8 Pipeline News November 2017 • www.pipeline-news.com8 Pipeline News November 2017 • www.pipeline-news.com
recently awardedNEWProjects
GAS – The AmericasU.S.
DOMINION ENERGY – (11/17) Project: Line A Abandonment ProjectOperator: Dominion Energy Carolina Gas
Transmission LLCType: Project includes pipeline abandonment
to be done in three phasesLength: 60 milesDiameter: 10 inchesLocation: York County, SCDocket: CP17-3
KINDER MORGAN INC. – (11/17)Project: Utica Marcellus Texas PipelineType: Project includes abandonment and
conversion of 964 miles of natural gas service on the Tennessee Gas Pipeline, the construction of new pipeline and laterals to provide basin connectivity
Length: 320 milesLocation: Louisiana – TexasCapacity: 430 MbpdCompletion: 4Q 2018Comments: Project will be designed to transport
propane, butanes, natural gasoline, y-grade and condensate in batches along the system
NORTHERN NATURAL GAS CO. – (11/17)Project: Cedar Station UpgradeType: Project includes pipeline looping
Length: 7.8 milesDiameter: 20 inchesLocation: Dakota County, MN Docket: CP17-76
Contractor: Minnesota Ltd.Type: Contract includes pipeline looping for the
project
TALL OAK MIDSTREAM – (11/17)Operator: Tall Oak Midstream III LLC Project: East STACK systemType: Project includes construction of a natural
gas gathering systemLength: 50 milesDiameter: 12 to 20 inchesLocation: Hughes, Seminole, Pontotoc, Coal,
Pittsburg, Atoka and McIntosh counties, OK
Completion: 4Q 2017Comments: Tall Oak III expects to add a cryogenic
processing facility to its East STACK system and is engaged in discussions with the area’s producers to determine the best size for the plant and a strategic location that ensures flexible access to premium residue and NGL markets
TRANSCANADA CORP. – (11/17)Operator: Columbia Pipeline GroupProject: Central Virginia Connector ProjectType: Project includes replacement and upgrade
of three compressor units, installation of pipe and valve modifications, and installation of other appurtenant facilities
Length: .10 milesLocation: Greater Richmond, VACapacity: 45 MMDth/dCost: $6.3 millionDocket: CP16-493
NGLs – The AmericasU.S.
EPIC Y GRADE PIPELINE LP – (11/17)Owner 1: EPIC Y Grade Services LPOwner 2: EPIC Midstream Holdings LPProject: EPIC NGL PipelineType: Project includes construction of pipelineLength: 650 milesDiameter: 16, 20, 24 and 30 inchesLocation: Orla, Pecos, Crane and Midland counties,
TX - Corpus Christi, TX Capacity: 220 Mbpd (initial) 440 Mbpd (maximum)Completion: 1Q 2019Comments: Project will link producers’ NGL reserves in
the Permian and Eagle Ford Basins to Gulf Coast refiners, petrochemical companies and export markets, and will run side by side with the previously announced EPIC Crude Oil Pipeline for most of the route
OIL – The AmericasU.S.
EPIC PIPELINE CO. LLC – (11/17)Owner 1: Castleton Commodities InternationalOwner 2: Ironwood Midstream Energy PartnersOwner 3: TexStar Midstream LogisticsProject: EPIC Crude Oil PipelineType: Project includes construction of pipelineLength: 730 milesDiameter: 16, 20, 24 and 30 inchesLocation: Orla, Pecos, Crane and Midland counties,
TX - Corpus Christi, TX Capacity: 550 MbpdStatus: Project is undergoing an open seasonCompletion: 1Q 2019Comments: Project will link producers’ NGL reserves in
the Permian and Eagle Ford Basins to Gulf Coast refiners, petrochemical companies and export markets, and will run side by side with the previously announced EPIC NGL Pipeline
ORYX MIDSTREAM SERVICES II LLC – (11/17)Project: Oryx II PipelineLength: 220 milesDiameter: 16, 20 and 24 inchesLocation: Carlsbad, TX - Midland, TXCapacity: 400 MbpdCompletion: 4Q 2018Comments: Project will be constructed in phases and
will have the ability to expand based on shipper needs
OIL – InternationalMiddle East
KUWAIT OIL CO. – (11/17)Project: Al Zour RefineryType: Project includes construction of an oil
refining plant, which will be one of the largest refining plants worldwide
Location: KuwaitCapacity: 615 MbpdCost: $14.5 billionCompletion: 1Q 2019Comments: Project is part of the Clean Fuels Project to
upgrade, expand, and transform the 270 Mbpd Mina Abdullah and 466 Mbpd Mina Al Ahmadi refineries into an integrated 800 Mbpd merchant refining complex and permanently shut down the 200 Mbpd Shuaiba Refinery
Contractor: Larsen & Toubro Type: Project includes engineering,
procurement and construction for the refinery
Cost: $265 million
OFFSHORE – The AmericasCaribbean/South & Central America
STATOIL – (11/17)
PIPELINE News magazine is THE source for pipeline project information and construction news, worldwide with over 250 projects listed each month.
pipeline-news.com
PLN sixth.indd 1 7/6/2016 1:53:14 PM
www.pipeline-news.com • November 2017 • Pipeline News 9
Project: Peregrino Phase II ProjectType: Project includes the construction of a
fixed platform and associated subsea pipeline
Location: Campos Basin, offshore BrazilCapacity: 250 MMbblCost: $3.5 billionComments: Project will enable the extension of the
economic life of the Peregrino field
Contractor: TechnipFMC Type: Contract includes the engineering,
procurement, manufacturing, construction, installation and pre-commissioning of the rigid pipelines, flexible lines and the required subsea equipment for the project
OFFSHORE – InternationalAfrica
PETROSHOROUK – (11/17)Project: Zohr Field Development ProjectType: Project includes construction and
installation of an export pipeline and umbilicals
Diameter: 8 and 30 inchesLocation: offshore EgyptCompletion: 4Q 2018
Contractor: BHGESegment: Zohr Field Development Project Phase IIType: Contract includes project management,
engineering, procurement, fabrication, construction, testing and transportation of the subsea production system
Western Europe & EU Countries
HURRICANE ENERGY PLC – (11/17)Project: Lancaster Early Production System ProjectType: Project includes installation of production
flowlines, manifolds and the FPSO mooring system; and commissioning and ongoing production of oil via the FPSO
Location: offshore West ShetlandCapacity: 17 MbpdCompletion: 1Q 2019
Contractor: TechnipFMCType: Contract includes engineering,
procurement, construction and installation for the project
Asia Pacific
CHINA NATIONAL OFFSHORE OIL CORP. – (11/17)
Project: Lingshui 17-2 Gas DevelopmentType: Project includes construction and
installation of a subsea production system, including the installation of a subsea distribution unit south of the floater, a pipeline-end manifold and five other manifolds, three to be installed in the east and two in the west
Location: Qiongdongnan Basin, South China SeaCapacity: 2.3 Bcm/y (initial) 30 Bcm/y (maximum)Completion: 2020Comments: Gas will initially be sent to Hong Kong
through an existing pipeline for power generation, but will also target the Pearl River Mouth Delta region in Guangdong province
214-515-5000 • www.polyguard.com
Innovat ion based. Employee owned. Expect more.
RD-6 Fastest Coatingin the West
Contractors say there is no faster or trouble free girth weld coating system than Polyguard® RD-6®. On a recent project (12” pipe, FBE
mainline coating) a first time crew coated 150 joints on day one after training. On day two, after adding a driver to the 5 man crew, 201 joints were completed. No coating system has less installation problems than
Polyguard® RD-6®. Ask someone who has installed it.
One of thousands of projects using Polyguard RD-6 non-shielding coating. Our first was in 1988.
www.Polyguard.com/pipeline
®
Country
For more information, visit
Contractor: Offshore Oil Engineering Co.Type: Contract includes the front-end
engineering and design for the project
Contractor: Wood GroupType: Contract includes subsea and flow
assurance services