    Difference between PERT and CPM and theirapplication in house construction

  • 7/31/2019 Network Analysis OR MBA PPT

    2/14

    Agenda

    Introduction

    Techniques PERT & CPM

    Applications Differences

    Benefits

    Conclusion

  • 7/31/2019 Network Analysis OR MBA PPT

    3/14

    Introduction

    Network Analysis

    Technique of operations research

    Planning, scheduling and controllingLarge and complex projects.

    Objective

    Schedule required activities efficientlyComplete it on or before specific time limit

    Minimum cost.

  • 7/31/2019 Network Analysis OR MBA PPT

    4/14

    Network Analysis - Techniques PERT Program Evaluation and review Technique

    CPM Critical Path Method

  • 7/31/2019 Network Analysis OR MBA PPT

    5/14

  • 7/31/2019 Network Analysis OR MBA PPT

    6/14

    CPMCPM Critical Path Method

    Developed by EI DuPont company along with

    Remington Rand corporation.Aim was to provide a technique for control of the

    maintenance of the cos plants.

    Use extended to cost & resource allocation.

  • 7/31/2019 Network Analysis OR MBA PPT

    7/14

    Applications of network analysis Construction

    Software development

    Research projects Product development

    Engineering

  • 7/31/2019 Network Analysis OR MBA PPT

    8/14

    Application in house constructionActivity Description Duration

    A Acquiring land 4

    B Foundation 6

    C Construction of basic

    structure

    2

    D Wood works 5

    E Concrete 2

    F Plumbing & Electrical

    work

    7

    G Flooring & designing 4

    H Finishing interior &

    exterior

    1

    Construction

    Project

    E.g. 1

  • 7/31/2019 Network Analysis OR MBA PPT

    9/14

    1 2 3 4

    5

    6

    7 8

    Solution

    A B C

    D

    E

    F

    G

    H

    E= 0

    L= 0E= 4

    L= 4

    E= 10

    L= 10

    E= 12

    L= 12

    E= 17

    L= 17

    E= 14

    L= 14

    E= 24

    L= 24

    E= 25

    L= 25

    Critical Path :1- 2- 3- 4- 5- 7- 8 25 weeks

    Non critical path : 1- 2- 3- 4- 6- 7- 8 19 weeks

    Float 6 weeks

  • 7/31/2019 Network Analysis OR MBA PPT

    10/14

    Difference b/w PERT & CPMPERT

    Uses 3 estimates to form

    weighted avg of expectedcompletion time.

    Tool for planning &control of time.

    CPM

    Uses 1 estimate to form

    weighted avg of expectedcompletion time.

    Tool for planning &control of time & cost.

  • 7/31/2019 Network Analysis OR MBA PPT

    11/14

    ContdUsed for projects

    involving activities ofnon-repetitive nature.

    Used for projectsinvolving activities ofrepetitive nature.

  • 7/31/2019 Network Analysis OR MBA PPT

    12/14

  • 7/31/2019 Network Analysis OR MBA PPT

    13/14

    ConclusionThus these techniques help in completion of projects

    with no over-runs of time and cost.