NIStructE Keynote Address
-
Upload
seunadelani -
Category
Documents
-
view
65 -
download
0
Transcript of NIStructE Keynote Address
KEYNOTE ADDRESS
ON
“Collapse of Engineering Structures: Causes, Implications and Prevention”
BY
ENGR DR EDET J. AMANANA, FNIStructE, FAEng, OON
(President of the Nigerian Academy of Engineering)
AT THE 23RD ANNUAL CONFERENCE OF
THE NIGERIAN INSTITUTION OF STRUCTURAL ENGINEERS (NIStructE)
The Chairman of this great occasion, Engr Mustapha Bulama, FNIStructE, FNSE
President of the Council for the Regulation of Engineering in Nigeria (COREN),
The President of Nigeria Society of Engineers (NSE),
The President Nigerian Institution of Structural Engineers, Engr Victor Oyenuga,
FNIStructE, FNSE,
President, Nigerian Institute of Civil Engineers (NICE)
Presidents of other Professional bodies here present,
Chairmen of branches of NSE here present,
Distinguished Fellows and Members of NIStructE,
Distinguished Invitees,
Gentlemen of the Press,
Distinguished Ladies and Gentlemen.
Introduction
I thank the President of NIStructE and the organising committee of this conference
for the honour they have done me by inviting me to give this keynote address. I must
confess this invitation came at a time when I had a bunching of activities in my
calendar and there was a great temptation for me to request that I be considered for
another conference maybe next or so. But I must confess that I could not bring
myself to say no to Engr Victor Oyenuga, our able president Victor, I thank you so
much for your call and your soft persuasive voice.
Talking about Collapse of Engineering Structures, structure is talking about the very
life and death of our profession; life in the sense that the greatest joy of the
structural engineer is in seeing an edifice he/she has created standing out
beautifully, majestically and fulfilling the function for which it was designed; death
because many a structural engineer has been known to wish themselves dead when
a structure which they gave their all to design has suddenly collapsed and brought
about the death of so many people.
The fact that the collapse of structures always results in death of so many including
the reputation of the structural engineer underscores the need to carefully study,
document and review each incident of collapse in order to learn new lessons, avoid
future collapses and progress the science and art of structural engineering.
Definitions
But before we go any further we would like to take some definitions.
First: What is Structural Engineering?
Second: What is Structural Collapse as different from Structural Failure – another
term often used when a structure cannot perform its designed function?
For the definition of Structural Engineering I shall adapt a definition credited in
the literature to the man who taught me structural engineering at the Imperial
College, Dr. Eric Brown. I define Structural engineering as “the art and science of
modelling materials we do not wholly understand into shapes and forms we cannot
precisely analyse to withstand forces we cannot properly assess in such a way that
the structure stands up and the public at large has no reason to suspect the extent
of our ignorance.” This definition is instructive and we shall see its relevance as we
analyse specific cases of collapse.
A
Structural Collapse
Before we turn our searchlight on structural collapse, let us look at the
complimentary issue of structural failure which may be defined as “an unacceptable
difference between expected and observed performance of the structure”. I was in
Abuja recently and I saw an almost completed eight storey structure built into the
slope of a hill in Maitama. The building is cracked all over but it is still standing; it
has not “collapsed”. But I bet not even a mad man will try to live there. This is a
situation in which the building structure has failed and cannot fulfil the function it was
designed for. That building will eventually be brought down. But there are many
situations in which failure is localised and the structural system has so much
redundancy that there is a redistribution of forces and structural collapse does not
occur.
Structural collapse may be defined as that state of failure of the structure in which
the whole structure or a part of it is incapable of sustaining any load and therefore
becomes unstable and falls down which result from inability of the structure to resist
static loads (static instability) or inability to withstand dynamic loads (dynamic
instability). It is pertinent to observe that every structural collapse originates from a
failure of a structural member or component. The study of structural collapse will
therefore necessarily entail careful analysis of the issues which bring about
structural failures. The study of these issues is so important to our profession that an
entirely new discipline “Forensic Engineering” has been created to deal with the
investigation of failures. Most of the landmark cases of structural collapse have been
the result of catastrophic failures of structural components which resulted in total
instability of the structure. In the discussion which follows, the words “failure” and
“collapse” shall be used interchangeably. I have done this because from the
engineer’s point of view, a structure which fails to perform its designed function
needs to be brought down – demolished.
Collapse of structures could manifest in three forms:
1) Partial Collapse is that state of failure when only part of the structure is
affected. This would typically happen when a structural element has failed but
the structure system has enough redundancy for the loads to be redistributed
in such a way that the structural system does not become unstable but is still
able to sustain applied load.
2) Progressive Collapse is the state of affairs in which the failure of a structural
element brings about the transfer of forces to other parts of the structural
system where there is inadequate resistance and so the whole system
becomes unstable and collapse progresses from one part of the structures to
other part until the complete structure falls down.
3) Total/Sudden Collapse happens without any prior indication or warning.
Structural Design
In the design of structures, the limit state of performance can be classified into two
categories i.e. the Ultimate Limit State (ULS) and the Serviceability Limit State
(SLS). A limit state is a set of performance criteria (e.g. vibration levels, deflection,
strength, stability, buckling, twisting) that should not be exceeded when the structure
is subjected to loads. Any design process involves a number of assumptions and
actions. To satisfy the Ultimate Limit State, the structure must not fail when
subjected to the peak design loads. To satisfy the Serviceability Limit State Criteria,
a structure must remain functional for its intended use when subjected to
routine/everyday loading, the structure must not cause users or occupants
discomfort under routine service conditions.
Therefore, in carrying out the design of a structure, it is very important to have:
1) A complete and accurate assessment of all possible loads and different
combinations of their applications throughout the life cycle of the structure
from construction through service.
2) An accurate assessment of the quality, strength and variability of the
materials used in forming the structural components/members. A good
example of how quality, strength and variability play out in our environment in
the wide variability of the strength of concrete used in our construction sites.
What many of our builders called concrete is often a “slurry” which cannot
stand the standard test of concrete mixes with regard to slump and other tests
which would give an indication of what strength to expect.
3) A proper understanding of structural behaviour cases of the structure in which
consideration must be given to all loading under stages of construction and
operation with due regard to possible scenarios of serviceability and ultimate
limit states.
The different codes of practice give guidance on these matters and the use of
appropriate softwares whose limitations must be properly understood will help is
performing the complex calculations involved in structural analysis and design.
B
Study of Landmark Engineering Failures/Collapse
Exposure to landmark engineering failures and the subsequent investigation reports
gives structural engineers a better theoretical understanding of the nature of
materials they work with. They become aware of the manner in which engineering
design strategies evolve and how those design theories approximate to service
conditions. They also gain a greater appreciation for the inherent professional
responsibilities of their chosen profession. In addition to technical factors, the study
of engineering failure case histories provides opportunities for discussions of
important nontechnical topics: ethics, professional liability, human factors, and the
critical interpersonal skills and interdisciplinary relationships and regulatory
framework required for the delivery of a successful project.
We shall now look at a few typical failures which have been documented in the
literature to examine their causes, and implications and draw lessons on how they
could have been prevented. We believe that for engineers, a single sketch
communicates more information than pages of writing. We shall therefore use
sketches to illustrate our points here.
Hyatt Regency Walkway Collapse, Kansas City, Missouri, USA, July 17, 1981
A 40-storey tower comprising of an atrium and a function block with three walkways
spanning 37m, the Hyatt Regency Crown Center in Kansas City, Missouri was
opened in July 1980 after four years of design and construction. The walkways were
suspended from the atrium’s ceiling by 32mm diameter hanger rods. The second-
floor walkway directly below the fourth-floor walkway, was suspended from the
beams of the fourth-floor walkway, and third and fourth-floor walkways hung from
the ceiling.
On July 17, 1981, about 2000 people were on the atrium floor and on the suspended
walkways to see a local radio stations dance competition when a loud crack echoed
throughout the building and the second and fourth-floor walkways crashed to the
ground, killing 114 people and injuring more than 200 others.
Causes
From the investigation carried out by the National Institute of Standards and
Technology (NIST), it was discovered that the hanger rod pulled through the box
beam causing the connection supporting the fourth-floor walkway to fail. Due to lack
of redundancy and alternate load paths, the other rods could not handle the
increased load once the adjacent rod failed and this failure caused the collapse of
both walkways.
Originally, the second and fourth-floor walkways were to be suspended from the
same rod and held in place by nuts. The preliminary design sketches contained a
note which specified strength of 413MPa for the hanger rods which was omitted on
the final structural drawings. Following the general notes in the absence of a
specification on the drawing, the contractor used hanger rods with only 248MPa of
strength. This original design however was impractical because it called for a nut
6.1m up the hanger rod and did not use sleeve nuts. The contractor modified this
detail to use two hanger rods instead of one and the engineer approved the design
change without checking it. This design change doubled the stress exerted on the
nut under the fourth floor beam.
This underscores the need for design engineers to think through their design details
and not leave room for the contractor to improvise. The contractor is not mentally
equipped to see all the design implications.
Fail
Tacoma Narrows Bridge, Tacoma, Washington, USA, November 7, 1940
Cause
It was the 3rd longest bridge in the world when it was opened in July 1940. It was
much narrower, lighter and more flexible than any other bridge of its time. The
bridge designer wanted the bridge to maintain a sleek appearance, that he designed
it without the use of stiffening trusses, replacing them with shallower plate girders.
This modification left Tacoma Narrows Bridge with one-third the stiffness of some of
its contemporaries like Golden Gate Bridge and George Washington Bridge. These
characteristics coupled with low dampening ability caused large vertical oscillations
in the bridge even in the moderate of winds which earned it the nickname “Galloping
Gertie”.
Under the effect of a storm whose wind speed was about 68kph, the cable stays on
the west side and north centre of the bridge broke thus causing the bridge to twist
violently in two parts (with rotation of more than 45o and vertical movement of 8.5m).
This twisting motion caused high stresses throughout the bridge and led to failure of
suspenders and eventually the collapse of the main span.
Implications
The collapse showed engineers and the world the importance of damping, vertical
rigidity and torsional resistance in suspension bridges. It also highlighted the
importance of failure literacy, knowledge of historical failures and their causes. The
imperativeness of studies on the aerodynamic forces that act on suspension bridges
was also highlighted.
Preventive Measures
Once the threat of twisting in the bridge was realized, there are many ways the
disasters could have been averted. Any of the following adjustments could have
prevented the collapse.
Using open stiffening trusses, which would have allowed the wind free
passage through the bridge.
Increasing the width-to-span ratio.
Increasing the weight of the bridge.
Dampening the weight of the bridge.
Using an untuned dynamic damper to limit the motions of the bridge.
Increasing the stiffness and depth of the trusses and girders
Streamlining the deck of the bridge.
Lessons Learnt
The question to be asked when innovations like suspension bridges were conceived
is “How do we strike a balance between public welfare and progress in the face of
new technology?” If the bridge has been designed similar to the ones that had
already proven their stability, it would never have collapsed. On the other hand, if
engineers never tried innovative techniques, suspension bridges might never have
been built at all.
The limits of technology was pushed by trying to create a longer sleeker and less
expensive bridge. Every time engineers push the limits of technology, they risk a
similar loss, sometimes even loss of life. At the conceptual stage of innovative
design, engineers or designers should ponder on and be able to provide answers to
questions like “When is a possible advance worth a risk to public safety?” and “What
can engineering profession do to make the implementation of new technology safer?”
Teton Dam Collapse, Teton River, Idaho, USA, June 5, 1976
Teton Dam, situated on the Teton River, northeast of Newdale, Idaho was designed
to provide recreation, flood control, power generation and irrigation for over 100,000
acres of farmland. The design of the foundation consisted of four basic elements:
1. 21-meter deep, steep-sided key trenches on the abutments above the
elevation of 1,550 meters;
2. A cut off trench to rock below the elevation of rock under the abutments;
3. A continuous grout curtain along the entire foundation;
4. The excavation of rock under the abutments.
These elements for the foundation were important because the types of rock located
in this area, basalt and rhyolite are not generally considered acceptable for structural
foundations.
When the construction of the dam began in February 1972, the embankment was
proposed to have a maximum height of 93 meters above the riverbed and would
form a reservoir of 365 million cubic meters when filled to the top. The dam was
closed and began storing water on October 3, 1975 but the river outlet works tunnel
and auxiliary outlet works tunnel were not opened. Due to these incomplete
sections, the water was rising at a rate of about 1m per day instead of the targeted
rate of 0.3-0.6m per day.
On June 3, 1976, a major leak flowing at about 500-800L/s was noticed which later
increased to 1100-1400L/s an hour later. Seepage at about 40m below the crest of
the dam was also noticed. Two hours later, a whirlpool was observed in the reservoir
directly upstream of the dam due to the expansion of the location of the leak up the
dam and after a while a chunk of the dam fell into the whirlpool leading to the entire
collapse of the dam.
After the failure, an Independent Panel was set up to review the cause of the
collapse. The panel summarised its conclusions as follows:
1. The design of the dam followed well-established USBR practices, but without
sufficient attention to the varied and unusual geological conditions of the site.
2. The volcanic rocks of the site are “highly permeable and moderately to
intensely jointed”.
3. Considerable effort was used to construct a grout curtain of high quality, but
the rock under the grout cap was not adequately sealed. The curtain was
nevertheless subject to piping – “too much was expected of the grout curtain,
and the design should have provided measures to render the inevitable
leakage harmless”.
4. The dam’s geometry caused arching that reduces stresses in some areas and
increased them in others and favoured the development of cracks that will
open channels through the erodible fills.
5. Finite element calculations suggested that hydraulic fracturing was possible.
6. Piping was identified as the most probable cause of the failure. Two
mechanisms on how the piping started were suspected to be possible. The
first was the flow of water under highly erodible and unprotected fill, through
joints in unsealed rock beneath the grout cap, and development of an erosion
tunnel. The second was cracking caused by differential strains or hydraulic
fracturing of the core material.
7. The fundamental cause of failure may be regarded as a combination of
geological factors and design decisions that, taken together permitted the
failure to develop.
This case may be best summarised in the words of the panel’s report,
1. The dam failed by internal erosion (piping) of the core of the dam deep in the
right foundation key trench, with the eroded soil particles finding exits through
the channels in and along the interface of the dam with the highly pervious
abutment rock
2. The exit avenues were destroyed and removed by the outrush of reservoir
water.
3. Openings existed through inadequately sealed rock joints, and may have
developed through cracks in the core zone of the key trench.
4. Once started, piping progressed rapidly through the main body of the dam
and quickly led to complete failure.
5. The design of the dam did not adequately take into account the foundation
conditions and the characteristics of the soil used for filling the key trench.
Ronan Point Apartment Tower Collapse, London, Britain, May 16, 1968.
Ronan Point Progressive collapse was due to failure of a structural element cause
by gas explosion on 19th floor of the 22 storey block of flats. The blocks of flats were
constructed using precast floors, walls and staircases. Ecah floor slab was
supported by the load bearing walls beneath it and the wall and floor panels were
fitted together in slots and bolted; the joints being packed with dry mortar to secure
the connection.
The force of the explosion knocked out the opposite corner walls of the apartment
which was the only support of the walls above. So there we had a structural system
which had no support resulting in static instability and collapse. The design life
expectancy of the building was 60 years. It was however demolished after 10 years.
Poor workmanship was suspected and so demolition was by dismantling the building
floor so that the joints could be studied. The degree of shoddy workmanship was
shrieking.
A public enquiry was held in Britain after the extensive research into all the factors
associated with the design, construction and failure and collapse of the building
Advisedly, the research focused in the following
1) Construction materials for building and associated facilities – the gas supply
system
2) Adequacy of design loads (dead, live, wind, explosion)
3) Design method modified to introduce progressive collapse for buildings over 5
storeys high. Design checked by analysing the structure after removal of
statical structural member ensuring alternate load path.
This collapse triggered investigation in the design and construction methodology by
government and private organisations in Europe and USA. The lessons learnt
changed building regulations throughout the world.
In many cases the analysis and study of structural failures/collapses have resulted in
the advancement of structural engineering knowledge and improved practices
especially where the original engineer appears to have done everything in
accordance with the state of the profession and acceptable practice yet
failure/collapse still occurred. Such cases are.
1) Tacoma narrows Bridge
2) Ronan Point Collapse
L’Ambiance Plaza Collapse
L’Ambiance Plaza was planned as a 16 storey building with 13 apartment levels on
top of 3 parting levels set between two offset rectangular towers. Post-tensioned
concrete slabs 175mm thick and steel columns made up the structural frame with
two shear walls in each tower to provide lateral stability. Using the lift slab method,
the 16 floor slabs were constructed on the ground one on top of the other. Then
packages of two or three slabs were lifted into temporary position by hydraulic jacks
and held in place by steel wedges. Once the slabs were positioned, they were
permanently attached to the steel columns. Because of the importance of the shear
walls to stability of the system, the drawings specified that they should be within
three floors of the lifted slabs.
At the time of collapse, the 9th, 10th and 11th floor slab package in the lowest tower
were packed under 12th roof slab and shear walls were about 5 levels below the
lifted slabs. Steel wedges were being welded to support the slabs when all of a
sudden the slabs above cracked like a “sheet of ice” and fell on the slab below and
with that high impact loading the whole construction came tumbling down in 5
seconds only. Twenty eight (28) construction workers died in the collapse.
All the parties involved in the design and construction of the building hired forensic
engineering firms to investigate possible causes of collapse. Prompt legal
settlements prematurely ended the investigation. $14 million was paid in settlement
to different parties. Investigations revealed the following.
a) Although the buildings constructed by the lift slab method are stable once
they are completed, great care must be taken to ensure lateral stability during
construction.
b) Many design deficiencies were undetected because design was fragmented
among many subcontractors and there was no Engineer of Record”
c) For system buildings such as lift slab construction there is need to establish
and strictly follow a standardised step-by-step procedure with at least 3
experts working in close collaboration to ensure – the structural engineer of
record, lift slab expert, and post-tensioning expert.
Considering overall structural stability of the system;
It is important that the designer’s assumption about structural behaviour are
consistent with detailing mistake
Manufactured Structures – where structural components are bought and
assembled to form a building could lead to a disconnect between the
manufacturer’s structural engineer who would typically use the latest software
to design the structure to the finest limit to make their product competitive and
the contractor’s/erector’s engineer who would typically be unfamiliar with the
software and even all the design assumptions. This situation underscores the
need for “ENGINEER OR RECORD”
Collapse of structures especially buildings is also on the increase in Nigeria these
days. It is instructive to note that most of the buildings in which collapse cases were
recorded are newly-built which are yet to fulfil their intended design life. Recent
researches have shown that small scale structures are more likely to collapse than
high-rise structures due to the fact that adequate care and precautions are taken
into consideration in designing and constructing high-rise structures while a lot of
negligence is employed in designing and building low-rise structures. It is of interest
to say that most of the collapses we have experienced in Nigeria in the past years
are majorly low-rise structures and few high-rise structures if any.
Some Collapse of Building Incidents in Nigeria
1) The collapse of a multi-storey (4 – 5 storey) building in Nigeria’s capital Abuja
on Aug 11 2010 claimed about 23 lives and 10 seriously injured. The building,
condemned as dangerous by the authorities and which was thought to be four
or five floors high, tumbled down at around dawn on Wednesday in Garki
Area 11 neighbourhood of Abuja, south of the Central Business District. The
collapse was linked to substandard materials and disregard for building
regulations. The building has been condemned by the authorities and
developers had continued to add an additional floor despite the warnings from
the regulatory authorities.
2) A similar incidence in Lagos where a 4-storey building in Ebute- Metta, Lagos
collapsed which claimed nearly 30 lives and lot of people serious injured. The
building suddenly gave in on a Tuesday evening. The building was supposed
to be a residential apartment but it also housed restaurants and 18 shops on
the ground floor thus exceeding the intended design usage. The building has
been just three years old, and officials are blaming poor construction for the
collapse. Local media are reporting that city planners only gave permission for
two storeys building on the site, not four. The owner of the construction
company fled after the incidence.
3) The case of the collapse of a building located on a plot adjacent to 109
Western Avenue, Iponri, Lagos State was investigated by the Nigerian
Institution of Structural Engineers. The investigation revealed that:
a) The building originally existed as a single storey block (bungalow)
b) The owner who acted as his own contractor, decided to add many more
storeys (floors to it).
c) There is evidence of a planning permit of only on additional storey.
d) That the Town Planning Authority discovering the contravention, marked
it for demolition, the owner went ahead with construction at nights until
the collapse occurred during the concreting of the fourth floor.
Structural failures/collapses are always caused by the aggregate effect of a number
of factors which come together at a particular time to cause distress.
Failures/Collapses may be systemic – which means the failure is brought about by
the manner in which the organisation/project is organised/managed
Responsibility for failure must be apportioned.
“Corporate Manslaughter and Corporate Homicide Act 2007” concentrates on
corporate management standards and make the organisation – contractor or
designer responsible for collapse to undergo appropriate sanctions”.
Failures/Collapse due to Systemic inadequacies – adoption of foreign codes without
associated recognition of necessary management procedures to ensure that safety
is achieved.
RISK MANAGEMENT PRINCIPLES in which the key stakeholders in a construction
project take adequate precautions to assess, understand and management their
risks and rewards.
Owner/Investor
Designers
Builders
There is need to clarify responsibility between all parties involved in the construction
process and emphasise obligation to manage risk.
Adequate Design
Adequate understanding of structural action
Use of appropriate software
Construction Lapses
Failure to build in line with proper design and specification
Wrong construction methodologies (lack of training and experience)
Operational Lapses
Faulty operation subjects structure to forces not envisaged in design