NEC, EV and the Olympic Programme - GMH Planning · NEC, EV and the Olympic Programme: How the NEC...
Transcript of NEC, EV and the Olympic Programme - GMH Planning · NEC, EV and the Olympic Programme: How the NEC...
NEC, EV and the Olympic Programme:How the NEC and EV were used to deliver the
London 2012 Olympic Park
Lee McDonaghPlanning Manager, MaceRepresenting CLM Delivery Partner
Introduction
The NEC has become not just a Contract, but a framework and a way of working; along with Project Controls it has jointlydriven performance, secure delivery and reduced risk.
NEC and EV, mutually exclusive?
Three Discussion Themes:
Olympic Programme Overview
NEC 3: Different Perspectives
The Earned Value Perspective
4
Timeline of the Olympic Park
Site preparation
Build infrastructure
Build venues
Test events
Olympic/Paralympic Games
Deconstruction / Transformation
2007
2008/11
2012
2008/11
2011/12
2012/13
Legacy2013 -2025
The Challenge – Complexity1
19120
96
869
4,40027,000
1,520
10,490
529
27,300(£m)
1
Programme
Major ProjectsNEC3 Contracts (+ 1 Development Agreement,
184 JCT and 3 concessions)Tier 1 suppliers
Critical Tier 2 & 3 suppliers (Insolvency Risk)
Unique Design Interfaces
Integrated Plan Activities
Linked ActivitiesSite Workers (Daily Average)
Daily vehicle movements (materials)
Site entry points (plus rail head)
Budget (average burn rate of £150m/month, peak £190m)Key date - 27 July 2011
Tie
r 1
Pro
ject
Lea
d D
esi
gn
Lead
Des
ign
Pro
ject
Tie
r 1P
ark
Op
era
tions
(F
orm
erly
Log
istic
s)T
ier 1
London 2012 Tier 1 Supply Chain Map
7
Delivery & Political Environment
Complexity of contractual footprint (and intensity of spend)
Target cost contracts (NEC 3 Option C)
Levels of design maturity at contract award
Change management
Budget constraints – affordability
Time constraints – fixed end date
Public scrutiny (NAO - FOI)
Logistically constrained site
Complex supply chain
Current market conditions
8
The Challenge – Completed
8 Olympic Park Sporting Venues
Stadium and Warm up Track
Aquatics, Waterpolo
Handball, Basketball
Velodrome and Velopark
Hockey
1 Broadcast / Media Centre (1 million square feet) & Multi Storey Car Park
The Challenge
Delivery Constraints
Complexity & Risk
NEC 3 has become a key enabler supporting the London 2012 Olympic Big Build Programme
10
The Contract Structure – The Operational View
The Employer ODA~
The Project Sponsor
The Contractor
The Project Manager – CLM
Manages the contract for the employer:
• Programme• Cost• Deliverables
The Supervisor
‘Check the works ’Quality and Defects
The NEC 3 Contract –The Practitioner's View
An Output focused contract (with the Programme as a central theme)
Requires behaviour change to be successful
- Collaborative not Transactional contract- Joint approach to managing problems, risk and
issues- Align all parties’ commercial interest
11
Olympic Park Delivery Strategy
NEC3 Contract Management: Real Time
Supplier Management
Integration management
Contingency and risk management
Performance and control (cost, time)
- Earned Value- Baselines and Change Control- Trends and Forecasts
ContractManagementFramework
DeliveryManagementFrameworkO
lym
pic
Inte
grat
ed V
iew
TraditionalView
RiskManagementFramework
PerformanceManagementFramework
(Project Controls)
Accepted ProgramContractor Deliverables
(PM Approval)Early Warnings Compensation
Events Payments TargetAchievement
SBH example
70 contract deliverables (one off and recurrent)
• Budget (4)• Schedule (10)• Fatality (12)• Prosecution (9)• Security (2)
Risk ReductionMeeting
CLM/Supplier
Revised Quote
CLM Response
CLM Response
CLM Response
No Response by CLM = Acceptance by Default
Supplier CE
Supplier Quote
2wks
2wks2wks 2wks
2wks
• Incentivisation
• Tier 2 VfM
• Cost Verification
• Prelim Optimisation
• Risk Mitigation
• Final Account Strategy
Contractual Obligations Business Obligation
NEC ‘Real Time’ Contract: Key Aspects
NEC 3Works Contract
Strong GovernanceRigorous change control between client and DP
- Monthly approval of individual ‘business cases’- >5,000 changes processed- Strict levels of delegated authority- Three lines of defence for contingency management
Monthly Trend Reviews
- Assess maturing risks / contingency burn - AFC glide path to achieve affordability targets
Monthly Performance Reviews
- Status and progress (time, cost, quality, priority themes, risks and issues)
- Independent assurance using robust, consistent performance information – focus on the issues, NOT data integrity
- Underpinned by back-to-back contractor reviews
Strong Governance – Strong Controls
Programme Controls - FrameworkStable but flexible delivery-driven WBS created
Original Baseline Budget (OBB) or ‘Yellow Book’published (November 2007)
Baseline modelled in systems & reconciled to OBB
Management subsystem links established via the WBS and procurement codes
Robust change control process implemented
A ‘control culture’ and trust in reporting accuracy built up
Forecast dataset created in P6
All contracts included Project Controls requirements
Earned Value – Programme Strategy
A Single data collection structure implemented through project teams and into Tier 1 contractors
Fully integrated budget-loaded programme
Earned Value (£) as the common means of reporting progress over a diverse programme of projects
Various funding sources and strict budgetary and change governance
17
18
Delivery Platform - Performance Measurement & Commercial Management
CLM Level 1 Schedule
CLM Level 2 Cost Loaded Schedule
P6ProductionDatabase
Tier 1 Contractor Cost Loaded Schedules
Labour (hours and cost)EquipmentMaterialsSuppliesContracted ServicesTransport and TravelOther
P6External
DatabaseN o. A ct i vi t y Jan Feb M arch A pr i l M ay T arge t Ac t ual Ch ang es
10 1 Pr oj ect M an £10 £10 £ 10 £10 £10
10 2 Desi gn £12 £40
10 3 Tender s £30
10 4 Subst r uctur e £ 15 £20 £ 40
10 5 Super st rucut r e £ 50 £70 £ 80
10 6 Snaggi ng £10
CLM Commercia l M anagementTier 1 Contractors Submission Under NEC Contract
Resources & NEC Activity List
Schedule Performance & Cost Performance
Reports etc.
Detailed EVand %
Complete
Reviewed by CLM - Summary
Submitted
Actual Cost(via CLM
Cert)
COBRA
Earned Value
Actual Cost
ODA Finance (Oracle)
Reporting
One week to turn around month-end results
Flash reports to remove data anomalies
Project Cost Performance Reports
Programme Cost Performance Report
Project Status Report
Monthly Programme status report -Dashboards used for communicating key performance trends to senior management
Monthly/Quarterly Project Reviews
Quarterly Funders Report
Governance Framework
Mature Programme Controls Schematic
Tailored reports to support
Governance decision points
Key Meeting
Key Meeting
Functions (Design, Town Planning, SHQE, etc) and Stakeholder
defined priority themes
Contract Admin (inc Procurement)
Change Control
Risks, Issues and Trends
Schedule &Integration
Cost Engineering
Enterprise Accounting C
ontro
lled
Perfo
rman
ce
Man
agem
ent B
asel
ine
WBS
WBS
Approved Changes
Contractor Project Team
Contractor Project Team
Contractor Project Team
Com
mon
pro
cess
es &
tool
s de
fined
in
Con
tract
Wor
ks In
form
atio
n
Perfo
rman
ce
Dat
a
Contractor Project Team
Performance
Data
Reporting hub for analysis
Data with
Narrative
Dat
a wi
th
Narr
ativ
e
Benefits
EV was pivotal in the successful programme controls used for London 2012.
All 32 criteria specified in ANSI / EIA 748 and APM were applied, the most influential being:
1. Define authorised work and resources via WBS
3. Ensure management subsystems support each other, the WBS and the OBS
8. Maintain Performance Measurement Baseline at Control Account (C/A) level
15. CBB = approved project budgets + contingencies
17. Prohibit multiple accounting as direct costs are summarised through the WBS
22. Produce monthly performance measurement data at C/A level
27. Develop monthly AFC’s and compare to CBB
28. Incorporate all authorised changes in a timely manner
21
London 2012 EV System v ANSI and APM
1. Implemented and used in checks and balances
2. Implemented and influential when required
3. Implemented, enforced and very influential over the programme
Criteria Ranking Criteria Ranking Criteria Ranking1 3 12 2 23 32 2 13 1 24 13 3 14 1 25 24 1 15 3 26 25 1 16 2 27 36 2 17 3 28 37 2 18 1 29 28 3 19 1 30 29 2 20 2 31 310 2 21 2 32 311 2 22 3
Key Learning: Generic Lessons
Accepted Programme – regular updates, quality of information and staff capability
Defined Cost – clear definitions, recognise importance of Cost Verification
EWNs – two-way process PM/Client and Contractor
Close Out – Start mid-contract
Supply Chain – back-to-back Tiers 1 and 2
Resources – intensive to administer (all aware, but often ignored)
Key Learning: Client / Employer
Procurement, creates the start point only
- does not guarantee the required results- too much one-dimensional thinking
Administrative Burden (resource intensive but worth it)
Lock down AFC after completion / takeover quickly and collaboratively
Need a holistic approach to Commercial Management -Contract, Programme Controls, Delivery and Risk
Right Governance and Assurance structure is vital
Create common employer / supplier understanding (training & more)
Large quantities of change can be handled
Works Information is key (build in flexibility)
Key Learning: Suppliers
Disconnect between corporate and operational understanding of NEC3
Need to improve quality of Quotations!
- “Price of Everything”, “Cost of nothing”- ability to truly understand cost / quote build-up- Lack of programme impact in Quotations
Greater recognition of ‘Public Sector’ demands
- traceability of costs- visibility of decisions (particularly Tier 2 awards)- the role of Project Manager v Employer
Pre-completion takeover / handover management
Spend the time and resources to get your Baseline right (and minimise heartache down the road)
Keep Baseline high level and ensure Forecast is dynamic
Everyone must work within the WBS structure
Cost collection system fully keyed-in by coding
Contractors keyed in at lower levels
Provide right level of alignment, training and assurance to include:
- Customer’s and stakeholder’s organisations- Early engagement with Contractors teams
Run Services and Operations on Level of Effort (with performance measured against milestones and KPI metrics)
Keep checking fitness-for-purpose
Key Learning: Project Controls
Be FlexibleAdjust the systems deployed to suit the phase and nature of construction
Keep it SimpleSimplified terms Clear, concise and graphic reportingData analytics but report on the issues
Aim for ‘No Surprises’Comprehensive BaselineSpotting risks and issues early enables early mitigationLeads to effective management of scope, cost & schedule
Key Learning: Final Thoughts
ODA Learning Legacy
Set challenging targets, well above industry norms – these have largely been achieved
Learning Legacy project to capture lessons learnt, innovations and best practice as a showcase for UK plc
Comprises academic research papers, peer review studies, case studies, micro-reports and template ‘champion products’
Outputs disseminated via:
- Learning Legacy website www.london2012.com/learninglegacy
- Events in conjunction with ICE, CIOB, HSE and the UK Green Building Council
Summary
Over the last five years, over £7bn has been spent delivering the platform to host the London 2012 Olympic Games
120 NEC3 Contracts have been managed in the spirit of mutual trust and cooperation, handling over 40,000 formal contract communications to date
Construction was on time and under budget and we had the facts to prove it
NEC3 has been a facilitator of performance
Project Controls have demonstrated performance
The construction of the venues and infrastructure for the London 2012 Games is funded by the National Lottery through the Olympic Lottery Distributor, the Department for Culture, Media and Sport, Greater London Authority and the London Development Agency.