New Facade for Redmond Berry - Report
-
Upload
hizkia-irwanto-gouw -
Category
Documents
-
view
224 -
download
5
description
Transcript of New Facade for Redmond Berry - Report
Building Report: Redmond Barry
ABPL90268: Building Envelopes. Chris Jensen
Ben De Nardi 384121, Kai Ning Huang 314675, Hizkia Gouw 378785
Report 1: Redmond Barry
2
Contents:
1. Existing building report Pg. 3
2. Façade additions Pg. 5
3. Specifications Pg. 16
4. Suppliers Pg. 21
5. Glossary Pg. 24
6. References Pg. 25
Report 1: Redmond Barry
3
The Redmond Barry building.
The Redmond Barry building was built in 1961, and is named after Sir Redmond Barry. Sir
Redmond Barry was a judge in colonial Victoria, Australia and the first chancellor of Melbourne
University. It is located on the main campus of Melbourne University on Tin Alley.
West Wall
Existing building conditions
The building is considered an example of post-war modernist architecture, with the
landmark tower and use of cream bricks. The Redmond Barry is a 12 storey building constructed
using a slab and podium system of steel and reinforced concrete columns, with shear wall infill’s.
The podium is a low wall that acts as the foundations for the building. The shear walls
counter the effects of lateral forces on the building. In the Redmond Barry building these are the
brick infill walls that are expressed in the façade. The structural columns and floor slabs can also be
seen throughout the façade.
The north and south façade are composed of single brick walls with single layer glazing units
that are framed by the structural columns and floor slabs. The north wall has had aluminium sun
shades retro-fitted to the exterior. The east wall is the lift core and has a single brick wall enclosing
the lift cores. The west wall houses the fire stairs and is also a solid brick façade.
Report 1: Redmond Barry
4
The building is 61 metres long and 13 metres wide, the long axis of the building is on an east-
west plane.
Façade performance:
Improvements to the building envelope will bring the buildings energy performance up to
contemporary BCA (Building Council Australia) standards.
Overall performance improvement
Report 1: Redmond Barry
5
Façade Improvements
To improve the buildings energy performance and user comfort the following improvements
will be made to the façade. The building envelopes changes are aimed at improving the buildings:
• Thermal performance – especially in regards to cooling the building
• Natural daylight
These alterations will increase the buildings ability to passively deal with temperature
fluctuations and therefore decrease the need to consume energy to heat and cool the interior.
Daylight will also reduce the need for artificial lighting, also reducing energy use within the building.
Aesthetics:
Any alterations to the building’s façade will change the buildings appearance, whilst not a
primary consideration, it is a consideration.
The following alterations will be made to the Redmond Barry building.
Report 1: Redmond Barry
6
South Wall:
The space above the lecture theatres on the southern wall are extruded, which expands the
classroom spaces (refer to drawing A.007). Those blocks are similar in term of width and length (6 x
9-42 m), but vary in height (6, 8, and 10 levels height). The positions of those blocks are in line with
the existing column grid of the Redmond Berry (refer to drawing A.001). Curtain wall are installed in
the south façade of the extrusions, where precast concretes are used for the sides. A metal roof
cladding is used for each block.
Glazing:
The primary intention of using the glazed curtain wall on the south side is to maximise the
daylight into the building. This will brighten the space and reduce the need for artificial lighting
during the daytime. As there is no direct sunlight on the southern façade no shading devices will
need to be installed. Moreover, the use of curtain wall without shading would also provide
undistracted view from the inside.
On the southern wall a Unitized Curtain Wall system will be used as the construction
technique. The main benefit of this technique over traditional stick curtain walls is the speed of
construction. It also minimalizes the need for on-site labour and workers during the installation
Report 1: Redmond Barry
7
phase, as all the elements are not only pre-fabricated but also pre-assembled as a complete unit in
the factory.
This prefabrication method would also give huge advantage in term of the quality control.
For example, because of the units are specifically designed, the amount of movement between the
structure and the thermal movement of the frame at the joints between each curtain wall unit, can
be carefully engineered into the system. In addition, it will also reduce or eliminate the need of site
sealing. So, at the end, the installation of the curtain wall is less dependable on the quality of
workmanship onsite. The offset to these benefits is the increase in cost, both in construction and
shipping the modules to the site.
Each module of the curtain wall unit contains the combination of double glazing and a
spandrel panel. The use of double glazing (refer to drawing A.025) will reduce the heat loss from the
large areas of glazing within the curtain wall. The spandrel glasses (6mm Jasper Colour Viridian
Seraphic Standard) are used to cover the floor slabs to prevent them being seen from exterior. The
spandrel panels (refer to drawing A.025) are also need to be insulated in order to perform a fire
protection, accordance to AS1530.4.
Rockwool Fireseal Curtain Wall Batt from Bradford will be used as the insulation material. It
can provide fire protection to a curtain wall system for up to 2 hours. The rockwool insulation batts
are installed between the spandrel panels and the edge of the concrete slab.
The installation of the Unitized Curtain Wall will be done by Keystone Installation, a specialist
in façade installation constructing service. The installation process is a simple one (refer to drawing
A.023). The first step is to determine the position of the anchor assembly in the floor slabs, and then
install them in the correct position.
The second step is the erection of the curtain wall. The two common methods are
with a crane on either the outside or inside of the building. In this instance a ground based external
crane is preferable as it has more access and manoeuvrability.
The other typical crane used in high-rise construction is the tower crane. This requires the
crane to be attached to the building that is being constructed, which in this case is not possible, as all
four facades are being altered.
Report 1: Redmond Barry
8
Pre-cast concrete:
To create the extrusions above the existing lecture theatres precast concrete cladding panels
are installed. The speed of installation and quality control afforded, due to the controlled casting
environment, by precast concrete panels over in-situ concrete is the reason for using pre-cast panels
in this instance.
There will be two types of bearing connections that will be applied to hold the precast in
place (refer to drawing A.021). The first type of connection is using concrete corbels and cast in
dowel fixings (load carrying fixing), which connect the bottom of the panel with the floor slab. The
second type, tie-back fixing, will be used to tie the top of the panel into the concrete beam. In this
fixing, a steel angle will be bolted into the precast panel and the concrete beam.
In term of the performance, those precast panel will be insulated using bulk insulation inside
each panel (refer to drawing A.021). 75mm Bulk Insulation (Flexitel 24kg/m3) increases the r value of
the wall by a significant amount, which also means a better thermal resistance for the wall. In
addition, each concrete panel will also contain vents (200x300mm in size), which will allow fresh air
to be drawn from the exterior by the convection that is created by the trombe wall and thermal
chimneys. The opening of the vents is designed with a slight angle in order to prevent water
penetrating into the building. Wire mesh covers each vent, so insects and animals and some dirt
cannot get in.
Metal Roofing:
The roof of the extrusions will be covered by a metal roof. The precast concrete panels in the
side of the extrusion are extended to create a parapet of 500mm height. This parapet hides the
metal roof from the exterior of the building. The Lysaght Klip Lock 46 is used for the metal roofing.
The roof will have 2 degrees slope toward south wall (curtain wall) with a box gutter just behind the
parapet.
Two types of insulation will be used in the roof: reflective insulation and glass-wool
insulation. The reflective insulation material (thermofoil medium duty sarking foil) is installed just
beneath the metal roof. It performs as a waterproofing membrane and vapour barrier that providing
a secondary barrier against moisture, heat, wind, dust penetration, and condensation control under
Report 1: Redmond Barry
9
the metal roofing. Then the glass-wool insulation (Anticon 95) is placed in the space between the
purlin. It provides efficient thermal insulation for the roofing.
Concrete floor slab:
Floor board insulation
Concrete floor slabs are used for the extension from the existing floor slab. In order to
achieve a required R-value, board insulations (Kooltherm K10 FM Soffit Board) are installed just
under the floor slab (refer to drawing A.022). The dimension of each insulation board is 2270 x
1200mm, with 30mm thickness. Each soffit board is fully fixed to the concrete slab using 11
insulation fasteners provided by Kingspan. The insulation fasterners are penetrated into the slab by a
minimum of 40mm.
Report 1: Redmond Barry
10
North Wall:
The northern façade will be replaced with a double glass curtain wall. This wall will work to
allow more natural lighting into the building. It will also act as a trombe wall; this will improve
cooling within the building and maintain the interior air quality.
The exterior glazing unit will need to allow maximum daylight through. Typically with high
light transmission glazing products a high percentage of transmission means poor performance in it
insulating qualities. For the purpose of the trombe wall creating a hothouse effect beyond the initial
façade is a positive; therefore the exterior leaf will be single glazed panels. The thermal chimneys on
the east and west walls will act in tandem with the trombe wall in promoting convection.
Trombe wall diagram
The interior glazing will be a double glazed, with mechanized vents (refer to drawing ). The
double glazing improves the insulation of the wall whilst keeping maximum transparency. It will also
act as a fire barrier between floors.
The vents will be placed at the top and at the bottom of each section. The vents will be
automatically operated to maintain interior air temperature as well as for night purging. The cooler
air will be collected from the lower vents as well as vents in the southern wall, whilst the higher
vents will expel the warmer air from the interior. The vents will be operated by an automated
building management system (BMS). The aim will be to maintain a temperature range of 21° to 24°.
The BMS will also manage the night purge. The vents will be opened in the late evening to flush the
hot air out of the building and let it cool down over night. During the winter months, the night purge
will operate on reduced hours, so as to retain heat for the building users for the next day, but also
bring fresh air into the building.
Report 1: Redmond Barry
11
The roof of the trombe wall will be a metal cap. This will be painted black to promote the
heating of the air within the trombe wall.
The installation of the Trombe Wall glazing will be done by Keystone Installation. See South
wall details for installation process.
Fittings:
The hung curtain wall will be attached to the existing floors slabs by the components
supplied by Spider fittings. A connector bracket is attached to each floor slab (refer to drawing ),
from which tension rods are then thread through. The tension rods have the 4-point wall spiders
(refer to drawing ) threaded onto them. Each of the wall spiders has attachment points that routels
use to connect the glass. The routels have a silicon ring that thermally breaks the aluminium.
Glazing:
A single leaf of 6mm Clear VFloat glazing will be used on the exterior for the trombe wall.
This glass was picked for its high daylight transmission, 88%, allowing maximum daylight into the
building. The high U-value and SHGC act to the benefit of the trombe wall.
As the glazing heats up the air within the trombe wall cavity the hot air rises. As the hot air
rises it draws cooler air up via convection. This cooler air is supplied into the building through the
vents that are located on the southern side and at the bottom of each floor of the northern side. This
creates an internal atmosphere that is constantly supplied with fresh cool air.
The glazing will need to be lifted into place via a crane, with labourers in cherry pickers
attaching the glass to the pre-positioned wall spiders.
Double Glazing:
The internal wall of the trombe wall will be double glazed. Viridian windows make a Viridian
Energy tech unit which is two sheets of 4mm glass with a 12mm air gap. This arrangement continues
Report 1: Redmond Barry
12
to allow maximum daylight transmission, 75%, whilst also being an effective insulating barrier
between the internal and external environment.
A low U-value means that despite the increased temperature from the trombe wall this will
not be transferred to the interior environment of the building.
The double glazing can be fitted during the construction of the external glazing of the
trombe wall as it is set back from the external leaf of glass.
Metal roof:
An aluminium panel that is coloured black is fitted over the top of the trombe wall. It caps
across from the existing roof and encapsulates the front edge of the external glazing. This cap
prevents moisture entering the trombe wall environment and being black captures more heat to
heighten the working of the trombe wall.
Report 1: Redmond Barry
13
West Wall:
On the west wall two concrete thermal chimneys will be added. The northern one will work
with the trombe wall in removing hot air from the air cavity of the trombe wall. The southern
chimney will remove hot air from the interior of the building via direct vents into the bottom of each
floor. The existing brick veneer wall on the west wall will also be replaced by precast panel with
insulation and interior lining, which will increase the thermal performance of the wall and provide
flexibility to the connection between the thermal chimneys and the wall itself.
Thermal chimney diagram
Precast Concrete Panel:
150mm precast concrete panel will be employed in both west wall and thermal chimneys.
As mentioned above, the precast concrete panels have advantages on installation speed and quality
control; and this is the reason that precast concrete panel is the more preferable building material
than other types of concrete in this project.
The joints of the precast panels’ construction will be the open- drained joint. It consists of an
expansion chamber which acts as a rain barrier, a loose-fitting baffle which placed in the chamber, an
air-seal which placed at the interior face of the panel and a short length flashing sitting beneath. The
baffle in the chamber prevents direct entry of the wind-driven rainwater. The air pressure between
Report 1: Redmond Barry
14
the chamber and the baffle will be the same as the external air pressure. Thus, no rainwater will be
driven into the building because of the pressure difference. The air-seal at the face of interior is the
barrier of the external and internal air pressure. The water enters the joint will be eventually
discharged by the short length flashing.
The open-drained joint is designed for the mid-rise and high-rise buildings. The air-seal at the
rear is protected from the UV light; therefore the seal will perform perfectly in long-term. The joint
can also be installed from inside, which provide great flexibility to the builder for the west wall
construction. The open-drained joint is also able to tolerant large movement. However, in the
chimneys there is no floor supporting the panels horizontally, which might be an issue for the
construction. In order to prevent the chimneys from falling down, restraint connections will be used
between the vertical panel joints. Panels will be bolted with cleat at every vertical joint, and
therefore it stabilizes the panels against out-of-balance gravity loads and resists the horizontal wind-
loads.
The chimneys will be a simple precast panel construction, but the west wall will be precast
panels with insulation and interior lining because it has to achieve the standard R-Value in BCA. A
layer of insulation of R2.7 will be placed behind the precise panels to increase the R-Value of wall
significantly. The plasterboard will be the interior lining with supported by the battens (30mm x
75mm in size). Same as the south wall extrusion, the west wall connected to the chimneys will have
small openings (100mm height, 200mm width) at the bottom of each level. These opening allow the
ventilation between the interior and the chimneys. They will be covered by wire mesh to prevent
unwanted objects get into the building. And they could be shut down during the winter to stop the
ventilation and keep the heat inside the building.
Metal Roof:
Same as the south extrusion, the thermal chimneys will employ the Lysaght Klip Lock 406 as
the roof system. The parapet is deeper to 1000mm and the slope will be increased to 8 degrees. A
rotating turbine ventilator will be located on the roof of each chimney, which helps exhaust the hot
air from the chimney. The rotating turbine ventilator could potentially be an electricity generating
device which transfers the wind force from the hot air exhausting out into electricity.
Report 1: Redmond Barry
15
Window Glazing
The window glass on the chimney will be Viridian SuperClear glass 10mm which has light
transmission rate at 90%. The more transparent means the more direct sun light can get into the
chimneys and heat up and air quicker. A layer of metal absorber with black coating will be place
behind the window glazing to increase the light absorbing of the chimneys.
East Wall:
The brick veneer wall that surrounds the lift core will be retained; insulation will be pumped
into the cavity behind the brick wall to meet modern BCA standards for the R-value. The product of
the infill insulation will be Sealection 500 from Unsulfoam. It is a polyurethane foam insulation which
could be injected into the cavity of the wall leaves and set. This product at 90mm thick is R 2.4.
To the north of the brick wall a concrete thermal chimney will be added. This will function
with the trombe wall being installed on the north wall. The thermal chimneys added to the building
will be concrete, which heats up and creates a convection effect, drawing cool air up as the hot air
rises.
Report 1: Redmond Barry
16
Specifications
This next chapter will contain the specifications for each of the new component of the
improvements made to the Redmond Barry building.
Trombe Wall
Glazing:
The glazing will be sourced from an Australian company called Viridian Glass. The exterior
panes will be Clear Vfloat, and the interior units will be from the Viridian energy Tech range.
Product Name Pane thickness
(mm)
Pane size U-value SHGC Daylight %
Clear VFloat 6 913 x 3350 5.8 0.82 88%
Viridian
Energy Tech
4mm with a
12mm gap
various 1.9 0.74 75%
Vents:
The glazed vents will be sourced from Hanlon windows. The vents will be the aluminium
Awning/Casement windows, series 466, with the automated option. The cooling and heating
percentages are in comparison to a base case window. This is measured as an increase in
performance as a percentage
Product
name
Glazing size
(mm)
Vent size
(mm)
U-value SHGC Cooling % Heating %
Aluminium
Awning
Window
Series 466
247 x 346 410 x 400 4.6 .3 56% 40%
Report 1: Redmond Barry
17
Double Glazing:
The cavity created between the floor slabs and the structural columns will be double glazed.
These aluminium units will also come from Hanlon windows. They will be 4 different sizes from the
Thermal heat range, series 730.
Product
name
Glazing size
(mm)
Vent size
(mm)
U-value SHGC Cooling % Heating % Number of
frames
needed per
cavity
Series 730 2300 x 850 2366 x
863
3.8 .42 52% 36% 4
Series 730 338 x 850 346 x
863
3.8 .42 52% 36% 8
Series 730 2300 x 388 2366 x
346
3.8 .42 52% 36% 2
Wall Spiders:
The aluminium components used to hang the exterior glass wall will be sourced from China,
from Spider Fittings.
Spider fittings will provide the routels that attach the glazing to the wall spiders, which are
then attached to the concrete floor slaps by connectors, with the whole assemblage held taught by
the tension rods.
The curtain wall is attached to the floor slabs every three floors.
Product name Size (mm) $ per unit # of units (approx.)
Wall spider 2501 250 x 250 $17.70 1200
Connector Z01 145 x 46 (dia.) $5.00 150
Routel T02 115 x 59 (dia.) $5.80 4800
Tension Rods G01 –
12”
27(dia) $13.90 2400
Report 1: Redmond Barry
18
West Wall
R-Value:
Layer R-Value
Outside Surface air Film 0,030
150mm Precast Concrete 0,104
90mm Insulation Wall Batt 2.7
10mm Plasterboard 0,059
30mm Air Gap 0.2
Total 3.093
Thermal chimney:
R-Value:
Layer R-Value
Outside Surface air Film 0,030
150mm Precast Concrete 0,104
Total 0.134
East Wall
R-Value:
Layer R-Value
Outside Surface air Film 0,030
355mm Precast Concrete 0,26
90mm Foam Insulation 2.4
110mm Brick Wall 0.18
Total 2.87
Report 1: Redmond Barry
19
Thermal chimney:
R-Value:
Layer R-Value
Outside Surface air Film 0,030
150mm Precast Concrete 0,104
Total 0.134
Southern Wall
Sourced from Viridian glass the curtain wall will use Clear Vfloat glass and the Viridian
Seraphic Standard, Jasper colour.
Usage Product Name Panel
thickness
Panel size U-value SHGC Daylight %
Double Glass
panel
Clear VFloat 2 x 6mm with
air gap in
between
1520 x 2300,
1520 x 2910
5.8 0.82 88%
Spandrel Unit Viridian Seraphic
Standard (Colour:
Jasper)
6mm 1520 x 950 5,5 0.67 55%
Concrete:
R-Value
Layer R-Value
Outside Surface air Film 0,030
150mm Precast Concrete 0,104
25mm Airspace 0,170
75mm Bulk Insulation Wall Batt 2,1
13mm Plasterboard 0,076
Report 1: Redmond Barry
20
Inside Surface air Film 0,120
Total 2,6
Metal Roofing:
R-Value
Material R-Value
0,48mm Metal Roof 0,00
Reflective Insulation Material 1,387
80mm Ceiling Insulation 1,8
13mm Plasterboard 0,076
Total 3,263
Concrete Floor Slab:
R-Value
Material R-Value
1cm Thick Carper Flooring 0,18
200mm Concrete Slab 0,139
30mm Board Insulation 1,4
Total 1,718
Report 1: Redmond Barry
21
Suppliers
Glazing
Material Supplier Website
Clear VFloat Viridianglass http://www.viridianglass.com/Products/vfloat/default.as
px?ProductType=Specifier
Viridian Seraphic
Standard (Colour: Jasper)
Viridianglass http://www.viridianglass.com/Products/seraphic-
standard/default.aspx?ProductType=Specifier
Viridian Energy Tech Viridianglass http://www.viridianglass.com/Products/seraphic-
standard/default.aspx?ProductType=Specifier
Unitized Curtain Wall
Installer
Keystone
Installations
http://www.keystoneinstallations.com.au/
Window frames Hanlon
windows
http://www.hanlonwindows.com.au/products_aluminiu
m.php
Curtain wall components Spider fittings http://www.spiderfittings.org
Rockwool Fireseal Curtain
Wall Batt
(spandrel insulation)
Bradford
Insulations
http://wwwbradfordinsulation.com.au/Products/Comme
rcial/Fire-protection/fireseal-curtain-wall-batt.aspx
Pre-cast concrete
Material Supplier Website
150mm Precast Concrete SA Precast Pty http://www.saprecast.com.au/
75mm Bulk Insulation
(Flexitel 24kg/m3)
Bradford
Insulation
http://www.bradfordinsulation.com.au/Products/Comme
rical/HVAC/Flexitel.aspx
13mm Plasterboard
(Enviro Multistop)
Boral http://www.boral.com.au/
Sealection 500 Insulfoam http://www.insulfoamsolutions.com.au/Pages%20Builder
s/Performance.html
150mm Precast Concrete SA Precast Pty http://www.saprecast.com.au/
Report 1: Redmond Barry
22
Metal Roofing
Material Supplier Website
0,48mm Metal Roof
(Lysaght Klip-Lok 46)
Lysaght http://www.lysaght.com/product/lysaght-klip-lok-406
Reflective Insulation
Material (Thermofoil
Medium Duty Sarking
Foil)
Bradford
Insulation
http://www.bradfordinsulation.com.au/Products/Comme
rical/Thermofoil-Foil-Sarking/Thermofoil-MD-
Sarking.aspx
80mm Ceiling Insulation
(Anticon 95)
Bradford
Insulation
http://www.bradfordinsulation.com.au/Products/Comme
rical/roofing-blanket/Anticon.aspx
13mm Plasterboard
(Enviro Multistop)
Boral http://www.boral.com.au/
Concrete floor slab
Material Supplier Website
1cm Thick Carpet
Flooring (Chamonix)
Carpet Court http://www.carpetcourt.com.au/products/Carpet/urban-
lifestyle/Chamonix
200mm Concrete Slab SA Precast Pty http://www.saprecast.com.au/
30mm Board
Insulation
(Kooltherm® K10 FM
Soffit Board)
Kingspan http://www.kingspaninsulation.com.au/Products/Kingspan-
Kooltherm/Kooltherm-K10FM-Soffit-Board/R-values.aspx
Thermal Chimney
Material Supplier Website
5500 ISOWEB Window KAWNEER http://www.kawneer.com/kawneer/north_america/en/p
roduct.asp?cat_id=1910&prod_id=1867
GOLD™ HIGH
PERFORMANCE WALL
BATTS
Bradford http://www.bradfordinsulation.com.au/Products/Reside
ntial/Thermal-insulation/Gold-high-performance-
wall.aspx
Report 1: Redmond Barry
23
Regular 10mm
Plasterboard
Boral http://www.boral.com.au/productcatalogue/product.asp
x?country=AUS&product=930
0,48mm Metal Roof
(Lysaght Klip-Lok 46)
Lysaght http://www.lysaght.com/product/lysaght-klip-lok-406
150mm Precast Concrete SA Precast Pty http://www.saprecast.com.au/
Report 1: Redmond Barry
24
Glossary
U-value1:
The U-Value is a measure of the rate of heat gain or loss through a glazing unit. It is due to
the environmental differences between the indoor and outdoor air. The lower this number is the
better the glazing is for insulating the building.
SHGC (Solar Heat Gain Coefficient)2:
The SHGC is the proportion of total solar radiation that is transferred through the glass at a
normal rate of incidence. The lower this number is the better for insulating the building.
R-value
The R-Value is a measure of thermal resistance of a material.
The higher that the R-Value is indicates the greater the effectiveness of the buildings insulation. It is
also the reciprocal of the U-Value.
1http://www.viridianglass.com/default.aspx
2ibid
Report 1: Redmond Barry
25
References
http://artemisbs.com/curtain-wall-products/unitized-curtain-wall/
http://islandglass.bm/commercial/curtain-wall/unitized/
http://www.boral.com.au/
http://www.bradfordinsulation.com.au/Products/Commerical/HVAC/Flexitel.aspx
http://www.carpetcourt.com.au/products/Carpet/urban-lifestyle/Chamonix
http://www.enclos.com/news-
page/modular_prefab_the_installation_of_unitized_curtainwall_systems
http://www.hanlonwindows.com.au/products_aluminium.php
http://www.insulfoamsolutions.com.au/Pages%20Builders/Performance.html
http://www.keystoneinstallations.com.au/
http://www.kingspaninsulation.com.au/Products/Kingspan-Kooltherm/Kooltherm-K10FM-Soffit-
Board/R-values.aspx
http://www.lysaght.com/product/lysaght-klip-lok-406
http://www.saprecast.com.au/
http://www.spiderfittings.org
http://www.sustainability.vic.gov.au/resources/documents/Window_protection.pdf
http://www.syracuseglass.com/E-
DOCS/Spandrel%20Glass/EDOCS/Spandrel%20Glass%20Insulation.pdf
http://www.viridianglass.com/default.aspx
http://www.wausauwindow.com/education/curtainwall/curtainwall.pdf
http://wwwbradfordinsulation.com.au/Products/Commercial/Fire-protection/fireseal-curtain-wall-
batt.aspx