No.1 - 2013 BD 1 PROJECT HAI SU TRANG / HAI SU DEN PROJECT ACHIEVED 1,000,000 MANHOURS WITHOUT ANY LOST TIME INCIDENTS Page 8 SU TU TRANG PROJECT OBTAINED ITS FIRST GAS AHEAD OF SCHEDULE PTSC M&C- TOP 500 LARGEST VIETNAM ENTERPRISES Page 9 Page 15 Page 6 A TWO-YEAR MARATHON JOURNEY

Transcript of No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9....

Page 1: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

No.1 - 2013

BD 1 PROJECT

HAI SU TRANG / HAI SU DEN PROJECT

ACHIEVED 1,000,000 MANHOURS WITHOUT ANY LOST TIME INCIDENTS Page 8

SU TU TRANG PROJECT OBTAINED ITS FIRST GAS AHEAD OF SCHEDULE

PTSC M&C-

TOP 500 LARGEST VIETNAM ENTERPRISES

Page 9

Page 15

Page 6

A TWO-YEAR MARATHON JOURNEY

Page 2: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

The Bien Dong 1 (BD1) Project is an EPCI turnkey project awarded to PTSC M&C by Bien Dong Petroleum Operating Company (Bien Dong POC). This is the first and greatest offshore project ever performed by a Vietnamese local contractor, opening up new horizons for the Viet-nam oil & gas industry in the future especially at the water depth of over 133 meters.

Page 3: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

MANAGEMENT MESSAGE

05

Petroleum Management Unit (Petronas) carried out a capability audit at PTSC M&C fabrication yard

Gazprom’s visit to PTSC M&C PTSC M&C was ranked 67th amongst top 500 largest Vietnam enterprises

12

9

1413

8 HST/HSD Project achieved 1,000,000 manhours without any lost time incidents 6 BD1 Project –

A two-year marathon journey

Su Tu Trang Project obtained its First Gas ahead of schedule

Upgrading RongDoi Booster Compressor 10

PTSC M&C was awardedDua Subsea Development Project 11

Dear Readers,

2012 is the year of Dragon which is tradi-tionally characterized by luck, strength and prosperity. However as it turns out, 2012 is a tumultuous year to Vietnam’s economy: the property market was frozen, stock prices dipped sharply to some of the lowest levels ever and the banking industry expe-rienced unexpected turbulence. The future is indeed never certain.

If there is any lesson learned from these difficult time, we believe it is a realization that quick money does not last and long-term successes do require skill, hard work and resilience even though lucks certainly have some says. At PTSC M&C, 2012 is the year full of events to us: we were negatively affected by the economic slow-down; the delay of few of our important forecasted projects forced us to downsize our work-force, an unforgettable and painful experi-ence to our management and employees. On the bright side, the solid foundation in terms of experience and competency built through years of hard-work and dedication has helped us navigate through the rough water. In 2012 we successfully offshore installed and handed over three strategi-cally important projects to our clients, among them is the prestigious and national Bien Dong 1 Central Processing Platform. Financially in 2012 we recorded the highest revenue and profit figures since the compa-ny was founded and PTSC M&C was ranked 67th amongst 500 largest enterprises, up 38 positions compared to 2011.

Our sphere of action in 2013 is to continue to maintain the focus on providing cutting-edge EPCI/EPCIC services for oil and gas offshore projects. In addition, on the front lines, we will keep boosting our response to the regional markets by collaborating with leading clients and partners in such countries as Australia, India, Myanmar, Malaysia and some other countries in the region.

”In 2012 we successfully off-shore installed and handed over three strategically impor-tant projects to our clients”

We also understand that no one is success-ful on his own, the achievements and mile-stones we have completed today would not be possible without the cooperation, support and understanding from Clients, partners, related parties and friends. Man-agement and employees of PTSC M&C would like to express our deepest thanks and appreciation to all of you, we wish you a new year ahead full of successes, good health and lucks.

Finally, we hope you enjoy this newsletter. Your feedback or comments, as always, are appreciated.

From Board of Director, PTSC M&C

Left to right: Mr. Tran Minh Tam- Deputy Director; Mr. Tran Thien Le - Deputy Director; Mr. Nguyen Quang Hieu - Deputy Director; Mr. Dong Xuan Thang - Director; Mr. Bui Hoang Diep - Deputy Director; Mr. Tran Duc Thang - Deputy Director

Page 4: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

In October 2012, PQP Topsides – the most technically complicated and vital part of the Bien Dong 1 Project left PTSC M&C’s fabrica-tion yard and en route to its loca-tion offshore Vietnam, marking an important milestone for the Project after a 2-year marathon journey.

The Bien Dong 1 (BD1) Project is an EPCI turnkey project awarded to PTSC M&C by Bien Dong Petroleum Operating Company (Bien Dong POC). This is the first and biggest offshore project ever performed by a Vietnamese local contractor, opening up new ho-rizons for the Vietnam oil & gas

The BienDong1 Project has achieved more than 10,274,209 man-hours without any lost time injuries

06 07

BD1 PROJECT - A TWO-YEAR MARATHON JOURNEY

construction industry in the future as well as proving the capability in provision of EPCI services of Viet-namese local contractors.

To acknowledge and honor the contribution of company employ-ees to the successful completion of the fabrication and pre-com-missioning work for the PQP-HT Topside, during the period of two (02) days from 13th to 14th Octo-ber 2012, PTSC M&C celebrated a team building event at Vung Tau City. At this momentous event, those individuals who have ex-celled themselves in the “Run-To-Target” campaign launched by the company were awarded for their

outstanding services extended to the BD1 Project.

As at October 2012, the offshore installation campaign of the PQP-HT Topsides was also successfully completed by float-over operation. Statistically, the BD1 Project has achieved more than 10,274,209 man-hours without any lost time injuries, which is a lively testimony of the coordinated effort made by Bien Dong POC and PTSC M&C.

The scope of work of the whole BD1 Project encompasses the engineering, procurement, con-struction, installation, offshore hook-up support for 01 Central

Processing Platform (PQP-HT) (including a 70-person-on-board living quarter); 02 Wellhead Plat-forms namely Hai Thach 1 (HT1) and Moc Tinh 1 (MT1), 03 jackets (PQP-HT, WHP-MT1 and WHP-HT1); 01 Link Bridge of which the total weight of facilities is approxi-mately 60,000MT coupled with 70km pipelines and 21km subsea cables. So far, this project has been considered as one of the most technically complicated offshore projects in Vietnam.

Page 5: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

Hai Su Trang/Hai Su Den Project achieved 1,000,000 manhours without any lost time incidents

08

The celebration is, more importantly, an in-dicator of the commitment shown by PTSC M&C so far in delivering this project safely.

The achievement of 1 million man-hours was built upon the strong foundation of professionalism and support of Thang Long JOC’s, PTSC M&C’s management and workforce. This reinforces the strong relationship that exists between these two companies and sets in place a founda-tion to grow and develop this cooperation spirit.

On 7th September 2012, Thang Long JOC and PTSC M&C celebrated the Health Safety and Environment Day to acknowledge the turning point of Hai Su Trang/Hai Su Den project upon achieving the target of 1 million man-hours without any LTI.

SU TU TRANG PROJECT OBTAINED ITS FIRST GAS AHEAD OF SCHEDULEOn 15th November 2012, at PetroVietnam Head Office in Ha Noi City, Cuu Long Joint Operating Company celebrated the First Gas Ceremony of the Su Tu Trang Project in block 15-1, offshore Vietnam.

Having attended the ceremony were there representatives of the Government Office, Ministry of Industry and Trade, Ministry of Planning and Investment, Petro-Vietnam, PetroVietnam Explora-tion and Production Corporation (PVEP) CLJOC’s partners, PTSC Mechanical and Construction (PTSC M&C) as well as other subcontractors.

Block 15.1 in Cuu Long Basin offshore Vietnam is evaluated as one of the best potential prospects in Vietnam. Since the Petroleum Contract was signed

09

Till date, the offshore installation campaign for Hai Su Trang and Hai Su Den Jackets and Pipelines was completed. In addition, the pre-commissioning and commission-ing work for Hai Su Trang and Hai Su Den Topsides was initiated and scheduled for completion in March 2013. PTSC M&C is in the process of doing the T&I engineering for two topsides supporting the installation campaign commencement in March 2013. Simultaneously, all procedure/ equipment for Hook-up and Commissioning (HUC) work is being prepared, ready for HUC schedule in April 2013.

in September 1998, exploration and production activities in the Block 15.1 have been implemented efficiently with 230 million barrels of oil and 684 million cubic meters of gas produced so far.

Su Tu Trang is amongst four discov-eries of Cuu Long JOC under the Petroleum Contract in block 15.1. In March 2010, the EPCI contract to build Su Tu Trang Wellhead Platform was awarded to PTSC M&C as a prime EPCI contractor. Although Su Tu Trang is not a challenging project in terms of schedule, it is however an EPCI project that required high technical standards and stringent construction requirements. In order to preserve the quality and schedule of the Project, PTSC M&C utilized existing fabrication yards, took ad-vantages of advanced technology as well as mobilized a strong resource of 750 workers and engineers who dedicated their utmost efforts to

contribute to the successful comple-tion of the project, achieving approx. 2,300,000 man-hours without any lost time injury.

At the First Gas Ceremony, Mr. Franck Poli, President of Perenco Company, a partner of Cuu Long JOC emphasized that the success of the Su Tu Trang Project could be measured by the skills and dedica-tion of the CLJOC employees and Partners’ seconded personnel in CLJOC, and the contribution and support of all stakeholders including the Government of Vietnam, Min-istries, PetroVietnam, Partners, the EPCI prime contractor PTSC M&C as well as other subcontractors and suppliers. He also believed that the Su Tu Trang Long Term Production Test (LTPT) program could provide assurance of commercial quantities of hydrocarbons that could be de-veloped to supplement the national energy demand.

Page 6: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

Rong Doi Booster Compressor is one of the projects developed by Korean National Oil Corporation (KNOC) to upgradeits ex-isting platform in block 11-2located 320km offshore Vietnam.

PTSC M&C was subcontracted by its sister company – PTSC Offshore Services (PTSC OS) the scope of de-tailed engineering, procurement and construction (EPC) for the Discharge Cooler and Booster Compressor systemweighing approximately 600 tons. The key functions of these sys-tems lie in their capability to enhance the pressure in gas pipeline from Rong Doi Well Head Platform to Nam Con Son Gas Pipeline.

The team formed by KNOC, PTSC OS, PTSC M&C and other subcon-tractors worked with the cooperative

10

spirit and zeal to successfully com-plete the project without any lost time incidents. Accordingly, the production target has been achieved since Octo-ber 2012. As reported by KNOC, the recoverable volume of this block is 753 billion standard cubic feet and produc-tion will continue by 2024.

UPGRADING RONG DOI BOOSTER COMPRESSOR

PTSC M&C WAS AWARDEDDUA SUBSEA DEVELOPMENT PROJECT

Located in the Chim Sao - Dua Field, block 12W offshore Vietnam, the Project relates to the development of the Dua subsea field as a subsea tie-back to the Lewek EMAS FPSO. The Project work-scope comprises instal-lation and construction engineering, onshore fabrication, procurement, construction, load-out, transporta-tion, offshore installation, hook-up, pre-commissioning, commissioning assistance of the buckle triggers, PLEM, Twin Pipeline Active Manifold (TPAM), 17 km of dual 10’’ flowlines, flexible risers, umbilical and associ-

ated subsea facilities.

Currently, the Project is being well-performed ensuring good quality. The onshore work carried out by PTSC M&C is ahead of schedule; particularly, the buckle triggers were completed 3 weeks in advance and are now ready for the 1st offshore installation campaign in February 2013. The team of PTSC M&C and Premier Oil employees are making great attempt to prepare for the 2nd offshore campaign in May 2013.

11

In September 2012, PTSC M&C was awarded the Dua Subsea Development Pro-ject (Project) by Premier Oil Offshore Vietnam (POVO). The contract values approxi-mately 58 million US dollars.

Page 7: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

PETROLEUM MANAGEMENT UNIT (PETRONAS)CARRIED OUT A CAPABILITY SURVEY

From 7th August to 8th August 2012 the delegation from Petronas Carigali Sdn Bhd of Malaysia, led by Mr. Zainud-din Kamarudin, General Manager paid a 2-day visit to PTSC M&C as part of its capability audit to update its bidder list for future projects.

After the site tour at the fabrica-tion yard and auditing PTSC M&C’s current capability, the Petronas team highly appreciated PTSC M&C’s ex-perience and infra-structure. In the meeting, Mr. Zainuddin Kamarudin highlighted on the business expan-sion plans of Petronas Carigali Sdn Bhd in South East Asia and Vietnam is considered as one of the potential markets in which Petronas will fur-ther develop their business oppor-tunities in the oil and gas explora-tion and production segment.

Since 2004, PTSC M&C has pro-vided Petronas with optimum solu-tions to build its offshore complex

Mr. Zainuddin Kamarudin, General Manager of Petronas Carigali Malaysia

12 13

GAZPROM’S VISIT TO PTSC

As part of the agreement jointly made by Gazprom and PetroVietnam, the delegation from Gazprom paid a working visit to PetroVietnam’s sub-sidiaries from 10th to 21st October 2012 with the aim of having a better understanding about Vietnam’s oil & gas industry. On 18th October, the delegation was warmly received by representatives from PTSC Headquar-ter and PTSC M&C Board of Management.

Gazprom is one of the giant global energy companies specialized in geological exploration, production, transportation, storage processing and sales of gas, gas condensate and oil. Currently, Gazprom is holding the world’s largest natural gas reserves. It has also partnered with Petro-Vietnam on a natural gas project in block 05.2 and 05.3 offshore Vietnam.

In an effort to give Gazprom’s delegation an insight into the techni-

projects in Vietnam such as Ruby A Expansion, Ruby-B, PLDP-A and Topaz.The successful completion of these projects is an indicator of the effective cooperation between Petronas and PTSC M&C. It also sets in place a foundation to strengthen and develop the business relation-ship which has been built up so far.

Being evaluated as a leading EPCI contractor in Vietnam, PTSC M&C expressed its interest in having more opportunities to offer comprehen-sive EPCI services to Petronas and make a positive contribution to Petronas sustainable development in Vietnam and region.

cal services provided by PTSC, PTSC gave a detailed presentation about its core services as well as its capability. Both parties had an open and fruitful discus-sion about each company’s sustainable development strategy and the potential-ity of cooperation.

After the constructive discussion, the delegation visited PTSC’s workshops and observed major pro-jects being carried out at PTSC’s fabrication yard.

Gazprom expressed their impression on the business growth of PTSC as well the experience levels it has achieved in Vietnam to date. Besides the delegation also sent the sincere thanks to the hospitality of PTSC and its subsidiaries dedicated to the delegation during their visit in Vietnam and believed that the spirit of friendship and cooperation between these two parties would remain strong.

Page 8: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

14

The achievements were thanks to the tireless endeavors of the company Board of management and dedicated employees who have strived daily in pursuit of work and made great attempt to navigate the company business through challenging waves caused by the vulnerable economy and stiff competition of the world players in the oil and gas segment.

Top 500 Vietnam Largest Enterprises by revenue ranking is being conduct-ed under the model of Fortune 500 which is in accordance with interna-tional standards. Amongst 300,000 Vietnamese enterprises, top 5,000

PTSC M&C was ranked 67th amongst top 500 largest Vietnam enterprises

On 11th December 2012, PTSC M&C was delightfully announced to be ranked 67th amongst top 500 largest Viet Nam enterprises.

ones with high revenue are select-ed; accordingly, 500 largest enter-prises are shortlisted. PTSC M&C has been officially listed in the top 500 Vietnam largest Enterprises since 2010 in which the company was ranked 115th. Improvement was made in 2011 and 2012 when our position is increased to 105th and 67th respectively.

At the top of the ranking is PetroVi-etnam which was ranked No.1 since the first launch of the rating pro-gram. PTSC M&C’s Parent company (PTSC Corporation) stood at No.26 in the list.

Mr. Tran Thien Le, Deputy Director, received the Merit Certificate of Top 500 Vietnam largest

enterprises

PTSC M&C Newsletter, No. 1, 2013Edited and designed by Business Development Department

Page 9: No.1 - 2013 BD 1 PROJECT - PTSCmc.ptsc.com.vn/images/file/Newsletter-Q3-Q4-2012.pdf · 2014. 9. 24. · lation and construction engineering, onshore fabrication, procurement, construction,

PTSC Mechanical and Construction JSC

No. 31, 30/4 Street, Ward 9, Vungtau City, SR Vietnam

No. 3 - 2012

BD 1 PROJECT

HAI SU TRANG / HAI SU DEN PROJECT

ACHIEVED 1,000,000 MANHOURS WITHOUT ANY LOST TIME INCIDENTS Page 8

SU TU TRANG PROJECT OBTAINED ITS FIRST GAS AHEAD OF SCHEDULE