New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to...

66
Appendix A NOISE AND VIBRATION ASSESSMENT

Transcript of New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to...

Page 1: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

Appendix A NOISE AND VIBRATION ASSESSMENT

Page 2: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.
Page 3: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

TRANSPORT FOR NSW

New Intercity Fleet Eveleigh Facility Project NOISE AND VIBRATION ASSESSMENT

MARCH 2017

Page 4: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.
Page 5: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

WSP | Parsons Brinckerhoff Level 1, 41 McLaren Street North Sydney NSW 2060 GPO Box 6245 Sydney NSW 2060

Tel: +61 2 8907 0900 Fax: +61 2 8907 0999

www.wsp-pb.com

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for its intended purpose. Any unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly prohibited. If you have received this document in error or by any means other than as authorised addressee, please notify us immediately and we will arrange for its return to us.

Report ref: 2202522PA-170223-CXM-REPORT Noise Impact Assessment Eveleigh NIF edited for accessibility Date: March 2017

REV DATE DETAILS

00 9/12/16 Internal draft

01 9/12/16 Draft issue

02 24/01/2017 Updated Draft Issue

03 8/03/2017 Final

New Intercity Fleet Eveleigh Facility Project NOISE AND VIBRATION ASSESSMENT Transport for NSW

Page 6: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.
Page 7: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

i

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

TABLE OF CONTENTS EXECUTIVE SUMMARY .............................................................................................. V

1 INTRODUCTION ............................................................................................ 1 1.1 Scope of this report ................................................................................................................ 1

2 PROJECT DESCRIPTION ............................................................................. 3 2.1 Project overview...................................................................................................................... 3 2.2 Location ................................................................................................................................... 3 2.3 History of operations .............................................................................................................. 3 2.4 Assessment terminology ....................................................................................................... 4

3 SENSITIVE RECEIVERS ............................................................................... 7

4 EXISTING ENVIRONMENT............................................................................ 9 4.1 Noise monitoring methodology ............................................................................................. 9 4.2 Noise monitoring results ........................................................................................................ 9

5 ASSESSMENT CRITERIA ........................................................................... 15 5.1 Operational ............................................................................................................................ 15 5.2 Construction .......................................................................................................................... 16 5.3 Sleep disturbance ................................................................................................................. 18 5.4 Off-site road traffic ................................................................................................................ 19 5.5 Vibration ................................................................................................................................. 19

6 OPERATIONAL ASSESSMENT .................................................................. 23 6.1 Introduction ........................................................................................................................... 23 6.2 Existing operations ............................................................................................................... 23 6.3 Commissioning activities ..................................................................................................... 23 6.4 Maintenance and stabling activities ................................................................................... 29 6.5 Other operational changes .................................................................................................. 30 6.6 Operational vibration assessment ...................................................................................... 30

7 CONSTRUCTION NOISE ASSESSMENT ................................................... 31 7.1 Assessment scenarios ......................................................................................................... 31 7.2 Assessment method ............................................................................................................. 32 7.3 Noise source levels .............................................................................................................. 32 7.4 Predicted noise levels .......................................................................................................... 34 7.5 Assessment of predicted noise levels ................................................................................ 35 7.6 Sleep disturbance ................................................................................................................. 35

Page 8: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

ii

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

CONTENTS (Continued)

8 CONSTRUCTION VIBRATION ASSESSMENT ........................................... 37

9 CONSTRUCTION NOISE AND VIBRATION MANAGEMENT .................... 39 9.1 Application of additional mitigation measures .................................................................. 42

10 OFF SITE ROAD TRAFFIC NOISE .............................................................. 43

11 SUMMARY OF ENVIRONMENTAL NOISE AND VIBRATION IMPACTS ..................................................................................................... 45

L i s t o f t a b l e sTable 3.1 Noise catchment areas ........................................................................................................... 7 Table 4.1 Noise measurement equipment ............................................................................................. 9 Table 4.2 Unattended noise measurement results (dBA) .................................................................... 10 Table 4.3 Short term attended noise monitoring results ...................................................................... 10 Table 5.1 Operational criteria for closest residential receivers ............................................................ 16 Table 5.2 Operational criteria for non-residential receivers ................................................................. 16 Table 5.3 Interim Construction Noise Guideline construction noise management levels

for residential receivers and working hours .......................................................................... 17 Table 5.4 Construction noise management levels for residential receivers ......................................... 18 Table 5.5 Noise management levels at sensitive land uses (other than residences) .......................... 18 Table 5.6 Applicable Road Noise Policy assessment criteria .............................................................. 19 Table 5.7 BS7385 Cosmetic damage criteria, peak component particle velocity,

(mm/s 1) ................................................................................................................................ 20 Table 5.8 Guideline values for short term vibration on structures (DIN 4150-3),

guideline values for velocity, (mm/s) .................................................................................... 20 Table 5.9 Vibration limits (human comfort), Vibration dose value, (m/s1.75) ......................................... 21 Table 6.1 NIF train commissioning assessment scenarios .................................................................. 24 Table 6.2 Noise source levels .............................................................................................................. 25 Table 6.3 Source directivities, adjustment by angle (dBA) ................................................................... 25 Table 6.4 Predicted noise levels at nearest sensitive receivers ........................................................... 26 Table 6.5 Effectiveness of mitigation measures ................................................................................... 28 Table 7.1 Construction assessment scenarios ..................................................................................... 31 Table 7.2 Construction equipment sound power levels ....................................................................... 33 Table 7.3 Predicted noise levels for subject site 1 construction activities ............................................ 34 Table 7.4 Predicted noise levels for subject sites 2 and 3 construction activities ................................ 34 Table 7.5 Sleep disturbance assessment for residential NCAs ........................................................... 36 Table 8.1 Indicative safe working distances for construction vibration ................................................ 37 Table 9.1 Transport for NSW Construction Noise Strategy standard mitigation

measures .............................................................................................................................. 39 Table 9.2 Indicative noise reduction from construction controls .......................................................... 41 Table 9.3 Application of mitigation measures in addition to Transport for NSW

Construction Noise Strategy standard mitigation measures ................................................ 42 Table 11.1 Summary of noise and vibration impacts using recommended mitigation ........................... 45

Page 9: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

iii

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

L i s t o f f i g u r e sFigure 2.1 Facility layout .......................................................................................................................... 5 Figure 3.1 Subject Site locations, NCAs and noise monitoring locations ................................................ 8

L i s t o f a p p e n d i c e sAppendix A Noise Monitoring Data

Page 10: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

iv

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 11: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

v

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

E X E C U T I V E S U M M A RYWSP | Parsons Brinckerhoff Acoustics have been engaged to provide an operational and construction noise and vibration assessment for activities and modifications at the Eveleigh Maintenance Facility associated with the New Intercity Fleet (NIF) being commissioned and maintained at the facility.

The facility has a number of different users on the facility which provide maintenance and stabling services for Millennium, Oscar, Endeavour and XPLORER fleets in addition to heritage trains. The Millennium and Oscar fleet maintenance is done in sheds in the west of the facility. The Endeavour and XPLORER fleet are maintained in the Eveleigh Maintenance Centre (EMC) and heritage trains are operated and maintained by 3801 Limited within the Large Erecting Workshop.

The modifications to the existing infrastructure to accommodate the NIF trains includes:

extending the existing decanting facility

extending the Eastern Siding and Engineering Roads 1 and 2

extending the overhead wiring (OHW) in the Millennium shed and

modifying the supporting infrastructure (e.g. signals, lighting, driver’s walkways) associated with theabove extensions.

In addition to these modifications, the NIF will be delivered to the facility by diesel locomotive and then undergo static and dynamic commissioning activities at the facility. Once the commissioning has been completed, the facility will be used for routine maintenance of the NIF when it enters service. The Millennium fleet maintenance will be moved to another site on the network.

The facility is surrounded by a mix of residential, commercial and rail corridor land uses. The closest residential receivers are located on the southern boundary of the facility on Rowley Lane, Explorer Street and Railway Parade. The next closest residential receivers are located across the rail corridor on Wilson Street and also to the north east on Cornwallis Street. The facility is also adjacent to the Australian Technology Park, which is located on its eastern boundary. The surrounding receivers were grouped into noise catchment areas (NCA), labelled A to H, based on the land use and distance from the facility.

The existing noise environment was characterised by a series of short term and long term noise measurements. An unattended noise monitor was established at the southern boundary close to the potentially most affected residential receivers. The noise environment at other receivers was characterised by attended noise measurements. The background noise environment at all of the receivers was dominated by urban hum during the day, evening and night. Noise from the existing facility was audible at the closest receivers to the south.

Assessment criteria for the facility was established using the Industrial Noise Policy (EPA, 2000) and the noise measurements for operational changes. Construction noise criteria were established using the Interim Construction Noise Guideline (EPA, 2009) and the Construction Noise Strategy (Transport for NSW, 2013. Criteria for off-site road traffic noise impacts was established using the Road Noise Policy (EPA, 2011). Criteria for vibration impacts were established using Assessing Vibration: A Technical Guideline (Vibration Guideline) (DEC, 2006) and DIN Standard 4150-2 Part 3: Structural Vibration in Buildings: Effects on Structures (DIN Deutsches Institut für Normung, 1999).

The operational noise assessment was concerned with the impacts associated with operational changes which occur as a result of the infrastructure extensions, the commissioning and maintenance of NIF trains.

Existing operations, aside from those associated with maintenance of the Millennium fleet are not expected to change as a result of the introduction of the NIF and are therefore were not assessed.

Page 12: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

vi

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network. The delivery and shunting of the NIF will require diesel locomotives to be used within the facility. Up to five NIF trains could be being commissioned at any one time.

The static commissioning is expected to include full testing of all on board services, the most noise intensive being air conditioning, compressors, static inverters, digital voice announcements, brakes and horns.

The assessment predicted noise levels at the nearest sensitive receiver from the commissioning activities in addition to the use of the diesel locomotives in the facility using conservative assumptions as detailed in the report.

The predictions indicated that use of diesel locomotives and the simultaneous commissioning of all five NIF trains would exceed the operational noise criteria at the nearest receivers in NCA D. Receivers in the other NCAs are not predicted to be impacted by the commissioning. As a result of the predicted exceedance, a number of mitigation measures were recommended:

scheduling the commissioning activities to occur during the day period, where possible

scheduling specific commissioning activities to not occur simultaneously on all five trains

limiting the use of the diesel locomotives in the facility

utilising screening from static trains, the train wash or other buildings within the facility wherelocomotives are required to stand on idle.

After the trains have been commissioned, the facility will be used for routine maintenance of the NIF trains. The maintenance required for the NIF trains will be similar to that already carried out on the Millennium fleet at the facility. In addition the NIF will be subject to the same noise emission standards as existing rolling stock and therefore would not generate more noise than existing trains. As a result, noise impacts from regular maintenance activities are not expected to change with the introduction of the NIF.

The modifications to the existing infrastructure are predicted to result in an increase in the operational noise level by less than 3 dBA. A change in noise level of 3 dB or more is typically considered the smallest noticeable change by the average person. As a result, these modifications are not considered to significantly change the noise impact of the facility.

Impacts associated with the commissioning activities are expected to be carried out over a period of four years. The predicted noise levels indicated that the first two rows of houses adjacent to the facility on Rowley Lane would be impacted during the worst case commissioning activities when all activities are occurring at the same time. Mitigation and management measures were investigated to reduce noise levels which indicated that noise levels could be reduced towards the PSNLs by utilising a number of measures where reasonable and feasible.

Furthermore the residential buildings on Rowley Lane were built after the facility was operating in its current state. As the dwellings were built adjacent to an industrial facility it is assumed that they have sufficient ventilation systems to allow for windows to be closed. Noise levels estimated inside the dwellings with windows closed are expected to meet the internal design noise levels in AS 2107 Acoustics – Recommended design sound levels and reverberation times for building interiors for sleeping areas.

The use of horns within the facility was predicted to exceed the sleep disturbance screening criterion. As a result, it is recommended that the horns be managed in a similar manner as they are now which includes testing horns on the network instead of at the facility.

The construction of the modifications are expected to generally occur during standard hours (Monday to Friday 7am to 6pm and Saturdays 8am to 1pm). Work outside of these hours may occur for the overhead wiring connections when a possession is required.

Page 13: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

vii

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

The construction noise assessment indicated that only the closest receivers to the construction works were expected to be impacted above the construction noise guidelines. No residential receivers were predicted to experience noise levels above the highly noise affected level. The assessment indicated impacts as follows:

NCA A and B would be impacted above the noise management levels (NML) during demolitionworks at the Eastern Siding

NCA C commercial receivers would be impacted above the NMLs for all assessed activities carriedout at the Eastern Siding

NCA D would be impacted above the NMLs for demolition and installation of overhead wiring

NCA F, G and H would be impacted above the NMLs for demolition and track extension works.

As a result of the predicted exceedances, a number of noise management measures have been recommended.

No off site road traffic impacts above the guideline levels are expected as a result of the operational or construction phases of the project.

Vibration impacts are not expected from construction or operation of the project, as long as the safe working distances for equipment are complied with and operational activities are consistent with that currently undertaken. The condition of any heritage item should be assessed prior to assigning a vibration limit.

Page 14: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

viii

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 15: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

1

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

1 INTRODUCTIONWSP | Parsons Brinckerhoff has been commissioned on behalf of Transport for NSW to prepare the noise and vibration impact assessment (NVIA) for the proposed changes to the Eveleigh Maintenance Facility for the New Intercity Fleet (hereafter, referred to as ‘the project’). The purpose of the NVIA is to support the Review of Environmental Factors (REF) for the project.

This NVIA is one of a number of technical reports supporting the REF for the project.

The facility currently operates as a rail maintenance and stabling facility for Sydney Trains Millennium and Oscar fleets, NSW Trainlink Endeavour and XPLORER fleets and 3801 Limited’s heritage rail fleet.

The project proposes to modify existing track and supporting infrastructure within the facility to accommodate the commissioning, maintenance and stabling of the New Intercity Fleet.

1.1 Scope of this report

The scope of this report is to assess the potential construction and operational noise and vibration impacts associated with the modifying the facility.

Page 16: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

2

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 17: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

3

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

2 PROJECT DESCRIPTION2.1 Project overview

To support the introduction of the New Intercity Fleet (NIF), a suitable facility is required to serve as a commissioning and maintenance site for the new trains. The existing Eveleigh Maintenance Facility (referred to hereafter as “the facility”) is located approximately two kilometres south west of the Sydney Central Business District (CBD) and has been identified as the preferred location to support the commissioning and maintenance operations for the NIF.

To accommodate the NIF, Transport for NSW are proposing to undertake track, civil and overhead wiring (OHW) modifications at the facility which are longer than the current intercity fleet. The key activities would include:

extension of Engineering Roads 1 and 2 and the associated OHW by approximately 49 metres

extending the suction and non-potable water supply and the installation of additional decant pointassociated with the existing decant facility, to accommodate Long NIF decanting on both tracks

relocation of the existing Welder’s facility (located within the Welder’s Training Annex building) toanother building / location within the facility or at an offsite location

demolition of the Welder’s Training Annex building

extension of the OHW for the full length of Roads 6 and 7 in the Millennium Shed

extension of the Eastern Siding by approximately 26 metres

static commissioning of the NIF within the Millennium shed

dynamic commissioning of the NIF on the Sydney Trains network

routine maintenance and stabling of the NIF.

2.2 Location

The facility is located immediately south of the existing rail corridor, approximately 300 metres east of Erskineville station and approximately 250 metres west of Redfern station. The rail corridor encompasses the T1 (North Shore, Northern & Western Line), T2 (Airport, Inner West & South Line), T3 (Bankstown Line) and T4 (Eastern Suburbs & Illawarra Line) lines.

The facility is bordered by mixed land uses including the residential area of Eveleigh, the Australian Technology Park (ATP) to the immediate south and east and the existing rail corridor to the immediate north. The ATP is a commercial district, occupied by numerous Government and privately owned firms.

The facility has been highly modified as part of its historical and current use as a train stabling and maintenance facility. Direct vehicle access to the site is provided by an existing access road off Railway Parade, Eveleigh.

The location of facility is shown in Figure 2.1.

2.3 History of operations

The facility has been operating as a train commissioning, stabling and maintenance facility since 1888 when the Eveleigh Railway Workshops was established. Since 1888, the facility has undergone a number of modifications and additions to support the increase in passenger train movements and the introduction of new train fleets over time. The facility is of exceptional historical and social significance, with its location wholly within the curtilage of the Eveleigh Railway Workshops, listed as item 01140 on the NSW State Heritage Register (SHR).

Page 18: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

4

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Currently, Sydney Train’s suburban fleet and the intercity fleet operated by NSW Trainlink utilise the facility for stabling and maintenance purposes. The facility also supports the stabling and maintenance of steam and diesel engine heritage trains which are operated by 3801 Limited.

2.4 Assessment terminology

For the purposes of this assessment, the following definitions are used:

the ‘project’ refers to:

all physical modification works to be undertaken to accommodate the commissioning, stabling andmaintenance of the New Intercity Fleet at Eveleigh

commissioning, stabling and ongoing maintenance operations associated with the New IntercityFleet at Eveleigh

the ‘Eveleigh Maintenance Facility’ (the facility) refers to the boundary of the train stabling andmaintenance yard, which incorporates all existing internal tracks and buildings as shown in Figure 2.1

the construction works footprint has been divided in to three distinct study areas based on their locationwithin the facility and are referred to as:

subject site 1 – Engineering Roads 1 and 2 subject site 2 – Millennium Shed subject site 3 – Eastern Siding.

Page 19: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

5

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

Figure 2.1 Facility layout

Page 20: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

6

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 21: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

7

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

3 SENSITIVE RECEIVERSThe facility is located in an area of mixed land use. The facility is bounded to the north by the main suburban rail corridor with medium and high density residential properties along Wilson Street, Holdsworth Street and Leamington Avenue and the Carriageworks commercial premises located along the northern side of the rail corridor.

To the east of the facility is the Australian Technology Park (ATP) which is made up of various commercial land uses. At the eastern end of the ATP there are residential apartment buildings located on Cornwallis Street.

The south of the facility is bounded by multi-storey residential apartment buildings. The west of the facility is bounded by the Illawarra line rail corridor and beyond that there are medium and high density residential buildings on Burren Street.

The Macdonaldtown stabling yard is located to the northwest of the facility and includes a number of large concrete noise barriers along the length of Leamington Lane and along the western side of the Illawarra rail corridor on Burren Street.

The location of the sensitive land uses and existing noise barriers are presented in Figure 3.1.

Sensitive land uses have been grouped into noise catchment areas (NCAs). In each of these NCAs, representative receivers have been selected to assess the noise levels at that receiver and those in its vicinity with similar acoustic conditions. The location of the NCAs and representative receivers are shown in Figure 3.1. The details of the representative receivers are presented in Table 3.1.

Table 3.1 Noise catchment areas

NCA DESCRIPTION LAND USAGE CLOSEST SUBJECT

SITE

DISTANCE TO CLOSEST SUBJECT

SITE (m)

A Terraced housing with some limited low rise apartment buildings and commercial properties. NCA borders old suburban car workshops and is located over the rail corridor from subject site 3.

Primarily residential with some commercial

3 90

B Residential apartment blocks (3 to 4 storeys) located along Cornwallis Street.

Residential 3 125

C Australian Technology Park, containing offices and other similar commercial uses. Adjacent to Subject site 3.

Commercial 1,2 and 3 50, 60, 5

D Residential development on southern border of Eveleigh facility consists of townhouses and apartment blocks up to 5 storeys tall.

Residential 2 18

E Commercial properties on Eveleigh facility southern border

Commercial 2 45

F Terraced residential properties on Burren Street. Existing noise barrier located at rear of properties along rail corridor.

Residential 2 150

G Medium density terraced and free standing houses in addition to apartment block located adjacent to Carriageworks, located over the rail corridor from Eveleigh facility.

Residential 1 70

H Commercial precinct containing Carriageworks and disused railway workshops and maintenance yard.

Commercial and industrial

1 and 3 55 and 55

Page 22: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

8

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Figure 3.1 Subject Site locations, NCAs and noise monitoring locations

Page 23: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

9

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

4 EXISTING ENVIRONMENT4.1 Noise monitoring methodology

Short term attended and long term unattended noise measurements were taken between 17 and 29 February 2016, and 21 November and 2 December 2016. The noise monitoring was conducted with reference to Australian Standard AS 1055 Acoustics, Description and Measurement of Environmental Noise.

Table 4.1 describes the noise monitoring equipment used onsite, with the monitoring locations shown in Figure 3.1.

Table 4.1 Noise measurement equipment

ID EQUIPMENT DESCRIPTION

ADDRESS SURVEY DATE MANUFACTURER & TYPE NO.

SERIAL NO.

BG1 Sound Level Meter

157 Little Eveleigh Street, Redfern 21 November 2016, 24 November 2016 and 2 December 2016

Norsonic – Nor140 1406502

BG2 7 Carriageworks Way, Eveleigh

BG3 43 Burren Street, Erskineville

BG4 1-5 Rowley Street, Eveleigh

BG5 32 Rosehill Street, Redfern

Logger Environmental Noise Logger

1-5 Rowley Street, Eveleigh 21 November – 2 December 2016

SVAN Sound and Vibration Analyser – SVAN 958

36993

- Calibrator All All Rion NC-73 11248294

The data were gathered over a period of typical traffic movement and activity in the area (i.e. outside of school holiday periods). The monitoring equipment was fitted with windshields and were field calibrated before and after monitoring. No significant drifts in calibration (± 1.0dB) were noted.

The weather conditions at the time of monitoring were recorded at Observatory Hill Weather Station (Bureau of Meteorology station number 066062), which is located approximately four kilometres north of the project.

Periods of inclement weather (wind speeds greater than five metres per second and significant rainfall) and extraneous noise that were identified to adversely affect the noise monitoring were excluded from the analysis of monitoring data.

Operator attended noise surveys and observations were conducted at the noise monitoring locations on 21 November 2016, 24 November 2016, and 2 December 2016. The primary purpose of the attended monitoring was to measure background noise levels and characterise the existing ambient environment based on a short term noise measurement sample.

4.2 Noise monitoring results

Table 4.2 summaries the long term unattended noise monitoring results. The data are reported as the average equivalent continuous average sound levels (Leq(15min)) and rating background levels (RBL) as defined in the NSW Industrial Noise Policy (INP) (EPA, 2000). Graphs of the long term measurement results are presented in Appendix A.

Table 4.3 presents the results of the short term attended noise monitoring.

Page 24: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

10

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Table 4.2 Unattended noise measurement results (dBA)

ID DAY LEQ(15MIN)

DAY RBL

EVENING LEQ(15MIN)

EVENING RBL

NIGHT LEQ(15MIN)

NIGHT RBL

BG4 61 45 56 42 51 39 Note: Day is defined as Monday to Saturday 7.00am to 6.00pm; 8.00am to 6.00pm Sundays and Public Holidays, Evening is 6.00pm to 10.00pm and Night is the remaining periods.

Table 4.3 Short term attended noise monitoring results

LOCATION DATE START TIME

LEQ (15MIN)dBA

L90(15MIN)dBA

MEASURED EVENT NOISE LEVELS LMAX, dBA

COMMENTS

BG1 (NCA A)

21/11/16 12.00 pm 57 54 Construction activity nearby: 55-57 Aeroplane: 62-66 Road traffic: 66-71 Pedestrian traffic: 65-69

Facility related noise not discernible

24/11/16 9.33 pm 55 43 Pedestrian: 45-77 Train: 46-54 Road traffic: 51-56 Aeroplanes: 52-53 Entry gate: 60-76 Generator: 43-45 Hand tools up to 47

Facility related noise not discernible

24/11/16 11.54 pm 52 42 Pedestrian: 46-52 Train: 50-55 Road traffic: 44-56 Residential noise (e.g. dog and voice): 56-60 Entry gate: 73-85 Generator: 42-43 Light vehicle: 53-55

Facility related noise not discernible

BG2 (NCA G)

2/12/2016 10.23 am 60 47 Aeroplane: 60-71 Forklift activity: 55-70 Emergency vehicle siren audible Train: 53-70 Carpark activity: 50-53 Reverse alarm: 43-50 Facility related events Train horn: 53-75

24/11/16 9.51 pm 55 42 Train: 50-67 Mechanical plant: 41-42 Carpark activity: 50-59 Residential noise (e.g. voice): 48-50 Facility related events Horn: 55-58

Page 25: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

11

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

LOCATION DATE START TIME

LEQ (15MIN)dBA

L90(15MIN)dBA

MEASURED EVENT NOISE LEVELS LMAX, dBA

COMMENTS

24/11/16 10.08 pm 55 42 Train: 47-70 Mechanical plant: 42-44 Carpark activity: 50-59 Residential noise (e.g. voice): 48-50 Horn audible Facility related events Activity within shed (impact) up to 45

BG3 (NCA F)

2/12/2016 9.57 am 51 43 Pedestrian (walking and voice): 52-60Insects: 42-45Train (inner west line): 50-59Train (Bankstown line) 49-52Train horn audibleRoad traffic: 50-70Aeroplanes: 50-57Construction 47-65

Facility related noise not discernible

24/11/16 8.14 pm 52 41 Pedestrian: 55-73 Train (inner west line): 45-59 Train (Bankstown line): 48-59 Road traffic: 49-62 Aeroplanes: 58-62 Mechanical hum slightly audible in lulls of road and rail traffic.

Facility related noise not discernible

24/11/16 10.31 pm 46 38 Train (inner west line): 48-59 Train (Bankstown line): 46-53 Road traffic: 45-48 Pedestrian: 44-68 Dog: 45-49 Mechanical hum: 37-38

Facility related noise not discernible

BG4 (NCA D)

21/11/16 10.40 am 54 47 Road traffic: up to 47 Aeroplane: 52-64 General residential noise (e.g. dog, pedestrian, door closing): 50-54 Facility related events Activity within shed (impact) up to 65 Diesel engine testing: 47 Horn: 76-80

Page 26: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

12

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

LOCATION DATE START TIME

LEQ (15MIN)dBA

L90(15MIN)dBA

MEASURED EVENT NOISE LEVELS LMAX, dBA

COMMENTS

24/11/16 8.42 pm 50 43 Road traffic: 50-55 Aeroplane: 50-60 General residential noise (e.g. dog, pedestrian, door closing): 51-72 Mechanical plant up to 43 Facility related events Rolling stock: 54-56 Activity within shed (impact): 45-48 Diesel engine testing: 53-55 Door alarm and announcement tests audible

24/11/16 10.54 pm 50 41 Road traffic: 55-60 Pedestrian: 41-43 Aeroplane: 47-56 Train: 47-50 Mechanical plant: 40-42 Facility related events Rolling stock: 49-62 Diesel engine testing: 54-55 Horn up to 58 High pressure air: 44-57

BG5 (NCA B)

21/11/16 11.25 am 55 48 Train: 50-60 Aeroplane: 63-69 Tractor: 58-65 Mechanical plant up to 48

Facility related noise not discernible

24/11/16 9.10 pm 50 46 Road traffic: 52-68 Car entering garage up to 65 Aeroplane: 55-57 Pedestrian: 48-55 Mechanical plant: 45-47

Facility related noise not discernible

24/11/16 11.20 pm 49 47 Train: 50-58 Road traffic: 58-66 Pedestrian noise: 59 Mechanical plant: 46-47

Facility related noise not discernible

The results of the long term monitoring are considered representative of the receivers closest to BG4. Noise monitoring was conducted on the boundary of the Eveleigh maintenance facility. As a result, noise from activities within the facility would affect the noise monitoring. However, noise from activities are intermittent and did not dominate noise levels measured at the logging location.

As the INP method for determining the RBL takes the lowest tenth percentile background noise levels, it is considered that due to the intermittent nature of works at Eveleigh, the calculated RBL is representative of receivers adjacent to the facility in the absence of noise from the facility.

Furthermore, the result of the monitoring are within 2 dBA of previously measured background noise levels used to assess the facility (Eveleigh Maintenance Centre Noise Impact Assessment, Wilkinson Murray Report 1431 Version A, May 2014).

Page 27: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

13

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

At location BG1 (NCA A), the noise environment was dominated by urban hum comprising primarily of distant traffic noise. During the day, some nearby construction work also contributed to the measured levels. During the evening and night, a nearby generator contributed to the background noise environment with distant traffic noise also a significant contributor.

At location BG2 (NCA G) the background noise environment was dominated by urban hum with a significant contribution coming from train passbys within the rail corridor. Noise sources from the facility were observed to be impulsive noises from horns and impacts within the maintenance sheds.

At BG3 (NCA F) the activities within the facility were generally not discernible and the noise environment was comprised urban hum with significant contributions from train passbys on the existing network.

At BG4 (NCA D) the noise environment was made up of intermittent noise from the facility in addition to a background of urban hum during the day, evening and night periods.

At BG5 (NCA B), the noise environment was dominated by general urban hum, nearby mechanical plant and the facility was not discernible at this location.

Page 28: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

14

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 29: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

15

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

5 ASSESSMENT CRITERIA The assessment has been prepared with reference to the following guidelines, policies and standards:

noise

Industrial Noise Policy (INP) (EPA, 2000) Interim Construction Noise Guideline (ICNG) (DECC, 2009) Construction Noise Strategy (CNS) (Transport for NSW, 2013) Road Noise Policy (RNP) (EPA, 2011)

vibration

Assessing Vibration: A Technical Guideline (Vibration Guideline) (DEC, 2006) DIN Standard 4150-2 Part 3: Structural Vibration in Buildings: Effects on Structures (DIN

Deutsches Institut für Normung, 1999).

5.1 Operational

Operational noise is assessed according to the Industrial Noise Policy (INP) (EPA, 2000). The INP is the appropriate assessment method for the proposal as the Rail Infrastructure Noise Guideline (RING) (EPA, 2013) assessment method specifically excludes noise from maintenance and stabling yards.

The INP defines two criteria for the assessment of noise; the intrusive and amenity criteria. The more onerous criterion is then adopted as the project specific noise level (PSNL) which the proposal is assessed against.

The intrusive criterion is intended to protect residential receivers against intrusive noise in the short term. It is defined as Leq(15min) dBA less than or equal to the rating background level (RBL) plus 5 dBA. The RBL is the background noise level determined in accordance with Appendix B of the INP.

The amenity criterion is intended to maintain noise amenity and limit cumulative noise increases for sensitive land uses. In Table 2.1 of the INP, recommended amenity noise levels are defined for each day, evening and night period for each sensitive land use. The recommended amenity noise levels apply to noise from industrial noise only and where existing industrial noise exceeds or approaches the recommended amenity levels, a modifying factor (INP Table 2.2) is applied to limit the cumulative increase in total industrial noise at a receiver.

The closest and potentially most affected residential receivers to the operational activities are located in NCA D. It is expected that where compliance is achieved at NCA D, compliance would also be achieved at the other NCAs, located further away.

The receivers in all NCAs are considered to be an urban amenity area as the background noise environment is dominated by urban hum during all times of the day, evening and night.

Table 5.1 presents the criteria and PSNL for receivers in NCA D. Table 5.2 presents the project specific noise level for non-residential receivers as presented in the INP.

Page 30: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

16

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Table 5.1 Operational criteria for closest residential receivers

NOISE MONITORING LOCATION

TIME PERIOD1

RBL dBA INTRUSIVE CRITERIA

LEQ(15MIN) dBA

EXISTING INDUSTRIAL

NOISE LEVEL LEQ(15MIN) dBA

ACCEPTABLE NOISE LEVEL

LEQ(PERIOD) dBA

AMENITY CRITERIA2

LEQ(PERIOD) dBA

PSNL LEQ(15MIN) dBA5

NCA A Day 54 59 <47 60 60 59

Evening 43 48 45 50 48 48

Night 42 47 43 45 41 41

NCA B Day 48 53 48 60 60 53

Evening3 46 51 47 50 47 47

Night 46 51 47 45 37 37

NCA D2 Day 45 50 <61 60 60 50

Evening 42 47 <56 50 50 47

Night 39 44 <51 45 45 44

NCA F Day 43 48 <41 60 60 48

Evening 41 46 <42 50 50 46

Night 38 43 38 45 45 43

NCA G Day 47 52 <50 60 60 52

Evening 42 47 42 50 50 47

Night 42 47 44 45 39 39

Note 1: Day is defined as Monday to Saturday 7.00am to 6.00pm; 8.00am to 6.00pm Sundays and Public Holidays, Evening is 6.00pm to 10.00pm and Night is the remaining periods.

Note 2: It is considered that the existing industrial noise measured at the logging location is from the existing Eveleigh maintenance yard. Since the existing industrial noise level used to determine the amenity criteria should exclude that of the premises being assessed (Section 2.1, INP) the amenity criteria do not require modification.

Note 3: The measured evening RBL was higher than the night. In accordance with the INP Application Notes, in this situation the evening RBL should be set no higher than the night RBL.

Table 5.2 Operational criteria for non-residential receivers

RECEIVER TIME PERIOD AMENITY CRITERIA1

LEQ(PERIOD) dBA

Industrial (NCA H) When in use 70

Commercial (NCA C, NCA E and NCA H) When in use 65 Note 1: The PSNL has been set as a Leq(15min) in order to provide a conservative assessment. Where compliance is achieved over a 15 minute period is therefore implied it will occur over the day, evening or night period.

Note 2: For NCA H, the most stringent assessment criteria have been applied.

5.2 Construction Noise impacts from construction activities are assessed using the Interim Construction Noise Guideline (ICNG) (DECCW 2009) and the Transport for NSW Construction Noise Strategy (CNS) (Transport for NSW, 2013). The ICNG defines a noise management level for residential and other sensitive land uses. Above this level, feasible and reasonable mitigation should be considered to reduce noise levels.

Page 31: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

17

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

Table 5.3 defines noise management levels (NML) as specified in the ICNG and how they are applied for residential receivers. NMLs are the level of noise above which receivers are considered to be ‘noise affected’. They are based on the measured RBL as defined in the INP plus an additional allowance of 10 dB during standard hours and 5 dB outside of standard hours.

Where construction noise levels are above 75 dBA at residential receivers during standard hours, they are considered ‘highly noise affected’ and require additional considerations to mitigate potential impacts.

Table 5.3 Interim Construction Noise Guideline construction noise management levels for residential receivers and working hours

TIME OF DAY NML LEQ(15MIN)1,2 dBA HOW TO APPLY

Recommended standard hours: Monday–Friday 7 am–6 pm Saturday 8 am– 1 pm No work on Sundays or public holidays

Noise affected

RBL + 10 dB

The noise affected level represents the point above which there may be some community reaction to noise.

Where the predicted or measured Leq(15min) dBA is greater thanthe noise affected level, the proponent should apply all feasible and reasonable work practices to meet the noise affected level.

The proponent should also inform all potentially impactedresidents of the nature of works to be carried out, the expected noise levels and duration, as well as contact details.

Highly noise affected

75 dBA

The highly noise affected level represents the point above which there may be strong community reaction to noise.

Where noise is above this level, the relevant authority (consent, determining or regulatory) may require respite periods by restricting the hours that the very noisy activities can occur, taking into account:

times identified by the community when they are less sensitiveto noise (such as before and after school for works nearschools, ormid-morning or mid-afternoon for works near residences)

if the community is prepared to accept a longer period ofconstruction in exchange for restrictions on construction times.

Outside recommended standard hours

Noise affected

RBL + 5 dB

A strong justification would typically be required for works outside the recommended standard hours.

The proponent should apply all feasible and reasonable work practices to meet the noise affected level.

Where all feasible and reasonable practices have been applied and noise is more than 5 dB above the noise affected level, the proponent should negotiate with the community.

Note 1: Noise levels apply at the property boundary that is most exposed to construction noise, and at a height of 1.5 m above ground level. If the property boundary is more than 30 m from the residence, the location for measuring or predicting noise levels is at the most noise-affected point within 30 m of the residence. Noise levels may be higher at upper floors of the noise affected residence.

Note 2: The RBL is the overall single-figure background noise level measured in each relevant assessment period (during or outside the recommended standard hours). The term RBL is described in detail in the NSW Industrial Noise Policy (INP) (EPA 2000).

Page 32: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

18

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Table 5.4 provides a summary of the applicable NMLs based on the background noise monitoring conducted. In addition, Table 5.5 lists the NMLs that have been adopted for non-residential sensitive receivers as required by the ICNG.

Table 5.4 Construction noise management levels for residential receivers

NCA NML Leq(15min) dBA

Day (SH) Day (OOHW) Evening (OOHW) Night (OOHW)

A 64 59 48 47

B 58 53 51 51

D 55 50 47 44

F 53 48 46 43

G 57 52 47 47

Note: SH = Recommended standard working hours. OOHW = outside of recommended standard hours work as defined in Table 5.3.

Table 5.5 Noise management levels at sensitive land uses (other than residences)

LAND USE NML LEQ(15 MIN) dBA (APPLIES WHEN PROPERTIES ARE BEING USED)

Commercial (NCA C, NCA E, NCA H) 70 (external)

Industrial (NCA H) 75 (external)

5.3 Sleep disturbance

Operational and construction noise during the night have the potential to disturb people’s sleep patterns.

Guidance in the ICNG and INP Application Notes references further information in the Road Noise Policy (RNP) (EPA, 2011) that discusses criteria for the assessment of sleep disturbance.

The RNP and the INP application notes suggest a screening level of L1(1min) dBA, equivalent to the RBL + 15 dB. Where this level is exceeded, further analysis should be carried out. Section 5.4 of the RNP then goes on to state that:

maximum internal noise levels below 50 to 55 dBA would be unlikely to result in people’s sleep beingdisturbed

if the noise exceeds 65 to 70 dBA once or twice each night the disturbance would be unlikely to haveany notable health or wellbeing effects.

Based on the above, at levels above 55 dBA, sleep disturbance would be considered likely. Assuming that receivers may have windows partially open for ventilation, a 10 dB outside to inside correction has been adopted as indicated in the INP. Therefore sleep disturbance screening criterion of Lmax 65 dBA has been adopted in this assessment.

Page 33: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

19

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

5.4 Off-site road traffic

The project will generate construction and operational vehicle movements on the surrounding roads which have the potential to impact sensitive receivers along the access routes.

The RNP has been used to assess traffic noise from generated during the operational and construction phases of the project.

Table 5.6 presents the road traffic noise criteria from the RNP for land use developments with a potential to create additional traffic on an existing road. The external noise criteria are applied one metre from the external facades of the affected building and at a height of 1.5 metres from the most affected storey.

Table 5.6 Applicable Road Noise Policy assessment criteria

ROAD CATEGORY TYPE OF PROJECT/LAND USE DAY (7.00am to 10.00pm)

NIGHT (10.00pm to 7.00am)

Collector/sub-arterial/arterial/freeway

Existing residences affected by additional traffic on existing freeways/arterial/sub-arterial roads generated by land use developments

Leq(15hr) 60 dBA Leq(9hr) 55 dBA

Local road Existing residences affected by additional traffic on existing freeways/arterial/sub-arterial roads generated by land use developments

Leq(1hr) 55 dBA Leq(1hr) 50 dBA

In addition, the RNP application notes state that where an existing receiver is affected by a land use development, the increase in road traffic noise above the existing road noise level should be limited to 2 dBA. This applies where the existing noise level is either above or within 2 dBA of the criteria presented in Table 5.6.

5.5 Vibration Vibration from construction and operation can lead to:

cosmetic and structural building damage

loss of amenity due to perceptible vibration, termed human comfort.

Importantly, cosmetic damage is regarded as minor in nature; it is readily repairable and does not affect a building’s structural integrity. Damage of this nature is typically described as hairline cracks on drywall surfaces, hairline cracks in mortar joints and cement render, enlargement of existing cracks, and separation of partitions or intermediate walls from load bearing walls. If there is no significant risk of cosmetic damage then structural damage is not considered a significant risk and is not further assessed.

COSMETIC BUILDING DAMAGE

There is currently no guidance in NSW specifically addressing cosmetic damage to buildings from vibration. Two international standards are typically referenced for the assessment of cosmetic damage in buildings; British Standard BS 7385-2: 1993 Evaluation and measurement for vibration in buildings and German Standard DIN 4150-3: 1999 Structural Vibration – Part 3: Effects of vibration on structure

The guidance in the Transport for NSW Construction Noise Strategy (CNS) refers to BS 7385 for safe working distances to avoid cosmetic damage of buildings. The standard provides guidance on the ‘evaluation and measurement of vibration in buildings’ and defines guidance for categorising building damage in terms of ‘cosmetic’, ‘minor’ and ‘major’; providing limits for each (refer to Table 5.7).

Page 34: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

20

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Table 5.7 BS7385 Cosmetic damage criteria, peak component particle velocity, (mm/s 1)

GROUP TYPE OF STRUCTURE 4–15 Hz 15–40 Hz 40 Hz AND ABOVE

1 Reinforced or framed structures

Industrial or heavy commercial buildings

50

2 Un-reinforced or light framed structures

Residential or light commercial buildings

15 – 202 20 – 50 50

Note 1: Values referred to are at the base of the building, on the side of the building facing the source of vibration (where feasible).

Note 2: At frequencies below 4 Hz, a maximum displacement of 0.6 mm (zero to peak) should not be exceeded.

These peak vibration limits are set so that the risk of ‘cosmetic’ damage in residential or commercial buildings is minimal. They have been set at the lowest level above which damage has been credibly demonstrated. The limits also assume that the equipment causing the vibration is only used intermittently, however if the equipment is used continuously, then the limits may need to be reduced by up to 50 per cent.

For ‘minor’ or ‘major’ vibrational damage to occur, the standard states that vibration need to be two times and four times (respectively for group 1 and group 2) the values shown in Table 5.7.

Guidance in BS 7385 also suggests that unless structurally unsound, heritage items should not be considered to be more sensitive than dwellings for the purposes of assessment.

Vibration limits given in DIN 4150 are more conservative than BS 7385 and specifically address heritage items as being more sensitive. Table 5.8 presents a summary of the vibration limits from DIN 4150.

Table 5.8 Guideline values for short term vibration on structures (DIN 4150-3), guideline values for velocity, (mm/s)

Type of structure 1Hz to 10Hz 10Hz to 50Hz 50Hz to 100Hz

Buildings used for commercial purposes, industrial buildings and buildings of similar design.

20 20 to 40 40 to 50

Dwellings and buildings of similar design and/or occupancy. 5 5 to 15 15 to 20

Structures that, because of their particularly sensitivity to vibration, cannot be classified under lines 1 and 2 and are of great intrinsic value (for example heritage listed buildings).

3 3 to 8 8 to 10

In this assessment, the DIN 4150 limits have been adopted for heritage items as they represent the more conservative limits.

Page 35: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

21

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

HUMAN COMFORT (AMENITY)

Table 5.9 presents the limits (vibration dose values) above which there is considered to be a risk that the amenity and comfort of people occupying buildings would be affected by construction work. The limits are taken from Assessing Vibration: A Technical Guideline (DEC, 2006).

Table 5.9 Vibration limits (human comfort), Vibration dose value, (m/s1.75)

LOCATION ASSESSMENT PERIOD

PREFERRED VALUES MAXIMUM VALUES

Critical areas Day or night time 0.10 0.20

Residences Daytime 0.20 0.40

Residences Night time 0.13 0.26

Offices, schools, educational institutions, and places of worship

Day or night time 0.40 0.80

Workshops Day or night time 0.80 1.60

Page 36: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

22

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 37: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

23

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

6 OPERATIONAL ASSESSMENT6.1 Introduction

The operational activities associated with the project are expected to consist of commissioning activities and once complete, maintenance and stabling activities. The following sections outline the expected activities and an assessment of the potential noise impacts associated with these operational activities.

6.2 Existing operations

The facility has operational activities associated with the Endeavour and XPLORER maintenance centre and 3801 Limited in addition to other stabling and ad-hoc maintenance activities as required by the Sydney Trains. These existing operations are not expected to change as a result of the NIF trains being commissioned and maintained at the facility and therefore no assessment of these activities is required.

6.3 Commissioning activities

The commissioning of the new trains is expected to occur at the Eveleigh facility on roads five to nine within the Millennium Shed. Up to five NIF sets can be commissioned at the same time within the facility.

Both static and dynamic commissioning activities are required to be carried out. The static commissioning involves comprehensive testing of all train systems and services, similar to preparation for service routine. The dynamic testing involves taking the NIF train out on the network to test systems concerned with the network and the train in motion.

The activities required to carry out the commissioning are as follows:

all NIF trains will be delivered as ten car sets and hauled from the port to the facility by a diesellocomotive

up to two diesel locomotives may be required to move NIF trains into the Millennium shed

either one locomotive would be used to haul NIF train into the facility then uncouple and then travelaround the network to couple at the back of the train and propel it into the shed

or an additional locomotive would be coupled at the rear of the train. The lead locomotive wouldhaul the train into the facility and then uncouple, leaving the rear locomotive to propel the train intothe shed

locomotives would not be required to operate at full power during shunting or at idle

uncoupling would typically take 5 to 15 minutes, during which time the locomotive would be idlingcontinuously

dynamic testing such as signal interference testing is required to be undertaken on the network

there are 13 signal systems to be tested NIF trains would be propelled by a diesel locomotive to testing locations signal interference testing is only required on the first two NIF trains

trains can self-propel within the facility and on the network once the signal interference and type testingis completed on the first two NIF trains

the trains self-propelling within the facility is not a significant noise source

static commissioning is to take place on roads five to nine within the Millennium shed

static commissioning and dynamic testing may take place at any time during the day, evening or night,seven days a week to meet operational requirements.

Page 38: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

24

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

ASSESSMENT SCENARIOS

The activities with the most potential to cause noise impacts at the nearest noise sensitive receivers have been assessed. Table 6.1 provides a summary of the assessment scenarios.

Table 6.1 NIF train commissioning assessment scenarios

ID DESCRIPTION LOCATION EQUIPMENT TIME PERIOD

1 2 locomotives manoeuvre NIF train within the facility

On roads approaching Millennium Shed

2 diesel locomotives equivalent to 81 or 82 class diesel locomotives

Day, evening or night

2 2 locomotives idle outside Outside of the Millennium Shed

2 diesel locomotives equivalent to 81 or 82 class diesel locomotives

Day, evening or night

3 1 loco idles outside Outside of the Millennium Shed

1 diesel loco equivalent to 81 or 82 class diesel locomotives

Day, evening or night

4 5 NIF trains running all services Inside Millennium Shed

Each NIF train running air compressors, static inverters and air conditioning

Day, evening or night

5 Brake testing (assumed 5 New Intercity Fleet trains tested at the same time)

Inside Millennium Shed

Brake testing including emergency and other brakes

Day, evening or night

6 Digital Voice Announcement (assumed 5 New Intercity Fleet trains tested at the same time)

Inside Millennium Shed

DVA on each NIF train Day, evening or night

7 Horn testing Inside Millennium Shed

Country horn test Day, evening or night

METHOD

Predictions of noise levels at receivers have been made using the ISO 9613 method as implemented in the CadnaA 4.2 noise modelling software. The following conservative assumptions were used:

flat topography between the source and the nearest receivers

hard ground absorption

all noise sources in each scenario operating simultaneously

noise source levels and directionalities as stated in Table 6.2 and Table 6.3

noise sources for those located on top of the trains have been assumed to be at 4 metres and thoseunder the train at 0.5 metres

all activities can occur during the day, evening or night.

Noise source levels for each of the activities and equipment has been sourced from information provided within Sydney Trains Environmental Management System Document EMS-09-GD-0080 Noise and vibration from Rail Facilities Chapter 4 – Stabling Yards, and other published sources where applicable.

Page 39: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

25

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

The noise levels for the NIF have been based on the most recently produced train sets, the Waratah (A-set). Table 6.2 presents the noise levels used for the assessment.

Table 6.2 Noise source levels

TRAIN TYPE1 OPERATING CONDITION

SOUND POWER LEVEL DETAILS

Waratah Static inverter Leq(15min) 83 dBA Located at top of train, two units per car.

Waratah Air compressor Leq(15min) 86 dBA Underfloor at end of train. One unit per four car set.

Waratah Air conditioning (AC) unit

Leq(15min) 80 dBA On full load. Located at top of train, two units per car.

Waratah Brake test discharge Leq(15min) 96 dBA

Lmax 120 dBA (emergency brakes)

Lmax 115 dBA (other brake release)

Underfloor at end of train. One unit per four car set.

Waratah Horn testing Town L1(1min) 136 dBA

Country L1(1min) 145 dBA

Underfloor at end of train.

Waratah DVA testing Leq(15min) 91 dBA Distributed along both sides of train, four locations per side per car.

Diesel locomotive Moving at 8km/h Leq(15min) 107 dBA Primarily noise sources from engine bay and exhaust.

Diesel locomotive Idle Leq(15min) 103 dBA Primarily noise sources from engine bay and exhaust.

Note 1: Waratah (A-set) noise emissions have been used to represent emissions from the NIF.

The directionality of the noise sources has also been included as presented in Table 6.3. The directionality is based on previously published stabling and maintenance facility assessments and Asset Standards Authority (ASA) requirements where applicable.

Table 6.3 Source directivities, adjustment by angle (dBA)

LOCATION OF SOURCE 0° 45° 90° 135° 180° NOTES

Top of train 0 0 0 -9 -15 0 degrees is defined straight up from top of train

Bottom of train -12 -5 0 -5 -12 0 degrees is defined as perpendicular to the track

Horn1 0 -4.5 -8 -10 -11 0 degrees is parallel with the track

Note 1: directionalities of the country and yard horn have been taken from Asset Standards Authority, T-HR-RS-00100-ST RSU 100 Series – Minimum Operating Standards for Rolling Stock – General Interface Standards

PREDICTED NOISE LEVELS

Noise levels were predicted for the assessment scenarios at the nearest NCAs to the commissioning activities. A summary of the predicted Leq(15min) noise levels is presented in Table 6.4.

Cells have been highlighted grey where they exceed the night PSNL, green where they exceed the evening PSNL and orange where they exceed the day PSNL.

Page 40: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

26

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Table 6.4 Predicted noise levels at nearest sensitive receivers

ASSESSMENT AND DISCUSSION

The predicted noise levels in Table 6.4 indicate that the activities would exceed the PSNLs in NCA D. All other NCAs are not expected to receive noise levels above the PSNLs.

For NCA D Scenarios 2 to 6 all exceed the day, evening and night PSNLs and scenario 1 exceeds the night PSNLs.

The most substantial noise sources are the diesel locomotives that are used to haul and propel the NIF trains within the facility, train horns and simultaneous commissioning activities on five trains occurring within the sheds.

For activities that occur within the shed, the assumptions are based on activities taking place on five NIF trains at once, which is a worst case assumption. In reality, the commissioning activities in any 15 minute period are unlikely to include the same activity occurring simultaneously on all five trains.

The use of diesel locomotives is expected to occur only over the first few months prior to NIF being approved to operate on the network. Therefore the potential impact of diesel trains would be term and would be limited to a few months of locomotives operating in the precinct prior to the type approval and after this only when locomotives delivered trains.

The commissioning activities (scenarios 4 to 6) that occur within the sheds are operational activities that are expected to occur over the course of four years. Impacts associated with the commissioning activities are expected during the day, evening and night when they occur. Whilst they will not form part of the permanent operations of the facility as the operations will occur over a number of years, they are considered to have similar impacts as a permanent operation.

A detailed review of the predicted noise levels indicate that noise levels within NCA D vary between less than 30 dBA at the receivers on Henderson Road to the worst case predicted noise levels presented in Table 6.4 for the receivers at the boundary of the facility. The existing buildings within NCAD provide good acoustic shielding to those receivers located behind them. This indicates that the impact of the noise levels above the PSNLs is limited to the first two rows of residential properties adjacent to the facility.

The nearest residential receivers in NCA D were constructed after the current configuration of the Eveleigh facility was established. AS 2107 specifies noise levels in sleeping areas at night should be between Leq(15min) 35 and 40 dBA.

Due to the fact that the receivers were built adjacent to an industrial facility, receivers would have a ventilation system sufficient to allow windows to be closed at night. Assuming a correction of 20 dBA for a

Page 41: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

27

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

closed façade, the internal Leq(15min) noise levels would all be less than 40 dBA, indicating that an acceptable level of noise can be achieved within the nearest residential buildings.

However, the predicted worst case noise levels indicate operational noise levels above the PSNLs would only occur at NCA D for both the temporary use of locomotives within the facility in addition to commissioning activities which are expected to occur over four years. As a result, mitigation measures should be considered to reduce external noise levels towards the PSNLs where reasonable and feasible.

SLEEP DISTURBANCE

For the horn testing, the sleep disturbance screening criteria as described in Section 5.3 are the most appropriate criteria. The predicted maximum noise levels at the nearest receivers in NCA D from testing the horns in the Millennium Shed are as follows:

country horn: Lmax 106 dBA

town horn: Lmax 97 dBA.

These predicted noise levels are in excess of the 65 dBA sleep disturbance screening criterion for the nearest receivers. Where receivers close their windows at night, this translates to an internal noise level of 86 and 77 dBA for country horns and town horns respectively. These noise levels are in excess of the maximum internal noise levels discussed in Section 5.3.

Horns are currently used at the facility with some testing occurring on the network in the vicinity of Redfern station. The proposed commissioning activities are likely to require similar usage of horns within the facility. Whilst the predicted noise levels are above the screening criteria, the use of horns for commissioning activities is not considered to increase the frequency or noise level above that of the existing horns used on the site.

However, in consideration of the predicted exceedances of the sleep disturbance screening criteria, mitigation and management measures should be considered for implementation as described in the Noise Mitigation and Management section.

NOISE MITIGATION AND MANAGEMENT

As there are predicted exceedances of the PSNLs, feasible and reasonable mitigation should be investigated to reduce the noise emission towards the PSNLs in NCA D. Noise management and mitigation measures should include consideration of the following:

scheduling commissioning activities to reduce the number of trains that are conducting noise intensiveactivities at the same time

scheduling noise intensive commissioning activities such as brake and Digital Voice Announcementstesting during the day and evening time

scheduling use of diesel locomotives for shunting in the facility to avoid night time period

use locomotives in lowest permissible power/notch setting within facility

shutting off diesel locomotives when not in use

stand idling locomotive immediately behind train wash in front of 3801 Limited shed to shield thelocomotive from the residential receivers

allocate a place for diesel locomotives to stand and idle, if required in a location that is shielded from thenearest residential receivers

adopt a similar horn testing regime as currently in place at Eveleigh, such as testing country and townhorns on the network

utilise existing building / structures (e.g. train wash, Australian Technology Park, other trains) to shieldresidential receivers from noise from standing locomotives, when it does not significantly impact theoperation of the Precinct or as directed by the Eveleigh Precinct Manager.

Page 42: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

28

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

In addition, where intensive night time commissioning activities are planned that may exceed the night PSNLs, it is recommended that the community in NCA D be informed at least 24 hours in advance.

Table 6.5 presents the potential reductions in noise level that could be achieved for the applicable mitigation measure.

The measures shown in the table indicated significant reductions in the noise levels and in some cases, compliance with the PSNLs can be achieved through applying the measures.

It is recommended that an operational management plan is developed to include these measures to reduce the potential noise emissions within practical operational centralists.

Table 6.5 Effectiveness of mitigation measures

SCENARIO MANAGEMENT MEASURE POTENTIAL REDUCTION

dB

PREDICTED LEVEL IN NCA D WITH

MITIGATION MEASURE LEQ(15MIN)

dBA

PERIODS OF COMPLIANCE1

1 Use stabled train to shield nearest receivers

5-7 41 Day Evening Night

2 Use stabled train to shield nearest receivers

5-7 52 Day (marginal)

3 Use stabled train to shield nearest receivers

5-7 49 Day Evening (marginal)

Stand idling locomotive in front of EMC 30 <30 Day Evening Night

Stand idling locomotive behind train wash

13 43 Day Evening Night

4 Use stabled train to shield nearest receivers

5-7 45 Day Evening Night (marginal)

3 trains powered up with all services running

3 49 Day Evening (marginal)

2 trains powered up with all services running

5 47 Day Evening

1 train powered up with all services running

6 46 Day Evening Night (marginal)

3 trains powered up with all services running and stabled train to shield nearest receivers

7 42 Day Evening Night

5 1 train only undertaking brake testing 6 46 Day Evening Night (marginal)

Use stabled train to shield nearest receivers

5-7 47 Day Evening

Page 43: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

29

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

SCENARIO MANAGEMENT MEASURE POTENTIAL REDUCTION

dB

PREDICTED LEVEL IN NCA D WITH

MITIGATION MEASURE LEQ(15MIN)

dBA

PERIODS OF COMPLIANCE1

6 1 train only undertaking DVA testing 6 46 Day Evening Night (marginal)

Use stabled train to shield nearest receivers

5-7 45 Day Evening Night (marginal)

Note 1: A marginal compliance is where the predicted noise level is 2 dB or less above the PSNL. According to Chapter 11 of the INP, a noise level of more than 2 dB above the PSNL is considered an exceedance for compliance purposes.

6.4 Maintenance and stabling activities

After the NIF trains have been commissioned and enter regular service, the Eveleigh facility will be used as a maintenance and stabling facility where Level 1 and 2 maintenance will be carried out regularly. This is expected to include:

internal and external cleaning

minor works such as replacing seats, changing wiper blades and minor repairs to compressors

preparation of trains for service

pantograph maintenance

repair and replacement of air conditioning units.

In addition, occasional Level 3 maintenance would be carried out. This includes more extensive repairs such as changing bogeys.

All of these activities are currently carried out within the Oscar and Millennium Sheds routinely. The location, operating times and activities are not expected to substantially change when the NIF are maintained at the facility.

The extension of the OHW in the Millennium Shed as part of the NIF changes to the facility are not expected to generate additional noise impacts as their purpose is to allow the trains to move further into the shed. Therefore no significant increase in noise impact is expected to result from the maintenance of the NIF compared with the existing situation with Millennium and Oscar sets.

The NIF trains will be subject to the same noise emission standards as the current rolling stock. Therefore there is not expected to be any additional noise impacts associated with stabling the NIF at the facility.

The maintenance and stabling operations should continue to be managed in line with current noise management practices at the facility.

Page 44: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

30

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

6.5 Other operational changes

In addition to the maintenance and commissioning activities, occurring within the Millennium Shed (subject site 2) the changes associated with subject site 2 and 3 also have the potential to increase the impact of the development.

SUBJECT SITE 1 – ENGINEERING ROADS 1 AND 2

The changes at subject site 1 include a small extension of the existing Engineering Roads and extending the water pipeline and the installation of an additional decant point.

The extension of engineering roads 1 and 2 by 49 metres to the west is not expected to significantly change the noise levels experienced by the nearest sensitive receivers. The nearest receivers to the in NCA F are over 415 metres away. The end of the Engineering Roads being 49 metres closer would change the noise emission by less than 1 dB which is not considered acoustically significant. A change of 3 dB or more is typically considered to be the smallest change in noise that the average person can perceive.

Receivers in NCA G are located across the rail corridor from the engineering roads. The extension of the engineering road is expected to move 45 metres closer to the closest receiver. There is an existing noise wall along the northern boundary of the rail corridor that is more than 4 metres in height above the existing rail corridor. The noise wall blocks line of sight and provides significant shielding for these receivers and as a result, additional significant noise impacts are not expected to occur at these receivers.

Based on the above, no additional operational noise impacts are expected as a result of the proposed changes at subject site 1.

SUBJECT SITE 3 – EXTENSION OF EASTERN SIDING

The Eastern Siding is proposed to be extended by 26 metres to the east. This would bring standing trains closer to the residential receivers in NCA B. The residential receivers are currently approximately 150 metres from the end of the eastern siding. This is predicted to result in an increase to the existing noise level of less than 2 dBA. This change is not considered acoustically significant and no additional operational impacts would be expected as a result of the changes to the siding.

6.6 Operational vibration assessment

Significant operational vibration is not expected to be generated from the proposed activities and no further assessment is required.

Page 45: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

31

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

7 CONSTRUCTION NOISE ASSESSMENT7.1 Assessment scenarios

The proposed changes to the facility at the three subject sites are to be conducted in stages. The details of construction have been based on the staging and activities presented in the Constructability Feasibility and Staging Report (GHD June 2016 Draft version C ref: 2125210-215812).

The most significant noise generating stages have been identified for assessment. Table 7.1 presents the assessed scenarios for each subject site. According to the constructability report, the duration of the works is expected to take between 3 and 4 months for each subject site.

Where works on the OHW are required, a track possession is necessary. Track possessions typically take place during periods of less operational activity such as at weekends and during the night. At this the timing of the possessions cannot be confirmed and therefore it has been assumed that it may take place during the night period in order to minimise potential disruption to operations.

Table 7.1 Construction assessment scenarios

SUBJECT SITE SCENARIO ID ACTIVITY TIME OF DAY1

1 1A Site establishment Standard hours

1B Demolition of existing buildings Standard hours

1C Demolition of existing slabs and rail tracks

Standard hours

1D Install new slab footings and tracks Standard hours and out of hours works

1E Extension of decant facility piping Standard hours

1F Installation of new OHW for extended tracks

Standard hours and OOHW

1G Relocation of buffer stops and associated infrastructure.

Standard hours

2 2A Site establishment Standard hours

2B Installation of new OHW in the Millennium Shed

Standard hours and OOHW

2C Demolish old OHW footings and dispose

Standard hours

3 3A Site establishment Standard hours

3B Relocate heritage train Standard hours

3C Demolish existing footings Standard hours

3D Install new footings and tracks Standard hours

3E Relocation of buffer stops and associated infrastructure

Standard hours

3F Install new OHW for extended tracks Standard hours and OOHW

Note 1: Time periods are those defined by the ICNG in Section 5.2.

Page 46: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

32

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

7.2 Assessment method

Noise levels from construction activities have been predicted at the nearest receiver types in each NCA as presented in Table 3.1. As a worst case scenario, each item of plant in the scenario has been assumed to be operating simultaneously and at the closest point to the receiver.

The prediction accounted for the attenuation due to distance and shielding from topography and intervening structures. The calculation also accounted for air absorption in accordance with ISO 9613 Part 1 Acoustics - Attenuation of sound during propagation outdoors - Part 1: Calculation of the absorption of sound by the atmosphere (ISO 9613-1).

In addition, certain activities are specified by the ICNG to require the addition of 5 dB to the predicted level to account for the “annoying” characteristics of the noise produced. These activities include jackhammering and steel cutting.

7.3 Noise source levels

The noise sources levels for each item of plant used in each scenario are presented in Table 7.2. Noise levels were sourced from AS 2436 Guide to noise and vibration control on construction, demolition and maintenance sites (AS 2436), UK Department of Environment, Food and Rural Affairs Construction Noise Database and WSP | Parsons Brinckerhoff database.

Page 47: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

33

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

Table 7.2 Construction equipment sound power levels

PLANT PLANT SWL dBA

USAGE FACTOR 1A 1B 1C 1D 1E 1F 1G 2A 2B 2C 3A 3B 3C 3D 3E 3F

Trucks 107 10% X X X X X X X

Mobile crane 104 75% X X X X X X X X X

Excavator mounted hammer1 113 25% X

Backhoe 100 75% X X X

Loader 107 75% X X

Jackhammer1 112 25% X X X

Power tools 105 25% X X

Hand tools 100 50% X X X X X X X X

Rail cutting saw1 119 25% X X X

Concrete trucks 107 50% X

Tractor/truck rail installer 110 75% X X

Hiab truck 105 75% X X X

Hi-rail cherry picker 105 75% X X X X

Overhead wire truck 104 75% X X X

Compactor 110 75% X X

Vibratory roller1 102 75% X X

Compressor 94 75% X X X

Rail tamper1 114 50% X X

Ballast tamper1 115 50% X

Light tower 85 100% X X X X

Total SWL 104 116 120 120 106 108 104 104 108 114 104 105 118 122 105 108

Note 1: These items require a +5 dB correction to be added in accordance with the ICNG. Note 2: The total sound power level is calculated as a logarithmic sum of all of the equipment and includes the usage percentage for each item.

Page 48: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

34

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

7.4 Predicted noise levels

Table 7.3 and Table 7.4 presents the predicted worst case construction noise levels for Subject Sites 1 and 2 and 3 respectively. Cells have been shaded to indicate exceedance of the NMLs for the applicable time period as follows: orange for day (SH), yellow for day (OOHW), green for evening (OOHW) and grey for night (OOHW).

Table 7.3 Predicted noise levels for subject site 1 construction activities

Note 1: SH = Recommended standard working hours. OOHW = outside of recommended standard hours work as defined in Table 5.3.

Note 2: Cells have been shaded for exceedances of the applicable time periods as follows: orange for day (SH), yellow for day (OOHW), green for evening (OOHW) and grey for night (OOHW).

Table 7.4 Predicted noise levels for subject sites 2 and 3 construction activities

Note 1: SH = Recommended standard working hours. OOHW = outside of recommended standard hours work as defined in Table 5.3.

Note 2: Cells have been shaded for exceedances of the applicable time periods as follows: orange for day (SH), yellow for day (OOHW), green for evening (OOHW) and grey for night (OOHW).

Page 49: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

35

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

7.5 Assessment of predicted noise levels

The worst case predicted noise levels indicate the following impacts at subject site 1:

exceedance of the day NMLs in NCA G for scenarios 1B, 1C, 1D

exceedance of the day (OOHW), evening and night NMLs in NCAs G for scenario 1F

exceedance of the commercial NML in NCA H for scenario 1C and 1D

in addition to the above, scenario 1D is also expected to exceed the day NML in NCA F, day OOHW inNCA B, evening NML in NCA A and F and the night NMLs in NCA A, D and F.

all other scenarios are not expected to impact the NCAs.

As a result, noise levels are within acceptable levels during standard hours for residential NCAs except NCA G. Where work occurs outside of standard hours at subject site 1, additional impacts are predicted NCAs inA, B, D and F.

For subject site 2, the following impacts are expected:

exceedance of the day, evening and night NMLs in NCA D for scenario 2B and 2C

exceedance of the night NML in NCA E for scenario 2B

all other NCAs are not expected to be impacted by the works.

Due to the proximity of the works at subject site 2 to NCA D, the predicted noise levels are higher than other NCAs and impacts are expected for NCA D when works are carried out at any time of the day, evening and night. NCA E is only potentially affected during the night. Exceedances of the noise management levels are not expected at other NCAs for works at subject site 2 carried out at any time of day, evening and night.

For subject site 3, the following impacts are expected:

exceedance of the day NMLs in NCAs A and B for scenarios 3C and 3D

exceedance of the evening and night NMLs in NCAs A and B in scenario 3F

large exceedances of the commercial NML in NCA C

compliance with the NMLs for all other NCAs.

The works at subject site 3 are on the border of NCA C and therefore the highest impacts are predicted in this NCA. The closest residential NCAs are NCA A and B where noise levels during the evening and night are predicted to exceed the noise management levels for scenario 3F. Predicted noise levels were all within acceptable levels for all other residential NCAs and scenarios.

Predicted noise levels at receivers were not predicted to be above the highly noise affected level at any subject site and scenario.

7.6 Sleep disturbance

For the assessment of the potential for sleep disturbance, a +5 dB was added to the predicted Leq(15min) levels predicted in Table 7.3 and Table 7.4 to approximate a maximum noise level emission from the activity.

The assessment of the potential of sleep disturbance consider residential properties affected by work carried out during the night period only.

Table 7.5 presents the predicted noise levels during scenarios that occur during the night for residential NCAs. Cells are highlighted grey where the screening criterion is exceeded.

Page 50: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

36

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Table 7.5 Sleep disturbance assessment for residential NCAs

A review of the predicted noise levels indicates that the sleep disturbance screening criteria were exceeded in NCA G for scenario 1D. The predicted internal noise level, assuming a partially open window is 63 dBA. The latest available guidance on sleep disturbance (contained within the RNP) indicates that one or two events between 65 and 70 dBA would be unlikely to have any notable health or wellbeing effects.

With closed windows, an additional 10 dBA reduction of external noise can be expected. This would mean an internal noise level of 53 dBA could be achieved which is below the level at which sleep disturbance is typically considered likely.

Mitigation measures should be implemented to minimise the chance of maximum noise levels occurring as a result of the construction works. In addition, residents should be made aware of the potential for sleep disturbance so that they may be able to close their windows where possible.

Page 51: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

37

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

8 CONSTRUCTION VIBRATIONASSESSMENT

The significant vibration generating equipment is expected to be as follows:

excavator mounted hammer

jackhammers

vibratory rollers/compactors.

The Transport for NSW CNS includes safe working distances for human comfort and building damage as for the above equipment. Using these safe working distances, the potential for impacts to heritage items was extrapolated.

Table 8.1 presents the indicative safe working distances for cosmetic damage for standard and heritage structures in addition to human comfort.

Site specific safe working distances should be developed on site as the propagation of vibration is highly dependent on local ground conditions and specific equipment being used. Where work is proposed within the safe working distances, mitigation and management measures should be implemented to ensure that vibration can be controlled to appropriate levels.

The condition of the heritage items must be considered when setting vibration limits for construction works. Structures such as heritage industrial buildings which are structurally sound should not necessarily be considered more vibration sensitive than other structures.

Table 8.1 Indicative safe working distances for construction vibration

PLANT ITEM RATING SAFE WORKING DISTANCES (m)

Cosmetic damage (BS 7385)

Cosmetic damage for heritage items1 (DIN 4150)

Human comfort

Vibratory roller <50kN (1-2 tonnes) 5 15 15-20

<100kN (2-4 tonne) 6 20 20

Hydraulic hammer (300kg 5-12t excavator)

2 6 7

Jackhammer Hand held 1 5 Avoid contact with structure

Note 1: Heritage items should be assessed on a case by case basis and the condition of the items considered when setting vibration limits.

Page 52: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

38

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 53: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

39

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

9 CONSTRUCTION NOISE AND VIBRATIONMANAGEMENT

A construction noise and vibration management plan (CNVMP) should be developed for the project, prior to commencement of works. The management plan would utilise detailed construction methodologies of the contractor. The management plan would include (but is not limited to) the following:

identified nearby residences and other sensitive land uses

approved hours of work and what work would be undertaken

dominant noise and vibration generating activities

details of noise mitigation and management measures to be applied

information for worker training to minimise noise impacts

community consultation protocol(s)

complaints handling protocol(s)

construction works should be planned and carried out during standard construction hours whereverpossible.

Table 9.1 presents the standard mitigation measured contained within the Transport for NSW Construction Noise Strategy (CNS) which should be considered as mitigation measures as part of the noise management plan.

Table 9.1 Transport for NSW Construction Noise Strategy standard mitigation measures

ACTION REQUIRED DETAILS

Management measures

Implement any project specific mitigation measures required

In addition to the measures set out in this table, any project specific mitigation measures identified in this report.

Implement community consultation measures

Periodic notification (monthly letterbox drop or equivalent), website, project Infoline, Construction Response Line, email distribution list.

Site inductions All employees, contractors and subcontractors are to receive an environmental induction.

Behavioural practices No swearing or unnecessary shouting or loud stereos/radios on site. No dropping of materials from height, throwing of metal items and slamming of doors.

Noise Monitoring A noise monitoring program is to be carried out for the duration of the works in accordance with the Construction Noise and Vibration Management Plan and any approval and licence conditions.

Source controls

Construction hours and scheduling

Where feasible and reasonable, construction should be carried out during the standard daytime working hours. Work generating high noise and/or vibration levels should be scheduled during less sensitive time periods.

Construction respite period High noise and vibration generating activities may only be carried out in continuous blocks, not exceeding three hours each, with a minimum respite period of one hour between each block.

Equipment selection Use quieter and less vibration emitting construction methods where feasible and reasonable.

Page 54: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

40

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

ACTION REQUIRED DETAILS

Maximum noise levels The noise levels of plant and equipment must have operating sound power or sound pressure levels that would meet the predicted noise levels.

Rental plant and equipment Noise emissions should be considered as part of the selection process.

Use and siting of plant Avoid simultaneous operation of noisy plant within discernible range of a sensitive receiver.

The offset distance between noisy plant and adjacent sensitive receivers is to be maximised.

Plant used intermittently to be throttled down or shut down.

Plant and vehicles to be turned off when not in use.

Noise-emitting plant to be directed away from sensitive receivers.

Plan works site and activities to minimise noise and vibration

Plan traffic flow, parking and loading/unloading areas to minimise reversing movements within the facility.

Non-tonal reversing alarms Non-tonal reversing beepers (or an equivalent mechanism) must be fitted and used on all construction vehicles and mobile plant regularly used on the facility and for any out-of-hours work.

Minimise disturbance arising from delivery of goods to construction sites

Loading and unloading of materials/deliveries is to occur as far as possible from sensitive receivers.

Select site access points and roads as far as possible away from sensitive receivers.

Dedicated loading/unloading areas to be shielded if close to sensitive receivers.

Delivery vehicles to be fitted with straps rather than chains for unloading, wherever possible.

Path controls

Shield stationary noise sources such as pumps, compressors, fans etc.

Stationary noise sources should be enclosed or shielded whilst ensuring that the occupational health and safety of workers is maintained.

Shield sensitive receivers from noisy activities

Use structures to shield residential receivers from noise such as site shed placement; earth bunds; fencing; erection of operational stage noise barriers (where practicable) and consideration of site topography when situating plant.

In addition to the standard mitigation measures identified in the Transport for NSW CNS, the following specific mitigation measures have been developed as a result of the predicted impacts associated with the proposal.

To minimise noise levels, the work practices in Table 9.1 practices should be implemented in addition to minimising the potential for construction vehicles to access the facility prior to 7am.

To minimise the risk of vibration impacts, the following is recommended:

ensure that safe working distances are complied with

where work is required within the distance, site-specific safe working distances are to be established on-site prior to the relevant vibration generating works commencing

where possible, the use of less vibration intensive methods of construction or equipment should beconsidered where possible to reduce the potential for cosmetic damage

all equipment should be maintained and operated in an efficient manner, in accordance withmanufacturer’s specifications, to reduce the potential for adverse vibration impacts

if vibration intensive equipment is to be used within the safe working distances, vibration measurementsare to be undertaken when work commences

Page 55: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

41

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

assess the condition of heritage items to assign the appropriate vibration limits and set safe workingdistances

conduct building condition surveys of buildings before and after works where work inside the safeworking distances is required.

To minimise the potential for sleep disturbance, where night works are proposed to be undertaken, the following controls should be implemented where feasible and reasonable:

avoid conducting noise intensive night works for more than two consecutive nights

schedule noise intensive activities to before 10pm

schedule activities which are likely to cause maximum noise events such as deliveries, moving materialor equipment and compacting works to avoid the night time period (10pm to 7am)

avoid dropping tools or materials from height, striking materials, dragging materials or making metal onmetal contact

educate workers on the importance of minimising noise and avoid creating short duration high noiselevel events

inform surrounding residents by mail of planned works prior to the works commencing.

Table 9.2 provides an indicative benefit of typical mitigation measures for construction activities, based on guidance in AS 2436 and experience on similar construction projects.

Table 9.2 Indicative noise reduction from construction controls

MANAGEMENT AND ENGINEERING CONTROLS POSSIBLE NOISE BENEFIT, dBA

Noise Management Controls

Operate during approved hours N/A

Undertake regular noise monitoring to determine the impact of operating plant on sensitive receivers

N/A

Appropriate training of onsite staff N/A

Undertake community consultation and respond to complaints in accordance with established project procedures

N/A

Turning off machinery when not in use 0-5

Respite periods for pile drivers and rock breakers N/A

Engineering Controls

Portable temporary screens 5-10

Screen or enclosure for stationary equipment 10-15

Maximising the offset distance between noisy plant items and sensitive receivers. 3-6

Avoiding using noisy plant simultaneously and/or close together, adjacent to sensitive receivers.

2-5

Orienting equipment away from sensitive receivers. 3-5

Carrying out loading and unloading away from sensitive receivers. 3-5

Using noise source controls, such as the use of residential class mufflers, to reduce noise from all plant and equipment including bulldozers, cranes, graders, excavators and trucks

5-10

Selecting Facility access points and roads as far as possible away from sensitive receivers 3-6

Using spotters, “smart” reversing alarms, or “squawker” type reversing alarms in place of traditional reversing alarms

N/A

Page 56: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

42

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

9.1 Application of additional mitigation measures

According to the Transport for NSW CNS, where there is potential for a project’s construction noise objectives to be exceeded, a number of additional measures to mitigate such exceedances should be explored. The additional mitigation measures matrix is primarily aimed at pro-active engagement with affected receivers.

Table 9.3, reproduced from the Transport for NSW CNS, outlines what measures may apply depending on the level by which the predicted noise levels exceed the measured RBLs, and the time of the day.

Additional mitigation measures that may be applicable to affected receivers include letterbox drops, noise monitoring, individual briefings, phone calls, specific notifications, proposal specific respite offers and alternate accommodation. Specific additional mitigation measures would be identified for affected receivers at the CNVMP stage of the project.

Table 9.3 Application of mitigation measures in addition to Transport for NSW Construction Noise Strategy standard mitigation measures

Page 57: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

43

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

10 OFF SITE ROAD TRAFFIC NOISEThe potential for the proposal to generate additional traffic on the surrounding roads has been considered.

As the operations of the maintenance facility are not expected to significantly change, the road traffic generated by the facility is also not expected to significantly increase.

During construction, additional vehicles would need to access the facility for employees, equipment and material deliveries.

For works at subject site 1 and 2, access to the sites would be via the existing driveway on Railway Parade. For subject site 3, the access would be off Cornwallis Street. It is envisaged that construction employee would access the facility and utilise existing parking facilities at the main entrance off Railway Parade.

The potentially affected roads would be Railway Parade, Henderson Road, and Cornwallis Street. Other major roads in the vicinity which would provide access include Gibbon Street, Botany Road and Swanson Street.

The RNP criteria for traffic generating developments is limited to an increase of 2 dBA or less above the existing traffic noise levels. In order to generate an increase of more than 2 dBA, the traffic volume needs to increase by more than 60%. Given the small size and scale of the proposed construction works, an increase of more than 60% of the total traffic volumes on any of the project related roads is not considered likely. Therefore the risk of adverse impacts from construction traffic is considered low.

Page 58: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

44

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 59: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

45

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

11 SUMMARY OF ENVIRONMENTAL NOISEAND VIBRATION IMPACTS

The predicted impacts with the mitigation recommended in Sections 6.3 and 9 as a result of the proposal have each been assigned a rating. The rating considers the likelihood of the impact occurring and the magnitude of the impact on the receiving environment. The ratings are defined where one or more of the following conditions are satisfied:

negligible: where the predicted changes are not sufficient to affect ambient noise or vibration levelsbeyond natural variations

minor: where there is predicted to be some level of generated noise and vibration or there is aperceptible change that would occur for less than a week during construction and is generally below theoperational criteria

moderate: where there is predicted to be a perceptible change in noise and vibration lasting more than aweek, an exceedance of the ‘noise affected’ noise management levels, the potential for sleepdisturbance to occur at some point or the potential for ground-borne vibration to cause cosmeticdamage or to result in ‘annoyance’ at some point during construction

major: where there is predicted to be a notable change in noise and vibration lasting more than threeweeks, an exceedance of the ‘highly noise affected’ construction noise management levels, the risk oflong-term sleep disturbance or an accepted certainty that ground-borne vibration would have an impacton people or buildings.

Table 11.1 Summary of noise and vibration impacts using recommended mitigation

SOURCE ASSESSED IMPACT RECOMMENDED MITIGATION

Operational noise daytime Minor See section 6.3

Operational noise: evening Minor to moderate See section 6.3

Operational noise: night Moderate See section 6.3

Operational noise: sleep disturbance Moderate to major See section 6.3

Operational vibration Negligible Not applicable

Operational road traffic Negligible Not applicable

Construction noise: standard hours Minor to major See Section 9

Construction noise: outside of standard hours Minor to major See Section 9

Construction vibration: building damage Minor See Section 9

Construction vibration: human perception Minor See Section 9

Construction road traffic Minor See Section 9

Page 60: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.
Page 61: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

46

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

APPENDIX A NOISE MONITORING DATA

Page 62: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

A-1

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

Page 63: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

A-2

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 64: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

A-3

New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Transport for NSW

Page 65: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.

A-4

Transport for NSW New Intercity Fleet Eveleigh Facility Project Noise and Vibration Assessment

Page 66: New Intercity Fleet Eveleigh Facility Project Review …...Commissioning activities are expected to include static testing in the Millennium shed and dynamic testing on the rail network.