NLC INDIA LIMITED PRE FEASIBILITY...
-
Upload
truongdieu -
Category
Documents
-
view
225 -
download
0
Transcript of NLC INDIA LIMITED PRE FEASIBILITY...
NLC INDIA LIMITED
PRE FEASIBILITY REPORT
2x660 MW SUPER-CRITICAL LIGNITE BASED POWER PLANT AT MUDANAI DISTT. CUDDALORE,
TAMILNADU
NOVEMBER 2016
DESEIN PRIVATE LIMITED
CONSULTING ENGINEERS DESEIN
HOUSE, GREATER KAILASH-II NEW DELHI – 110 048
NLC INDIA LIMITED
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
INDEX
S.NO. DESCRIPITION SHEET NO.
1.00.00 Introduction and Background 1-2
2.00.00 Site Selection and Feasibility Studies 3-4
3.00.00 Project Highlights and Technical Features 4-9
4.00.00 Environmental Aspect 10-13
NLC INDIA LIMITED
Sheet - 1
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
1.00.00 Introduction and Background
Electricity is a basic human need and essential requirement for all facet of
our life. Power development is one of the key infrastructure elements for
the socio-economic growth of the country. The entire Indian Economy
hinges on the availability of reliable and quality power at competitive rates
to rural India for its overall growth and to Indian Industry to make it globally
competitive.
NLC India Limited (a NAVRATNA CPSU) is engaged in mining and power
generation since its inception and has contributed to the social and
economic development of the country for over 5 decades. NLCIL is
presently having lignite mining operations in Neyveli (Tamilnadu) and
Barsingsar with associated power generation units of 3289 MW capacity.
NLCIL is also owning and operating a 2X500 MW coal based station at
Tuticorin (in Joint Venture project with TANGEDCO, Tamil Nadu). .
NLCIL has the advantage of vast expertise in both mining and power
sectors giving it a unique position for setting up of cost effective power
projects. In addition to operation of Mine-I, Mine-IA and Mine-II, NLCIL
had initiated action for development of Mine-III and 2x500 MW lignite fired
thermal power project. Accordingly, NLCIL had appointed M/s Desein
Private Limited as a consultant for preparing the Feasibility Report.
The proposal for seeking approval of Terms of Reference (TOR) of
Environmental Impact Assessment (EIA) study was submitted vide
proposal no. IA/TN/THE/53173/2016 to Ministry of Environment & Forests
(MOEF). In response, MOEF has informed that “as per the Ministry of
Power’s O.M. dated 13.11.2009, the 13th Plan (01.04.2017 onwards)
NLC INDIA LIMITED
Sheet - 2
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
capacity addition will be through supercritical units only. Hence, necessary
action may be taken accordingly.”
The consultant was accordingly advised to examine the feasibility to revise
the project configuration from 2x500 MW to 2x660 MW taking in to
account all relevant aspects including availability of basic inputs like land,
water & fuel and availability of proven technology & equipment suppliers
for lignite based Super Critical Steam Generator units etc. Various rounds
of discussions were held with all prospective equipment suppliers to
ensure adequate competition in tendering process.
The above points have been suitably addressed and hence the present
proposal is for implementation of 2x660 MW Lignite based super critical
units at Mudanai (Neyveli) in Cuddalore District of Tamil Nadu.
It is worthwhile mentioning that the proposed plant would be the first lignite
fired 660 MW Supercritical Unit in India. Numerous references of installed
units of lignite fired Supercritical plants are found outside the country in
Germany, USA, Japan & China as given below:
LIGNITE BASED SUPER CRITICAL THERMAL POWER PLANTS IN OPERATION
Sl. No. Name of the Plant Country Capacity
1. LIPPENDORF TPS GERMAN 2 X 920 MW
2. BOXBERG TPS GERMAN 1 X 900 MW
3. SCHWARZE TPS GERMAN 2 X 800 MW
4. MEHRUM TPS GERMAN 1 X 660 MW
5. MATSUURA TPS JAPAN 2 X 1000 MW
6. MANL TPS USA 2 X 1100 MW
7. NIEDERAUSSEM GERMAN 1 X 1000 MW
8. NEURATH TPS GERMAN 2 X 1100 MW
9. BAICHENG CHINA 2 X 660 MW
10. HUANENG JIUTAI CHINA 2 X 670 MW
NLC INDIA LIMITED
Sheet - 3
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
2.00.00 Site Selection and Feasibility Studies
The present project site near village Mudanai was selected by the site
selection team of NLCIL for development of 2x500 MW lignite based
project after examining four alternative site based on the following
considerations:
1. Availability of suitable & adequate land
2. Availability of reliable source of water
3. Availability of road and railway access
4. Environmental aspects
5. Availability of infrastructural facilities
6. Conformity to Siting Criteria of MOEF
The Site Selection Committee Report is placed at Annexure-I. The salient
details of alternative sites are briefly elaborated below:
Site-I Near Village Kolliruppu
The site is on the western side of the village Kolliruppu adjacent to
upcoming Neyveli New Thermal Power Project (NNTPP) of NLC India
Ltd., and comprises of about 200 acres of land in possession of NLCIL. As
the land area is only 200 acres, the site is not considered suitable.
Site-II Near Village Mudanai
The site is on south west side of Thermal Power Station-II (TPS-II) near
village Mudanai and comprises of about 608 acres of land in possession
of NLCIL. The site is in close vicinity of Mine-II & III so the lignite could be
fed through conveyor system. There is an under-utilized ash dyke of the
TPS-II and water reservoir of TPS-II near the site-II, which could be used
NLC INDIA LIMITED
Sheet - 4
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
for the proposed TPS-II 2nd expansion project. The plant area and
associated facilities could be accommodated within the land in possession
of NLCIL. The site elevation is 50m to 57 m MSL. The site is therefore
considered suitable.
Site-III Near Village Marungur
The site is located at a distance of approx. 12 kms. South West of TPS-II.
There is no land in possession of NLCIL. The entire land is fertile
agricultural land and will pose lot of problem in acquisition. Further, it will
require crossing of river Manimutharu for transportation of Lignite through
conveyor system. Hence, this site was not considered suitable.
Site-IV Near Village Kammapuram
The site-IV is located at a distance of 8.5 kms. South of TPS-II and
comprises of 1452.98 acres of land for which administrative approval was
accorded by Govt. of Tamil Nadu. NLCIL has plan for augmentation of
Mine-II from 15 MTPA to 18.75 MTPA. It is learnt that this 1452.98 acres
land will be required for additional external dump area. Hence this site is
not considered suitable for for TPS-II 2nd expansion project.
3.00.00 Project Highlights and Technical Features
In line with the observations of MOEF and considering the feasibility
aspect brought out at 1.0 above, it is proposed to adopt Ultra Supercritical
technology. The advantages of supercritical technology are listed below:
Higher plant efficiency
Less Fuel Consumption
NLC INDIA LIMITED
Sheet - 5
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
Less Infrastructure Investment for Fuel Transport / Storage and Ash
Disposal
Less Emission (CO2, SOx, NOx, Dust/Ash)
Less Auxiliary Power Consumption of plant auxiliaries.
Less Water Consumption (No need of continuous blow down in
case of once through boiler.)
Lower operating costs
Greater operating flexibility
Location
The site is on south west side of Thermal Power Station-II (TPS-II) near
village Mudanai and comprises of about 608 acres of land in possession
of NLCIL. The nearest airports are at Trichy Airport at a distance of 150
kms. And Chennai airport at a distance of approx. 200 KMs. Nearest
railway station at Uthangal Mangalam on Vridhachalam- Cuddalore
section is at a distance of 1.5 kms.
Land Requirement
The plant & associated facilities including green belt, ash disposal and
Townships of the project is proposed to be accommodated within the land
under possession of NLC India Limited. The overall plant layout is shown
in the Plot Plan placed at Annexure-II.
Capacity : 2X660 MW - Present proposal
Mode of Operation : Base Load
Fuel : Lignite from the basket of captive mines
comprising of Mines I, IA, II & the
proposed Mine-III
NLC INDIA LIMITED
Sheet - 6
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
Lignite Availability and Transportation
The daily Lignite requirement for 2x660 MW units shall be about 32280
tonnes. Annual Lignite requirement for the plant shall be around 10 MTPA
considering PLF of 85% and the same is proposed to be met from nearby
mine blocks of NLCIL. The envisaged mode of Lignite transportation from
the proposed mine is by belt/ piped conveyor system as the site chosen is
very close to the mine block.
Cooling Water Source, Requirement and Commitment
Consumptive make-up water requirement of the project shall be 3400
m3/hr with ETP Recovery and 4221 m3/hr without ETP Recovery.
Makeup water from the source shall be pumped to an in-plant raw water
reservoir having storage capacity of about 10-15 days to take care of
emergencies. Presently, Natural Draft Cooling Towers NDCT have been
proposed for the project. It is envisaged to adopt Cycle of Concentration in
such a way to achieve zero discharge of plant’s treated effluents to any
water body outside the project area.
Steam Generator Technology
The Steam Generators (SG) shall be super-critical, once through type,
water tube, direct pulverized lignite fired, top supported balanced draft
furnace, single reheat, radiant, dry bottom type, suitable for outdoor
installation. The gas path arrangement shall be single pass (tower type) or
two pass type rated to deliver approx. 2100 t/hr of superheated steam at
270 kg/cm2(a) & temperature of 603±5ºC with feed water temperature of
about 305ºC at the economizer inlet. The reheat steam temperature
would be of 610±5ºC.
NLC INDIA LIMITED
Sheet - 7
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
The SG would be designed to handle and burn HFO/Light Diesel Oil
(LDO) as secondary fuel up to 30% SG MCR (maximum continuous
rating) capacity for flame stabilization during low-load operation. For unit
light up and warm up purposes, light diesel oil (LDO) would be used with
air atomization.
Steam Turbine Technology
The steam turbine shall be tandem compound, single reheat,
regenerative, condensing, multi cylinder design with separate HP,
separate IP and separate LP casing(s) OR combined HP-IP and separate
LP casing(s), directly coupled with generator suitable for indoor
installation.
Turbine shall be capable of operating continuously with valves wide open
(VWO) to swallow 105% of EMCR steam flow to the turbine at rated main
steam and reheat steam parameters. The steam turbine generator shall
also be capable of delivering at generator terminals at least 105% of rated
output (Guaranteed Output) without any constraints with all the valve wide
open, rated steam condition and condenser pressure as optimized by TG
supplier targeting lowest heat rate with 0% makeup.
Lignite Handling System
External Lignite Handling System (ELHS) shall comprise of two (2)
identical & parallel streams of around 3000 TPH rated capacity each to
deliver Lignite from mines to the power plant site. In view of long distance
( 10.5 km), Pipe Conveyor / Belt Conveyor System may be envisaged for
lignite transportation. Possibilities of having lignite crushing facilities and
the crushed lignite stockyard at the mine end shall be examined in detail
during FR formulation stage.
NLC INDIA LIMITED
Sheet - 8
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
Internal Lignite Handling System (ILHS) consisting of two (2) identical &
parallel streams to operate at rated capacity of around 3000 TPH each are
envisaged for the proposed Power Plant to cater to the fuel requirements
of 2X660MW Units i.e. Unit – 1&2.
Beneficiary States
The project is being set up to supply power to home state of Tamil Nadu &
other willing beneficiaries.
Project Implementation Schedule
Commercial Operation Date (COD) of the first 660 MW units is envisaged
in 48 months from the zero date and second unit at an interval of 6 months
thereafter. The zero date shall be reckoned as the date of main plant
award.
Associated Transmission System (ATS) Clearance
The power generated from the project will be evacuated through 2 nos.
D/C 400 KV transmission lines up to the nearest 400 KV Pooling
Substation of Central Transmission Utility i.e. Power Grid Corporation of
India Limited (PGCIL). Unit start-up power requirements shall be met by
back charging of one of 400 kV transmission line. The present provisions
for power evacuation are tentative and shall be reviewed based on the
finalized ATS of the project by PGCIL. Commitment from PGCIL shall be
obtained for the necessary infrastructure for power evacuation from the
proposed generating station, by erecting transmission lines as deemed fit
and necessary.
NLC INDIA LIMITED
Sheet - 9
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
Project Financing
The overall debt-equity ratio proposed is 70:30. Equity will be financed
through internal resources and the debt portion is proposed to be financed
from Domestic Commercial Borrowings.
Indicative Project Capital Cost
The indicative project capital cost of the proposed 2x660 MW project shall
be as under:
Cost of Project including IDC Rs. 9240 Crores
Cost per MW Rs. 7.00 Crores
The above estimated cost is of the order cost without any detailed
estimation of bill of quantities for the purpose of Pre-Feasibility Report
only. However, the detailed cost estimates and financial analysis will be
carried out during Detailed Project Feasibility Report stage based on the
site specific data.
Conclusion
On analysis of all aspect involved for the development of the project, it is
concluded that:
“It is technically feasible to establish 2x660 MW units based on Super-
critical Technology at the site identified for the project considering the
availability of infrastructural facilities subject to tying up of basic inputs and
obtaining the statutory & non statutory clearance of the concerned
authorities.”
NLC INDIA LIMITED
Sheet - 10
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
4.00.00 Environmental Aspect
A Draft Environmental Impact Assessment report for this project will be
prepared based on the TOR prescribed by MOEF. Tamil Nadu State
Pollution Control Board will then be approached for conducting Public
Consultation. Thereafter, the EIA report will be finalized incorporating
public hearing minutes & action plan for its submission to Ministry of
Environment & Forests (MOEF) for obtaining Environmental Clearance
(EC), in accordance with the procedure laid down in the MOEF Notification
dated 14th September’ 2006 and its further amendment dated 01st
December’ 2009. All relevant notifications in respect of environmental
protection measures/ guidelines including the December 2015 notification
shall be fully complied.
Air Pollution Control System
High efficiency electrostatic precipitators (ESPs) will be installed to limit
the particulate emission to 30 mg/Nm3 to facilitate wider dispersion of
particulate and gaseous pollutants. A twin flue chimney of appropriate
height will be provided for wider dispersion of pollutants. On-line
equipment will be provided for monitoring of stack emissions.
To control NOx emission, supercritical boilers having advanced low NOx
generation system will be installed. In addition, Selective Catalytic
Reduction (SCR) system will be installed to limit the NOx emission as per
latest environmental guidelines.
FGD system will be installed in flue gas duct to the chimney as per latest
environmental stipulation. The design and layout of steam generator and
its auxiliaries will take into account wet flue gas desulphurisation (FGD)
system to be installed taking suction from duct after ID fan and feeding the
NLC INDIA LIMITED
Sheet - 11
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
desulphurised flue gases back to the chimney with provision for bypassing
the FGD system.
For control of fugitive dust emissions within and around coal handling
plant, dust extraction/ suppression systems would be provided. Dust
suppression system shall also be provided in the coal stock yard.
Noise Pollution Control Systems
The major noise generating sources in a thermal power plant are the
turbines, turbo-generators, compressors, pumps, fans, coal handling plant
etc. from where noise is continuously generated. Acoustic enclosures
shall be provided wherever required to control the noise level below 90 dB
(A). Wherever required, the workers shall be provided with protective
equipment such as ear plugs and ear muffs.
Solid Waste Management Systems
Ash will be the major solid waste generated from the power project. An
ash management scheme shall be implemented consisting of dry
collection of ash, supply of ash to entrepreneurs for utilization and
promoting ash utilization to maximum extent and safe disposal of unused
ash. Ash utilization.
The proposed expansion project is based on lignite as fuel, which contains
low ash (approximately 5 to 8%) and hence the ash disposal burden is
quite less compared to a coal fired power station. Moreover Neyveli is
located in southern region surrounded by many cement industries and
there are many cottage industries who manufacture fly ash bricks,
window/ door frames, paver blocks using the ash. In fact 100% ash
utilization is achieved in the existing stations of NLCIL. Hence Emergency
NLC INDIA LIMITED
Sheet - 12
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
Ash Dyke of 125 Acres developed for TPS II is envisaged to be used for
this expansion project.
Water Pollution Control System
An effluent management scheme, consisting of collection, treatment,
recirculation and disposal of effluents shall be implemented in order to
optimize the makeup water requirement as well as liquid effluent
generation.
The liquid effluents shall be collected and treated/ recycled as per the
following design philosophy:
The sludge from clarifiers of water PT Plant shall be collected in a
sump/ pit and shall be treated in order to extract most of the water
from the sludge for reuse & solid particles in the form of semi-solid
shall be dispose of suitably either for land fill or in the bottom ash
dyke.
The waste effluents from neutralization pits of DM plant and
condensate polishing plant shall be collected in the common
neutralization pits and neutralized before pumping to dispose of in
bottom ash dyke along with bottom ash slurry.
Similarly service water waste from different parts of the power plant
such as ESP, BTG area etc. shall be dispose of in bottom ash dyke
along with bottom ash slurry.
Oily waste from the power plant shall be collected & treated in oil
water separator in order to separate oil. Clear water shall also be
dispose of in bottom ash dyke along with bottom ash slurry.
Re- circulating type cooling water (C.W) system with cooling
towers, with C.W. blow down from cold water side to ensure no
thermal pollution. The blow down shall be led to central monitoring
NLC INDIA LIMITED
Sheet - 13
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
basin after treating through clarifiers/ tube settlers, filters, UF filters
& RO, the RO permeate shall be reuse in CW make up. The
sludge from clarifiers/ tube settlers, & RO reject shall be disposed
of in bottom ash dyke along with bottom ash slurry.
Lignite particle settling pond shall be provided to remove lignite
particles from lignite handling plant waste. Decanted water shall be
pumped back to the lignite dust suppression system
An independent plant effluent drainage system would be constructed to
ensure that plant effluents do not mix with storm water drainage. Efficient
operation of various treatment schemes shall be ensured so that the
quality of treated effluent from CMB conforms to relevant standards,
prescribes by regulatory agencies.
The sewage from plant and township shall be treated in a sewage
treatment plant. The treated sewage conforming to prescribed standards
shall be utilized for plantation to the extent possible.
Description of the Environment
In order to identify the environmental impacts due to the construction and
operation the project and associated facilities, an EIA study is proposed to
be undertaken to establish baseline environmental status for various
environmental attributes within the study area. The major environmental
disciplines to be covered in the EIA report includes ambient air quality,
water quality, noise, soil, ecology (terrestrial and aquatic), land use,
geology, hydrology and demographic & socio-economic conditions.
NLC INDIA LIMITED
Sheet - 14
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
Annexure 1
NLC INDIA LIMITED
Sheet - 15
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
NLC INDIA LIMITED
Sheet - 16
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
NLC INDIA LIMITED
Sheet - 17
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
NLC INDIA LIMITED
Sheet - 18
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
NLC INDIA LIMITED
Sheet - 19
ISO 9001:2008 Registered Company Certificate No. 10692
CIN : U74899DL1970PTC005474
A D e v e l o p m e n t S e r v i c e f o r I n d u s t r i e s & U t i l i t i e s
1 KOLLIRUPPU
2.MUDANAI
4.KAMMAPURAM
3.MARUNGUR