Nickel Rim South Mine - SAIMM€¦ ·  · 2009-11-19Nickel Rim South Mine ... formula based on...

14
The Southern African Institute of Mining and Metallurgy HARD ROCK SAFE Safety Conference 2009 R Collins _____________________________________________________________________________________ Page 135 Nickel Rim South Mine Project Overview September 2009 2 “Raising the Bar for a Canadian Mining Project” Xstrata Nickel’s - Nickel Rim South Project By: Rick Collins - Project Manager (HATCH). 1. Nickel Rim South – the project 2. Project delivery method 3. Safety expectations – Zero Harm goal 4. Setting & maintaining the safe work culture 5. Safety tools 6. Shaft sinking challenges 7. Sustainable development 8. Lessons learned for future projects

Transcript of Nickel Rim South Mine - SAIMM€¦ ·  · 2009-11-19Nickel Rim South Mine ... formula based on...

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 135

Nickel Rim South Mine

Project Overview

September 2009

2

“Raising the Bar for a Canadian Mining Project”

Xstrata Nickel’s - Nickel Rim South Project

By: Rick Collins - Project Manager (HATCH).

1. Nickel Rim South – the project2. Project delivery method3. Safety expectations – Zero Harm goal4. Setting & maintaining the safe work culture5. Safety tools6. Shaft sinking challenges7. Sustainable development8. Lessons learned for future projects

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 136

3

Nickel Rim SouthProject Location

Hwy 144

Hwy 17 E

Hwy 69 S

Hwy 69 NNickelRim

South 20 miles

45 miles

SUDBURY BASIN

Toronto 400km

Strathcona

Mill

Smelter

North Bay 120km

Sault Ste-Marie 300km

4

Nickel Rim SouthProject Timeline/Overview

2001 Nickel Rim discovery 1100m – 1700m.

2002 Exploration drilling program expanded.

2003 FEL 2 and FEL 3 studies. Shaft pilot hole drilled. Road, power, pipelines to site.

2004 Project Go-Ahead March. Site prep and surface const. Vent Adit and pilot raises.

2005 Sinking plant +5 hoists, 2 head-frames.Full shaft-sinking commenced.

2006 Shaft sinking, Main Shaft and Vent Shaft

Phase Zero diamond drilling commenced

2007 Underground lateral development, vent raising & phase 1 drilling commenced.

2008 Surface and Underground construction, 10km development, 95 km drill core.

2009 12km development, 40km drilling, Backfill plant, permanent Dry/Admin bldg, Production 546kT Ore.

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 137

5

Nickel Rim SouthSafety First

• Project 92% complete. Work hours 6.4M to current

• Peak full time jobs 930 (XNi 380, contractors 550)

• Best run: no LTIs 4.95 Yrs (5.7M hrs)

• Incident frequencies 3x lower than Ontario mining norms

• Project On Track – Safety & Production tied together

6

Nickel Rim SouthProgress and Performance

Project Highlights

1. Two deep shafts (3420m) zero lost time incidents

2. March ‘09 – surpassed 5M hrs Zero LTIs

3. Zero Reportable Environmental Incidents

4. SPI = 1.00, running precisely to

baseline schedule

5. CPI =1.03, despite period of escalation in mining costs

6. First production 8 months ahead of FEL 2 study

7. Quality - NCR rate 0.90 vs. target KPI 1.00

VENTILATION

SHAFT

MAIN

SHAFT

CONTACT

ZONE

FOOTWALL

ZONE

1480 FW DRIFT

1660 FW DRIFT

1280 L

1480 L

1660 L

1700 L

DIAMOND DRILLING

1320 L

1520 L

1475 L

1625 L

Main shaft 1735 m depth

7.6 dia

Completion within 33 mth

Sinking rate 3.6 m/d

Vent shaft 1685 m depth

6.1 dia

Completion within 28 mth

Sinking rate 4.0 m/d

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 138

7

Nickel Rim SouthEPCM Delivery

• Small Owner team with specific deliverables

• EPCM by HATCH-McIntosh Eng’g (HMA 2003-09)

• Eng’g peak 120: HMA Surface Infrastructure, u/ground engin’g, ventilation, C&A. Shaft sink’g + H/frames by Cementation

• EPCM site team peaked at 65

• EPCM cost 12% of capital (Eng’g 6%, PCM 6%).

• EPCM Contract inc ‘Gain-share Pain-share’ formula based on annual safety & ev KPIs

• Partner contractors engaged early- site prep, hoist supply, shaft sinking, long-leads, constructability. Footwall Zone

Contact Zone

8

EPCM model benefits:

• Single group accountability for delivery

• Contract linked to project success; safety, cost, schedule

• Co-ordinate ‘best’ engineering

• Cross-project control systems

• Pre-procurement of long-lead items (materials/equip’t)

• Improved likelihood of Project Success!

Nickel Rim SouthEPCM Delivery

Project Orientation

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 139

9

Nickel Rim SouthSafety Expectations

• Xstrata’s mandate comes from the Top: The goal is “Zero Harm”

• Tone & expectations reflect from CEO to project team to contractors to individuals at face

• ‘Vision and Values’ clear, unequivocal, well communicated and translated

• ‘Zero Harm’ means zero incidents; LTI – FAs – Near Misses

• Not there yet; working toward zero MAs. Low FA & NM is a leading indicator

• Annual targets set to measure progress for LT, MA, RWI, TRIF, RWD

• Targets tightened 20% pa for Continuous Improvement

• Bottom-line approach... Safety can never be “good enough”.

10

Nickel Rim SouthSetting a Safety Culture

• Contractor pre-selection includes safety performance analysis

• Team input to management selection

• ‘One-team’ must be created, co-location is critical

• Orientation - the vital first contact (made personal – because it is!)

• Training and Safety discussion never stops (huddles)

• Contractor corporate structures engaged

• Positive recognition forced; celebrate milestones safely achieved

• Accident prevention is behavioral based Safe behaviors can’t change at the gate

• Guard against complacency –a silent killer on long projects!

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 140

11

Nickel Rim SouthSafety Tools

• Internal Responsibility system

• Stop and Correct

• Five-point safety and Pre-Op check system

• Regular alignment (now-state to future-state)

• PASS system

• Best Practices - most stringent contractor or project procedures

• Root-cause analysis

• Leading-indicator vs. lagging indicator reviews

• Positive recognition rewards vs. incentives.

12

Nickel Rim SouthShaft Sinking Challenges

• Over & Under work inherent challenges

• Tie-off points & harness use

• Shaft equipping decks

• Modification protocol compliance

• Bucket (kibble) travel & bucket wells

• Brutus mucking jaws – bail changes

• Rigging & Slinging

• Heat, ammonia & water challenges

• Hoist automation & speed-clamps.

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 141

13

Nickel Rim SouthShaft Sinking Challenges

• Lack of trained & experienced people

• Training facilities

• Off-site behavioral issues

• Extreme winter temperature differentials

• Station construction – rhythm break

• Changeover conversions

• Contractual arrangements

• Design responsibility for temporary facilities in head frames, dumps, hoisting etc.

14

Nickel Rim SouthSustainable Development

• Occupational health programs - Owner and major contractor partners

• On-site OHN and free services (flu-shots, ergonomics, EAP advice etc.)

• Reportable environmental spills – zero accidences

• All permits in place prior to start

• Agreement with local First Nation band (WFN)

• Agreement with adjacent airport (NavCan)

• Local community engagement – open houses etc.

• Energy reduction designs eg. LEED certification

• Regular SD audits vs. 17 common Xstrata stds.

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 142

15

Nickel Rim SouthSome Lessons Learned

• Safety is a LINE responsibility. Safety dept does guidance & training

• Multi-contractor communications - increased team ‘supervisor’ presence

• Contractor management critical (excellent shaft miner vs. lateral miner)

• Specialty team checklists for major set-ups (sinking, devel’t comm’g) reduces preparedness risks

• Design risk reviews and construction Hazops - deep into project

• Estimate new-worker training requirements carefully – market driven

• Complacency from repetitive tasks/good results - creates environment where failure goes unrecognized

• In transition, apply same diligence to Operations workforce as to contractors; anticipate delayed culture change

• Modification protocol needs high level attention/compliance.

16

Nickel Rim SouthSome Lessons Learned

• When the Owner is committed project team job is easier

• Good results from attention to leading, not lagging, indicators

• Continuous Improvement - need to challenge our existing standards/procedures

• In-depth orientation with one-on-one assessment is vital!

• “One team” culture needs early establishment

• Think-it-through planning is critical for non-routine tasks

• Stop and Correct is an excellent field tool. No-one walks past an unsafe act/condition

• Above all “working in an unsafe manner must become socially unacceptable”.

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 143

17

Nickel Rim - 2003

18

Nickel Rim South - 2004

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 144

19

Nickel Rim South - 2005

20

Nickel Rim South - 2006

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 145

21

Nickel Rim South - 2007

22

Nickel Rim South - 2008

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 146

23

Nickel Rim South - 2009

Question and Answers

Thank You.

Nickel Rim South

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 147

The Author

J Richard (Rick) Collins, Associate, Project Manager, Hatch

Rick Collins has 27 years experience in engineering, construction and project management of

medium and large-scale projects. Experience includes planning and execution for underground

projects in hard rock, mixed and soft-ground conditions; for mining, road, rail, hydro and transit

projects. Career to date includes 17 years EPCM for project owners, 5 years with contractors, 3

years with design-constructor (Channel-Tunnel Project), and 2 years engineering business

management.

The Southern African Institute of Mining and Metallurgy

HARD ROCK SAFE Safety Conference 2009

R Collins

_____________________________________________________________________________________

Page 148