NC 12 – Rodanthe Breach Long-Term Improvements Merger Team Meeting

24
NC 12 – Rodanthe Breach Long-Term Improvements Merger Team Meeting September 11, 2014

description

NC 12 – Rodanthe Breach Long-Term Improvements Merger Team Meeting. September 11, 2014. Project Area. Phase IIb Status. Concurrence Point 2/2A signed in November 2012 Alternatives to be studied in detail: Bridge on New Location Bridge within Existing NC 12 Easement. - PowerPoint PPT Presentation

Transcript of NC 12 – Rodanthe Breach Long-Term Improvements Merger Team Meeting

Page 1: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

NC 12 – Rodanthe Breach Long-Term ImprovementsMerger Team MeetingSeptember 11, 2014

Page 2: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Project Area

Page 3: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb StatusConcurrence Point 2/2A signed in November 2012

Alternatives to be studied in detail:Bridge on New LocationBridge within Existing NC 12 Easement

Page 4: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- CP 2/2A Alternatives

Page 5: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb StatusEA signed on December 2013

Public Hearings Held in January 2014Meetings in Ocracoke, Rodanthe/Buxton, and Manteo

Comment Period ended January 24

Page 6: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Public Hearing CommentsReceived 12 oral comments and 78 written comments

Commenters asked to state alternative preference, reasons why, and suggestions for design improvements to both alternatives

Page 7: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Public Hearing CommentsPreferences:

Bridge within Existing NC 12 Easement: 12Bridge on New Location: 33, plus 64 petition signatures

Other:Alternative that can be built sooner: 3Beach Nourishment/ No Bridges: 26, plus 208 petition signatures

Page 8: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Local Government/ NGODare County- Prefer Bridge in EasementCitizens Action Committee to Replace the Bonner Bridge

Hatteras Island Property Management Group

Southern Environmental Law CenterSurfrider Foundation, Outer Banks Chapter- Prefer Bridge on New Location

Page 9: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- Bridge on New LocationDOI Comments- Preference for Bridge on New LocationMinimize Impacts to T&E speciesManagement of Refuge resources

NMFS Comments- Preference for Bridge within Existing NC 12 Easement Impacts to SAV habitat

Page 10: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- Bridge on New LocationShift alignment east to minimize amount of bridge within SAV habitatDense SAV areas along southern end of 2013 bridge alignment

Alignment change should not increase impacts within Refuge

Page 11: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- Bridge on New Location

Page 12: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- Bridge on New Location

Page 13: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- Bridge on New Location

Page 14: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb- Bridge on New LocationResidential Relocations

Visual Impacts

Jurisdictional Wetland Impacts

Essential Fish Habitat/ Submerged Aquatic Vegetation

Page 15: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb Alignments

Page 16: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Bridge within Existing NC 12 Easement Bridge on New Location

Permit Requirements

Section 404 Permit Section 401 Permit CAMA Major Development

Permit USFWS Special Use

Permit

Section 404 Permit Section 401 Permit CAMA Major Development

Permit USFWS Special Use

Permit/ Highway Easement

NPS Special Use Permit USCG Advance Approval

Page 17: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Additional RequirementsSection 106 Coordination

Section 7 Consultation

Essential Fish Habitat Assessment

Page 18: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Discussion

Page 19: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Litigation StatusFourth Circuit Court Decision

Issued August 6, 2014

Upheld NEPA analysis of project

Section 4(f) analysis sent back to District Court for further consideration

Page 20: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb Alignments

Page 21: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Future Extension Concept

Page 22: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Future Extension Concept

Page 23: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Discussion

Page 24: NC 12 –  Rodanthe  Breach Long-Term Improvements Merger Team Meeting

Phase IIb Next StepsHold CP 3 (LEDPA) Meeting

Hold CP 4A (Avoidance & Minimization) Meeting

Complete Section 106, Section 7, EFH coordination

Issue any additional environmental analysis, decision document for Phase IIb

Award design-build contract for construction