Ngb Ppt [Final]
-
Upload
udit-agrawal -
Category
Documents
-
view
228 -
download
0
Transcript of Ngb Ppt [Final]
-
8/3/2019 Ngb Ppt [Final]
1/27
Transportation Tariffs for
Natural Gas Pipelines
Natural Gas Business
ByUdit Agarwal(M-10-33), Rajat Gupta(M-10-25), Venu Vijay(M-10-35), Swarbhanu Handique(M-10-32)
-
8/3/2019 Ngb Ppt [Final]
2/27
Factors affecting NG Pipeline Tariff
Determination
Large upfront investments.
Long gestation period.
Risk of low utilization.
Relative economics of alternate fuels.
Constitutes upto 25% of the end price of the gas.
-
8/3/2019 Ngb Ppt [Final]
3/27
-
8/3/2019 Ngb Ppt [Final]
4/27
Cost Plus approach
Tariff is determined on the basis of:
Capex investment
Opex investment
Taxation
Return on capital
Normative Parameters
Best for developing Gas Markets.
-
8/3/2019 Ngb Ppt [Final]
5/27
Indexation
Tariff is fixed on the basis of pre-set performance target.
Tariff rate is allowed to be updated.
Updation depends on achievement of performance
targets.
Adopted by UK and many EU countries.
Not suitable for developing Gas markets.
-
8/3/2019 Ngb Ppt [Final]
6/27
Market based rate setting
Tariff is fixed on the basis of market based rates.
Gas market should have enough competition.
Adopted by markets having developed pipeline
infrastructure.
Approved basis for setting tariff in USA.
-
8/3/2019 Ngb Ppt [Final]
7/27
-
8/3/2019 Ngb Ppt [Final]
8/27
NG pipeline tariff in India
Two methods are prevalent in India for determining NG
tariff:
Zonal-Postalized System.
Postalized System
-
8/3/2019 Ngb Ppt [Final]
9/27
Zonal Postalized Tariff
Zones of length 300 km & width of 50 kms or 10% of pipelinelength(whichever is lesser) each
Same zone pay the same tariffs
Entity to supply gas to all techno feasible customers in the zone.
300 KM 300 KM 300 KM
Zone 1 Zone 3Zone 2
50KM
50KM
-
8/3/2019 Ngb Ppt [Final]
10/27
Example
ParticularsEWPL (East west
pipeline of RGTIL)HVJ-GREP-DVP
Zone 1 (closest to gassource)
15 20
Zone 2 42 22
Zone 3 54 25
Zone 4 59 28
Zone 5 (farthest from
gas source)61 na
Zonal tariffing : An illustration (rates in Rsper mmbtu)
Source :: http://www.equitymaster.com/detail.asp?date=04/19/2011&story=4&title=Zonal-tariff-
Blockage-in-the--gas-pipeline
-
8/3/2019 Ngb Ppt [Final]
11/27
Bidding criteria
Lowness of PV oftariff bid for each year(70% wt)
tariff to be bid zone-wise (TZn >= TZn-1) with
40% weight for TZ1
20% weight for %age increase over TZ1
10% weight for %age increase over TZ2
Highness ofPV of natural gas volumes (in
MMSCMD) proposed to be transported(30% weightage)
-
8/3/2019 Ngb Ppt [Final]
12/27
An Illustration
Tariff Zone Tariff
First Tariff Zone Tariff bid for the first tariff Zone for first year
Second Tariff Zone Tariff bid for the first tariff Zone for first year X [1 +
(PF2/100)]
Third Tariff Zone Tariff bid for the first tariff Zone for first year X [1 +
(PF2/100) + (PF2/100) X (PS2/100)]
Fourth Tariff Zone Tariff bid for the first tariff Zone for first year X [1 +
(PF2/100) + (PF2/100) X (PS2/100) + (PF2/100) X(PS2/100)^2]
PF2 - % increase bid for Zone 2
PS2 - % increase bid for Zone 3
-
8/3/2019 Ngb Ppt [Final]
13/27
Zonal Postalized system
Merits:
To balance the perspectives of the entities Incentive for the entities
Ensure transparent bidding process
-
8/3/2019 Ngb Ppt [Final]
14/27
-
8/3/2019 Ngb Ppt [Final]
15/27
Zonal Postalized system
Demerits:
Imbalance in economic growth.
Industries that are located far from gas sourcesbecomes uncompetitive
Unfair penalty on retail consumers located far fromthe gas source
-
8/3/2019 Ngb Ppt [Final]
16/27
Complex issue
0.50 0.53 0.55 0.58 0.61 0.64 0.67 0.70
0.61 0.58 0.55 0.53 0.50 0.53 0.55 0.58
Z1 Z4Z2 Z5Z3 Z6 Z7 Z8
Z4Z2 Z3Z2 Z1Z4 Z3Z5
3.00Gas A
4.20
5.20
Gas B
5.90
3.70
5.78
Tariff determination in intersection of pipeline
-
8/3/2019 Ngb Ppt [Final]
17/27
Postalized tariff system
Example: HVJ Pipeline
Based on Discounted Cash flow (DCF) methodology .
The rate of return on capital employed shall be the rate of
return on capital employed equal to 12% post-tax.
Reasonable rate of return on the total capital employed todetermine the return on capital employed in the project over
its economic life.
Total capital employed shall be equal to the gross fixed assets
in the project less accumulated depreciation plus normativeworking capital (equal to thirty days of operating costs
excluding depreciation and eighteen days natural gas pipeline
tariff receivables).
-
8/3/2019 Ngb Ppt [Final]
18/27
Postalized tariff system
The volumes of natural gas is considered as divisor inthe determination of the unit natural gas pipeline tariff
over the economic life of the project.
Year of natural gas pipeline
operations
Percentage Utilization
First 60%
Second 70%
Third 80%
Fourth 90%
Fifth 100%
-
8/3/2019 Ngb Ppt [Final]
19/27
Postalized tariff system
Merits:
Ideal for Attracting New pipeline investments in developing
NG markets.
Return rate being risk related is a fair way of compensatingcapital investment.
Simple to operate.
Perceived balanced economic development.
Uniform tariff policy can easily work for gas transmission
pipeline business where capital cost rather than the operating
expenditure holds the key.
-
8/3/2019 Ngb Ppt [Final]
20/27
Postalized tariff system
De Merits:
Multiple inefficiencies in the form of cross-subsidies.
Uniform tariffs, if taken a closer look at, are same as Freight
equalization policy adopted in 1948 by GOI.Factories were set up all along the ports or around big cities
except Bihar ( one of the richest in mineral resources) . The
policy simply destroyed Bihar's huge competitive advantage of
holding minerals. Significant deviations in estimating cost.(example: HVJ
Pipeline)
-
8/3/2019 Ngb Ppt [Final]
21/27
HVJ Pipeline Case
Government fixed HVJ transportation tariff at Rs 1150/tcm
based on the recommendation of Sankar Committee on
Natural Gas Pricing(December 1996).
When reworked, transportation tariff of natural gas worksout to Rs 679/tcm.(In 2004).
Significant deviations due to changes in capital investment,
debt-equity ratio, cost of capital, and transportation volume.
-
8/3/2019 Ngb Ppt [Final]
22/27
Analysis
Zonal Postalized seems to be a better option.
Allows freedom to the bidding entity to bid tariff based on
its real cost of capital.
Demand-Supply and Market Dynamics of end-produce shall
take care of (any) tariff-based advantage that is likely to
accrue to any natural gas consumer in zones located near to
the source of natural gas.
Why should consumers of a natural gas-rich state subsidize
consumers in other states L Mansingh.
-
8/3/2019 Ngb Ppt [Final]
23/27
Recommendations
Each zone to be given proportionate weightage as per the formula:
S = n/2[2a + (n-1)d]
S = 70%(Total Weightage), a= Farthest Zone, n= no. of zones, d=
6%( increase in tariff in subsequent zone)
Example: Let no. of Zones = 5, d = 6%, then a= 2%
TZ1 = 26%, TZ2 = 20%, TZ3 = 14%, TZ4 = 8%, TZ5 = 2%.
SD ( ) of PV across the five zones should not be zero. Bidders are
not allowed to keep same tariff across all the five zones.
Final Calculation = K* Composite Score *
When arranged in ascending order, the bidder placed in the median
will win.
In case of even number of bidders, the one with lower wins.
-
8/3/2019 Ngb Ppt [Final]
24/27
Contributions:
Udit Agarwal(M-10-33)- Introduction and various methodologies
of tariff determination.
Rajat Gupta(M-10-25)- Introduction to zonal postalized &
Postalized tariff
Venu Vijay(M-10-35)- Rationale, Merits, and De-merits of zonal
postalized tariff.
Swarbhanu Handique(M-10-32)- Postalized tariff rationale,
merits, demerits. Analysis of the tariff recovery basis on the
development of gas markets in India, and Recommendations
(Conclusions).
-
8/3/2019 Ngb Ppt [Final]
25/27
References:
Energy Security Insights(Volume 4, Issue 2, April-June 2009).
Infralines paper on Transportation Tariff of HVJ and Dahej-
Vijaipur Pipeline.
Provisional gas transmission tariff for Reliance, GAIL networks
approved (Hindu Business Line April 20, 2010).
GAIL to benefit from PNGRB tariff revision(The Financial
Express October 28, 2011)
PNGRB Regulations GSR340(E),GSR594(E), GSR480(E),
GSR38(E), GSR769(E), GSR802(E)
PNGRB Regulations GSR807(E), GSR986(E).
-
8/3/2019 Ngb Ppt [Final]
26/27
Q & A
-
8/3/2019 Ngb Ppt [Final]
27/27