ND Oil & Gas Research Program North Dakota Pipeline Authority
Justin J. Kringstad January 23, 2014 - Bismarck, ND
ND Drilling Stats
2 JJ Kringstad - North Dakota Pipeline Authority
US Williston Basin Oil Production - 2013
3
3 JJ Kringstad - North Dakota Pipeline Authority 3
November 2013
Estimated Williston Basin Oil Transportation
4
4 JJ Kringstad - North Dakota Pipeline Authority 4
Cushing $96.74
Brent $108.18 WTI + $11.44
Crude Oil Prices – Jan. 22, 2014
5 JJ Kringstad - North Dakota Pipeline Authority
Estimated Williston Basin Oil Transportation
6
6 JJ Kringstad - North Dakota Pipeline Authority 6
Estimated ND Rail Export Volumes
7 JJ Kringstad - North Dakota Pipeline Authority 7
Williston Basin Oil Production & Export Capacity, BOPD
Production forecast is for visual demonstration purposes only and should not be considered accurate for any near or long term planning.
8 8 JJ Kringstad - North Dakota Pipeline Authority
Sandpiper Pipeline Open Season
9
9 JJ Kringstad - North Dakota Pipeline Authority 9
North Dakota Pipeline Company LLC - formerly known as Enbridge Pipelines (North Dakota) LLC • Open Season Dates: November 26, 2013 – January 24, 2014 • 225,000 BOPD ND Capacity to Clearbrook, MN (24”) • 375,000 BOPD Clearbrook, MN to Superior, WI (30”) • In-service Date: Q1 2016 • Project cost: $2.6 Billion
Map: Enbridge
Simple Terms Orange – Challenges on existing infrastructure Blue – Lack of pipelines
GREEN – % of gas captured and sold Orange – % flared from wells with at least one mcf sold. Blue – % flared from zero sales wells
November 2013 Data – Non-Confidential Wells Statewide
Solving the Flaring Challenge
10 JJ Kringstad - North Dakota Pipeline Authority
*
*Hess Tioga Gas Plant shut-in for 140 MMCFD expansion starting in November
Capturing the 11% Faster Well Connections
11 11 JJ Kringstad - North Dakota Pipeline Authority
12
ND Gas Gathering Statistics
12 JJ Kringstad - North Dakota Pipeline Authority
13
ND Gas Plant Capacity
13 JJ Kringstad - North Dakota Pipeline Authority
New NDPA Natural Gas Report
14 JJ Kringstad - North Dakota Pipeline Authority
Faster Connections
Target New Wells
High Volume Areas
Conclusion 1: Getting the right wells connected quickly is moving in the right direction
15 JJ Kringstad - North Dakota Pipeline Authority
Understanding Which Wells Are Flaring
16 JJ Kringstad - North Dakota Pipeline Authority
Capturing the 11% Catching Early Production
17 17 JJ Kringstad - North Dakota Pipeline Authority
Gas Plant Capacity
Looping & Compression
Maintenance & Pigging
Conclusion 2: Finding a way to quantify system enhancements would greatly assist in
understanding the timeline
18 JJ Kringstad - North Dakota Pipeline Authority
Justin J. Kringstad, Director North Dakota Pipeline Authority
600 E. Boulevard Ave. Dept. 405 Bismarck, ND 58505-0840
Phone: (701)220-6227
Fax: (701)328-2820 E-mail: [email protected]
Websites:
www.pipeline.nd.gov www.northdakotapipelines.com