NCDOT Division 10 Update

ASHE- September 20th, 2018

Brett D. Canipe, PE Deputy Division Engineer

Page 2: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Today’s Roadmap 1. Direction of the Department

2. Division Stats

3. Division Organizational Structure

4. State Transportation Improvement Program (STIP)

5. Major Active Construction Projects. I-85 Widening, Monroe

Expressway, I-77 Managed lanes

6. Future Projects

7. Hurricane Florence

2

Division 10 Update 9/19/18

Page 3: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

NCDOT’s Paradigm Shift • BUISNESS MODEL

– Organizational Restructure; Central Units and Divisions – Responsive Customer Service – Accelerated Project Delivery !! – Alternate Funding; Build NC Bond Act of 2018, a new financing tool to help

expedite critical highway projects. Signed into law June 20, 2018. $300 mil/year for 10 years.

“Transportation is the backbone of our state’s economic competitiveness and our quality of life. Build NC is a tool that will allow us to continue strong project delivery.” –Transportation Secretary MG (Ret) Jim Trogdon, PE.

3

Division 10 Update 9/19/18

Page 4: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

NC Department of Transportation

Mecklenburg

Cabarrus

Stanly

Union

Anson

11085 Lane Miles / 2728 Bridges and Culverts

446 Employees

Division 10 Update 9/19/18

Page 5: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

Division 10 Org Structure

5

Division 10 Update 9/19/18

Page 6: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

Current Workload

• Maintenance-Operations: 11 independent work units, manages a $30 -$40 mil annual operating budget, $38 mil resurfacing budget, and a $7-$8 mil bridge replacement program. $90 mil STIP funding Interstate Maintenance

• Construction Program: 4 Resident Engineer Offices. 83 projects under construction with 10 active local projects. 3 High Profile projects: I-77 Managed Lanes, Interstate 85, and the Monroe Expressway. Upcoming I-485 Design Build-Managed Lanes (I-5507) lets Sept 19 2018 with construction anticipated to start summer 2019.

• Project Development Team: 70% of STI projects, 40% of the budget. Currently managing planning and design for 63 STI projects, 57 DDC projects, 46 bridge replacements, and providing oversight for 62 local projects. 6

Division 10 Update 9/19/18

Page 7: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

State Transportation Improvement Program (STIP)

7

STIP identifies funding and scheduling of projects in NCDOT’s capital program (55% of DOT Budget) 10 Year Program (currently 2018-2027)

• 1st Five Years is “Delivery STIP” – committed projects • 2nd Five Years is “Developmental STIP” – projects in early scoping

and environmental development stage

Updated every 2 years Current STIP contains over $25 Billion of projects

• Highway, non-highway, bridges, safety, Interstate Maintenance, CMAQ

Division 10 Update 9/19/18

Presenter
Presentation Notes
Strategic Transportation Investments (STI) is the process to develop the : State Transportation Improvement Program (STIP) Total DOT Budget is around $4.5B We are currently programming P 5.0 will create the 2020-2029 STIP
Page 8: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

8

40% of Funds 30% of Funds 30% of Funds

Statewide Mobility

Regional Impact

Division Needs

Focus Address Local Needs • Selection based on 50% Data & 50% Local Input

• Funding based on equal share for each Division (14) = ~$42M / yr

Focus Address Significant Congestion and Bottlenecks • Selection based on 100% Data

• Projects Programmed prior to Local Input Ranking

Focus Improve Connectivity within Regions • Selection based on 70% Data & 30% Local Input

• Funding based on population within Region (7)

Estimated $20B in Funds for SFY 2018-2027

How STI Works Division 10 Update 9/19/18

Presenter
Presentation Notes
Div 10 Statewide Teir Region E is funded with $590 mil Division 10 in Division Teir $225 mil
Page 9: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

9

regions & divisions

Division 10 Update 9/19/18

Page 10: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

P5.0 Schedule

10

Division 10 Update 9/19/18

Page 11: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

11

Three major highway projects

Division 10 Update 9/19/18

Page 12: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

12

I-3802A

Construction began: Spring 2015 Estimated cost: $297.14 million Completion: December 2020 (I-85 final traffic pattern December 2018)

Division 10 Update 9/19/18

Presenter
Presentation Notes
Traffic in its final Pattern on I-85 by the end of 2018 I-3802 B is +/- 5miles from exit 63 to 68 is about a year behind us. That project will be in it’s final pattern by the end of 2019.
Page 13: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

13

Project Highlights • Design-Build contract • Widen I-85 to eight lanes between NC 73

(Exit 55) to north of Moose Rd (Exit 63+) • Rebuild three interchanges • Improve Winecoff School Rd • Improve Kannapolis Hwy • Project continues into Division 9 as I-3802B

Division 10 Update 9/19/18

Presenter
Presentation Notes
Project Challenges: Utility conflicts Rebuilding every bridge over interstate Additional work
Page 14: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

14

Dale Earnhardt Blvd (Exit 60): Future

Division 10 Update 9/19/18

Page 15: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

15

US 29/601 (Exit 58): Future

Division 10 Update 9/19/18

Page 16: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

16

R-3329 / R-2559

Construction began: May 2015 Estimated cost: $800 million Substantial completion: Late 2018

Division 10 Update 9/19/18

Page 17: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

17

Project Highlights

• Design-Build contract • 20-mile-long tolled Expressway • 8 interchanges • 21 box culverts • 37 bridges • All-electronic, Open Road Tolling

Division 10 Update 9/19/18

Presenter
Presentation Notes
Just over 18 miles of tolled facility Opening after Thanksgiving this year 2 axle $.14 mile ($2.54 end to end) transponder rate Transponder tolls 35% less than bill by mail
Page 18: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

18

Eastern Terminus

Source: Monroe Bypass Constructors

Division 10 Update 9/19/18

Page 19: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

19

Western Terminus July 2018

Source: Monroe Bypass Constructors

Division 10 Update 9/19/18

Presenter
Presentation Notes
Traffic Shifted a few weeks ago to elevated mainline – 485 east of Stallings Rd.
Page 20: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

20

I-3311C / I-4750AA / I-5405

Construction began: November 2015 Estimated cost: $647 million* Substantial completion: Late 2018

*Estimated cost does not include additions to the project made by the MPO with bonus allocation funds.

Division 10 Update 9/19/18

Presenter
Presentation Notes
Substantial completion: I-77MP intends to open the managed lanes without the direct connects: Hambright, I-85, Lakeview, I-277. Direct Connectors will be open in 2019.
Page 21: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

21

Project Highlights

• Public-private partnership • 26 Mile Project • Construct four express lanes from uptown

Charlotte (Exit 11) to Cornelius (Exit 28) and two express lanes from Cornelius (Exit 28) to Mooresville (Exit 36)

• Construct four direct connectors (Hambright Rd, I-85, Lakeview Rd, I-277)

Division 10 Update 9/19/18

Page 22: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

22

Express Lanes: Separate lanes in an existing highway corridor in which drivers can choose to

pay a variable toll for a more reliable trip

Also called HOT Lanes, Managed Lanes or Toll Lanes

Division 10 Update 9/19/18

Page 23: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

Upcoming Construction Projects

• U-5806; Concord Mills Blvd/Concord Mills Entrance- Concord Mills Flyover $7.5 mil construction, under contract

• I-5714/U-5114 I-77/Gilead Interchange to DDI and US-21/Gilead Rd improvements (Michigan Left) $ 23.3 mil Oct 2018

• R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

• I-5715; Upgrade NC-73/I-77 Interchange to Split Diamond FY 2020 • U-4714A&B John Street improvements from Trade Street in Matthews to

Wesley Chapel-Stouts Rd in Indian Trail. $128m FY 2021

• I-5507 I-485 DB Express Lanes. Opened Bids 9/18/18. Blythe Construction/WSP $346 mil (Engineers Estimate of $350 mil). Construction to start June 2019

23

Division 10 Update 9/19/18

Page 24: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

Hurricane Florence Response

• 44 Bridges overtopped or damaged • Currently 47 roads closed (44 in Anson County) • Had over 180 roads closed earlier this week • Deploying 4 additional NCDOT Crews to Anson County this week. • Assessing all routes in Cabarrus, Stanley, Union, and Anson Counties

for Damage. • Will draft contracts for repairs not completed by NCDOT

24

Division 10 Update 9/19/18

Page 25: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

NC-218

25

Division 10 Update 9/19/18

Page 26: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

NC-218

26

Division 10 Update 9/19/18

Page 27: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

Transportation

NC-218

27

Division 10 Update 9/19/18

Page 28: NCDOT Division 10 Update - ashecps.orgashecps.org/wp-content/uploads/2018/10/Div-10_ASHE... · • R-2530B; Widening of NC-24/27 from NC-740 to the Pee Dee River $ 60 mil. March 2019

28

THANK YOU