New DDEC Paper No. 47/2013 District Development and … · 2014. 12. 30. · 1 DDEC Paper No....
Transcript of New DDEC Paper No. 47/2013 District Development and … · 2014. 12. 30. · 1 DDEC Paper No....
1
DDEC Paper No. 47/2013
(for discussion on 2.12.2013)
District Development and Environment Committee, Southern District Council
Progress Report on Planning Works in Southern District
Annex 1
Matters discussed at previous meetings that required follow-up actions
(Progress as at 18.11.2013)
Annex 2
Planning Department-Progress Report on Planning Works in Southern District
(Progress as at 31.10.2013)
Annex 3
Highways Department-Progress Report on Road Works in Southern District
(Progress as at 31.10.2013)
Annex 4
Civil Engineering and Development Department-Progress Report on Other Works in Southern District
(Progress as at 31.10.2013)
Annex 5
Housing Department-Progress Report on Public Housing Works in Southern District
(Progress as at 31.10.2013)
Annex 6
Food and Environmental Hygiene Department-Progress Report on FEHD District Minor Works in Southern District
(Progress as at 31.10.2013)
Annex 7
Lands Department-Progress Report on Lands Department Temporary Government Lands Allocation in Southern District
(Progress as at 31.10.2013)
2
Abbreviations for government departments in this report: (in alphabetical order)
CEDD Civil Engineering and Development Department
DEVB Development Bureau
DSD Drainage Services Department
EPD Environmental Protection Department
FEHD Food and Environmental Hygiene Department
HD Housing Department
HyD Highways Department
LandsD Lands Department
LCSD Leisure and Cultural Services Department
MD Marine Department
PlanD Planning Department
SWD Social Welfare Department
TD Transport Department
THB Transport and Housing Bureau
WSD Water Supplies Department
3
Annex 1
Matters discussed at previous meetings that required follow-up actions
(Progress as at 18.11.2013)
Latest Progress on Matters Date of First Discussion
(Date of updates)
1. The former Harbour Mission School, Ap Lei Chau
Updates on the item will be reported when there is further progress.
April 2006
2. Ex- Shek O Quarry
Updates on the item will be reported when there is further progress.
30.11.2009
3. Request to Improve the Drainage System of the Villages in Southern District
(I) On Pokfulam Village
DSD advised that the Technical Feasibility Statement (TFS) compiled by DSD was approved by Development Bureau (DEVB) on 1 August 2013
Currently, the project is a Category B project in the Public Works Programme (PWP Item No. 4400DS).
Preliminary design of the project has commenced. DSD introduced the location of the proposed sewage pumping station and the preliminary
sewer alignment to Pokfulam Village Sewerage System Concern Group (the Concern Group) and Member of the local constituency on 22
November 2013. DSD and EPD will follow up on the comments raised by the Concern Group during the meeting.
16.5.2011
(26.11.2013)
4
(II) On Shek O Village, Wong Chuk Hang San Wai Village, Kau Wai Village and Tai Hau Wan Village
LCSD should be approached in advance for processing application for any proposed permanent alienation of portion of the Wong Chuk Hang
Road Garden by FEHD for constructing a public toilet for alternative arrangement with the MTRCL in respect of its original plan to reinstate
the concerned area into a planting area.
FEHD advised that ArchSD provided two preliminary proposals on 15 October after conducting joint inspection to the site at Wong Chuk Hang
San Wai Village with LCSD on 15 August. One proposal suggested the entrance of the public toilet facing Wong Chuk Hang Road and the
other one suggested the entrance facing San Wai Village. Having discussed with DC member Mr. Fergus FUNG, the entrance facing Wong
Chuk Hang Road was more acceptable. FEHD had informed ArchSD to conduct feasibility study on this proposal.
(14.11.2013)
(25.11.2013)
4. Renewal Application for WSD worksite at Ap Lei Chau Praya Road (TGLA No. GLA-THK 1162)
WSD responded that LandsD had allocated and handed over the site at Tai Tam Reservoir Road near Parkview (Tai Tam Reservoir Road site) to
WSD as contractor’s pipe material storage and maintenance yard on 30 August 2013 and 6 September 2013 respectively.
Further to the 11th
DDEC meeting on 30.9.2013, WSD submitted a modified hoarding design scheme for the maintenance yard at Tai Tam
Reservoir Road site on 6.11.2013 via the Secretariat for Member’s reference. Members were also requested to offer comments on the
respective schemes on or before 15.11.2013. WSD received the replies from nine Members in total on 15.11.2013, and amongst them five
Members supported Option B of the modified hoarding design (see Appendix 1), one Member has no comment and three Members objected to
the modified design and recommended WSD to adopt the scheme suggested by Mr. Paul ZIMMERMAN in the 11th
meeting (i.e. the hoarding of
LCSD’s nursery at Pok Fu Lam Road, see Appendix 2).
As the majority of the Members support Option B of the modified hoarding design, WSD hoped that DDEC would approve this scheme so as to
enable the relocation of the existing WSD’s maintenance yard at Ap Lei Chau Praya Road to Tai Tam Reservoir Road within three months upon
confirmation of the hoarding design. Based on the current progress, WSD is unable to relocate the maintenance yard at Ap Lei Chau Praya
Road on or before 31.12.2013. As such, WSD has written to DLO/HKW&S on 6.11.2013 for application of short-term extension of WSD’s
maintenance yard at Ap Lei Chau Praya Road, until WSD’s Contractor can be moved to the Tai Tam Reservoir Road site.
(20.2.2012)
(21.11.2013)
LandsD advised that approval of the Temporary Government Land Allocation of the Tai Tam Reservoir Road site was granted to WSD and the
site was also taken over by WSD in early September 2013.
(12.11.2013)
5
5. Short-term and Long-term Uses of the Site of Aberdeen Fire Station (AFS)
Please refer to Annex 2 (p.7) of this paper.
26.3.2012
(20.11.2013)
6. Utilisation of Facilities in Public Space at Stanley Plaza under the Charge of the Link
LandsD advised that the LINK submitted 2 applications to place tables and chairs in front of Stanley Plaza. LandsD approved the LINK’s
application at the “Public Open Space” in February 2013. Regarding the application at the “Non-building Area”, LandsD has in-principle
approved the application subject to the agreement with the LINK on the amount of waiver fee.
28.5.2012
(12.11.2013)
7. Re-tendering of Short-Term Tenancies for Shipyard Use at Ap Lei Chau Praya Road
LandsD advised that the tender for the short term tenancies was invited from 29.5.2013 to 5.7.2013. A total of 144 bids were received. LandsD
had assessed the submitted tenders in accordance with applicable procedure; and has informed the successful tenders of the 16 short term
tenancies. Moreover, information on the successful tenderers, such as the name and amount of rent etc., has been uploaded to LandsD website
accordingly.
30.7.2012
(12..2013)
8. Planning Application for the “Comprehensive Development Area” Site in Wong Chuk Hang
Updates on the item will be reported when there is further progress.
26.11.2012
9. Provision of Facilities in the Convenience of Residents at the Government Land Adjacent to Jumbo Pier
Proposal 2: Construction of public lavatory
FEHD advised that ArchSD’s reply on 8.10.2013 revealed that there was no public sewer within 100 m from the government land near the
tennis court of Marina Club and the stability of the adjacent slope was required testing. Therefore the proposed site was not suitable for the
construction of public toilet. Whereas the suggestion of construction of new public toilet at portion of planting area near the existing temporary
refuse collection point at Shum Wan Pier Drive was feasible from technical point of view. FEHD had requested ArchSD to conduct feasibility
study on this proposal.
4.2.2013
(25.11.2013)
6
Annex 2
District Development and Environment Committee, Southern District Council
Progress Report on Planning Works in Southern District
(As at 31.10.2013)
I. Outline Zoning Plan
District Plan No. Project Description Progress / Remarks
Shouson Hill S/H17/12 The Town Planning Board (TPB) on 22.3.2013 gazetted
the draft Shouson Hill & Repulse Bay Outline Zoning
Plan (OZP) No. S/H17/12 under section 5 of the Town
Planning Ordinance for public inspection for 2 months.
The OZP incorporated amendments mainly related to
the rezoning of a “Government, Institution or
Community” (“G/IC”) site at Shouson Hill Road West
to “Residential (Group C)3” (“R(C)3”).
The District Development and Environment
Committee of the Southern District Council was
consulted on the proposed amendments on
15.4.2013.
During the 2-month exhibition period, TPB
received 210 representations (2 support and 208
oppose). The representations were published for
public comments on 7 June 2013 until 28 June
2013. No comment was received. TPB heard the
representations on 13 September 2013 and decided
not to uphold all the representations. The Chief
Executive in Council on 5.11.2013 approved the
draft OZP. The approved Shouson Hill & Repulse
Bay OZP No. S/H17/13 was exhibited for public
inspection on 15.11.2013.
7
Aberdeen &
Ap Lei Chau
S/H15/28 TPB on 12.7.2013 gazetted the draft Aberdeen & Ap
Lei Chau OZP No. S/H15/28 under section 5 of the
Town Planning Ordinance for public inspection for 2
months. The OZP incorporated amendments mainly
related to the rezoning of a “Government, Institution or
Community (1)” (“G/IC(1)”) site in Wong Chuk Hang
to “Other Specified Uses” annotated “Business” use.
The District Development and Environment
Committee of the Southern District Council was
consulted on the proposed amendments on
29.7.2013.
During the 2-month exhibition period, which ended
on 12.9.2013, TPB received 1 representation
submitted by Mr. TSUI Yuen-wa, the Southern
District Councillor. The representation was
published for public comments on 27.9.2013 until
18.10.2013. No comment was received. The
representation is tentatively scheduled for
consideration by the TPB in December 2013.
II. Planning Application
Application submitted for Town Planning Boards’s Consideration (1.9.2013 – 31.10.2013)
S.12A Application for Amendment of Plan
District Application No. Applied Use Location Consideration / Result Remarks
8
Shouson
Hill
Y/H17/1 To rezone the
application site
from “R(C)3”
to “Residential
(Group C)10”
(“R(C)10”)
subject to a
maximum
building height
of 187.82mPD
and 3 storeys
including
carports
3 Deep Water
Bay Road
On 8.11.2013, the Metro Planning
Committee (MPC) of TPB decided to
reject the planning application and the
reasons were:
(a) the current “R(C)3” zoning with
BH restriction of 3 storeys in
addition to 1 storey of carports
is appropriate and is compatible
with the surrounding land uses.
There is no strong planning
justification to support the
proposed rezoning from
“R(C)3” to “R(C)10”;
(a) the proposed rezoning with BH
restriction of 3 storey including
carports and 187.82mPD will
limit the design flexibility of the
development/redevelopment on
the site; and
(b) the approval of the rezoning
application would create
inconsistency in terms of
planning control for other sites in
the “R(C)3” zone within the
same Special Control Area.
During the first three weeks of the statutory
publication period, 104 comments were
received. Among them, 103 supported the
rezoning proposal as they considered the
proposed rezoning appropriate and effective to
preserve the existing amenities and characters
of the area and the general public views. One
objecting comment was mainly because the
application was unreasonable and unfair to the
owner and the restrictions under the current
OZP are sufficient.
During the first three weeks of the public
inspection period of the further information
(FI), 126 public comments were received.
Among them, 125 supported and 1 objected to
the application. The reasons were similar to
those mentioned above.
S.16 Application for Permission
District District District District District District
9
Ap Lei
Chau A/H15/256 Proposed Yacht
Centre-led
Mixed
Development
(including
Yacht Centre,
Marine Exhibit,
Shop and
Services and
Boatyards)
Government
land to the east
of Ap Lei Chau
Praya Road, Ap
Lei Chau
On 11.10.2013, the MPC agreed to
further defer the consideration of the
application by 2 months as requested
by the applicant.
During the first three weeks of the statutory
publication period, 1,628 public comments
were received. Among them, 1,023 supported
the application, 218 objected the application,
364 provided comments on the application
and the remaining 23 provided no comments.
The main supporting reasons were that the
application could avoid the environmental
impacts caused by the existing shipyards and
promote the tourism industry in Aberdeen.
The main reasons for objection were that the
application would have adverse impact on
Hong Kong’s ship repairing/maintenance
industry and the proposed shipyard operation
mode in the application was not suitable for
serving the customers of existing shipyards.
During the first three weeks of the statutory
publication period of the FI, 1,771 public
comments were received. Among them,
1,712 supported the application, 32 objected
the application and the remaining provided
comments/no comments on the application.
The reasons were similar to those mentioned
above.
10
Repulse
Bay
A/H17/129 Proposed
Minor
Relaxation of
Building
Height
Restriction
for Permitted
House
Development
Near 35
South Bay
Road
On 11.10.2013, the MPC approved
the planning application subject to
the following conditions:
(a) the submission and
implementation of a revised
layout of the proposed
development with a view to
reducing the total height of the
lower ground floor and
mechanical floor to the
satisfaction of the Director of
Planning or of the TPB;
(b) the provision of fire service
installations and water supplies
for firefighting to the satisfaction
of the Director of Fire Services or
of the TPB; and
(c) the submission and
implementation of tree
preservation and landscape
proposals, and provision of
quarterly tree monitoring reports
to the satisfaction of the Director
of Planning or of the TPB.
During the first three weeks of the statutory
publication period, 1 public comment was
received. The public comment objected to
the application as there would be no public
gain and no evidence that it was necessary to
build 1 storey for ancillary electrical and
mechanical facilities.
During the first three weeks of the public
inspection period of FI, 1 public comment
was received. The public comment objected
to the application as the approval of the
application would set an undesirable
precedent.
11
Repulse
Bay
A/H17/131 Proposed
School
(Kindergarten)
1/F, 35 Beach
Road,
Repulse Bay
On 11.10.2013, the MPC decided to
reject the planning application and the
reasons were:
(b) the proposed school was located
at a shopping centre accessible
via Beach Road with busy
traffic. Adverse traffic impact
arising from the proposed use
was anticipated. The applicant
had failed to demonstrate that
there would be effective traffic
measures to mitigate the
impact; and
(c) approval of the application
without adequately addressing
the traffic problem would set an
undesirable precedent for
similar applications in the area.
The cumulative effect of
approving such similar
applications would aggravate
the traffic condition of Repulse
Bay.
During the first three weeks of the statutory
publication period, 34 public comments
were received. Among them, 32 opposed the
application mainly on the grounds of adverse
traffic and noise impacts. The remaining 2
raised concerns on the necessity of a new
kindergarten.
12
Tai Tam A/H18/73 Proposed
Shop and
Services (on
Cockloft
Floor) for
House
Redevelopme
nt
461 Shek O
Village, Shek
O, Hong
Kong
On 27.9.2013, the MPC decided to
reject the planning application and the
reasons were:
(a) there was no strong justification
for the proposed ‘Shop and
Services’ use at the cockloft of
the application site; and
(b) approval of the application
would set an undesirable
precedent for similar
applications in the “Village
Type Development” zone. The
cumulative effect of which
would disturb the local
residential neighbourhood.”
During the first three weeks of the statutory
publication period, 8 public comments were
received. Among them, 7 opposed the
application mainly on the grounds of adverse
hygiene, traffic and environmental impacts
to the Shek O Village. The remaining one
raised concerns that the proposed use would
potentially change the character of village.
Stanley A/H19/66 Proposed
Holiday
Camp and
Emergency
Vehicular
Access for
the Related
Redevelopm
ent
A piece of
Government
Land, Stanley
Bay, Stanley,
Hong Kong
(The Hong
Kong
Federation of
Youth Groups
Stanley
Outdoor
Activities
Centre)
On 11.10.2013, the MPC agreed to
defer the consideration of the
planning application to the meeting
held on 22.11.2013 as requested by
the applicant.
During the first three weeks of the statutory
publication period, 1 comment was received.
The public comment considered that the
proposed redevelopment should adopt green
building methods and recycled materials.
During the first three weeks of the statutory
publication period of the FI, 11 public
comments were received. All comments
objected to the application mainly due to the
proposed development would affect the water
sports and recreation facilities nearby and the
proposal would cause significant adverse
visual, landscape and environmental impacts
on the surrounding area. The applicant on
8.11.2013 requested for a further deferment to
MPC meeting to be held on 13.12.2013.
13
Stanley A/H19/67 Proposed
Utility
Installation
for Private
Project
(Cable
Trench,
Drainage,
Water Pipe
and
Maintenance
Staircase)
Government
Land adjoining
18 Carmel
Road, Stanley,
Hong Kong
On 25.10.2013, the MPC agreed to
defer the consideration of the
planning application as requested by
the applicant.
During the first three weeks of the statutory
public period, 1 public comment was
received. The commenter objected the
construction of new maintenance staircase
and concerned about the proposed works
would adversely affect the slope stability.
The applicant on 30.10.2013 submitted FI.
The application is tentatively scheduled for
consideration by MPC on 13.12.2013.
S.17 Application for Review
District Application No. Applied Use Location Consideration / Result Remarks
Pok Fu Lam
A/H10/84
House
(Swimming
Pool and
Private
Garden)
Government
land adjoining
House B1,
Villa Cecil,
200 Victoria
Road, Pok Fu
Lam
On 13.9.2013, the TPB agreed to
defer the consideration of the
planning application as requested by
the applicant.
During the first three weeks of the statutory
publication period, 3 public comments were
received. Among them, 2 objected the
application mainly on the grounds that the
application site should not be used for private
use under the “Green Belt” zone. The
remaining one supports the application.
14
III. Progress of Hotel Development Projects in Wong Chuk Hang Business Area being Approved by Town Planning Board with Planning
Permission still Valid
1. 55-57 Wong Chuk Hang Road Approved hotel development completed.
[Lease modification for non-industrial use (including hotel) completed in 2004]
2. 1 Yip Fat Street Validity period of planning permission extended to Feb 2014.
[Lease modification for non-industrial use (excluding hotel) completed in 2010]
3. 34 Wong Chuk Hang Road Validity period of planning permission extended to Feb 2014.
[Lease modification for non-industrial use (excluding hotel) completed in 2010]
4. 43 Heung Yip Road Lease modification for non-residential use (including hotel) executed in 2007; approved development
considered as commenced.
5. 64 Wong Chuk Hang Road Planning permission valid until Feb 2016.
[Special Waiver under PN 1/2010 was executed in March 2013.]
6. 39 Wong Chuk Hang Road
Planning permission valid until Sep 2017.
[The previous lease modification application for non-industrial use (including hotel) was withdrawn by the
applicant in 11/2012. The existing lease is for industrial use and hotel is not permitted.]
7. 41-43 Wong Chuk Hang Road
Planning permission valid until Sep 2017.
[The previous lease modification application for non-industrial use (including hotel) was withdrawn by the
applicant in 11/2012. The existing lease is for industrial use and hotel is not permitted.]
15
Annex 3
District Development and Environment Committee, Southern District Council
Progress Report on Road Works in Southern District
(As at 31.10.2013)
I. Preliminary Project Plan of Construction Works
PWP No. / Cat. Type Project
Description Agency Progress / Remarks
Est. (Actual) Start
Date
Est. (Actual)
Completion Date
Cat. D item – Junction
Improvement at
Chung Hom Kok
Road / Stanley
Gap Road
Highways
Department
The cost estimate for the project was
assessed to be about $40M due to the latest
requirements on geotechnical works and
preservation of existing trees. Since the
project estimate exceeded the Cat D limit,
TD is reviewing the fund bidding and
implementation programme. The ground
investigation works were completed. TD is
currently looking at alternative option.
Under review Under review
16
Annex 4
District Development and Environment Committee, Southern District Council
Progress Report on Other Works in Southern District
(As at 31.10.2013)
I. Works Commenced
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
174WC/A Replacement and
Rehabilitation of Water
Mains Stage 1 Phase 2
WSD Construction works for Contract No. 15/WSD/05
commenced in August 2006. The progress of mainlaying
works are as follows:
(a) Wong Chuk Hang Road (footpath and carriageway)
(mainlaying completed) [100%]: all outstanding
minor works was completed in September 2013.
(8.2006)
(12.2008)
(9.2013)
(9.2013)
17
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
182WC/A Replacement and
Rehabilitation of Water
Mains Stage 2
WSD Construction works commenced in 2007. Works are
currently being carried out at :
1. Contract No. 8/WSD/06
(a) Shouson Hill Road (connection works in progress)
[98%]
[Reason: New XPs were obtained and preparation
works were in process but were affected by inclement
weather and congested underground utilities.];
(b) Deep Water Bay Road (in progress) [98%];
(c) Big Wave Bay Road (connection works completed)
[100%];
(d) Shek O North Service Reservoir (connection works
completed) [100%];
(e) Stanley Market (in progress) [99%]; and
(f) Stanley Beach Road (connection works in progress)
[95%].
(3.2007)
(11.2007)
(5.2009)
(12.2007)
(8.2007)
(6.2008)
(11.2008)
12.2013
12.2013
12.2013
(12.2012)
(8.2013)
12.2013
12.2013
18
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
2. Contract No. 28/WSD/06
(WSD and its contractor propose to extend the use of
TGLA No. GLA-THK1759 in Kai Lung Wan as work
areas. Details would be introduced at the meeting.
(Please see Appendixes 3-5.)
(a) Main Street Ap Lei Chau (in progress) [85%]
[Reason: Reason: Preparation works in process but
works programme had been delayed by interfacing
issues with MTRC];
(b) Lee Chi Road (in progress) [88%]
[Reason: Preparation works in process but works
programme had been delayed by interfacing issues with
MTRC];
(c) Tin Wan Street (completed) [100%];
(d) Tin Wan Praya Road (connection works in progress)
[98%]
[Reason: Due to congested underground utilities, works
programme was delayed. Further review of works
details for remaining connection works was in process.
Renewal of CNP and XP are required and anticipated
to be obtained in late-2013];
(e) Shek Pei Wan Road (completed) [100%];
(f) Pok Fu Lam Road (completed) [100%];
(g) Chi Fu Road and Chi Fu Close (in progress) [97%]
[Reason: Works have been commenced on 23 August
2013];
(h) Hing Wo Street (connection works in progress)
[97%] ; and
(i) Ka Wo Street (completed) [100%].
(11.2008)
(6.2008)
(11.2008)
(6.2008)
(10.2008)
(5.2008)
(10.2008)
(9.2008)
(5.2008)
(11.2007)
(3.2014)
3.2014
3.2014
(1.2013)
12.2013
(10.2012)
(8.2013)
1.2014
12.2013
(5.2013)
19
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
186WC/A Replacement and
Rehabilitation of Water
Mains Stage 3
WSD
Water mains replacement and rehabilitation works in
Southern District under Contract No. 18/WSD/08
commenced on 18 March 2009. Works currently being
carried out in Southern District include:
(a) Pok Fu Lam Road Footpath and Carriageway (in
progress) [55%];
(b) Shek Pai Wan Road and Aberdeen Praya Road
Carriageway (pending for XP issue) [3%];
(c) Aberdeen Reservoir Road Carriageway (in progress)
[80%] ;
(d) Yip Fat Street Footpath and Carriageway (in progress)
[97%];
(e) Wong Chuk Hang Road and Heung Yip Road Footpath
(pending for XP issue) [87%]
[Reason: Design review for sections of water mains is
in progress. A new XP will be applied and works
programme was revised.];
(f) Repulse Bay Road Footpath (in progress) [85%];
(g) Red Hill Service Reservoir (in progress) [70%];
(h) Area in the vicinity of Stanley Mound Service
Reservoir (in progress) [98%];
(3.2009)
(8.2010)
(8.2011)
(1.2011)
(9.2009)
(10.2009)
(7.2011)
(10.2010)
(3.2011)
11.2014
6.2014
11.2014
6.2014
3.2014
8.2014
12.2013
3.2014
12.2013
20
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
(i) Stanley Gap Road Carriageway (pending for XP issue)
[85%];
(j) Tai Tam Road Carriageway (in progress) [5%]
[Remarks: Design review for the proposed water main
is in progress. Works programme will be revised after
further investigation.];
(k) Stanley Village Road Footpath and Carriageway (in
progress) [84%] ;
(l) Area in the vicinity of Pok Fu Lam Service Reservoir
(in progress) [78%] ;
(m) Aberdeen Main Road Footpath and Carriageway
(pending for XP issue) [40%]
[Reason: XP is still awaited and works programme
was revised.] ;
(n) Repulse Bay Road Carriageway (in progress) [60%]
[Remarks: Design review for sections of water mains is
in progress. Works programme will be revised after
further investigation.];
(o) Victoria Road Footpath and Carriageway (in progress)
[12%]
[Remarks: Design review for the proposed water
mains is in progress. Works programme will be
revised after further investigation.];
(p) Pok Fu Lam Village (in progress) [80%] ; and
(q) Pok Fu Lam Reservoir Road Carriageway (in
progress) [30%].
(3.2010)
(9.2010)
(9.2010)
(11.2011)
6.2012
(2.2012)
(8.2012)
(11.2011)
(7.2012)
3.2014
12.2013
7.2014
12.2013
3.2014
12.2013
12.2013
12.2013
7.2014
21
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
013WS/A Salt Water Supply
System for Pok Fu
Lam area
WSD Contract No. 10/WSD/09 commenced in October 2009 for
the construction of:
(a) Telegraph Bay Salt Water Pumping Station and the
associated sea water intake;
(b) Wah Fu Salt Water Service Reservoir and Wah Fu Salt
Water Pumping Station; and
(c) Pok Fu Lam Road Salt Water Service Reservoir.
The contract had been substantially completed in July
2013. The civil works of road reinstatement and
landscaping works at Telegraph Bay site were completed
in September 2013. Salt water supply to Wah Fu Estate
was effected in October 2013.
(10.2009)
(10.2009)
(10.2009)
(10.2009)
(7.2013)
(7.2013)
(7.2013)
(7.2013)
22
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
191WC/A Replacement and
Rehabilitation of Water
Mains Stage 4 Phase 1
WSD Contract No.12/WSD/10, which consists of construction
works in Southern District, commenced on 18 July 2011.
Works are being carried out. Works in Southern District
are as below:
(a) Consort Rise Footpath and Carriageway (in progress)
[51%]
[Reason: alignment review was carried out due to
congested underground utilities. Temporary traffic
arrangement was revised.];
(b) Bisney Road Footpath and Carriageway (in progress)
[27%];
(c) Yue Kwong Road footpath and carriageway (in
progress) [80%]
[Reason: Due to unexpected underground condition
and congested utilities, works programme for the
remaining works was reviewed];
(d) Island Road Footpath and carriageway (in progress)
[44%];
(e) Repulse Bay Road Footpath and carriageway (in
progress) [48%];
(f) Area in the vicinity of Aberdeen Water Treatment
Works (in progress) [46%];
[Reason: Mainlaying works were in process but were
affected by inclement weather.]
(g) Area in the vicinity of Pok Fu Lam Road (in progress)
[75%];
[Reason: Mainlaying works were in process but were
affected by inclement weather.];
(h) Area in the vicinity of Mount Davis Road (in progress)
[78%];
[Reason: Mainlaying works were in process but were
affected by inclement weather.];
(7.2011)
(1.2012)
(1.2012)
(3.2012)
(2.2012)
(7.2012)
(4.2012)
(7.2012)
(7.2012)
8.2015
5.2014
5.2014
12.2013
8.2015
1.2014
7.2014
12.2013
12.2013
23
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
(i) Shum Wan Road Footpath and Carriageway (in
progress) [40%]; and
(j) Belleview Drive Footpath (in progress) [50%]
(k) Deep Water Bay Road Footpath and Carriageway (in
progress) [38%]
(l) Tai Tam Reservoir Road Footpath and Carriageway (in
progress) [35%]
(m) Sandy Bay Road Carriageway (in progress) [30%]
(10.2012)
(10.2012)
(11.2012)
(12.2012)
(12.2012)
5.2014
6.2014
4.2014
5.2014
5.2014
24
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
369DS/A Harbour Area
Treatment Scheme,
stage 2A - construction
of the sewage
conveyance system and
advance works for
upgrading of
Stonecutters Island
sewage treatment
works
Drainage
Services
Department
Contract DC/2007/24 (HATS 2A Construction of
Sewage Conveyance System from Aberdeen to Sai Ying
Pun) commenced on 31/7/2009; Contract DC/2008/09
(HATS 2A Construction of Sewage Conveyance System
from Ap Lei Chau to Aberdeen) also commenced on
17/8/2009.
Under Contract DC/2007/24, rock excavation of the
shaft at Wah Fu was complete; the tunnel between
Sandy Bay and Cyberport was broken through on 22
October 2012, permanent lining of the tunnel is
substantially complete; the excavation of tunnels from
Cyberport to Aberdeen, together with that from Sandy
Bay to Sai Ying Pun is in progress; concreting for
permanent lining of the western section of the tunnel
from Sandy Bay to Sai Ying Pun is complete and from
mid-point to Sandy Bay is in progress. About 84.0%
of works under the contract has been completed.
The Horizontal Direction Drilling of DC/2008/09
including tunnel holes enlargement is complete. Pipe
pulling for one of the twin tunnels is complete. About
92.9% of works under the contract has been completed.
(7.2009) 12.2014
25
PWP No. / Cat. Project Description Agency Progress / Remarks [Completion rate (%)) Est. (Actual)
Start Date
Est. (Actual)
Completion Date
341DS/A Harbour Area
Treatment Scheme,
stage 2A -
Upgrading of
Stonecutters Island
sewage treatment
works and
preliminary
treatment works
Drainage
Services
Department
Contract DC/2009/24 (Harbour Area Treatment Scheme
Stage 2A Upgrading of Preliminary Treatment Works
(PTWs) at Sandy Bay, Cyberport, Wah Fu, Aberdeen and
Ap Lei Chau) commenced on 31/8/2011. The works
mainly include the upgrading of the sewage treatment
and de-odourisation facilities in these PTWs.
Upgrading works at Sandy Bay, Wah Fu, Aberdeen, Ap
Lei Chau and Cyberport PTWs were in progress.
About 47% of works under the contract has been
completed.
(8.2011) 10.2015
26
Progress Report on Landslip Prevention Works
I. Works Commenced
PWP No. /
Cat.
Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual)
Start Date
Est. (Actual)
Completion
Date
Head 705
Subhead
5001BX
Landslip Prevention
and Mitigation
Programme (LPMitP)
CEDD Landslip prevention and mitigation works for 48 man-made slopes and 4
natural hillside catchments in Southern District were completed. And 18
man-made slopes and 12 natural hillside catchments in Southern District are
currently in progress.
1. Slope No. 11SW-D/CR51 at Tsung Man Street [97%]
2. Slope No. 11SW-C/CR161 at Sassoon Road [95%]
3. Slope No. 11SW-C/C169 at at Bisney Road [75%]
4. Slope No. 15NE-B/C142 at Big Wave Bay Road [100%] (Works
Completed)
5. Slope No. 15NW-B/C86 at Ap Lei Chau Service Reservoir [90%]
6. Slope No. 15NE-A/C316 at Stanley Gap Road [85%]
7. Slope No. 11SW-C/C502 at Victoria Road [80%]
8. Slope No. 15NE-A/C23 at Repulse Bay Road [85%]
9. Slope No. 11SW-C/CR803 at Pok Fu Lam Reservoir Road [100%]
(Works Completed)
10. Slope No. 11SW-C/C110 at Pok Fu Lam Reservoir Road [50%]
11. Slope No. 11SW-D/C644 Aberdeen Old Main Street [75%]
12. Slope No. 15NE-B/C59 at Shek O Road [30%]
13. Slope No. 15NW-B/C345 at Shum Wan Road [20%]
(7.2012)
(8.2012)
(11.2012)
(1.2013)
(2.2013)
(3.2013)
(5.2013)
(5.2013)
(6.2013)
(7.2013)
(7.2013)
(8.2013)
(8.2013)
12.2013*
11.2013*
6.2014@
(9.2013)
11.2013*
2.2014*
11.2013+
3.2014
(8.2013)
12.2013*
1.2014
3.2014
5.2014*
27
PWP No. /
Cat.
Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual)
Start Date
Est. (Actual)
Completion
Date
14. Slope No. 11SW-D/F360 at Deep Water Bay Road [7%]
15. Slope No. 15NE-B/FR31 at Shek O Road [35%]
16. Slope No. 15NE-B/C237 at Shek O Road [25%]
17. Slope No. 15NE-A/CR399 at Tai Tam Road [10%]
18. Slope No. 15NE-B/C212 at Pak Pat Shan Road [5%]
19. Slope No. 11SW-D/F444 at Peel Rise [55%]
20. Slope No. 11SW-D/F445 at Peel Rise [55%]
21. 9 Natural hillside catchments behind Queen Mary Hospital [55%]
22. 3 Natural hillside catchments above Singapore International School,
Nam Long Shan Road, Wong Chuk Hang [70%]
(8.2013)
(6.2013)
(8.2013)
(8.2013)
(9.2013)
(6.2013)
(6.2013)
(1.2012)
(7.2012)
8.2014*
5.2014
6.2014
1.2014
9.2014
11.2013
11.2013
12.2014
2.2014+
* Anticipated completion date is revised as the works have been affected by inclement weather
@
Anticipated completion date is revised as application for Restricted Zone Permit along Bisney Road still
in progress
+ Anticipated completion date is revised as the design was revised to suit the actual site condition.
28
PWP No. /
Cat.
Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual)
Start Date
Est. (Actual)
Completion
Date
Head 705
Subhead
5001BX
Landslip Prevention
and Mitigation
Programme (LPMitP)
CEDD In the coming year, CEDD plan to progressively commence the landslip
prevention and mitigation works for another 36 man-made slopes and 3
natural hillside catchments.
1. Slope No. 15NE-A/C135 at Stanley Gap Road
2. Slope No. 15NE-B/C160 at Shek O Road
3. Slope No. 11SE-D/C147 at Tai Tam Road
4. Slope No. 15NE-B/C60 at Shek O Road
5. Slope No. 15NE-A/C402 at Tai Tam Road
6. Slope No. 11SW-D/CR81 at Aberdeen Main Road
7. Slope No. 11SW-C/CR46 at Wah Fu Estate
8. Slope No. 15NW-B/C114 at Island Road
9. Slope No. 11SE-D/FR37 at Tai Tam Road
10. Slope No. 11SE-C/C534 at Tai Tam Road
11. Slope No. 11SW-D/C165 at Shouson Hill Road
12. Slope No. 15NE-A/C13 at Repulse Bay Road
13. Slope No. 15NE-A/C90 at South Bay Road
14. Slope No. 15NE-A/C176 at Tai Tam Road
15. Slope No. 15NE-A/C608 at Tai Tam Road
16. Slope No. 15NE-B/FR34 at Shek O Road
17. Slope No. 15NE-A/CR603 at Tai Tam Reservoir Road
18. Slope No. 15NE-A/C70 at Repulse Bay Road
19. Slope No. 11SE-D/C149 at Tai Tam Road
20. Slope No. 11SE-C/FR197 at Repulse Bay Road
21. Slope No. 15NE-A/C193 at Tai Tam Road
11.2013
11.2013#
7.2014
11.2013#
12.2013#
11.2013#
6.2014
11.2013#
4.2014
2.2014#
11.2013#
2.2014#
11.2013
2.2014#
12.2013#
11.2013#
6.2014
1.2014#
11.2013
11.2013
11.2013
7.2014
5.2014#
2.2015
9.2014
5.2014#
11.2014#
3.2015
8.2014
11.2014
1.2015#
6.2014
11.2014#
7.2014#
8.2015#
8.2014
5.2014
12.2014
11.2015#
5.2014
12.2014
5.2014
29
PWP No. /
Cat.
Project Description Agency Progress / Remarks [Completion rate (%)] Est. (Actual)
Start Date
Est. (Actual)
Completion
Date
22. Slope No. 15NE-A/C611 near Tai Tam Road
23. Slope No. 15NE-A/FR111 near Tai Tam Road
24. Slope No. 15NE-A/FR115 near Tai Tam Road
25. Slope No. 15NW-B/FR16 at Island Road
26. Slope No. 15NE-A/CR40 at Repulse Bay Road
27. Slope No. 11SE-C/C13 at Repulse Bay Road
28. Slope No. 15NE-A/C197 at Tai Tam Road
29. Slope No. 15NW-B/C54 at Island Road
30. Slope No. 15NE-A/CR45 at Repulse Bay Road
31. Slope No. 15NE-A/C192 at Tai Tam Road
32. Slope No. 11SE-D/C406 near junction between Shek O Road & Cap
Collinson Road
33. Slope No. 15NE-B/C7 at Shek O Road
34. Slope No. 15NE-B/C72 at Big Wave Bay Road
35. Slope No. 11SW-C/CR981 at Pok Fu Lam Village
36. Slope No. 15NW-B/C117 at Island Road
37. 3 Natural hillside catchments above Ap Lei Chau Bridge Road
# Anticipated start date is revised due to reschedule of works programme.
11.2013
11.2013
11.2013
12.2013
4.2014
9.2014
9.2014
9.2014
9.2014
9.2014
9.2014
9.2014
9.2014
10.2014
10.2014
11.2013
11.2014
9.2014
9.2014
9.2014
2.2015
3.2015
10.2015
6.2015
4.2015
5.2015
5.2015
5.2015
5.2015
4.2015
6.2015
1.2015
30
Annex 5
District Development and Environment Committee, Southern District Council
Progress Report on Public Housing Works in Southern District
(As at 31.10.2013)
I. Works Commenced (up to the end of two financial years later)
Project Description
PWP / Estate No. Est. (Actual) Start Date Est. (Actual)
Completion Date Remarks
Lift Modernisation
for Ap Lei Chau
Estate
BSE/CM2 May 2014 March 2017 The lift modernisation work for Ap Lei Chau
Estate involves four sections of work. The
work for five lifts in Section I (Lei Yee
House L2, Lei Ning House L5, Lei Chak
House L8, L11 and L14) is anticipated to
commence in the second quarter of 2014 and
to be completed in the first quarter of 2015.
II. Works with Tender Value above $1Million in 2009-2010
Project Description
PWP / Estate No. Est. (Actual) Start Date
Est. (Actual)
Completion Date
Remarks
31
Project Description
PWP / Estate No. Est. (Actual) Start Date
Est. (Actual)
Completion Date
Remarks
Lift Modernisation
for Wah Fu (I) &
(II) Estates
BSE/HW (June 2011) February 2016 The lift modernisation work for Wah Fu (I)
and (II) Estates involves five sections of
work. Five lifts involved in Section I had
been completed in 2012. Another Five lifts
involved in Section II were completed and
put into operation in October 2013.
The work for four lifts in Section III and IV
(Wah Chui House L2, Wah King House L6,
Wah Cheong House L12 and Wah Chun
House L8) had been commenced and
anticipated to be completed by early 2015.
32
Annex 6
District Development and Environment Committee, Southern District Council
Progress Report on FEHD District Minor Works in Southern District
(As at 31.10.2013)
Item
No.
Proposed
Minor Works Location
Estimated
Start Date
[Actual
Start Date]
Estimated
Completion
Date
[Actual
Completion
Date]
Remarks FEHD Contact
Person
ASD
Contact
Person
1
Pokfulam
Village
Public Toilet
Block C
Pokfulam
Village To be confirmed
To be
confirmed There is no update at the moment.
Chief Health
Inspector,
Mr. WONG Hung
Yuen
【2903 0401】
To be
confirmed
2
Wu Nam
Street Public
Toilet
Wu Nam
Street
near
Aberdeen
Bus
Terminus
【2.9.2013】 June 2014 Works commenced on 2.9.2013 and the estimated
completion date is in June 2014.
Chief Health
Inspector,
Mr. WONG Hung
Yuen
【2903 0401】
Property
Services
Mgr/PM12,
Mr. MOK
Kwok-kit
【2773
2474】
33
Annex 7
District Development and Environment Committee, Southern District Council
Progress Report on Lands Department Temporary Government Lands Allocation in Southern District
(As at 31.10.2013)
Item
No.
TGLA No./
File Ref.
Type of
TGLA
(New/
Renewal)
Location
Proposed
Area (m2)
Proposed
User
Proposed
Term
User Dept.
(Allocatee)
Date of
Allocation
Date of
Withdrawn
Remarks
(Current
Situation)
1 GLA-THK
1538
[L/M7/SHGS/8
2(68)]
Renewal Pak Sha Wan near
Ap Lei Chau Praya
Road
799 Works Area Extend up
to 30.6.2015
LCSD 7.11.2013 - Approved on
7.11.2013.
2 GLA-THK
1962
601/SHGS/82
New Wong Chuk Hang
Road
225 Works Area From the
date of
approval to
31.7.2017
HyD - - Departmental
consultation
completed.
Objections
received have
been conveyed to
HyD for their
follow up action.
The response
from HyD is still
being awaited.
34
Item
No.
TGLA No./
File Ref.
Type of
TGLA
(New/
Renewal)
Location
Proposed
Area (m2)
Proposed
User
Proposed
Term
User Dept.
(Allocatee)
Date of
Allocation
Date of
Withdrawn
Remarks
(Current
Situation)
3 GLA-THK
1823
525/HGS/82
Renewal Cyberport Road 1,550 Works Area Extend up
to 31.3.2014
WSD - 31.10.2013 WSD withdrew
the renewal
application on
31.10.2013 .
4 GLA-THK
1842
481/SHGS/82
Extension
area of the
existing
TGLA
Government land at
Cyberport
Not
available
For Vehicular
access
Up to
30.7.2014
DSD - - Under
departmental
circulation.
5 612/SHGS/82 New Government land
opposite to 18-21
Bisney Road
52 RCP From the
date of
approval for
5 years
FEHD - - Under
departmental
circulation.