NodeB Installation Manual-System Commissioning

download NodeB Installation Manual-System Commissioning

of 73

Transcript of NodeB Installation Manual-System Commissioning

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    1/73

    Chapter 1 System Commissioning Process 1-1.................................................

    1.1 About This Chapter 1-1................................................................................1.2 Manual Application in NodeB Family 1-1......................................................

    1.3 Reference Manuals 1-1................................................................................1.4 Tools for System Commissioning 1-2...........................................................1.5 Prerequisites for System Commissioning 1-2...............................................1.6 Process of System Commissioning 1-3........................................................

    Chapter 2 Commissioning Hardware 2-1.............................................................

    2.1 About This Chapter 2-1................................................................................2.2 Verifying Hardware Installation 2-1...............................................................

    2.2.1 Overview 2-1........................................................................................

    2.2.2 Procedures 2-2.....................................................................................2.3 Verifying DIP Switch and Jumper Settings 2-2.............................................2.3.1 Overview 2-2........................................................................................2.3.2 Procedures for Macro NodeB 2-3........................................................2.3.3 Procedures for Mini NodeB 2-3............................................................

    2.4 Verifying VSWR of Antenna and Feeder System 2-4...................................2.4.1 Overview 2-4........................................................................................2.4.2 Procedures 2-4.....................................................................................

    2.5 Checking Macro NodeB Power-on 2-6.........................................................

    2.5.1 Overview 2-6........................................................................................2.5.2 Procedures 2-6.....................................................................................

    2.6 Checking Mini NodeB Power-on 2-7............................................................2.6.1 Overview 2-7........................................................................................2.6.2 Procedures 2-7.....................................................................................

    Chapter 3 Commissioning Software 3-1..............................................................

    3.1 About This Chapter 3-1................................................................................3.2 Verifying Operation and Maintenance Channel 3-1......................................

    3.2.1 Overview 3-1........................................................................................3.2.2 Procedures of Verifying Local Maintenance Channel 3-1....................3.2.3 Procedures of Verifying IPoA Maintenance Channel 3-2.....................3.2.4 Procedures of Verifying Alarm Report 3-2...........................................

    3.3 Verifying Software Version 3-3.....................................................................3.3.1 Overview 3-3........................................................................................3.3.2 Procedures 3-3.....................................................................................

    3.4 Checking Data Consistency 3-4...................................................................3.4.1 Overview 3-4........................................................................................

    3.4.2 Procedures 3-4.....................................................................................

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    2/73

    Chapter 4 Commissioning Iub Interface 4-1........................................................

    4.1 About This Chapter 4-1................................................................................4.2 Verifying Iub Interface Data Consistency 4-1...............................................

    4.2.1 Overview 4-1........................................................................................4.2.2 Procedures for IMA Group in Use 4-1..................................................4.2.3 Procedures for UNI Link in Use 4-2.....................................................

    4.3 Verifying E1/T1 Link Status 4-4....................................................................4.3.1 Overview 4-4........................................................................................4.3.2 Procedures 4-4.....................................................................................

    4.4 Verify IMA Group and IMA Link Status 4-4...................................................4.4.1 Overview 4-4........................................................................................4.4.2 Procedures 4-4.....................................................................................

    4.5 Verifying UNI Link Status 4-5.......................................................................4.5.1 Overview 4-5........................................................................................4.5.2 Procedures 4-5.....................................................................................

    4.6 Verifying NCP and CCP Status 4-6..............................................................4.6.1 Overview 4-6........................................................................................4.6.2 Procedures 4-6.....................................................................................

    4.7 Verifying AAL2NODE and AAL2PATH Status 4-6........................................4.7.1 Overview 4-6........................................................................................4.7.2 Procedures 4-6.....................................................................................

    Chapter 5 Commissioning Clock 5-1...................................................................

    5.1 About This Chapter 5-1................................................................................5.2 Verifying Center DA 5-1................................................................................

    5.2.1 Overview 5-1........................................................................................5.2.2 Procedures 5-1.....................................................................................

    5.3 Verifying Clock Source 5-2...........................................................................5.3.1 Overview 5-2........................................................................................5.3.2 Procedures 5-2.....................................................................................

    Chapter 6 Commissioning Uplink RF Channel 6-1.............................................

    6.1 About This Chapter 6-1................................................................................6.2 Calibrating Uplink RF Channel Gain of Macro NodeB 6-1...........................

    6.2.1 Overview 6-1........................................................................................6.2.2 Procedures 6-1.....................................................................................

    6.3 Calibrating Uplink RF Channel Gain of Mini NodeB 6-3...............................6.3.1 Overview 6-3........................................................................................6.3.2 Procedures 6-3.....................................................................................

    6.4 Setting NDDL Unit Attenuation (Macro NodeB) 6-4.....................................6.4.1 Overview 6-4........................................................................................

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    3/73

    6.4.2 Procedures 6-4.....................................................................................

    Chapter 7 Commissioning Downlink RF Channel 7-1........................................

    7.1 About This Chapter 7-1................................................................................

    7.2 Calibrating DL RF Channel Gain of Macro NodeB Cell 7-1..........................7.2.1 Overview 7-1........................................................................................7.2.2 Procedures 7-2.....................................................................................

    7.3 Calibrating DL RF Channel Gain of Mini NodeB Cell 7-3.............................7.3.1 Overview 7-3........................................................................................7.3.2 Procedures 7-4.....................................................................................

    Chapter 8 Commissioning Service 8-1................................................................

    8.1 About This Chapter 8-1................................................................................

    8.2 Verifying Cell Status 8-1...............................................................................8.2.1 Overview 8-1........................................................................................8.2.2 Procedures 8-1.....................................................................................

    8.3 Verifying Service 8-2....................................................................................8.3.1 Overview 8-2........................................................................................8.3.2 Procedures 8-2.....................................................................................

    Chapter 9 Handling Problems 9-1........................................................................

    9.1 About This Chapter 9-1................................................................................9.2 E1/T1 Abnormal 9-1.....................................................................................

    9.2.1 Fault Symptom 9-1...............................................................................9.2.2 Procedures 9-1.....................................................................................

    9.3 "Number of Tx/Rx Links Configured" Not Equal to " Number of Tx/ Rx Links Activated" in a IMA Group 9-3.............................................................

    9.3.1 Fault Symptom 9-3...............................................................................9.3.2 Procedures 9-3.....................................................................................

    9.4 NCP/CCP/AAL2NODE Abnormal 9-3...........................................................9.4.1 Fault Symptom 9-3...............................................................................9.4.2 Procedures for IMA Group Bearing NCP, CCP or AAL2NODE 9-3.....9.4.3 Procedures for UNI Link Bearing NCP, CCP or AAL2NODE 9-4.........

    9.5 "Local Cell Status=Local Cell Unavailable" 9-4............................................9.5.1 Fault Symptom 9-4...............................................................................9.5.2 Procedures 9-4.....................................................................................

    9.6 "Cell Operation Status=Cell not Setup" While "Local Cell Status=Local Cell Available" 9-5.....................................................................................

    9.6.1 Fault Symptom 9-5...............................................................................9.6.2 Procedures 9-5.....................................................................................

    9.7 Call Failure while "Cell Operation Status=Enable" 9-6.................................9.7.1 Fault Symptom 9-6...............................................................................

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    4/73

    9.7.2 Procedures 9-6.....................................................................................

    Appendix A Measuring VSWR of Antenna & Feeder System A-1......................

    A.1 Introduction to SiteMaster A-1......................................................................

    A.2 Selecting Measurement Mode A-1...............................................................A.3 Setting Frequency Range A-2......................................................................A.4 Calibrating the SiteMaster A-2......................................................................A.5 Measuring VSWR A-3..................................................................................A.6 Displaying VSWR Value A-3........................................................................

    Appendix B Starting 141 Test B-1.........................................................................

    Appendix C Transmitter Analyzer Parameters Configuration C-1.....................

    C.1.1 Overview C-1.............................................................................................C.1.2 Testing Channel Total Power C-1.............................................................C.1.3 Test Code Domain Power C-1...................................................................

    Index .................................................................................................................

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    5/73

    HUAWEI

    WCDMA NodeB

    Installation Manual System Commissioning

    V100R003

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    6/73

    WCDMA NodeB

    Installation Manual

    Volume System Commissioning

    Manual Version T2-030455-20040930-C-1.31

    Product Version V100R003

    BOM 31041355

    Huawei Technologies Co., Ltd. provides customers with comprehensive technical support

    and service. Please feel free to contact our local office or company headquarters.

    Huawei Technologies Co., Ltd.

    Addr es s: Administration Building, Huawei Technologies Co., Ltd.,

    Bantian, Longgang District, Shenzhen, P. R. China

    Postal Code: 518129

    Website: http://www.huawei.com

    Email: [email protected]

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    7/73

    Copyright 2004 Huawei Technologies Co., Ltd.

    All Rights Reserved

    No part of this manual may be reproduced or transmitted in any form or by any

    means without prior written consent of Huawei Technologies Co., Ltd.

    Trademarks

    , HUAWEI, C&C08, EAST8000, HONET, , ViewPoint, INtess, ETS, DMC,

    TELLIN, InfoLink, Netkey, Quidway, SYNLOCK, Radium, M900/M1800,TELESIGHT, Quidview, Musa, Airbridge, Tellwin, Inmedia, VRP, DOPRA, iTELLIN,

    HUAWEI OptiX, C&C08 iNET, NETENGINE, OptiX, iSite, U-SYS, iMUSE, OpenEye,

    Lansway, SmartAX, infoX, TopEng are trademarks of Huawei Technologies Co.,

    Ltd.

    All other trademarks mentioned in this manual are the property of their respective

    holders.

    Notice

    The information in this manual is subject to change without notice. Every effort has

    been made in the preparation of this manual to ensure accuracy of the contents, but

    all statements, information, and recommendations in this manual do not constitute

    the warranty of any kind, express or implied.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    8/73

    Summary of Updates

    This section provides the update history of this manual and introduces the contents of

    subsequent updates.

    Update History

    This manual is updated for a major product version to maintain consistency with system

    hardware or software versions and to incorporate customer suggestions.

    Manual Version Notes

    T2-030455-20040430-C-1.30 Initial field trial release

    T2-030455-20040930-C-1.31 Secondary field trial release

    Updates of Contents

    Updates between manual versions are cumulative. Therefore, the latest manual

    version contains all updates made to previous versions.

    Updates Made between Versions 1.30 and 1.31

    z Optimize the description of operation instruction.z Add "about this chapter" section in each chapter.z Add index

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    9/73

    About This Manual

    Release Notes

    The product version that corresponds to the manual is WCDMA NodeB V100R003.

    Organization of the Manual

    The manual consists of nine chapters and three appendixes.

    Chapter 1 System Commissioning Process describes reference manuals, tools,

    prerequisites and commissioning process of system commissioning.

    Chapter 2 Commissioning Hardware describes the procedures for commissioning

    NodeB hardware.

    Chapter 3 Commissioning Software describes the procedures for commissioning

    NodeB software.

    Chapter 4 Commissioning Iub Interface describes the procedures for

    commissioning the Iub interface.

    Chapter 5 Commissioning Clock describes the procedures for commissioning the

    NodeB clock.

    Chapter 6 Commissioning Uplink RF Channel describes the procedures for

    commissioning NodeB uplink RF channel.

    Chapter 7 Commissioning Downlink RF Channel describes the procedures for

    commissioning NodeB downlink RF channel.

    Chapter 8 Commissioning Service describes the procedures for commissioning

    NodeB service.

    Chapter 9 Handling Problems describes the procedures for handling NodeB fault

    during NodeB system commissioning.

    Appendix A Measuring VSWR of Antenna Feeder System

    Appendix B Starting 141 Test

    Appendix C Transmitter Analyzer Parameters Configuration

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    10/73

    Target Readers

    The manual is intended for the following readers:

    z NodeB Installersz NodeB Field Engineersz NodeB System Engineers

    Conventions

    This document uses the following conventions:

    I. General conventions

    Convention Description

    Arial Normal paragraphs are in Arial.

    Arial Narrow Warnings, cautions, notes and tips are in Arial Narrow.

    Bold Headings, Command, Command Description are in boldface.

    Terminal Display Terminal Display is in Courier New; message input by the user via theterminal is in boldface.

    II. Symbols

    Eye-catching symbols are also used in this document to highlight the points worthy of

    special attention during the operation. They are defined as follows:

    Caution , Warning , Danger : Means reader be extremely careful during the

    operation.

    Note , Comment , Tip , Knowhow , Thought : Means a complementary description.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    11/73

    Installation Manual System Commissioning WCDMA NodeB Table of Contents

    i

    Table of Contents

    Chapter 1 System Commissioning Process............................................................................... 1-1

    1.1 About This Chapter............................................................................................................ 1-1

    1.2 Manual Application in NodeB Family................................................................................. 1-1

    1.3 Reference Manuals............................................................................................................ 1-1

    1.4 Tools for System Commissioning ...................................................................................... 1-2

    1.5 Prerequisites for System Commissioning.......................................................................... 1-2

    1.6 Process of System Commissioning................................................................................... 1-3

    Chapter 2 Commissioning Hardware .......................................................................................... 2-1

    2.1 About This Chapter............................................................................................................ 2-1 2.2 Verifying Hardware Installation.......................................................................................... 2-1

    2.2.1 Overview ................................................................................................................. 2-1

    2.2.2 Procedures .............................................................................................................. 2-2

    2.3 Verifying DIP Switch and Jumper Settings........................................................................ 2-2

    2.3.1 Overview ................................................................................................................. 2-2

    2.3.2 Procedures for Macro NodeB.................................................................................. 2-3

    2.3.3 Procedures for Mini NodeB..................................................................................... 2-3

    2.4 Verifying VSWR of Antenna and Feeder System.............................................................. 2-4

    2.4.1 Overview ................................................................................................................. 2-4

    2.4.2 Procedures .............................................................................................................. 2-4

    2.5 Checking Macro NodeB Power-on .................................................................................... 2-6

    2.5.1 Overview ................................................................................................................. 2-6

    2.5.2 Procedures .............................................................................................................. 2-6

    2.6 Checking Mini NodeB Power-on........................................................................................ 2-7

    2.6.1 Overview ................................................................................................................. 2-7

    2.6.2 Procedures .............................................................................................................. 2-7

    Chapter 3 Commissioning Software............................................................................................ 3-1

    3.1 About This Chapter............................................................................................................ 3-1

    3.2 Verifying Operation and Maintenance Channel................................................................. 3-1

    3.2.1 Overview ................................................................................................................. 3-1

    3.2.2 Procedures of Verifying Local Maintenance Channel............................................. 3-1

    3.2.3 Procedures of Verifying IPoA Maintenance Channel.............................................. 3-2

    3.2.4 Procedures of Verifying Alarm Report .................................................................... 3-2

    3.3 Verifying Software Version ................................................................................................ 3-3

    3.3.1 Overview ................................................................................................................. 3-3

    3.3.2 Procedures .............................................................................................................. 3-3

    3.4 Checking Data Consistency............................................................................................... 3-4

    3.4.1 Overview ................................................................................................................. 3-4

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    12/73

    Installation Manual System Commissioning WCDMA NodeB Table of Contents

    ii

    3.4.2 Procedures .............................................................................................................. 3-4

    Chapter 4 Commissioning Iub Interface ..................................................................................... 4-1

    4.1 About This Chapter............................................................................................................ 4-1

    4.2 Verifying Iub Interface Data Consistency .......................................................................... 4-1 4.2.1 Overview ................................................................................................................. 4-1

    4.2.2 Procedures for IMA Group in Use........................................................................... 4-1

    4.2.3 Procedures for UNI Link in Use............................................................................... 4-2

    4.3 Verifying E1/T1 Link Status ............................................................................................... 4-4

    4.3.1 Overview ................................................................................................................. 4-4

    4.3.2 Procedures .............................................................................................................. 4-4

    4.4 Verify IMA Group and IMA Link Status.............................................................................. 4-4

    4.4.1 Overview ................................................................................................................. 4-4

    4.4.2 Procedures .............................................................................................................. 4-4

    4.5 Verifying UNI Link Status................................................................................................... 4-5

    4.5.1 Overview ................................................................................................................. 4-5

    4.5.2 Procedures .............................................................................................................. 4-5

    4.6 Verifying NCP and CCP Status ......................................................................................... 4-6

    4.6.1 Overview ................................................................................................................. 4-6

    4.6.2 Procedures .............................................................................................................. 4-6

    4.7 Verifying AAL2NODE and AAL2PATH Status................................................................... 4-6

    4.7.1 Overview ................................................................................................................. 4-6

    4.7.2 Procedures .............................................................................................................. 4-6

    Chapter 5 Commissioning Clock................................................................................................. 5-1 5.1 About This Chapter............................................................................................................ 5-1

    5.2 Verifying Center DA........................................................................................................... 5-1

    5.2.1 Overview ................................................................................................................. 5-1

    5.2.2 Procedures .............................................................................................................. 5-1

    5.3 Verifying Clock Source ...................................................................................................... 5-2

    5.3.1 Overview ................................................................................................................. 5-2

    5.3.2 Procedures .............................................................................................................. 5-2

    Chapter 6 Commissioning Uplink RF Channel........................................................................... 6-1

    6.1 About This Chapter............................................................................................................ 6-1 6.2 Calibrating Uplink RF Channel Gain of Macro NodeB....................................................... 6-1

    6.2.1 Overview ................................................................................................................. 6-1

    6.2.2 Procedures .............................................................................................................. 6-1

    6.3 Calibrating Uplink RF Channel Gain of Mini NodeB.......................................................... 6-3

    6.3.1 Overview ................................................................................................................. 6-3

    6.3.2 Procedures .............................................................................................................. 6-3

    6.4 Setting NDDL Unit Attenuation (Macro NodeB)................................................................. 6-4

    6.4.1 Overview ................................................................................................................. 6-4

    6.4.2 Procedures .............................................................................................................. 6-4

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    13/73

    Installation Manual System Commissioning WCDMA NodeB Table of Contents

    iii

    Chapter 7 Commissioning Downlink RF Channel...................................................................... 7-1

    7.1 About This Chapter............................................................................................................ 7-1

    7.2 Calibrating DL RF Channel Gain of Macro NodeB Cell..................................................... 7-1

    7.2.1 Overview ................................................................................................................. 7-1

    7.2.2 Procedures .............................................................................................................. 7-2

    7.3 Calibrating DL RF Channel Gain of Mini NodeB Cell ........................................................ 7-3

    7.3.1 Overview ................................................................................................................. 7-3

    7.3.2 Procedures .............................................................................................................. 7-4

    Chapter 8 Commissioning Service.............................................................................................. 8-1

    8.1 About This Chapter............................................................................................................ 8-1

    8.2 Verifying Cell Status .......................................................................................................... 8-1

    8.2.1 Overview ................................................................................................................. 8-1

    8.2.2 Procedures .............................................................................................................. 8-1

    8.3 Verifying Service................................................................................................................ 8-2

    8.3.1 Overview ................................................................................................................. 8-2

    8.3.2 Procedures .............................................................................................................. 8-2

    Chapter 9 Handling Problems...................................................................................................... 9-1

    9.1 About This Chapter............................................................................................................ 9-1

    9.2 E1/T1 Abnormal ................................................................................................................. 9-1

    9.2.1 Fault Symptom........................................................................................................ 9-1

    9.2.2 Procedures .............................................................................................................. 9-1

    9.3 "Number of Tx/Rx Links Configured" Not Equal to "Number of Tx/Rx Links Activated" in a

    IMA Group................................................................................................................................ 9-3 9.3.1 Fault Symptom........................................................................................................ 9-3

    9.3.2 Procedures .............................................................................................................. 9-3

    9.4 NCP/CCP/AAL2NODE Abnormal...................................................................................... 9-3

    9.4.1 Fault Symptom........................................................................................................ 9-3

    9.4.2 Procedures for IMA Group Bearing NCP, CCP or AAL2NODE.............................. 9-3

    9.4.3 Procedures for UNI Link Bearing NCP, CCP or AAL2NODE ................................. 9-4

    9.5 "Local Cell Status=Local Cell Unavailable" ....................................................................... 9-4

    9.5.1 Fault Symptom........................................................................................................ 9-4

    9.5.2 Procedures .............................................................................................................. 9-4

    9.6 "Cell Operation Status=Cell not Setup" While "Local Cell Status=Local Cell Available"... 9-5

    9.6.1 Fault Symptom........................................................................................................ 9-5

    9.6.2 Procedures .............................................................................................................. 9-5

    9.7 Call Failure while "Cell Operation Status=Enable" ............................................................ 9-6

    9.7.1 Fault Symptom........................................................................................................ 9-6

    9.7.2 Procedures .............................................................................................................. 9-6

    Appendix A Measuring VSWR of Antenna & Feeder System ...................................................A-1

    A.1 Introduction to SiteMaster .................................................................................................A-1

    A.2 Selecting Measurement Mode...........................................................................................A-1

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    14/73

    Installation Manual System Commissioning WCDMA NodeB Table of Contents

    iv

    A.3 Setting Frequency Range..................................................................................................A-2

    A.4 Calibrating the SiteMaster .................................................................................................A-2

    A.5 Measuring VSWR..............................................................................................................A-3

    A.6 Displaying VSWR Value....................................................................................................A-3

    Appendix B Starting 141 Test ......................................................................................................B-1

    Appendix C Transmitter Analyzer Parameters Configuration..................................................C-1

    C.1.1 Overview.................................................................................................................C-1

    C.1.2 Testing Channel Total Power .................................................................................C-1

    C.1.3 Test Code Domain Power ......................................................................................C-1

    Index ................................................................................................................................................ i-1

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    15/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 1 System Commissioning Process

    1-1

    Chapter 1 System Commissioning Process

    1.1 About This Chapter

    This chapter presents system commissioning process as follows:

    z Manual Application in NodeB Familyz Reference Manualsz Tools for System Commissioningz Prerequisites for System Commissioningz Process of System Commissioning

    1.2 Manual Application in NodeB Family

    This manual applies to the NodeB family, including BTS3812, BTS3806, BTS3806A,

    and BTS3802C. In this manual, macro NodeB refers to BTS3812, BTS3806, or

    BTS3806A with large capacity. Mini NodeB refers to BTS3802C with small capacity. If

    not otherwise specified, the description of commissioning is applicable to both macro

    NodeBs and micro NodeBs.

    1.3 Reference Manuals

    Besides WCDMA NodeB Installation Manual-System Commissioning (hereinafter

    refereed to as this manual), make sure the manuals listed in Table 1-1 are available

    before commissioning the NodeB system.

    Table 1-1 Reference manuals for system commissioning of NodeB family

    NodeB type Reference manual

    BTS3812 WCDMA NodeB Installation Manual - Indoor Equipment Installation

    WCDMA NodeB Installation Manual - Antenna & Feeder System Installation

    WCDMA NodeB Installation Manual - Software Installation

    BTS3812 & BTS3806 & BTS3806A WCDMA NodeB Data Configuration Manual

    WCDMA NodeB Hardware Description-Boards

    WCDMA NodeB Hardware Description-Cabinets and Cables

    BTS3812

    WCDMA NodeB Maintenance Manual - Troubleshooting

    BTS3806A WCDMA Outdoor NodeB Installation Manual - Equipment InstallationBTS3806A

    WCDMA NodeB Installation Manual - Antenna & Feeder System Installation

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    16/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 1 System Commissioning Process

    1-2

    NodeB type Reference manual

    WCDMA NodeB Installation Manual - Software Installation

    BTS3812 & BTS3806 & BTS3806A WCDMA NodeB Data Configuration Manual

    WCDMA NodeB Hardware Description-Boards

    WCDMA NodeB Hardware Description-Cabinets and Cables

    WCDMA NodeB Maintenance Manual - Troubleshooting

    BTS3806 WCDMA NodeB Installation Manual - Indoor Equipment Installation

    WCDMA NodeB Installation Manual - Antenna & Feeder System Installation

    WCDMA NodeB Installation Manual - Software Installation

    BTS3812 & BTS3806 & BTS3806A WCDMA NodeB Data Configuration Manual

    WCDMA NodeB Hardware Description-Boards

    WCDMA NodeB Hardware Description-Cabinets and Cables

    BTS3806

    WCDMA NodeB Maintenance Manual - Troubleshooting

    BTS3802C WCDMA Mini NodeB Installation Manual - Equipment Installation

    BTS3802C WCDMA Mini NodeB Installation Manual - Antenna & Feeder SystemInstallation

    WCDMA NodeB Installation Manual - Software Installation

    BTS3802C WCDMA Mini NodeB Data Configuration Manual

    WCDMA NodeB Hardware Description-Boards

    WCDMA NodeB Hardware Description-Cabinets and Cables

    BTS3802C

    WCDMA NodeB Maintenance Manual - Troubleshooting

    1.4 Tools for System Commissioning

    Besides the NodeB LMT and RNC LMT, prepare the following tools for NodeB system

    commissioning:z Multimeter z VSWR measuring instrument: Site Master (S330A or S331A), YBT250, network

    analyzer (HP8753E)z Test-UEz Antistatic wrist strap

    1.5 Prerequisites for System Commissioning

    The prerequisites for NodeB system commissioning are as follows:

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    17/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 1 System Commissioning Process

    1-3

    z The hardware installation of both the NodeB cabinet and the antenna and feeder

    system is completed and accepted.z The NodeB software installation is completed.z

    The RNC installation and system commissioning is completed.z The far end or near end operation and maintenance channel of the NodeB is

    normal.

    1.6 Process of System Commissioning

    NodeB system commissioning brings the NodeB system into normal operation after

    hardware installation and software installation.

    Figure 1-1 shows the process of NodeB system commissioning.

    Start

    End

    Commissioning Iub interface

    Commissioning clock

    Commissioning service

    Commissi oning softw are

    Commis sioning uplink RF c hannel

    Commis sioning downlink RF c hannel

    Commissioning hardware

    Figure 1-1 NodeB System commissioning process

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    18/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-1

    Chapter 2 Commissioning Hardware

    2.1 About This Chapter

    Hardware Commissioning covers the following procedures:

    z Verifying Hardware Installationz Verifying DIP Switch and Jumper Settingsz Verifying VSWR of Antenna and Feeder Systemz Checking Macro NodeB Power-onz Checking Mini NodeB Power-on

    Caution:

    Pay attention to the following items during hardware commissioning:z Wear an antistatic wrist strap before installing boards and modules.z Do not leave boards and modules anywhere after taking them out of the packing material. Insert

    them loosely in their corresponding slots before power-on check. Secure them with screws after the

    power-on check.z For macro NodeBs, secure NodeB dual duplexer & low-noise amplifier modules (NDDL) before

    installing antenna and feeder jumpers.z For macro NodeBs, do not install NDDLs or NodeB linear power amplifier modules (NLPA) upside

    down. Otherwise, damage might be done to the modules.z For mini NodeBs, check the level degree of a module after installing it by placing two level bars

    perpendicular to each other on the subrack top plane. If the level error is over five degrees, it is

    necessary to adjust its position.z For outdoor installation, install a sunshade on the plastic shell of the cabinet.

    2.2 Verifying Hardware Installation

    2.2.1 Overview

    This procedure verifies NodeB hardware installation, including both equipment

    installation and antenna & feeder system installation.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    19/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-2

    2.2.2 Procedures

    Verify hardware installation as follows:

    1) Check NodeB equipment installation. Table 2-1 lists the reference manuals.2) Check NodeB antenna & feeder system installation. Table 2-1 lists the reference

    manuals.

    Table 2-1 Reference manuals for verifying hardware installation

    NodeBtype

    To check equipment installation,refer to

    To check antenna & feeder systeminstallation, refer to

    BTS3812 Chapter 9 in BTS3812 WCDMANodeB Installation Manual -Indoor Equipment Installation

    Chapter 4 in WCDMA NodeB InstallationManual Antenna & Feeder SystemInstallation

    BTS3806 Chapter 9 in BTS3806 WCDMANodeB Installation Manual -Indoor Equipment Installation

    Chapter 4 in WCDMA NodeB InstallationManual Antenna & Feeder SystemInstallation

    BTS3806A Chapter 9 in BTS3806A WCDMAOutdoor NodeB Installation Manual- Equipment Installation

    Chapter 4 in WCDMA NodeB InstallationManual Antenna & Feeder SystemInstallation

    BTS3802C Chapter 8 in WCDMA Mini NodeBInstallation Manual - EquipmentInstallation

    Chapter 4 in WCDMA Mini NodeB InstallationManual Antenna & Feeder SystemInstallation

    3) Check engineering parameters

    Start the configuration management system and open the engineering parameter file

    according to the procedures described in BTS3812&BTS3806&BTS3806A WCDMA

    NodeB Operation Manual - Data Configuration or BTS3802C WCDMA Mini NodeB

    Operation Manual - Data Configuration. Verify that the engineering parameters are

    correctly recorded. These engineering parameters are reference information for the

    latter commissioning operations.

    2.3 Verifying DIP Switch and Jumper Settings

    2.3.1 Overview

    This procedure verifies the settings of the DIP switches and jumpers. Table 2-2 lists

    the DIP switches and jumpers concerned.

    Table 2-2 DIP switches and jumpers in NodeB system commissioning

    NodeB DIP switch Jumper

    Macro NodeB DIP switches in NDTI NRFB uplink jumper

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    20/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-3

    NodeB DIP switch Jumper

    DIP switches in NAOI NRFB downlink jumper

    Mini NodeB DIP switches (E1/T1, 75/120, and E1_R) inNMCU maintenance chamber

    NDRU connect mode

    2.3.2 Procedures for Macro NodeB

    Verify the settings of macro NodeB DIP switches and jumpers as follows:

    1) Pull out the installed NDTI/NAOI, verify DIP switches on NodeB digital trunk

    interface units (NDTI) and NodeB ATM optical interface units (NAOI)

    Notes:

    The E1/T1 ports of NDTIs and NAOIs may work in the balanced or unbalanced mode. By default, they

    work in the unbalanced mode. That is, the default transmission cables are 75- coaxial ones. For more

    details about NDTI and NAOI DIP switch settings, refer to WCDMA NodeB Hardware Description Manual

    Boards.

    2) Insert the NDTI/NAOI back into the slots according to the data configuration.

    3) Verify uplink (UL) jumpers and downlink (DL) jumpers on NodeB radio frequency

    backplane (NRFB)

    Notes:

    z The jumpers on the NRFB are set before delivery. You can reconfigure them if the NodeB

    configuration type change. For more details, refer to WCDMA NodeB Hardware Description Manual

    Cabinets and Cables.z The NRFP DL jumpers and UL jumpers are on the NRFP front where NTRXs and NDDLs are

    installed.

    4) Verify the power amplify module jumpers by referring to WCDMA NodeB

    Hardware Description Manual Cabinets and Cables.

    2.3.3 Procedures for Mini NodeB

    Verify the settings of micro NodeB DIP switches and jumpers as follows:

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    21/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-4

    1) Verify the setting of DIP switches (E1/T1, 75/120, and E1_R) in the NMCU

    maintenance chamber by referring to WCDMA NodeB Hardware Description

    Manual Boards for the setting of the NMCU DIP switches.

    Note:

    z The E1_R DIP switch sets the grounding status of E1/T1 sheaths. The E1/T1 DIP switch indicates

    the E1_R DIP switch status to software. Set digits 3 and 4 of the E1/T1 DIP switch according to

    E1_R DIP switch settings.z E1/T1 ports may work in the balanced or unbalanced mode. By default, they work in the unbalanced

    mode. That is, the default transmission cables are 75- coaxial ones.z For more details, refer to WCDMA NodeB Hardware Description Manual - Boards.

    2) Execute the MML command LST NDRUWM on the NodeB O&M system to query

    the connect mode of the NDRUs. Verify the interconnect jumper of NDRU

    according to the NDRU connect mode configured.

    2.4 Verifying VSWR of Antenna and Feeder System

    2.4.1 Overview

    This procedure is to verify that the voltage standing wave radio (VSWR) of the

    antenna and feeder system is smaller than 1.5.

    Common VSWR measuring instrument includes SiteMaster, YBT250, network

    analyzer (HP8753E). This chapter describes VSWR measurement by Site Master

    (S330A or S331A).

    2.4.2 Procedures

    Verify the VSWR of the antenna and feeder system as follows:1) Turn off the NLPA switches on the NLPA panel.

    2) Execute the MML command SET TTASWNDDLATTEN on the NodeB O&M

    system to turn off the NTTA power.

    3) On the cabinet top, disconnect NodeB cabinet from the antenna and feeder

    system.

    4) Connect the Site Master with the antenna and feeder system through a cable, as

    shown in Figure 2-1.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    22/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-5

    Antenna

    Jumper

    NTTA

    SiteMaster

    Cable

    Feeder

    Figure 2-1 Connecting SiteMaster with the antenna and feeder system

    Note:

    z For Macro NodeB, NTTA is optional in the antenna and feeder system.z Mini NodeB does not support NTTA.

    5) Test the VSWR with the SiteMaster. For more details, see Appendix A in this

    manual. Table 2-3 lists the accessory required for the measurement.

    Table 2-3 Accessory for VSWR measurement of antenna and feeder system

    No. Accessory

    1 Cable with a DIN female connector and an N male connector

    6) The VSWR of the antenna and feeder system must be not more than 1.5. The

    equivalent return loss is 14dB.

    Note:

    z To install the macro NodeB antenna & feeder system correctly, refer to Chapter 4 in WCDMA NodeB

    Installation Manual Antenna & Feeder System Installation.z To install the mini NodeB antenna & feeder system correctly, refer to Chapter 4 in BTS3802C

    WCDMA Mini NodeB Installation Manual Antenna & Feeder System Installation.

    7) On the cabinet top, disconnect the antenna and feeder system from Site Master.

    8) Connect the NodeB cabinet with the antenna and feeder system.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    23/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-6

    2.5 Checking Macro NodeB Power-on

    2.5.1 Overview

    This procedure is to conduct the power-on check of a macro NodeB.

    2.5.2 Procedures

    Check the power-on of a macro NodeB as follows:

    1) Check power supply to make sure that:z The power supply of the BTS3812/BTS3806 is 40 to 60 V DC.z The power supply of the BTS3806A is 176 to 224 V AC or 90 to 135 V AC.

    Note:

    z The BTS3812/BTS3806 complies with ETS 300 132-2 regarding power supply of nominal 48 VDC.z The BTS3806A complies with ETS 300 132-2 regarding power supply of nominal 220 VAC or 110

    VAC.

    2) Power on fansz Remove all boards and modules except fan modules from backplanes.z Power on the cabinet, and then check that the fans work normally.

    3) Power on a baseband subrack boardz Secure a baseband subrack board.z Switch on the NodeB baseband unit (NBBU) in the NodeB DC switch box

    (NDCS).z Check the RUN indicator on the board. Confirm that the indicator works normally.

    4) Power on the other baseband subrack boardsz Secure other baseband subrack boards.z

    Check that the RUN indicators on the boards work normally.5) Power a radio frequency (RF) subrack modulez Secure an NTRX module.z Switch on the NodeB radio frequency unit (NRFU) in the NDCS.z Check the RUN indicator on the module.z If the indicator works normally, switch off NRFU.

    6) Power on the other radio frequency (RF) subrack modulesz Secure other RF subrack modules.z Switch on NRFU in the NDCS.z Check that the RUN indicators on the modules work normally.

    7) Power on NLPAs

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    24/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-7

    Caution:

    Before powering on the NLPAs, connect the antenna and feeder system to the NodeB.

    z After switching off NLPAs, secure them one by one.z Switch on the NLPAs one by one.z Check that their RUN indicators work normally.

    Note:

    For more details about indicator status, refer to WCDMA NodeB Hardware Description Manual Boards.

    2.6 Checking Mini NodeB Power-on

    2.6.1 Overview

    This procedure is to conduct the power-on check of a mini NodeB.

    2.6.2 Procedures

    Check the power-on of a mini NodeB as follows:

    1) Check that the power supply of the BTS3802C is 150 VAC to 300 VAC.

    2) Turn the switches PWR and CTL on NPSU to "OFF".

    Note:

    The switches PWR (power switch for NodeB) and CTL (power switch for NDRU) on NPSU are set to"ON" before delivery. When PWR and CTL on NPSU are in the "ON" state, the entire NodeB begin to

    operate after the NPSU is powered on.

    3) Turn on the MCB in the lightning protection box to power on NPSU. Check

    whether the green INPUT indicator on NPSU is normal.

    4) Turn the switch PWR on NPSU to "ON". Check whether the green INPUT

    indicator on NPSU is in the "on" state and whether the M_RUN indicator on the

    NMCU is flashing at 0.5 Hz.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    25/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 2 Commissioning Hardware

    2-8

    5) Turn the switch CTL on NPSU to "ON". Check whether the RUN indicator on

    NDRU is flashing at 0.5 Hz.

    Note:

    Refer to WCDMA NodeB Hardware Description Manual Boards for information about indicator status.

    In case of any fault during the power-on check process, contact Huawei Technical Support.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    26/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 3 Commissioning Software

    3-1

    Chapter 3 Commissioning Software

    3.1 About This Chapter

    Software commissioning covers the following procedures:

    z Verifying Operation and Maintenance Channelz Verifying Software Versionz Checking Data Consistency

    Before software commissioning, you shall:

    z Download the correct data configuration file to the NodeB.z Power on NodeB and check that RUN indicators on all boards and modules flash

    at 0.5 Hz.

    Note:

    z For data configuration of macro NodeBs, see BTS3812 & BTS3806 & BTS3806A WCDMA NodeB

    Operation Manual - Data Configuration.z For data configuration of mini NodeBs see BTS3802C WCDMA Mini NodeB Operation Manual -

    Data Configuration.

    3.2 Verifying Operation and Maintenance Channel

    3.2.1 Overview

    This procedure is to verify that:

    z The local maintenance channel and IPoA maintenance channel are normal.z The alarms can be reported correctly.

    3.2.2 Procedures of Verifying Local Maintenance Channel

    Verify the local maintenance channel as follows:

    1) Check that the computer of the local maintenance terminal (LMT) and the NodeB

    main processing & timing unit (NMPT) are in the same IP subnet.

    2) Connect the LMT computer with the NMPT ETH Port.

    3) Start the LMT and log on to the NodeB.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    27/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 3 Commissioning Software

    3-2

    4) Make sure that you can log on to the NodeB and that the LMT can communicate

    with the NodeB normally.

    3.2.3 Procedures of Verifying IPoA Maintenance Channel

    Verify the IPoA maintenance channel as follows:

    1) Connect the LMT computer with the RNC BAM.

    2) Start the LMT and log on to the NodeB.

    3) Make sure that you can log on to the NodeB through the IPoA and that the LMT

    can communicate with the NodeB normally.

    Note:

    z There are three maintenance channels for a macro NodeB, namely dial-up maintenance channel,

    local maintenance channel and IPoA maintenance channel. For details, see BTS3812 & BTS3806 &

    BTS3806A WCDMA NodeB Data Configuration Manual.z There are two maintenance channel for a mini NodeB, that is, IPoA maintenance channel and local

    maintenance channel. For details, see BTS3802C WCDMA Mini NodeB Data Configuration Manual.z For NMPT in macro NodeBs or NMCU in mini NodeBs, the Ethernet port IP address is preset to

    17.21.2.15/255.255.0.0 before delivery. You may query the IP address through LST IP command and

    dynamically reconfigure it through SET IP command.

    3.2.4 Procedures of Verifying Alarm Report

    Verify the alarm report as follows:

    1) Double-click NodeB alarms in the Alarm Management System to display alarm

    details. Check that you can display alarms reported.

    2) Clear the alarms according to online Help information. Check that you can clear

    all alarms when transmission cables between NodeB and RNC are normal.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    28/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 3 Commissioning Software

    3-3

    Notes:

    If the transmission cables are not normal, you cannot clear the following alarms:z ALCAP abnormalz CCP abnormalz NCP abnormalz E1/T1 Loss Of Signal (LOS)z IMA/UNI link Loss of Cell Delineation (LCD)z NodeB clock source abnormal (if you apply the default NodeB clock source Iub interface clock).

    For any alarm that cannot be cleared when transmission cables between NodeB and RNC are normal,

    contact Huawei Technical Support.

    3.3 Verifying Software Version

    3.3.1 Overview

    This procedure is to verify that the current software version is in the "Normal" state.

    3.3.2 Procedures

    Verify software version as follows:

    1) Carry out MML command LST VER on the NodeB O&M system. This command

    lists the current NodeB version information, including:z Current software versionz Current software version statusz Hardware versionz Current BootRom version

    2) Pay attention to the following two cases:z If the current software version status is "Normal", it indicates that the software

    version of all boards is the same as that of the NodeB.z If the current software version status is "Fractional", it indicates that the software

    version of some boards is not the same as that of the NodeB. In this case

    contact Huawei Technical Support for the required version.

    Note:

    In case of inconsistency between the current version and the wanted version, contact Huawei Technical

    Support for the version you need and upgrade the software version according to the attached guides.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    29/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 3 Commissioning Software

    3-4

    3.4 Checking Data Consistency

    3.4.1 Overview

    This procedure is to verify that NodeB static data in the configuration file in Flash is

    consistent with the running data.

    3.4.2 Procedures

    Check data consistency as follows:

    1) Check that the static data in NodeBCfg.xml in Flash is consistent with therunning data in RAM through MML command CHK DATA on the NodeB O&M

    system.

    2) Reset the NodeB through MML command RST SYS on the NodeB O&M system

    in case of inconsistency between the running data and the data in NodeBCfg.xml

    file in Flash.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    30/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-1

    Chapter 4 Commissioning Iub Interface

    4.1 About This Chapter

    Iub interface commissioning covers the following procedures:

    z Verifying Iub Interface Data Consistencyz Verifying E1/T1 Linkz Verify IMA Group and IMA Linkz Verifying UNI Linkz Verifying NCP and CCP Statusz Verifying AAL2NODE and AAL2PATH

    4.2 Verifying Iub Interface Data Consistency

    4.2.1 Overview

    This procedure is to verify the consistency of Iub interface data between NodeB and

    RNC.

    4.2.2 Procedures for IMA Group in Use

    Only macro NodeB can apply IMA group. When a macro NodeB uses the IMA mode,

    follow the steps in Table 4-1 to verify the consistency of Iub interface data.

    There may be multiple IMA groups, UNIs, CCPs and AAL2PATHs. Check them one

    by one.

    Table 4-1 Iub interface data

    Step Item RNC NodeB Consistentor not

    RNC command NodeBcommand

    IMA group No. Y [ ] N [ ]Verify IMAgroup

    Number of IMA links

    Y [ ] N [ ]

    LST IMAGRP LSTIMAGRP

    IMA group No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Verify NCP

    Peak CellRate(kbps)

    Y [ ] N [ ]

    LST IUBP LST CP

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    31/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-2

    Step Item RNC NodeB Consistentor not

    RNC command NodeBcommand

    IMA group No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Port No. Y [ ] N [ ]

    Verify CCP

    Peak CellRate(kbps)

    Y [ ] N [ ]

    IMA group No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Peak CellRate (kbps)

    Y [ ] N [ ]

    Verify AAL2 Node(ALCAP)

    ATM address Y [ ] N [ ]

    LSTAAL2ADJNODE

    LSTAAL2NODE

    IMA group No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Sustain CellRate (kbps)

    Y [ ] N [ ]

    Verify AAL2PATH

    PATH ID Y [ ] N [ ]

    LST AAL2PATH LSTAAL2PATH

    Destination IPaddress

    Y [ ] N [ ]

    Local IPaddress

    Y [ ] N [ ]

    Verify IPoA

    VPI and VCI Y [ ] N [ ]

    LST IPOAPVC LST IPOA

    For the Help information of the commands, see NodeB MML command Help and

    RNC MML command Help.

    Note:

    In case of inconsistency, reconfigure the corresponding items of macro NodeB. For more details, refer to

    BTS3812 & BTS3806 & BTS3806A WCDMA NodeB Data Configuration Manual .

    4.2.3 Procedures for UNI Link in Use

    When UNI link is in use, follow the steps in Table 4-2 to verify the consistency of Iub

    interface data.

    There may be multiple UNIs, CCPs and AAL2PATHs. Check them one by one.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    32/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-3

    Table 4-2 Verifying Iub interface data

    Step Item RNC NodeB Consistentor not

    RNC command NodeBcommand

    Verify UNIlink

    UNI link No. Y [ ] N [ ] DSP UNILNK DSPUNILNK

    UNI link No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Verify NCP

    Peak CellRate(kbps)

    Y [ ] N [ ]

    UNI link No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Port No. Y [ ] N [ ]

    Verify CCP

    Peak CellRate(kbps)

    Y [ ] N [ ]

    LST IUBP LST CP

    UNI link No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Peak CellRate(kbps)

    Y [ ] N [ ]

    Verify AAL2 Node(ALCAP)

    ATM address Y [ ] N [ ]

    LST AAL2ADJNODE

    LST AAL2NODE

    UNI link No. Y [ ] N [ ]

    VPI and VCI Y [ ] N [ ]

    Sustain CellRate(kbps)

    Y [ ] N [ ]

    Verify AAL2PATH

    PATH ID Y [ ] N [ ]

    LST AAL2PATH LST AAL2PATH

    Destination IPaddress

    Y [ ] N [ ]

    Local IPaddress

    Y [ ] N [ ]

    LST IPOAPVC LST IPOAVerify IPoA

    VPI and VCI Y [ ] N [ ]VerifyLocal Cell

    Local Cell ID Y [ ] N [ ] LST CELL LSTLOCELLCFG

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    33/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-4

    Note:

    z In case of inconsistency, reconfigure the corresponding items according to BTS3802C WCDMA Mini

    NodeB Data Configuration Manual.z BTS3802C mini NodeB does not support IMA transmission mode.z The UNI link number at RNC shall corresponds to that at NodeB. It is not necessary to make them

    the same.

    4.3 Verifying E1/T1 Link Status

    4.3.1 Overview

    This procedure is to verify E1/T1 link status.

    4.3.2 Procedures

    Verify E1/T1 link status as follows:

    1) When E1/T1 links connect NodeB to RNC, display the status of E1/T1 links

    through the MML command DSP E1T1 on the NodeB O&M system.

    2) If the links are in the "Normal" status (Link Status=NORMAL), the E1/T1s are

    functional. If there is a link in "ABNORMAL" status, refer to section 9.2 .

    4.4 Verify IMA Group and IMA Link Status

    4.4.1 Overview

    This procedure is to verify the IMA group status and IMA link status.

    4.4.2 Procedures

    Verify IMA group and IMA link status as follows:

    1) Display IMA group status through MML command DSP IMAGRP on NodeB

    O&M system. See the following example:%%DSP IMAGRP: CN=MASTER, BN=0, IMAGRPN=0;%%

    IMA Group Status

    ----------------

    Cabinet No. = MASTER

    Board No. = 0

    IMA Group No. = 0

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    34/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-5

    NE Status = OPERATIONAL

    FE Status = OPERATIONAL

    Group Failure Status = NO FAILURE

    Tx Available Bandwidth(cells/s) = 13472

    Rx Available Bandwidth(cells/s) = 13472

    Number of Tx Links Configured = 3

    Number of Rx Links Configured = 3

    Number of Tx Links Activated = 3

    Number of Rx Links Activated = 3

    2) Display IMA link status through MML command DSP IMALNK on NodeB O&M

    system. Check that the number of Tx links configured is the same as that of Tx

    links activated and that the number of Rx links configured is the same as that of

    Rx links activated. This indicates all IMA links configured are functional.

    3) End the procedure if:z The IMA group is operational.z "Number of Tx/Rx Links Configured" equals to "Number of Tx/Rx Links

    Activated".z All of the IMA links are normal.

    4) If there are any abnormal link, see section 9.3 for handling suggestions.

    4.5 Verifying UNI Link Status

    4.5.1 Overview

    This procedure is to verify UNI link status.

    4.5.2 Procedures

    Verify UNI link status as follows:

    1) Display UNI link status through MML command DSP UNILNK on NodeB O&M

    system. See the following example:

    %%DSP UNILNK:;%%RETCODE = 0 Succeed.

    UNI Link Status

    ---------------

    UNI Link No. = 0

    Link Status = Normal

    2) If the link status is "Normal", this procedure ends. If the link status is "Abnormal",

    see section 9.2 for troubleshooting.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    35/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-6

    4.6 Verifying NCP and CCP Status

    4.6.1 Overview

    This procedure is to verify NCP status and CCP status.

    4.6.2 Procedures

    Verify NCP status and CCP status as follows:

    1) Display CP status through MML command DSP CP on NodeB O&M system.

    Check that all CP ports configured are in the "Normal" status. See the following

    example:

    %%DSP CP:;%%

    NCP/CCP Port Status

    -------------------

    CCP/NCP Port Type = NCP

    CCP/NCP Port No. = 0

    CCP/NCP Port Status = Normal

    2) If the NCP and CCP status are normal, this procedure ends. If there is a NCP or

    CCP that is not in "Normal" status, see Section 9.4 for handling suggestions.

    4.7 Verifying AAL2NODE and AAL2PATH Status

    4.7.1 Overview

    This procedure is to verify AAL2NODE (ALCAP) status and AAL2PATH status.

    4.7.2 Procedures

    Verify AAL2NODE (ALCAP) status and AAL2PATH status as follows:

    1) Display AAL2NODE status through DSP AAL2NODE . Check that the AAL2node is in the "Normal" status. See the following example:

    %%DSP AAL2NODE: CN=MASTER;%%

    AAL2 Node Status

    ----------------

    Cabinet No. = MASTER

    AAL2 Node Status = NORMAL

    2) Display AAL2PATH status through MML command DSP AAL2PATH on NodeB

    O&M system. Check that the AAL2 paths are in the "Normal" status.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    36/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 4 Commissioning Iub Interface

    4-7

    3) If the AAL2NODE and the AAL2PATHs are in normal status, this procedure ends.

    If there is an AAL2NODE or AAL2PATH that is not in "Normal" status, see

    section 9.4 for handling suggestions.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    37/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 5 Commissioning Clock

    5-1

    Chapter 5 Commissioning Clock

    5.1 About This Chapter

    Clock commissioning covers the following procedures:

    z Verifying Center DAz Verifying Clock Source

    5.2 Verifying Center DA

    5.2.1 Overview

    This procedure is to verify the center DA value. At NodeB initial deployment, "Center

    DA" shall be the same as "Original DA".

    5.2.2 Procedures

    Verify center DA as follows:

    1) Display center DA of the NMPT through the MML command DSP CURRCLK onthe NodeB O&M system. See the following example.

    Current Clock Status ---------------------

    Configured Clock Source = IUB

    Configured Clock Source Status = OUTSCOPE

    Configured Work Mode = LOCK

    Current Work Mode = FREE

    Clock Status = FREE

    Center DA = 2531

    Current DA = 2532

    Original DA = 2531

    2) If the value of "Center DA" is not the same as that of "Original DA", modify

    "Center DA" to that of "Original DA" through MML command MOD CENTERDA

    on the NodeB O&M system.

    Notes:

    Generally, "Center DA" of NMPT is calibrated and set to "Original DA" before delivery.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    38/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 5 Commissioning Clock

    5-2

    5.3 Verifying Clock Source

    5.3.1 Overview

    This procedure is to verify the clock source status.

    5.3.2 Procedures

    Verify clock source status as follows:

    1) Select the clock source for the NodeB according to the following rules:z Select GPS reference source if the NodeB is equipped with GPS.z Select the external reference source if the NodeB is configured with an external

    reference source instead of a GPS and if the precision of the external referencesource meets the requirements.

    z Select Iub reference source if the NodeB is configured with neither GPS nor an

    external reference source.

    Notes:

    z External clock source may be a 2 MHz clock, such as the synchronization interface of SDH or BITS.z The precision of the reference source must be no less than 0.05 ppm.

    2) When selecting the Iub reference source, specify an E1/T1 of the Iub interface

    from which the NodeB extracts clocks. Carry out the MML command ADD

    IUBCLK on NodeB O&M system to select an E1/T1 that connects to the RNC.

    Notes:

    Display the E1/T1 selected as Iub clock through the MML command DSP IUBCLK on the NodeB O&M

    system.

    3) Set work modes of the clock by the following two rules:z Set the clock work mode to "free" through the MML command MOD CLKMODE

    on the NodeB O&M system to prevent the alarm of abnormal clock source if the

    precision of the reference source cannot meet corresponding requirement.z Set the clock work mode to "phase-lock" through the MML command MOD

    CLKMODE on the NodeB O&M system if the precision of the reference source

    satisfies the corresponding requirement.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    39/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 5 Commissioning Clock

    5-3

    Notes:

    Display the clock work mode through the MML commandDSP CLKon the NodeB O&M system.

    When the reference source is normal, phase-lock speed of the clock varies with the reference sources

    as follows:z When the NodeB traces Iub clock, it locks the reference source within one and a half hours.z When the NodeB traces GPS clock, it locks the reference source within 36 minutes.z When the NodeB traces the external clock, it locks the reference source within six minutes.

    The phase-lock speed of the clock does not affect normal services.

    4) Start clock quality test through MML command STR CLKTEST on the NodeB

    O&M system to display the difference between the NodeB clock and reference

    source.z If the difference is a negative value, it means the NodeB clock is slower than the

    reference clock.z If the difference is a positive value, it means the NodeB clock is faster than the

    reference source.z Under most cases when the precision of the reference source meets the

    requirement, the difference is zero.

    5) Stop the clock quality test through the MML command STP CLKTEST on the

    NodeB O&M system.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    40/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 6 Commissioning Uplink RF Channel

    6-1

    Chapter 6 Commissioning Uplink RF Channel

    6.1 About This Chapter

    By calibrating uplink RF channel gain of NodeB, you can:

    z Clear the variance among the modules and boards;z Ensure that the gain between cabinet top and intermediate-frequency input port

    satisfies the requirement.

    Uplink RF channel commissioning covers the following procedures:

    z Calibrating Uplink RF Channel Gain of Macro NodeBz Calibrating Uplink RF Channel Gain of Mini NodeBz Setting NDDL Unit Attenuation (Macro NodeB)

    6.2 Calibrating Uplink RF Channel Gain of Macro NodeB

    6.2.1 Overview

    This procedure is to calibrate the uplink RF channel gains of macro NodeB.

    6.2.2 Procedures

    Calibrate the UL RF channel gains of macro NodeB as follows:

    1) If the logical cell to commission is set up, block the cell through MML command

    BLK CELL on the NodeB O&M system.

    Notes:

    The main and diversity Rx channels of the corresponding NTRX of a cell are always switched on no

    mater in what status the logical cell and local cell are.

    2) Query NDDL attenuation through the MML command DSP NDDLTTA on the

    NodeB O&M system if there is a TTA, and note down the attenuation of the main

    and diversity channels of the NDDL.

    3) Set the soft switch of the TTA to "OFF" through the MML command SET

    TTASWNDDLATTEN on the NodeB O&M system. In this case, the system

    automatically sets the NDDL attenuation to zero.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    41/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 6 Commissioning Uplink RF Channel

    6-2

    4) Remove the antenna and feeder system from the NodeB cabinet top, and then

    connect large-power match load or small-power match N connector to the

    antenna port of this cell on the cabinet top.

    Note:

    If there is no user or intra-frequency interference, use antenna and feeder system as a match load.

    5) Start "RTWP measurement" on the O&M system. The system displays the

    measurement result in graphical format. The RTWP measurement result of both

    the main and the diversity Rx antenna shall be 105.5 dBm ! 2 dB and their

    difference should be no more than 5 dB.6) If the RTWP measurement result satisfies the conditions described in step 5),

    jump to step 9). If the RTWP measurement result does not meet the conditions

    described in step 5), display the gain of the current Rx channel through MML

    command DSP RXINITGAIN on the NodeB O&M system.

    7) According to the difference between displayed RTWP and the target value

    (-105.5 dBm), adjust the initial gain of the Rx channel through the MML

    command SET RXINITGAIN on the NodeB O&M system. The adjustable range

    of initial gain of Rx channel is -2dB +2dB. The adjustment step is 0.1dB. Adjust

    the gain to make the displayed RTWP approximate to the target value.

    8) If the displayed RTWP fails to satisfy the requirements in step 5) after the

    adjustment, check the hardware installation.

    Note:

    z To check the installation of BTS3812, see Chapter 9 in BTS3812 WCDMA NodeB Installation

    Manual Indoor Equipment Installation.z To check the installation of BTS3806, see Chapter 9 in BTS3806 WCDMA NodeB Installation

    Manual Indoor Equipment Installation.z To check the installation of BTS3806A, see Chapter 7 in BTS3806A WCDMA Outdoor NodeB

    Installation Manual Equipment Installation.z To check the installation of antenna and feeder system, see Chapter 4 in WCDMA NodeB Installation

    Manual Antenna and Feeder System Installation.

    9) After the above operation, if the RTWP measurement result does not meets the

    conditions described in step 5), contact Huawei Technical Support. If the RTWP

    measurement result meets the conditions described in step 5), restore the

    system.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    42/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 6 Commissioning Uplink RF Channel

    6-3

    z Remove the match load connected to the cabinet top in step 3) and re-connect

    the antenna and feeder system to the cabinet top.z Unblock the logical cell blocked in step 1) through the MML command UNBLK

    CELL on the RNC O&M system.z Set the soft switch of the TTA to "ON" and set the attenuations of the NDDL units

    to their original values through the MML command SET TTASWNDDLATTEN on

    the NodeB O&M system if there is a TTA.

    6.3 Calibrating Uplink RF Channel Gain of Mini NodeB

    6.3.1 Overview

    This procedure is to calibrate the uplink RF channel gains of mini NodeB.

    6.3.2 Procedures

    Calibrate the UL RF channel gains of mini NodeB as follows:

    1) Block the cell to commission through the MML command BLK CELL on the

    NodeB O&M system if the logical cell is set up.

    2) Check whether the main and diversity Rx channels of the corresponding NDRU

    of the cell to commission are switched on through the MML command DSP

    NDRURFCHANSW on the NodeB O&M system.

    3) If the Rx channels are not switched on, switch them on through the MML

    command SET NDRURXSW on the NodeB O&M system.

    Notes:

    By default, the BTS3802C RF Rx channel switch is in the "on" state.

    4) Remove the antenna and feeder system from the NodeB and connect

    large-power match load or small-power match N connector to the corresponding

    antenna port of this cell on BTS3802C cabinet.

    5) Start "RTWP measurement" on the O&M system. The system displays the

    measurement result in graphical format. The RTWP measurement result of both

    the main and the diversity Rx antenna should be 105.5 dBm ! 2 dB and their

    difference should be no more than 5 dB.

    6) If the RTWP measurement result satisfies the conditions described in step 5),

    jump to step 7). If the RTWP measurement result does not meet the conditions

    described in step 5), carry out " NDRU/Start uplink channel gain calibration"

    on the NodeB Advanced Maintenance Terminal. The system automatically

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    43/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 6 Commissioning Uplink RF Channel

    6-4

    adjusts the uplink channel gain to make the RTWP approximate to the target

    value (-105.5 dBm).

    Caution:

    Before carrying out "NDRU/Start uplink channel gain calibration" on the NodeB Advanced Maintenance

    Terminal, make sure that a match load connects to the antenna port of BTS3802C cabinet.

    7) Remove the match load connected to the antenna port in step 3) and re-connect

    the antenna and feeder system to the antenna port.

    8) Unblock the logical cell blocked in step 1) through the MML command UNBLKCELL .

    6.4 Setting NDDL Unit Attenuation (Macro NodeB)

    6.4.1 Overview

    This procedure is to verify the NDDL Unit Attenuation value.

    To set NDDL attenuation means to make the NDDL uplink gain match the loss of the

    antenna and feeder system so that the total gain from the antenna port to the NDDLis zero.

    6.4.2 Procedures

    Verify the NDDL attenuation value as follows:

    1) Calculate the uplink gain of the antenna and feeder system.z Figure 6-1 simplifies the connection between components of the antenna and

    feeder system.

    Antenna Jumper TTA Jumper Feeder Lightningarrester

    NodeB

    L1 G1 L2 L3 L4

    Jumper

    L5

    Figure 6-1 Simplified connection between components of antenna and feeder system

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    44/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 6 Commissioning Uplink RF Channel

    6-5

    Note:

    L1,L2 and L5 are loss of jumper. L3 is loss of feeder. L4 is loss of lightning arrester.G1 is gain of TTA.

    z The uplink gain of the antenna and feeder system is calculated in the following

    formula:

    G(dB)=G1L1L2L3L4L5

    z In practice, the NDDL Unit Attenuation closely relates to the engineering

    installation. Currently, the TTA gain G1 is 12 dB, the lightning arrester loss L4 is

    0.1 dB. Table 6-1 lists the loss of corresponding jumpers and feeders.

    Table 6-1 Component loss of antenna and feeder system

    SN Cable type Insertion loss Connector

    1 1.5 m 1/2" jumper 0.3 dB Both ends are DIN male connector.

    2 2.5 m 1/2" jumper 0.5 dB Both ends are DIN male connector.

    3 3.5 m 1/2" jumper 0.7 dB Both ends are DIN male connector.

    4 7/8" feeder 6.11dB/100m Both ends are DIN female connector.

    5 5/4" feeder 4.43dB/100m Both ends are DIN female connector.

    2) Determine the NDDL Unit Attenuation value according to the value range of G:z When there is a TTA and the value of G is no less than 6, the TTA switch must

    be set to "ON", and the NDDL unit attenuation value to G.z When there is a TTA and the value of G is less than 6, the TTA switch must be

    set to "ON", and the NDDL Unit Attenuation value to 6.

    Caution:

    Before hardware installation, make a proper engineering plan to avoid the situation that the value of G isless than 6dB even if TTA is equipped.

    z When there is no TTA in the antenna and feeder system, the value of G must be

    less than zero. The TTA switch must be set to "OFF", and the NDDL Unit

    Attenuation value to zero.

    3) Query NDDL attenuating value through the MML command DSP NDDLTTA onNodeB O&M system. If the NDDL attenuation value is the value determined in

    step 2), go to step 4). Otherwise, set the TTA switch and the NDDL Unit

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    45/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 6 Commissioning Uplink RF Channel

    6-6

    attenuation value through the MML command SET TTASWNDDLATTEN on

    NodeB O&M system.

    4) Launch RTWP measurement on the NodeB O&M system. The RTWP

    measurement result shall meet the conditions in step 5) in section 6.2 . If itdoes not meet the conditions, the possible causes might be as follows:

    z Incorrect calculation of the gain of the antenna and feeder system leads to NDDL

    attenuation setting error.z If the value of G is no more than 6 when there is a TTA installed for the antenna

    and feeder system, the RTWP measurement result is obviously small. Try to

    avoid this case in the engineering plan.z There is antenna and feeder installation problem. Check the hardware

    installation of the antenna and feeder system according to WCDMA NodeB

    Installation Manual Antenna & Feeder System Installation. z There is intra-frequency interference.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    46/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 7 Commissioning Downlink RF Channel

    7-1

    Chapter 7 Commissioning Downlink RF Channel

    7.1 About This Chapter

    By calibrating DL RF channel gain of NodeB, you can:

    z Clear the variance among boards.z Ensure that the power of RF transmit signals at the antenna port on the cabinet

    top is consistent with the configured cell transmit power.

    There are two methods to display the downlink transmit power:

    z Method 1: Use RF measurement instruments to measure the power of RF

    transmit signals at the antenna port on the cabinet top. The instruments include

    E4445A, E4440, E4406, and YBT250. For more details, see appendix C.z Method 2: Display the total cell transmit power through the NodeB O&M system.

    The total cell transmit power is calculated according to the detected power

    reported by NLPA.

    This section applies method 2 to calibrate RF downlink channel and covers the

    following procedures:

    z Calibrating DL RF Channel Gain of Macro NodeB Cellz Calibrating DL RF Channel Gain of Mini NodeB Cell

    7.2 Calibrating DL RF Channel Gain of Macro NodeB Cell

    7.2.1 Overview

    This procedure is to calibrate the DL RF channel gain of a macro NodeB cell.

    Caution:

    If you employ indoor antennas, connect a large-power attenuator to the antenna connector on the

    cabinet top to prevent radiation injury due to large-power microwave emitting.

    The prerequisites for downlink RF channel commissioning includes:

    z The NodeB antenna and feeder system is properly installed.z NodeB is working normally and the local cell is available.

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    47/73

    Installation Manual System Commissioning WCDMA NodeB Chapter 7 Commissioning Downlink RF Channel

    7-2

    7.2.2 Procedures

    1) Deactivate the logical cell through the RNC MML command DEA CELL .

    2) Create a 141 test on the NodeB O&M system.z Select the cell on the 141 test window.z Set the maximum transmit power of the cell to 44 dBm in the [Set Cell

    Parameters] dialog box.z Select [DL Test Started/Start RF Test/DL Test/Maximum Transmit Power] from the

    141 test window to start the Maximum Transmit Power test.

    Caution:

    Connect the antenna and feeder system to the cabinet before carrying out the DL test.

    3) Carry out the MML command STR NLPAPWRMON on the NodeB O&M system.

    The slot number of the NLPA must correspond to the cell being calibrated. The

    system reports the output power of the NLPA in the display area, as shown in

    Figure 7-1.

    Figure 7-1 NLPA output power

  • 7/27/2019 NodeB Installation Manual-System Commissioning

    48/73

    Installation Manual System Comm