessment.

2.6 Primary noise and vibration-related risks

Noise and vibration-related impacts can arise when levels from an industry or construction activities result in unacceptable levels at surrounding sensitive receivers. Noise and vibration have the potential to be generated during the construction and operational phases of the project. The key activities with the potential to generate noise and vibration during the project include:

Site establishment; construction of new access tracks, substation and transmission lines; commissioning anddemobilisation/rehabilitation, including associated traffic movements

Noise from the substation and transmission lines during operation.

Additionally, the other key noise and vibration-related risk would be cumulative impacts at surrounding sensitive receivers.

Page 19: Noise and Vibration assessment

Noise and Vibration assessment

11

3. Existing environment

3.1 Surrounding sensitive receivers

Surrounding receivers in relation to the project are shown on Figure 3-1. As displayed, there are two passive recreation areas within the vicinity of the project: Coonara Point Campground and Rest Area and O’Hares Campground. There are also a number of private residential properties along Bradleys Drive, Nurenmerenmong. The Snowy Hydro’s accommodation camp at Lobs Hole (Snowy 2.0 works accommodation) is also located nearby. Although this location would be sensitive to noise from project activities, it was not considered to be a sensitive receiver location in ‘Appendix R: Noise and Vibration Impact Assessment Snowy 2.0 Main Works’, (EMM, 2019) owing to its affiliation with the project. It is expected that the contractor responsible for the Snowy 2.0 works accommodation would design these facilities to meet relevant requirements to provide adequate levels of amenity.

Details of the receiver locations identified in Figure 3-1 are listed in Table 3-1.

Table 3-1: Nearby noise sensitive receivers

Receiver ID

Receiver details Receiver type Approximate co-ordinates (UTM MGA Zone

Easting (m) E Northing (m) S

A3 Coonara Point Campground and Rest Area

Passive recreation area 622202 6039251

A5 O’Hares Campground Passive recreation area 623443 6035053

R20 Private properties at Nurenmerenmong and McPherson Plains caravan park

Residential 615307 6040979

A16 Snowy 2.0 works accommodation n/a* 625947 6039216

* Not applicable, the Snowy 2.0 works accommodation forms part of the overall Snowy 2.0 construction works

There would also be sensitive receivers along routes and towns (such as Cooma, Batlow, Tumbarumba and Tumut) affected by haulage and daily construction traffic (ie traffic between accommodation locations and the construction sites).

The Snowy 2.0 Transmission Connection Project Non-Aboriginal Heritage Assessment (Jacobs, 2020) (Jacobs, 2020) identified two heritage structures within the disturbance area. These are listed in Table 3-2 and shown in Figure 3-1.

Table 3-2: Non-Aboriginal heritage items identified within the project area

Identifier Name Location

R45 Lobs hole Copper mine water race 150 m south west of the first set of structures in project area east

R49 Circular stone wall 145 m west of the fourth set of structures in project area east

Page 20: Noise and Vibration assessment

BRADLEYS DRIVE

ELLIOTT WAY

LOBS HOLE RAVINE ROAD

KOSCIUSZKO NATIONAL PARK

Line 66

Line 2

Line 64

BAGO STATEFOREST

MARAGLESTATE

FOREST

Coonara Pointcampground

and rest area

O'Harescampground

Kosciuszko NationalPark Elliott

Way entry point

A16: Snowy Hydroaccommodation camp

R20: McPhersonsPlains Alpine

Caravan Park

R20

R20

R20 R20

A3

A5

Ravinecampground

TALBINGORESERVOIR

MINE TRAIL

O'HARES TRAIL

TOLBAR TRAIL

JACO

BS N

SW S

PATIA

L -GI

S MA

P file

: IA

1999

00_N

VA_F

001_

r1v1_

Sens

itiveR

eceiv

ers |

4/12

/2020

VIC

ACT

NSW

TALBINGO

RAVINE

MARAGLE CABRAMURRA

0 1 2 km 1:75,000 @ A4

Imagery: Aerometrex 2020

Project area Sensitive receiver - accommodation Kosciuszko National Park Elliott Way entry pointDisturbance area Sensitive receiver - private residence Campground Proposed 500kV substation Historic heritage - significant item (NSW Archaeology 2019) Electricity transmission line Potential helipad location Snowy 2.0 cable yard Track Proposed structure Snowy 2.0 element Major road Proposed transmission line Snowy 2.0 Disturbance footprint Waterway Proposed access track - Option A Water body Proposed access track - Option B State forest

NPWS estate

Figure 3-1 | Sensitive receivers

Page 21: Noise and Vibration assessment

Noise and Vibration assessment

13

3.2 Meteorology

Certain meteorological conditions can enhance the propagation of noise and their influence is required to be accounted for where they are found to be a feature of the locality. In the EIS completed for the Snowy 2.0 Main Works a review of whether noise-enhancing meteorological conditions were a ‘significant’ feature of the local environment was undertaken. This included a review of prevailing winds and temperature inversions consistent with the methods detailed in Fact Sheet D of the NSW Environment Protection Authority’s (EPA’s) “Noise Policy for Industry” (NPI) (2017). This review found that wind noise-enhancing effects were not a feature of the local setting, although the occurrence of temperature inversion conditions was significant’ with ‘F’ and ‘G’ atmospheric stability class conditions occurring more than 30% of night time periods in winter (EMM, 2019). As such, it was concluded that noise-enhancing meteorological conditions were a feature of the local environment. This conclusion was considered to be relevant for the purpose of this assessment.

3.3 Background noise levels

An understanding of background noise levels is necessary to determine a locality’s sensitivity to changes in the acoustic environment. Background noise monitoring was undertaken as part of the noise and vibration assessment undertaken for the Snowy 2.0 Main Works EIS. Although none of the five Snowy 2.0 EIS background noise sampling locations were located near the project works being assessed, they provide an indication of background noise conditions around the wider project setting. These results are reproduced in Table 3-3.

Table 3-3: EIS background noise monitoring results summary (EMM, 2019)

ID Location Period Measured and (adopted) rating background level, RBL dB(A)

Measured equivalent noise level, LAEQ period dB(A)

EIS L1 Brownlie Court, Talbingo Day 28 (35) 48

Evening 29 (30) 47

Night 23 (30) 35

EIS L2 Yarrangobilly Village Campground, Snowy Mountains Highway

Day 31 (35) 53

Evening 31 (30) 45

Night 32 (30) 41

EIS L3 Sawyers Hut, Snowy Mountains Highway Day 26 (35) 54

Evening 25 (30) 49

Night 24 (30) 46

EIS L4 Tooma Road, Tooma Day 25 (35) 57

Evening 24 (30) 51

Night 23 (30) 53

EIS L5 Rock Forest, Adaminaby Day 34 (35) 41

Evening <30 (30) -

Night <30 (30) -

EIS L6 Snowy Mountains Highway, Adaminaby Day 26 (35) 58

Evening 21 (30) 53

Night 21 (30) 47

Page 22: Noise and Vibration assessment

Noise and Vibration assessment

14

The term rating background level (RBL) above in Table 3-3 refers to the median value of monitored background noise levels measured over each period and is used for the purpose of establishing background noise levels. Additionally, the term ‘LAeq’ refers to the equivalent continuous sound level or energy-time average for the relevant period of monitoring. As listed, measured daytime RBLs ranged between 25 and 34 dB(A), evening values between 21 and 31 dB(A), and levels at night ranged from 21 and 32 dB(A). In the absence of monitored background noise levels, the NPI provides the minimum RBLs listed in Table 3-4:for the purpose of the noise assessment.

Table 3-4: Adopted background noise levels dB(A)

Day (7am to 6pm) Evening (6pm to 10pm) Night (10pm to 7am)

35 30 30

These minimum recommended RBLs are consistent with those measured at receivers around Snowy 2.0 and are typical for the remote project setting where there would be limited anthropogenic noise sources contributing to background noise levels. As such, these minimum recommended RBLs were applied in the assessment.

Page 23: Noise and Vibration assessment

Noise and Vibration assessment

15

4. Policy setting and criteria

4.1 Construction noise

4.1.1 Noise management levels

The “Interim Construction Noise Guideline” (ICNG) (Department of Environment and Climate Change [DECC], 2009) provides guidance for assessing noise from construction activities in NSW. It establishes noise management levels (NMLs) according to the hours in which construction may take place. Construction is considered to have the potential to cause a noise impact if the predicted noise exceeds the noise management levels. Table 4-1 lists ICNG guidance for establishing construction NMLs at residential receivers.

Table 4-1: ICNG guidance for establishing construction NMLs at residential receivers

Time of day Management level

LAeq(15min)

How to apply

Recommended standard hours:

Monday to Friday 7am to 6pm

Saturday 8am to 1pm

No work on Sundays or public holidays

Noise affected

RBL + 10 dB(A)

The noise affected level represents the point above which there may be some community reaction to noise.

Where the predicted or measured LAeq(15 min) is greater than the noise affected level, the proponent should apply all feasible and reasonable work practices to meet the noise affected level.

The proponent should also inform all potentially impacted residents of the nature of works to be carried out, the expected noise levels and duration, as well as contact details.

Highly noise affected

75 dB(A)

The highly noise affected level represents the point above which there may be strong community reaction to noise.

Where noise is above this level, the relevant authority (consent, determining or regulatory) may require respite periods by restricting the hours that the very noisy activities can occur, taking into account: times identified by the community when they are less sensitive to noise (such as before and after school for works near schools, or mid-morning or mid-afternoon for works near residences if the community is prepared to accept a longer period of construction in exchange for restrictions on construction times.

Outside recommended standard hours (OOH) - All other times including public holidays

Noise affected

RBL + 5 dB(A)

A strong justification would typically be required for works outside the recommended standard hours.

The proponent should apply all feasible and reasonable work practices to meet the noise affected level.

Where all feasible and reasonable practices have been applied and noise is more than 5 dB(A) above the noise affected level, the proponent should negotiate with the community.

Considering the adopted RBLs presented in Table 3-4: and the guidance above from the ICNG, the following NMLs listed in Table 4-2 were established to assess potential construction noise impacts at the identified surrounding residential receiver location (receiver R20).

Page 24: Noise and Vibration assessment

Noise and Vibration assessment

16

Table 4-2: ICNG NMLs for residential receivers

Receiver type

Day (during standard hours)

Day (outside standard hours)

Evening Night

L90 (RBL)

dB (A)

NML Leq 15

min dB(A) L90 (RBL)

dB (A)

NML Leq 15

min dB(A) L90 (RBL)

dB (A)

NML Leq 15

min dB(A) L90 (RBL)

dB (A)

NML Leq 15

min dB(A)

Residential 35 45 35 40 30 35 30 35

The ICNG also provides construction NMLs for non-residential land uses. This guidance has been reproduced below in Table 4-3, which was applied at receivers A3 and A5.

Table 4-3: ICNG NMLs for non-residential receivers

Non-residential receiver type Noise management level, LAeq(15min)

(applies when properties are being used)

Passive recreation areas External noise level – 60 dB(A)

4.1.2 Construction traffic noise impacts

Section 9 of the “Construction Noise and Vibration Guideline” (CNVG), (NSW Roads and Maritime, 2016) provides guidance for the assessment of noise associated with additional traffic generated during construction. This guidance was adopted for this assessment and has been reproduced below:

‘For RMS projects an initial screening test should first be applied by evaluating whether noise levels will increase by more than 2dB(A) due to construction traffic or a temporary reroute due to a road closure. Where increases are 2dBA or less no further assessment is required.

Where noise levels increase by more than 2dB(A) [i.e. 2.1 dBA] further assessment is required using Roads and Maritimes Criteria Guideline. This documents RMS’ approach to implementing the Road Noise Policy. Consideration should be given under the Noise Criteria Guideline as to whether construction traffic or temporary reroute triggers new road criteria due to changes in road category’.

This guidance was considered for the purpose of reviewing potential noise associated with additional traffic generated as a result of the project.

4.1.3 Sleep disturbance during construction

The ICNG does not provide a specific method for assessment of potential sleep disturbance noise impacts and guidance on the acceptability of these events is taken from the NSW Road Noise Policy (RNP), (DECCW, 2011).

The RNP provides two criteria:

• Sleep disturbance screening criterion – used to identify situations where there is the potential for sleep disturbance

• Sleep disturbance awakening criterion – levels below which awakening is unlikely to occur.

The sleep disturbance screening criterion recommends that where the LA1 (1 minute) does not exceed the LA90 (15

minute) by 15 dB(A) or more, sleep disturbance impacts are likely to be maintained at an acceptable level. The LA1, (1 minute) descriptor is meant to represent a maximum noise level when measured using a 'fast' time response.

The sleep disturbance awakening criterion is the threshold at which an awakening reaction is likely to occur. Research discussed in the RNP identified this threshold to be an internal bedroom noise level of around 50 to 55

Page 25: Noise and Vibration assessment

Noise and Vibration assessment

17

dB(A). Windows often allow the greatest amount of sound transmission from outside to inside across a building façade. Noting guidance presented in AS2436-2010 - Guide to noise and vibration control on construction, demolition and maintenance sites, where bedrooms are ventilated by an opened window, a sleep disturbance awakening criterion measured outside the bedroom window of 60 to 65 dB(A) would generally apply.

4.2 Operational noise

4.2.1 Overview

Operational noise criteria for the project was determined in accordance with the NSW EPA’s NPI which seeks to regulate noise impact from ‘industrial activity’ pertaining to noise from fixed industry and mechanical plant (including substations and transmission lines) rather than from road, rail or construction sources. To achieve this, the NPI applies two separate noise levels: one aimed at limiting the intrusiveness of the project’s noise against the prevailing level of background noise, and the other focused on achieving suitable acoustic amenity for the surrounding land uses from industry. The more stringent of these is used to define the operational noise criteria for a project.

4.2.2 Intrusiveness noise level

A noise source will be deemed to be non-intrusive if the monitored LAeq (period) noise level of the development does not exceed the RBL by more than 5 dB(A). Based on the RBLs adopted in Table 4-4, the following criteria noise intrusiveness criteria would apply:

Table 4-4: NPI intrusiveness noise levels

Receiver type Time of Day L90 (RBL)

dB (A)

Allowance Noise intrusiveness criteria dB(A)

Residential receivers Day (7 am to 6 pm) 35

+5 dB(A)

40

Evening (6 pm to 10 pm) 30 35

Night (10 pm to 7 am) 30 35

4.2.3 Amenity noise level

The recommended amenity noise levels represent the objective for total operational noise at a receiver location, whereas the project amenity noise level represents the objective for noise from a single development at a receiver location. To ensure that operational noise levels remain within the recommended amenity noise levels for an area, the project amenity noise levels below in Table 4-5 would apply:

Table 4-5: NPI amenity noise criteria, residential receivers

Receiver type Time of Day Recommended LAeq Noise Level dB(A)

Project amenity LAeq 15

minute Noise Level dB(A)

Residential receivers Day (7 am to 6 pm) 50 48

Evening (6 pm to 10 pm) 45 43

Night (10 pm to 7 am) 40 38

The NPI also presents amenity noise levels for non-residential receivers. These have been reproduced below in Table 4-6.

Page 26: Noise and Vibration assessment

Noise and Vibration assessment

18

Table 4-6: NPI amenity noise criteria, other receivers

Receiver type Time of day Recommended amenity LAeq 15

minute Noise Level dB(A)

Passive recreational area When in use 48

4.2.4 Project operational noise criteria

Considering the intrusive and amenity criteria developed above, the NPI recommends that the more stringent values be applied for each period of assessment. Considering this, the criteria listed in Table 4-7 were adopted for the purpose of assessing the potential for operational noise impacts from the project.

Table 4-7: Project operational noise criteria

Receiver type Time of day Recommended LAeq Noise Level dB(A)

Residential receivers Day (7 am to 6 pm) 40

Evening (6 pm to 10 pm) 35

Night (10 pm to 7 am) 35

Passive recreational area When in use 48

4.2.5 Sleep disturbance during operations

For premises where night operations occur, the potential for noise levels to lead to sleep disturbance should be considered. Where noise levels from an operational premises at a residential receptor at night exceeds the following, the NPI recommends that a maximum noise level event assessment should be undertaken:

LAeq,15min 40dB(A) or the RBL + 5dB(A), whichever is greater, and/or;

LAFMax 52 dB(A) or the RBL +15 dB(A), whichever is greater.

Based on this guidance, an operational sleep disturbance screening criterion of LAeq,15min 40 dB(A) was applied.

4.3 Vibration

4.3.1 Overview

Vibration arising from construction activities can result in impacts on human comfort or the damage of physical structures such as dwellings. These two outcomes have different criteria levels, with the effects of vibration on human comfort having a lower threshold.

4.3.2 Human comfort

With respect to human comfort, vibration arising from construction activities must comply with criteria presented in “Assessing Vibration: a technical guideline”, (DECC, February 2006) and British Standard 6472-1: 2008 Guide to evaluation of human exposure to vibration in buildings Part 1: Vibration sources other than blasting [BS 6472-1: 2008]. DECC, 2006 identifies three different forms of vibration associated with construction activities:

Continuous: uninterrupted vibration occurring over a defined period

Impulsive: short-term (typically less than two seconds) bursts of vibration which occurs up to three times over an assessment period

Intermittent: interrupted periods of continuous or repeated impulsive vibration, or continuous vibration that varies significantly in magnitude

Page 27: Noise and Vibration assessment

Noise and Vibration assessment

19

Continuous vibration may result from steady road traffic or steady use of construction equipment (e.g. generator). Impulsive vibration may arise during the loading or unloading of heavy equipment or materials or infrequent use of hammering equipment. Intermittent vibration may arise from the varied use of construction equipment (i.e. a dump truck moving around a site, idling while being loaded with materials, and then dumping the materials) or repeated high-noise activities such as hammering, piling or cutting.

Preferred and maximum values of human exposure for continuous and impulsive vibrations are listed (DECC, February 2006) in Table 4-8 below.

Table 4-8: Preferred and maximum weighted root mean squared (rms) values for continuous and impulsive vibration acceleration (m/s2) 1-80 Hz

Location Assessment period1

Preferred values Maximum values

z-axis x and y axis z-axis x and y axis

Continuous vibration

Critical areas2 Day or night 0.0050 0.0036 0.010 0.0072

Residences Day 0.010 0.0071 0.020 0.014

Night 0.007 0.005 0.014 0.010

Offices, schools, educational institutions and places of worship

Day or night 0.020 0.014 0.040 0.028

Impulsive vibration

Critical areas2 Day or night 0.0050 0.0036 0.010 0.0072

Residences Day 0.30 0.21 0.60 0.42

Night 0.10 0.071 0.20 0.14

Offices, schools, educational institutions and places of worship

Day or night 0.64 0.46 1.28 0.92

Workshops Day or night 0.64 0.46 1.28 0.92 1 Daytime is 7am to 10pm. Night-time is 10pm to 7am 2 includes hospital operating theatres or precision laboratories.

Intermittent vibration is assessed differently using vibration dose values (VDV). Preferred and maximum VDVs for different types of receivers have been reproduced in Table 4-9 below.

Table 4-9: Preferred and maximum VDVs for intermittent vibration (ms-1.75), (DECC, 2006)

Location Day time (7 am to 10 pm) Night time (10 pm to 7 am)

Preferred VDV Maximum VDV Preferred VDV Maximum VDV

Critical areas1 0.10 0.20 0.10 0.2

Residences 0.20 0.40 0.13 0.26

Offices, schools, educational institutions and places of worship

0.40 0.80 0.40 0.80

Workshops 0.80 1.60 0.80 1.60

1 Includes operating theatres, precision laboratories and other areas where vibration-sensitive activities may occur.

Page 28: Noise and Vibration assessment

Noise and Vibration assessment

20

4.3.3 Buildings and structures

Appendix J4.4.3 of Australian Standard AS2187.2 – 2006 Explosives – Storage and use Part 2: Use of explosives provides frequency-dependent guide levels for cosmetic damage to structures arising from vibration. These levels are adopted from British Standard BS7385: 1990 Evaluation and measurement for vibration in buildings Part 2: Guide to damage levels from groundbourne vibration [BS7385-2:1993] and are shown below in Table 4-10.

Table 4-10: Transient vibration guideline values for cosmetic damage

Type of building Peak particle velocity (ppv) mm/s

4 to 15 Hz 15 to 40 Hz 40 Hz and above

Reinforced or framed structures

Industrial and heavy commercial buildings 50

Un-reinforced or light-framed structures

Residential or light commercial type buildings 15 to 20 20 to 50 50

Guidance for more sensitive structures is presented in the German standard, DIN 4150-3 Vibrations in buildings – Part 3: Effects on structures (DIN 4150-3: 2016). Vibration velocities not exceeding 3 mm/s at 1 to 10 Hz are recommended in this standard.

4.3.4 Construction Noise and Vibration Guideline

Section 7 of the CNVG provides useful guidance for safe working distances to achieve human comfort (Assessing Vibration: a technical guideline, (DECC, February 2006) and cosmetic building damage (BS7385-2:1993) criteria for a range of different plant and equipment. These have been reproduced below.

Table 4-11: Recommended safe setback distances

Plant Rating / description Safe working distance (meters)

Cosmetic damage (BS7385-2: 1993)

Human response (DECC, 2006)

Vibratory Roller <50 kN (typically 1-2 tonne) <100 kN (typically 2-4 tonne) <200 kN (typically 4-6 tonne) <300 kN (typically 7-13 tonne) >300 kN (typically 13-18 tonne) >300 kN (> 18 tonne)

5 m 6 m 12 m 15 m 20 m 25 m

15 to 20 m 20 m 40 m 100 m 100 m 100 m

Small hydraulic hammer 300 kg – 5 to 12 tonne excavator 2 m 7 m

Medium hydraulic hammer 900 kg – 12 to 18 tonne excavator 7 m 23 m

Large hydraulic hammer 1600 kg – 18 to 34 tonne excavator 22 m 73 m

Vibratory pile driver Sheet piles 2 to 20 m 20 m

Pile boring ≤800 mm 2 m(nominal) 4 m

Jackhammer Hand held 1 m (nominal) 2 m

Page 29: Noise and Vibration assessment

Noise and Vibration assessment

21

4.4 Blasting

Technical Basis for Guidelines to Minimise Annoyance Due to Blasting Overpressure and Ground Vibration (ANZEC, 1990) provides guidance for establishing goals for assessing blast air-blast overpressure and ground vibration. These are listed below in Table 4-12 and Table 4-13.

Table 4-12: Airblast overpressure criteria

Airblast overpressure (dB(Lin Peak)) Allowable exceedance

115 5% of total number of blasts over a 12 month period

120 0%

Table 4-13: Peak particle velocity criteria

Peak particle velocity (mms-1) Allowable exceedance

5 5% of total number of blasts over a 12 month period

10 0%

These criteria would be applicable at the residential receivers at Nurenmerenmong (R20). The air-blast overpressure limit applies within 3.5 m of these receivers. The peak particle velocity ground vibration levels apply within distances equivalent to the longest dimension of the foundations of a building or structure away from buildings and structures associated with R20.

4.5 Other policy considerations

The Kosciuszko National Park Plan of Management (Department of Environment and Conservation, 2006) (KNP POM) outlines tranquillity as a high priority environmental quality of the park. As relevant to this project, the plan lists potential noise impacts to visitors and wildlife as potentially arising from recreational scenic flights and road traffic.

The proposed helicopter use during construction is not classified as recreational use and as such is not covered by the Management Policies and Actions for Recreational and Charter flights (Section 8.17.1 of KNP PoM), however the principle of reducing this impact where possible is noted. Private vehicle use represents the principal generator of noise pollution along key transport corridors of the park.

Page 30: Noise and Vibration assessment

Noise and Vibration assessment

22

5. Estimation of emissions

5.1 Noise emissions during construction

Overall sound power levels (SWLs) were predicted for each phase of construction. These phases were determined based on the indicative staging information as outlined in the EIS. The overall SWLs were estimated with reference to individual plant and equipment levels presented in national and international standards and guidelines, as well as from Jacobs measurement database. Table 5-1 below summarises estimated overall noise emissions for the agreed assessment scenarios. Estimated emissions from blasting should rock be encountered is outlined below in Section 5.2.

Table 5-1: Construction stages and equipment sound power levels

Stage Scenario Equipment No. of plant in 15 min period

Individual equipment maximum LAeq sound power level – dB(A)

Substation

1 a) Early works and site establishment

Excavator 10T

Franna

Truck mounted crane

Delivery truck

TOTAL

1

1

1

2

99

99

94

110

113

1 b) Earthworks and vegetation clearance

Dump truck 20 – 30T

Dozer D8

Excavator 40T

Rockbreaker 10 – 20T1

Vibratory roller 20 – 30T1

TOTAL

3

2

2

1

2

111

111

109

118

109

127

1 c) Civil and building works Concrete truck and pump

Franna

Truck mounted crane

Delivery truck

Excavator 10T

Angle grinder

TOTAL

2

1

1

2

1

2

106

99

94

110

99

108

116

1 d) High voltage electricity lines and structures

Truck mounted crane

Delivery truck

Angle grinder

TOTAL

2

2

2

94

110

99

113

1 e) Pre commissioning activities

Hand tools

TOTAL

6 99

107

1 f) Site clean-up and landscaping

Hand tools

Franna

Truck mounted crane

Delivery truck

TOTAL

6

1

2

2

99

99

94

110

114

Page 31: Noise and Vibration assessment

Noise and Vibration assessment

23

Stage Scenario Equipment No. of plant in 15 min period

Individual equipment maximum LAeq sound power level – dB(A)

1 g) Tie in works Mobile crane

Hand tools

TOTAL

1

5

94

108

108

Transmission line

2 a) Site establishment and deliveries

Excavator 10T

Chainsaw

Franna

Truck mounted crane

Delivery truck

Helicopter

TOTAL

1

1

1

1

1

1

99

99

99

94

110

125

125

2 b) Access tracks Grader

Dozer D8

Excavator 40T

Rockbreaker 10 – 20T1

Vibratory roller 20 – 30T1

TOTAL

2

2

2

1

2

112

111

109

118

109

127

2 c) Earthworks and clearing Dozer D8

Excavator 40T

Rockbreaker 10 – 20T1

Vibratory roller 20 – 30T1

TOTAL

2

2

1

2

111

109

118

109

126

2 d) Structure construction Concrete truck and pump

Franna

Truck mounted crane 50 – 100T

Delivery truck

Angle grinder

TOTAL

2

1

1

2

2

106

99

94

110

108

116

2 e) Overhead stringing of conductors and earth wires

Truck mounted crane 50 – 100T

Winch

TOTAL

2

1

104

108

110

2 f) Site clean-up and rehabilitation

Hand tools

Franna

Truck mounted crane

Delivery truck

TOTAL

6

1

2

2

99

99

94

110

114

2 g) Commissioning Hand tools

TOTAL

6 99

107

Page 32: Noise and Vibration assessment

Noise and Vibration assessment

24

Stage Scenario Equipment No. of plant in 15 min period

Individual equipment maximum LAeq sound power level – dB(A)

Other earthworks

3 a) Helipad Dozer D8

Excavator 40T

Rockbreaker 10 – 20T1

Vibratory roller 20 – 30T1

TOTAL

2

2

1

2

111

109

118

109

126

3 b) Tensioning and pulling sites

Dozer D8

Excavator 40T

Rockbreaker 10 – 20T1

Vibratory roller 20 – 30T1

TOTAL

1

1

1

1

111

109

118

109

125

Note 1: Denotes “annoying” item of equipment as defined in the ICNG (i.e. contains characteristics such as impulsiveness, tonality etc.), and as such includes

a +5 dB penalty adjustment to predictions.

5.2 Noise emissions during construction blasting activities

Depending on the underlying geology, blasting may be required to facilitate the break-up of rock within the disturbance area. Specific blasting and seismic details would need to be assessed on a site and blast specific basis. It is important that the actual buffer zone distances, associated specifically with this project, be identified and appropriate measures taken to limit overpressure and vibration to acceptable levels at identified sensitive receiver locations.

Estimated maximum instantaneous charges to meet the airblast overpressure and vibration limits listed in Section 4.4 were determined using formula as outlined in Australian Standard 2187.2-2006, applicable to free-face blasting in ‘average field conditions’ which states:

Vibration formula:

and

Overpressure formula:

Where:

P = pressure (pascals) V = ground vibration as peak particle velocity in mm/s R = distance between charge and point of measurement in m Q = effective charge mass per delay or maximum instantaneous charge in kilograms

6.1

2/11140−

=

QRV

Page 33: Noise and Vibration assessment

Noise and Vibration assessment

25

5.3 Noise emissions during operation

During operation, the key sources of noise emissions would be from infrastructure at the substation. Estimated emissions from the various sources associated with the substation are listed below in Table 5-2. The individual sound power levels listed were provided by TransGrid. It is noted that reactors can typically exhibit ‘tonality’ or an imbalanced noise spectrum, and so +5 dB(A) corrections were applied consistent with guidance presented in the NPI.

Table 5-2: Noise emissions inventory, operations

Source Plant/equipment Estimated individual sound power level dB(A) per unit

Indicative overall sound power level dB(A)

Substation 500 kV transformers x 3 (each transformer comprises of 3 x individual phases)

100 dB(A) per phase 110

500 kV reactors x 2 95 dB(A)*

Auxiliary transformers x 3 85 dB(A)

Voltage transformers x 2 85 dB(A)

Operational noise can also arise from transmission lines. Typical noise effects associated with transmission lines include:

Corona discharge noise – Audible noise generated by corona on transmission lines has two major components: a ‘wideband’ crackling noise, and a ‘narrowband’ tonal hum (the 100 Hz tone being the most significant). The wideband noise is the dominant component of the emitted sound energy. The narrowband tonal noise component does have the potential to become significant on new conductors with a hydrophobic surface, but only under wet conditions. Effects depend on the humidity in the atmosphere surrounding the transmission lines as well as the voltage of the line. The noise is caused by a breakdown of air into charged particles due to the interaction of the associated electrical field and air particles

Aeolian (wind-induced) noise – during periods of notable wind speed, the resistance caused by air particles flowing across the transmission line has potential to generate audible noise

In a study of corona noise from a 500 kV transmission line undertaken by SLR during damp, foggy conditions a noise level of 44 dB(A) was measured at a distance of 30 m (NGH Environmental, 2013). Noting that corona noise levels vary depending on transmission voltage, meteorological conditions and height, the study estimated a level of 35 dB(A) (i.e. equivalent to night time operational criteria at around 250 m.

5.4 Vibration-generating plant and equipment

Of the plant and equipment expected to be used during construction listed above in Table 5-1, the following have the potential to cause vibration-related impacts:

Rockbreaker 10 – 20T

Vibratory roller 20 – 30T.

The safe working distances for typical items of vibration intensive plant are listed in Table 5-3. The safe working distances are quoted for “cosmetic” damage (refer British Standard BS 7385), human comfort (refer to Assessing Vibration: A technical guideline (DECC, 2006)) and heritage structures (refer to German Standard DIN 4150).

Page 34: Noise and Vibration assessment

Noise and Vibration assessment

26

Table 5-3: Recommended safe working distances for vibration intensive plant

Plant item Rating/description Safe working distance

Cosmetic damage (BS 7385)

Human response (DECC, 2006)

Heritage structures (DIN 4150)

Vibratory roller

<50 kN (typically 1-2 t) 5 m 15 m to 20 m 11 m

<100 kN (typically 2-4 t) 6 m 20 m 13 m

<200 kN (typically 4-6 t) 12 m 40 m 15 m

<300 kN (typically 7-13 t)

15 m 100 m 30 m

>300 kN (typically 13-18 t)

20 m 100 m 40 m

>300 kN (> 18 t) 25 m 100 m 50 m

Small hydraulic hammer

300 kg – 5 to 12 t excavator

2 m 7 m 5 m

Medium hydraulic hammer

900 kg – 12 to 18t excavator

7 m 23 m 15 m

Large hydraulic hammer

1600 kg – 18 to 34 t excavator

22 m 73 m 44 m

The safe working distances presented in Table 5-3 are indicative only and will vary depending on the particular item of plant and local geotechnical conditions.

5.5 Cumulative impacts

Cumulative impacts occur when sensitive receivers are affected by noise and/or vibration impacts from more than one project or development. There is the potential for the nearby receivers (see Section 3.1) being affected by noise from the project, as well as from Snowy 2.0. These impacts were evaluated by adding the predicted noise levels from both projects and comparing against the assessment criteria established in Section 4.

Cumulative impact from other project including HumeLink and various safety improvements and intersection upgrades along the Snowy Mountains Highway Snowy Mountains Highway which may occur concurrently during construction are not expected to contribute to any cumulative noise impacts due to the lack of sensitive receivers in proximity to the project.

Page 35: Noise and Vibration assessment

Noise and Vibration assessment

27

6. Assessment of impacts

6.1 Assessment approach

To evaluate potential construction noise impacts, the Construction Noise Estimator (CNE), (Roads and Maritime Services, 2017) was used. Noise from each stage of construction identified in Table 5-1 was predicted at each of the nearest noise sensitive receivers identified in Section 3.1. Key assessment details are summarised below in Table 6-1.

Table 6-1: Construction noise assessment details

Model input Details

Sources Stages of construction as listed in.

Prediction methodology

Distance based attenuation with corrections applied to account for shielding effects (e.g. terrain).

These predictions were evaluated by comparing the results against the construction NMLs and sleep disturbance limits established in Section 4.

The significance of noise associated with addition traffic movements generated during construction was also evaluated using the CNE. The estimated volumes of project construction traffic (see Section 2.4.3) were added to the volumes along haulage roads in the Snowy 2.0 Main works EIS (EMM, 2019) to determine whether the CNVG and RNP criteria would be exceeded at nearby sensitive receivers along these routes.

The potential for vibration-related impacts was evaluated by comparing the recommended safe setback distances for relevant plant and equipment (see above in Section 5.4) with the locations of the identified surrounding sensitive receivers and heritage structures.

The potential for airblast overpressure and vibration impacts during blasting activities was evaluated by predicting the safe setback distances to meet ANZEC, 1990 for different maximum instantaneous charges. These setback distances were compared to the relative location of the identified nearby receivers to assess the potential for impacts.

Operational noise levels from the substation were predicted using the CONCAWE algorithm (Manning, 1981) which includes corrections for meteorological effects as well as attenuation associated with source to receiver separation, atmospheric absorption, ground effects and barriers. Levels were calculated at the surrounding receivers identified in Section 3.1 and evaluated by comparing against the criteria established in Section 4.2.4. Corona noise impacts were evaluated by comparing the emissions from a similar 500 kV transmission line with the relative location of the surrounding receivers identified in Section 3.1.

Finally cumulative noise impacts were evaluated by adding the predicted noise levels from the project, the Snowy 2.0 project and the HumeLink project at the surrounding receivers identified in Section 3.1, and comparing against the assessment criteria established in Section 4.

6.2 Predicted construction noise impacts

Predicted noise levels from the project construction activities listed in Table 5-1 at the identified nearby sensitive receiver locations (with results for A16 also listed) are summarised below in Table 6-2.

Page 36: Noise and Vibration assessment

Noise and Vibration assessment

28

Table 6-2: Predicted worst-case Leq 15 min dB(A) noise levels, construction

Stage NML Leq 15 min dB(A) for R20 NML Leq

15 min

dB(A) for A3 and A5

Predicted worst-case Leq 15 min dB(A)

Day, standard hours

Day, outside standard hours

Evening Night When in-use

A3 A5 R20 A16

Substation

1 a) 45 40 35 35 60 <20 <20 <20 <20

1 b) 45 40 35 35 60 <20 <20 <20 <20

1 c) 45 40 35 35 60 <20 <20 <20 <20

1 d) 45 40 35 35 60 <20 <20 <20 <20

1 e) 45 40 35 35 60 <20 <20 <20 <20

1 f) 45 40 35 35 60 <20 <20 <20 <20

1 g) 45 40 35 35 60 <20 <20 <20 <20

Transmission line

2 a) 45 40 35 35 60 30 <20 <20 57

2 b) 45 40 35 35 60 32 <20 <20 59

2 c) 45 40 35 35 60 31 <20 <20 58

2 d) 45 40 35 35 60 21 <20 <20 48

2 e) 45 40 35 35 60 <20 <20 <20 42

2 f) 45 40 35 35 60 <20 <20 <20 46

2 g) 45 40 35 35 60 <20 <20 <20 39

Other works

3 a) 45 40 35 35 60 <20 <20 <20 32

3 b) 45 40 35 35 60 30 <20 <20 57

As displayed, predicted worst-case noise levels during construction were predicted to remain below project NMLs at the identified receiver locations (refer to Section 3.1). Levels up to 59 dB(A) were predicted at receiver A16 (Snowy 2.0 works accommodation) although this is not considered to be a sensitive receiver given its association with Snowy 2.0.

Given that construction works are expected to be carried out 12 hours per day, seven days per week between the hours of 6 am and 6 pm, the potential for sleep disturbance impacts from noise during construction activities was also evaluated. As outlined above in Section 4.1.3, sleep disturbance impacts from construction noise sources are considered likely when LA1 (1 minute) noise levels exceed the LA90 (15 minute) by 15 dB(A) or more. Noting the adopted night time LA90 (15 minute) (i.e. RBL) or 30 dB(A), this limit equates to LA1 (1 minute) 45 dB(A) and applies at residential receiver R20. The highest predicted LA1 (1 minute) at R20 for all activities listed in Table 5-1 was 26 dB(A), well below the sleep disturbance screening criterion. Considering this, it is unlikely that sleep disturbance impacts would occur during construction of the project.

Page 37: Noise and Vibration assessment

Noise and Vibration assessment

29

6.3 Predicted construction traffic noise impacts

Additional traffic movements anticipated during construction of the project are outlined in Section 2.4. The noise and vibration assessment prepared for the Snowy 2.0 Main Works EIS (EMM, 2019) included traffic forecasts along key haulage routes. These forecasts included traffic expected to be from the Snowy 2.0 Main Works. Using these flows to represent existing conditions and applying the maximum expected construction traffic volumes for the project (see Section 2.4), Table 6-3 summarises the results predicted at the most-affected sensitive receivers along each road utilised by project construction traffic.

Table 6-3: Predicted construction traffic noise impacts

Haulage road Predicted change in noise levels at most-affected receiver dB(A)

Predicted noise levels at most-affected receiver dB(A)

RNP criteria [external] dB(A)

Day (7am to 10pm)

Night (10pm to 7am)

Day (7am to 10pm)

Night (10pm to 7am)

Day (7am to 10pm)

Night (10pm to 7am)

Snowy Mountains Highway

+1.0 +2.6 54.0 52.2 60 55

Link Road +1 +2.4 52.7 51.2 60 55

Lobs Hole Ravine Road

+0.6 +1.4 53.2 51.8 60 55

As listed, although increases greater than 2 dB(A) at night were predicted at the most affected receivers along the Snowy Mountains Highway and Link Road, the resulting overall levels (including traffic from Snowy 2.0) do not exceed the criteria listed in the RNP. As such, it can be concluded that additional traffic movements from project construction activities are not expected to result in unacceptable changes in traffic noise levels at sensitive receivers along these key haulage routes.

As identified in Section 2.4.3 there are a number of other roads that would be utilised by project construction vehicles. In the absence of baseline traffic flows it isn’t possible to apply the same assessment approach as above. Along these routes it is anticipated that there may be receivers where traffic noise levels may increase by more than 2 dB(A) as a result of the additional traffic from the project. Still, it is not expected that these increases would result in levels exceeding the criteria listed in the RNP and as such, no actions are expected to be required.

6.4 Predicted construction vibration impacts

As identified in Section 5.4 and Section 5.2, the major potential sources of vibration impacts for the project were identified as being the use hydraulic rock breakers and vibratory rollers, as well as blasting activities. Considering the setback distances for hydraulic rock breakers and vibratory rollers in Section 5.4 and the relative location of the surrounding sensitive receivers, it was concluded that building cosmetic damage and human comfort impacts from the use of these plant and equipment would be unlikely. Care would need to be taken if works involving use hydraulic rock breakers and vibratory rollers is required within 50 m of heritage items R45 and R49, and appropriate measures have been included below in Section 7.

6.5 Predicted construction blasting impacts

Using the approach outlined in Section 5.2, the setback distances in Figure 6-1 were estimated to provide an indication of acceptable blast sizes. This graph displays the distance that the criteria listed in Section 4.4 would be met for different maximum instantaneous charge (MIC) kg values. Again, these values are expected to vary significantly depending on the geological conditions, local shielding and meteorological factors at the site.

Page 38: Noise and Vibration assessment

Noise and Vibration assessment

30

Figure 6-1: Estimated effective mass charges to minimise annoyance

Figure 6-1 shows that the risk of airblast or ground vibration impacts during blasting would be minimal for most vibration sensitive receivers. However, in view of the potential proximity of some heritage items within the Lobs Hole Ravine area, it is important that where blasting is required in this area, monitoring is undertaken at critical locations surrounding the site to confirm predicted over-pressure and vibration levels and to in turn modify the blast design and buffer zones accordingly around the site. Measures to manage potential risks associated with blasting activities are included below in Section 7.

6.6 Predicted operation noise impacts

6.6.1 Substation

Predicted noise levels from operation of the substation are summarised below in Table 6-4.

Table 6-4: Predicted operational noise levels, substation

Project operational noise criteria Leq 15 min dB(A) for R20

Project operational noise criteria Leq 15 min dB(A) for A3 and A5

Predicted worst-case Leq 15 min dB(A)

Day Evening Night When in-use A3 A5 R20 A16

40 35 35 48 <20 <20 <20 <20

Operational noise levels were predicted to be less than 20 dB(A) at the identified receiver locations. This is well below the established operational noise criteria, as well as the operational sleep disturbance screening criterion of LAeq,15min 40 dB(A) at receiver R20. Considering this, noise impacts from the operation of the substation is not anticipated.

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

50.0

10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200

Max

imum

Inst

anta

neou

s Ch

arge

(MIC

) ( k

g)

Distance from Blast (m)

Maximum MIC per delay

Overpressure

Vibration

Page 39: Noise and Vibration assessment

Noise and Vibration assessment

31

6.6.2 Transmission line

As outlined above in Section 5.3, a study of corona noise discharge from a 500 kV transmission line under conducive meteorological conditions study estimated a level of 35 dB(A) (i.e. equivalent to night time operational criteria at around 250 m. Given that all of the sensitive receiver locations identified in Section 3.1 are more than 1 km from the transmission line, corona noise impacts are not expected and were not considered further in the assessment. Further, it is expected that the transmission line would be designed and constructed to ensure that corona discharge complies with relevant NPI criteria.

6.7 Predicted cumulative impacts

Worst-case cumulative noise levels at the receivers identified in Section 3.1 are listed below in Table 6-5.

Table 6-5: Worst-case cumulative construction noise review

Predicted worst-case Leq 15 min

dB(A), project contribution Predicted worst-case Leq 15 min

dB(A), Snowy 2.0 contribution Predicted worst-case Leq 15 min

dB(A), cumulative levels

A3 A5 R20 A16 A3 A5 R20 A16 A3 A5 R20 A16

32 <20 <20 59 38 34 <30 58 39 34 <30 62

Receiver R20: Day time (standard hours) NML = Leq 15 min 45 dB(A); Day time (outside standard hours) NML = Leq 15 min 40 dB(A); evening NML

= Leq 15 min 35 dB(A); and night time NML = Leq 15 min 35 dB(A); Receivers A3 and A5: NML when in-use = Leq 15 min 60 dB(A)

At the nearest residential receiver R20, worst-case cumulative noise levels from construction activities associated with the project and Snowy 2.0 were predicted to remain below NMLs for all periods. At recreational receivers A3 and A5, cumulative levels up to 39 dB(A) were predicted, well below the 60 dB(A) NML. Levels up to 62 dB(A) were predicted at receiver A16. It is noted that construction of the HumeLink project may also be underway at the same time, although the environmental impact assessment has not yet been completed for this project so its potential noise impacts are not known. Where construction activities took place at the same time, cumulative noise levels could be as high as 3 dB(A) above the contribution from the noisier project.

Considering the results above, it was concluded that cumulative construction noise impacts from the project and Snowy 2.0 would not result in unacceptable noise levels at the nearest receivers around the project.

As such, it was determined that the potential for noise and vibration impacts during the project is limited. Measures to minimise noise and vibration from the project in line with best practice were developed. These are presented below in Section 7.

Page 40: Noise and Vibration assessment

Noise and Vibration assessment

32

7. Mitigation and management

Standard techniques for controlling noise impacts during construction are presented in the ICNG. As listed in Table 7-1, this control should be implemented as reasonable and feasible.

Table 7-1: Proposed construction noise management, standard measures

Measure Details Timing

Standard best practice ICNG measures

Implementation of relevant standard measures as outlined in Section 6 of the ICNG.

Prior to and during Construction

Assessing Vibration: a technical guideline, (DECC, February 2006) provides general guidance for limiting vibration impacts during construction. Relevant recommendations have been reproduced below and should be considered as appropriate.

Table 7-2: Proposed vibration management, standard measures

Measure Details Timing

Controlling vibration levels from the source

Do not conduct vibration intensive works within the recommended safe setback distances. Avoid the use of vibration intensive plant within the nominated human comfort distances.

During construction

Based on the outcomes of the assessment, the following additional measures were also recommended:

Table 7-3: Proposed vibration management, additional measures

Measure Details Timing

Controlling vibration levels from the source

• Particular care should be taken when undertaking vibration-intensive activities (e.g. use of hydraulic rock breakers and vibratory rollers, and blasting) within distances approaching the recommended safe setback distances around heritage items R45 and R49. Where maintaining these setback distances isn’t possible, a suitably qualified person should be present or monitoring should be undertaken during the works to suspend activities in the instance of any issues

• A detailed blast plan would be prepared by the blasting contractor prior to each blast to mitigate the potential for the recommended safe setback distances being encroached

During construction

No noise impacts were determined during operation of the project and therefore no measures have been recommended.

Page 41: Noise and Vibration assessment

Noise and Vibration assessment

33

8. Conclusion

An assessment was completed to evaluate the potential for noise and vibration impacts associated with the construction and operation of the project. Potential noise, vibration and airblast overpressure levels at identified surrounding receiver locations were assessed quantitatively using various predictive methods. Results were evaluated by comparing the predictions against limits established based on guidance from relevant NSW, National and international standards and guidelines.

Using this approach, the following potential for impacts were determined:

Predicted worst-case noise levels during construction were predicted to remain below project NMLs at the identified receiver locations. Levels up to 59 dB(A) were predicted at receiver A16 (Snowy 2.0 works accommodation) although this is not considered to be a sensitive receiver given its association with Snowy 2.0

Sleep disturbance impacts were not predicted during construction or operation

Additional traffic movements from project construction activities are not expected to result in unacceptable changes in traffic noise levels at sensitive receivers along the intended haulage routes

Building cosmetic damage and human comfort impacts from vibration generated from the use of hydraulic rock breakers and vibratory rollers at identified receiver locations would be unlikely. Care would need to be taken if this equipment was required within 50 m of heritage items R45 and R49

Airblast overpressure and vibration impacts from blasting activities were not anticipated at the identified sensitive receiver locations. Again, care would be required to avoid damage to R45 and R49 if blasting was required around these locations

Operational noise from substation and transmission lines would not result in unacceptable impacts at the identified sensitive receivers

The potential for cumulative noise impacts during the construction of the project and Snowy 2.0 was also determined to be negligible with cumulative levels remaining below NMLs at the identified sensitive receiver locations.

Considering these outcomes, it was determined that the potential for noise and vibration impacts during the project was limited. Still, measures to minimise construction noise in line with best practice were recommended as required, with specific measures recommended regarding vibration. No noise impacts were determined during operations and so no measures were recommended.

Page 42: Noise and Vibration assessment

Noise and Vibration assessment

34

9. References

Australia and New Zealand Environment Council, (1990). Technical basis for guidelines to minimise annoyance due to blasting overpressure and ground vibration

British Standards Group, (1993). British Standard BS 7385-2:1993 Evaluation and measurement for vibration in buildings – Part 2: Guide to damage levels from groundborne vibration

British Standards Group, (2008). British Standard 6472-1: 2008 Guide to evaluation of human exposure to vibration in buildings Part 1: Vibration sources other than blasting

EMM, (2019). Appendix R: Noise and Vibration Impact Assessment Snowy 2.0 Main Works

German Standards (DIN-Normen), (2016). DIN 4150-3 Vibrations in buildings – Part 3: Effects on structures

Jacobs Group Australia, (2020). Snowy 2.0 Transmission Line Connection Project Non-Aboriginal Heritage Assessment

NGH Environmental, (2013). Noise Assessment Nyngan Solar Plant. NGH Environmental, Wagga Wagga, NSW

NSW Department of Environment and Climate Change, (2009). Interim Construction Noise Guideline. DECC, Sydney South, NSW

NSW Department of Environment and Conservation, (2006). Assessing Vibration: a technical guideline

Department of Environment, Climate Change and Water, (2010). NSW Road Noise Policy. DECCW, Sydney South, NSW

NSW Environmental Protection Authority, (2017). Noise Policy for Industry. NSW EPA, Sydney South

Roads and Maritime Service, (2016). Construction Noise and Vibration Guideline

Standards Australia, (2006). Australian Standard AS2187.2 – 2006 Explosives – Storage and use Part 2: Use of explosives

Standards Australia, (2010). Australian Standard 2436-2010: Guide to noise and vibration control on construction, demolition and maintenance sites.

Standards Australia, (2016). Australian / New Zealand Standard AS/NZS 2107:2016 Acoustics: Recommended design sound levels and reverberation times for building interiors

Page 43: Noise and Vibration assessment