NEC NEO Commissioning
description
Transcript of NEC NEO Commissioning
-
Firstly we login desktop PNMT Icon then OK
-
User name: admin then PNMT(USB) then login
-
When connect IDU then we go to configuration then equipment setup
-
At first maintenance on
-
From equipment setup we go to setup then configure
-
TX-Power setup here
-
Put Frequency here
-
Capacity ,modulation, frame id setup here
-
Receive level show process-1
-
Tx-power and receive level show-2
-
Port check-1
-
Port check-2(enable and disable)
-
IP-File configure
-
User Interface
-
NTFS setup
-
LAN Port Usage
-
At last antenna alignment Mode On before start alignment
-
INSTRUCTION SHOULD FOLLOW BEFORE & AFTER ALIGNMENTAfter complete commissioning must antenna alignment mode ONDuring alignment IDU should not switched Off.After complete alignment then must be Alignment mode OFF
-
THANK YOU
MD AZIZUL HOQUEFUTURE RF TECHNOLOGY LTD.For any query Please contact 01713130316
Firstly we login desktop Pnmt login then OK