New Dimension of Digital Construction - KIBIM Dimension of... · 4D Mixed Reality Synchro Software...
Transcript of New Dimension of Digital Construction - KIBIM Dimension of... · 4D Mixed Reality Synchro Software...
4D Construction Planning on the (LAX) Midfield Satellite Concourse North Project
Shaohua Guan 4D Planner Synchro, Turner-PCL, A Joint Venture
Sean Zook, R.A. Construction VDC/BIM Manager Turner-PCL, A Joint Venture
4D Production Team
• (1) Scheduling Manager • (3) CPM Schedulers • (1) 4D Scheduler • (1) VDC Manager • (3) VC Engineers Operation Team input from • Superintendents • Project Managers With BIM support from • Design Consultants • Subcontractors
Pulling the BIM Together
Fabrication Models
Navisworks
Synchro
https://partslab.pcl.com/
Civil 3D Revit
PLUGIN
Jared Landa, Superintendent Bahman Daniali, Senior Scheduler Shao Guan, 4D Planner Sean Zook, VDC Manager Jared Landa, Superintendent Shao Guan, 4D Planner Sean Zook, VDC Manager Shao Guan, 4D Planner Sean Zook, VDC Manager Jared Landa, Superintendent Bahman Daniali, Senior Scheduler Shao Guan, 4D Planner Project Team
Case Study #1
Draft Pictorial Schedule
Draft 4D
Review
Update 4D Plan
Pull Plan Session
Case Study #2 – Team & Process
Patrick Goforth, Project Manager Dave Kimmons, Superintendent Ryan Priest, Tunnel Scheduler Shao Guan, 4D Planner Bahman Daniali, Senior Scheduler Stakeholder Consumers
TPJV Executives LAWA Inspectors
Sub-Trades Grading Site Utilities Structural Concrete
Baseline Tunnel
Schedule
Pull Plan Session
Solution(s) Diagrammed
Fragnet Schedule
Developed
Master Schedule Updated
4D Model Synchronized