New York State Department of TransportationKendrick Road Bridge
Over I-390
Design-Build ProjectRequest for Qualifications
Informational MeetingJune 27, 2012
Kendrick Road BridgeAgenda
• Introductions and Opening Remarks• Project Overview • Questions and Answers
Peter RussellAtt: Kendrick Road Bridge
New York State Dept. of TransportationContract Management Unit, Non-Engineering
and Design-BuildPhone: 518-485-8620
Kendrick Road BridgeRules of Contact
Kendrick Road Bridge
Goals:• Improve Area Traffic Patterns Widen Existing Bridge
Provide Access Ramp to NB I-390
• Improve Bridge Service Life Improve Seismic Resistance Extend Deck Life
• Deliver Project Safely, On Schedule, On Budget, and Environmentally Compliant
Kendrick Road BridgeGeneral Scope of Work
• Widening Kendrick Road Bridge Structure Widen Abutments, Pier, Pile Foundations, Embankments, Approach Slabs and
Pavement Widen Bridge Deck, New Sidewalk, Lighting, Utilities, Railing Mill Top 2 Inches and Concrete Overlay Existing Deck• Provide Access Ramp to I-390 NB New Ramp, Pile Foundations, Piers and Superstructure Frame into Widened Steel Structure Replace Safety Shape and Noise Wall Acceleration Lane Pavement, Shoulder• Traffic Signal at Kendrick Rd./Ramp Intersection• Repair/Modify Canal Wall• Highway and Street Lighting• Provide WZTC
Kendrick Road BridgeGeneral Scope of Work (cont.)
• Other Work includes:• Bearing Replacement• Approach Guiderail Replacement• Possible Pedestal Repair/Modification• Possible Miscellaneous Steel Repair of Existing Structure• Steel Painting• Bike/Pedestrian Path Restoration and Improved Access• Coordination with Adjacent On-going Construction Project• Coordination with Canal Operations• Replace/Relocate Navigation Lights• Install/Replace/Relocate Traffic Signs and VMS Sign• Replace Existing Bridge Joints
Kendrick Road BridgeProcurement Schedule
Activity Due Date
Issue Draft RFQ June 20, 2012
Pre-SOQ Informational Meeting June 27, 2012
Final Date for receipt of Proposer’s questions July 25, 2012
Issue Date for Final Addendum to the RFQ and/or answers to Proposer’s questions
July 30, 2012
SOQ Due Date August 8, 2012
Short-List announced August 21, 2012
Issue Draft RFP August 22, 2012
Draft RFP Info Meeting August 29, 2012
Final RFP to Short-Listed Teams September 6, 2012
Proposal Due Date November 1, 2012
Selection/Award November 21, 2012
Execute Contracts December 13, 2012
Notice to Proceed December 14, 2012
Kendrick Road BridgeGeneral Information
• Lump Sum Design-Build Contract• Two Step Design-Build Procurement Process• Project Schedule
– Total Duration 18 Months +/-
• There will be a Payment Schedule provided in the RFP• Stipend Under Consideration by NYSDOT• Liquidated Damages may be imposed for missed
milestones and final completion• All Environmental Permits and ROW by NYSDOT• Construction Related Permits by Design-Builder
Kendrick Road BridgeQuality Control (QC)
• QC is Design-Builder’s Responsibility• Design-Builder shall appoint a QC Manager responsible for QC
Plan for both Design and Construction• Design QC shall be by the Designer in accordance with the QC
Plan• Construction Inspection shall be by an Independent
Engineering Firm (Hired by the Design-Builder)• Materials Testing shall be by an Independent Testing Firm or
Laboratory (Hired by the Design-Builder)• The Independent Testing Firm shall report to the Construction
Inspection Firm who shall report directly to the Department• Offsite Plant Quality Control will be performed by the
Department
Kendrick Road Bridge
Quality Assurance (QA)
• QA is Department’s Responsibility• The Department may perform QA on any of the
Design-Builder’s activities• The Department may utilize an independent
Consultant to perform QA of the Design-Builder’s Designs
Kendrick Road Bridge
SOQ Evaluation and Selection• Pass/Fail Evaluation Factors
– Legal– Financial– Proposal Responsiveness
• Quality Evaluation Factors– Organization and Key Personnel (35%)– Experience of the Firms (28%)– Project Understanding (20%)– Past Performance (15%)– Backlog/Capacity (2%)
Kendrick Road Bridge
Additional Information
• Responses to Proposer Questions will be posted on the Department Website
• Additional Reference Information to be Posted on Website:
Design Report, Bridge Inspection Report, “As Builts”, Borings
• Final Addendum will be issued by Monday, July 30, 2012 • There will be a Buy America Clause• There will be a DBE Participation Goal
Kendrick Road Bridge
Project Website
https://www.dot.ny.gov/main/business-center/DesignBuildProjects
Peter RussellAtt: Kendrick Road Bridge
New York State Dept. of TransportationContract Management Unit, Non-Engineering
and Design-BuildPhone: 518-485-8620
Kendrick Road BridgeRules of Contact