New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting,...

25
New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV

Transcript of New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting,...

Page 1: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

New ProjectsProjects In-process

Deferred Projects

West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV

Page 2: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

New ProjectsProjects In-process

Deferred Projects

West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV

Page 3: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. Joint ON Line [Financial close 2-11-11]2. 230 kV Shunt Reactors [Completed] 3. Harry Allen 345/230 kV Transformer Bank 24. Harry Allen – Northwest 500 kV Line Permitting5. Northwest - Amargosa 500 & 230 kV Permitting6. Harry Allen – El Dorado 500 kV Line Permitting

Page 4: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. Northwest 2nd 500/230 kV Transformer2. Mohave Decommissioning Requirements3. Harry Allen Combined Cycle Interconnection4. Carson Lake 230 kV5. Bordertown 345/120 kV transformer6. VEA Interconnection @ Northwest7. EEI STEP Autotransformer Project8. Westconnect

Page 5: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. Sunrise 500 kV Tap2. VARs Thunderbird Substation3. Blackhawk Substation

Page 6: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

Construct ◦ 235-mile 500 kV transmission line Robinson-Harry Allen◦ Robinson Summit 500/345 kV substation◦ Falcon-Gonder Fold◦ Add 70% series compensation: 35% at Falcon and 35% at

Robinson◦ Harry Allen Terminal

ON Line flow◦ ~ 600 MW SPPC to NPC◦ ~ 600 MW NPC to SPPC

Total Project estimate $509.6M◦ $14.7M in 2010◦ $217.6M in 2011◦ $262.5M in 2012

Page 7: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

Three 100 MVAR shunt reactors◦ Decatur◦ Equestrian◦ Magnolia

Required due to high voltage on the transmission lines during light loads 

Off-peak voltages are at 242 kV limit for 230 kV-class equipment, reactors are needed to prevent damage

$9.2M in 2010

Page 8: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

PacifiCorp has submitted a request to Nevada Power for the addition of a second 345/230 kV transformer at Nevada Power’s Harry Allen Substation. The project is under construction, ISD: 6/15/2011. With its installation, TOT 2C (WECC Path 35) rating will increase to 400 MW N-S and 580 MW S-N.

Used to serve load in Red Butte, Utah. The Red Butte load is primarily served by the Utah Associated Municipal Power Systems (“UAMPS”), which is in the PacifiCorp Balancing Authority Area.

PACE to pay project costs

Page 9: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

This Project is the permitting & acquisition of a 500 kV line ROW Harry Allen to Northwest Substation

This route is needed to eliminate the 2x1500 MW transformer (2014+) loss under a Lenzie – NW 500 kV outage.  This parallel line would mitigate this N-1 substantially and thereby delay expensive upgrades.

This project is the permitting & acquisition of 230/500 kV line ROW from Northwest Substation into the Amargosa Valley

 This line would also enable the delivery of high levels of solar from the Amargosa Valley via the NW sub, reinforce NW substation for a west side 500 kV line,  and remove the need to build through Pahrump to second source NW sub (a 160 mile 500 kV detour)

This Project is the permitting and acquisition of a 500 kV line right-of-way from Harry Allen Substation to El Dorado Substation

NV Energy was directed to re-submit request after further development.

Page 10: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

Studies in 2006 indicated a 2010 need for a second Northwest 500/230 kV transformer to meet projected load growth in the Las Vegas Valley.

Postponed until 2014+, using RAS with Gen trip and 500 -> 230kV flow redirection through Crystal PSTs.

Projected “flat” load growth in the Las Vegas Valley allows this postponement.

Page 11: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

New 230 kV, 30 mile line to interconnect ~150 MW of new geothermal resources and provide a second source to Fallon, Nevada.

Approved in 2007 with a 2013 COD.

Estimated budget is 35.0 M

Page 12: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

New 345/120 kV, 280 MVA transformer and ~15 miles of 120 kV line to provide additional capacity to west Reno and Lake Tahoe.

Approved in 2007 with a 2012 COD.

Has been delayed to 2014 by permitting

Estimated budget is 20.4M

Page 13: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

The owners of the Mohave Generating Station are decommissioning the facility and removing the existing Mohave 13.8 kV reserve bus. The bulk of the existing Mohave 500kV facilities will remain.

The existing 69/13.8/500 kV interconnection has acted as a second source for the Nevada Power transmission system with a peak backup capacity of 50 MVA.

When the reserve bus is removed, Nevada Power will need a second service point to maintain reliability.

New 2 span 500 kV line required.

Page 14: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

Transmission work required to interconnect the 489 MW HA CC to the Harry Allen 500 kV Substation.

◦ Including the transmission line about 0.5 miles◦ The new 500 kV line terminal at Harry Allen◦ The relocation of the APEX line terminal at Harry Allen.

June 1, 2011 expected HACC COD

Page 15: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

VEA has submitted an interconnection request to Nevada Power for the interconnection of the VEA’s Sterling 230 kV substation to Nevada Power’s Northwest 230 kV substation.

The interconnection will allow VEA to meet NERC voltage reliability requirements during N-1 contingencies.

The transmission line is proposed to be forty-two (42) miles long, energized at 230 kV and utilize 954-ACSR.

The VEA interconnection project was approved by the Commission in the 2006 IRP.

Page 16: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

The Commission approved $4.5M in funding for the EEI Step Transformer Sharing Program in Amendment Four of the 2006 IRP. $1.5M was spent prior to 2010.

Nevada Power is requesting the Commission to authorize Nevada Power to spend $4.0 M in Action Plan Period 2010-12.

Page 17: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

Nevada Power has been authorized by the Public Utilities Commission to fund its participation in WestConnect during the 2009 IRP Action Plan Period.

Nevada Power participates in the WestConnect Steering

Committee and Transmission Planning Committee.

Sierra Pacific Power has been authorized by the Public Utilities Commission to fund its participation in WestConnect during the 2009 IRP Action Plan Period.

Sierra Pacific Power participates in the WestConnect Steering

Committee and Transmission Planning Committee.

Page 18: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

The Commission has approved about $12.8M dollars for Sunrise Tap lands only: for the 500/230 kV substation and 230 kV ROWs.

Sunrise has been deferred until 2018

The Commission approved about $54.1M in the 2006 IRP for Thunderbird (lands and construction) only about $1M has been spent to date.

Thunderbird has been deferred until about 2017 and will likely be deferred longer if the load forecast remains flat.

The Commission approved $29.8M in the 2004 IRP for Blackhawk Substation.

Blackhawk has been indefinitely deferred and will likely be driven by renewable development if it goes forward.

Page 19: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

Required by Assembly Bill 387

Regulated under PUCN Docket 09-07010

Identifies transmission plans and costs to access RETAAC/PUCN approved renewable energy zones

Filed in each NV Energy triennial Integrated Resource Plan

First RECTP filing was July 1, 2010

Page 20: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

New ProjectsPROPOSED PROJECTS

West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV

Page 21: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. O'Banion – Elverta/Natomas 230 kV Double Circuit Line

◦ Joint Project with WAPA◦ Scheduled for Completion May 2011

2. 230 kV Shunt Capacitor at Natomas (50 MVAR)

◦ Scheduled for Completion June 2011

Page 22: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. Convert Sutter – O’Banion 230 kV Line from Single to Double Circuit

2. 200 MVAR 230 kV Shunt Caps

3. Power Factor Improvement Program

4. Iowa Hill Pumped Storage Plant (400 MW)

Page 23: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

New ProjectsPROPOSED PROJECTS

WestConnect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV

Page 24: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. O'Banion – Elverta/Natomas 230 kV Double Circuit Line

◦ Joint Project with SMUD◦ Scheduled for Completion May 2011

2. Upgrade Tracy Sub to DBDB Configuration◦ Scheduled for Completion last quarter 2012

3. Reconductor Shasta - Flanagan – Keswick 230 kV Line

◦ Scheduled for Completion June 2014

Page 25: New Projects Projects In-process Deferred Projects West Connect Annual Stakeholders Meeting, February 17, 2011, Las Vegas, NV.

1. Convert Sutter – O’Banion 230 kV Line from Single to Double Circuit

2. Fiber Optic addition to Hedge – Tracy 230 kV line

3. Reconductor the Elverta – Tracy 230 kV lines