Information Pack for: New Data Centre Development
Located at Western International Park ,Hayes Road, Southall, UB2 5XU
Private & Confidential
Mark Underwood – Senior Business Development DirectorT: 0207 499 1300 M: 07887 641 310 E: [email protected]
April 2012
![Page 2: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/2.jpg)
Western International Park (WIP)
Ownership
• Virtus has entered into a conditional purchase agreement with Kier Property Developments for a 2 acre
brownfield site at Trade City, Western International Park (WIP)
• All conditions for the sale have been met and final legalities are being concluded.(See confirmation letter from
Wragge Solicitors)
• Virtus are in advanced discussions with Kier to acquire a further circa 2.2 acres above the current 2 acre site
taking total capacity to circa 4.2 acres
Planning
• Full planning consent granted from the London Borough of Hounslow for Data Centre use for a scheme
designed by Norman Disney & Young (NDY) delivering 64,000 sqft of net technical space using Direct Fresh Air
technology. (Planning reference number: 01032/E/P35)
• Virtus is currently in the normal 3 month judicial review period
Power delivery
• Virtus has secured 20MW of power via SSE
• Power delivered from the North Hyde sub-station and will be constructed in 3 separate trenches of 10MW per
trench (N+1)
• North Hyde sub-station is circa 800m from WIP
• Virtus SSE Customer Reference number: DRQ 432
Carriers
• Virtus has entered into a formal agreement with GEO Networks for the delivery of diverse fibre routes to WIP
• Virgin Media have a major POP and committed to delivering diverse connectivity to site
• Other major carriers within very close proximity include:- Level 3, Abovenet, SSE,
Verizon and Cable &Wireless Worldwide
![Page 3: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/3.jpg)
Flexible site options
Powered shell
• Construction and leasing of an industrial shed to accommodate preferred and customised M&E design on
commercial terms to be agreed
Fully fitted space
Option of either:-
• Design, construction and operation of fully fitted whitespace to include specific technology, resilience and
redundancy compliance with customer criteria
OR
• Virtus in conjunction with NDY have designed a modular scheme that delivers 64,000sqft / 5,946m² of net
technical space at a density of 1.5kW/m²
• 2N resilience on UPS.
• Scheme utilises direct fresh air technology and delivers a “design PUE” of circa 1.25.
• Scheme can be altered (if needed) to accommodate customer specific criteria (High level CGI’s and floor
designs included in presentation)
![Page 4: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/4.jpg)
Western International Park (WIP) Site
Location
Approx. distances by road
• Heathrow Airport – 5 miles
• City of London – 15 miles
• East Grinstead – 47 miles
Site Location
Former Western International
Market, Hayes Road, Southall,
UB2 5XU.
Co-ordinates
51°29'46.49"N, 0°24'16.35"W
Major motorway
J3 off the M4
![Page 5: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/5.jpg)
Western International Park (WIP)
![Page 6: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/6.jpg)
Appendices
Appendix 1 – Wragge & Co Solicitors site ownership confirmation
Appendix 2 – Formal planning consent for site (Hounslow Council)
Appendix 3 – Signed SSE acceptance form for 20MVA supply & cable route
Appendix 4 - Current design CGI WIP
Appendix 5 – WIP Key Facts
Appendix 6 – Current scheme design of ground floor
Appendix 7 - Current scheme design of first floors
Appendix 8 - Current scheme design of second floor
![Page 7: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/7.jpg)
Appendix 1 – Wragge & Co Solicitors
site ownership
![Page 8: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/8.jpg)
Appendix 2 – Planning consent
![Page 9: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/9.jpg)
Appendix 3 – SSE route map and
power quotation acceptance
![Page 10: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/10.jpg)
Appendix 4 - Current design CGI WIP
![Page 11: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/11.jpg)
Data Centre – Key Facts
• 64,000 sqft technical space arranged over three floors
• Self contained site with full perimeter security and controlled access
• 20MW power secured from local power network (SSE North Hyde Substation – approx. 800m) delivered with
cables configured to N+1. Each cable laid in diverse trench
• Numerous fibre providers located in area with dark fibre connection planned for installation during
construction
• Design PUE of <1.3 by utilising latest direct fresh air cooling technology
• Uptime Institute certification to Tier III standards to be sought
• Concurrently maintainable systems throughout
• Dedicated plant to each floor
• Modular design to allow phased build out
Appendix 5 – WIP Key Facts
![Page 12: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/12.jpg)
Ground Floor – Key Facts
• 2 x 5,600sqft data halls
• 648 kW of IT power per hall
• Standby generators (N+1)
• Electrical transformers for all data halls
• Fibre and HV power intake rooms
• De-box/build room
• Security office and loading bay
Appendix 6 – Current scheme design
of ground floor
![Page 13: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/13.jpg)
First Floor – Key Facts
• 4 x 6,600sqft data halls
• 1944 kW IT load per “pair” of halls
• Dedicated UPS per “pair” of halls – 2N
configuration
• Fresh air cooling galleries
• Office accommodation
Appendix 7 - Current scheme design
of first floor
![Page 14: New data centre Info Pack Version 1](https://reader033.fdocuments.in/reader033/viewer/2022051818/549766f6b47959744d8b526c/html5/thumbnails/14.jpg)
Second Floor – Key Facts
• 4 x 6,600sqft data halls
• 1944 kW IT load per “pair” of halls
• Dedicated UPS per “pair” of halls – 2N
configuration
• Fresh air cooling galleries
• Office accommodation
Appendix 8 - Current scheme design
of second floor