NMCD CMIS Project Closeout

7
Presenters: Larry Pacheco, CIO Dan Donoghue, PM August 25, 2010

description

NMCD CMIS Project Closeout. Presenters: Larry Pacheco, CIO Dan Donoghue, PM. August 25, 2010. CMIS Project Overview. CMIS Background. Project funding : $1.1m General Fund/$600k NMCD - PowerPoint PPT Presentation

Transcript of NMCD CMIS Project Closeout

Page 1: NMCD CMIS Project Closeout

Presenters:Larry Pacheco, CIODan Donoghue, PMAugust 25, 2010

Page 2: NMCD CMIS Project Closeout

2007 2008 2009/2010 2011 2012

Establish Project Management

Office

Change Control Management

Provide Independent Verification and Validation

Application Security

1 – OMP

Training

NCOMS Standards

Requirements Gathering

4. – Property

3 – Booking

2 – F-Track

5 – Release &

Discharge

14 – Inmate Trust

13 – Housing

12 – Security

17 – Discipline

11 - Grievance

9 – Visitation

8– Classification

10– Medical

6 – Good Time

15 – STIU

16 – Parole Board

RFP Process

7– Sentencing

Page 3: NMCD CMIS Project Closeout

Project funding : $1.1m General Fund/$600k NMCD CMIS is the principal electronic offender

management system at NMCD. CMIS manages approximately 26,000 offenders from pre-sentencing through probation and parole.

Project Goals:• Move from client-server to web-based

Allow easier maintenanceEnhance securityAdd functionalityConsolidate screens

Leverage other states’ work through NCOMS consortium.

Page 4: NMCD CMIS Project Closeout

NCOMS –National Consortium of Offender Management Systems

Sharing code with other states Idaho to NMCD – OMP NMCD to Utah– F-Track Alaska to NMCD – Booking NMCD to Missouri - Security NMCD to Missouri – OMP Missouri to NMCD - Property

Quicker and more cost effective $20-30M system for approximately $5M

Page 5: NMCD CMIS Project Closeout

Budget $1.7m spent/$1.1m from Legislature

Schedule• 5 change requests• Project completed on time

Scope – No scope changes IV&V – Project green Vendor – 50 of 52 deliverables accepted

Page 6: NMCD CMIS Project Closeout

Developed 7 ½ modules over two years. RFP only called for 4.

Trained applications staff on new technologies

Successful user acceptance Successful train-the-trainer sessions Successfully introducing a paradigm shift

for OMP implementation Moved from a maintenance shop to a

projectized shop

Page 7: NMCD CMIS Project Closeout

1. FY11 – Continue deploying modules developed in FY09 and FY10.

2. Develop three new modules according to CTA specifications.

3. FY12 – Requesting $400,000 in C2 funding to accelerate module development and deployment.

4. Continue developing and deploying CMIS modules according to CTA specifications.