1.1 Summary of Progress-Total length of project is 122.88 km from Km 398.240 to Km 521.120 with total project cost Rs.1665 Cr. (Concessionaire TPC:- Rs. 2434.68 Cr.) Appointed Date was 01/04/2016 and scheduled date of completion of construction was 26/09/2016 (with 910 days construction period).
For convenience of execution of works, the Concessionaire has divided the entire project road length into following three sections;
Sections Location (Km) Total Length (km)
Remarks
From To
Section - I 398+240 441+565 43.325 M/s APCO Infratech Limited
Section - II 441+565 471+150 29.585 M/s APCO Infratech Limited
Section - III 471+150 521+120 49.970 M/s Oriental Structural
Engineers Pvt. Ltd
Physical & Financial Progress:
Cumulative physical progress achieved:-62.88%, Targeted:-100.00%(Schedule Completion date:- 26.09.2016)
Cumulative financial progress achieved:-69.00%.Total expenditure till date is Rs.1679.97Cr.
Highway & Structure Progress: MCW:-Total progress of DBM layer is 69.01% i.e. 84.80 Km towards equivalent 6-lane Main Carriageway (MCW) out of 122.88 Km equivalent 6-lane Main Carriageway (MCW).
Service Road:-Total progress of BC layer of service road is 52.40% i.e. 78.10 km completed out of 149.09km.
The highway and structure progress summary is tabulated below –
Linear Progress (Road Works):-MAIN CARRIAGEWAY
Activity Description
Unit Total Length
Completed Remarks
C & G Km. 122.88 93.85Embankment Km. 122.88 93.85 * In progress Sub-Grade Km. 122.88 88.20GSB/CT sub base Km. 122.88 85.86WMM /CT base Km. 122.88 85.42Aggregate layer Km. 42.93 16.85
DBM Km. 122.88 84.80BC Km. 122.88 73.50
SERVICE ROADActivity
DescriptionUnit Total
LengthCompleted Remarks
C & G Km. 149.090 96.50Embankment Km. 149.090 95.60 *In progressSub-Grade Km. 149.090 91.50Sub base(CT) Km. 149.090 84.70Base course(CT) Km. 149.090 83.40Aggregate Layer Km. 149.090 80.10BC Km. 149.090 78.10
Sl.No. Type of Structure Total Completed In
ProgressYet toStart Remarks
1 ROB 2 - 2 -2 Major Bridges 3 2 1 -3 Minor Bridges 20 7 12 14 Grade Separator 12 4 6 25 Over Pass 2 0 2 -6 Underpass 2 2 0 -7 Vehicular Underpass 20 9 9 28 Pedestrian Underpass 11 4 5 2
Total 72 28 37 79 Box culvert/ Slab
Culvert 114 57 41 1610 Pipe Culverts 88 36 18 34
Total 202 93 59 50
Mobilization: The Concessionaire and its Sub-contractors has fully mobilized sufficient Plant & Machineries, equipment, Engineers/Personal and Workmen for execution of the project highway.
Land Acquisition/Front Availability :
Till January 31, 2017 out of 731.560 Ha of proposed land(equivalent to 122.88 km -6 lane) 668.129 Ha(Equivalent to 101.278 km - 6 lane i.e. 82.42%) land has been handed over to the Concessionaire and 96.865 Km length has been handed over towards service road (SR) i.e. 64.97%. The Section wise along the project highway the encumbered free length towards Main Carriage Way and Service Road are summarized below :-
S. No.
Package Side Scope (M) Available Front (M)
Hindrance (M) Available Front (%)
MCW SR MCW SR MCW SR MCW SR1 Package
- ILHS 43325 28230 32955 19585 10370 8645 76.06% 69.38
%RHS 43325 28860 20545 6080 22780 22780 47.42% 21.07
%2 Package
- IILHS 29585 13860 26975 8550 2610 5310 91.18% 61.69
%RHS 29585 12000 25705 8625 3880 3375 86.89% 71.87
%3 Package
- IIILHS 49970 34670 48035 28035 1935 6635 96.12% 80.86
%
RHS 49970 31470 48340 25990 1630 5480 96%.74 82.58%
Total LHS 122880
76760 107965
56170
14915 20590 87.86% 73.18%
RHS 122880
72330 94590 40695
28290 31635 76.98% 56.26%
Equivalent Six Lane (M)
122880
149090
101278
96865
21602 52225 82.42% 64.97%
Utility Estimate Approval &Their Shifting Status: On Appointed Date total 23 Nos. of Utilities belongs to various departments spread along the project highway requires its relocation to take up the Project Highway work. In which 05 Nos. are avoided by Project highway realignment/Alternate Proposal under Change of Scope Notice. The remaining 18 Nos. of utilities pertaining to various Government Departments of West Bengal, Jharkhnad and private entity in which 6 Nos., 07 Nos., 02 Nos. and 03 Nos. belongs to Electrical lines, Water Pipelines, Gas Pipeline and Police Station/School respectively.15 Nos. out of 18 Nos. belongs to Govt. departments and rest 03 Nos. belongs to Private Entity.
Utility Estimate Approval Status: All 15 Nos. of utility belonging to various departments approved by Competent Authority. The utility estimate approved from Competent Authority for 07 nos. on appointed date, 01 no. in December 2014, 01 no. in February 2015, 01 no. in April 2015, 01 no. July 2015, 01 no. in August 2015 and 01 no. in June 2016It is also to be noted that 01 no. of utility estimate belonging to DVC (Electrical line) for which the 25% approval of utility estimate are yet awaited from Competent AuthorityIn addition to above additional estimate of utilities belonging to the various departments are ADDA, DMC, WB-PHED, DPL Electrical, Jharkhand PHED water pipeline and DVC are yet to be approved by Competent Authority. The estimate approval of existing high mast, Jharkhand PHED hand pump and revised estimate of WB-PHED are still awaited by the Competent Authority.
Utility Shifting Status: Out of 06 Nos. of approved Electrical line utility estimate belongs to various departments 02 are completed and 04 are in progress (45%).Out of 06 nos. of approved Water Pipeline line utility estimate belongs to various departments 02 is completed and 04 are in progress (83%). Out of 03 Nos. of approved School/Police Station utility estimate belongs to various departments 01 is completed and 02 nos. are not yet started for want of land acquisition.Current Issues - Land Availability: The balance encumbrance free land 17.58% i.e. 21.602
Km towards Main Carriageway and 35.03% i.e. 52.225 Km towards service road is yet to be handed over to the Concessionaire.
Utility Estimate Approval: 01 No of utility estimate belonging to DVC (Electrical Line) for which the
25% approval of utility estimate are yet awaited from Competent Authority.
Additional estimate of utilities belonging to the various departments are ADDA, DMC, WB-PHED, DPL Electrical, Jharkhand PHED water pipeline and DVC are yet to be approved by the Competent Authority.
The estimate approval of existing high mast, Jharkhand PHED hand pump and revised estimate of WB-PHED are still awaited by the Competent Authority.
Local protest:
Govindpur (Km 406+500 to Km 410+000) &Nirsa (Km 422+000 to 435+000) –Concessionaire is not able to take up work due to public agitation as well as no-availability of encumbrances free land on above said stretches.
Decision Pending.
BograChoti (Km 468+000 to Km 470+000) - 2.000 Km- Locals are protesting for 6-laining, however the valuation of structures has been completed by intervention of District Administration.
Declaration of unsafe location U/s 4 of West Bengal Restriction on Construction in unsafe area Act 1979 by DM, Burdwan.
GEECL Gas Pipeline - 25.000 Km - The gas pipeline is running parallel along the project stretch on LHS from Km 455.750 to Km 505.900 affecting approximately 25 Km. The agency has filed a case in High Court in Kolkata.
Change of Scope Status: Notice for COS in 3 cases under Clause No.16.1 & 16.2 of Concession Agreement are still awaited from Competent Authority.
COS-09 – Foot Over Bridge at Banscopa.
1.2 Critical Issues & Action Log1.2.1 – Pending issues and Action Log
S No
Issue Descriptio
nType
Ongoing/ New
Issue/ Resolved
Concerned
Authority
Chainage(s) affected due to the issue
(Km)Length affected
(km)Action(s) taken till
nowAction(s)
suggested by the IE
Expected date/
Actual Date for
resolving issue
From To
1Land
Handed Over
Land Acquisit
ion Issue
Ongoing NHAI21.602 Km. land handed over to concessionaire
21.602 carriageway Km. i.e. 17.58% for
MCW and 52.225 Km. i.e. 35.95%
for SR
Every month the matter being followed up with NHAI, CALA West Bengal and CALA Jharkhand
The matter being follow
with Authority
2Govindpur
and Nirsa
Land Acquisit
ion Issue
Ongoing NHAI 406+500426+000
410+000429+000
3.5 Km. and 3 Km.
Recently authority had convened meeting dated 24.07.2016 with Public Representative and Administration
The matter being follow
with Authority
3 BograchottiLand
Acquisition
IssueOngoing NHAI 468+000 470+000 2.0 Km.
Valuation of structures has been completed by intervention of District administration
The matter being follow
with Authority
4 GEECL Gas Pipeline
Clearance Issue Ongoing
NHAI/M/s Great
Eastern Energy
Corporation Limited
455+750 505+900 25 Km.Matter is pending with Hon’ble High Court
The matter being follow
with Authority
1.2.2 Obligations as per Contract
1. Project Mile stone in Schedule-G of Concession Agreement
Project Mileston
e
Conditions/ stipulations in Schedule G of the Concession Agreement Present status
Milestone I
Project Milestone-I shall occur on the date falling on the 180th day from the Appointed Date. (Scheduled Date was September 27, 2014)Prior to the occurrence of Project Milestone-I, the Concessionaire shall have commenced construction of the Project Highway and expended not less than 10% of the total capital cost set forth in the financial package.
This Milestone was achieved.Approval regarding achievement is yet awaited from NHAI.
Milestone II
Project Milestone- II shall occur on the date falling on the 365th day from the Appointed Date. (Scheduled Date was March 31, 2015)Prior to the occurrence of Project Milestone, the Concessionaire shall have commenced construction of all bridges and expended not less than 25% of the total capital cost set forth in the financial package.
This Milestone was achieved.Recommendation regarding achievement of Milestone-II is submitted by IE to NHAI.Approval from NHAI is awaited.
Milestone III
Project Milestone- III shall occur on the date falling on the 730th day from the Appointed Date. (Scheduled Date is March 30, 2016)Prior to the occurrence of Project Milestone- III, the Concessionaire shall have commenced construction of all Project Facilities and expended not less than 75% of the total capital cost set forth in the Financial Package.
Recommendation regarding extension of Project Milestone-III for 15 months up to June 2017 submitted by IE to NHAI.Approval of EOT from NHAI is awaited.
Scheduled Six-Laning
Date
Shall Occur On September26, 2016 (910th day from Appointed Date)
IE had recommended the revised Schedule Completion date as December 27, 2017.Approval from NHAI is awaited.
2. The land handed over as per CA for Six lane project Highway as on date are summarized below –
S. No
Description Land to be made available as per CA
(Km.)
Cumulative Handed over
Length
Short fall
( Km)(Km) (%)
1 As On Appointed Date (01-04-2014)
98.30 23.095 23.49% 75.205
2 Within 90 days from Appointed Date (30-06-2014)
122.88 30.012 24.42% 92.868
3 As On January 31, 2017(Equivalent 6-lane)
-- 101.278
82.42% 21.602
1.2 Project overview1.3.1 Salient Features of Project
Project Name
Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
NH No.(Old) 2Scheme/ Phase PPPMode of the Execution (BOT Toll/ BOT Annuity/ EPC/ HAM/ Item Rate/ Others) BOT Toll
No. of Lanes/Configuration 6-LaneLength of the Project(in Km) 122.88 Km
Total Project Cost (in Cr.) 1665 Cr. (As Per CA)2434.86 Cr. (As Per Financial Model)
No. of Bypasses (Name of Town, Length) 01 (Panagarh By-Pass, 8.12 Km)No. of Major Bridges (Number and Location)
Existing –03 (Km 420.075, Km 441.330, Km 482.375);New– 03 (Km 464.665, Km 517.12, Km
No. of Toll Plazas (Number and Location) 02 (Km 438+500 & Km 507+085)
No. of Fly Over (Number and Location)12 (Km 398.820, Km 407.545, Km 408.320, Km 456.315, Km 464.185, Km 475.665, Km 467.045, Km 496.595, Km 501.985, Km 504.300, Km 506.205, Km 515.983)DPR Consultant Name Intercontinental Technocrats Pvt. Ltd.
Lead & Consortium Members of Banks Bank of Baroda (Lead Bank), IndusInd Bank, IFIN, Bank of Maharashtra, , IIFCL
Concessionaire Name(SPV & Parent Company)
Barwa-Adda Expressway Limited (INTL Transportation Networks Limited)
Date of Award(LOA Date) April 05, 2013Appointed Date April 01, 2014Concession Period 20 years (from Appointed Date)Construction Period(in Days) 910 daysO&M Period(in Days) 20 years (from Appointed Date)Scheduled Date of Completion September 26, 2016Independent Engineer SA Infrastructure Consultants Pvt. Ltd in association
with Sugam Technocrats Pvt. Ltd.IE Agreement Date January 19, 2014IE Mobilization Date February 19, 2014
1.3.2 Project Milestones
Project Milestone Description(Days from Appointed Date)
Planned ActualDelay(No. of Months) Current StatusFinancial
ProgressScheduled
DateFinancial Progress Revised Date
Milestone I
180th day from Appointed Date i.e September 27, 2014, Construction works commenced and minimum expenditure is 10% of total capital cost.
10.00% 27-09-2014 12.20% 27-09-2014
Milestone II
365th day from Appointed date i.e March 31, 2015, Construction of all Bridges commenced and minimum expenditure is 25% of total capital cost.
25.00% 31-03-2015 27.54% 31-03-2015
Milestone III
730th day from Appointed Date i.e March 30, 2016, Construction of all Project Facilities commenced and minimum expenditure is 75% of total capital cost set forth in the Financial Package.
75.00% 31-03-2016 48.69% 30-06-2017 15.00
Till January 31, 2017 the cumulative
financial progress is –
69.00%
Scheduled Completion 910th day from Appointed Date i.e.(Six Laning Completed in accordance with CA)
100.00% 26-09-2016 27-12-2017 15.00
1.3.3 Location Map
Dhanbad
Durgapur
1.3.4 Key Plan
1.3 Physical Progress
Component % Weightage
Physical Progress
(During Current Month)(Cumulative, Upto Current
Month)Road Works 56.78% 0.91% 36.42%Major Bridge works and ROB / RUB 3.25% 0.02% 2.77%
Structures 29.57% 0.65% 19.30%Other Works 10.40% 0.15% 4.39%
Total Physical Progress 100.00% 1.73% 62.88%
1.4.1 Detailed Scope of work and Physical Progress by Component
Component
Cost Weightag
e in Project
(%)
Item DescriptionCost
Weightage in Component
(%)
Planned in Scope (As per Scope of Work)
% Physical Progress in
Project
% Physical Progress in Component
Value of Physical Progress
(7X4)
1 2 3 4 5 6 7 8
Road Works (Main
Carriageway)
0.26% Clearing & Grubbing 0.46% 0.19% 73.08% 0.33%4.21% Embankment 7.41% 3.07% 72.92% 5.41%3.60% Sub Grade 6.34% 2.48% 68.89% 4.37%7.12% GSB 12.54% 6.10% 85.67% 10.74%1.56% WMM 2.75% 1.30% 83.33% 2.29%4.70% CT Sub-Base 8.28% 2.28% 48.51% 4.02%2.35% CT Base 4.14% 1.08% 45.96% 1.90%2.35% AG Layer 4.14% 1.04% 44.26% 1.83%15.69% DBM 27.63% 10.63% 67.75% 18.72%12.08% BC 21.28% 6.64% 54.97% 11.69%0.19% Rigid Pavement 0.33% 0.15% 78.95% 0.26%0.29% Road marking 0.51% 0.04% 13.79% 0.07%2.38% RE wall filling 4.19% 1.43% 60.08% 2.52%
Major Bridge works and ROB / RUB
2.16% ROB 66.46% 1.79% 82.87% 55.08%1.09% Major Bridges 33.54% 0.98% 89.91% 30.15%
Structures
2.35% Minor Bridges 7.95% 1.83% 77.87% 6.19%7.73% Grade Separator 26.14% 4.80% 62.10% 16.23%2.03% Over Pass 6.86% 1.20% 59.11% 4.06%0.21% Underpass 0.71% 0.20% 95.24% 0.68%1.60% Vehicular Underpass 5.41% 1.25% 78.13% 4.23%0.46% Pedestrian Underpass 1.56% 0.39% 84.78% 1.32%3.39% Crash Barrier/Guard stone 11.48% 1.85% 54.51% 6.26%8.88% RE Wall 30.02% 5.65% 63.65% 19.11%2.46% BC/SC 8.32% 1.79% 72.76% 6.05%0.46% Pipe Culverts 1.56% 0.34% 73.91% 1.15%
Other Works
2.40% Lined & unlined Drain 23.08% 1.30% 54.17% 12.50%2.73% Retaining wall & Toe wall 26.25% 1.00% 36.63% 9.62%0.83% Pitching &turfing 7.98% 0.12% 14.46% 1.15%0.59% TD & Permanent Traffic
Signages 5.68% 0.18% 30.45% 1.73%1.07% Miscellaneous 10.32% 0.62% 57.78% 5.96%1.36% Toll Plaza 13.06% 0.80% 58.90% 7.69%0.60% HTMS 5.73% 0.28% 47.01% 2.69%0.82% Electrical 7.89% 0.08% 9.75% 0.77%
GRAND TOTAL 100.00% 62.88%
Total Length 122.88
Total Work frontUnavailable
21.602 17.58%
Pending LandAcq.PendingClearancesEncumbrances
Length (Km) % Totallength
Total Length
122.88Total Length Completed (Till DBM)
84.80 69.01%
BC 73.50 59.81%
DBM 84.80 69.01%
Base Course 85.42 69.51%Sub-Base 85.86 69.87%Sub-Grade 88.20 71.78%Embankment 93.85 76.38%
Length (Km)
% Totallength
Total Length
149.09Total LengthCompleted(Till BC)
78.10 52.38%
BC 78.10 52.38%
AG Layer 80.10 53.73% CT Base Course
83.40 55.94% CT Sub- Base Course 84.75 56.84%Sub-Grade 91.50 61.37%C&G 96.50 64.73%
1.5.2 Strip Plan(Summary)
1. Work front Unavailable & Reason forUnavailability 2. Length Completed by layer (MCW)
3. Length Completed by Layer(SR)
Length(km)
% TotalPendingLength
1.6 Land Acquisition and Clearances
1.6.1 LA Summary
Description Total Required (ha)Total in possession at
start(ha)
Total to be acquired(ha)
Existing ROW 529.637 528.655 -Pvt. Land To be Acquired 201.290 - 201.290Public Land To be TransferredGrand Total 731.56 528.655 201.290
1.6.2 LA Detail by CALA
CALA
Total Land
left to be
Acquired (Ha)
3H Pen
d ing (ha)
3H Don
e (ha)
3G Pen
d ing (ha)
3G Don
e (ha)
3D Pending (ha)
3D Don
e (ha)
3A Pending (Ha)
3A Don
e (ha)
Amount Awarde
d (Crore Rs.)
Amount Deposit
ed (Crore Rs.)
Amount Disburse
d by CALA
PendingAmount
(CroreRs.)
(CroreRs.)
DLAO & Competen
t Authority, Dhanbad
78.53 48.45 30.08 26.93 51.6 11.8 66.73 11.8 66.73 172.54 182.85 54 128.85
ADM (LA) and
Competent
Authority, Burdwan
122.76 17.04 105.72 8.71 114.05 0 122.76 0 122.76 622.59 893.53 360 533.53
GrandTotal 201.29 65.49 135.8 35.64 165.6
5 11.8 189.49 11.8 189.49 795.13 1076.38 414.00 662.38
Note : Paper possession of 32.53 Ha of land in Jharkhand received with full of encumbrances. The physical possession yet to be received.
1.6.3 Clearances SummaryEnvironment
Proposal Description Status Length
ImpactCurrent Stage
Issues/Comments
West Bengal Obtained Nil Completed NilJharkhand Obtained Nil Completed Nil
Forest LandProposal Description Status Length
ImpactedCurrent Stage Issues/Comments
Not Applicable
WildlifeLength
Not ApplicableTree Cutting
Proposal Description Status Length Impacted Current Stage Issues/CommentsWB portion (15456 Numbers of
Tree)Permission obtained 43.325 All most
completed NilJharkhand (11032 Numbers of
Tree)Permission obtained 79.52 All most
completed Nil
Railways(ROBs/RUBs)GAD Number Status Location/ Chainage Current Stage Issues/Comments
BSEC-CDSC/B-A/ROB-443+710/GAD-01 (1 OF 2) GAD approved 443.710 work in progress Nil
SCPL/C-805/TR/ ROB/520+373/101 GAD approved 520.387 work in progress Nil
1.6.4 Status of utilities shifting
UtilityCategory
Name Status
Length affected
(Km)
Department
Date of request
by Authority
for estimate
Date when Estimate
was Received
from concerned
dept.
Date of Approval
by Authority RO/ HQ
Date of Deposit of
super-vision charge
Progress of Physical Shifting
Date of Certification from Agency
for Completio
n
EstimateAmount
Issue/ Comments
Electricity
JSEBD
EstimateApproved
43.33
Jharkhand
State Electricity
Board Distribution
24-01-2013
In -Progress
TBD 35.24
DPSCLEstimateApproved
13.78
Dishergarh Power Supply
Company LTD/Indian
Power Company
25-05-2016 In -Progress 6.98
Ambiguity in dismantled
material and its salvage value (YTS)
WBSEDCL
EstimateApproved 51.23
WB State Electricity
Distribution Company
LTD.
13-03-2014 In -Progress 38.92
DPL EstimateApproved 2.00 Durgapur
Projects LTD. 29-11-2013 Completed 1.50
DVC EstimateApproved 4.77
Damoder Valley
Corporation
17-07-2015 In -Progress 4.32
DSP
EstimateApproved
0.16 Durgapur Steel plant 27-08-2015
Completed
1.18
Water
JH-DW&SD
EstimateApproved 29.895
Jharkhand DW&SD – Smaller
08-04-2015 In -Progress 14.99
DMC EstimateApproved 9.00
Durgapur Municipal
Corporation 20-12-2013 In -Progress 2.54
UtilityCategory
Name Status
Length affected
(Km)
Department
Date of request
by Authority
for estimate
Date when Estimate
was Received
from concerned
dept.
Date of Approval
by Authority RO/ HQ
Date of Deposit of
super-vision charge
Progress of Physical Shifting
Date of Certification from Agency
for Completio
n
EstimateAmount
Issue/ Comments
Water
WB-PHED
EstimateApproved 22.78 WB PHED 20-12-2013 In -Progress 22.97
DPL EstimateApproved 1.5 Durgapur
Projects LTD. 09-04-2014 Completed 1.24
ADDA Durgapur
EstimateApproved 8.13 ADDA
Durgapur 20-12-2013 In -Progress 4.59 Asansol
Mechnical
EstimateApproved 0.36 Asansol
Mechanical 16-12-2014 In -Progress 5.72
ADDA Asansol
Department to shift at their own
cost ADDA Asansol
Completed
Gas Pipe Line
Essar India LTD
Department to shift at their own
cost Essar India
LTD Completed
GEECLDepartment to shift at their own
cost GEECL In -Progress
OthersSchool Estimate
Approved Gopal Math School (Km 489+900
RHS) 16-02-2015
Completed 2.78
Police Station
EstimateApproved
Kulti Police Station (Km
447+780LHS) 18-04-2016 Yet to Start 0.93 Land not yet
handed over
Others Police Station
EstimateApproved
Faridpur Police Station (Km 496+200
LHS) 18-04-2016 Yet to Start 0.93 Land not yet
handed over
Additional Estimate
ADDA Estimate Yet to Approve 1.27 ADDA 19-10-
2015 07-12-2015 Yet to Start
DMC Estimate Yet to Approve 1.4 DMC 17-08-
2015 02-11-2015 Yet to Start WB-
PHEDEstimate Yet to Approve 0.18 WB-PHED 12-01-
2016 25-01-2016 Yet to Start DPL
Electrical
Estimate Yet to Approve 1.5 DPL Electrical
31-10-2015 Yet to Start
Jharkhand PHED
Estimate Yet to Approve 0.34 Jharkhand
PHED water 21-02-2015 Yet to Start
water pipeline pipeline
DVC Estimate Yet to Approve DVC Yet to Start
1.7 Change of Scope
S No.
COS Proposal Details Date of first
submission to IE
Current Status COS Amou
nt (INR Cr.)
Expected/ Actual Date of Approval
COS-1
Re-alignment due to JDW&SD 1m dia water pipe line - Tentative Cost
25-02-2015
In principal approved 33.73 16-11-2015
Re-alignment due to JDW&SD 1m dia water pipe line - Detailed Cost
27-11-2015
Approval awaited 31.82 NHAI, HQ Since 18-01-2016
COS-2
Protection culvert over IOCL pipeline at Dhadka-Melakula&Rajbandh - Tentative Cost
10-10-2014
In principal approved 4.89 18-07-2016
COS-3
Additional PUP in Kanska(Panagarh Bypass) - Tentative Cost 27-02-2015
In principal approved 10.12 18-07-2016
Cos-4 Increase in size of PUP(10.0*3.5m vs 7.00*3.0m) - Tentative Cost 25-02-2015
In principal approved 1.63 18-07-2016
COS-5
Additional structure in Panagarh Bypass - Tentative Cost Estimate
24-09-2015
In principal approved 6.5 11-03-2016
Additional structure in Panagarh Bypass - Detailed Cost estimate
13-06-2016
Approval awaited 8.03 IE, under review
COS-6
Additional underpass at Km 494+530 06-10-2015
In principal approval awaited
1.5 NHAI, HQ
COS-7
Additional underpass at Km 497+480 08-10-2015
In principal approved 21.5 15017/1/2013/PIU(DUP)/2986 dt.
15.11.2016COS-
8Re-alignment due to oil pipe line of HPCL/IOCL 12-11-
2015In principal approval awaited
20.331 NHAI, HQ Since10-03-2016
COS-9
Foot Over Bridge Banskopa (At Km 506+780) 28-06-2016
In principal approval awaited
3 NHAI
COS-10
Road Boundary Stone 19-07-2016
In principal approval awaited
0.615 IE under review
No.Equipment Name Make Model
Age ofEquipment
Planned/ Required Quantity
ActualQuantity
Deployed During the
Month
Reason(s) for Under/Over Mobilization
Expected Delay due to
Under- Mobilization
(Months)Remarks
1 Crusher Plant * 4 4 4 Adequate Mobilization
NA
2 WMM Plant * 4 4 4 Adequate Mobilization
NA
3 Batching Plant 5 5 5 Adequate Mobilization
NA
4 Hot Mix Plant 4 4 4 Adequate Mobilization
NA
5 Weigh Bridge 10 10 10 Adequate Mobilization
NA
6 Dozer 6 6 6 Adequate Mobilization
NA
7 Excavators (1-1.2 cum bucket) 38 38 38 Adequate
MobilizationNA
8 Motor Grader (135-195 HP) 25 25 25 Adequate
MobilizationNA
9 Vibro. Soil Compactor (8-10 MT) 30 30 30 Adequate
MobilizationNA
10 Tendam Roller 13 13 13 Adequate Mobilization
NA
11 Pneumatic Tyred Roller 6 6 6 Adequate
MobilizationNA
12 Front Wheel Loader (3.0 cum bucket) 16 16 16 Adequate
MobilizationNA
13 Tipper (10 T/25 T) 169 169 169 Adequate Mobilization
NA
1.8 Mobilization of Resources
No.Equipment Name Make Model
Age ofEquipment
Planned/ Required Quantity
ActualQuantity
Deployed During the
Month
Reason(s) for Under/Over Mobilization
Expected Delay due to
Under- Mobilization
(Months)Remarks
14 Water Tanker (10 KL) 30 30 30 Adequate Mobilization
NA
15 Back Hoe Loader (JCB) 13 13 13 Adequate
MobilizationNA
16 Hydra Crane (14 MT) 8 8 8 Adequate Mobilization
NA
17 Crane (70 T) 3 3 3 Adequate Mobilization
NA
18 Air Compressor 7 7 7 Adequate Mobilization
NA
19 Diesel Tanker 6 6 6 Adequate Mobilization
NA
20 DG (25 to 750 KVA) 64 64 64 Adequate Mobilization
NA
21 Total Station 6 6 6 Adequate Mobilization
NA
22 Auto Level 33 33 33 Adequate Mobilization
NA
23 Transit mixture 33 33 33 Adequate Mobilization
NA
24 Broomer 4 4 4 Adequate Mobilization
NA
25 Trailer 6 6 6 Adequate Mobilization
NA
26 Mini VTR 6 6 6 Adequate Mobilization
NA
27 Sensor Paver 11 11 11 Adequate Mobilization
NA
28 Concrete Pump 5 5 5 Adequate Mobilization
NA
29 Kerb Paver 6 6 6 Adequate Mobilization
NA
30 Bitumen Browser 7 7 7 Adequate Mobilization
NA
No.Equipment Name Make Model
Age ofEquipment
Planned/ Required Quantity
ActualQuantity
Deployed During the
Month
Reason(s) for Under/Over Mobilization
Expected Delay due to
Under- Mobilization
(Months)Remarks
31 Light Tower 10 10 10 Adequate Mobilization
NA
1.9 Financial Progress Details
1.9.1 Pen Picture-Escrow
TPC (Cr)
Cumulative inflow to Escrow
till previous month (Cr)
Cumulative outflow from Escrow till previous month
Inflow to Escrow during the month
(Cr)
Outflow from Escrow during the
month
(Cr) (Cr)2,434.86 786 785.57 11.43 11
Are the Escrow withdrawals in accordance with the order of withdrawal as specified in the Concession Agreement?Tick as applicable Yes√ No
If not, details to be provided below:
1.9.2 Escrow details
TPC(Cr) Cumulative exp. till
date (Cr)
Escrow Plan till date-Debt
(BOT)(Cr)
Escrow Plan till date- Equity
(BOT) (Cr)
Escrow Plan till date-VGF(BOT)
(Cr)
Escrow Actual till date-Debt (BOT) (Cr)
Escrow Actual till date-Equity
(BOT) (Cr)
Escrow Actual
till date-VGF
(BOT) 2,434.86 1499.76 1440 996.65 - 797 0
1.10 Monitoring of Operations & Maintenance Obligations
1.10.1 Maintenance Status during Construction Phase
1. Trimming of over growth of plants and shrubs in median portion activity should be expedited immediately. Plantation is to be done fast.
2. Cleaning of carriageway, median, bridge footpath & shoulders to be completed immediately. Median cleaning is not satisfactory.
2. Pot holes observed in project highway section. It should be repaired immediately. Specially Barwa-Adda section, Maithan section, km.450, Km 456, Km 469,km 494, Gandhi more, Km 509 &All diversion roads should make smooth immediately.
4. Delineator and Barricading has not been done in site as per instruction of IIT safety Consultant.
5. All junction location existing/new Kerb should be painted immediately as per Technical specification. Do not use distemper. Paint should be confirm as per IS-164 requirement
6. All roots of trees etc. on existing bridges, ROB should be removed immediately and cleaning should be done immediately.
7. Diversion provided on newly constructed ROB at Km. 520+383does not follow the reviewed diversion plan and IRC specifications vide our letter no. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/1932 dt. 22.10.2016for safety.
8. Diversion roads are required repair at many places especially in Section - II
The Concessionaire has deployed the route patrolling vehicles, ambulances and cranes with requisite crew for incident management and team for maintenance of the project highway and ensures the project highway is trafficable.During this month Concessionaire has filled the pot holes at some location with WMM and Bituminous materials.Concessionaire has been instructed to all pot holes should be repaired with bituminous materials.
1.10.2 Maintenance Status during Operations & Maintenance Phase
The Concessionaire has deployed the route patrolling vehicles, ambulances and cranes with requisite crew for incident management and team more than the stipulated numbers in the Concession Agreement for maintenance of the project highway and ensures the project highway is trafficable.
1.11 Pen Picture on safety features
Details to be provided after assessment of the site requirement vis-à-vis provisions in the Concession Agreement:
Location of Black Spots
Suggested Remedial Measures within provision so
Concession Agreement
Additional Remedial Measures(if any)
Financial implication so
additionalRemedial
Measures for Authority(Cr.)
Kajora area hospital,PS: Andal, NH-2
A median opening needs to be closed after construction of 6-lane. However various types of temporary crash barrier &retro reflective Signages installed at the location. Safety measures have been provided.
No No
Gandhi More, PS-Durgapur, NH-2
6- lane Grade Separator is under construction as per CA. However various types of temporary crash barrier & retro-reflective Signages installed at the location. Safety measures have been provided.
No No
Panagarh Bazaar - Kanksa PS Rail-over Bridge to Darjeeling More 3.2 Km. Dist.:
Burdwan, NH-2
A new bypass road has been constructed along with a new ROB which is under construction as per CA.However various types of temporary crash barrier &retro reflective Sinages installed in Panagarh Bazaar till the opening of Bypass.
No No
1.12 SALIENT FEATURES OF PROJECT HIGHWAY
1.12.1. Road Width: Bituminous Carriageway = 2 x 10.50m Central Median Width = Retain Existing Width Paved Shoulders = 2 x 1.5 to 2.0mEarthen Shoulders = 2 x 2 m
1.12.2. Pavement Composition (For Widening Stretches):Bituminous Concrete = 40-50 mmDBM = 50-100 mmWMM = 250 mmGranular Sub base = 200 mmSub grade (CBR 12% & 15%) = 500 mm
1.12.3. Pavement Composition (For Re-Construction/Re-Alignment Stretches):
Bituminous Concrete = 50 mmDBM = 50-55 mm AG Layer = 100 mmCT Base = 100-105 mmCT Sub Base = 250 mmSub Grade = 500 mm
1.12.4. Pavement Composition for Strengthening Over Existing Road:Bituminous Concrete = 40-50 mmDBM = 50-90 mm
1.12.5. Pavement Composition for Service Road: Bituminous Concrete = 40 mmAG Layer = 100 mmCT Base = 100 mmCT Sub Base = 250 mmSub Grade = 500 mm
1.12.6. Details of New/Widening of Structures and Project Facilities to be constructed along the project Highway:Sl. No.
Descriptions As per CA As per Site Condition
1 ROB 02 (Km 443+710 & 520+383)
02(Km 443+710 & 520+383)
2 Major Bridges 03 033 Minor Bridges 20 204 Box Culverts 47 475 Slab Culverts 67 676 Pipe Culverts 88 887 Underpass 2 28 VUP 20 209 PUP 11 1110 Grade Separator
(GS) 12 1211 Over Pass (OP) 02 0212 Toll Plaza 02(Km 438+500 & Km
507+000)02 (Km 438+550 & Km
507+085)
13 Wayside Amenity Complex
01 (Km 463+000, As per CA)
01 (Km 468+800, As per DPR drawing & Proposed
Land Acquisition Plan)14 Bus Bays and
Shelters 20 Nos. LHS + 20 Nos. RHS 20 Nos. LHS + 20 Nos. RHS15 Truck Lay Byes 10 Nos. LHS + 04 Nos. RHS 10 Nos. LHS + 04 Nos. RHS16 Highway
Lightings As per Site Condition As per Site Condition17 HTMS Works As per Site Condition As per Site Condition
18 Tree Plantation
NHAI had deposited 1.64 Cr. towards afforestation for Avenue Plantation due to lack of space within the ROW.
Meridian Plantation, as per Site Condition
19 Administrative Base Camp 02 02
20 Traffic Aid Post 02 02
NCR DETAILS :-Sr.
No
Date Issued by
Issuing Reference
Locations Descriptions Closing Ref. Remark
1 27-09-2014
RE Safety/NCR/01/2014
Culvert Ch.452+352.5 (LHS)
Ch.450+500 (LHS)&
Ch.446+019 (LHS)
Safety measures to be taken immediately by the protection of culvert location by providing advance information sign board, hard barricading as per site conditions.
BAEL/PRJ/ TEC/ICO-581/2015/828 dated
13.05.2015
CLOSED
2 27-09-2014
RE Safety/NCR/02/2014
Ch.403+335 (LHS)Ch.404+120 (LHS)Ch.439+710 (BHS)
&Ch.440+095 (LHS)
Safety measures to be taken immediately by the protection of culvert location by providing advance information sign board, hard barricading as per site conditions.
BAEL/PRJ/ TEC/ICO-581/2015/829 dated
13.05.2015
CLOSED
3 30-09-2014
RE Safety/NCR/03/2014
Ch.506+205 (LHS)Ch.515+983 (GS)Ch.501+985 (GS)
&Ch.496+710 (Box
culvert)
Safety measures to be taken immediately by the protection of above location by providing information sign boards, advance informatory sign board, hard barricading, delineator, reflective tape and necessary safety arrangements as per technical specification
BAEL/PRJ/ TEC/ICO-581/2015/838 dated
19.05.2015
CLOSED
4 12.01.2015
TL Safety/NCR/04/2015
Diversion at Km. 398+811 (LHS)
Exposed GSB at the diversion portion to be covered with Bituminous layer as mentioned in the traffic diversion plan and provide adequate safety arrangement as per IRC specification.
BAEL/PRJ/ TEC/ICO-581/2015/830 dated
13.05.2015
CLOSED
5 12.01.2015
RE Safety/NCR/05/2015
Vide letter no.
1.SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/671 dated
13.01.2015
2. SAICPL-Sugam/Barwa-
Adda-Panagarh/IE/NH-2/2014/880
dated 17.03.2015
Ch. 403+350 to 403+600 (LHS)
GSB layer should be covered immediately with subsequent bituminous layer and safety measures to be taken immediately by providing proper advanced information sign boards like men at work, road closed. No overtaking, delineators, cats eye and hard barricading as per approved traffic diversion plan and IRC-SP-55.
BAEL/PRJ/ TEC/ICO-581/2015/833 dated
14.05.2015
CLOSED
6 14.01.2015
TL STR/NCR/06/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/675 dated
14.01.2015
Pipe Culvert at Km. 460+120 (LHS)
PCC has to be layed as per thickness provided in reviewed typical drawing and then NH-4 pipes has to be layed.
BAEL/PRJ/ TEC/ICO-581/2015/ 624 dated
06.02.2015
CLOSED
7 17.01.2015
TL HWY/NCR/07/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/693 dated
17.01.2015
Km. 500+750 to Km. 500+800 (LHS)
The laid WMM Top layer has to be removed. The exposed WMM 1st layer below has to be scarified and brought to required level followed by proper grading, compaction and density check. After confirmation the Top layer can be laid conforming to specified thickness.
BAEL/PRJ/ TEC/ICO-581/2015/703 dated
04.03.2015
CLOSED
8 06.08.2015
TL MAT/NCR/08/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Km. 501+900 to Km. 501+970 (LSR)
The laid cement treated base has not satisfy the specification required
BAEL/PRJ/ TEC/ICO-581/2015/1049 dated
10.09.2015
CLOSED
Panagarh/IE/NH-2/2014/1215
9 21.08.2015
TL MAT/NCR /09/2015Vide
letter no.SAICPL-Sugam/Barwa-
Adda-Panagarh/IE/NH-2/2014/1249
Ch. 406+300 to ch. 406+430 (LSR)
The laid cement treated base has not satisfy the specification required
BAEL/PRJ/ TEC/ICO-581/2016/1362 dated
01.03.2016
CLOSED
10 21.08.2015
TL MAT/NCR/10/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1250
Ch.406+190 to 406+430 (LSR)
The laid aggregate layer is not satisfying the specification
BAEL/PRJ/ TEC/ICO-581/2016/1361 dated
01.03.2016
CLOSED
11 08.09.2015
TL HYW/NCR/11/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1290
Ch. 473+100 to473+300 (RHS)
CT Sub base laid without approval of Pavement Design
BAEL/PRJ/ TEC/ICO-581/2015/1139 dated
14.10.2015
CLOSED
12 09.09.2015
TL HYW/NCR/12/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1294
Ch. 455+040 to Ch. 455+890 (R/S) overlay MCW & Ch.453+440 to
Ch. 453+535 (R/S) widening MCW
DBM (VG-40) job mix formula is not in the line of assumptions made in pavement design with regards to Va&Vb as per IRC:37:2012
BAEL/PRJ/ TEC/ICO-581/2015/1285 dated
21.01.2016
CLOSED
13 09.09.2015
TL HYW/NCR/13/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1298
Ch. 515+290 to 515+520 (LHS)
DBM (VG-40) job mix formula is not in the line of assumptions made in pavement design with regards to Va&Vb as per IRC:37:2012
BAEL/PRJ/ TEC/ICO-581/2015/1138 dated
14.10.2015
CLOSED
14 10.09.2015
TL HYW/NCR/14/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1299
Ch. 515+320 to 515+340 (LHS)-Road
Separator side
Improper laying of kerb due to which DBM layer has covered the entire thickness of L-portion of the Kerb.
BAEL/PRJ/ TEC/ICO-581/2015/ 1083 dated
22.09.2015(Dismantled)
Re-laid on dated 24.09.2015
CLOSED
15 12.09.2015
TL MAT/NCR/15/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1305
Ch. 451+500 to 452+000 (LHS)-MCW
overlaying
Required thickness of DBM as per Pavement Design is 85mm, but laying thickness of DBM is less than required.
BAEL/PRJ/ TEC/ICO-581/2016/1363 dated
05.03.2016
CLOSED
16 15.12.2015
TL MAT/NCR/16/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1457
Ch. 515+300 to 515+650 (RHS)-MCW
Poor quality and improper thickness of Bituminous Concrete
BAEL/PRJ/ TEC/ICO-581/2016/1364 dated
05.03.2016
CLOSED
17 16.12.2015
TL MAT/NCR/17/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1458
Ch. 465+200 to 465+320 (LHS)
widening portion
WMM mixed with unapproved material slag (crushed slag)
BAEL/PRJ/ TEC/ICO-581/2016/1284 dated
21.01.2016
CLOSED
18 18.12.2015
TL Safety/NCR/18/2015
Vide letter no.SAICPL-
Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/1464
Ch. 472+900 to 473+700 (RHS) [VUP at Km. 473+340 and its approach on both
side]
Inadequate safety measures can cause threat to traffic movement at the road inner edge which may lead to major accident
BAEL/PRJ/ TEC/ICO-581/2016/1242 dated
22.01.2016
CLOSED
19 19.12.2015
TL STR/NCR/19/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1466
Ch. 499+013 (LHS & RHS)
Safety issue of Diversion BAEL/PRJ/ TEC/ICO-581/2016/1659 dated
20.10.2016
CLOSED
20 20.12.2015
TL STR/NCR/20/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1469
Ch. 465+060 (RHS)-Panagarh end
Construction of culvert BAEL/PRJ/TEC/ICO-581/2016/1423 dt.
18.04.2016
CLOSED
21 23.12.2015
TL Safety/NCR/21/2015Vide letter
no.SAICPL-Sugam/Barwa-
Adda-Panagarh/IE/NH-2/2014/1476
Ch. 497+390 to 497+440&Ch.
497+500 to 497+615 (LHS) deep excavation
Inadequate safety measures can cause serve threat to traffic movement (road user) at mentioned location which send to major accident
BAEL/PRJ/ TEC/ICO-581/2015/1264 dated
07.01.2016
CLOSED
22 28.12.2015
TL MAT/NCR/22/2015Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1482
Ch. 471+150 to 472+000 (LHS) (MCW)
Non-conform gradation of Bituminous concrete (Grade – II)
BAEL/PRJ/ TEC/ICO-581/2015/1286 dated
21.01.2016
CLOSED
23 26.05.2016
TL Highway/NCR/23/2016
Vide letter no.SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/1715
Ch.399.510 to 400.560 R/S (MCW)
&Ch.422.720 to 423.000
R/S (MCW)
Milling and strengthening of major crack of existing carriageway.
- -
24 27.05.2016
TL MAT/NCR/24/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1721
Ch. 516 + 230 to Ch. 516+480 Left hand
side (main carriageway)
Non-conform Gradation of Bituminous Concrete (Grade – I)
BAEL/PRJ/ TEC/ICO-581/2015/1718 dated
01.12.2016
CLOSED
25 27.05.2016
TL MAT/NCR/25/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1723
Km. 475+615 (RHS) Box culvert A2 return
wall 2nd lift
Invalid concrete cube test BAEL/PRJ/ TEC/ICO-581/2015/1719 dated
01.12.2016
CLOSED
26 31.05.2016
TL STR/NCR/26/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1724
Km. 450+143 Cracked found in Girder of Minor Bridge
BAEL/PRJ/TEC/ICO-581/2016/1686dt. 12.11.2016
CLOSED
27 31.05.2016
TL Highway/NCR/27/2016
Vide letter no.SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/1728
Ch.399.510 to 400.560 R/S (MCW)
&Ch.422.720 to 423.000
R/S (MCW)
Milling and strengthening of major crack of existing carriageway
- -
28 01.06.2016
TL MAT/NCR/28/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1731
Ch. 453+500 to 453+800 (RHS)
Mix Material non-conformed as per IRC:111, Table- 9
- -
29 24.06.2016
TL HYW/NCR/29/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1772
Ch. 425+840 to Ch. 426+040 (RHS)
Sub standard DBM Works ::-1. Longitudinal and transverse crack observed.2. Many location geo glass grid exposed3. Many location DBM thickness vary from 15mm to 25mm approx
- -
30 20.07.2016
TL HYW/NCR/ 30/2016
Vide letter no.SAICPL-Sugam/Bar
wa-Adda-
Ch. 501+582 to Km. 501+962 (Left Service
Road Separator)
Left Service Road Separator portion has inappropriate width.
- -
Panagarh/IE/NH-2/2014/1823
31
31.08.2016
TL MAT/NCR/31/2016Vide Letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1868
Km. 461+355, Girder no. 01
cube test not as per specification
- -
32 16.09.2016
TL HYW/NCR/32/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1886
515+190 to Km. 515+240(MCW_LHS).
longitudinal crack and settlement has been observed
- -
33 19.09.2016
TL HYW/NCR/33/2016Vide letter
no. SAICPL-Sugam/Barwa-
Adda-Panagarh/IE/NH-2/2014/1889
ch. 486+350 to ch. 486+412 (RHS).
Construction of drain cum footpath (cover slab) which is not as per drawing and specifications
BAEL/PRJ/TEC/ICO-581/2016/1669dt.
03.11.2016
CLOSED
34 28.09.2016
TL MAT/NCR/34/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1897
Km. 450+916 & Km. 452+100 (RHS).
Required concrete compressive strength not acceptable
- -
35 28.09.2016
TL STR/NCR/35/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1898
Km. 467+880 to Km. 467+960(RHS).
Defect in execution of drain work
- -
36 30.09.2016
TL HWY/NCR/36/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1907
Box Culvert location at Km. 519+100 (RSR).
Service Road Settlement and Longitudinal crack
- -
37 17.10.2016
TL MAT/NCR/37/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1925
Km. 507+063to Km. 507+101.50(L-
06)_LHS
Flexural strength test results not accepted due to less than 0.3 Mpa of Specified Characteristic Strength
- -
38 19.10.2016
TL HW/NCR/38/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1930
Ch.431+400 to 431+770(RHS), Ch.432+350 to 432+600(RHS), Ch.431+160 to
431+400(RHS) and Ch. 431+770-432+010(RHS)
Laying of Geo Glass Grid over major crack portion of existing carriageway
- -
39 19.10.2016
TL HWY/NCR/39/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1931
Km. 472+200 to Km. 472+750, Km.
474+020 to Km. 474+140, Km.
476+760 to Km. 476+860, Km.
476+900 to Km. 476+950, Km.
488+550 to Km. 489+250, Km.
495+150 to Km. 495+350 & Km. 495+950 to Km.
496+130 (Left Hand Side) &
Km. 491+840 to Km. 492+250 (Right Hand
Side)
Construction of Chute Drains at separators in between MCW and Service roads
- -
40 25.10.2016
TL STR/NCR/40/2016Vide letter no.
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1935
Minor Bridge at Km 495+725 (LHS)-
Abutment wall A1 & A2.
1. Spacing of Weep-Holes not as per drawing & specification in walls of Minor Bridge on both end A1 & A2.2. Irregular Shape of Weep-Hole & partly chocked with concrete.3. Honey-Combed occurs
BAEL/PRJ/TEC/ICO-581/2016/1691dt. 18.11.2016
CLOSED
on wall towards earthface.41 26.10.
2016TL HW/NCR/41/2016
Vide letter no. SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/1937
1. Ch. 429+990 to Km. 430+510 (RHS)
2. Ch. 399+480 to Ch. 399+840 (RHS)
Laying of Geo Grid instead of Geo Class Grid (Fibre) as mentioned in submited methodology in Major Crack portion area of existing carriageway without milling / repair and not as per approved pavement design
- -
42 16.11.2016
TL STR/NCR/42/2016SAICPL-Sugam/Barwa-
Adda-Panagarh/IE/NH-2/2014/1960
Km. 514+700 to Km. 514+950 (LHS) -
Executed length 250 mt.
1. For 600 mm width of drain (Type-2) height is restricted to 1000 mm. But at site the height is more than 1000 mm for the same width of drain has been executed.2. Typical cross section of RCC drain has been reviewed for maximum depth of 1.6m only, but at site execution has been made more than 1.6m height for the same width of 0.6m.3. Longitudinal profile of RCC Drain is not in symmetric with the Separator (LHS)
- -
43 18.11.2016
TL STR/NCR/43/2016SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/1962
Pipe culvert at Km. 460+652 (LHS)
1. Settlement of Hard Bed/ PCC below the laid NP4 pipe due to water logged and improper compaction.2. Pipe joints opened.3. NP4 pipe edge damaged.
- -
44 19.11.2016
TL HWY/NCR/44/2016SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/1969
Km. 506+300 to Km. 506+500 (LSR)
Sub-Grade Layers 1 & 2 laid on site without Laboratory Test and Field Test being done.
BAEL/PRL/TEC/ICO-581/2017/1759 dt.
11.01.2017
CLOSED
45 22.11.2016
TL Highway/NCR/45/2016
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1975
Km. 426+585 to Km. 426+700_LHS_ Median
Kerb
Laid kerb is having lot of voids and honey combs
- -
46 23.11.2016
TL HWY/NCR/46/2016
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1979
520+505 to 520+610 (LHS) 520+750 to
520+770 (LHS)
Slippage cracks of BC/ DBM observed in patches
- -
47 28.11.2016
TL Highway/NCR/47/2016
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1983
(1) Ch.414+350 to 414+720-(LHS), (2)-418+300 to 418+700(LHS), (3)-421+700 to
421+930(LHS), &(4)-421+950 to 422+070(LHS)
Separator drain is not constructed as per Drawing & Specifications in between MCW(LHS) & Service Road.
- -
48 01.12.2016
TL Highway/NCR/48/2016
SAICPL-Sugam/Barwa-Adda-
Panagarh/IE/NH-2/2014/1993
1)Ch.445+760 to Ch.445+920 at Median in between MCW-LHS
& MCW-RHS, (2)-Ch.445+265 to Ch.445+465 at
separator in between SR & MCW(RHS), (3)-
Ch.452+860 to Ch.453+610 at
separator in between SR & MCW(LHS).
Chute Drain constructed at median between MCW(RHS & LHS) & at the separators between MCW and Service Roads at the locations mentioned below instead of drain pipes as mentioned in IRC:SP:87.2010 clause no.2.15.1. Compliance of IE's letter ref.SAICPL-SUGAM/Barawa-adda-Panagarh/IE/NH-2/2014/1903 dt.28.09.2016 is still pending.
- -
49 21.12.2016
TL MAT/NCR/49/2016SAICPL-Sugam/Bar
Km. 503+985 (LHS), Underpass
I) spraying prime coat in place of Tack coat.
- -
wa-Adda-Panagarh/IE/NH-
2/2014/2015
II) No any mechanical broomer, sprayer and spraying unproperly.III) Mixing water randomly with emulsion.
50 24.12.2016
TL HWY/NCR/50/2016SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/2016
Km. 488+850 to Km. 489+150_LHS
Laying of CC Paving block in Separator portion between SR & MCW has not been done as per specification. The thickness of paver block and base course is observed 50mm & 50mm is place of 60mm and 200 mm.
- -
51 24.12.2016
TL HWY/NCR/51/2016SAICPL-Sugam/Barwa-
Adda-Panagarh/IE/NH-2/2014/2017
Km. 483+300 to Km. 483+800_LHS
Severe deformation of rutting observed in MCW between Km. 483+300 to Km. 483+800_LHS.This location pavement thickness has not been provided as per reviewed Pavement Design.To be removed and replaced with reviewed pavement design thickness
- -
52 24.12.2016
TL HWY/NCR/52/2016SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/2018
Km. 513+720, Km. 513+900, Km.
514+070 & Km. 514+190 (LHS)
4 nos. Jerks have been observed in MCW between Km. 513+700 to Km. 514+200_LHS.To be rectified immediate.
- -
53 27.12.2016
TL STR/NCR/53/2016SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/2018
Km. 464+910(RHS), Minor Bridge
R.C.C. Girder of length 17 mtr. has been cracked at different area of Web as well as Flange of Girder. (Girder no. G4, date of casting : - 25.06.2015, RFI No. :- 2825)
Note :- The Girder has been rejected and advice not to be used in Super Sturucture of the Minor Bridge.
- -
54 03.01.2017
TL HWY/NCR/54/2017SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/2026
Km. 481+080 to Km. 481+800 (RHS)
Severe deformation of rutting observed in MCW(RHS) in ROB approach at Km. 481+080 to Km. 481+800 (RHS). This location pavement thickness has not been provided as per reviewed pavement design. To be removed and replaced with reviewed pavement design thickness.
- -
55 03.01.2017
TL HWY/NCR/55/2017SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/2027
Km. 476+880 to Km. 477+000(LHS)
Laying of CC Paver Block in Seperator Portion between MCW & SR has not been done as per specification.The thickness of paver block and base course is observed 50mm & 100mm in placed of 60mm and 200mm
- -
56 18.01.2017
TL HWY/NCR/56/2017SAICPL-Sugam/Bar
wa-Adda-Panagarh/IE/NH-
2/2014/2039
Km. 476+720 to Km. 476+880 (LHS), Km.
492+170 to Km. 492+260 (RHS)
Laying of CC Paver Block in Seperator Portion between MCW & SR has not been done as per specification.The thickness of paver block and base course is observed 50mm & 100mm in placed of 60mm and 200mm
- -