Nigeria: Environmental and Social Management Plan-ILE-IFE
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
The World Bank GroupNigeria: Environmental and Social Management Plan-ILE-IFEP095003 NG: Rural Access and Mobility Project- Phase 2
-7/6/2012
[Type the abstract of the document here. The abstract is typically a short summary of the contents of the document. Type the abstract of the document here. The abstract is typically a short summary of the contents of the document.]
TABLE OF CONTENT
Chapter 1: ENVIRONMENT MANAGEMENT PLAN2
1.1SPECIFIC ACTIVITIES BY SPIU2
1.2SPECIFIC ACTIVITIES BY CONTRACTOR2
1.3SITE SPECIFIC MANAGEMENT PLAN-CLUSTER-(ILESA Region)2
1.3.1Cultural Properties2
1.3.2Sensitive Features2
1.3.3Community properties2
1.3.4Farm Lands, Bushes and Tree cutting:2
1.4IMPLEMENTATION OF ESMP2
1.5ENVIRONMENTAL MONITORING PROGRAMME2
1.5.1Monitoring of Earthworks Activities2
1.5.2Monitoring of Concessionaire / Contractor's Facilities, Plant and Equipment2
1.6BUDGET2
Chapter 2IMPLEMENTATION & MONITORING SCHEDULE2
2.1ENVIRONMENTAL CELL, SPIU2
2.2IMPLEMENTATION ARRANGEMENTS2
2.2.1Independent Engineer (IE)2
2.2.2Contractor2
2.2.3Contractor2
2.3REPORTING SYSTEM2
2.4ENVIRONMENTAL CAPACITY BUILDING2
Chapter 3ENVIRONMENTAL MONITORING PROGRAM2
3.1PERFORMANCE INDICATORS (PI) OF MONITORING2
3.2MONITORING OF PERFORMANCE INDICATORS2
3.2.1Ambient Air Quality (AAQ) Monitoring2
3.2.2Ambient Noise Monitoring2
3.2.3Water Quality2
3.2.4Soil Quality2
3.2.5Plantation and Survival Rate2
3.3ENVIRONMENTAL MONITORING COST2
LIST OF TABLES
Table 11: Environmental Management Plan2
Table 12: Environmental Budget2
Table 21: Summary of Reporting of Environmental components and Responsibilities2
Table 22: Modules for Training2
Table 31: Environmental Monitoring Plan2
LIST OF BOXES
Box 21: Qualification and Responsibilities of Environmental Officer of Independent Engineer2
Box 22: Qualification and Responsibilities of Environmental Officer of Contractor2
ACRONYMS
APHAAmerican Public Health Association
ARAPAbbreviated Resettlement Action Plan
ESIAEnvironmental and Social Impact Assessment
ESMPEnvironment and Social Management Plan
FMEnvFederal Ministry of Environment
HSE Health, Safety & Environment
ICBInternational Competitive Bidding
IEIndependent Engineer
NOCNo Objection Certificate
OP Operational Policy (World Bank)
ROWRight of Way
R&RResettlement & Rehabilitation
SPIUState Project Implementation Unit
WB World Bank
WHOWorld Health Organization
(E1965 v4)
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
Chatper 1
(SECL, Nigeria in JV with VSPL, India)| Page (iii)
: ENVIRONMENT MANAGEMENT PLAN
The Environmental and Social Management Action Plan (ESMP) is required to ensure sustainable development of the road during construction and operational phases. ESMP is site and time specific. For the proposed construction packages of the project road, ESMP has been designed for each cluster. The ESMP has two main component (i) Generic ESMP and (ii) Specific ESMP. The generic ESMP is applicable for all the road clusters, but the specific ESMPs are applicable only to the specific clusters. The generic and Specific ESMPs are being developed considering the operation policies of World Bank as well as the National Policies on Environment.
The implementation of ESMP is important. For this an institutional framework has been developed and roles and responsibilities of the various line departments are made. Some capacity development program are also identified as part of the ESMP as sub-project. The essence of the project is its proper maintenance during and post rainy season. This is also to be considered and need of community based implementation program suggested.
In general, SPIU of Osun state, Nigeria (with assistance from Contractor and Independent Engineer/Supervision Consultant) is the responsible entity for ensuring that the mitigation measures are carried out. Mitigation measures for generic impacts are listed in Table 1.1. The list provides reference implementing organisation and responsible entity.
SPECIFIC ACTIVITIES BY SPIU
The role of SPIU in the implementation of ESMP involves the following activities:
· ESIA clearance from Federal Ministry of Environment, if required;
· Clearance of ESIA from World Bank;
· Disclosure of ESIA document in Nigeria as well as in the info shop of World Bank and
· Permission from Forest Department for felling of trees, wherever applicable.
SPECIFIC ACTIVITIES BY CONTRACTOR
The activities to be performed by the contractor to implement the ESMP shall comprise the following:
· Confirm the Tree Cutting Schedule based on the final design and provide modified schedule to SPIU.
· Fell the trees after SPIU secures Forest Department permission, wherever applicable;
· Fell the trees in farm land after SPIU provides necessary compensation to the farm land owners;
· Finalizing the selection of material sources (quarry and borrow material, water, sand etc);( refer Annexure 1.1, 1.2, 1.3 and 1.4).
· Selection, design and layout of construction areas, abour camps etc. (Refer Annexure 1.6)
SITE SPECIFIC MANAGEMENT PLAN-CLUSTER-(ILESA Region)Cultural Properties
In this project there is no impact on cultural property (e.g. church, mosque etc.). Impact on cultural properties during the road construction phase in the Corridor of Impact will be avoided through adequate scheduling of vehicles and construction machineries. Care shall be taken for the chance found cultural properties. It is the prime responsibility of the contractor to inform the SPIU’s Environment and Social safeguard specialist regarding the chance found cultural property so that necessary safeguard measure can be taken up.
Sensitive Features
Some section of the project road is passing through Sasha forest areas, which is a protected area. Tree felling at this section may require for the project road widening. The road within the Sasha forest section is however having sufficient RoW (around 6m) to accommodate the project. However, some tree cutting may be required not only for the project construction but also for the movement of construction vehicles, storage areas for construction materials etc. A compensatory afforestation of 2 trees per tree cutting shall be made at this section of project road.
Community properties
As such in this section no such community property is going to get affected due to the proposed construction of project road. There is no impact on ground water resources, school, water tank, palm oil production unit. However, one bus stop is going to get affected as part of the project. A new bus shelter to be provided for this section.
Farm Lands, Bushes and Tree cutting:
As such in this section no such farm land is adjacent to project has been identified. The farm land is at least 2-3m apart from the road sections and there are naturally grown bushes along the project roads. Private farm land owners shall be compensated if their land is going to be taken for this project for the loss of livelihood, if any.
IMPLEMENTATION OF ESMP
The Environmental Officer of the contractor should be available for the entire duration of the project and shall be primarily responsible for compliance of ESMP. The Environmental Specialist from the Independent Engineer/ Supervision Consultant shall monitor the compliance of the ESMP and all the design drawings of various civil structures shall be implemented after his approval. The proposed organogram for the implementation and monitoring of ESMP is presented in figure 1.1. The details of the implementation and monitoring schedule of ESMP are described in Chaper-2. The key issues that require special attention along with the mitigations to be implemented have been detailed in Table 1.1.
Figure: 1.1: Organization Structure for Implementation of ESMP
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
(SECL, Nigeria in JV with VSPL, India)| Page (2)
Table 11: Environmental Management Plan
Environmental Impact / Aspect
Mitigation Measures[footnoteRef:1] [1: Some of the mitigation measures are preventive in nature while some others include additional measures in terms of environmental conservation and involve physical and construction work. ]
Location[footnoteRef:2] [2: Unless otherwise stated, the Project Site covers area beyond ROW, such as borrow areas, and equipment storage sites.]
Time Frame[footnoteRef:3] [3: Time frame refers to the duration or instant of time when the mitigation measures will be taken.]
Responsibility
Cross reference
Implementation
Supervision
DESIGN STAGE
Geometric Design
The proposed alignment is selected / adjusted
1. to minimise farm land disturbance
1. to avoid culturally & environmentally sensitive areas – cultural properties, water bodies etc.
During alignment Design
Contractor
SPIU
Design Report
Issues from stakeholder Consultations
Various issues raised were examined & suitably incorporated based on merit & other road safety measures.
During Design
Contractor
SPIU
ESIA report
Orientation of Implementation Agency
A comprehensive training / orientation schedule has been prepared at different stages of SPIU.
During Design
SPIU
SPIU
Chapter 2, ESMP.
PRE-CONSTRUCTION STAGE
Farm Land Acquisition
Land requirement details to be sent to the Govt. and permission to be taken for the same.
Affected farm land owners to be compensated for their livelihood as per OP: 4.12 (Involuntary Resettlement)
Right of Way (ROW)
Before construction starts
SPIU.
SPIU
Tree cutting in forest areas
Compensatory afforestation shall be made
Right of Way (ROW)
Before construction starts
SPIU.
SPIU
Forest Law of Nigeria
Mobilisation & Site Clearance
Removal of Vegetation
Vegetation will be removed from the ROW before the commencement of Construction.
ROW
Before construction Starts
Contractor
IE, SPIU
Feasibility report and design drawings
Procurement of plants and machineries
Specifications of plant and machinery to be procured need to comply to the relevant international standard norms and with the requirements of emission control legislations in Nigeria
Prior to mobilisation at site
Contractor
IE, SPIU
International standard specifications and Air & Noise Standards of FMEnv
Setting up of construction camps
The construction camps will be located at least 500m away from habitations and there must be necessary (temporary) living accommodation and ancillary facilities as approved by the IE/SC.
construction campsite
During Establishment, Operation and Dismantling of Such Camps.
Contractor
IE, SPIU
Annexure 1.6
Setting up of construction plant and machinery sites
Construction plant and machinery site to be located at least 1000m away from the nearest habitation.
At plant location
During erection, testing, operation and dismantling of such plants
Contractor
IE, SPIU
CONSTRUCTION STAGE
Land
Loss of farm land due to heavy movement of construction vehicles
Temporary impact on farm land is envisaged due to movement of construction vehicles. Proper scheduling of vehicles to be made to bring and dispose of construction materials. Since the road lengths are smaller, hence the storage of material can be made at one end of the road.
Temporary acquisition of farm land due to vehicle movement shall be compensated as per OP:4.12.
RoW
During Construction
Contractor
IE, SPIU
Soil Erosion and Sedimentation control
Main reason of soil erosion is rains. Contractor should plan the activities so that proper surface pitching is done to avoid loose soil. Following preventive measures to be taken such as:
1. Embankment slopes to be covered, soon after completion.
1. Vegetation growth along the project roads to be maintained for soil stability;
1. Proper road side drainage will be given to minimize erosion.
1. Top soil from borrow area, construction site to be protected / covered for soil erosion.
1. Along sections abutting water bodies, stone pitching needs to be carried out.
1. Community based maintenance of road be made during and after rainy season
Throughout Project Corridor,
and equipment storage sites, etc.
Upon completion of construction activities at these sites.
During construction
Contractor
SPIU
Standard engineering practices, community based maintenance program
Loss of farm land top soil
· The top soil will be covered;
· Top soil to be stripped to a specified depth of 150mm
· Top soil to be stored in stockpiles and shall be covered.
· Stockpiles to be designed in such a way that slope do not exceed 1:2 (vertical to horizontal).
· Silt fencing to protect the edges of the pile and height of stockpiles to be restricted to 2m.
All along Project Corridor, where productive land is acquired
During construction
Contractor
IE, SPIU
Standard practice, WB safeguard documents
Compaction of Soil and Damage to Vegetation
Construction vehicles should operate within the Corridor of Impact avoiding damage to soil and vegetation.
Diversions, access road used during construction period will be redeveloped by Contractor, to the satisfaction of the owner / villagers.
Construction vehicle, machinery and equipment shall move or be stationed in the ROW only. While operating on temporarily acquired agricultural land for any construction activities, top soil will be preserved in stockpiles.
Throughout Project Corridor and all areas temporary acquired.
During construction
Contractor
IE, SPIU
Contamination of soil
· Oil & fuel spills from construction equipment shall be controlled by good O&M practices;
· Contaminated soil shall be disposed of as per guidelines of FMEnv;
· Vehicle maintenance and refueling in construction camps should be confined to areas with traps oil / grease to prevent wastewater from entering into rivers and streams
At fuel storage areas – usually at construction camps, temporarily acquired site.
During Construction.
Contractor
IE, SPIU
Guidelines of FMEnv and World Bank
Quarrying
Material sources
1. Quarry material shall be sourced from approved and licensed aggregate and sand quarries. Copy of licenses to be submitted to the IE.
1. For operating new quarries, the Contractor shall obtain materials from quarries only after consent of concerned authorities and only after development of a comprehensive quarry’ redevelopment plan.
1. Adequate safety precautions shall be ensured during transportation of quarry material from quarries to the construction site. Vehicles transporting the material shall be covered to prevent spillage. Operations to be undertaken by the Contractor as per the direction and satisfaction of the IE.
During construction
Contractor
IE, SPIU
Generation of Debris
Debris generated due to the dismantling of the existing culverts and other concrete structures and cutting materials shall be suitably reused in the proposed construction as fill materials for embankments
Throughout Project Corridor.
During Construction
Contractor
SPIU
Air
Dust Generation
· Vehicles covering construction materials shall be covered;
· Plant and machinery to be at least 1 km away in the downwind direction from nearest human settlements;
· Regular water sprinkling at morning and evening hours at the construction yards.
Throughout Project Corridor, all access roads, temporarily acquired sites.
Beginning with & throughout construction until side slopes are covered.
Contractor
SPIU
Equipment Selection, Maintenance and Operation
1. Regular pollution under check for construction vehicles shall be made;
1. Further, idling of vehicles to be stopped during construction period;
1. Automatic diesel logger may be installed in vehicles to minimise idling
Throughout Project Corridor, all access roads, sites temporarily acquired and all borrow areas.
During Construction.
Contractor
IE, SPIU
Water
Alteration of drainage due to construction /replacement of culverts
1. Diversions will be constructed during dry season, with adequate drainage facility, and will be completely removed before the onset of wet season.
1. Debris generated due to the excavation of foundation or due to the dismantling of existing structure will be removed from the water course.
1. Temporary Silt fencing to be provided on the mouth of discharge into natural streams.
Throughout Project Corridor, all access roads, temporarily acquired sites.
Whenever encountered during construction
Contractor
IE, SPIU
Runoff and drainage
1. Throughout continuous drain is provided.
Throughout Project Corridor
During Construction
Contractor
IE, SPIU
Water requirement for project
1. Contractor will provide a list of sources (surface / ground) for approval from IE.
1. Prior to use of source Contractor will take written permission from authority, to use the water in construction activity, and submit a copy to IE
Throughout Project Corridor, all access roads, temporarily acquired sites.
During Construction
Contractor
IE, SPIU
Silting / sedimentation
1. Measures suggested under “Soil Erosion and Sedimentation control” will be enforced.
1. Silt fencing is provided around water bodies.
1. Construction activities will be done carefully near water bodies during wet season.
1. Soil trap are suggested / will be provided in all ancillary sites and camps.
Throughout construction period
Contractor
IE, SPIU
Contamination of water
1. Measures suggested under “Contamination of soil” will be enforced.
1. Construction work close to water bodies will be carried out intermittently during wet season with adequate monitoring.
1. Labour camps will be located away from water bodies.
1. Car washing / workshops near water bodies will be avoided.
All areas in immediate vicinity of construction campsite chosen by the Concessionaire / Contractor.
Throughout construction period, During Establishment, Operation and Dismantling of Labour Camps.
Contractor
SPIU
Noise
Noise from Vehicles, Plants and Equipment
· Construction activities near habitation areas shall be prohibited between 9 p.m to 6 a.m.
· Maintenance of vehicles, equipments and machinery shall be made.
· All plants and equipments to confirm to the noise standards of FMEnv.
· Provision of ear-plugs to contractors exposed to high noise levels.
· Noise barriers to be given at sensitive location
Throughout Project Corridor, all access roads, sites temporarily acquired and all borrow areas.
Throughout construction
Contractor
IE, SPIU
Flora & Fauna
Loss of trees and Avenue Planting
1. Plant a minimum of 2 times of trees as compensatory afforestation for the number of tree cutting along the ROW. Cost of plantation included in the ESMP Budget.
1. Concessionaire / Contractor has to make sure that no trees / branches to be fell by labourer for fuel, warmth during winter. Enough provision of fuel to be ensured.
After completion of construction activities
Contractor
IE, SPIU
Fauna
1. Construction workers must protect natural resources and wild animals.
1. Hunting will be prohibited.
1. Nesting grounds & migratory paths, if any are protected.
During construction
Contractor
IE, SPIU
Socio – Economic Environment
Accidents
The Concessionaire / Contractor will provide, erect and maintain barricades, including signs marking flats, lights and flagmen as required by the Independent Engineer.
During Construction
Contractor
IE, SPIU
Resettlement Action of People
Affected population will be compensated as per WB policy and entitlement framework.
During Construction
Contractor, SPIU
IE, SPIU
Temporary Loss of Access
1. The works shall not interfere with or cause inconvenience to public or restrict the access to use and occupation of public or private roads, and any other access footpaths to or of properties whether public or private.
All along the Project corridor
During
Construction
Contractor
IE, SPIU
Road Safety And Construction Safety
Risk from Electrical Equipment
1. Adequate precautions will be taken to prevent danger from electrical equipment.
1. No material or any of the sites will be so stacked or placed as to cause danger or inconvenience to any person or the public.
1. All necessary fencing and lights will be provided to protect the public.
1. All machines to be used in the construction will conform to the relevant Nigerian Standard , will be free from defect, will be kept in good working order, will be regularly inspected and properly maintained as per IS provisions and to the satisfaction of the Independent Engineer.
Entire Project site.
During Construction
Contractor
IE, SPIU
Risk caused by Force’ Majure
All reasonable precaution will be taken to prevent danger of the workers and the public from fire, flood, drowning, etc. All necessary steps will be taken for prompt first aid treatment of all injuries likely to be sustained during the course of work.
Entire Project site
During
Construction
Contractor
IE, SPIU
Safety Measures During Construction
· To ensure safety of the temporary accesses during construction, safety devices shall be installed.
· Traffic rules and regulation shall be strictly adhered to local laws.
· Workers undertaking various operations during construction shall be protected by providing helmets, masks, safety goggles, hand gloves and rubber boots etc.
· First aid kits shall be provided at construction site for workers to meet minor accidents during construction
All construction sites
During construction
Contractor
IE, SPIU
Hygiene
· At every workplace, good and sufficient water supply shall be maintained to avoid waterborne / water-related / water-based diseases to ensure the health and hygiene of workers.
· Adequate drainage, septic tanks, soak pits and wastewater disposal shall be provided at workplace.
· Preventive Medical care shall be provided to workers.
· An action plan shall be prepared and implemented
All Worker’s Camps
During construction
Contractor
IE, SPIU
Annexure 1.4
HIV/AIDS from construction crews
· Camps will be located at least 500-1km away from habitation;
· The entry and exit from the camps will required to strictly monitored with details of visitors;
· Arranging HIV/AIDs awareness campaign in villages at regular intervals;
· Crews need to be rotated in the project and they need to be allowed to meet their partner (back home) at regular intervals.
· Contractor through the IE need to inform the location of such camps to SPIU in advance.
Construction Camps and Surrounding Villages
During pre-construction and construction stage
Contractor
IE/SPIU
The EHS policy of World Bank and its partners
OPERATION STAGE
Water quality degradation due to road run-off
Silt fencing, Oil & Grease traps, etc. shall be provided at sensitive water bodies to ensure that the water quality is not impaired due to contaminants from road run-off and sediment load. Monitoring shall be carried out as specified in the Monitoring plan
At sensitive water bodies identified.
As specified in the monitoring plan
During Operational Stage
SPIU
SPIU
As per Monitoring plan in chapter6.
Contamination of Soil and Water Resources from Spills Accidents
1. Contingency plans to be in place for cleaning up of spills of oil, fuel and toxic chemicals.
1. Spill of oil, fuel and automobile servicing units without adequate disposal systems in place to be discouraged.
1. Accidental spills are potentially disastrous, but its probability is quite low as one of the objectives of this project is to enhance road safety.
1. The Public will be informed about the regulations on land pollution.
1. Land pollution monitoring program has been devised for checking pollution level and suggesting remedial measures.
Entire Project corridor.
During Operational Stage
SPIU
SPIU
Traffic and Accident Safety
1. Depending on the level of congestion and traffic hazards, traffic management plans will be prepared.
1. Traffic control measures including speed limits to be enforced strictly.
1. Road control width to be enforced. Local government bodies and development authorities will be encouraged to control building development along the highway.
All along the Project corridor and surrounding areas.
During Operational Stage
SPIU
SPIU
Through Operation Stage.
Road side tree plantation
1. Trees planted along the corridor shall be maintained for a period of three years. Maintenance works include, watering of the saplings, and all necessary measures for survival of the sapling.
1. The avenue plantation should be completed, maintained and casualties to be replaced.
1. Discouraging local peoples from cutting tree / branches for fuel, cattle food etc.
1. Educating people about the usefulness of trees.
All along the corridor Immediately from the planting of sapling
During Operational Stage
SPIU
SPIU
Monitoring at critical locations
The monitoring of Air, land, water and Noise to be carried out identified critical locations besides locations identified by IE along the project corridor.
SPIU
SPIU
ESMP Budget.
Noise
1. HORN PROHIBITED sign post will be enforced
1. Maintenance of noise barriers
1. Discouraging local people from establishing sensitive receptor near the road.
1. The public will be informed about the regulations on noise pollution.
After completion of construction
Throughout and after project development period
During Operational Stage
State Police, State Transport Dept., SPIU
SPIU
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
ENVIRONMENTAL MONITORING PROGRAMME
The Environmental Monitoring Programme has been detailed out in chapter 3. Successful implementation of the Environmental Monitoring Program is contingent on the following:
· The Independent Engineer is to request the Contractor to commence all the initial tests for monitoring (i.e. for Air, Water Quality and Noise Levels) early in the Contract to establish 'base' readings (i.e. to assess the existing conditions prior to effects from the Construction activities being felt).
· The Independent Engineer is to request the Concessionaire / Contractor to submit for approval a proposed schedule of subsequent periodic tests to be carried out.
· Monitoring by the Independent Engineer’s Officer of all the environmental monitoring tests, and subsequent analysis of results.
· Where indicated by testing results, and any other relevant on-site conditions, IE to instruct the Concessionaire / Contractor to:
· Modify the testing schedule (dates, frequency)
· Modify (add to or delete) testing locations
· Verify testing results with additional testing as/if required
· Require recalibration of equipment, etc., as necessary
· Request the Concessionaire to stop, modify or defer specific construction equipment, processes, etc., as necessary, that are deemed to have contributed significantly to monitoring readings in excess of permissible environmental "safe" levels.
Monitoring of Earthworks Activities
Most of the environmental problems related to the construction works are anticipated to be associated with the earthworks, particularly for the Quarries and Borrow Areas. Details regarding the guidelines and procedures adopted to minimise the environmental impacts of opening, operating and closing of Quarries and Borrow Areas are presented in Annexure 1.1 to 1.4. Other environmental effects associated with the earthworks including the development of adequate temporary drainage to minimise detrimental effects (e.g. erosion) due to run-off, and safety aspects related to Works implementation.
Monitoring of Concessionaire / Contractor's Facilities, Plant and Equipment
· All issues related to negative environmental impacts of the Contractor's Facilities, Plant and equipment are to be controlled through:
· The Contractor's self-imposed quality assurance plan
· Regular / periodic inspection of the Concessionaire / Contractor’s plant and equipment
· Monthly appraisal of the Contractor.
Other environmental impacts are to be regularly identified and noted on the monthly appraisal inspection made to review all aspects of the Contractor's operation. The officer is to review all monthly appraisal reports, and through the team leader is to instruct the Contractor to rectify all significant negative environmental impacts.
BUDGET
The environmental budget for the various environmental management measures proposed in the ESMP is detailed in Table 1-2. There are several other environmental issues that have been addressed as part of good engineering practices, the costs for which have been accounted for in the Engineering Cost. The rates adopted for the budget has been worked out on the basis of market rates and the Schedule of rates. Various environmental aspects covered/will be covered under engineering costs are listed below:
· Turfing and Pitching of slopes
· Construction of slope protection works as retaining walls; breast walls toe walls, drains, and gabions.
· Construction of roadside amenities as bus stops etc.
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
·
Table 12: Environmental Budget
Item No.
Component
Description
Unit
Quantity
Unit cost (Naira)
Total cost (Naira)
Detailed Cost
Cost (Million)
1
MITIGATION / ENHANCEMENT COST
1.1
Horticulture
Compensatory Re-plantation of trees for timber grade trees @30 trees per km and compensation for 2 tree to be cut in Sash forest area and timber grade trees @5 trees in other sections of project road.
No.
3900
2000.00
78,00,000.00
7.8
1.2
Bamboo tree guard as per design provided by the engineer
No.
4000
1000.00
40,00,000.00
4.0
1.3
Compensation for Economic Trees
COVERED IN ARAP
1.4
Soil
Providing Oil Interceptors as per design and drawing at vehicle parking areas and as per directions of the Environmental Specialist / Environmental Engineer of the Engineer.
Nos.
5
1,00,000.00
5,00,000.00
0.5
1.5
Soil Erosion
Protection Measures for Soil Erosion like retaining wall, breast wall, turfing , vegetative cover etc.
To be Covered in Engineering Cost
1.6
Water Quality
Silt Fencing around soil stockpiled near water bodies and at areas identified by the engineer.
m
150
4000.00
6,00,000.00
0.6
1.7
Noise Barrier
Provision of Noise barriers in the form of compound walls
m
50
6000
3,00,000.00
0.3
TOTAL MITIGATION / ENHANCEMENT COST
13.2
2
MONITORING COST
2.1
Construction Stage
2.1.1
Air
Sampling of Ambient Air Quality for PM2.5, PM10, at 6 locations including the plant and machinery site , once in a season for both dry and wet season for a period of 20 months
No. of Samples
18
10,000.00
1,80,000.00
0.18
2.1.2
Water Quality
Grab sampling, once in a month for culverts culvert location in dry season and twice in a month for wet season and analysis of locations near the cross drainage site for 1.5 years as per the Monitoring Plan. The location of monitoring shall be 10 at major culvert locations for a period of 20 months (12 months dry and 8 months wet)
Dry Season: 10x12=120
Wet Season: 10x2x8=160
Total= 280
The parameters to be monitored are TSS and TDS, BOD, COD, E.Coli, Phosphate and Nitrate
No. of Samples
280
10,000.00
28,00,000.00
2.8
2.1.3
Noise
Monitoring of noise level – weekly at 2 construction camp and once in a season for the other 5 baseline monitoring locations for the 20 months construction period.
Camp site samples: 1x4x2x20=160
Other areas: 1x5x2x1.5=15
Total: 175
Nos.
175
5,000.00
8,75,000
0.875
2.1.4
Soil
Sampling and analysis of soil quality - once in season (dry, wet ) at 10 locations for 20 months of construction period
Samples: 2x10x1.5=30
Nos.
30
20,000.00
6,00,000.00
0.6
2.1.5
Transportation Cost
Transportation cost for monitoring of noise, air and water during construction period for 20 months
L.S.
-
-
3,00,000.00
0.3
Monitoring Cost during Construction Stage
4.755
2.2
Operation Stage
2.2.1
Air
Sampling of Ambient Air Quality and gaseous pollutants (PM10, PM2.5, CO, SOx, NO2) once in a season for 2 seasons (dry and wet) at 6 locations for first 5 years as per the Monitoring Plan
No. of Samples
60
20,000.00
12,00,000.00
1.2
2.2.2
Water Quality
Grab sampling, once in a season for 2 seasons at 15 locations (10 Surface and 5 Ground) for every year for the first 3 years as per monitoring plan and parameters as per APHA standard.
No. of Samples
90
20,000.00
18,00,000.00
1.8
2.2.3
Noise
Monitoring of noise level - once in a season for 2 seasons in a year for the first 5 years (at baseline monitoring locations) at 5 locations. The monitoring to be carried out for 60 seconds interval for every hour, Day time and Night time
Nos.
50
5,000.00
2,50,000.00
0.25
2.2.4
Soil
Sampling and analysis of soil quality - once in a season for two season (dry and wet) for first 3 years as per the Monitoring Plan at 3 locations
Nos.
18
20,000.00
3,60,000.00
0.36
2.2.5
Transportation Cost
Transportation cost for monitoring of noise, air and water during operation period for first 5 years
L.S.
-
300,000.00
0.3
Monitoring Cost during Operation Stage for first 5 years
3.91
TOTAL MONITORING COST
8.665
3
MISCELLANEOUS COST
3.1
Training
Training
L.S.
-
20,00,000.00
2.0
3.2
Advocacy and Policy Making
Holding meetings for policy planning and subsequent review meetings with Revenue Department, Forest Department, local representatives, NGOs, etc. regarding development controls.
Year
2
50,000.00
1,00,000.00
0.1
3.3
Administrative Charges including logistics
Maintenance of vehicle with the Environment Cell, Data processing, administrative support, stationery etc.
Months
24
1,00,000.00
24,00,000.00
2.4
3.4
Miscellaneous Items
Digital Camera for the Environment Cell
No.
1
50,000.00
50,000.00
0.05
3.5
Portable sound level meter
No.
1
4,00,000.00
4,00,000.00
0.4
TOTAL MISCELLANEOUS COST
4.95
TOTAL COST
26.815
Contingency @ 5% on Total Environmental Cost
1.34
GRAND TOTAL
28.2 (approx.)
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
IMPLEMENTATION & MONITORING SCHEDULE
This chapter provides an assessment of the existing institutional arrangement within SPIU and, reflects on capacity building / training issues that need to be addressed to ensure timely implementation of ESMP. The institutional arrangement proposed for this project has been presented here with newly defined roles and responsibilities. The responsibility of implementing the mitigation measures lies with the SPIU, Osun State. All construction activities being taken up by the contractor through International Competitive Bidding. The Independent Engineer shall monitor the implementation of the work on behalf of SPIU. The contractor will be responsible for planning all Environmental and Social Management Plan (ESMP) activities. In the pre-construction phase of the project the concessionaire shall study the ESMP to identify environmental issues and arrive at a suitable strategy for implementation.
ENVIRONMENTAL CELL, SPIU
SPIU already has an organizational and institutional capacity at the headquarters created to meet the requirements for implementation of the environmental mitigation measures in the ESMP. As part of the project it is envisaged that they will continue to:
· Monitor progress of the implementation of the ESMP measures in consonance with the timeline for the project within the allotted budget;
· Maintain interaction with the various other statutory bodies like Federal Ministry of Environment and Forest Department and Land Revenue Department;
· Interact with the Environmental Expert of the Independent Engineer on the state of the environment and mitigation and enhancement measures adopted;
· Occasionally inspect the environmental measures being implemented by the Contractor;
· Report progress of works, both in terms of physical progress and quality for transmission to statutory authorities such as the Ministry of Environment and Forests;
· Document and disseminate good practices, bottlenecks and their resolution during the implementation of environmental measures.
IMPLEMENTATION ARRANGEMENTS
The SPIU is responsible for the implementation of the provisions made within the ESMP through its site offices. The services of Independent Engineer will be procured to assist the site offices for monitoring the environmental aspects of the project during implementation. The organization chart for implementation arrangements is shown in Figure 1-1.
Independent Engineer (IE)
The Independent Engineers (IE), to be procured through International Competitive Bidding (ICB) shall assist the SPIU with the implementation of project, once the project documents are ready. The Environmental Expert of the IE shall be the key personnel to ensure the successful implementation of ESMP provisions. Since ICB procurement is envisaged, the selected consultants are expected to have the necessary professional(s) to tackle the issues that the project is likely to bring up. The Environmental Specialist of the Independent Engineer will be a key position, which can be leveraged to ensure that the contractor complies with the various ESMP requirements.
In case it is not feasible the field engineers supervising construction can be trained on environmental aspects, who then shall perform additional duty of apprising the Team Leader and the Environmental Specialist of any significant development on environment.
Contractor
For effective implementation and management of the ESMP, The BOT / Annuity concessionaire shall contrive to establish a Safety, Health and Environment (SHE) Cell headed by an Environment Officer to deal with the environmental issues of the project. This officer shall interact with the contractor, SPIU, IE and other line departments to ensure that the mitigation and enhancement measures mentioned in the ESMP are adhered. The Environmental officer of the concessionaire shall be the interface between the Environmental Specialist of IE and the Environmental Officer of the contractor. His prime responsibility shall be to apprise the Environmental Specialist of the IE about the ground conditions. He shall also procure the requisite clearances and the NOCs for the project and shall also strictly supervise that the contractor adheres to the ESMP. The environmental officer can also look after the additional charges of safety and health.
Box 21: Qualification and Responsibilities of Environmental Officer of Independent Engineer
Qualifications & Experience
· Postgraduate in Environmental Science / Environmental Management / Zoology / Botany / Ecology / Environmental Planning / degree in Civil Engineering with specialisation in environment.
· 5 years of total experience with a minimum of 3 years in the implementation of ESMP of highway projects and an understanding of environmental, health and safety issues.
· Prior practical experience in State and National Highways would be an advantage.
Roles & Responsibilities
· He / She shall be reporting directly to the Chief Project Manager of the Concessionaire.
· Primarily responsible for implementation of the ESMP on site and ensuing that the environmental quality is meeting the standards laid down by Federal ministry of Environment and other related authority.
· The EO shall implement the ESMP by assigning the necessary resources (manpower, money and machinery) and attend such meetings as are required for the effective implementation of the ESMP on site.
· He shall maintain a “Complain Register” to record any grievances from members of public.
· He shall maintain a register of all road side trees planted and present within ROW.
· The EO shall be the interface of the concessionaire with the client and the IC.
Contractor
Execution of works will be the responsibility of the contractor. The contractor shall employ an Environmental Officer whose qualification and responsibilities shall be as per Box 2.2. The contractor shall be responsible for both the jobs done by the petty contactor (if Sublet) as well by him. In both the cases the concessionaire will implement the environmental measures (either through the contractors or themselves). This has been done with a view to ensure that road construction and environmental management go together.
Box 22: Qualification and Responsibilities of Environmental Officer of Contractor
Qualifications & Experience
· Postgraduate in Environmental Science / Environmental Management / Zoology / Botany / Ecology / Environmental Planning / Environmental Engineering.
· 3 years of experience with a minimum of 2 years in the implementation of ESMP of highway projects and an understanding of environmental, health and safety issues.
· Prior practical experience in State and National Highways would be an advantage.
Roles & Responsibilities
· The Environmental Officer shall report directly to the Resident Construction Manager / Project Manager so that the pertinent environmental issues that he raises are promptly dealt with.
· He shall also have a direct interaction with the Environmental Expert and the Environmental Officer of the IC and the concessionaire respectively.
· Monitor / implement measures laid out in the ESMP and or as directed by the IE for the work executed both by petty contractors and the contractor.
· Provide key inputs in the development of the Contractors’ implementation plan for all construction activities, including haulage of material to site, adhering to the requirements of the ESMP and getting approval of concessionaire and the IC on the same before start of works.
· Ensure that the regulatory permissions required for the construction equipment, vehicles and machinery (given in the ESMP) have been obtained and are valid at all times during the execution of the project.
· Prepare / fill up the environmental and safety related forms given in the ESMP
· Prepare Safety Plans, Emergency Response Plans and Quarry Management and other safety, health and environment related Plans for approval of the IC and the concessionaire.
· Identify locations for siting construction camps and other plants, machinery, vehicles and equipment, as well as locations for storage and disposal of wastes, both from the construction camps and from the site and obtain approval for the same from the concessionaire and the IC.
· Detail out site-specific environmental mitigation and enhancement measures and obtain approval of concessionaire and the IC for the same
· Carry out the measurements of environmental mitigation and / or enhancement works and prepares bills for the same for approval and payment through the Concessionaire’s Environmental Officer
· Ensure that the safety of the workers and other site users is not compromised during construction
· Ensure that adequate monitoring facilities are available for collecting samples of all discharges from the Contractor’s plants, equipment and camps
· Verify the extent of environmental compliance at sites from where the Contractor is procuring the material – quarries, sand and suggest appropriate mitigation measures, if required
· Responsible for implementation of safety and health regulations if also acting as safety officer
The environmental officer shall have a small environmental, health and safety team to help him in implementing the ESMP. These team members may / may not report to him / her directly but shall apprise him of all the incidents and mark a formal report of any incident having an impact on the Health, Environment and Safety issues.
Duty Officers (DO)
The Duty Officers shall, on day to day basis, monitor the Project Facilities and report to the EO on activities that adversely affect the environment in the vicinity.
Supervisors
They shall take the necessary mitigation measures.
Plant Engineer
The Plant Engineer has the responsibility of managing and controlling plant and machinery and fleet of vehicles shall ensure that the environment is not degraded at his plant site. Even though the Environmental Officer shall routinely monitor to detect any negative issues due to operations and bring it to the knowledge of Plant manager for taking rectification works. In case of emergency the Plant Engineer shall immediately notify the Environmental officer for necessary actions.
REPORTING SYSTEM
Reporting system provides necessary feedback for project management to ensure quality of the works and that the program is on schedule. The rationale for a reporting system is based on accountability to ensure that the measures proposed as part of the Environmental Management Plan get implemented in the project. Reporting system for the suggested monitoring program operates at two levels as:
· Reporting for environmental condition indicators and environmental management indicators
· Reporting for operational performance indicators at the SPIU site level.
The reporting system will operate linearly – contractor who is at the lowest rung of the implementation system reporting to the Concessionaire, who in turn shall report to IE and the SPIU as per figure 1-1. All reporting by the concessionaire shall be on a quarterly basis, while the reporting time of the contractor shall be decided upon by the concessionaire. The SPIU Site Office will be responsible for setting the targets for the various activities anticipated during construction phase in consultation with the IE/SC and obtaining agreement from the Contractor after mobilisation but before beginning of works on site. The contractor will report from then on regarding the status on each of these. The SPIU Site Office will monitor the activities through its own staff or the consultant’s Environmental Specialist after it has obtained the Contractor’s report with the Consultant’s remarks on it during the construction phase. During the operation phase, the supervision as well as reporting responsibilities will lie with the SPIU Site Office.
Table 21: Summary of Reporting of Environmental components and Responsibilities
Format No.
Item
Timing
Independent Engineer
SPIU PIU / Site office
Supervision
Reporting
Overseeing / Compliance
CONTRACTOR MOBILIZATION AND SITE CLEARANCE
M1
Reporting by contractor to IC for dumping locations & construction and labour camp site
Before start of construction
As required
Quarterly
As required
M2
Reporting by contractor to IC for construction and labour camp site
Before start of construction
As required
Quarterly
As required
M3
Target sheet for Tree cutting
Before start of work
As required
After cutting
As required
M4
Reporting for borrow areas
Before start of construction
As required
Quarterly
As required
CONSTRUCTION PHASE
C1
Target sheet for Pollution Monitoring
As per Monitoring Plan
As required
After Monitoring
As required
C2
Top soil Conservation
Before start of work
As required
Quarterly
As required
OPERATION PHASE
O1
Target sheet for Pollution Monitoring
During Operation
As required
After Monitoring
As required
O2
Redevelopment of Borrow Areas
After completion of usage of Borrow Area
As required
After Monitoring
As required
O3
Survival Rate of Trees
During Operation
As required
After Monitoring
As required
ENVIRONMENTAL CAPACITY BUILDING
Training of staff will be done at a number of levels. Some short-term training is required for the Environment Manager, other staff members of the Environment Unit and the contractor staff to raise their levels of environmental awareness. The training can be conducted by either some external agency or through the help of in-house expertise of the SPIU and the consultants and help of Federal Ministry of Environment and World Bank. In the long-term training, special environmental issues will be examined and likely solutions provided to the Environment Unit.
The main focus of future training programmes has to be on implementation with special ESMP basis. Since project preparation is drawing to a close, the officials can concentrate on the progress of the project. The following modules can be taken up:
Table 22: Modules for Training
Sl. No.
Timing
Target Group
Mode of training
Short Description
Responsibility
1
After finalization of Contracts for Civil Works
Members of the Osun-SPIU site office, Environmental Specialist of the IE, Concessionaire and the Environmental staff of the Civil Contractor
Lectures, Presentations, Discussions
Overview of responsibilities
· The roles and responsibilities of the IE and the Contractor
· Reporting arrangements
· Contractual obligations, Environmental Protection and Social Development
External Agency or SPIU
2.
During implementation
Members of the SPIU site office, Counterpart staff from other departments such as Revenue, Forests, etc.
Lectures, Discussions,
Presentations,
Role Play
Inter-Departmental Co-ordination
· Clearance requirements and prescribed procedures
· Expectations of other departments – documentation and follow-up
· Developing formats for ease of reporting
External Agency, Consultants, SPIU
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
ENVIRONMENTAL MONITORING PROGRAM
Environmental monitoring is an effective tool in making necessary recommendations and adopt suitable control strategies so that menace of rising environmental pollution could be minimized and a relief be extended to the people including labours in case of any damage caused under occupational health hazards. The monitoring is necessary for the following reasons:
· To assess what impacts have occurred;
· To evaluate the performance of mitigation measures proposed in the ESMP.
· To ensure that the conditions of necessary consent and approvals are adhered to.
· To suggest improvements in management plan, if required
· To see that benefits expected from the EA are achieved as the project proceeds.
· To meet legal and community obligations.
PERFORMANCE INDICATORS (PI) OF MONITORING
The physical, biological and social components, which are significant in affecting the environment at critical locations, have been suggested as Performance Indicators. The following specific environmental parameters can be qualitatively measured and compared over a period of time and therefore selected as Performance Indicators for monitoring due to their regulatory importance and the availability of standardized procedures and relevant expertise.
· Ambient Air Quality
· Noise Levels
· Water Quality
· Soil Quality
· Plantation and Survival Rate
MONITORING OF PERFORMANCE INDICATORSAmbient Air Quality (AAQ) Monitoring
The baseline air quality in these project sections do not show any significant pollution as the areas is still in a virgin condition. However, with the construction of roads there is estimation of movement of heavy vehicles during the construction phase as well chance of increase in induced traffic during the operation phase.
The major increase of pollution in the region during the construction phase would be dust as the existing roads are earthen in nature. Hence constant monitoring of PM10 and PM2.5 may be required. These parameters are to be monitored at selected locations such as plant and machinery sites, concrete mixer site excavation works, etc. starting from the commencement of construction activity. The chance of increase in other pollutants like SO2, NOx and CO but are estimated to be negligible and will be intermittent in nature during the construction stage.
However, during the operation stage monitoring is required to be done for all the parameters like Particulate Matter (Size less than 10micron or PM10), Particulate Matter (Size less than 2.5 or PM2.5), Sulphur Dioxide (SO2), Oxides of Nitrogen (NOx) and Carbon Monoxide (CO). These parameters need to be monitored at the first 5 years of the operation stage to establish a data bank to ensure that the project has not made any significant impact to the nearby settlements and vegetation. The monitored results are to be checked with the standards of FMEnv/State Ministry of Environment.
Ambient Noise Monitoring
The measurement for monitoring the noise levels to be carried out at sensitive locations and at construction sites along the project road in accordance to the Ambient Noise Standards of FMEnv/State Ministry of Environment. Sound pressure level would be monitored on twenty-four hour basis.
Water Quality
Water quality of local water resources that is used by local community shall be monitored.
The water quality during the construction phase shall be monitored at the major culvert construction site at the downstream mainly for pH, total solids, total suspended solids, total dissolved solids. In addition, the parameters like BOD, COD, Phosphate, Nitrate as well as E.Coli be monitored during the construction stage.
During the operation stage in order to capture information on impact on surface and ground water quality at least a trend shall be set for the first 3 years of the operation stage for 2 seasons in the year for the parameters as suggested in American Public Health Association (APHA)/State Ministry of Environment (Osun).
Soil Quality
The soil quality of the surround fields close to the construction site and plant site will be monitored to understand the impact of soil quality. The physic-chemical parameters recommended for analysis are physical Parameter: Texture, Grain Size, Gravel, Sand, Silt, Clay; Chemical Parameter: pH, Conductivity, Calcium, Magnesium, Sodium, Nitrogen, Absorption Ratio.
Plantation and Survival Rate
The widening and up gradation of the project requires felling of roadside trees. This loss will be compensated by compensatory afforestation. The compensatory avenue plantation shall be made as per the guidelines of forest department. Two times of the tree cutting will be compensatory afforested (cost of the plantation budgeted in ESMP).
ENVIRONMENTAL MONITORING COST
A separate budgetary provision has been made for implementation of Environmental Monitoring Plan. The environmental monitoring cost is estimated based upon the environmental monitoring program being considered in Table 3.1. A budgetary provision of Naira 4.755 million has been kept for environmental monitoring during construction stages. For operation stage Naira 3.91 Million has been considered for first 5 years.
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
Table 31: Environmental Monitoring Plan
Environment Component
Project stage
Institutional Responsibilities
Parameters
Standards
Locations
Frequency
Implementation
Supervision
Air
Construction
PM10 μg /m3, PM2.5 μg/m3, SO2, NOX, CO
FMEnv/State Ministry of Environment
Plant site, and at locations of baseline monitoring
Once in a season for 2 seasons (dry, wet ) for 20 months
Contractor through approved monitoring agency/Lab
IE & SPIU
Operation
PM10 μg /m3, PM2.5 μg/m3, SO2, NOX, CO
At locations of baseline monitoring
Once in a season for 2 season in a year for the first 5 years.
Contractor through approved monitoring agency/Lab
IE & SPIU
Surface Water Quality
Construction
pH, temperature, DO, BOD, COD, Total Suspended Solid, turbidity, Total Hardness, Coliform/E.Coli
Standard parameters for Surface water quality as per APHA and State Ministry of Environment
At locations of baseline monitoring
Grab sampling, once in a month during dry season and twice in a month for wet season for the entire construction period i.e 20 month at 10 locations
Contractor through approved monitoring agency/Lab
IE & SPIU
Operation
pH, temperature, Oil &
Grease, Total Suspended Solid, turbidity, Chlorine, Iron, sulphate, nitrate
Standard parameters for Surface water quality as per APHA and State Ministry of Environment
At locations of baseline monitoring
Grab sampling, once in a season for 2 seasons at 10 selected locations every year for the first 3 years.
Contractor through approved monitoring agency/Lab
IE & SPIU
Ground Water Quality
Operation
pH, Temperature,
TSS, Total hardness,
Suspended Solid, Chlorine, Iron, Sulphate, Nitrate
Ground Water Quality Standard as per APHA
At identified location in the settlement areas
Grab sampling, once in a season for 2 seasons at 10 selected locations every year for the first 3 years.
Contractor through approved monitoring agency/Lab
IE & SPIU
Noise Levels
Construction
Leq dB (A) (Day and Night) Average and Peak values
Ambient Noise
Standard
FMEnv
At equipment yards and at locations of baseline monitoring
Once in a week for the entire construction period at the construction yard.
Once in a season for the entire construction period at the baseline locations.
Contractor through approved monitoring agency/Lab
IE & SPIU
Operation
Leq dB (A) (Day and Night) Average and Peak values
At locations of baseline monitoring
Once in a season for all the season in every alternate year for first 5 years,– 60 Seconds interval for every hour, Day time and Night time
SPIU through approved monitoring agency/Lab
IE & SPIU
Soil
Construction
Physical Parameter: Texture, Grain Size, Gravel, Sand, Silt, Clay; Chemical Parameter: pH,
Conductivity, Calcium, Magnesium, Sodium, Nitrogen, Absorption Ratio
Near Construction
sites along the road
and at locations of baseline monitoring
Once in every season for the construction period
Contractor through approved monitoring agency/Lab
IE & SPIU
Operation
Physical : Texture, Grain Size, Gravel, Sand, Silt, Clay; Chemical Parameter: pH,
Conductivity, Calcium, Magnesium, Sodium, Nitrogen, Absorption Ratio
At the baseline monitoring locations
Once in every year for the two season for the first 3 years.
Contractor through approved monitoring agency/Lab
IE & SPIU
Tree plantation/ green belt development
Construction
Tree Survival rate
90% Tree
Survival Rate
Throughout the
Project in
substantially
completed section
Once in a month
Contractor through approved monitoring horticulture agency
IE & SPIU
Operation
Tree Survival rate
90% Tree
Survival Rate
Throughout the
Project stretch
Once in three month
Contractor through approved monitoring horticulture agency
IE & SPIU
Water Bodies
Construction
Turbidity in Storm
Water bodies load in receiving water bodies
As specified by
the engineer
Water quality
standards
At the drains,
and tanks construction site/ along the ROW
Dry and wet season
Contractor
IE & SPIU
Operation
Turbidity in Storm
water
Silt load in receiving water bodies
As specified by
the engineer /
Water quality
standards
At the drains,
and tanks construction site/ along the ROW
Dry and wet season
Contractor
IE & SPIU
(Federal Ministry of Agriculture and Rural Development)Detailed engineering design, safeguards studies and Preparation
of bidding documents for prioritized 222.83km rural roads in osun state of Nigeria
ESMP (ILE-IFE Region)
ANNEXURES
Annexure 1-1: Guidelines for New Quarry Management
1. Management Plan for New Quarry
The contractor shall prepare a quarry management plan for operation of new quarries and submit it to the IE for approval and necessary actions. The plan shall consist of the following:
1.1 Selection Details
1.1.1 Location and Layout
Sketch plans and photographs to be provided along with adequate details:
· A map and sketch plan of the area showing the location of the proposed quarry site with respect to the project road, nearby villages, worker accommodation locations along with indicative distances of the different sites from each other and from the road.
· A detailed sketch plan of the quarry area showing approach and haulage roads, location of the rock outcrops to be quarried, indicating which sites will be quarried in which year or phase, location of stock piles, location of guard house, perimeter fence, location of water sources, amenities, and any further details.
· Photographs of the site
1.1.2 Selection Criteria
· A brief statement as to how the site was chosen.
· Alternative sites that were considered to be mentioned.
· Record any public consultations involved while choosing and what the public concerns were, if any.
1.1.3 Agreement with landowners
Statement of ownership of the land along with lease / purchase agreements.
1.1.4 Licenses and permits
Contractor to state the licences and permits that are necessary for operation, and attach them as appropriate.
1.2 Operation
1.2.1 Method of extraction
· A brief method statement of extraction indicating the techniques to be used, use of explosives if any, if so how are the charges laid, how often the blasting shall be done, etc.
· Appropriate reference should be made to the contractor’s safety manual.
· A copy of the operator’s licence to handle explosives should be submitted to the IC.
1.2.2 Loading and haulage
Contractor to describe the process in a few sentences of loading of rocks fragments; means of transportation to site.
1.2.3 Crusher Plant
Per say there is no such crusher plant is expected in the project, hence the chances of fugitive emission is less. Concrete mixers will however be used in the project.
1.2.4 Storage of explosives
Contractor to state where these are to be procured from, where they will be stored and how the supply of explosives will be kept secure (if they are to be kept off site, state what precautions will be given for transportation).
1.2.5 Products
A list of aggregate sizes and any other products from the quarry. Make sure the sketch map states where these will be stock piled.
1.2.6 Testing and quality assurance
· Refer quality assurance plan of contractor if any.
· If not, contractor to provide details of sampling frequency, who takes the does the testing, which standards are to be complied with, and any further pertinent details.
1.2.7 Water sourcing
Contractor to indicate the operations that shall need water, and its source (an indication on the sketch map will suffice).
1.2.8 Safety
· Contractor to divulge safety measures to the IE.
· Ensure that workers at the quarry sites are aware of the appropriate sections of the safety plan.
1.2.9 Workers Accommodation
Contractor to provide details of how many workers will be accommodated on site and what the accommodation arrangements and standard will be.
2. Environmental Management
2.1 Environmental Management during Operation
2.1.1 Removal of trees and plants
Contractor to describe briefly the floral species that have had to be removed (it will be helpful give local names if English or scientific names are not known), and roughly how many.
2.1.2 Overburden
Contractor to state where this will be deposited (indicate on the sketch map), and what methods will be taken to contain it, if any.
2.1.3 Silt management
Contractor to state how silt arising from quarry operations will be managed, e.g. provision of a silt retention pond, and show where this is on the sketch map. Say how the silt retention pond will be managed (i.e. how often it will be dredged).
2.1.4 Surface water drainage
If it will be necessary to provide drainage channels, contractor to show on the sketch map where these are and confirm that they will be kept free of blockages.
2.1.5 Soil and water contamination
Contractor to list sources of possible contaminants to the soil (fuel stores, etc) and what will be done to control it (minimise spillages, control leaks from plant, etc).
2.1.6 Air pollution
· What are the sources of air pollution?
· Details of air pollution control measures in each case.
· Details of worker protection equipment along with appropriate reference to the safety plan.
2.1.7 Noise
Sources of noise, distance from settlement, labour camp and proposed mitigation to the population / workers exposed.
2.1.8 Traffic
Impact of quarry operations on traffic and how this may be controlled.
2.1.9 Approach road
Contractor to state whether this will be maintained, and if so in what condition.
2.2 Environmental Management at Closure of the site
2.2.1 Dismantling and removal of machinery
Contractor to state whether and when this shall be done.
2.2.2 Slope stabilisation and / or protection
Measures taken to protect the slope and to guard against any possible serious rock fall, or any measures to safeguard against hazards like this.
2.2.3 Rehabilitation
· Rehabilitation plan of the quarry.
· The contractor shall be responsible for the Redevelopment Plan prior to completion after five years, during the defect liability period. The IC and the APRDC shall be responsible for reviewing this case of redevelopment prior to the issuing the defect liability certificate.
2.2.4 Hand-over
Terms of hand-over of the quarry site to the owner/authority at the end of its use.
2.2.5 Removal of debris and solid waste
Confirmation of Contractor in removal of debris and solid wastes and disposal at a suitable site.
For each aggregate-cum-quarry sand source, the plan should be the same. The table below gives the format:
SI. No.
Item
Unit
Details
Remarks by IE, if any
1.
Name / identity of the location
2.
Nearest project road Chainage.
3.
Name of the owner
4.
Area involved
m2
5.
Existing land use (verification from land records with revenue department)
6.
Land use of the area surrounding the proposed site including a map
7.
Access roads – existing conditions, proposed development and maintenance
8.
Tree cutting and vegetation clearance if any, along with compensation measures
Nos.
9.
Arrangement with the owner (agreement with land owner should be attached as an Annexure)
10.
Quantity of material to be withdrawn vis-a-vis the material available
Cum
11.
Particular areas to be quarried should be clearly identified
12.
Machinery & equipment to be used
13.
Drainage plans
14.
Top soil management
15.
Description of the operating practices to be adopted.
16.
Health facilities
17.
Safety provisions made including fire protection systems and the availability of different personal protective equipment
18.
Monitoring plans for air, noise and water quality
19.
Copy of the license from Mining & Geology, Police & Fire dept.
20.
Conditions laid down in the clearances / licenses and plans to ensure compliance
21.
Information on whether or not the quarry will be closed under this project. If yes, the proposed closure & restoration plan.
22.
Concerns of the local people living in the immediate / near vicinity should be identified and appropriates measures should be reflected
23.
Photograph of the quarry prior to commencing operations.
24.
Sketch of the layout of the quarry
Attach Photograph of Proposed Site, Location Map, Consents, licenses, safety plan, tree compensation plan, restoration plan, drainage plan, monitoring plan, Agreement with land owner etc. as annexure
Submitted Checked & Approved
Signature Signature
Name Name
Designation Designation
ContractorIndependent Engineer
Annexure 1.2: Guideline for Rehabilitation of Quarries and Borrow Areas
Quarries and Borrow Areas
The contractor shall use materials from the existing and licensed quarry areas only. In case any new quarries are opened by the contractor, he shall secure permissions for the same and shall follow the rehabilitation plan.
1. The objective of the rehabilitation programme is to return the borrow pit sites to a safe and secure area, which the general public should be able to safely enter and enjoy. Securing borrow pits /quarry sites in a stable condition should be a fundamental requirement of the rehabilitation process. This could be achieved by filling the quarry / borrow pit floor to approximately the access road level.
1. It is important to plan restoration from the outset and coordinate restoration with quarrying activities. In addition to the bio-diversity issues, land planning considerations are also taken into account when defining a rehabilitation project in order both to preserve the environment and to generate income for the local communities. In this framework quarry rehabilitation often leads to the creation of wetlands and natural reserves or recreation areas.
1. Special quarry / borrow pit rehabilitation plan should be specified according to the location and shaping of the mining slopes after exploitation and overburdened dump, with different subsequent uses e.g. forest, meadow, water body etc., the re-greening and replanting methods..
1. Other criteria which should be followed for rehabilitation of quarry/ borrow pits are as given below:
1. Quarries and borrow pits will be backfilled with rejected construction wastes and will be given a vegetative cover. If this is not possible, then slopes will be smoothed and depression will be filled in such a way that it looks more or less like the original ground surface.
1. During works execution, the contractor shall ensure preservation of trees during piling of materials; spreading of stripping material to facilitate water percolation and allow natural vegetation growth; reestablishment of previous natural drainage flows; improvement of site appearance; digging of ditches to collect runoff; and maintenance of roadways where a pit or quarry is declared useable water source for livestock or people nearby. Once the works are completed, and at own expense the contractor and contractor shall restore the environment around the work site to its original splits.
1. To create a safe environment, the faces of borrow pit excavation sites have to be reduced to a naturally stable slope or be adequately fenced to prevent access to the top and bottom of the faces. Such a fence must be of a height as prescribed under local mine act with a barbed wire top strand designed to exclude the public from the quarry area. Depending on the location of the site presence of a permanent lake is considered to be a satisfactory alternative to a fence.
1. Appropriate plant species for the planting programme have to be selected in consultation with ecological consultant and local forest department and farm land owners for the loss of economic trees made during the quarry and borrow operations.
1.
Annexure 1.3: Guidelines for Existing Quarry Management
The Contractor will finalise the locations from the list given by Consultant's for procuring materials. The Contractor shall establish a new quarry only with the prior consent of the Independent Engineer (IE) only in cases when: (i) Lead from existing quarries is uneconomical and (ii) Alternative material sources are not available. The Contractor shall prepare a Redevelopment Plan for the quarry site and get it approved by the IE.
The construction schedule and operations plans to be submitted to the IC prior to commencement of work shall contain a detailed work plan for procuring materials that includes procurement, transportation and storage of quarry materials.
CONSTRUCTION STAGE
Development of site: To minimise the adverse impact during excavation of material following measures are need to be undertaken:
i) Adequate drainage system shall be provided to prevent the flooding of the excavated area
ii) At the stockpiling locations, the Contractor shall construct sediment barriers to prevent the erosion of excavated material due to runoff
iii) Construction of offices, laboratory, workshop and rest places shall be done in the up-wind of the plant to minimize the adverse impact due to dust and noise.
i) The access road to the plant shall be constructed taking into consideration location of units and also slope of the ground to regulate the vehicle movement within the plant.
iv) In case of storage of blasting material, all precautions shall be taken as per The Explosive Rules, 1983.
QUARRY OPERATIONS INCLUDING SAFETY
SI. No.
Item
Unit
Details
Remarks by IE, if any
1.
Name / identity of the location
2.
Nearest project road Chainage.
3.
Name of the owner
4.
Area involved
5.
Arrangement with the owner (agreement with the third party / contractor should be attached as an Annexure and should necessarily require the adaptation of good quarry management practices - a description of the requirements should be included)
Cum
6.
Quantity of material to be withdrawn vis-à-vis the material available
8.
Machinery & equipment to be used
Cum
9.
Drainage plans
10.
Top soil management
11.
Description of the operating practices
12.
Health facilities
13.
Safety provisions made including fire protection systems and the availability of different personal protective equipment
14.
Conditions laid down in the clearances / licenses and plans to ensure compliance
15.
Monitoring plans for air quality
16.
Information on whether or not the quarry will be closed under this project. If yes, the proposed closure & restoration plan.
17.
Photograph of the quarry prior to commencing operations.
19.
Sketch of the layout of the quarry
i) During excavation, slopes shall be flatter than 20 degrees to prevent their sliding. In cases where quarry strata are good and where chances of sliding are less this restriction can be ignored.
ii) In case of blasting, procedure and safety measures shall be taken as per The Explosive Rules, 1983
iii) The contractor shall ensure that all workers related safety measures shall be dune as per guidelines for Workers and Safety.
Topsoil will be excavated and preserved during transportation of the material measures shall be taken to minimize the generation of dust and prevent accidents.
The IC shall review the quarry site for the management measures during quarry operation, including the compliance to pollution norms.
POST CONSTRUCTION STAGE
· The Contractor shall restore all haul roads constructed for transporting the material from the quarries to construction site to their original state.
· The IE shall be entrusted the responsibility of reviewing the quarry site for the progress of implementation of Redevelopment Plan.
· The redevelopment of exhaust quarry shall be the responsibility of the agency providing the permit to ensure the implementation of Redevelopment Plan.
For existing quarry managed directly by a third party / contractor from whom the contractor is sourcing the materials, the plan should contain the following:
Attach Photograph of Proposed Site, Location Map, consents, licenses and Agreement with land owner
REMARKS
Submitted Checked Approved
Signature SignatureSignature
Name NameName
Designation DesignationDesignation
ContractorContractorIndependent Engineer
Annexure 1.4: Guidelines for Siting, Operation & Redevelopment of Borrow Areas
(A) Siting
Specific locations of borrow areas to be used will be identified by contractor based on the recommendations of the ESIA report. In case the contractor or the contractor wants to open any new borrow areas other than mentioned in this report, and then the selection and recommendations for borrow areas will be based on environmental as well as civil engineering considerations.
Certain precautions have to be taken to restrict unauthorised borrowing by the contractor and the contractor. No borrow area shall be opened without permission of the Engineer.
Table 1: Probable Borrow Area along the Project Corridor
Sample no.
Name of Village
Material type
Site identification
Approximate Quantity (Cum)
Available
Land /Terrain
Surrounding
Land /Terrain
Remarks
NearestChainage (Km.)
Left / Right
Offset from nearest Chainage (m)
Length (m)
Breadth (m)
Depth (m)
Total (Cum)
(B) Criteria for Evaluation of Borrow Areas
i. Existing land use (Agricultural / Barren / Scrub / grazing / any other type)
ii. Vegetation / trees to be removed
iii. Erosion/degradation potential
iv. Distance and name of the nearest settlement
v. Distance from the nearest surface water body
vi. Drainage pattern of the area
vii. Distance of the nearest Reserve Forest (if any)
viii. Distance of the nearest Sacred Tree (if any)
ix. Distance from the nearest school / hospital / primary health centre
x. Daily / Occasional use of borrow area by the community
xi. Any schemes or avenues for generation of income for adjoining community
(C) Documentation of Borrow Pit
The contractor must ensure that following data based must be documented for each identified borrow areas that provide the basis of the redevelopment plan.
1. Chainage along with offset distance
1. Area (in Sq m)
1. Type of Access/width from carriageway
1. Soil Type
1. Slope / Drainage Characteristics
1. Water Table of the area or identify from nearest well etc/ask people
1. Existing Land-use such as barren/agricultural/grazing land
1. Location/Name/Population of Nearest Settlement/Community & distance from Borrow Area/Type and characteristics of settlement
1. Daily / occasional use of the Borrow Area by the community, if any
1. Identification of any other community facility in the vicinity of the borrow pit
(D) Guidelines for Stripping, Stocking, Preservation of Top Soil
During the excavation of the borrowing material contractor must ensure that the topsoil from all areas of cutting and all areas to be permanently covered shall be stripped to a specified depth of 150mm and stored in stockpiles. At least 10% of the temporarily acquired area shall be earmarked for storing topsoil. The stockpile shall be designed such that the slope does not exceed 1:2 (vertical to horizontal), and the height of the pile is restricted to 2m..
(E) Guidelines for Enhancement
As far as possible borrow area selected for enhancement shall be on government / community land in the vicinity of settlement. The contractor must ensure that any enhancement design proposed should be workable, maintenance free and preferably worked out in consultation with the community and proposed enhancement materials should be locally available. The borrow area can be developed either of the following:
Vegetative Cover:
1. Vegetative cover must be established on all affected land.
1. Topsoil must be placed, seeded, and mulched within 30 days of final grading if it is within a current growing season or within 30 days of the start of the next growing season.
1. Vegetative material used in reclamation must consist of grasses, legumes, herbaceous, or woody plants or a mixture thereof.
1. Plant material must be planted during the first growing season following the reclamation phase.
1. Selection and use of vegetative cover must take into account soil and site characteristics such as drainage, pH, nutrient availability, and climate to ensure permanent growth.
1. The vegetative cover is acceptable if within one growing season of seeding:
1. The planting of trees and shrubs results in a permanent stand, or regeneration and succession rate, sufficient to assure a 75% survival rate;
1. The planting results in 90% ground coverage.
1. The site shall be inspected when the planting is completed and again at one year to ensure compliance with the reclamation plan.
Certificate of Completion of Reclamation
1. Contractors have to obtained certificate of satisfaction from the landowner and submit it to the Engineer before final payment is to done.
(F) Drawings to be Prepared
1. The contractor have to prepared the drawings showing both cross-section as well as plan of the identified borrow areas incorporating following inputs:
1. Contours if any, depth if any
1. Location of trees, height, foliage spread and afternoon shaded area on ground
1. Any other existing details at the road / property interface such as signage/railing/etc.
1. Details of immediate surrounding for at least 5m on either sides
(G) Photographs to be Include
The contractor must ensure that photographs are to be taken before and after the excavation of borrow materials and also after the implementation of redevelopment plan, incorporating the following:
1. Overall View from access side
1. Any other community resource in the vicinity
1. All spots to be detailed such as access to borrow pit /cluster of existing trees etc.
(H) OUTPUTS
The contractor must ensure based on the above-mentioned guidelines following outcomes must be evolved:
1. Working plan
1. Cross Section
1. Longitudinal Section/Elevation of Site
1. Details of all proposed Enhancements including signage etc.
1. BoQ
Annexure 1.5: Guidelines for Sediment Control
Prior to the start of the relevant construction, the Contractor shall submit to the Engineer for approval, his schedules for carrying out temporary and permanent erosion / sedimentation control works as are applicable for the items of clearing and grubbing, roadway and drainage excavation, embankment / sub-grade construction, culverts and other structures across water courses, pavement courses and shoulders. He shall also submit for approval his proposed method of erosion / sedimentation control on service road and borrow pits and his plan for disposal of waste materials. Work shall not be started until the erosion / sedimentation control schedules and methods of operations for the applicable ' construction have been approved by the Engineer.
The surface area of erodible earth material exposed by clearing and grubbing, excavation, borrow and fill operations shall be limited to the extent practicable. The Contractor may be directed to provide immediate control measures to prevent soil erosion and sedimentation that will adversely affect construction operations, damage adjacent properties, or cause contaminati