NEW SOUTH WALES SUPREME COURT Cargill … · referral of dispute under rules of ICC did not ......
Transcript of NEW SOUTH WALES SUPREME COURT Cargill … · referral of dispute under rules of ICC did not ......
NEW SOUTH WALES SUPREME COURT
CITATION: Cargill International SA v Peabody Australia Mining Ltd [2010] NSWSC 887
JURISDICTION:
Equity Commercial List
FILE NUMBER(S): 2010/009966
HEARING DATE(S):
10 June 2010 JUDGMENT DATE:
11 August 2010
PARTIES: Cargill International SA (Plaintiff) Peabody Australia Mining Ltd (Defendant)
JUDGMENT OF:
Ward J LOWER COURT JURISDICTION:
Not Applicable
LOWER COURT FILE NUMBER(S): Not Applicable
LOWER COURT JUDICIAL OFFICER: Not Applicable
COUNSEL: J Stevenson SC with D McLure (Plaintiff)
F Gleeson SC with K Day (Defendant) SOLICITORS:
Macpherson + Kelley Lawyers (Plaintiff) Freehills (Defendant)
CATCHWORDS:
COMMERCIAL ARBITRATION application under s 38(4)(b) of Commercial Arbitration Act 1984 (NSW) for leave to
appeal from Arbitrator’s award on grounds of manifest error of law or strong
evidence of error or in the alternative to remit questions of law to Arbitrator under article 34(2)(b)(ii) of Model Law
if former, whether leave to appeal should be granted under Commercial Arbitration Act
if latter whether denial of natural justice under the Model Law HELD Model Law applies
referral of dispute under rules of ICC did not operate as an ‘opt-out’ of Model Law under s 21 of the International Arbitration Act 1974 (Cth) – the decision in Eisenwerk
Hensel Bayreuth Dipl-Ing Burkhardt GmbH v Australian Granites Ltd [2001] 1 Qd R 461 is plainly wrong and should not be followed referral of dispute to ICC Rules did not indicate that parties intended to opt-out of
Model Law to extent it applied as the curial law or lex arbitri had Commercial Arbitration Act applied, threshold requirements for grant of leave not
satisfied discretion to grant leave would not have been exercised in any event no denial of natural justice
plaintiff’s application dismissed ADMIRALTY AND MARITIME JURISDICTION
whether dispute was one arising out of a maritime claim HELD dispute did arise out of a maritime claim so that exclusion agreement by adoption of
article 28(6) of the ICC Rules would not apply
LEGISLATION CITED: Admiralty Act 1988 (Cth) Commercial Arbitration Act 1984 (NSW)
International Arbitration Act 1974 (Cth) International Arbitration Amendment Bill 1988 (Cth)
International Arbitration Amendment Act 2010, No 97 (Cth)
CASES CITED: Aerospatiale Holdings Australia Pty Ltd v Elspan International Ltd (1992) 28 NSWLR
321 Agricultural & Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570 American Diagnostica Inc v Gradipore Ltd (1988) 44 NSWLR 312
Appleton Papers Inc v Tomasetti Paper Pty Ltd (1983) 3 NSWLR 208 Australian Securities Commission v Marlborough Gold Mines Ltd [1993] HCA 15;
(1993) 177 CLR 485 BCCI v Ali [2002] 1 AC 251 Beaufort Developments (NI) Ltd v Gilbert-Ash (NI) Ltd [1999] 1 AC 266
Beveridge v Whitton [2001] NSWCA 6 Bread Manufacturers of NSW v Evans [1981] HCA 69; (1994) 180 CLR 404
British Sugar plc v NEI Power Projects Ltd (1997) 87 BLR 42 CAL No 14 Pty Limited v Motor Accidents Insurance Board [2009] HCA 47; (2009) 239 CLR 269
Carbotech-Australia Pty Ltd & anor v Yates & 14 ors [2008] NSWSC 540 Carcione Nominees Pty Ltd & Anor v Western Australian Planning Commission &
Ors [2005] WASCA 56
Dranichnikov v Minister for Immigration and Multicultural Affairs [2003] HCA 26; (2003) 197 ALR 389;
Durayappah v Fernando (1967) 2 AC 337 Eisenwerk Hensel Bayreuth Dipl-Ing Burkhardt GmbH v Australian Granites Ltd
[2001] 1 Qd R 461 Equuscorp v Glengallan [2004] HCA 55; (2004) 218 CLR 471 Export Credits Guarantee Department v Universal Oil Products Co [1983] 2 All ER
205; [1983] 1 WLR 399 Farah Constructions Pty Limited v Say-Dee Pty Limited [2007] HCA 22; (2007) 230
CLR 89 Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407 Gatoil International Inc v Arkwright–Boston Manufacturers Metal Insurance Co [1985]
AC 255 Gett v Tabet (2009) 254 ALR 504; [2009] NSWCA 76
Gordion Runoff Limited v Westport Insurance Corporation [2010] NSWCA 57 Heilbrunn v Lightwood plc [2007] FCA 1518; (2007) 164 FCR 1 Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1
WLR 896 John Holland Pty Ltd aka John Holland Construction & Engineering Pty Ltd v Toyo
Engineering Corp (Japan) [2001] 2 SLR 262 Kirk v Industrial Relations Commission of New South Wales [2010] HCA 1; (2010) 262 ALR 569
Maggbury Pty Ltd v Hafele Australia Pty Ltd [2001] HCA 70; (2001) 210 CLR 181 Mobil Oil Australia Pty. Ltd. v Federal Commissioner of Taxation [1963] HCA 41;
(1963) 113 CLR 475 Natoli v Walker (1994) 217 ALR 201 Nishina Trading Co Ltd v Chiyoda Fire & Marine Insurance Co Ltd (The Mandarin
Star) [1968] 1 WLR 1325; [1968] 3 All ER 712; [1968] 2 Lloyd's Rep 47 Pacific Carriers v BNP Paribas [2004] HCA 35; (2004) 218 CLR 451
Port of Geelong Authority v The “Bass Reefer” (1992) 37 FCR 374 Promenade Investments Pty Ltd v State of New South Wales (1992) 26 NSWLR 203 Raguz v Sullivan [2000] NSWCA 240
Russell v Duke of Norfolk (1949) 1 All ER 109 Sharah v Healey [1982] 2 NSWLR 223
Shell International Petroleum Ltd v Gibbs [1983] 2 AC 375 Smith Ltd v H & S International [1991] 2 Lloyd’s Rep 127 Sunport Shipping Ltd v Tryg-Baltica International (UK) Ltd [2003] 1 Lloyd’s Rep 138
The “Catur Samudra” [2010] SGHC 18 The Kalliopi A [1988] 2 Lloyd’s Rep 101
The Radauti [1987] 2 Lloyd’s Rep 276 The Solon [2000] CLC 593 The Queen v Commonwealth Conciliation and Arbitration Commission: ex parte
Angliss Group (1969) 122 CLR The Zeus [1888] 13 PD 188
Toll v Alphapharm [2004] HCA 52; (2004) 219 CLR 165 Tradhol Internacional SA v Colony Sugar Mills Limited 2009 WL 3929893 (C.A.2(N.Y)) (20/11/09)
Trustees of Henry Smith’s Charity v AWADA Trading & Promotion Services (1983) 47 P&CR 607
Westcott v Hahn [1918] 1 KB 495
Westport Insurance Corporation v Gordion Runoff Ltd [2009] NSWSC 245
TEXTS CITED: Aronson, Dyer and Groves, Judicial Review of Administrative Action, 3rd ed, 2004
Barret-White S., and Kee C., “Enforcement of Arbitral Awards where the seat is Australia – how the Eisenwerk Decision might still be a sleeping assassin: (2007) 24(5) Journal of International Arbitration 515
Blackaby N., Partasides C., Redfern A., and Hunter M., Redfern and Hunter on International Arbitration, 5th edn, Oxford University Press, 2009
Davies S., “International Arbitration: when arbitral rules and procedural rules collide”, Australian Mining and Petroleum Law Association Yearbook, 2002 Chow P., “Issues in International Commercial Arbitration: Conflict between Model
Law and Arbitral Rules” (2003) 19 BCL 426 Croft and Fairlie, “The New Framework for International Commercial Arbitration in
Australia”, ACICA Conference, December 2009 Dicey, Morris and Collins, The Conflict of Laws, Sweet & Maxwell, 2006 and updating October 2009 edn
Gehle B., “The Eisenwerk decision is generally considered as bad law”, Vindobona Journal of International Commercial Law & Arbitration, 2009 13 VJ 251
Greenberg S., “ACICA’s New International Arbitration Rules” (2006) 23 (2) Journal of International Arbitration 189 Heydon, “Limits to the Powers of Ultimate Appellate Courts” (2006) 122 LQR 399
Lewison, The Interpretation of Contracts, 4th edn, Sweet & Maxwell, London, 2007 Megens P. and Cubitt C., “Arbitrators' perspective: the evolving face of international
arbitration - the past, the present and the future”, International Arbitration Law Review, 2010, 13(1), 1-7 Mustill and Boyd, Commercial Arbitration, 2nd edn, Butterworths, 1989
Pryles M., “Exclusion of the Model Law” [2001] Int ALR 175 Submissions made to the Commonwealth Attorney General, in response to the
Discussion Paper of 21 November 2008, by ICC Australia, ACICA, the Chartered Institute of Arbitrators, the NSW Bar Association, the Law Society of NSW, the Law Council of Australia, and the Victorian Bar
DECISION:
Plaintiff's application dismissed
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
COMMERCIAL ARBITRATION LIST
WARD J
WEDNESDAY 11 AUGUST 2010
10/009966 CARGILL INTERNATIONAL SA V PEABODY AUSTRALIA MINING LTD
JUDGMENT
1 HER HONOUR: This application relates to a partial award made by Mr David Jackson QC, as
arbitrator, on 7 December 2009 in a dispute arising out of a Standard Coal Trading Agreement made on
5 December 2005 between Carg ill International SA and Peabody Australia Mining Limited (then
known as Excel Coal Ltd) for the supply of coal to Carg ill. (For convenience, I will adopt the same
terminology as that used in the Arbitrator’s award and refer to the parties as Carg ill and Excel,
respectively.)
2 In the arbitration Excel claimed moneys outstanding in respect of certain coal deliveries made by it in
2009 at the end of the period covered by the agreement and Cargill counterclaimed for demurrage in
respect of the late delivery to it of a number of shipments of coal earlier in the course of the agreement
in mid 2007. Those disputes were referred to arb itration pursuant to the arbitration clause contained in
the parties’ agreement (clause 18.9). It is conceded that the arbitration conducted by Mr Jackson was
an international commercial arbitrat ion for the purposes of the International Arbitration Act 1974 (Cth)
(the Commonwealth Act).
3 The Arbitrator found in favour of Excel’s claim for USD299,822.74 (basically, for the amount of the
short payment by Cargill in 2009) and dismissed the whole of Cargill’s counterclaim, having held that
demurrage was not payable during the force majeure per iod (the duration of which had been one of the
matters in dispute between the parties). In so doing, the Arbitrator found, relevantly, that:
(a) the period of force majeure had commenced at 0815hrs on 8 June 2007 and ran through to
0700hrs on 25 June 2007;
(b) the notice of intention to claim force majeure given by Excel to Cargill on 13 June 2007
satisfied the requirement in clause 17.2 of the agreement that such notice be given as early as
practicable; and
(c) in any event, Cargill was not then entitled (by reason of the fact that it had reached an
enforceable agreement to resolve disputed rights, or had by its conduct waived or would be
estopped in equity from asserting any entitlements, in respect of demurrage fo r that part of the
force majeure period) to raise the question whether demurrage was payable in the period from
0815hrs on 8 June 2007 to 1800 hrs on 21 June 2007 (to which I refer as the estoppel/waiver
finding); though the Arbitrator went on to say that if Cargill had been so entitled he would
have concluded that demurrage was not payable in that period by reference to the conclusion
he had already reached in relation to the force majeure period.
4 There is no challenge to any of the Arbit rator’s findings summarised in (a) to (c) above (t hough Carg ill
does seek to challenge the conclusion that demurrage was not payable during the period of force
majeure as so found). Rather, Cargill challenges the Arbitrator’s December 2009 award by reference to
what is contended to be the Arbitrator’s failure to deal (or to deal correctly) with an alternative
argument said to have been put by Cargill to the Arbitrator in relation to its demurrage claim.
5 That alternative argument, in essence, is that the period between the commencement of conditions
amounting to force majeure (0815 on 8 June 2007) and the giv ing (at 1348 on 13 June 2007) of a force
majeure notice, whether or not that notice had been given as early as practicable (and hence whether
or not that notice was a valid and effective notice in compliance with clause 17.2 of the agreement),
should have been accepted as counting as “laytime” under the agreement.
6 If that alternative argument were to be correct, then it seems not to be disputed that laytime would have
continued to run from 0815 on 8 June 2007 and would have exp ired not long after that at 0956hrs on 8
June 2007. (On any view, this would mean, on the Arbitrator’s findings, that force majeure
commenced before, albeit only very shortly before, the exp iration of laytime.) Once layti me had
expired, the Iron Bradyn would have been on demurrage (and once on demurrage all time lost,
including time lost on account of force majeure, continues to count as demurrage).
7 Leaving aside for the present the import of Excel’s arguments (which were accepted by the Arbitrator)
based on waiver/estoppel or the like, Cargill contends that, had the Arbitrator found that the vessel
went on to demurrage as at 0956hrs on 8 June 2007, this would have meant that Carg ill’s counterclaim
for demurrage ran for the whole of the force majeure period from 8 to 25 June 2007.
8 In the present proceedings, Cargill seeks to challenge the Arbitrator’s award in one of two alternative
ways, depending on the conclusion which is reached as to an initial ju risdictional q uestion, that being
whether the arb itration is governed by the Commercial Arbitration Act 1984 (NSW) (the State Act), as
Carg ill contends, or the UNCITRAL Model Law in accordance with s 16 of the Commonwealth Act, as
Excel contends.
9 The first is under the State Act. Cargill seeks leave pursuant to s 38(4)(b) of the State Act to appeal
from the award (which requires it to establish that the State Act applies and then to satisfy the threshold
requirements of section 38, namely that there was an error of law that substantially affects the parties’
rights and either that there has been a manifest error of law on the face of the award or that there is
both strong evidence of error and the question is one which is likely to add substantially to the certainty
of commercial law).
10 Secondly, if (contrary to Cargill’s primary submission) the State Act does not apply, Cargill seeks an
order setting aside the award under article 34(2)(b)(ii) of the Model Law, on the basis that the award is
in conflict with the public policy of the State due to the failure of the arbitrator to address Cargill’s
alternative argument (that failure, it is said, amounting to a denial of natural justice).
11 In its Amended Summons in these proceedings, Cargill sought not only leave to appeal but also, if
successful in obtaining leave, a determination of the relevant questions of law upon the hearing of that
appeal. However, before me it was conceded that it was not appropriate to entertain any ap peal in the
context of the present application, having regard to what was said by Allsop P (with whom Spigelman
CJ and Macfarlan JA agreed) in Gordion Runoff Limited v Westport Insurance Corporation [2010]
NSW CA 57, from [103] . Accordingly, the relief now claimed by Cargill (in the event that the State
Act applies) is limited to the grant of leave to appeal.
12 I note that it is contended by Excel that, if the Model Law applies, then Article 34 of the Model Law
provides the exclusive recourse against an arbitral award in the present case and that Cargill is thus
precluded from apply ing for leave to appeal under s 38(4)(e) of the State Act because that provision is
inconsistent with the more limited form of recourse against an arbitral award available und er article 34
of the Model Law (and thus the State Act is, to the extent of the inconsistency, invalid by operation of s
109 of the Commonwealth Constitution). It was conceded by Mr Stevenson, though only for the
purposes of this application, that if there were found not to have been an agreement between the parties
to ‘opt out’ of the Model Law, then there would be a section 109 inconsistency between the two modes
of review and that Cargill could proceed for a review of the Arbitrator’s decision only unde r the
provisions of the Model Law.
13 Finally, in the event that the Model Law does apply, and Carg ill succeeds on its application to set aside
the award, then Carg ill requests that the matter be remitted to the Arbitrator pursuant to article 34(4) of
the Model Law for a determination by the Arb itrator o f what I will refer to as the Alternative
Argument.
Background Facts
14 The agreement (a standard form agreement developed by an entity known as globalCOAL and of
which there have been successive versions since May 2001) was for the delivery, over the period from
March 2006 to December 2008, of coal FOB (“free on board”) to three specified vessels at the port of
Newcastle. (There was some dispute as to the extent to which the SCoTA form of agreement was used
in the Australian coal industry in transactions for the sale of coal in and from Australia but it does not
seem to be disputed that it is and can be used for the sale of seaborne thermal coal; and that it is so used
in a percentage of trading contracts entered into in this country.) The version used by the parties in this
case was version 5a (the standard terms of which incorporated all revisions effective as at 0630 GMT
on 19 October 2005); however, there has been no subsequent change to the force majeure p rovisions in
the current version of the agreement (hence any determination of a point of construction on the force
majeure provisions of the earlier version has potentially wider relevance than for this case alone).
15 The coal deliveries were made by rail. Unfortunately, those deliveries which were due to take place in
June 2007 were delayed due to disruption to the rail infrastructure in the Hunter Valley caused by
severe storms in that month. The consequential delay in loading and departure of the three vessels in
question gave rise to a claim for demurrage by Carg ill. For the purposes of the present application, the
particular dispute between the parties relates only to the claim for demurrage in respect of the delivery
of coal to the MV Iron Braydn.
16 Carg ill’s claim for demurrage in respect of the late delivery of coal due in June 2007 seems first to
have been raised shortly after the coal was in fact delivered in Ju ly 2007. Excel relied upon the force
majeure provisions of the agreement to deny the claim for demurrage. There was some correspondence
between the two entities during the latter part of 2007 and early 2008 in relation to that claim.
17 The Arbitrator, in his award, referred to the communications between Excel and Cargill in relation to
that claim from 2007 onwards and expressed the opinion that, as at November 2007, the only matter in
issue between the parties in relat ion to the demurrage claim was whether it extended to the period
beyond 21 June 2007.
18 Relevantly, the Arbitrator noted that, by February 2008 (when Cargill issued an invoice for an
“undisputed amount” of demurrage, without prejudice to its claim for the balance, which was described
as the “disputed amount”), there was no hint that Carg ill was reserving to itself an entitlement to claim
demurrage for the period extending back before 21 June 2007. The so-called “disputed amount” (in
respect of which Cargill had reserved its position at that time) related to the claim for demurrage for the
period from 21 to 25 June 2007. It represents the USD amount for which Excel was ultimately
successful in the arb itration before the Arbit rator. However in relation to the “disputed amount”, the
Arbitrator noted (at [7]) that the effect of the correspondence between the p arties was that it was
accepted that Excel was not liable for demurrage in the period from 8 June to 21 June 2007. (Th is
becomes relevant when considering one of the threshold requirements for the grant of leave under the
State Act, as the Arbitrator’s estoppel/waiver finding, which is not challenged, has the effect that
Carg ill is precluded from revisiting any claim for demurrage at least in the period prior to 21 June
2007.)
19 No further steps seem to have been taken by Cargill, whether in relation to the overall demurrage now
claimed or for the “disputed amount”, until the term of the contract was coming to an end. At that
point, when Cargill made payment in respect of the final invoice issued by Excel for the later (2009)
coal deliveries it withheld an amount which included the “disputed amount” in respect of the 2007 coal
deliveries. Excel then made a claim for short payment of that sum (USD299,882.47), after which
Carg ill served revised invoices claiming demurrage for the whole of the period from 8 to 25 June 2007.
That claim was maintained by it by way of counterclaim in the arbitration (Excel being the moving
party in the arbitral proceedings).
20 The Arbitrator noted that in the arbitration p roceedings Cargill had put in issue every step whic h might
lead to an entitlement on the part of Excel to rely on the force majeure provisions. The issues before
the Arbitrator (which he observed were more numerous than would ordinarily be found in a
commercial arbit ration involving amounts of the kind there involved) included the time at which the
force majeure event had occurred; whether notice of the force majeure event had been given as early as
practicable, as required under the agreement; whether, under the agreement, as properly construed,
demurrage was payable during a force majeure period; and whether Cargill was estopped or otherwise
precluded from then asserting its claim for demurrage.
21 The issue which is the nub of the Alternative Argument (and which Cargill contends the Arbitrator
failed properly to address) relates to the calculation of the period of laytime under the agreement and,
in particular, whether (after commencement of force majeure) laytime continues to run up until the
time at which a force majeure notice (valid or otherwise) is given. As Senior Counsel for Cargill, Mr
Stevenson SC, accepted, the logical extension of this argument (if correct) is that unless a force
majeure notice is given simultaneously with the commencement of a force majeure event, then laytime
continues to run until such notice, valid or otherwise, is given. (By contrast, the effect of the
Arbitrator’s determination is that if a valid force majeure notice is given in compliance with clause 17.1
of the agreement, then clause 17.3 means that a party does not become liable for demurrage during the
period from the happening of the force majeure event the subject of that notice and that the giving of a
notice of intention to claim force majeure under clause 17.2 as early as practicable in the circumstances
means that time lost on account of force majeure does not count as laytime.)
22 The practical context in which this issue arose was as follows. As noted earlier, the coal was to be
delivered on board the Iron Bradyn at the port of Newcastle. The procedure for the delivery and
loading of coal involved the giving of a notice of read iness once the particular ship had arrived in port.
There was then a period of ‘turntime’ (12 hours), following which ‘laytime’ commenced.
23 Laytime (defined in clause 1.1) is the time allowed under the agreement for the loading of the vessel at
the delivery point, after which time demurrage (defined in clause 1.1 as the financ ial compensation
payable if the time used in completing loading was longer than laytime) became payable. Under the
agreement, laytime was to be calculated by reference to the nominated quantity of coal to be loaded on
the vessel according to the formula set out in clause 7.5 (namely, the number of hours or part thereof
calculated by dividing the tonnage of the shipment, expressed in metric tonnes, by the relevant “Cargo
Handling Rate” expressed in Metric Tonnes per hour). (In that regard, I note that Carg ill also asserts
that the Arbitrator made an error of law in placing reliance, for the purposes of addressing the argument
as to laytime, on the definition of Cargo Handling Rate including its reference to Weather Working
Days, a matter I consider in due course.)
24 In respect of the coal to be delivered in June 2007 to the Iron Bradyn, the issue between the parties is
now not as to the time of commencement of force majeure (although that was previously in issue);
rather the question is whether, in the circumstances, laytime continued to run after the commencement
of the force majeure period for the purposes of calculating when Excel became liable for demurrage.
25 It seems to be accepted that, but for the severity of the storms that occurred in early June 2007 and the
consequential disruption to the rail infrastructure over most of that month, laytime (the period in which
the Iron Bradyn was required to be loaded and after which demurrage would have been payable by
Excel) would have ceased (and the Iron Bradyn would have gone on demurrage) at 0956hrs on 8 June
2007. It also seems to be accepted that, had the Iron Bradyn been on demurrage prio r to the
commencement of force majeure, the operation of force majeure would not have affected Excel’s
liab ility for demurrage (it being broadly said that ‘once in demurrage, always in demurrage’, although
there seem to be some exceptions (not material in the present case) to that principle, as identified by the
Arbitrator at [170]).
26 Excel gave a notice of intention to claim force majeure of the kind contemplated by clause 17.2 at
1348hrs on 13 June 2007. (It had the day before given a notice of force majeure for the purposes of
clause 17.1 and in that regard I note that the agreement contemplated two separate force majeure
notices, only the second of which was in contention before the Arbitrator.) Whether the 13 June 2007
force majeure notice had been given as early as practicable for the purposes of clause 17.2 of the
agreement was in issue before the Arbitrator, who u ltimately found that it had. (Cargill had asserted
that the failure to give a notice as early as practicable rendered it of no effect.)
27 As noted earlier, the Arbitrator ult imately found that Excel d id not become liable for demurrage in
respect of the Iron Bradyn until 25 June 2007 (after the cessation of the force majeure period).
28 Carg ill’s principal submission in relation to the force majeure notice was that it was not valid or
effective, as it had not been issued as early as practicable in the circumstances. It does not seek the
challenge the Arbitrator’s finding in that regard. It relies now on the alternative submission it says it
raised, namely that, even if the notice was not held to be invalid or ineffect ive, nevertheless the “delay”
in its issue was to be taken into account when calculat ing whether laytime had exp ired and whether the
vessel had gone on demurrage (as Carg ill contended) on 8 June 2007. I consider in more detail below
the content of the submissions put to the Arb itrator. For present purposes I simply note that Cargill’s
complaint, in substance, is that the Arbitrator failed to deal at all (or dealt incorrectly) with the
Alternative Argument identified now as being to the effect that (irrespective of whether the force
majeure notice was a notice compliant with clause 17.2) laytime continued to run until a force majeure
notice was given. (As I understand it, this argument requires acceptance of the proposition that a notice
given as early as practicable in all the circumstances may nevertheless still be a notice the giv ing of
which was the subject of delay for the purposes of clause 17.2.)
29 Senior Counsel for Excel, Mr Gleeson SC, submits that, to the extent that the Alternative Argument
was put to the Arbitrator, it was rejected on the basis that the Arbitrator had concluded that notice was
given as early as practicable (and hence, as I understand the submission, it was not necessary for the
Arbitrator expressly to consider an argument predicated on a proposition antithetical to such a finding –
namely, that there had been a delay in the giv ing of the notice) (as to which it says there was no
manifest error of law) and, alternatively, to the extent that what Cargill is now seeking is to put an
argument which was not in fact put (or put clearly) before the Arbitrator, there cannot be said to have
been any denial of natural justice in the Arb itrator not having considered or expressly addressed the
argument. It is submitted that Cargill was not deprived of a fair hearing of the case as put by it at the
arbitration.
Issues
30 There are a number of jurisdictional and threshold issues which arise on the present application:
(i) Whether the agreement of the parties to refer any disputes to international arbitration und er the
rules of arbitration of the International Chamber of Commerce (the ICC Rules) constitutes an
agreement to opt out of the Model Law for the purposes of s 21 of the Commonwealth Act,
such that the State Act applies.
(ii) If the answer to (i) is yes, whether the dispute is one falling with in the Admiralty jurisdiction
of this Court (so as to override the effect of s 40 of the State Act, which precludes the grant of
leave to appeal where there is an “exclusion agreement” under which the parties have waived
recourse to the court in respect of their agreement).
(iii) If the answer to both (i) and (ii) is yes, whether the threshold requirements in s 38(5) of the
State Act for the grant of leave to appeal are satisfied (namely that (a) the determination of the
relevant questions of law could substantially affect the rights of one or more parties to the
arbitration agreement; and (b) there is either a manifest error on the face of the partial award
or there is strong evidence that the Arbitrator made an error of law and, if so, the
determination of that question may add or be likely to add substantially to the certainty of
commercial law).
(iv) If the answer to (i) above is no, and the Model Law applies, whether the Arbitrator fa iled to
address the Alternative Argument, so as to amount to a denial of natural justice (such that the
award was in conflict with the public policy o f Australia for the purposes of s 34 of the
Commonwealth Act).
(v) Whether, as a matter of discretion, the court should grant the relief sought (under the State Act
or the Model Law, as the case may be) if Cargill has otherwise made out an entitlement to
relief.
Summary
31 For the reasons set out below, I have concluded as follows on the above issues:
(i) I consider that an agreement by parties to refer any disputes to international arbitrat ion under a
particular set of procedural rules (as opposed to an agreement that the lex arbitri should be
other than that of the Model Law) does not constitute an implied agreement to opt out of the
Model Law for the purposes of s 21 of the Commonwealth Act (and that the decision in
Eisenwerk Hensel Bayreuth Dipl-Ing Burkhardt GmbH v Australian Granites Ltd [2001] 1 Qd
R 461 to the contrary is plainly wrong and should not be followed).
I am further of the view that the parties, when adopting the ICC Rules as the procedural rules
to govern their arbitrat ion in the terms in which they did, cannot be said to have done so with
the knowledge or intention that this would necessarily be construed as an opt out clause for
the purposes of s 21. While I would accept that the parties, represented by experienced legal
representatives as they were, should be taken to have entered into their agreement with
knowledge of the state of the law at that time (which was to the effect that a clause providing
for settlement of d isputes in accordance with ICC Rules had been construed as constituting an
implied agreement to opt out of the Model Law) the clause in fact adopted by the parties was ,
in my view, sufficiently distinguishable from the Eisenwerk clause to cast doubt on such a
result being the objective common intention of the parties at that time.
Accordingly, I find that there was not an agreement between the parties in writing to o pt out
of the Model Law for the purposes of the Commonwealth Act and that the Model Law applies.
(ii) Had I found otherwise on question (i) (ie, that the Model Law had been excluded and the State
Act applied), then I would have found that the dispute was one arising out of a marit ime claim
within the Admiralty jurisdiction of this Court, for the purposes of s 41 of the State Act, so as
to override the operation of the ‘exclusion agreement’ under which the parties waived
recourse to the court in respect of their agreement.
(iii) Had I found for Cargill on (i) above and held that the State Act applied, then given my finding
on (ii) above it would have been necessary to consider the threshold requirements set out in s
38(5) of the State Act for the grant of leave to appeal. In that regard, I am of the view that:
substantial effect on parties’ rights?
In light of the Arbit rator’s findings as to the existence of an enforceable agreement in
2008 in effect to compromise the claim for demurrage (or as to estoppel /waiver) it
seems to me that the determination of the relevant questions of law (assuming
Carg ill’s contentions on those questions were to be accepted) could at most permit
Carg ill to claim demurrage for the short period from 21-25 June 2007 and therefore
would have a lesser impact financially than Cargill has contended.
Excel’s argument, as I understand it, goes further than this and is that, because the
Arbitrator’s finding based on clause 17.3 was that demurrage was not payable during
the force majeure period and this finding is not challenged , any determination in
Carg ill’s favour of the Alternative Argument (i.e. even for the 21-25 June 2007
period) would not sound in any recovery by Cargill. The difficulty I have with that
proposition is that if Carg ill is correct on its interpretation of clause 7.11.2, and
laytime runs (in any particular case) from the period force majeure commences until
the giving of a notice of intention to claim force majeure under clause 17.2, then the
finding that demurrage was not payable by reason of force majeure over a period in
which the vessel was on demurrage would s eem to be inconsistent with this and,
therefore, any reconsideration of the clause 7.11.2 argument must necessarily entail a
review of the position under clause 17.3.
Therefore, I would have been prepared to accept that a determination of the
Alternative Argument was one which could have had a substantial effect on the rights
of Cargill (albeit a lesser financial effect than that for which Carg ill is contending).
(The determination of the weather working day issue is not, however, one which of
itself would be likely to have had a substantial effect on the parties’ rights, as
conceded by Mr Stevenson, and it alone would not have a substantial effect on the
parties’ rights.)
manifest error?
As to the alleged error the subject of the first ground of appeal, namely the
construction of clause 7.11.2 in relat ion to the running of laytime until any notice of
the kind contemplated in clause 17.2 is given, I am not satisfied that there has been
shown to be a manifest error on the face of the partial award. I consider that the
Arbitrator’s construction in this regard was one which was reasonably arguable. Any
error o f construction that might have been made in this regard (and I am by no means
suggesting that there was one) is not so obvious as to satisfy the test of manifest
error.
As to the alleged error the subject of the second ground of appeal, namely the
working weather days argument, again I am not satisfied that there has been shown to
be a manifest error on the face of the partial award. To the extent that the Arbitrator
construed clause 7.11.2 by reference to the definition of ‘Weather Working Days’ in
the definition of Cargo Handling Rate again I think such a construction was
reasonably arguable. A lthough the purpose of the definit ion of Cargo Handling Rate,
on its face, was to enable the calculat ion of the period of laytime to be allowed for
the purposes of a shipment, as opposed to the question whether the period of laytime
so calculated was to be suspended by reason of weather conditions or force majeure
in any particular case, I think the possibility that the definition could be construed as
having the operation for which Excel contended is not so unarguable as to make its
adoption by the Arbitrator a matter in which he made a manifest error of law.
I accept that, insofar as the Arbitrator took into account, when reaching his
conclusion on this point, the parties’ post-contractual conduct as evidence of their
understanding of the clause, as an apparent aid to construction, this would appear to
have been in error. However, the Arbitrator also reached his conclusion on this issue
by reference to the content or operation of the relevant specification schedule.
Therefore, I cannot find that his overall decision was one which was not otherwise
reasonably open to him. I consider that the construction adopted by the Arbitrator by
reference to the Cargo Handling Rate decision was one which was reasonably open
to be reached without reference to the parties’ understanding of the clause at all and
therefore it cannot be said that his conclusion on that point was a manifest error of
law.
Strong evidence of error/certainty of commercial law?
I am not satisfied that there is strong evidence that the arbitrator made an error of law
in relat ion to the first alleged error in relation to the construction of clause 7.11.2.
Had I been satisfied that there was strong evidence as to the making of an error of
law in the construction of clause 7.11.2 of the agreement, then I would have found
that the determination of that question might add or be likely to add substantially to
the certainty of the law in this area, since it relates to the construction of a standard
form document in use in the area of international commerce.
As to the second alleged error, given that the Arb itrator seems to have had regard, as
an aid to construction, to the parties’ post contractual conduct and that th is may have
affected the weight placed by him on the other matter which led to his finding that
the weather working day definit ion had a substantive negative operation (and was not
merely an integer in the definition of Cargo Handling Rate), I am of the view that
although there was not a manifest error of law in relat ion to the construction of
clause 7.11.2 by reference to the concept of weather working days, there is strong
evidence of an error of law in this regard. For the same reason as indicated abov e, I
would have found that the determination of this question was one that might add or
be likely to add substantially to the certainty of the law in this area.
Given the findings summarised above, even had I found for Cargill on the initial jurisdictiona l
question, I would not have found that it had established an entitlement to relief. I would not
have been satisfied that the threshold requirements for the grant of leave to appeal under the
State Act had been satisfied. (In relation to the second ground of appeal where I consider
there was strong evidence of an error of law, the determination of which might add or be
likely to add substantially to the certainty of the law in this area, the determination of that
question alone – ie, not coupled with the determination of the Alternative Argument - would
not have been likely to substantially to affect Cargill’s rights).
(iv) I am not satisfied that there has been a denial of natural justice. I am of the view that the
Arbitrator considered and dealt with the submissions as made to h im in relation to the
construction and operation of clause 7.11.2. I think there is some force in the suggestion by
Excel that what is now sought to be put by Cargill is a modificat ion or reformulation of the
alternative submission that was in fact put before the Arbit rator. If so, he cannot be crit icised
for having not dealt with it. However, even if it can be said that there has been no
modification or reformulation as such, I consider that the Arbitrator’s findings are consistent
with a conclusion that there is no operative delay for the purposes of clause 7.11.2 in
circumstances where there was a force majeure notice issued as early as practicable. The
Arbitrator raised the issue as to the effect of a notice not given timeously, during the course of
debate with Sen ior Counsel then appearing for Carg ill on the arbit ration. He was clearly
appraised of the submission that even if the notice was effective, and had been given as early
as practicable, there might be a continuation of laytime fo r the purposes of Cargill’s claim for
demurrage (and he seems to have dealt with this submission, implicitly, by rejecting the
premise that there could be such a notice which nevertheless amounted to delay for the
purposes of clause 7.11.2). The Arbitrator appears to have addressed the thrust of the
Alternative Argument put to him in his Part ial Award, even if he did not frame h is reasons in
the way in which the argument is now put. Carg ill cannot in my view be said to have been
deprived of a fair hearing in that regard.
(v) Had I been satisfied that the jurisdictional and threshold requirements for the grant of leave to
appeal under the State Act (or for the setting aside or revision of the award for denial of
natural justice under the Model Law) were met, I would nevertheless not have exercised
discretion in this case to grant leave to appeal on the question of law relating to the
construction of clause 17.2 (and hence the question as to the argument based on ‘weather
working days’ does not arise). In summary, it seems to me that it would be inconsistent with
the emphasis placed on judicial restraint in intervention of arbitrat ion awards such as this, to
permit what seems in essence to be a desire to re-litigate what had been a carefully argued
(and analysed) construction argument (particularly since the unchallenged estoppel/waiver
finding, and the doubt as to whether any inconsistency between the existing findings and those
to be challenged could be revisited in light of the clause 17.3 finding, could well mean that
any redetermination of the construction issues may now be of litt le or no practical benefit to
Cargill).
Reasons
32 I have outlined above the factual background to the present dispute. In summary, if the Model Law
does not apply then the relevant questions are whether Cargill has satisfied the threshold requirements
for the grant of leave to appeal under the State Act and whether, as a matter of discretion, leave should
be granted; if the Model Law does apply then the question is as to whether there has been a denial of
natural justice. I consider the issues for determination below.
(i) Is there an opt out agreement?
33 The UNCITRAL Model Law has the force of law pursuant to s 16 of the Commonwealth Act and
appears as schedule 2 to that Act. Section 21 of the Commonwealth Act provides that:
21 If the parties to an arb itration agreement have (whether in the agreement or in any
other document in writ ing) agreed that any dispute that has arisen or may arise
between them is to be settled otherwise than in accordance with the Model Law , the
Model Law does not apply in relation to the settlement of that dispute. (my emphasis)
Is it necessary that the opt-out agreement be express?
34 Section 21 requires that, to exclude the Model Law, there must be an agreement in writing but says
nothing as to whether that agreement must be express or can be implied from the terms of the parties’
written agreement.
35 Mr Gleeson placed emphasis on the fact that (as made clear in the Explanatory Memorandum to the
International Arbitration Amendment Bill 1988 (Cth)) s 21 is an ‘opt out’ provision. The notes to
Clause 7 of the Bill (relating to the then new s 21) stated that:
The Model Law is implemented on an ‘opt out’ basis by the amending legislation.
Accordingly, the provisions of the Model Law will apply to an international comme rcial
arbitration … unless the parties agree otherwise, either in the arbitrat ion agreement or in any
other agreement in writing.
There is nothing in that exp lanatory note to require that there be an express exclusion, as opposed to an
implied exclusion, of the Model Law. That said, in the Outline section of the Explanatory
Memorandum, it is said that the Bill will amend the Act, relevantly, to implement the UNCITRAL
Model Law “on an ‘opt out’ basis so that its provisions will apply unless the parties expressly exclude
it”(my emphasis).
36 Mr Gleeson submits that what the adoption of an opt out procedure makes clear is that the parties must
turn their minds to the issue and do something (in writing) expressly to exclude the Model Law and
that, in the absence of an express exclusion, they should not be taken impliedly to have done so. It
seems to me that it by no means follows that an implied agreement to exclude the Model Law could not
be the result of the parties having turned their minds to the question of the law which should govern
their arbit ration and adopted a different law. The adoption, if that be the case in any particular
agreement, of a d ifferent curial law suggests that the parties have indeed turned their minds to the
question of what law should govern their arbitrat ion. The fact that they may have provided for this in
an indirect way, by way of adoption of a particular system of law as the lex arbitri, rather than by the
direct exclusion of the lex arbitri which would otherwise apply does not seem to me to be any the less
effective a means of indicat ing their intention in that regard. Apart from the brief reference in the
outline to the Explanatory Memorandum (not reiterated in the specific notes to the relevant clause) to
an express exclusion of the Model Law, there is nothing in that Memorandum or in the terms of s 21
itself to preclude the operat ion of an implied agreement as a means of exclusion of the Model Law,
provided that that implied agreement can be discerned from the terms of a written agreement between
the parties.
37 The implication of an agreement to exclude the Model Law must surely arise if the parties in their
written arbitration agreement (or any other document in writing) have chosen a wholly inconsistent
system of law to govern their arbitration. In those circumstances, I am not persuaded that (had they
done so in this case) this would not have been sufficient to enliven the operation of s 21. I do not read
s 21 as requiring that the agreement to ‘opt out’ be in express terms, as opposed to an agreement which
can be inferred from a written agreement. (To the extent that Eisenwerk , to which I refer below, is
authority for the proposition that the relevant opt out agreement can be one which is an implied
agreement, then I would not conclude that it was plainly wrong. Where I differ from the conclusion
reached in Eisenwerk is as to whether the choice of procedural rules to govern an arbitration amounts
to an implied exclusion of the lex arbitri.)
38 Was there an implied agreement between the parties in this case to settle any disputes otherwise than in
accordance with the Model Law?
39 Clause 18.9 of the agreement provided as follows:
In respect of matters which are to be referred to an Expert pursuant to the foregoing provisions
of this clause 18 any appeals from the Experts decisions, and other disputes or claims arising
out of or in connection with a Transaction and/or this Agreement, including any questions
regarding its existence, valid ity or termination, shall be referred to International Arbitration
under the Rules of Arbitration of the International Chamber of Commerce with any arbitrat ion
to be heard in Sydney in the English language before three arbitrators (my emphasis)
40 The agreement to refer disputes for arbitration under the ICC Rules, though with the modificat ion that
only a single arbitrator was to be appointed in this case, was confirmed (after the particular d isputes
had arisen) in an exchange of correspondence between their respective lawyers on 15 A pril 2009
(Cargill’s solicitor having earlier suggested that an ICC arbit ration was not necessary and that the
arbitration, by defau lt, would be governed by the Commonwealth Act (as well as the State Act) and the
Model Law – see p 138 vol 4 Ex A).
41 The question arises, therefore, as to whether the parties’ agreement to “refer” the d ispute for arbitrat ion
“under” the ICC Rules (terminology which in my view may well connote something other than what
would be comprised by an agreement for “settlement” of the dispute “in accordance with” any
particular system of law) constitutes an implied agreement to opt out of the Model Law for the
purposes of the Commonwealth Act. (It seems to me that there is a not immaterial d ifference in this
context between the respective clauses in Eisenwerk and in the present contract, in that the reference to
referral of the dispute for arbitration under the ICC Rules more clearly draws attention to the
procedural aspects or ru les governing the arbitrat ion rather than the ultimat e resolution or
determination of the dispute.)
Eisenwerk
42 Not surprisingly, Mr Stevenson relies (in support of his submission that the parties’ agreement to adopt
the ICC Rules constitutes an implied agreement to opt out of the Model Law for the purposes of the
Commonwealth Act), on the decision of the Queensland Court of Appeal in Eisenwerk , a case
determined in 1999. There, the part ies’ arbitrat ion agreement included a provision in sim ilar (though
not relevantly identical) terms to that contained in the arbitration agreement in the present case before
me, that clause being as follows:
Any dispute arising out of the Contract shall be finally settled, in accordance with the Rules of
Conciliat ion and Arbitration of the International Chamber o f Commerce, by one or more
arbitrators designated in conformity with those Rules.
43 In Eisenwerk , the question whether the parties had, by including the above clause, “opted -out” of the
Model Law for the purposes of s 21 of the Commonwealth Act arose on an appeal from the refusal by
Fryberg J to grant a stay, under s 7(2) of the Commonwealth Act, of court proceedings brought by the
respondent to the appeal and his Honour’s decision to restrain the appellant from pursuing an ICC
arbitration. Pincus JA (with whom Thomas JA and Sheperdson J agreed) took judicial notice of the
existence and content of the ICC Rules and construed the parties’ agreement fo r any dispute to be
‘finally settled in accordance with ICC Rules’ as an agreement that the dispute would be settled
otherwise than in accordance with the Model Law. His Honour thus held that the Model Law did not
apply. Pincus JA said at [11]-[12]:
It might be thought that the question whether a clause such as that contained in the contracts
which are in issue is effective to exclude the Model Law is a matter of some importance, for
the arbitration clause in the present case conforms to an international standard; making
allowances for variances, perhaps due to translation. cl. 13.1 of the General Conditions,
quoted above, is an adoption of the clause recommended by the ICC for use by those wishing
to have their disputes resolved under its rules. The 1988 ICC Rules as set out in Redfern and
Hunter, Law and Practice of International Commercial Arbitration, (2nd., 1991) state the
recommended clause as follows:
“All disputes arising in connection with the present contract shall be finally settled
under the Rules of Conciliation and Arbitration of the International Chamber of
Commerce by one or more arbitrators appointed in accordance with the said Rules.”
If Australian Granites’ argument is right, use of this recommended clause is insufficient to
avoid the, surely highly inconvenient, result that the parties are bound to both a Model Law
arbitration and an ICC arbitration . And the former would not be an arb itration under the
aegis of an established international organisation, as the latter is; it should be noted that the
Model Law has not been widely adopted. Only 19 countries had adopted it, to the month of
February 1998, and those countries did not include Germany: see A. Sh ields, “The
development of a uniform framework for international arbitrat ion” (1998) 16 The Arbitrator
217 at 224.
In my opinion the better view is that, by expressly opting for one well-known form of
arbitration, the parties sufficiently showed an intention not to adopt or be bound by any quite
different system of arbitration, such as the Model Law. It follows that, insofar as Australian
Granites relies upon (and succeeded below on) the argument that Article 8 of the Model Law
precluded the grant of a stay of the action in favour of Hensel, after delivery of its defence,
that view must be rejected. In consequence, the provision of domes tic law which governs the
right to a stay is s. 7(2) of the Act, quoted above. (my emphasis)
44 Eisenwerk has since been followed by the Supreme Court of Singapore in John Holland Pty Ltd aka
John Holland Construction & Engineering Pty Ltd v Toyo Engineering Corp (Japan) [2001] 2 SLR
262.
45 Eisenwerk stands as authority for the proposition that, by expressly adopting a different ‘form of
arbitration’ (there, that being the ICC Rules), parties will be taken to have shown a sufficient intention
not to adopt the form or system of arb itration provided fo r under the Model Law (and that this is
sufficient to amount to an opt-out agreement for the purposes of the Commonwealth Act).
46 What the Court of Appeal in Eisenwerk did not appear expressly to address was the question whether,
by providing for their d isputes to be settled by arbitration in accordance with the ICC Rules, the parties
had done any more than to adopt a particular set of arbitral rules, rather than the lex arbitri or curial law
as the law governing any such arbitration.
47 It is the conceptual distinction between the lex arbitri and the procedural rules of an arb itration on
which Mr Gleeson bases his primary submission that the decision in Eisenwerk is plain ly wrong and
should not be followed by this Court. Mr Gleeson submits that where the Queensland Court of Appeal
erred in Eisenwerk was that it was not taken to, or failed to appreciate, the critical d istinction between
the lex arbitri or curial law governing an arbitrat ion (which, if the seat of arb itration is within Australia
is likely, unless excluded by the parties, to be the Model Law) and the procedural rules of the
arbitration (which may be chosen by the parties themselves as a matter of contrac t to govern the
operation of the arb itration itself). (The Queensland Court of Appeal does appear, however, to have
been taken in argument to the fact that the provisions of the Model Law were capable of being varied
by agreement between the parties and that the ICC Rules were capable of applying as a partial
modification of the Model Law, leaving untouched other provisions of the Model Law such as the
recognition and enforcement provisions – at least so far as reference is made to the summary report,
appearing in the published reasons, of Counsel’s submissions on that appeal.)
Deference to be accorded to Eisenwerk decision
48 The need for me to be convinced (in o rder to accept Mr Gleeson’s submission that Eisenwerk should
not be followed) that the conclusion reached in Eisenwerk is plain ly wrong arises from the deference
that I am bound, as a first instance judge, to accord to decisions of intermediate appellate courts and,
here, to the interpretation there placed on s 21 of the Commonwealth Act by the Queensland Court of
Appeal and its application having regard to the clause there being considered. The High Court in
Australian Securities Commission v Marlborough Gold Mines Ltd [1993] HCA 15; (1993) 177 CLR
485, at 492, has said that:
[U]niformity o f decision in the interpretation of uniform national leg islation … is a
sufficiently important consideration to require that an intermediate appellate court -- and all
the more so a single judge -- should not depart from an interpretation placed on such
legislation by another Australian intermediate appellate court unless convinced that that
interpretation is plainly wrong.
49 To similar effect was the statement in Beveridge v Whitton [2001] NSWCA 6, by Heydon JA (as his
Honour then was), with whom Mason P and Powell JA agreed, apply ing that approach also to well-
considered dicta of intermediate appellate courts, at [30].
50 In Gett v Tabet (2009) 254 ALR 504; [2009] NSW CA 76, the Court of Appeal considered (at [274]-
[293]) the meaning of the phrase “plainly wrong”, in the context of the question as to when an
intermediate appellate court ought to depart from its own decisions in relation to a matter of common
law. At [283], the Court (comprised of Allsop P, Beazley and Basten JJA) noted that the adverbs
“plainly” and “clearly” in the context “bespeak the quality of the error or the level of conviction of
error that must be perceived” (and do not limit the circumstances of departure from previous authority
to those in which the error is patent or obvious or easily perceived). Their Honours concluded (at [294]
– [295]):
The phrases “plainly wrong” or “clearly wrong” can be understood to focus on at least one or
more of the following attributes of a ruling:
(a) the fact of error is immediately (in the sense mentioned in [283] above) apparent
from reading the relevant judgment;
(b) the strong conviction of the later court that the earlier judgment was erroneous
and not merely the choice of an approach which was open, but no longer preferred
(compare Chamberlain and Clutha), and
(c) the nature of the error that can be demonstrated with a degree of clarity by the
application of correct legal analysis.
In our view, the first possibility is liable to be h ighly subjective and should not be required,
where the other two possibilities are satisfied. The existence of (b) and (c) is a precondition to
the exercise of the power to depart from earlier authority.
51 At [301], their Honours said:
The phrase “plainly wrong” (or any like phrase) tends to focus attention on the jurisprudential
nature and character of the error and underly ing principle or course of authority or the
conviction as to the existence of the error. Factors considered by Aickin J in Queensland v
Commonwealth and in the joint judgment in John, on the other hand, suggest that there are
other considerations bearing on the question as to whether the earlier decision should be
overruled, erro r having been exposed to the requisite degree of conviction. These
considerations are properly invoked because they are relevant to the underlying principles of
certainty, predictability and transparency upon which the theory of precedent is founded. As
explained by Nettle JA in RJE (at [104]), there must be “compelling reasons” for departure
from earlier authority, whether in the same court or in a court of co -ordinate jurisdiction, a
phrase encompassing both jurisprudential and practical considerations.
52 The position stated in Marlborough was reiterated in Farah Constructions Pty Limited v Say-Dee Pty
Limited [2007] HCA 22; (2007) 230 CLR 89 (where the High Court also emphasised the need for
regard to be had to “long-established authority and seriously considered dicta of a majority of this
Court”, at [134]). (In CAL No 14 Pty Limited v Motor Accidents Insurance Board [2009] HCA 47;
(2009) 239 CLR 269, at [50], the High Court rejected the suggestion that Farah had altered the
doctrine of precedent (in a d ifferent regard) by expanding the principle in Marlborough to the common
law generally (the application of the relevant principle to the common law being well-established).)
53 In Justice Heydon’s article “Limits to the Powers of Ultimate Appellate Courts” (2006) 122 LQR 399,
at 415 n 114), when considering the factors which may affect the weight to be attributed by an ultimate
appellate court to its own dicta, Justice Heydon referred, among other things, to various circumstances
in which that dicta may have fallen from the court otherwise than in the course of considered argument
on the point. By analogy, the weight to be accorded to the conclusion in Eisenwerk may potentially be
affected by the fact that it does not appear from the court’s reasoning th at attention was drawn to the
distinction between the lex arbitri and the procedural rules of an arbitration, as such.
Other authorities
54 In his submissions, Mr Stevenson noted that there has been no demur by other courts to the reasoning
in Eisenwerk (though having been cited on seven or eight occasions on other points); that there is no
judicial expression of opin ion that it is wrong; and that there is no example of any court in Queensland
or any other State refusing to fo llow it. Nevertheless, I was not taken to any authority in which the
question as to whether Eisenwerk should be followed in this respect had been expressly argued before
the court and hence had been the subject of considered review.
55 In addition to the absence of express authority overturning or rejecting Eisenwerk , Mr Stevenson
pointed to the decision of Cole J in Aerospatiale Holdings Australia Pty Ltd v Elspan International Ltd
(1992) 28 NSWLR 321. There, his Honour (at 325) considered an arb itration clause which referred
disputes to arbitration “by a single arb itrator appointed at the request of either party by the President for
the time being of the Institution of Engineers of Australia in accordance with the Commercial
Arbitration Act 1984 (NSW)”. His Honour held that, by referring to the State Act, the parties had
agreed that the Model Law was not to apply for the purposes of s 21 of the Commonwealth Act.
56 Relevantly, Mr Stevenson submitted that, to the extent that his Honour was of the view that a specific
reference to a different set of arbitration procedures to the Model Law involved exclusion of it, this
decision supports the result in Eisenwerk . However, in Elspan, the reference was to an arbitrat ion
under the State Act itself (and therefore can be seen as a choice of the lex arbitri, not an adoption of a
particular set of procedural rules as such) and it seems to me to be distinguishable from Eisenwerk in
this regard.
57 Similarly, although reference was made by Mr Stevenson to the decision of Giles CJ Comm D (a s his
Honour then was) in American Diagnostica Inc v Gradipore Ltd (1988) 44 NSW LR 312, there again
the relevant choice was of the State Act (albeit in conjunction with the UNCITRAL Arbit ration Rules).
There, Giles CJ found (at 323) that an agreement to use the UNCITRAL Arb itration Rules for an
arbitration in conjunction with the “Arbitrat ion Act current in New South Wales, Australia” was a
sufficient agreement for the purposes of s 21 of the Commonwealth Act to opt out of the UNCITRAL
Model Law. Again, this decision is distinguishable by reference to the particular wording of the clause
in question. I agree with the submission by Mr Gleeson that American Diagnostica and Elspan
(neither of which expressly referred to or applied Eisenwerk ) do not support the reasoning in Eisenwerk
as in both cases what the parties expressly chose was the State Act (as the lex arbitri). I also note that
in American Diagnostica (at 324), h is Honour recognised that the lex arbitri, as the law governing the
conduct of the arbitration, went beyond matters of procedure, saying that:
Although the law governing the conduct of the arbitration (the lex arbit ri) is said to be
concerned only with procedural matters, it goes beyond, for example, the produ ction of
documents or the order of witnesses. The appointment, removal, and replacement of
arbitrators, time-limits, interim relief, consolidation of arbit rations, representation before the
arbitrator, the form and validity of the award, and the finality o f the award, are amongst the
matters which can fall within the lex arbitri.
Is reasoning of Eisenwerk plainly wrong?
58 Is the conclusion reached in Eisenwerk plainly wrong, such that it would be open for me to find that the
adoption by the parties of the ICC Rules did not necessarily amount to an agreement to opt out of the
Model Law (assuming for this purpose, though I think that such an assumption is doubtful, that the
respective arbitration clauses can be said to be relevantly indistinguishable)?
59 Mr Gleeson’s principal contention, as noted earlier, is that the adoption of arbitral rules by the parties
does not of itself constitute an opting out of the Model Law for the purposes of s 21 of the
Commonwealth Act and that in this regard the decision in Eisenwerk is plainly wrong and should not
be followed.
60 What was the reasoning underlying the conclusion in Eisenwerk? Although reference was made by
Pincus JA, first, to the perceived high level of inconvenience which would follow from a result tha t the
parties are bound to both a Model Law arb itration and to an ICC arbitrat ion; secondly to the fact that
the former would not be an arbitration under the aegis of an established international organization, as
the latter would be; and, thirdly, to the fact that the Model Law had not then been widely adopted, the
basis for the conclusion that there had been an implied opting out of the Model Law was the perceived
inconsistency and irreconcilability as between the provisions of the Model Law and those of t he ICC
Rules. In that regard, as noted above, had the provisions in fact been wholly irreconcilab le and had the
systems in question performed the same function in relat ion to an arbitration, then I would accept the
logic on which the Court of Appeal proceeded. However, fo r the reasons set out below that does not
appear to be the case.
61 Turning first to what I might describe as the peripheral or background matters raised (as to
inconvenience and the like), it seems to me that the perceived inconvenience of there being two sets of
rules is overstated in that many of the arbitral rules provided for under the Model Law are rules which
apply in default of any choice to the contrary by the parties. Therefore, as submitted by Mr Gleeson,
there is no reason why the two systems could not operate together (and, I might add, any inconvenience
in reconciling which of any two potentially applicable ru les was intended to apply, apart from being
something of the parties’ own making, would thus be readily able to be resolved by ignoring all default
rules which covered a matter dealt with in the ICC Rules). As to the second matter, it is not suggested
how the question whether an arbitration would or would not be under the aegis of an established
international organization is relevant in pointing to the intention of the parties whether or not to opt a
form of arbit ration not under the aegis of any such organization. Third ly, apart from the question of
how this would be relevant in any event, the breadth of acceptance worldwide of the Model Law is now
very different from that which was the case in 1999. (Mr Gleeson noted that, to the extent that it is
relevant, more than 60 countries have now adopted the Model Law, referring to statistics available
from the UNCITRAL website.)
62 Mr Gleeson, recognising the high test that must be met in order to come to such a conclusion, put
forward a series of propositions as to why Eisenwerk should be held to have been wrongly decided,
each in essence turning on the distinction between the lex arbitri governing an arbitrat ion and the
procedural ru les applicab le to an arb itration. In summary, those propositions were that the Court of
Appeal in Eisenwerk had:
(i) (this being the fundamental focus of the criticis m of this decision) failed to appreciate and
apply the distinction between the lex arbitri or curial law governing the conduct of the
arbitration (being the legislat ive framework in which the arbitration takes place, here the
Model Law unless excluded) and the procedural rules applicable to an arbitration by
agreement between the parties (here, the ICC Rules);
(ii) failed to appreciate that the ‘opt out’ provision in s 21 o f the Commonwealth Act allows the
parties to substitute an alternate law under which their d ispute will be resolved and is not
concerned with the parties’ choice of procedural rules;
(iii) failed to appreciate that the Model Law is a form of lex arbitri, not a different system of
arbitration procedure from that comprised by the ICC Rules and hence the Model Law
provisions can logically apply to arb itrations administered by a variety of permanent arbitral
institutions, such as the ICC (M r Gleeson referring there to Art icles 2(a), (d) and (e) of the
Model Law);
(iv) failed to take into account that the Model Law contains provisions which allow part ies a wide
degree of autonomy or control over how their d ispute is to be resolved (referring , in particular,
to Article 19 of the Model Law, the importance of which has been stressed in other contexts as
noted below) including the right (under Article 2(d) of the Model Law) to authorise a third
party (which would include an institution such as the ICC) to determine the procedure to be
followed and contemplates that the parties may include in their arbitrat ion agreement matters
as to arbitration rules (institutional or otherwise) (there referring to Article 2(e) of the Model
Law), this autonomy being subject only to the mandatory provisions of the Model Law
concerning the conduct of the proceedings or the making of an award (referring to Article 18);
(v) incorrectly assumed that the Model Law and the procedural rules as chosen by the parties (or
as determined by the arb itrator) cannot operate in conjunction with each other (the contrary
position being contemplated by Article 19, which allows the parties to determine the rules of
procedure to govern their arbitrat ion); (in support of which proposition Mr Gleeson referred
to the Report of the Secretary General, UNCITRAL Secretariat, Analytical Commentary on
draft text of a Model Law on International Commercial Arbitration , presented to the United
National Commission of International Trade Law, 18th
Session, Vienna, 3-21 June 1985, at
44-45 which identified Article 19 as the most important provision of the Model Law in that
the parties are thereby given a choice as to the procedures to be adopted for their arbitration);
(vi) incorrectly suggested that the provisions of the Model Law and the ICC Rules are inconsistent
and that such inconsistency is irreconcilab le (in particular, Mr Gleeson noted that the example
given by Pincus JA as to the differences in respect of provisions concerning the number and
identity of arbitrators under the Model Law and ICC Rules (comparing Article 10 of the
Model Law and s 18 o f the Commonwealth Act and Articles 1 and 8 of the ICC Rules) d id not
support the conclusion that there was any inconsistency in light of the fact that Articles 10(1)
and 11(2) o f the Model Law provide that the parties are free to determine the number of
arbitrators and to agree upon a procedure of appointing the arbitrator or arbitrators); and
(vii) wrongly assumed that there would be a high level of inconvenience if an arbitrat ion were to be
held in accordance with the ICC Rules but was subject to the Model Law as the lex arbitri.
63 As noted by Mr Gleeson, insofar as the Model Law deals with procedural matters, the provisions in the
Model Law generally apply by way of default or fall back provisions in the absence of specific
agreement by the parties or where the p rocedural rules selected are unable to apply for some reason
(referring by way of example to the wording “unless otherwise agreed by the parties” used in Articles
3, 11(1), 17, 24, 26 and 29) or the statement that “the parties are free to agree” on certain matters in
Articles 10, 11(2), 13, 19, 20, and 22). This illustrates the autonomy given to parties under the Model
Law and the ability to reconcile the two sources of potential ru les applicable to an arbitrat ion
conducted under the Model Law as the lex arbitri but adopting procedural rules from another source.
64 Apart from the express recognition in the Model Law that the parties may choose the procedural rules
of a part icular institution (Articles 2(a) and (d) of the Model Law) and hence contemplates that another
institution may have a procedural role to p lay in the conduct of the arbitration, the Model Law reserves
to the court the power to intervene where an institution fails to perform its procedural function and thus
contemplates that the Model Law may have a supervisory or supplementary role over and above the
role accorded to other institutions by reason of the parties’ contrac tual choice of rules. In this regard,
Mr Gleeson referred to the procedure for the appointment of arbitrators outlined in Article 11(4)(c) of
the Model Law.
65 As the parties’ freedom to choose the procedural rules governing the arbitration is expressed by Article
19 to be subject to any mandatory provisions of the Model Law, Mr Gleeson submitted that the parties’
choice of p rocedural rules cannot of itself constitute ‘opting out’ of the Model Law for the purposes of
s 21 of the Commonwealth Act and that the choice of procedural rules does not involve the parties
selecting any alternate law (such as the lex arbitri) under which their dispute will be resolved.
66 It seems to me that the critical d istinction is as to whether the opt out provision contemplated by s 21 is
one which focusses on the adoption of the Model Law as the lex arbitri or simply as the source of the
procedural ru les for the arbit ration. In its terms, clause 18.9 of the arb itration agreement in the p resent
case expressly focusses on the adoption of particular procedural rules (by reference to the ICC Rules,
those being of a procedural nature). That does not necessarily involve any adoption of a different
system of law as the lex arbitri (which, as exp lained in Dicey, Morris and Collins, The Conflict of
Laws, Sweet & Maxwell, 2006, at [16-035], is the law chosen by the parties to govern arbitral
procedure that is, the procedural law of arbit ration (at [16-039]) from that which would apply under the
Model Law, nor is it inconsistent with the application of the Model Law as the lex arbitri. (This is also
referred to as the ‘curial law’ of the arb itration (see Mustill and Boyd, Commercial Arbitration, 2nd
edn,
Butterworths, 1989, at 64). Ord inarily, the lex arbitri is that of the seat of the arbitration for the
reasons noted in Raguz v Sullivan [2000] NSWCA 240, where Spigelman CJ and Mason P (with whom
Priestley JA agreed) said at [93]:
The seat of arbitration is not necessarily where it is held, although where the parties have
failed to choose the law governing the conduct of the arb itration it will prima facie be the law
of the country in which the arb itration is held because that is the country most closely
connected with the proceedings: see James Miller & Partners Ltd v Whitworth Street Estates
(Manchester) Ltd [1970] AC 583 at 607, 609, 616; Black Clawson International Ltd v
Papierwerke Waldhof-Aschaffenburg AG [1981] 2 Lloyd’s Rep 446 at 453-454; Bank Mellat v
Helliniki Techniki SA [1984] QB 291 at 301.
67 Recently, Dicey and Morris in their updating companion (October 2009) to the 2006 edit ion, have
stated (affirming the position that parties can choose procedural ru les different to the seat of the
arbitration) (at [16-034]) that:
Where parties have expressly chosen the seat of their arb itration , it is the courts at the seat
which have exclusive supervisory jurisdiction to determine claims for a remedy going to the
existence or scope pf the arbitrator’s jurisdiction, or to allegations of bias.
Difference between the lex arbitri and procedural rules of the arbitration
68 In the private international law context, there are a number of laws which may govern different aspects
of or relat ing to an arb itration. Those may be summarised as being the proper law governing the
substantive rights of the parties in respect of their underlying dispute (here the proper law of the
contract), the proper law of the arbitration agreement (which may differ from the proper law of the
contract itself) which governs the obligation of the part ies to submit their d isputes to arbitration and to
comply with any arbitral award made in the context of that arb itration, and the lex arbitri or curial law
governing the conduct of the arbitration of any particular dispute referred to in accordance with the
arbitration agreement (to which I have referred above). (See Mustill and Boyd, Commercial
Arbitration, at 61-62)
69 As explained by Dicey and Morris (at [16-035]) the lex arbitri is the law chosen by the parties to
govern arbitral procedure that is, the procedural law of arbitrat ion (at [16-039]). The extent to which
the parties may choose the lex arbitri (or the extent to which such a choice may be given recognition by
the law applicable at the seat of the arbitration) will be determined in much the same way as in other
contexts the courts determine when to recognise and give effect to a choice by the part ies of the proper
law of their contract. However, the lex arbitri is recognised as being distinct from the proper law of the
contract (Smith Ltd v H & S International [1991] 2 Lloyd’s Rep 127, at 129-130; American
Diagnostica, at 324-328; Blackaby N., Partasides C., Redfern A., and Hunter M., Redfern and Hunter
on International Arbitration, 5th
edn, Oxford University Press, 2009, at 3.39-3.43). It is also to be
distinguished from the procedural ru les by which, in accordance with the lex arbitri, the parties may
agree that the arbitration will be conducted.
70 Giles CJ in Comm D in American Diagnostica, referred to the lex arbitri as the law governing the
conduct of the arbitration (at 324), and explained that the scope of the lex arbitri (or curial law of the
arbitration) goes beyond matters of procedure:
Although the law governing the conduct of the arbitration (the lex arbit ri) is said to be
concerned only with procedural matters, it goes beyond, for example, the production of
documents or the order of witnesses. The appointment, removal, and replacement of
arbitrators, time-limits, interim relief, consolidation of arbit rations, representation before the
arbitrator, the form and validity of the award, and the finality of the award, are amongst the
matters which can fall within the lex arbitri.
71 The learned authors go on to say, at 62;
The curial law governs: the manner in which the reference is to be conducted; the procedural
powers and duties of the arbitrator; questions of evidence; the determination of the proper law
of the contract .
72 Dicey and Morris note (in a passage substantially in the same form from the 1987 edn which was
approved by Giles CJ in American Diagnostica, at 325) that the choice of the seat of arbitrat ion is in
effect the choice of the lex arbitri to govern the arbitrat ion but that there remains the potential, after
choice of the lex arbitri for parties to choose a different set of procedural rules governing the
arbitration to those of the seat, save for the mandatory rules that will still apply according to the
relevant law of the seat, (at [16-035]);
Party autonomy in the choice of the law to govern arbitral procedure (the lex arb itri) is
expressed in the choice of a seat for the arbitrat ion. This “seat” is in most cases sufficiently
indicated by the country chosen as the place of the arb itration. For such a choice of place not
to be given effect as a choice of seat, there will need to be clear evidence that the parties (or
the arbitrators, if so authorised by the arties) agreed to choose another seat for the arbitra tion;
and that such a choice will be effect ive to endow the courts of that country with jurisdiction to
supervise and support the arbitration. The concept of the “seat” of the arbitrat ion is a juridical
concept. The legal “seat” must not be confused with the geographically convenient place
chosen to conduct particular hearings (there citing Naviera Amazonica)
The courts of the seat will have sole supervisory and primary supportive function in relation to
the conduct of the arbitration save where there has been an express and effective choice of a
different lex arbitri, in which event the role of the courts of the seat will be limited to those
matter specified by their own law as internationally mandatory, is non-derogable, even where
an express choice of a different lex arbitri has been made by the parties.
73 The dual source of procedural rules in the context of arb itration is referred to by Dicey and Morris (at
[16-030]) as follows:
The dual character of procedural law in arbitrat ion is reflected in the dual source of procedural
rules. All of the major international arbit ral institutions have their own procedural rules,
which will apply to arbitrat ions conducted under their auspices (save to the extent that the
parties expressly provide otherwise). From the perspective of the part ies to an international
arbitration (and of the arbitral institution) these rules will form the primary procedural code.
Even where the parties have chosen ad hoc rather than institutional arbitration, the parties may
select a set of procedural rules such as the UNCITRAL Arbitration Rules.
The other source of procedural law for arb itration is those provisions of national law which
deal specifically with arbitration – the lex arbitri properly so called. Such rules may perform
one of three functions: (a) directory: they may provide a source of arbitral rules which may be
applied to the extent that the parties have not expressly chosen their own rules of procedure
(whether by drafting specific ru les into their arbitration agreement or more commonly by
choosing a set of standard procedural rules, such as those of the ICC or LCIA or the
UNCITRAL Arbitrat ion Rules); (b) mandatory: national law may also however place
mandatory limits on the autonomy of the parties in arbitrat ion, by prescribing certain matters
of arb itral procedure from which no contracting out is permitted; (c) supportive; national law
may extend the support of national court processes to arbitration, by making availab le to the
parties certain judicial procedures to deal with matters which are outside the scope of the
arbitrators’ authority, since they require the coercive powers of the State.
74 Thus, as recognised in American Diagnostica and explained in the academic text referred to above it is
possible for part ies to choose different procedural rules to those applying under the lex arbitri of the
seat of the arbitration, though the mandatory procedural rules of the seat of the arbitration will apply
notwithstanding any attempt by the parties to preclude their applicat ion by choice of a different set of
procedural rules.
75 In American Diagnostica his Honour said:
That there can be a lex arbit ri different from the law of the country in which the arbitration is
held is implicit in what was said in James Miller & Partners Ltd v Whitworth Street Estates
(Manchester) Ltd, Black Clawson International Ltd v Papierwerke Waldhof-Aschaffenburg
AG and Bank Mellat v Hellenik Techniki SA referred to above. The place where the arbitrat ion
is held is not necessarily conclusive of the seat of the arbitrat ion, as is obvious when one
considers a peripatetic arbitrat ion, and in Naviera Amazonica Peruana SA v Compania
Internacional de Seguros del Peru , Kerr LJ said (at 120):
“There is equally no reason in theory which precludes parties to agree that an
arbitration shall be held at a place or in country X but subject to the procedural laws
of Y. The limits and implications of any such agreement have been much discussed
in the literature, but apart from the decision in the instant case there appears to be no
reported case where this has happened. This is not surprising when one considers the
complexities and inconveniences which such an agreement would involve.”
Can agreement on a lex arbit ri different from the law of the country in which the arb itration is
held entirely escape the local rules? The foundation for agreement on a lex arbitri is that all
arbitrations are consensual, party autonomy being the cornerstone of modern arbitrat ion, and
so Grad ipore said that the consensual nature of the arbitration permitted American
Diagnostica and Gradipore to agree to exclude the Act if it would otherwise have applied to
their arbitrat ion. But there must be a limit to the parties' freedom, because their choice of the
place of their arb itration may carry with it application to the arbitration of the law of that place
according to its terms so as to govern the conduct of the arbit ration. The freedom is to choose
the place. So far as the local rules compulsorily apply and are inconsistent with the chosen lex
arbitri, they can not be put aside by agreement that they do not apply.
76 In addition, his Honour said (at 328);
There is thus some judicial and other guidance contrary to Gradipore's submission. In
principle, party autonomy does not mean complete freedom to exclude a system of law, or
particular elements of a system of law, from the relationship between the parties. Confining
attention to statutory law, if the statute on its proper construction and with regard to the
legislative power of the legislature applies to the parties and their conduct of the arbitration,
and expressly or by necessarily implication can not be excluded by agreement, the agreement
of the parties to exclude it will count for nothing. If the statute applies to the arbitration, a
prohibition against contracting out cannot be avoided by contracting out of the prohibition.
77 Another means of distinction between the differing sources of law concerning how the arbitration is
governed is made by Mustill and Boyd (at 52) in their more recent 2001 Companion to the Second
Edition published in 1989. Mustill and Boyd distinguish between external and internal rules. The
internal rules being those rules (as chosen by the parties – whether they be rules formulated by
institutions such as UNCITRAL Arbitrat ion Rules, or ru les as set out in individual state legislation) and
the national laws of a state in which the arbitration is seated, which as a matter of that state’s law will
apply to the arbitration. Mustill and Boyd suggest that strictly speaking the internal rules are not laws
at all, but are simply the procedures by which, (as a matter of contractual force) the parties have agreed
(either implicitly or explicitly) to be bound.
Academic and other criticism of Eisenwerk
78 It is fair to say that the decision in Eisenwerk has been roundly criticised both for policy reasons (there
being concerns as to the impact it would have on the willingness of parties to engage in international
arbitration with Australia as the seat of the arbitration) and as to the perceived failure to recognise the
distinction between the lex arbitri and the procedural rules governing arbit ration (that being a
consistent theme of the criticism levelled at the decision).
79 The existence of academic criticism of a judicial decision does not, of course, compel the conclusion
that the judgment is plain ly wrong (although that does appear to be the academic consensus) but it
supports the contentions made by Mr Gleeson to that effect and, of some relevance to the question as
to the parties’ intention, it indicates the extent to which the parties or their legal advisers might be taken
to have been aware, as at 2005, of the state of the common law fo llowing the Eisenwerk decision in
relation to the effect of adoption of procedural ru les such as the ICC Rules on the question as to
whether there was an implied exclusion of the Model Law.
80 In particular, I was referred by Mr Gleeson to the following:
(i) Pryles M., “Exclusion of the Model Law” [2001] Int ALR 175, where reference is made to the
“fundamental juristic difference” between the arb itral procedural law and the arb itral ru les
selected by the parties to an arbitration, at 176, and the author expresses the view that the
selection of a set of arbitral ru les (which, insofar as they apply by virtue of the parties’
agreement, are contractual and not legislat ive in character) does not constitute the selection of
a different arbitral p rocedural law even though there may be some overlap between the two
(noting that the law governing the arbitral procedure will deal with some matters beyond the
authority of the parties to settle in the rules).
(ii) commentary in relation to, and legislative amendments in Singapore to overcome the effect of,
the John Holland decision (s 15(2) of the International Arbitration Act (Singapore) and Chow
P., “Issues in International Commercial Arb itration: Conflict between Model Law and Arbitral
Rules” (2003) 19 BCL 426, at 427 and footnote 6).
(iii) Greenberg S., “ACICA’s New International Arb itration Rules” (2006) 23 (2) Journal of
International Arbitration 189 (at p191) Greenberg expresses the view that the choice of a set
of institutional arb itration ru les where the seat of the arb itration is in a Model Law jurisdiction
does not impliedly exclude the application of the Model Law given that Article 19(1) of the
Model Law expressly allows the parties to do so.
(iv) Barret-White S., and Kee C., “Enforcement of Arbitral Awards where the seat is Australia –
how the Eisenwerk Decision might still be a sleep ing assassin: (2007) 24(5) Journal of
International Arbitration 515 (at 523-525), where (in a section entitled “Why Eisenwerk
should not be followed” (at 324) the authors address the argument that the Model Law and
ICC Rules are reconcilable and place emphasis on the default operation of the former.
(v) Justice Croft and DG Fairlie, “The New Framework for International Commercial Arbitrat ion
in Australia”, in a paper presented at the ACICA Conference, December 2009, in which the
authors note that the proposed amendments to the Commonwealth Act (now enacted in
Schedule 1 of the International Arbitration Amendment Act 2010, No 97 (Cth)) are intended to
clarify that the adoption of arbitral ru les by the parties does not constitute an ‘opting out’ of
the Model Law (at 5).
(vi) Submissions made to the Commonwealth Attorney General, on the Review of the
Commonwealth Act, in response to the Discussion Paper of 21 November 2008 – by ICC
Australia, ACICA (at 10), the Chartered Institute of Arbitrators (at 8), the NSW Bar
Association (at 7-10), the Law Society of NSW (at 2), the Law Council of Australia (ADR
Committee) (at 6-7), and the Victorian Bar (at 13) (all favouring amendment of the
Commonwealth Act to reverse the Eisenwerk decision).
81 Much of that criticis m, it can be seen, was published in the period after the part ies entered into their
agreement (and therefore cannot be said to have informed the minds of their lawyers in relation to the
Eisenwerk issue as at the date of entry into the agreement). There was, however, at least one other
published criticis m of the decision in the interim to which the respective legal advisers may have had
regard (that by Davies S., “International Arbitration: when arbitral ru les and procedural rules collide”,
Australian Mining and Petroleum Law Association Yearbook , 2002, at 649, which again, at 653)
criticises Eisenwerk for failing to take into account the fundamental ju rid ical difference between
arbitral rules on the one hand and the procedural law of an arbitration on the other (at 659).
82 More recently, the volume of dissent has increased with that expressed by Gehle B., “The Eisenwerk
decision is generally considered as bad law” (Vindobona Journal of International Commercial Law &
Arbitration 2009 Article The Arb itration Rules of the Australian Centre for International Commercial
Arbitration [FNa1] 13 VJ 251) and by Megens P. and Cubitt C., “Arbitrators' perspective: the evolv ing
face of international arb itration - the past, the present and the future”, International Arbitration Law
Review, 2010, 13(1), 1-7, at 6, where it was observed that the Eisenwerk decision was not only “at
odds with international practice and the objectives of the model law” but had, together with the John
Holland decision, “caused instant consternation in international arbitration circles” (my emphasis).
83 The above criticis m confirms the v iew I would in any event have formed (based on the analysis set out
earlier in these reasons) that there is a distinction between adoption of procedural rules and the
application of the lex arbitri and that since the Model Law (assuming that be the lex arbitri of an
arbitration the seat of which is in Sydney, as it was in this case) permits the adoption of rules other than
those for which it would in default of an alternative choice have provided, the choice by the parties of
the ICC Rules to apply in their arbitration would not of itself constitute an opting out of the Model
Law.
Conclusion
84 The distinction between the lex arbitri (or the laws of the seat relat ing to arbitrat ion) and procedural
rules which may be adopted consensually by the parties (subject to any mandatory provisions of the lex
arbitri) to govern the conduct of the arbitration (or internal rules, to adopt the terminology used by
Mustill and Boyd) is well recognised and is expressly accommodated under the Model Law.
85 Insofar as Article 19 of the Model Law allows the parties to adopt a set of procedural rules different
from those which would otherwise apply under the Model Law, it cannot be said that the Model Law
and ICC Rules are inconsistent and irreconcilable. In the context of an arbitration the seat of which is
in Australia, as a matter of law of the lex arbitri (that is the Model Law, as enacted by the
Commonwealth Act) the parties are permitted, within the framework of the Model Law provisions, to
apply some or all of another set of procedural rules to apply to their arbitration.
86 If, under the lex arbitri, the parties are able to opt out whether entirely or in part of the application of
the Model Law, then the decision to adopt ICC Rules as the procedural rules governing the arbitration
(which are not inconsistent with the application of the Model Law as the lex arbitri) cannot logically
amount to an implied agreement of the parties to have their disputes settled otherwise than in
accordance with the Model Law. Rather, they can be seen to be electing to utilise the options available
under the Model Law to choose different procedural rules to apply within the overall context of the
Model Law provisions. Any “opting out” which is (as seems to be the case here) limited to the
selection of the internal or procedural rules governing the arbitrat ion, is consistent with the Model Law
itself.
87 Accordingly, I am not persuaded that, simply by referring their d isputes to arbitration under the ICC
Rules, the parties in the present case could be said to have impliedly opted out of the Model Law for
the purposes of s 21 of the Commonwealth Act.
88 Given that the terms used in the p resent arbitration agreement are different from those considered in
Eisenwerk , it is possible that the above conclusion could be reached simply by distinguishing the facts
here from those in that case. That would arguably be the case if it could be said that the phrase “settled
otherwise than in accordance with the Model Law” in the arbitra tion clause there under consideration
operated as a selection of the lex arbitri and not the procedural rules of that Model Law. However,
insofar as the reasoning in Eisenwerk appears to be based on the perceived inconsistency between the
respective systems of procedural rules, it seems to me that it is by no means clear that it can be
distinguished in that fashion.
89 Mr Stevenson submitted that the question whether Eisenwerk was plainly wrong was one that I should
not entertain on an application for leave to appeal in the present case. However, in both Sharah v
Healey [1982] 2 NSWLR 223, at 227 and Appleton Papers Inc v Tomasetti Paper Pty Ltd (1983) 3
NSW LR 208, McLelland J (as his Honour then was) (dealing with a decision of the English Court of
Appeal in the first case and with conflict ing non-binding statements in the High Court and the House of
Lords in the latter case) emphasised the duty of the trial judge when faced with persuasive but non -
binding authority or dicta to which the judge was bound to accord great weight and respect. In
Appleton, his Honour said (at 218):
My duty in these circumstances, as I conceive it, is to decide for myself, invidious task as that
may be, what the relevant principles are or should be, obtaining such assistance as I can from
the persuasive authorities to which I have referred . In this connection I refer to what I said in
Sharah v Healey [1982] 2 NSW LR 223, at 227, 228 [namely that it is the duty of this Court to
apply the law as (rightly or wrongly) it finds it to be, not as another court states it to be in a
manner by which this Court is not bound], and to the passage from the speech of Lord
Dunedin in Leeds Industrial Co-operative Society Ltd v Slack [1924] AC 851, there quoted.
(my emphasis)
90 It seems to me that my duty, notwithstanding that this is an application for leave to appeal, is to
consider the application of Eisenwerk on the question as to whether there should be found (by referral
of the dispute to arbitration under the ICC Rules) to have been an implied agreement of the parties to
opt out of the Model Law – that being a necessary question to determine in considering the first of the
jurisdictional issues posed before me. In circumstances where there is a doubt as to how far, if at all,
the relevant arb itration clauses can be distinguished (and it was submitted for Cargill that they were
relevantly indistinguishable) it seems to me (consistent with my duty) necessary that I must form a
view on the correctness of the decision in Eisenwerk .
91 The conclusion to which I have come is that the decision does not properly recognise or give effect to
the distinction between the lex arbitri and the procedural ru les governing an arbitration. I am not
satisfied that there is any inability to reconcile the application of the Model Law with the adoption of
the ICC Rules as the procedural rules to govern the conduct of the parties’ arbitration. Accordingly,
insofar as Eisenwerk is authority for the proposition that the adoption by the parties of procedural rules
(such as the ICC Rules) to govern the conduct of the arbitration of their disputes amounts of itself to an
implied agreement to opt out of the Model Law (and while conscious of the respect to be accorded to
decisions of an intermediate appellate court such as this), I have formed the view that that decision is
plainly wrong and is one which should not be followed by this Court.
Is there otherwise an effective opting-out of the Model Law?
92 Mr Stevenson submitted that, even if I were to form the view (as I have) that Eisenwerk is plainly
wrong and should not be followed in this case, the objective intention of the parties must have been to
exclude the Model Law since the parties (represented as they have been by experienced practitioners in
this area) should be taken to have intended (knowing the effect of the Eisenwerk decision as it applied
at the time) to opt out of the Model Law for the purposes of s 21 of the Commonwealth Act. This
submission is put on the basis that the proper construction of a contract is to be determined by what a
reasonable person in the parties’ position would have understood it to mean in the circumstances
existing at the time of the contract’s execution (reliance being placed in that regard on Pacific Carriers
v BNP Paribas [2004] HCA 35; (2004) 218 CLR 451, at 461-462; Equuscorp v Glengallan [2004]
HCA 55; (2004) 218 CLR 471, at 483; Toll v Alphapharm [2004] HCA 52; (2004) 219 CLR 165, at
179; Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407, at [14]; [305]; [322]).
93 Thus, Mr Stevenson submits that the contracting parties should be taken to have known, when entering
their agreement in 2005, the effect of their adoption of the ICC Rules, by reference to what had been
decided in Eisenwerk in 1999 (and reported in the authorised reports from 2001) (BCCI v Ali [2002] 1
AC 251; Lewison, The Interpretation of Contracts, 4th
edn, Sweet & Maxwell, London, 2007, at
[4.06]). That being part o f the common law of Australia (Kirk v Industrial Relations Commission of
New South Wales [2010] HCA 1; (2010) 262 ALR 569, at [99]), it is said that any party wishing to
avoid the effect of Eisenwerk could easily have done so (say, by noting in the arb itration agreement
that the Model Law is to apply notwithstanding the adoption of the ICC Rules or by noting that the
parties are not to be taken to be entering into an agreement to opt out of the Model Law for the
purposes of s 21 of the Commonwealth Act). Not having done so, it is submit ted in effect that the
parties should be taken to have intended the result which would have followed had Eisenwerk been
correctly decided and followed in this Court.
94 In response, Mr Gleeson emphasised that “opting out” means “real opting out” and not ed that the
standard form contract entered into by the part ies in 2005 was the then version of a form of agreement
in place before the Eisenwerk decision was reported. It is submitted that there was no settled practice
or procedure arising from the Eisenwerk decision per se and that, having regard to the comment and
discussion on that case, one could not say that it was accepted as a general princip le that the proper
construction of s 21 would always lead to the conclusion that choice of arb itral rules of an institution is
an opting out of model law.
95 In the absence of a settled practice, and any evidence of any shared or mutual intention of the parties to
opt out of the result in Eisenwerk, Mr Gleeson argued that reliance on Lewison did not avail Cargill. In
that regard, I would have been inclined to think that experienced practitioners in the area of arbitrat ion
would have been well aware by 2005 of the risk that, by reference to Eisenwerk , an adoption of ICC
Rules might lead to the conclusion that they had opted out of the Model Law and to have made express
provision to indicate (if that be the case) that that was not the intention. The fact that a standard form
of contract, the subject in its various iterations of copyright from an earlier date, had been used does
not seem to me to detract from such a conclusion.
96 Whilst the House of Lords in BCCI v Ali did not expressly consider the relevance of case law upon the
interpretation of contracts, Lord Hoffman did there make the following observations (at [37]-[39]):
I agree with my noble and learned friend that the first issue raises an ordinary question of
construction. What would a reasonable person have understood the parties to mean by using
the language of the document against all the background which would reasonably have been
available to them at the time? But I regret that I cannot agree with his answer. It appears to me
to give too little weight to the actual language and background and to rely unduly upon the
expressions of judges used in other cases dealing with different documents.
The background is however very important. I should in passing say that when, in Investors
Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896, 913, I
said that the admissible background included "absolutely anything which would have affected
the way in which the language of the document would have been understood by a reasonable
man", I did not think it necessary to emphasise that I meant anything which a reasonable man
would have regarded as relevant. I was merely saying that there is no conceptual limit to what
can be regarded as background. It is not, for example, confined to the factual background but
can include the state of the law (as in cases in which one takes into account that the parties are
unlikely to have intended to agree to something unlawfu l or legally ineffective) or proved
common assumptions which were in fact quite mistaken. But the primary source for
understanding what the parties meant is their language interpreted in acco rdance with
conventional usage: "we do not easily accept that people have made linguistic mistakes,
particularly in formal documents". I was certainly not encouraging a trawl through
"background" which could not have made a reasonable person think that the parties must have
departed from conventional usage.
97 Statements to this effect had been made by Lord Hoffman previously in Investors Compensation
Scheme Ltd v West Bromwich Building Society [1998] 1 W LR 896, at 912; [1998] 1 All ER 98, at 114.
Both cases have been cited by the High Court in Maggbury Pty Ltd v Hafele Australia Pty Ltd [2001]
HCA 70; (2001) 210 CLR 181, where the following observations were made by Gleeson CJ, Gummow
and Hayne JJ (at [11]):
Interpretation of a written contract involves, as Lord Hoffmann has put it : ‘the ascertainment
of the meaning which the document would convey to a reasonable person having all the
background knowledge which would reasonably have been available to the parties in the
situation in which they were at the time of the contract’. That knowledge may include matters
of law, as in this case where the obtaining of intellectual p roperty protection was of central
importance to the commercial development of Mr A llen's ironing board (my emphasis,
citations omitted).
98 Lewison refers to the decision of Scrutton LJ in Westcott v Hahn [1918] 1 KB 495, at 511, where h is
Lordship said:
A flood of authorities in and since the seventeenth century were poured out upon the Court in
which somewhat similar words to this covenant had received a construction from the Courts.
In my view, however, the first thing to be done is to endeavour to ascertain from the words the
parties have used in this case their actual intention. If they have used words which by a settled
course of authority have acquired a technical meaning, the court will give effect to those
authorities; but, unless this is so, it appears to me very unprofitable to consider what Courts
have thought that other words in other documents meant and to see which reported case has
the lease differences from the present.
99 Reference was also made to the decision of Waller LJ in British Sugar plc v NEI Power Projects Ltd
(1997) 87 BLR 42, at 50, where his Lordship said:
Once a phrase has been authoritatively construed by a court in a very similar context to that
which exists in the case in point it seems to me that a reasonable businessman must more
naturally be taken to be having the intention that the phrase should bear the same meaning as
construed in the case in point. It would again take very clear words to allow a Court to
construe the phrase differently.
100 Lewison goes on to state:
Even if one might consider that the parties to the contract themselves might not have had the
previous decisions of the Courts in mind when making their contracts, their lawyers will have
done so in deciding whether or not to pursue a dispute subsequently.
citing The Radauti [1987] 2 Lloyd’s Rep 276 CA; The Kalliopi A [1988] 2 Lloyd’s Rep 101; The Solon
[2000] CLC 593 as authority for this proposition.
101 However, the comment is also made in Lewison (at 103, o f the 3rd
edn) that where an erroneous
decision has departed from orthodoxy, and a contract is entered into while the erroneous decision was
thought to represent the law, that will not provide a reason for applying the erroneous decision to the
contract in question, there cit ing Shell International Petroleum Ltd v Gibbs [1983] 2 AC 375; Trustees
of Henry Smith’s Charity v AWADA Trading & Promotion Services (1983) 47 P&CR 607.
102 Shell International supports the view that, simply because contracts may have been drafted on the
assumption that a specific legal interpretation of a phrase made in a case is good law and b inding, a
court will not necessarily be p recluded from later overru ling a particular interpretation placed upon that
phrase (at 390 – 391). There, the House of Lords in considering the meaning to be attributed to a
particular phrase in a contract, considered whether an earlier decision (Nishina Trading Co Ltd v
Chiyoda Fire & Marine Insurance Co Ltd (The Mandarin Star) [1968] 1 W LR 1325; [1968] 3 All ER
712; [1968] 2 Lloyd's Rep 47) construing the same phrase in a manner differently from that which their
Lordships considered was the correct interpretation should be overruled despite the uncertainty that
may be created in relation to agreements drafted on the basis of or with the interpretation placed on the
phrase by the erroneous decision of The Mandarin Star in mind.
103 Lord Roskill was of the view that, despite the uncertainty created in relation to contracts drafted on the
assumption that The Mandarin Star was good law, this was not (although it could be in other cases) a
relevant consideration when determining whether to overrule the decision. It should be noted that in
Shell International, the House of Lords did not expressly consider whether it should, despite the
overruling of and subsequent non-application of the erroneous legal interpretation made in The
Mandarin Star, nonetheless conclude that such an interpretation was intended by the parties (who
would have known of the interpretation and by adopting such a phrase migh t have impliedly intended
that such an interpretation apply). It was submitted before their Lordships that it should be taken that
the parties intended the decision to apply to the contract, on the basis that it was assumed to be good
law and because no s teps had been taken by relevant commercial bodies to change the standard form
contract adopted. However, Lord Roskill dealt with this submission not by considering what the
objective intention of the parties would have been by adopting the particular phrase in question (that is
whether it could be said that they intended the interpretation to apply in circumstances where they did
not take steps to draft the phrase differently to avoid its applicat ion) but instead dealt with this
submission as an appeal for promoting commercial certainty by not overruling the erroneous decision
(The Mandarin Star) in question, (which submission was not accepted).
104 While Lewison cites this case as authority for proposition that where a contract is entered into
assuming that decision correctly represents the law, that will not provide a reason for applying the
erroneous decision to the contract in question (which can be implied from the outcome of the decision,
although not the express reasoning), it might perhaps be more precise to read Shell International as
authority for the proposition that the fact that a contract has been drafted assuming the correctness of a
decision will not necessarily prevent the courts from finding that the decision is incorrect (and as a
consequence to refuse subsequently to apply the erroneous decision to the interpretation of the
contract). That was the approach of Sir John Donaldson MR in The Mandarin Star, who rejected an
argument of this kind as follows:
Mr. Joseph also submitted that as the terms of the lease were agreed before the decision of the
House of Lords in United Scientific Holdings Ltd. v. Burnley Borough Council , the lease had
to be construed and the intention of the parties deduced on the basis of the law as it was
thought to be at that time. Whilst this argument is not without its attractions, I think that it
must be rejected as involving an undesirable extension of the doctrine of stare decisis. A
somewhat similar argument was rejected by the House of Lords in Shell International
Petroleum Ltd v Gibbs.
105 In relation to the ability of parties who adopt a standard form contracts to do so against a background of
previous case decisions on the meanings of the words in the standard form contracts, Lewison refers (at
104 of 3rd
end) to the statement of Lord Hoffman in Beaufort Developments (NI) Ltd v Gilbert-Ash (NI)
Ltd [1999] 1 AC 266, where his Lordship states:
It is also important to have regard to the course of earlier judicial authority and practice on the
construction of similar contract. The evolution of standard forms is often the result of
interaction between the draftsmen and the courts and the efforts of the drafts men cannot be
properly understood without reference to the meaning which the judges have given to the
language used by his predecessors.
106 Clarke LJ in Sunport Shipping Ltd v Tryg-Baltica International (UK) Ltd [2003] 1 Lloyd’s Rep 138
similarly stated:
When a contract has been professionally drawn … the draftsmen is certain to have in mind
decisions of the courts on earlier ed itions of the clauses. Such decisions are part of the context
or background circumstances against which the particular contract falls to be construed. If the
draftsmen chooses to adopt the same words as previously construed by the courts, it seems to
me to be likely that, other things being equal, he intends that the words should continue to
have the same meaning.
107 While it might be difficult to say that a “settled practice” o f draftsmanship had arisen following one
judgment (Eisenwerk) in Australia in which the construction of a particular clause seems to have been
addressed, I think it might well be said that the apparent notoriety within arbitral circles of the decision
in the period at least from 2001 was likely to have given rise to an awareness on the part of lawyers
advising their clients on contracts containing arbitration clauses of this kind of the prudence of ensuring
that any doubt as to the parties’ intentions in respect of the lex arbitri should be removed (and I see no
reason to think that the practice would have differed where what was in consideration was a standard
form contract).
108 That said, the force of Mr Stevenson’s submission depends on the similarity (or otherwise) between
what I might refer to as the Eisenwerk clause and the clause adopted by the parties in their agreement.
It seems to me that this is where the argument fails.
109 While I would have been inclined (had the clauses mirrored each other in all relevant respects) to infer
that reasonable parties in the position of Carg ill and Excel, knowing the law and acting on the advice of
the experienced solicitors, must have intended to exclude the Model Law when they chose a form of
arbitration agreement relevantly the same as that construed in Eisenwerk and did not take steps to
ensure that the result in that case was avoided in their case, the fact is that here the parties adopted a
clause which uses somewhat different terminology (referring their disputes for arbitration under the
ICC Rules, not provid ing for the settlement of their disputes in accordance with those Rules). It seems
to me that I cannot properly draw the inference for which Mr Stevenson contends in light of that
difference, which I see as more than a mere semantic difference but as having potential substance
(insofar as the emphasis to referral of the arbitration to take place under particular ru les, in the present
formulat ion, in my mind highlights the very distinction between procedural rules and the overriding
role of the lex arbitri which I consider was not taken into account in Eisenwerk ).
110 Therefore, I have concluded that there was no implied agreement between the parties to opt out, for the
purposes of s 21 o f the Commonwealth Act, of the Model Law nor is any such intention to be in ferred
from the fact that the parties chose to adopt an arbitration clause similar to that which had been used in
Eisenwerk at a time when the potential consequence of using such a clause should have been well
known to those practising in the area of international arbitration.
111 The answer to the init ial jurisdictional issue, therefore, is that the Model Law applies. Strictly
speaking, that means that the balance of the issues in relation to the application for leave to appeal
under the provisions of the State Act do not arise. However, they were argued before me and I address
them as follows.
(ii) Does the claim arise out of a maritime contract?
112 The second jurisdictional issue arises from the provisions of the State Act under which leave to appeal
may be granted in respect of questions of law arising out of arbitral awards. Subject to subs (4), s 38(2)
of the State Act confers a right to appeal to this Court on any question of law arising out of an award.
In the absence of consent of all other part ies, an appeal can only be brought with the leave of the court
(s 38(4)(b)) and the grant of leave is subject to s 40, which provides that the court shall not grant leave
to appeal with respect to a question of law arising out of an award if there is in force an exclusion
agreement, that being defined as being an “agreement in writ ing …between the parties to the
arbitration agreement which excludes the right of appeal under section 38(2) in relat ion to the
award…”
113 Section 40(3) provides that an agreement may be an exclusion agreement for the purposes of the
section whether or not it forms part of the arb itration agreement. Mr Gleeson noted (and Mr Stevenson
accepts) that Article 28(6) of the ICC Rules in its terms amounts to an exclusion agreement for the
purposes of the Act and hence that, by the submission of the dispute to arbitration under the ICC Rules,
there was an exclusion agreement.
114 Pursuant to s 41(a), an exclusion agreement shall have no effect in relation to the award or question
where the award or question of law arising in the course of the arb itration relates in whole or in part to
a question of claim falling within the Admiralty jurisdiction of this Court. Accordingly, to avoid the
effect of the exclusion agreement, the Cargill needs to establish that the claim before the Arbitrator was
a maritime claim.
115 Section 9(1) of the Admiralty Act 1988 (Cth) confers jurisdiction on this Court, amongst others, in
respect of marit ime claims. A reference to a marit ime claim is a reference to a proprietary marit ime
claim or to a general maritime claim. The latter includes (s 4(3)(f)) “a claim arising out of an
agreement that relates to the carriage of goods or persons by a ship or to the use or hire of a ship,
whether by charterparty or otherwise”.
116 Reliance was placed by Mr Stevenson relies on Heilbrunn v Lightwood plc [2007] FCA 1518; (2007)
164 FCR 1 for the submission that the claim brought by Cargill for demurrage under a contract for the
delivery of coal FOB to a ship (for the subsequent carriage of the coal by ship) was a marit ime claim
(and hence the exclusion clause is overridden). Mr Gleeson relies, inter alia, on The Zeus [1888] 13 PD
188 for the contrary conclusion.
117 It is accepted that the relevant test in determining whether there is a maritime claim is that applied in
Heilbrunn - the ‘reasonably direct connection’ test, namely whether there is a reasonably direct
connection between the claims made and an agreement fo r the use o f a ship or the carriage of goods by
ship. In this case, as outlined earlier, the claims made in the arbitrat ion were for payment due in
respect of the delivery of goods to a ship and a counterclaim for demurrage fo r delay in loading the
ship.
118 In Heilbrunn, Allsop J (as his Honour then was) was considering whether a claim, against a
warehouseman in England, fo r damage which occurred when a vintage car was loaded into a sea
container to be transported by road to the port of Tilbury fo r loading on a s hip for sea carriage to
Australia was a maritime claim with in the Admiralty jurisdiction under the Act. His Honour held that
it was. In essence, his Honour considered that the agreement to load a shipping container was
sufficiently directly related to the anticipated carriage of goods by sea to satisfy s 4(3)(f), at [52]-[54].
The agreement under which the claim was made was for the loading of the sea container which was
then to be to the port and then by sea to Australia.
119 By contrast, in The Zeus, to which his Honour referred to in Heilbrunn, the claim was made under what
was described as an undertaking (by way of guarantee) by a colliery company to load a cargo of coal
onto a ship within a part icular period (and thereafter to pay demurrage). That claim was held not to be
an agreement “made in relation to the use or hire of any ship, or in relation to the carriage of goods in
any ship” within the meaning of the County Courts Admiralty Jurisdiction Amendment Act 1869 (32 &
33 Vict. c.51). The agreement was characterised as “merely an engagement to deliver coals at a
particular place” with a penalty to be paid if the contract was not performed within a limited t ime. The
use of the word ‘demurrage’ was said to be immaterial (when considering whether this was a claim
having the necessary relationship to the use or hire of or carriage of goods in a ship), it being a word of
different meanings, “… unless it can be established that the agreement is one in relation to the use or
hire of a ship”. Admiralty jurisdiction was there found not to have been established.
120 As is apparent, the present facts are broadly analogous with those in both Heilbrunn and Zeus in that
(as in Heilbrunn) the coal was to be delivered by Excel on board a ship for the purpose of its carriage
by sea (albeit that it was not being loaded into a sea container as such but was being transported by rail
for delivery over the ship’s rail) and the claim (as in Zeus) was for demurrage by reference to the delay
in loading the ship.
121 In Heilbrunn, Allsop J said from [22]:
The relevant question to address is whether the assertions of right or interest recognised by
law and carry ing an entitlement to relief made by the plaintiff in the application and statement
of claim (being the claim of the plaintiff) have (and has) the legal character of that which is set
out in s 4(3)(f): Owners o f Shin Kobe Maru v Empire Shipping Co Inc (1994) 181 CLR 404 at
422 and 426; and The ‘Global Peace’ 154 FCR at 459-60 [73]-[76].
This task is to be undertaken with the meaning and content of s 4(3)(f) understood.
Mr Cutler argued that the correct approach to the interpretation of s 4(3)(f) could be found in
Port of Geelong Authority v The ‘Bass Reefer’ (1992) 37 FCR 374 at 380-382 in which case
Foster J adopted the approach of Lord Keith of Kinkel in Gatoil International Inc v
Arkwright-Boston Manufacturers Mutual Insurance Co [1985] AC 255 at 270-271 and said
that the relationship connoted by the words "that relates to" in s 4(3)(f) must be "some
reasonably direct connection". The same passage from Lord Keith’s speech in Gatoil [1985]
AC at 270-271 was cited with apparent approval by Gummow J in Empire Shipping Company
Inc v Owners of the Ship ‘Shin Kobe Maru’ (1991) 32 FCR 78 at 95 (at first instance).
…Before dealing with these cases, it is appropriate to set out, by reference to settled
Australian law, some important considerations that attend the construction and interpretation
of the Act. The first consideration is the proper approach to the construct ion of the Act. In
Tisand Pty Limited v The Owners of the Ship MV ‘Cape Morton’ (Ex ‘Freya’) (2005) 143
FCR 43 at [59]- [65], the Full Court set out relevant governing principles. It is unnecessary to
repeat those passages other than to say the Act should be read in its legal and historical
context, and that the Act and the definitions of maritime claims have an international as
well as a domestic maritime context , including the International Convention for the
Unification of Certain Rules Relating to the Arrest of Sea-Going Ships 1952, done at Brussels
on 10 May 1952 (the "1952 Convention") and the Australian Law Reform Commission, Civil
Admiralty Jurisdiction, Report No 33 (1986) (the "ALRC Report").
The second consideration is that provisions conferring jurisdiction or granting powers to
courts should be interpreted liberally and without imposing limitations not found in the
express words: The ‘Shin Kobe Maru’ 181 CLR at 421 and see the numerous other High
Court authorities to like effect referred to in Hewlett Packard Australia Pty Limited v G E
Capital Finance Pty Limited (2003) 135 FCR 206 [187].
The third consideration is a particular aspect of the importance of the context provided by the
ALRC Report. In Owners o f MV Iran Amanat v KMP Coastal Oil Pte Ltd (1999) 196 CLR
130 at 138 the High Court in a jo int judgment (Gleeson CJ, McHugh, Gummow, Kirby and Hayne JJ) stressed the importance of the background of English legislation and authority
and any settled international construction:
… When the Parliament has enacted legislat ion, affecting the subject of international
shipping, and followed a statutory precedent from overseas which has by then
received a settled construction, there is every reason to construe the statutory
language in the same way in th is country unless such construction is unreasonable or
inapplicable to Australian circumstances. ...
Thus, both Gatoil [1985] AC 255 and The Antonis P Lemos [1985] AC 711 can be seen as
unanimous decisions of the final court of appeal in the United Kingdom interpreting domestic
legislation having its origins in an international convention, one aim of which was to bring
uniformity of approach among different legal systems. The existence of those decisions, the
desirability of international uniformity, or at least broad consistency, and an expressed
suggestion by the ALRC (which was heeded) that Parliament follow the word ing of the 1981
UK Act, which had been (recently) interpreted (as well as the antecedent provision in the 1956
UK Act) by the House of Lords in Gatoil [1985] AC 255 and The Antonis P Lems’ [1985] AC
711 necessarily constrain the interpretation of s 4(3)(f), certainly at first instance. Further, two
judges, of this Court (Foster J in The Bass Reefer 37 FCR 374 and Gummow J in The Shin
Kobe Maru 32 FCR 78) at first instance have applied Gatoil [1985] AC 255. (My emphasis)
122 From [38], in a passage on which Mr Stevenson places reliance, Allsop J said:
After discussion at 725-731, and for the reasons expressed at 731, Lord Brandon [in the
Antonis P Lemos] rejected the first contention of the owners. A wide and liberal, not narrow,
construction was, his Lordship said, to be given to the phrase "arising out of", equivalent to
"in connection with". In his discussion, Lord Brandon said at 727:
With regard to the first point, I would readily accept that in certain contexts the
expression "arising out of" may, on the ordinary and natural meaning of the words
used, be the equivalent of the expression "arising under," and not that of the wider
expression "connected with".
In my view, however, the expression "arising out of" is, on the ordinary and natural
meaning of the words used, capable, in other contexts, of being the equivalent of the
wider expression "connected with". Whether the expression "arising out of" has the
narrower or the wider meaning in any particular case must depend on the context in
which it is used.
I should apply The Antonis P Lemos [1985] AC 711 in this regard. All the reasoning of Lord
Brandon is equally applicable to s 4(3)(f). I would only add the following remarks. Given the
need for the 1952 Convention to apply to a wide variety of legal systems and given the
capacity of maritime claims to arise by reference to chartering and carriage arrangements
often of some complexity, it would make little p ractical sense to limit the types of claims to
which this paragraph was directed to contractual claims between part ies to the agreement.
Secondly, the provision is one in which jurisdiction is given to a court. It should be read
liberally: The Shin Kobe Maru 181 CLR at 421. Th ird ly, The Antonis P Lemos [1985] AC 711
was recently applied by a Full Court of this Court, though in a different context: that of
construing an arbitration clause containing the phrase "arising out of", in Comandate Marine
Corporation v Pan Australia Shipping Pty Limited (2006) 157 FCR 45 at 45 at [171]. The Full
Court, though in that different context, gave the same wide meaning to the phrase "arising out
of"’: Comandate Marine v Pan Australia 157 FCR 45 at [162]-[176].
123 Accordingly, a liberal v iew should be taken in determin ing when a claim arises out of an agreement but
the second part of the test is whether that agreement has a reasonably direct connection with the
carriage of goods by sea and a narrower view is taken on that aspect. In Heilbrunn, Allsop J said of
this question, from [44]:
The next question is whether any one or more of these agreements answers or answer the
description of "an agreement that relates to the carriage of goods... by a ship", as that phrase
was interpreted by the House of Lords in Gatoil [1985] AC 255.
In Gatoil [1985] AC 255 Lord Keith of Kinkel (with whose speech Lords Fraser of
Tullybelton, Scarman, Wilberforce and Roskill agreed) concluded that the phrase "related to"
should not be construed widely, but rather there should be "some reasonably direct
connection" with the activ ities described in the provisions (there ss 1(1)(h) and 47(2)(e) of the
1956 UK Act).
It is also be noted that in The Antonis P Lemos [1985] AC at 730 Lord Brandon expressed the
view that what "tilted the balance in favour of g iving a narrow meaning to the expression
‘relating to’" was the existence of two authorities, The Zeus (1888) 13 PD 188 and The
Aifanourios [1980] SC 346 (the reasoning in which latter case can be seen as contrary to some
of the comments of Lord Brandon about the natural and inevitable overlap in the list of
marit ime claims). Lord Brandon said (at [1985] AC at 730 G-H) that in the absence of these
authorities it might not be right to give the expression "relating to" (in s 4(3)(f) "relates to") a
narrow meaning as given by the House in Gatoil [1985] AC 255.
This apparent degree of tension between the two decisions (though the word "tension" is not
used in any way disrespectfully, in part icular since Lords Scarman and Roskill concurred in
both decisions) can be set against the background of the clear injunction of the High Court in
The Shin Kobe Maru 181 CLR at 421 (and the numerous other High Court decisions earlier
referred to) to read provisions conferring jurisdiction and discretion on courts liberally.
For the reasons that I have earlier given, however, it is not appropriate that, sitting at first
instance, I do other than apply Gatoil [1985] AC 255. Further, in what might be said to be in
support of a wide construction of "arising out of" and a narrower approach to "relates to", the
former expression should be wide to catch all claims that have a connection with an agreement
that has the appropriate maritime connection or character. The appropriate marit ime
connection or character fo r s 4(3)(f) might be seen to be assisted by the recognition that all the
general marit ime claims in Article 1 of the 1952 Convention and in s 4(3) are expressed to be
the foundation of an action in rem against a ship and to found the remedy of arrest. The
relational connection in the phrase "that relates to" is to be seen in that context. It also may be
important to see the appropriate marit ime connection by reference to the Constitutional reach
of s 76(iii). Section 4(3) must at all times be construed within the confines of the
Constitutional authority given to Parliament: cf the Acts Interpretation Act 1901 (Cth), s 15A.
Approaching the matter by applying Gatoil [1985] AC 255, does or do any one or more of the
agreements referred to in [43] above have a reasonably direct connection with the activity of
carriage of goods by a ship and thereby "relates or relate to the carriage of goods by a ship"
for s 4(3)(f)?
124 Adopting the reasoning of his Honour, the question whether a claim is a maritime claim is thus to be
determined by applying a liberal approach to the question whether there is claim ‘arising out of’ an
agreement but a narrower approach should be taken when considering the question of whether the
agreement has the appropriate maritime character. In Heilbrunn, there was the necessary relationship
or connection between the agreement and the carriage of goods by sea because the agreement for the
loading of the container was seen as being “essential to the performance of the sea carriage”. His
Honour said, at [52]:
The cars had to be loaded into the shipping container in preparation for sea transport. That is
what the defendant undertook to do. The loading of the container was, in substance, for the
sea carriage. … The agreement to load the shipping container between the arranger of the
carriage and its subcontractor had a reasonably direct relat ionship with the carriage of goods
by the ship. (my emphasis)
125 In the present case, although the coal was not being loaded into a separate sea container to be put on
board the ship, it is clear that the coal was being delivered for the purpose of and in preparation for its
carriage by sea. The specificat ion standards in the agreement make clear that aspects of the loading
obligations were referable to conditions relevant to the carriage of goods by sea.
126 It seems to me that this is not a case, such as Gatoil International Inc v Arkwright–Boston
Manufacturers Metal Insurance Co [1985] AC 255, where the contract in question is separate from the
action involved in putting the ship in readiness for goods to be carried by sea. Rather the steps to be
taken under the present contract were an essential part of putting the ship in readiness for the carriage
of goods by sea. In Gatoil, by contrast, there was a claim for a contract for insurance of goods that
were carried by ship and the House of Lords said this was not a sufficient connection. It can be seen
that in that case the contract was not entered into to make possible or to facilitate or to further the
purpose of carriage of goods by sea, but rather was to deal with the financial risk attaching to such
carriage. Similarly, in the Port of Geelong Authority v The “Bass Reefer” (1992) 37 FCR 374, claims
in relation to a lease of a cargo assembly at the port and a licence for priority berthing at a nominated
berth did not satisfy the reasonable connection test . Neither o f those cases is factually similar to the
present. Mr Gleeson referred also to The “Catur Samudra” [2010] SGHC 18 where the High Court of
Singapore held that to satisfy the direct connection test a claim under an agreement which is collateral
or ancillary to the contract of carriage must be intrinsically related to the use or hire of a vessel.
127 Mr Gleeson submitted that the distinction between the present case and the Heilbrunn case was that in
the present case the claim related to a contract anterior to something which subsequently happened on a
ship. It was submitted that the reasonably direct connection must be with the use of the ship itself
(relying on Geelong Authority and Heilbrunn). Further, it was submitted that the only connection with
a ship was that the obligation was to deliver foods over the ship rail, with t itle to the goods and risk of
loss or damage passing progressively to Cargill as the goods passed over the rail of the vessel.
128 It was said that the mere place for delivery could not transform the subject matter of the agreement
from one for the sale and delivery o f goods into a charterparty or the like. (As I understand it, this
argument assumes that the fact that the goods were ult imately to be transported by sea was incidental to
the contract, which could just as easily (assuming that were possible logistically) have been for
delivery of coal to, say, a trucking terminal for delivery by road and with no suggestion of a marit ime
flavour.) In that regard, the fact that there might have been a different result had Cargill chosen to
carry the coal it purchased by a different means seems to me not to be relevant – it might equally be
said that had the vintage Vauxhall been transported by air, the contract for the loadin g of it into a
container for transport by plane would not have been a maritime contract.
129 Here, the connection between the agreement for the delivery of coal and the carriage of that coal by
ship is obviously closer to the position in Heilbrunn than the relationship of the contracts in the Gatoil
and Geelong Authority cases to the use/hire of carriage of goods by ship.
130 If the contract to load and deliver a sea container to port was sufficiently connected to the use of a ship
to give rise to a marit ime claim (and not construed simply as a contract for the transport by road of
goods to a place o f delivery for later shipment by sea), then it is by no means clear why the agreement
in question (which involves the physical delivery of the goods onto the ship for subsequent transport by
sea) is not also sufficient to enliven the Admiralty jurisdiction. Indeed, but for the decision in Zeus, I
would find it difficult to see any reasonable basis for distinguishing between a situation where the
delivery is made by way of loading goods into a container to be transported to the port and placed on a
ship and the situation where the delivery is made not by loading a container but by way of loading a
freight car to be transported by rail to the port and then for the goods to be placed directly into the ship.
131 Does Zeus, which (but for the fact that it seemed to involve a claim for demurrage under a guarantee or
‘undertaking’ of performance of the work within time, as opposed to a claim for demurrage u nder a
contractual provision not labelled by reference to a guarantee or undertaking) seems almost on all fours
with the present factual situation, require a d ifferent conclusion from that reached in the similar
situation in Heilbrunn?
132 Zeus, considered without apparent disapproval in Heilbrunn and approved in Gatoil, was a very b riefly
reasoned judgment on appeal from the County Court of Northumberland in 1888. (It is perhaps not far
from the category of case the citation of which was “strongly deprecated” by the House of Lords, as
noted in Export Credits Guarantee Department v Universal Oil Products Co [1983] 2 All ER 205;
[1983] 1 W LR 399.) In terms of persuasive authority, the considered analysis of Allsop J in the
Heilbrunn case is, with respect, entitled to more deference than the decision in Zeus and seems to me
more likely to be reflective of maritime practice in the modern business world.
133 I note that reference was also made by Mr Gleeson to Tradhol Internacional SA v Colony Sugar Mills
Limited 2009 W L 3929893 (C.A.2(N.Y)) (20/11/09) as being broadly consistent with Zeus and
involving an FOB contract for sale of goods. In that case, the Court of Appeals held that the seller had
failed to establish a prima facie admiralty claim and was not entitled to an order of marit ime attachment
and garnishment. The relevant law to be applied as to whether there was a prima facie maritime claim
raised issues as to whether a contract including both marine and non-marine elements could be brought
within one of the two exceptions to the “mixed contracts rule” – which turned on whether the non-
marit ime obligations were severable or whether the non-maritime claims were merely incidental to the
marit ime ones, hence a different context from the question presently under consideration. The court
considered that the demurrage clause in a contract for the sale and loading of goods FOB was not the
focal point of the contract and that “In the context of the contracts at issue demurrage alone does not
raise a claim to which the remaining claims are merely incidental so as to support the second exception
to mixed contracts”, and held that Tradhol had failed to exp lain how its demurrage and ‘dead freight’
claims fitted within the mixed contract prohibition. As I read the decision, the court seems to have
proceeded on the assumption that a demurrage claim was a marit ime claim but that the remain ing
claims were not merely incidental to it or severable so as to overcome the problem for Tradhol that the
contract contained both maritime and non-maritime elements. If that is the proper conclusion to be
drawn from the reasons then it would seem to me to support the view that a claim for demurrage could
be seen as having a maritime flavour when linked with a contract for the carriage of goods by sea.
134 Applying the test enunciated in Heilbrunn, had this issue been necessary to determine, I would have
held that the claims the subject of the arbitrat ion in this case were marit ime claims falling with in the
Admiralty jurisdiction by reference to s 4(3)(f) of the Act on the basis that the loading of the coal onto
the ship was an essential step in the preparation of the vessel for the carriage of goods by sea and,
hence, the maritime exception would apply.
135 In the written submissions served for Excel, Mr Gleeson next argued that the Admiralty exception did
not apply in any event because the “exclusion agreement” was entered into after the commencement of
the arbitration (s 41(1)(d) of the State Act). That submission was based on the arbitration proceedings
having commenced on 18 March 2009 (upon receipt of the request by the ICC Secretariat) and the
reliance placed by Cargill in its written submissions on the exchange of correspondence in April 2009
as amounting to the arbitration agreement in question.
136 However, in oral submissions before me, Mr Stevenson made it clear that Carg ill accepted the
contention (which had been made by Excel’s lawyers in April 2009) that the reference to arbitrat ion
had occurred by virtue of the arb itration agreement itself (not an agreement comprised by the exchange
of correspondence) (T8.8). It was conceded (as noted above) that Article 28(6) of the ICC Rules, as
adopted by the parties by their arbitrat ion agreement in clause 18.9 of the standa rd coal trading
agreement entered into in 2005, amounted to an exclusion agreement for the purposes of s 40 of the
State Act. Therefore, it was contended by Mr Stevenson that the exclusion agreement was not one
entered into after the arb itration commenced and thus s 41(1)(d) d id not apply. In those circumstances,
I did not understand Excel’s written submission to the contrary to be pressed but, if it were, it would
not have succeeded.
137 Accordingly, had I been satisfied that the State Act applied, I would have determined the second
jurisdictional question in favour of Cargill.
(iii) Have the threshold requirements in s 38(5) of the State Act been satisfied?
138 Having considered the jurisdictional issues, I turn then to whether (had those been found in favour of
Carg ill) the threshold requirements for the grant of leave to appeal would have been satisfied. As
already noted, Cargill is seeking leave to appeal in relat ion to two issues – the first is as to the
construction of clause 7.11.2 of the agreement (namely, whether laytime should have continued until
the giving of a force majeure notice irrespective of whether that was a notice compliant with clause
17.2 in terms of its timing) and the second is as to whether laytime was suspended during any time that
was not a “Weather Working Day”.
Could determination substantially affect the rights of one or more parties
139 The first threshold requirement is that the court be satisfied that the determination of the relevant
question of law, having regard to all the circumstances, “could substantially affect the rights of one or
more parties to the arbitration agreement”. Factors relevant to the determination of this question
include the quantum of the amount in issue and the relationship between the costs of the appeal and the
significance of the question of law to be determined (Westport Insurance Corporation v Gordion
Runoff Ltd [2009] NSWSC 245, at [15]; Natoli v Walker (1994) 217 ALR 201, at 9).
140 For Cargill, it was submitted that if its contention as to the construction of clause 7.11.2 were to be
correct this would make a substantial difference to its rights as it would then have had an entitlement to
demurrage from 8 June (at a rate of USD50,000 per day), rather than only from 25 June 2007. (The
additional demurrage charges amount to USD850,000.)
141 Mr Gleeson contended that this submission failed to take into account the effect of the determination
made by the Arbit rator as to the estoppel/waiver issues that are not now the subject of any challenge by
Carg ill. It is said that because of those findings, the determination of neither of the grounds of appeal
could now have any substantial effect on the parties’ rights.
142 As to the first ground of appeal, the findings to which Mr Gleeson refers are the findings that the force
majeure notice was g iven as early as practicable (para 223(b) of the Part ial Award); tha t clause 17.3
applied and had the effect that laytime was suspended during the force majeure period (in effect, para
223(a) of the Part ial Award); and that Cargill was not entitled to resile from the position it had earlier
adopted (in February 2008) and seek demurrage for the period from 8 to 21 June 2007 (para 223(c)).
143 As to the second ground of appeal, it is said, first, that any appeal would be futile (because the
conclusion as to the weather working day issue was in the context of responding to an alternative
argument) and the Arb itrator’s finding as to the principal contention, ie that time d id not count towards
laytime by reason of the force majeure provisions, is not challenged. Thus it is said that whatever the
result of an appeal by reference to the alternative “Weather Working Day” argument, the outcome will
remain the same by reference to the principal finding). Secondly, it is said that it has been conceded by
Carg ill that there is no difference in monetary terms if an allowance was not made for wet weather but
was made for force majeure. Thirdly, it is submitted that (as per the first ground of appeal) this issue
could affect the parties’ rights only if Cargill were to be permitted to claim demurrage for the period up
to 21 June 2007 and the Arbitrator has found otherwise.
144 (Mr Stevenson concedes, as I understand it, that if leave to appeal is not granted in respect of the first
ground of appeal then there is no utility in a grant of leave in relat ion to the weather working day
point.)
145 Turning to the first ground of appeal, it is contended by Cargill that the Arbitrator should have found in
all the circumstances that the Iron Bradyn went on demurrage shortly after the commencement of the
force majeure period. While there is no challenge to the finding of the period over which force majeure
was operative, Carg ill’s position is that had there been a finding that the vessel was on demurrage as at
0956 hrs on 8 June 2007 then demurrage would have been payable from that time.
146 The interaction between clauses 7 and 17 (which I consider in more detail below) is relevant when
considering what would be the effect if, as Cargill contended, the time from the beginning of the
interruption did count as lay time.
147 Before the Arb itrator, Excel had claimed (in its Summary of Claimant’s Claims, as set out in the
Arbitrator’s award para 154) that clause 17.3 governed the situation and that it was not liab le for
damages for delay or failure to perform its primary contractual obligations in th e period from 8 to 25
June 2007 (and it sought a declaration to that effect). Clause 17.3, which I set out later in these
reasons, made express reference to the counting of laytime (but was subject to the proviso that the
affected party had complied with the requirements of clause 17.1). The Arbit rator considered that,
although they might have been better expressed, the opening words of clause 17.3 made clear that, in
the counting of laytime, delay caused by a force majeure was to be taken into account (a t [198]) and
that this meant that the running of laytime was suspended during the force majeure period.
148 It is by no means clear, therefore, how a finding that clause 17.3 operated (as the Arbitrator seems to
have found) such that laytime (and any liability for delay) was suspended during a force majeure period
(provided the notice requirements of clause 17.1 were complied with), would have been reconcilable
with a finding that, notwithstanding the commencement of a force majeure period, demurrage was
payable for part of that period if a notice under clause 17.2 was not issued immediately the force
majeure event occurred and the vessel went on demurrage during the course of the force majeure
period. A finding that laytime continued to run from the commencement of the force majeure period
(and demurrage was payable once laytime expired early in that period) until the giving of the force
majeure notice (and therefore that the Iron Bradyn went on demurrage earlier than 25 June 2007)
would seem to be inconsistent with the Arbitrator’s finding (para 223(a)) that no demurrage was
payable during a force majeure period.
149 Mr Gleeson contended that if leave were to be obtained by Cargill the issue whether there had been an
error of law would be immaterial as its counterclaim has already been rejected and there is no attempt
by Cargill to seek leave to appeal against the finding of the arbitrator rejecting the counterclaim the
whole of which was dis missed (para 224(e)), there being no immediate entitlement to claim demurrage
in any event.
150 Mr Stevenson’s response was that the Arbitrator’s findings in relation to waiver, election and the like
are encapsulated in para 139 of the word (namely that Carg ill was not then entitled to raise the
possibility that Excel had no entitlement to rely on the force majeure provisions of the agreement at all
in the relevant period) but that this said nothing as to whether Carg ill could raise the question of the
proper construction of the force majeure provisions. Mr Stevenson contends that nothing in the
Arbitrator’s findings justifies the conclusion that Cargill was not entitled to make the Alternative
Argument as to the proper construction of clause 7.11.2.
151 If the two findings (ie a rev ised finding on clause 7.11.2 and the existing finding on 17.3) could not
stand together then it would seem that the conclusion reached in relation to Excel’s claim for a
declaration that amounts had become payable under clause 17.3 would need to be revisited (whether or
not that finding had been the subject of a separate challenge) since there would seem to be an
inconsistency in saying both that a vessel goes onto demurrage during the force majeure period and that
liab ility for demurrage is suspended in that period. Therefore I am not persuaded that the overall
conclusion reached by the Arbitrator as to clause 17.3 necessarily renders futile an appeal o n the first
ground.
152 However, in my view (leaving aside the clause 17.3 argument) the effect of the Arbitrator’s
estoppel/waiver finding (which is not challenged) would seem to deprive a finding in relation to the
first ground of appeal of much of its effect. At best, Cargill would in those circumstances seem to be
limited to a claim for demurrage for the period from 21 to 25 June 2007 (a claim of much less than the
USD850,000 figure which Carg ill contended would be recoverable if it succeeded on this issue – being
a claim of USD250,000 at most, assuming the first and last day of that period are both included in the
calculation).
153 I have outlined above the circumstances in which Cargill did not press, as at February 2008, its claim
for the so-called “undisputed” amount and reserved its position only in relat ion to the “disputed”
amount. The Arbitrator d ismissed the whole of Cargill’s counterclaim on the basis that there was an
agreement by Carg ill to compromise its claim for demurrage and/or waived or was estopped from any
claims to demurrage in the period from 8 to 21 June 2007 (paras 142-144). That counterclaim was for
the “undisputed” amount referable to the period (from 8 to 21 June 2007 but also, as I understand it, for
the “disputed” amount referable to the period from 21 to 25 June 2007. There seems to be nothing in
the award to suggest that Cargill had waived or would be p recluded from raising the claim for
demurrage in that latter period.
154 Therefore, I accept the submission by Mr Glees on that a re-consideration by way of appeal of the
proper construction of clause 7.11.2 will not overcome the problem for Cargill of the estoppel/waiver
finding, but that finding seems to me to be confined to any claim for demurrage for the period 8 to 21
June 2007, not the later period.
155 Balancing a claim of that lesser magnitude against what would surely be the limited cost of arguing a
discrete construction point before the arbitrator, I would not accept that there could not be a substantial
effect on the parties’ rights arising from the determination of that discrete issues and thus would have
been prepared to conclude that the first threshold requirement was met and that the determination of the
question of law posed by the first ground of appeal could substantially affect the parties’ rights.
156 If so, then to the extent that the second ground of appeal can be called in aid to support the argument
based on the first ground of appeal (as Carg ill seeks to do in the manner I consider below), the
determination of that question of law may also be said to have the potential substantially to affect the
parties’ rights (though in an indirect way). However, if leave to appeal is not granted in relat ion to the
first alleged erro r, then it is not disputed that there would be no utility in granting leave in respect of the
second alleged error and thus the first threshold requirement would not be met in that case.
Requirement that there be manifest error of law on the face of the record
157 Although I have summarised above the errors said to have been made by the Arb itrator, in considering
this threshold requirement (and the alternative argument that there is a strong likelihood that there was
an error of law) it is necessary to focus in some detail on how it is said that the Arbitrator has erred in
his award.
158 Before so doing, I note that emphasis was placed by Mr Gleeson on the high hurdle confronting a party
seeking to establish manifest error of law on the face of an award for the purposes of s 38(5) of the
State Act. In Promenade Investments Pty Ltd v State of New South Wales (1992) 26 NSW LR 203,
Sheller JA said (at 225):
The expression “error of law on the face of the award” is one of a type well -known to courts.
The award having been examined the question is whether there is apparent (and such is the
denotation of the word “manifest”) an error of law. “Manifest error” is an expression
sometimes used in reference to reasons given by judges or the approach taken by juries: see,
eg, s 107(c)(iii) of the Supreme Court Act 1970 and the judgments of Kirby P in Azzopardi v
Tasman UEB Industries Ltd (at 151) and Otis Elevators Pty Ltd v Zitis (1986) 5 NSWLR 171
at 181. It is used to indicate something evident or obvious rather than arguable: see generally
per McHugh JA in Larkin v Parole Board (1987) 10 NSWLR 57 at 70-71. (my emphasis)
159 His Honour later went on to say (at 226), in the context of considering whether (and determining that it
was not) it would be appropriate for the judge to proceed to determine whether there was manifest error
without hearing adversarial argument:
… However as McHugh JA pointed out “manifest”, in the context of the subsection, which
contemplates the grant of leave before an appeal can be pursued, connotes an error of law that
is more than arguable. There should, in my opinion, before leave is granted be powerful
reasons for considering on a preliminary basis, without any prolonged adversarial argument,
that there is on the face of the award an error of law. (my emphasis)
160 For there to be manifest error, the error must be evident or obvious, not something which is reasonably
arguable and not something that takes prolonged adversarial argument to deduce. As is the case when
considering whether a decision is plainly wrong, it is the quality that bespeaks the error. The fact that I
might have come to a d ifferent conclusion on a point of construction would not be to the point (as I was
reminded more than once, no doubt lest I be tempted to stray down the path of construing the relevant
clauses afresh).
161 In that regard, the very fact that the argument as to the construction of the relevant clauses required
careful and detailed analysis by Counsel on the hearing before me (and, I should a dd, has given me
pause when considering whether and how the relevant submissions were put to and/or addressed by the
Arbitrator) seems to me to compel the conclusion that any error of law which the Arbitrator might have
made in construing the respective clauses is certainly not manifest on the face of the award. It is not
the case that there was an obvious point which could be said to have been overlooked or misconstrued
in the Arbitrator’s analysis. Rather, the construction adopted by the Arbitrator in respect of the
relevant clauses for the purpose of addressing the question whether demurrage was payable during the
force majeure period seems to be one which was reasonably arguable and open for him to find. I set
out below the basis on which I have come to that conclusion.
Clause 7.11.2 ‘error’
162 As to the first error, it is said that on the natural and ordinary meaning of clause 7.11.2 the t ime
between the beginning of an interruption for force majeure and the giving of a force majeure notice
should have counted as laytime.
163 Clauses 7.11.1 and 7.11.2 provided, relevantly, (with my emphasis) that:
7.11.1 Time spent or lost on account of Force Majeure shall not count toward Laytime
(unless the Vessel is on Demurrage) provided that either:
(a) Seller gives notice pursuant to clause 17.2; or …
7.11.2 If Seller does not give any notice or Statement of Facts to Buyer as required in clause
7.11.1, the time lost shall count as Laytime and any delay in giving such notice from
the beginning of the interruption shall count as Laytime…
164 The giving of a force majeure notice was dealt with in clause 17 (not surprisingly headed Force
Majeure):
17.1 Upon the occurrence of any event which affects or is likely to affect the ability of a
Party to perform its obligations under this Agreement, that Party shall give the other
Notice in Writing thereof, which shall include details of the event, and shall give
further notices of any change in the situation as may be appropriate from t ime to
time.
17.2 In the event that a Party wishes to claim Force Majeure (the “Affected Party”) in
accordance with clause 17.3 it shall g ive notice to such effect to the other Party (the
“Non-Affected Party”) as early as practicable which notice may be given orally and
confirmed by Notice in Writing as soon as possible.
17.3 Neither Seller nor Buyer shall be liable in any way whatsoever for delay and/or
failure to comply with this Agreement (other than a failure to make any payment due
under it) to the extent that and for as long as such failure is caused by Force Majeure
including the counting of Laytime, provided that the Affected Party;….
17.3.3 has complied in substance with the notice requirements of clause 17.1
165 I interpose to note that it seems to be accepted (and was treated as such by the Arbitrator) that the
notice provided for under clause 17.1 is different from (and logically would be likely to precede) a
notice of intention to make a clam in 17.2. Further, insofar as clause 7.11.2 refers to a notice “as
required” in clause 17.11.1, in that clause what is required is a notice “pursuant to” clause 17.2 (which
arguably might mean no more than a notice o f the kind referred to in that clause – a notice of intention
to claim force majeure – as opposed to a notice issued in accordance with the time specified in clauses
17.2, namely as early as practicable).
166 On a first reading of 7.11.1, it has the effect that laytime is suspended during periods of force majeure
(unless the vessel is already on demurrage) provided, relevantly, that notice is g iven pursuant to clause
17.2. Clause 7.11.2 then deals with the consequences of there being no notice “as required under
clause 7.11.1” and those consequences are, first, that time lost [on account of force majeure] shall
count as laytime and, secondly, that “any delay” in giving such notice from the beginning of the
interruption shall count as laytime. The second consequence (so specified) seems of itself to
contemplate that a notice “as required” under clause 7.11.1 could be given albeit with some delay. In
other words, if “as required” relates to the time at which a notice is issued, clause 7.11.2 seems to
contemplate that there might be some delay even if the notice was given as early as practicable.
167 For completeness, I note that clause 7.11.6 provides that:
7.11.6 Notwithstanding the provisions of clauses 7.11.1, 7.11.2 and 7.11.3, once the Vessel
is on Demurrage, all time lost (including time lost by reason of Force Majeure) shall
continuously count as Demurrage …
Cargill’s submissions to the Arbitrator
168 The Outline of Submissions, dated 14 August 2009, served by Cargill in relation to the arb itration were
contained volume 3 of the Court Book (Exhibit A).
169 The manner in which the clause 7.11.2 submission was put is highly relevant. At para 18 of Cargill ’s
written submissions, Cargill pointed to the fact that the provision in clause 7.11.1 (that time spent or
lost on account of force majeure did not count towards laytime) was qualified by the provision that the
notice of intention to claim force majeure be given as early as practicable and went on to say that “This
requirement that there be no delay in the service of this notice is reinforced by the terms of clause
7.11.2”; and that this provision applied unless the vessel was already on demurrage in which case it
would continue to run and be payable by Excel notwithstanding force majeure (clause 7.11.1 and 17.8)
(my emphasis). In that submission, it seems to me, the notion that notice be given as early as
practicable was equated with the situation of there being ‘no delay’ in the service of the notice (said to
have been reinforced by clause 7.11.2.
170 Carg ill d isputed not only that the events gave rise to force majeure but also that the notice was in
compliance with clause 17.2 “in part icular such that laytime would not count from 8 June 2007 or at
any time prior to service of that notice” (para 21(b) submissions) and submitted that even if the events
amounted to force majeure nevertheless that force majeure period (during which time would not count
against laytime) commenced when Excel contended it did or ended when Excel said that it did.
171 Of the issues there identified as requiring determination, Carg ill noted that one was whether there had
been compliance with the requirement for a valid and effect ive declaration of force majeure (and, if
not, the effect of non-compliance (para 34(b)) and as to whether and to what extent time d id not run for
the purposes of calculating laytime as a result of the events claimed to amount to force majeure (para
34(c)).
172 At para 40 of its then submissions, Cargill said:
If the seller (Excel) does not give any notice to the buyer (Cargill) in accordance with clause
17.2, the t ime lost shall count as laytime. Further any delay in giving such notice from the
beginning of the interruption shall count as laytime (clause 7.11.2). (my emphasis)
173 There was thus a distinction there drawn by Carg ill between the situation where there was no notice
compliant with the timing requirements of clause 17.2 and the situation whe re there was a ‘delay’ in
giving of the notice (the latter being the very submission now sought to be made and which it is said
the Arbitrator did not address or properly determine).
174 Mr Gleeson submitted that the key submission put by Cargill at the arb itration was that contained in
para 72 of Cargill’s then submissions, namely that:
In those circumstances [ie non compliance with the requirements] it is submitted that the
Force Majeure notice g iven by Excel on 13 June 2007 was not given as early as practicable as
required by clause 17.2 and is therefore not a valid and effective notice for the purposes of
that clause and thereby the Agreement generally
(that being in a section headed “Whether there has been compliance with agreement in claiming force
majeure” and thus the context in which it was put related to compliance with clause 17.2 from a timing
point of view).
175 An alternative submission was in paragraph 79 of the submissions:
Alternatively, even if Excel’s failure to give notice pursuant to clause 17.2 of the Agreement
as early as practicable does not invalidate the notice completely the delay in giving that notice
has the effect that time lost from the beginning of the interruption caused buy the Force
Majeure event until the notice was given shall count as laytime. This is pursuant to the first
sentence of clause 7.11.2 of the Agreement which provides…
176 Thus para 79 was clearly putting the proposition that there could b e a notice given as early as
practicable but one which also involved a delay for the purposes of clause 7.11.2. The result was said
in para 80 to be that:
Accordingly in those circumstances any Force Majeure period does not commence (and time
does not cease to count for the purposes of laytime) prior to the service of Excel’s Force
Majeure Notice on 13 June 2009 [sic] and until the time it was served.
177 In its submission as to whether and to what extent Excel is relieved from liability, Cargill again p ut
submissions in the alternative; as to where there was no force majeure event; as to whether, if there was
a force majeure event an effect ive notice had been given; and then, thirdly, as to whether (if the events
and circumstances did amount to force majeure fo r the purposes of 7.11 “but the delay in giv ing the
notice pursuant to clause 17.2 means that any time spent or lost from the Force Majeure) the delay
(prior to the issue of the notice) nevertheless did not count against laytime (para 85) and in tha t last
situation it was submitted that the force majeure period did not commence until the notice was given to
Cargill on 13 June 2007.
178 Those written submissions were supplemented by the oral submissions made on behalf of Carg ill by its
then Counsel (Mr Nell SC). Relevantly, the transcript records as follows:
MR NELL: That is the first scenario. The second scenario, which is really the same outcome
and which is picked up by the respondent’s [Cargill’s] submissions, is if the force majeure
notice that was purportedly given was not valid or effective at all, in part icular because it was
not given as soon as practicable in compliance with clause 17.2, the respondent’s primary
submission in that regard is that the clause is then effect ive; therefore time spent or lost as
result of the force majeure event will still count against laytime and the exception that is found
in clause 7.11 would not operate in those circumstances. As a practical matter, the effect of
that is the same as if there was no force majeure event and the figures should therefore be the
same as the first situation.
The third situation, which is also a reflection of the claim made by Excel, is if there was a
delay in giving the force majeure notice, and consistent with clause 7.11.2 … the time between
the force majeure event and the giving of the notice, in effect the period of the delay, will not
count for the purposes of laytime. (my emphasis)
179 Reliance was placed on the second half of the first sentence in clause 7.11.2 that “ If Seller does not
give any notice or Statement of Facts to Buyer as required [by the clause], the time lost shall count as
Laytime”.
180 Mr Nell submitted that if no notice [compliant with clause 17.2] is given, the effect of that would be
that the force majeure notice was given on 13 June and that if there was found to have been a delay in
the giving of the notice for the purpose of that clause, then any time lost or spent because of the force
majeure event from the commencement of that event, whenever it might have been up to that time on
13 June would count again laytime (and then from 13 June onwards). The Arb itrator’s response to that
submission was “If you don’t give the notice the time lost counts as laytime”, to which Mr Nell
responded:
MR NELL: We read that as saying not only if you don’t give a notice but in light of what is
7.11.1, if you don’t give a notice, that complies with 17.2.
THE ARBITRATOR: Well, it says pursuant to 17.2.
MR NELL: Yes. The point that I’m making, and perhaps I’m not making it clear enough, is
that 17.2 requires not only a notice to be physically g iven but that it be given as early as
practicable. If it is not given as early as practicable, then that notice is not a notice pursuant to
17.2 and in those circumstances the first half of 7.11.2 will say that time lost shall count as
laytime.
If however the notice is given and it is construed as having been given but delayed then
the second part of the sentence of 7.11.2 applies, and that is that the delay in giving the
notice from the beginning of the interruption up to the time the notice is given is laytime .
(my emphasis)
THE ARBITRATOR: But assuming that it wasn’t given timeously, why wouldn’t that
second part of the fist sentence of 7.11.2 apply? (my emphasis)
181 (What is said by Mr Gleeson is thus that any reference to clause 7.11.2 in the submissions made to the
Arbitrator was made in the context of the overarching submission that the notice was not given as early
as reasonably practicable. Mr Stevenson accepted that this was true to some extent.)
182 Carg ill contends that the Arbitrator failed to deal with its argument that, by reason of clause 7.11.2,
“any delay” between commencement of the force majeure period and the g iving of the notice meant
that laytime continued (notwithstanding the commencement of the force majeure period) until Excel
gave notice of force majeure in accordance with clauses 7.11.1 and 17.2 of the agreement (and Mr
Stevenson submits that, for the purposes of this argument it is irrelevan t whether or not that notice was
given as early as practicable).
183 Mr Gleeson submitted that the premise on which the A lternative Argument was based was that the fact
that notice was not given as early as pract icable d id not render the notice a nullit y but nevertheless still
meant that there was a delay in giving of the notice. Thus Mr Gleeson submitted that the premise of
both the primary and the alternative argument was that the notice had not been given as early as
practicable; whereas the premise of the argument put to me (which Mr Stevenson says was also put to
the Arbitrator) was that even if a notice was given as early as practicable there could still be delay for
the purposes of clause 7.11.2.
184 As I read the written submissions which were before the Arb itrator, it seems to me arguable that the
submission put to the Arbitrator was premised, as Mr Gleeson suggested, on there being a valid notice
albeit one not given as early as pract icable (as opposed to the argument that there was both a notice
given as early as pract icable and delay); but that the more straightforward reading of the submission
was that advanced by Mr Stevenson. (However, the very fact that there is any serious debate as to how
this submission was premised indicates the difficu lty for Cargill is establishing any manifest error by
the Arbitrator in the dealing by him with this submission.)
185 Accepting that the submission was premised as Mr Stevenson contends, that gives rise to what would
seem to be a contradiction in terms – how can there have been a delay if the notice was given as early
as practicable? The concept of delay, ordinarily, suggests something more than a mere lapse of time.
It suggests that there has been a procrastination or putting off of something that could have happened
earlier (see Macquarie Dictionary defin ition of the word in its usage respectively as verb and noun). It
is in this sense of the word that the Arbitrator himself seemed to approach the argument during the
course of the hearing, when he raised the question as to whether what was being put to him was that
there had been a failure to act ‘timeously’ and the consequences of that.
186 The semantic argument as to whether there can be an operative concept of delay where a notice has
been given as early as practicable does not appear to be one around which there was much debate
before the Arbit rator (there seems to have been no suggestion, for example, that if the two concepts
were mutually exclusive it might be thought that there was no work left to be done by the words in the
second half of the first sentence in 7.11.2). What was not, it seems, made clear to the Arbitrator was
that the alternative argument in para 79 of Cargill’s written submissions was one that meant that any
period of time which elapsed between the commencement of an interruption and the giving of a force
majeure event amounted to ‘delay’ fo r the purposes of the clause (and the Arbitrator cannot in my view
be crit icised or accused of a denial o f natural justice for having not dealt with that particular argument,
albeit that it seems to be the logical extension of what Cargill is now and was then putting). Mr
Gleeson thus contends that what has been done in the present application is to re-cast the ‘delay
argument’ as one which means that if there was any gap in time between the occurrence of the force
majeure event and the giving of the notice then that is delay and has the consequence that time
continues to count towards laytime.
187 Whether or not the alternative argument was art iculated as clearly before the Arbitrator as it was before
me, the notion that delay could be taken into account for the purposes of laytime even if there had been
a valid notice (by which Cargill seemed to be referring to one given as early as possible) seems to me
to have been before the Arbitrator.
188 Mr Gleeson submitted that once it was found that notice had been given as early as practicable there
could be no operative concept of delay in clause 7.11.2 – in effect that this was a contradiction in
terms. (I think there is force in that submission, though the construction of these clauses is not the task
before me.) The concept of delay, it was submitted, must be a reference to a notice which was n ot
given as early as pract icable (ie in respect of which there has been found to be some delay), in contrast
to a notice g iven as early as pract icable. (One might have thought that if any lapse of time was
sufficient for the purposes of calcu lating laytime during a force majeure event then it would have been
simple to p rovide for that expressly, without the need to employ the concept of delay – and that the
failure to give a notice as early as practicable would sound in a different consequence (such as any
damage resulting from the seller not having been on notice of a claim at an early enough time) rather
than one linked to the calculat ion of laytime (which would, on Cargill’s argument, be running in any
event up until a notice was ultimately given).)
189 What did the Arbitrator do?
190 The Arbitrator set out the issues he had identified for determination on the reference in paras 65-66 of
his reasons.
191 The first issue was the ‘disputed amount’ of USD 299,822.47 which related to the demurrage cla imed
for the period 21 to 25 June 2007. The Arb itrator expressly dealt with this on the basis (which he said
accorded with the way the part ies had dealt with it) of an assumption that there was a relevant event of
force majeure attracting the operation of clause 17 and as to whether that had come to an end by 21
June 2007 (as Cargill contended) or 25 June 2007 (as Excel contended). Pausing there, there was no
suggestion that Cargill was in any way estopped or precluded from raising its claim for demurrage for
this period. If, therefore, the Arbitrator’s conclusion as to the construction of clause 7.11.2 was in
error, then the finding as to estoppel/waiver would not preclude recovery for that amount. (The
Arbitrator found against Cargill on this first issue.)
192 The second issue was whether Cargill was entitled to re-open its claim for the undisputed amount (put
by the Arbitrator as ‘whether there was fo rce majeure in terms of the Agreement in respect of the
period 8 to 21 June 2007).
193 The third issue was as to when the force majeure event commenced. The Arb itrator noted that this was
one that arose if the second issue was determined in favour of Cargill (which it was not) but
nevertheless seemed to recognise that Cargill might contend it was entitled to raise the substance of the
third issue irrespective of the finding on the second issue. (That would presumably only be the case if
the commencement of the force majeure period had any relevance to the claim for demurrage in respect
of the later part of the force majeure period, which would seemingly arise only when considering how
laytime was to run for the purposes of that later claim ie whether, on Carg ill’s argument, laytime
continued to run over the force majeure period such that by the commencement of the disputed period
the vessel was already on demurrage. However, it was not suggested before me that there was any
significance to be attributed to the Arbitrator’s comment in this regard.)
194 The fourth and fifth issues related to what part of the defin ition of force majeure was to apply and what
consequences flowed therefrom and the seventh and eighth related to an argument in relation to clause
17.7 of the agreement, none of which are relevant in the present context.
195 The issue which gave rise to the first alleged erro r of law was the sixth issue, namely whether Carg ill
was given the force majeure notice as required by clause 17.2. The Arbitrator addressed this issue from
paragraph 199 of his award. He referred to the notification given by Excel under 17.1 (that being
distinct from a notice of intention to make a claim of force majeure which is dealt with in clause 17.2).
In paragraph 200 the Arb itrator recorded Cargill’s (p rimary) contention, which was that the notice
given on 13 June 2007 was not given as early as practicable after the alleged force majeure event
occurred (there being an issue in that regard as to whether the requirement that the notice be issued as
early as practicab le was to be tested by reference to the alleged force majeure event or the formation of
an intention to make a claim). The Arb itrator found it unnecessary to determine that issue as he was
satisfied that the notice given on 13 June 2007 had been given as early as practicable. (There was no
suggestion that it should, or could feasibly have been expected to, have been given simultaneously with
the force majeure event.)
196 The Arbitrator noted that clause 17.3 p laced importance on compliance with clause 17.1 rather than
17.2 (ie to a notice o f the existence of force majeure events rather than of intention to bring a claim)
and then said that the significance of that factor might be mit igated by the fact that, when clause 7.11
was applicable, reliance is placed on compliance with 17.2. The Arbitrator there s eemed to
contemplate that the circumstances in which a party was not liable by reason of force majeure (clause
17.3) had some connection in terms of its operation with the operation of clause 7.11 as to when and
how time lost on account of force majeure was to be affected by the giving of notice in relation thereto.
197 What the Arbitrator does not seem direct ly to have addressed in his reasons (and this is the nub of the
criticis m now directed by Cargill at the award) is the submission that was put in paragraph 18 of
Carg ill’s submissions (that even if the notice had been given as early as possible, there was
nevertheless an operative delay in the issue of that notice and laytime continued during that period).
198 However, apart from the brief reference during argument to the significance of the notice not being
given timeously, the manner in which Carg ill’s alternative submission was put seems to have been put
was not expressly linked to the proposition that the lapse of any period whatsoever between happening
of a force majeure event and the giving of notice would mean that laytime continued to run.
199 And, insofar as the written submissions referred to the requirement to give the notice as early as
practicable being reinforced by the requirement that there be no delay, there is force in Mr Gleeson’s
submission that the ‘delay’ argument was predicated on there being a finding that notice was not given
as early as practicable (the only distinction between the two arguments being said to be as to whether in
that event the notice was a nullity or had some room for operat ion).
200 Mr Gleeson submits that what the Arbitrator did was to reject the factual premise of the alternative
argument (namely that Excel had failed to give the notice as early as practicable) and thus the delay
argument failed and there was no error by the Arbitrator (nor any need for him separately to articulate
his conclusion in that regard).
201 As the above discussion should illustrate, there were arguments open on both sides in relat ion to the
question as to how clause 7.11.2 should be construed. Insofar as it seems that the Arbitrator formed the
view that if notice was given as early as practicable then there was no relevant delay for the purposes of
clause 7.11.2, I consider that this was a conclusion reasonably arguable and open for him to fin d. That
being the case, whether or not ultimately it might be said to have been wrong, there was no manifest
error of law in the drawing of that conclusion. That disposes of the second threshold requirement for
the grant of leave to appeal.
Weather Working Day ‘error’
202 As to the second error, it is said that the Arbitrator (in accepting the submission of Excel to the effect
that the definition of Weather Working Days in the defin ition of Cargo Handling Rate had the effect
that laytime was suspended during any period in which loading was hindered by bad weather)
misconstrued the agreement (by treating an integer in the calcu lation of Cargo Handling Rate, which
was necessary to determine the allowable period of laytime, as having a substantive negative operation)
and that the Arbitrator impermissibly used the parties’ post -contractual conduct as an aid to
construction (contrary to Agricultural & Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238
CLR 570, at [35], [163]; Franklins v Metcash, at [10]-[13], [58], [306]-[329]).
203 It was conceded that if leave to appeal on the clause 7.11.2 issue were not to be given, then this issue
would not arise.
204 Mr Gleeson noted, by way of background, that the Weather Working Days argument had been rais ed
by Excel as an alternative argument in the eventuality that the Arbitrator did not find that force majeure
had started at 8.15am on 8 June 2007 (but found that it had started at some later time on that day). As I
understand it, Excel’s argument was that if the Iron Braydn came on to demurrage at around 9 o’clock
on 8 June 2007 (as Cargill contends), there was nevertheless an allowance to be made in Excel’s favour
for bad weather and that this operated to reduce the claim for demurrage.
205 The Arbitrator noted Excel’s contention in that regard as being that the approach reflected in Cargill’s
earlier acceptance (that time did not count against Laytime from 7 June 2007 because of bad weather)
could also justify a conclusion that Laytime did not run from at least the time from which Excel relied
on force majeure.
206 “Cargo Handling Rate” was defined in clause 1.1 to mean the rate, as specified in the relevant
specification schedule at which the coal was to be discharged at the Delivery Point “fo r the purposes of
calculating Laytime”. The relevant specification schedule stated that the min imum shipment size was
to be 15,000 Metric Tonnes and that “the Seller shall load shipment aboard the Vessel at the following
average rates per WWD being a day of twenty-four (24) consecutive hours SHINC” (Sundays and
holidays included).
207 The Arbitrator noted in his award that, prima facie, the reference to WWD (Weather Working Day)
appeared to be an integer in the calculat ion of a Cargo Handling Rate but he ult imately accepted the
contention of Excel that it had a substantive negative operation in that any obligation to load, and the
counting of laytime, was suspended during the period when the loading was hindered by bad weather.
208 In coming to a view on this question (which the Arb itrator noted was a difficult issue because in his
view the agreement was not very clear in this respect), the Arbitrator express ly had regard, first, to the
description of Cargo Handling Rate in the Schedule (which he considered was something more than
simply part of a definition - perhaps because it expressed an obligation for the Seller to load the
shipment at the specified average rates) and, secondly, to the conduct of the parties “before Carg ill
sought to resile from its earlier position” (ie their conduct before Cargill reinstated its claim to
demurrage for the whole of the period) which he considered suggested that the partie s understood that
the agreement had the meaning for which Excel contended.
209 Mr Gleeson conceded that the second reason given by the Arbitrator was not strict ly a matter referable
to interpretation of the contract. Nevertheless, it was said that this was simply a recognition that the
parties had acted in a particu lar way, the Arbit rator having observed that this was a belated submission
and seemed to be a response to Excel taking the matter to arbitrat ion. On that aspect, I have difficu lty
accepting that the Arbitrator’s view of the parties’ post-contractual conduct was no more than a
recognition that the parties had acted in a particular fashion and not a factor which had (in conjunction
with the other matter to which reference was made) led the Arbitrator to view the operation of the
Cargo Handling Rate definit ion in the way he did. The Arbitrator exp licit ly made reference to this as
the second of the reasons he had for coming to that view of the definit ion (para 163) and treated it
almost as an admission by conduct (though explaining it in terms of an indication of the parties’
understanding of the operation of the clause). In that regard, it seems to me that to the extent that the
Arbitrator had regard to post-contractual conduct in construing the definition there was strong evidence
of an error of law in so doing.
210 What is not clear is that but for this error the Arbitrator would not still have come to the same
conclusion based on the first matter to which he said he had had regard. (Although expressed as one
of the two matters to which he had regard, this part of the Arbitrator’s reasoning seems to read as if the
Arbitrator was drawing some comfort (from the post-contractual conduct) for the conclusion he was
proposing to draw on the wording of the definition itself.)
211 If the Arbitrator’s conclusion could have been sustained by reference to the first reason set out above,
then the fact that one part of the Arbitrator’s reasoning could not be sustained might not be to the point.
However, it is not clear from the award whether the first reason advanced for treating the definition as
having negative operation would have been sufficient, in the Arbitrator’s eyes, to stand alone and, in
any event, this does not address the issue as to whether the definition could objectively be said to be
intended to have any substantive operation in relation to laytime at all.
212 It is submitted by Mr Gleeson that the finding as to the Weather Working Days issue (though
apparently conceding that reliance on post contractual conduct would not strictly be correct) was not a
manifest error because the approach which the Arbitrator took to the matter was reasonably arguable.
Mr Gleeson pointed to the outline given by the Arbitrator of the circumstances in which this issue had
arisen (Carg ill having initially submitted demurrage calculations with an allowance for bad weather up
to a particular time and then from that time basing the allowance on force majeure, but, by the time of
the arbitration Cargill had submitted that the earlier demurrage calculation had been mistaken), the
Arbitrator’s view being that this was a belated attempt to resile from the earlier approach.
213 As explained by Mr Gleeson, Excel’s argument was that the Cargo Handling Rate defin it ion, which
included the concept of Weather Working Days, encapsulated the concept that if there was not a usable
period of time to load the coal on the ship because of bad weather, that was not taken into account
when calculat ing at what average rate the coal had to get onto the ship. Insofar as the Arb itrator noted
that he considered the argument difficult but made a finding which was reasonably open to him to do
(whether or not he had acted in error in taking into account subsequent conduct) it is submitted by Mr
Gleeson that this does not surmount the high hurdle for manifest error of law. In other words, it is said
that if this is reasonably arguable and a question of construction, whether or not the Arbitrator in fact
reached the wrong conclusion (and how he did so) is immaterial.
214 Mr Stevenson contended that the relationship between the two alleged errors was that the Arbitrator’s
failure to consider Cargill’s alternative clause 7.11.2 argument led him into error in relation to the
weather working point. It is submitted that if the Arbitrator had accepted Cargill’s Alternative
Argument then that would have given rise to an inconsistency with the proposition that laytime d id not
run on any day which was not a weather working day, i.e. for some days after 8 June. (Mr Stevenson
submitted that the weather working day argument was irreconcilab le with the Alternative Argument
advanced by Excel.) (In that regard, the Arbitrator does seem to have had regard to the
interrelationship between the respective clauses in that he saw the weather working day point as
reaching the same outcome as that he had reached on the clause 7.11.2 argument.)
215 It seems to me that the proposition put by Cargill (that WWD was no more than an integer in the
definit ion of the Cargo Handling Rate and thence a step in determining the amount of time to be
allowed as laytime) has considerable force but I do not see this as a manifest error of law on the face of
the award (as opposed to an issue on which there is strong evidence of error). It seems to me that there
were d ifferent conclusions reasonably open as to the construction of the relevant definit ion and its
operation in the context of the agreement as a whole.
216 At para 163 the Arb itrator makes it clear that the reliance made by h im on the defin ition argument was
as support for his primary conclusion on the construction of clause 7.11.2, saying (after having first
concluded that time does not count towards delay from 8.15am on 8 June by reason of force majeure)
that: “I would also accept the same result would be achieved by reliance on the concept of weather
working days”. Mr Gleeson submitted that the finding that loading was hindered by bad weather from
8.15am on 8 June 2007 was a finding of fact. The only question of law was whether, as a matter for
construction, whether the Arbitrator should have accepted the proposition that the reference to weather
working days had a substantive negative operation in the definition. Mr Gleeson says that is not a
manifest error in the sense required by the authorities. I agree.
217 In any event, the Arbitrator’s finding on this issue was not ultimately determinative of Cargill’s claim.
It was an expression of opinion that the same result could have been achieved by a different ro ute. The
Arbitrator was of the view that in the circumstances time did not count towards laytime from 8 June by
reason of force majeure. The fact that he was also prepared to accept that the same result would be
achieved by reliance on the concept of weather working days (paras 162/163) does not take the matter
any further. (Th is, it seems to me, also counts heavily against the exercise of discretion to revisit the
issue assuming the basis for such relief were otherwise made out.)
Strong evidence of error of law and effect of determination on certainty of commercial law?
218 Again, it is noted that the test on this alternative threshold requirement is not who is u ltimately right or
wrong as a matter of law on the disputed question(s) of construction, but the strength of the claim that
there has been an error of law on the construction issues. In the absence of a finding that there has
been a manifest error of law, what is necessary is that there be “strong evidence” that the Arbitrator
made an error of law and that the determination of that question is one which may add or be likely to
add substantially to the certainty of commercial law.
219 In Promenade Investments, at 226, Sheller JA said:
Assuming that there is not a manifest error of law on the face of the award it may be argued
that there is strong evidence that the arbitrator made an error of law and that the determination
of the question may add, or may be likely to add, substantially to the certainty of commercial
law. The requirement that the question be one the determination of which may add
substantially to the certainty of commercial law indicates that it should be one of wider and
greater importance than, for example, the construction of a one-off clause in the context of a
particular agreement between the parties. One can discern here the sort of limitation which
Lord Diplock had in mind. The expression “commercial law” should be given no narrow
construction. The expression “strong evidence that the arbitrator … made an error o f law”
suggests first what might otherwise be called on the leave application a strong prima facie
case and second an error of law not manifest on the face of the award and demonstrable by
evidence. (my emphasis)
220 Is there a strong prima facie case that the Arbitrator made an error of law in not holding that the period
of time between the occurrence of a force majeure event and the giving of a notice of intention to claim
force majeure (whether or not that be as early as practicable) should be counted as laytime? The issues
as framed by the Arbitrator did not require a d irect determination of that question but it was thrown up
by the argument in relation to the adequacy or validity of the clause 17.2 notice.
221 To my mind, both arguments were reasonably available as a matter of construction. As against that
contended for by Cargill, it seems to me that had the parties intended laytime to continue after the
occurrence of a force majeure event up until the time that a notice of intention to cla im force majeure
was given (irrespective of whether that notice was given as early as practicable) then there was a very
simple way to do so and it would not have necessitated the use of any concept of delay. In that regard,
there seems a contradiction in terms between the situation where the notice was given as early as
practicable and that where there was in any event an operative delay for the purposes of counting
laytime. However, whatever the prospects of success for Carg ill’s argument on that point ult imately
may have been, I am not convinced that there is strong prima facie ev idence that the Arbitrator erred in
his construction of the clause.
222 As to the second of the alleged errors, for the reasons adverted to above, I would have been inclined to
find that the weather working days point was one as to which there was strong evidence that an error of
law had been made in this regard (both by reference to the use of post -contractual conduct and by
reference to the application o f a definition used in context for the purposes of another). On this issue I
would have been satisfied that the determination of the construction of clause 7.11.2 and the extent to
which it was affected by the reference to Weather Working Days in the definition of Cargo Hand ling
Rate was one which would be likely to add certainty to commercial law. Th is relates to an issue of
construction of clauses in a standard form agreement (not a one-off determination on the facts of this
particular case.) Even if its use is not as wide as that suggested by Cargill, the construction of such a
clause would in my view have potential significance beyond that of the present case. While the
particular form of the agreement in use has changed, the force majeure provisions have not changed in
the current version and hence I accept that the validity of the construction put by Cargill is one which
would be likely to add to the certainty of commercial law.
223 However, as Mr Stevenson accepts, the alleged error as to the operation of the weathe r working days
definit ion is of no moment unless Cargill obtains leave to appeal on the Alternative Argument in
relation to clause 7.11.2. Therefore this is not an error that of itself would have affected the overall
outcome of the dispute (and thus the first of the threshold requirements is not met in relat ion to this
error).
(iv) Has there been a denial of natural justice for the purposes of a review under the Model Law?
224 It is conceded that there is a more limited basis for review of arbitral awards under the Model Law, that
being contained in article 34. The only relevant basis for review asserted in the present case is that
contained in article 34(2)(b)(ii), namely that the award is in conflict with the public policy of the State.
225 By reference to s 19 of the Commonwealth Act, there is a conflict with the public policy of Australia if
there has been a breach of the rules of natural justice. Mr Stevenson submitted th at the Arbitrator did
not deal with Cargill’s clause 7.11.2 Alternative Argument and thus there has been a breach of the
hearing rule of natural justice.
226 The “hearing rule” (to use the terminology adopted by Aronson, Dyer and Groves, Judicial Review of
Administrative Action, 3rd ed, 2004, at 370) (or audi alteram partem rule), is one of the twin pillars of
natural justice, the other being the bias rule (nemo debet judex esse sua in propria causa) (as explained
in Carbotech-Australia Pty Ltd & anor v Yates & 14 ors [2008] NSWSC 540, at [46], per Brereton J).
(There is no suggestion of bias in this case.) At the most basic level, the hearing ru le requires a
decision-maker to hear a person before making a decision affecting that person's interests.
227 The High Court in Dranichnikov v Minister for Immigration and Multicultural Affairs [2003] HCA 26;
(2003) 197 ALR 389, said at [24];
To fail to respond to a substantial, clearly articulated argument relying upon established facts
was at least to fail to accord Mr Dranichnikov natural justice.
228 The operation of the hearing rule depends on the circumstances of the case in which it is applicable
(Bread Manufacturers of NSW v Evans [1981] HCA 69; (1994) 180 CLR 404, at [18], per Gibb CJ;
Durayappah v Fernando (1967) 2 AC 337, at 414). In Russell v Duke of Norfolk (1949) 1 A ll ER 109,
at 118, Tucker LJ said:
The requirements of natural justice must depend on the circumstances of the case, the nature
of the inquiry, the rules under which the tribunal is acting, the subject -matter that is being
dealt with, and so forth.
229 In Mobil Oil Australia Pty. Ltd. v Federal Commissioner of Taxation [1963] HCA 41; (1963) 113 CLR
475 (at 504) Kitto J stated:
What the law requires in the discharge of a quasi-judicial function is judicial fairness. This is
not a label for any fixed body of rules. What is fair in a given situation depends upon the
circumstances.
230 (The above passages from Mobil Oil and Russel were cited with approval in The Queen v
Commonwealth Conciliation and Arbitration Commission: ex parte Angliss Group (1969) 122 CLR at
546, 552.)
231 The mere fact that a decision is made that is adverse to the interests of a party does not mean that the
party has been ignored or denied natural justice in breach of the hearing rule (Carcione Nominees Pty
Ltd & Anor v Western Australian Planning Commission & Ors [2005] WASCA 56, at [93]).
232 In Bread Manufacturers, whilst it was found that the hearing rule did not apply to the decision maker in
question, Gibbs CJ was of the view that, even if the rule did apply, it would have been satisfied in the
circumstances of that case where “the Commission had received and no doubt considered the
submissions of the Association that prices should be increased, and did make an increase in prices
generally” (at [18]).
233 The Alternative Argument is, I accept, an argument of substance. It cannot be said to be trifling or to
have insignificant consequences if successful. The relevant facts upon which the argument was based
(namely the giving of the notice on 13 June 2007 some days after the event amounting to force
majeure) were established.
234 (So far as the second alleged error is concerned, it is not submitted that there was a denial o f natural
justice by failing to deal with the point - because the argument was clearly dealt with – rather, the
submission is that the Arbitrator was led into the error by his denial of natural justice on the 7.11.2
argument. It is said that had the Arbitrator addressed the clause 7.11.2 argument and seen that it
contradicted the weather working days argument (which he had found to be a d ifficu lt issue) he would
not have come to the conclusion he did on weather working days. Thus it is said that if the matter were
to be re-agitated, the submission would be that if the clause 7.11.2 argument was correct, then the
“tentative” conclusions in relation to weather working days could not be correct.)
235 Where I have some difficulty, however, is as to whether the clause 7.11.2 argument was clearly
articulated. That would be the case only insofar as the Alternative Argument as now put can be said to
emerge clearly from the written submissions and the exchange extracted earlier above.
236 There is considerable doubt in my mind is as to whether what was being clearly articulated in the
submissions put to the Arbitrator is the proposition for which Carg ill now contends, namely that
laytime continues to run unless and until a notice of intention to claim force majeure is given
(irrespective of whether the notice was given as early as practicable) and that on the proper
construction of clause 7.11.2, “delay” in the giv ing of a notice will occur whenever the notice is not
given simultaneously with the force majeure event. There is no suggestion in the Arbitrator’s reasons
that such a proposition was clearly articulated nor does it emerge clea rly from the written submissions
(particularly when reference is made to the statement contained in the submissions that the requirement
for notice to be given as early as practicable is reinforced by the reference to delay in clause 7.11.2).
237 Although Mr Stevenson submitted that there was no need for Mr Nell, Counsel appearing for Cargill on
that application, to make any argument about whether notice was given as early as pract icable in order
to run the Alternative Argument, the argument was linked in the sense that it was predicated on a
determination against Cargill on its principal submission that a notice which was not given as early as
practicable was not valid and effective for the purposes of the agreement.
238 Mr Gleeson’s submission, as I understand it, on the natural justice issue was that on the clause 7.11.2
argument, there are two possibilities: either Excel is correct in its submission that the argument was not
put before the Arbitrator in exactly the way it was put to me (and accordingly Carg ill cannot be heard
to complain that there was a denial of natural justice by reason of any failure to deal with the argument
in the way in which it was put) or, if the argument put to the Arb itrator was, as Excel contends,
predicated on there being a notice which was not given as early as practicable (but nevertheless still a
valid notice), then the Arbitrator dealt with it and there was no denial of natural justice (even if the
Arbitrator may have been wrong).
239 I accept Mr Gleeson’s submission that there is nothing in what was put to the Arbitrator which squarely
raised the proposition that if the notice is valid and effective (because it was given as early as
practicable) clause 7.11.2 nevertheless has the effect that time does not count on force majeure because
any gap in time between the objective event of force majeure and the giving of the notice is delay. The
proposition that one can satisfy a contractual obligation to do something as early as practicable but at
the same time there can be an operative delay was not one that seems to me to have been clearly put to
the Arbitrator.
240 If, closely read, the written submissions did go so far, is there anything to suggest that the Arbitrator
did not properly consider the argument just because it was not articulated in those terms in the award?
The Arbitrator clearly addressed his mind during the course of argument to the question of what
consequence might flow from the fact that the notice was not given t imeously. Ult imately, his finding
was that the notice was given as early as practicable and, by reference to the result which followed
from that, he must have considered that there was no delay for the purpose of clause 7.11.2 where there
was a notice which had been given as early as practicable.
241 In the circumstances, I am not satisfied that the argument now sought to be put by Cargill was clearly
articulated before the Arbitrator. That disposes of the claim that there has been a denial of natural
justice. Insofar as a version of the argument was put, it seems to have been heard by the Arbitrator and
what he has done is to reach a conclusion which implicitly rejected it. I am not satisfied that this
amounts to a denial of natural justice.
(v) Discretionary issues
242 This issue does not arise on the application fo r leave to appeal under the State Act, as the jurisdictional
and threshold requirements for leave under the State Act have not all been established. Had they been,
then I would have approached the question of discretion cognisant of the weight evident from the
legislation placed on the exercise of judicial restraint in interference with or intervention in arbitral
decisions which otherwise would be final and binding. I accept that there should be only limited curial
intervention. Similar issues arise when considering the exercise of discretion under the Model Law,
though they do not strictly arise for determination in the present case as I have not found a denial of
natural justice.
243 In its Commercial List Response, Excel raises the following matters in relation to whether the court
should exercise discretion to grant leave to appeal (assuming the jurisdictional and threshold
requirements have been satisfied:
(a) the one-off nature of the force majeure events giving rise to the dispute;
(b) the qualifications of the arbitrator (he being an experienced Queen’s Counsel and former
Federal Court Judge) appointed by agreement of the parties as sole arbit rator in order to
resolve their dispute;
(c) the amount in dispute (demurrage from 8 June being calculated at USD850,000, or from 21
June as being in the order of USD300,000) weighed against the (unquantified) cost of further
proceedings to review the partial award;
(d) the assertion that this is an attempt generally to re-litigate the subject matter of the arbitration;
(e) that the contentions, to the extent that they raise questions of law, are inappropriate for leave
to appeal as they involve issues of fact that must be reviewed or decided in order to d ispose of
the alleged questions of law;
(f) that the contentions, to the extent that they raise questions of law, do not involve bare
questions of law, but rather the examinat ion of how, against the contractual structure, the
parties acted in the particular case; and
(g) that, if leave is granted, the court is asked to determine the rights arising from the parties’
conduct rather than to determine questions of law arising from contractual documents o r
referred to in the partial award or on other discrete questions of law arising out of the partial
award.
244 As to the last three grounds, they were not raised in oral submissions and it is not clear to me how it is
said that the determination o f the construction questions as put to me would involve any need to revisit
factual findings of the Arbitrator.
245 What seems to me to be more relevant is that the determination of the first alleged error would not
overcome the finding in relation to estoppel/waiver in respect of the claim for demurrage fo r the bulk
of the period claimed and the determination of the second alleged error would take the matter no
further as this was no more than an alternative means of reaching a conclusion already. As to the other
grounds, the most relevant seem to me to be the fact that the financial consequences to flow from any
re-determination are by no means as substantial as have been asserted (and, in view of the find ing as to
the clause 17.3 operation, there may be little practical benefit at all from a reconsideration of the
matters of which complaint is made) and the fact that Cargill has had a considered hearing (and one on
far more than the usual number of issues for this kind of arbitration in the opinion of the Arbitrator).
246 In Promenade Investments, after considering the language used in the expression “manifest error”,
Sheller JA went on to say, at 225:
Nothing more is to be learnt from the language used but of course the discretion of the court
as to whether or not it will grant leave remains and regard must be had to the requirement of
subs (5)(a). The matters referred to by Lord Diplock in The Nema remain important factors in
determining whether leave should be given. [His Lordship there having raised the reluctance
to grant leave for a one-off question]
247 As to the discretion, in Promenade Investments, at 221, Sheller JA said:
In his second reading speech the then Attorney-General said that one of the major objectives
of this uniform legislat ion was to min imise judicial supervision and review (New South Wales
Parliamentary Debates, 22 November 1990, 10376 at 10378):
“If arbitration is to be encouraged as a settlement procedure and not as a dry run
before lit igation, a more restrict ive criterion for the granting o f leave is desirable and
the parties should be left to accept the decision of the arbitrator whom they have
chosen to decide the matter in the first place.”
The added requirements of manifest error of law on the face of the award or strong evidence
that the arbitrator made an error of law and that the determination of the question may add
substantially to the certainty of commercial law suggest that the draftsman was seeking to
constrain the exercise of court control over arbitral awards in the manner described by the
House of Lords in The Nema. A manifest error of law on the face of the award may be an error
which would be apparent to the judge upon a mere perusal of the reasoned award itse lf
without the benefit of adversarial argument. A determination which adds substantially to the
certainty of commercial law may be a determination of a question of the construction of a
contract in standard terms rather than the construction of a one-off clause. In such a situation,
strong evidence that the arbitrator made an error of law may equate with a strong prima facie
case that the arbitrator had been wrong in his construction.
248 I am not satisfied that this is a case (had the jurisdictional and threshold requirements been satisfied for
the grant of relief either under the State Act or the Model Law) in which, as a matter of discretion,
leave to appeal or the remission of the matter to the Arbit rator should be granted or ordered as the case
may be. The complexity of the construction issues as now put, when coupled with the fact that they do
not appear to have been clearly art iculated in that fashion before, suggests strongly that this is an
attempt to re -lit igate the issues which have already been dealt with in some detail. There should be
finality in that exercise, as provided for under the parties’ arbitration agreement.
Conclusion
249 For the reasons outlined above, I am of the view that the parties did not opt out of the Model Law and
hence the State Act does not apply. (Had I found otherwise, I would have held that the claims made in
the arbitration were maritime claims for the purposes of overriding the parties’ exclusion agreement
and hence this Court would have had jurisdiction to entertain the application for leave to appeal.)
250 Had the State Act applied, I would not have been satisfied that the threshold requirements for the grant
of leave to appeal were met. Although I consider there is strong evidence of error in relat ion t o the
conclusion drawn as to the operation of the definition of weather working days for the purposes of
calculating laytime, and I accept that this question is one the determination of which is likely to add to
the certainty of commercial law, it is a question which (considered in isolation of the Alternative
Argument in relat ion to clause 7.11.2) would not substantially affect the parties’ rights. In any event I
would not have been satisfied that this was a case in which I should have exercised discretio n to grant
leave to appeal in relation to that alleged error.
251 I am not satisfied that there has been a denial of natural justice.
252 I therefore d ismiss the application by Carg ill. As Mr Gleeson indicated that, in that event, Excel would
wish to be heard in relation to costs, I will deal with that aspect of the matter at a time convenient to
Counsel.
**********