Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19...

34
Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation documents: Premier Partner: Page 2: Andrew Marshall, Ecochlor Page 7: Marcie Merksamer, EnviroManagement Page 11: Nier Israeli-Spielberg, Filtersafe Page 15: Guillaume Drillet, SGS Page 22: SGS Whitepaper

Transcript of Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19...

Page 1: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Navigating the BWMS system selection maze19 May 2020 • 09:00-09:45 BST

Part ofBallast WaterWebinar Week18-22 May 2020

Presentation documents:

Premier Partner:

Page 2: Andrew Marshall, Ecochlor

Page 7: Marcie Merksamer, EnviroManagement

Page 11: Nier Israeli-Spielberg, Filtersafe

Page 15: Guillaume Drillet, SGS

Page 22: SGS Whitepaper

Page 2: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Navigating the BWMS Selection Maze

Ballast Water

Management

Webinar

Andrew MarshallVP of Business Development

Page 3: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

BWMS Selection

• Equipment reliability

• Treatment technology effectiveness in sailing waters

• Importance of vessel flow rates

• Ease of use for crew

• Manufacturer after-sales support

• Availability of parts & consumables 2

Page 4: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Retrofit Challenges

• Planning, planning and more planning

• Hire an experienced team

• Commit to deadlines

• Actively communicate with stakeholders

• Oversite at the shipyard

• New regulatory issues. Testing3

Page 5: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Importance of Crew Training

• On board vessel training at commissioning

• First full ballast operation crew training

• Computer based training software

• Simulator shipowner training sites

• Manufacturer international training site

• Continuous on board crew training 4

Page 6: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

POWERFUL TECHNOLOGY | RELIABLE | FULLY SUPPORTED | ACCOUNTABLE

Thank you. Any Questions?

www.ecochlor.com

Page 7: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

RivieraBallast Water Webinar Week

Navigating the BWMS Selection Maze

19 May 2020

Marcie Merksamer – Vice President

Environmental Consulting & Project Management

Page 8: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Success!Class Society

BWMS Maker

Owner

Shipyard

Installer / Engineering

Firm

Installation Experiences - Stakeholders

Understand the roles, tasks and support needed by each. Coordination is key.

Agenda Topics: Retrofit Installation Challenges & Crew Training

Page 9: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Installation Experiences - Schedule

Give installation process the required attention• Major equipment retrofit• Large investment & expense

Schedule• Avoid waiting to end of shipyard period• Multiple parties to coordinate

Rushing = Risk• Incomplete / insufficient processes

• BWMS, class, shipyard• Crew training• BWMS Commissioning Testing Required?

Agenda Topics: Retrofit Installation Challenges & Crew Training

Page 10: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Marcie Merksamer, FIMarESTEnviroManagement, [email protected]+1 805-331-0740www.enviromanageinc.com

Thank you!

Page 11: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

BWMS selection: what must be considered

1

• Filters in BWTS have two major Tasks:

1. Removal of Organic matter – assisting the efficiency of the Disinfection stage

2. Removal of TSS from the ballast water and preventing Sedimentation in the Ballast tank

• Varying water quality vs. Test certification phase

• Sizing of filtration area / filter

o BWP Capacity and filter location in relation to the pump

• Filter Cleaning Ability / Recovery Efficiency

o Maintaining Operational Flow Rate as designed

o Minimizing delay in Ballasting

• Equipment Configuration Flexibility – H/V

• Certified and appraised design by major class ( LR, ABS, DNV-GL, BV, CCS, KR etc..)

• After Market and support with global reach

Page 12: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Comprehensive crew training is key

• Knowing your equipment

• Technical Workshops at manufacturer facility

o ‘Hands On’, How does it work? Troubleshooting

• Visual aids

o Installation and Maintenance animations

• Regular periodical updates – Tech. Bulletin

• Follow recommended Maintenance schedule

2

Page 13: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

To Filter or Not to Filter? That is the question

Owners deliberation would possibly be:

• Impact on Disinfection – dosing, power

• Risking Noncompliance

3

Good point for discussion during our Q&A could be-

Page 14: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

Reliable marine filtration solutions

4

Page 15: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

WWW.SGS.COM

SGS Marine Services19 MAY 2020 – Updates on BWMS Commissioning TestingDr. Guillaume Drillet ([email protected])

Regional Manager / Chair of Global TestNet

Page 16: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

2

SAMPLING AND TESTING IN DIFFERENT CONTEXTS

Type Approval

Prototype tested

multiple time against

standard conditions

Commissioning

tests

Verification of

performance and

installation on a ship

Survey and

Certification

Verification of

performance and

BWMS integrity in

time

Port State

Control

Verification of

performance and

BWMS integrity during

inspection

The Convention aims at decreasing the number of organisms transfered, there is only one standard for this in the convention and only one way to verify we have met the standard: TESTING !

Page 17: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

3

CIRC.70 BWMS COMMISSIONING

TESTING GUIDANCE

◼ Requires Inlet and discharge samples but should change to only discharge (such as

in Vessel General permit (VGP)) after MEPC 75

◼ Representative sample volume (3m3 in the Code) but should change to 1m3 after

MEPC75 (very different from VGP)

◼ Indicative analysis for all D-2 parameters, but should be limited to the two large size

classes after MEPC75 (very different from VGP)

◼ Including self-monitoring parameters and system design limitation parameters of the

BWMS

◼ Approved at MEPC 73 but revisions proposed at

PPR7 and changes likely to be approved at

MEPC75

Page 18: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

4

STILL VERY DIFFICULT TO NAVIGATE...

◼ Flag requirements are different: Australia and

Cyprus require testing under the existing Circ70

guidance; Singapore under the agreed scheme

from PPR7; other Flag such as Liberia, Panama

recommend the testing on a voluntary basis (until

Oct 2021).

◼ Class: present or absent during the tests, some

require approval of the facilities others do not.

Differences in request depending on surveyors,

countries, Class....

◼ Manufacturers and yards: sometime present

sometimes not. Quality of installation differs widely

Page 19: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

5

100 INSTALLATION TESTED, >20% FAIL TO

MEET D-2; ALL IN THE LARGE SIZE CLASS

SO WHAT IS THE LEARNING?

◼ Obvioulsly, testing is a necessity !

◼ Testing across 10 countries, for ships

under 8 Classifications societies, 14

manufacturers; 5 flag states

◼ Statistics from SGS to be available

in a white paper shared with Riviera

after the webinar

◼ Aside from failures to meet the

discharge standard, there are

emerging issues related to calibrations

of sensors (flow-meter, TRO meters...)

Page 20: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

6

IMPACTS OF

COVID-19?

◼ Challenging months in Asia from

February to end-April !

◼ Testing restarting smoothly all over Asia

◼ Cross-training between office to expands

capabilities globally (already testing in

Europe, USA..etc) but still some travel

restrictions

◼ Auditing of cleaning procedures and testing

for cleaning verification also available for

shipping – SGS Disinfection verified Mark

Page 21: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

7

SGS Marine Services19 MAY 2020 – Updates on BWMS Commissioning TestingDr. Guillaume Drillet ([email protected])

Regional Manager / Chair of Global TestNet

Page 22: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

COMMISSIONING TESTING OF BALLAST

WATER MANAGEMENT SYSTEMS

A WHITE PAPER BY SGS GLOBAL MARINE SERVICES

May 2020

Page 23: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

2/13

1. EXECUTIVE SUMMARY

Given the entry into force of the International Maritime Organization (IMO) International Convention for

the Control and Management of Ships’ Ballast Water and Sediments (Convention), the number of ships

installing and commissioning ballast water management systems (BWMS) to meet their compliance

dates has risen steeply in the last 6 months. Commissioning may be the only occasion in the lifetime of

a ship that compliance with the D-2 performance standard is verified. Aside from a few Administrations

acting as front runners, the guidance on commissioning will not apply before October 2021. Thus,

ships with systems installed prior to that date have no requirements for testing to verify performance. It

is unclear how often, if at all, port State control (PSC) procedures will follow stages 3 and 4 of the PSC

Guidelines, i.e., where sampling may be called for. Between the end of October 2019 and mid-April

2020, the Global Marine Services group at SGS conducted commissioning tests for 95 BWMS in 9

countries, for vessels of 5 flag States, under 8 classification societies, and from 14 vendors.

The notable findings are as follows:

• of the ships sampled, approximately one fifth (21%) failed to meet the D-2 performance

standard,

• all failures to meet the D-2 performance standard occurred in the largest size class

(≥50 µm) of organisms. Rarely, failures also occurred in the ≥10 µm to <50 µm size class (2%)

and the indicator microbes (<10 µm; 6%),

• neither the BWMS manufacturer nor the designated classification society were present

during all of the tests, with 67% attendance by manufacturers, and 67% attendance by the

ship’s classification society, and

• 67% of analyses were carried out using indicative analysis only and 25% of analyses

were done in two stages—indicative analyses first, followed by detailed analyses to verify

or refute non-compliance results from indicative testing. Detailed analyses refuted 54% of the

failures that had been determined using only indicative analyses.

The SGS view is that only testing can help to verify that the risk mitigation objectives of the Convention

have been met. This existing set of data highlights the need to ensure that commissioning testing is

carried out for all ships as soon as possible to protect the environment and the shipowners; ideally, this

should somehow include ships that have already been installed with BWMS but for which the

installation and capacity to meet compliance has not yet been proven. Likewise, the importance of

conducting commissioning (and, eventually, compliance testing) to properly assess the largest size

class of organisms is critical, as has been demonstrated by these data. Finally, the key role of detailed

analysis in commissioning (and, eventually, compliance) testing is evident from the testing carried out

so far. Its value should not be underestimated.

Page 24: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

3/13

2. INTRODUCTION

The International Maritime Organization (IMO) promulgated the International Convention for the

Control and Management of Ships’ Ballast Water and Sediments (Convention), which places limits on

the allowable concentrations of viable organisms in ballast water discharged from ships.

Fundamentally, the Convention has a single objective, which is to prevent the spread of harmful

organisms and pathogens (HOAP) by ballast water and sediments with the aim to protect the

environment. There is only one standard in the Convention to verify that this objective is met:

The D-2 performance standard, which prescribes limits on the type and density of organisms

discharged in ballast water. The limits in the D-2 standard are set according to size class (organisms

are binned into one of two size classes) or by type of indicator microbe (indicator bacteria and

pathogens) (Table 1).

Table 1. Parameters in the International Maritime Organization D-2 performance standard.

Parameter Limit in Ships’

Ballast Water Discharge

Organisms ≥50 µm (typically zooplankton) <10 viable organisms/m3

Organisms ≥10 µm and <50 µm (typically phytoplankton) <10 viable organisms/mL

Indicator microbe: Escherichia coli <250 cfu/100 mL

Indicator microbe: Enterococci <100 cfu/100 mL

Indicator microbe: Vibrio cholerae (serogroups O1 and O139)

<1 cfu/100 mL

cfu = colony-forming unit

To meet the D-2 performance standard, most shipowners will install ballast water management

systems (BWMS), which are onboard treatment plants typically including a mechanical step

(filtration/hydro-cyclone) and a disinfection step (physical or chemical). The BWMS have undergone

robust testing in view of their type approval, and this has been carried out globally with the aim to

ensure consistency and reliability in the testing1. This approach was further strengthened with the

revision of the IMO Guidelines for approval of ballast water management systems (G8) from 2014 to

2016 and the evolution of the Guidelines into the BWMS Code (i.e., a mandatory document).

Upon being installed, the BWMS must undergo commissioning testing, which has the purpose “to

validate the installation of a ballast water management system (BWMS) by demonstrating that its

mechanical, physical, chemical and biological processes are working properly.” (MEPC 73/WP.10). In

that respect, SGS is of the view that parties involved in the planning and installation of the

1Global TestNet: https://www.globaltestnet.org/Home

Page 25: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

4/13

BWMS onboard the ship should not be involved in verifying that their own work has been

carried out appropriately, as this obviously creates a conflict of interest.

SGS Global Marine Services group, with their long history of marine, environmental testing, has been

conducting commissioning testing, having tested 95 BWMS to date to determine compliance to the

IMO D-2 standard following the commissioning guidelines as set out in BWM.2/Circ.70. Of these

BWMS tested, some were tested on a single ship (multiple BWMS installed), and some were tested

multiple times (e.g., re-tested after a failure).

3. GENERAL OBSERVATIONS

SGS marine teams have carried out testing on BWMS from 14 manufacturers representing in-line

and in-tank treatment, typically consisting of a filtration step followed by physical (e.g., ultraviolet [UV])

or chemical (e.g., chlorination and ozonation) disinfection. Given the location of the bulk of the world’s

shipyards, it is not surprising that most of the commissioning testing so far has occurred in Asia (Figure

1). For this dataset, the majority of tests occurred in three countries: Korea (36%), China (32%), and

Singapore (24%). In general, the testing was carried out smoothly, and only 3% of the tests were

cancelled due to complications with the BWMS operations (e.g., due to automatic shutdown). As

such, we can conclude that, in general, the BWMS are “functional” in that the parts of the BWMS

installed onboard are operational. This conclusion tends to support that idea the type approval testing

(operational testing) of these systems has been done appropriately.

Figure 1. Countries where commissioning tests were conducted.

36%

32%

24%

1%1%1%

1%

1%3%

Korea ChinaSingapore MalaysiaGreece TaiwanNetherlands Australia

Page 26: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

5/13

The mandatory aspect of commissioning is planned to occur later in 2021, but some Administrations

have already required ships sailing under their flag to carry out the testing. Currently, Singapore,

Australia, Cyprus, and theoretically all EU countries require commissioning of newly installed BWMS

following BWM.2/Circ.70. Panama has recently changed the instructions for ships sailing its flag from

mandatory to voluntary testing. Accordingly, nearly all of the ships on which the commissioning tests

occurred were flagged under the States of Singapore (33%) and Panama (60%) (Figure 2). Article 2.1

of the Convention stipulates that “Parties undertake to give full and complete effect to the provisions of

this Convention and the Annex thereto in order to prevent, minimize and ultimately eliminate the

transfer of Harmful Aquatic Organisms and Pathogens through the control and management of ships‘

Ballast Water and Sediments”; considering the fact that commissioning may be the only time in the life

of a ship that the installation of the BWMS may be tested for its capacity to meet the objectives of the

Convention (managing the concentration of organisms in the discharged water), it is expected that

more flag States will make the commissioning test mandatory prior to October 2021.

Figure 2. Flag States of tested ships.

The classification societies of the vessels going through commissioning were dominated by a few large

ones: ClassNK (34%), Korean Register of Shipping (KR, 21%); DNV GL (17%), and American Bureau

of Shipping (ABS, 13%) (Figure 3). However, SGS does not carry out commissioning testing on behalf

of the classification society—it is conducted for the ship owner of the vessel—and, therefore, the

classification societies were not always present onboard during this testing. The classification society

was present onboard during 67% of the installations, and for a few vessels, its name was not mentioned

by the client and, therefore, this information was compiled from information available on the internet a

33%

60%

5%1%1%

Singapore PanamaCyprus CroatiaMarshall Islands

Page 27: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

6/13

posteriori. It is important to note that in a few cases, the testing was done on a voluntary basis, and,

therefore, the classification society may not be involved. Yet, as a general note, classification societies

are involved in approving the sampling plan for the commissioning prior to the test and then may join the

test on the day it occurs. In some cases, the tests were carried out in other countries different from where

the BWMS was installed (testing took place after the ship left the yard).

Figure 3. Classification societies overseeing commissioning testing. ABS = American Bureau of Shipping, BV = Bureau Veritas, KR = Korean Register of Shipping, and LR = Lloyd’s Register.

4. SAMPLE COLLECTION

SGS has designed, developed, and validated a portable Ballast Water Sampler (BWS1) as part of a

research project funded by the German Federal Maritime and Hydrographic Agency (Bundesamt fuer

Seeschifffahrt und Hydrographie, BSH) (Figure 4). The BWS1 is designed to collect and filter a

relatively large volume of ballast water (cubic meters), which is required to provide statistically

meaningful results for organisms in the largest size class of organisms stipulated by the IMO D-2

standard (≥50 µm). The SGS sampling protocol used when deploying the BWS1 ensures isokinetic

sampling conditions as required by the IMO Guidelines for ballast water sampling (G2). A full

description of the sampler and analysis methods can be found in the IMO document BLG 17/INF.16,

and reports on the onboard performance of the sampler and analysis methods can be found in

documents MEPC 68/2/13 and MEPC 75/INF.11.

17%

21%

34%

9%

4%

13%

1%1%

DNV GL KR

ClassNK BV

LR ABS

Croatian Register Germanischer Lloyd

Page 28: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

7/13

Figure 4. Use of the sampling equipment (BWS1) with a ballast water management system installed on deck (left) and inside an engine room (right).

For the purpose of commissioning, SGS always aims to filter a volume of 3 m3 for the ≥50 µm size

class and 10 L (sampled continuously) for the ≥10 µm and <50 µm size class and the group of indicator

microbes. Yet, in some cases, because the sampling probe onboard may be small size and/or because

of operational situations in which the volume of treated water may be limited, the volume for the

≥50 µm size class may sometimes be lower than 3 m3. Regardless, it is always higher than 1 m3.

While onboard and connecting the BWS1 to the vessel’s sampling port, the SGS surveyors assess the

suitability of the installation for isokinetic sampling of ballast water, which is stipulated under the IMO

G2 Guidelines and the BWMS Code. Specifically, the surveyors verify the ports’ adherence to the G2

Guidelines and the standard developed by the International Organization for Standardization (ISO;

11711-1:2019). It was noted on a few occasions that the sampling point was not aligned with the

design reported in the ship’s BWM plan and/or that the sampling probe was absent/not aligned with the

G2 Guidelines. Notably, it is impossible for the surveyors to verify that the sampling probes are

installed correctly and facing into the flow of ballast water. Of the ships tested, few installations (7%)

adhered to both the G2 Guidelines and ISO 11711-1 specifications (Figure 5).

Page 29: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

8/13

Figure 5. Sample port installations. G2 = International Maritime Organization Guidelines for ballast water sampling (G2) and ISO = International Organization for Standardization.

The use of a portable sampler is of paramount importance in commissioning testing, which sometimes

must occur within short amount of time, for example, while the vessel is bunkering. The surveyors may

therefore be required to board at anchorage with all their equipment (Figure 6). It was possible to

deploy the equipment within less than an hour onboard the ship without requiring preparation from the

crew, and testing could be carried out in less than 5 hours if it was well planned. These experiences

confirmed the observations from voluntary detailed testing that were reported to be carried out in

approximately two hours by Singapore (MEPC 75/INF.11).

78%

7%

15%

Follows G2

Follows G2 and ISO 11711-1

Does not follow G2

Page 30: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

9/13

Figure 6. The equipment for sampling and analyses onboard is craned up into the vessel at anchorage.

5. SAMPLE ANALYSIS

During a research project funded by BSH, SGS was tasked with supporting the testing of a rapid, on-

board indicative test developed by LuminUltra Technologies. This approach is used to assess if the

ballast water discharge is not in compliance with the limits for all three size classes in the IMO D-2

performance standard. After measuring the concentration of adenosine triphosphate (ATP,

C10H16N5O13P3), the concentration of ATP is correlated to the density of viable organisms. Following

analysis, the risk level of the sample’s non-compliance with the D-2 standard is categorised as Low,

Medium, or High. The standard operating procedures (SOPs) for ATP analysis of all three groups of

organisms are provided in MEPC 66/INF.27, ANNEX 1, Appendices 1-3.

These analyses may be conducted onboard the vessel or in the laboratory if the laboratory is situated

nearby the ship. The analyses should be carried out within 6 hours (as is done during type approval

testing) to ensure that organisms do not decay between the sampling and the time of analyses. In

addition to indicative analyses using ATP, SGS affiliates sometimes use a fluorometry-based

compliance monitoring device, the Ballast-Check 2 (Turner Designs), and they can carry out detailed

analyses in the laboratory if required or requested.

Page 31: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

10/13

For detailed analyses of organisms in the ≥50 µm size class, the concentrated organisms are counted

under a stereomicroscope in a Bogorov counting chamber using recognised methods2. For detailed

analyses of organisms in the ≥10 µm and <50 µm size class, SGS uses the fluorescein diacetate/5-

chloromethylfluorescein diacetate (FDA/CMFDA) dual fluorophore-motility method, and organisms are

counted using epifluorescence microscopy and Sedgewick-Rafter counting chambers2. Indicator

microbes are analysed using standard methods in our accredited laboratories (accredited under ISO

17025 or similar).

The majority of clients requested testing for compliance following the guidance from IMO and

flag States, and therefore requested indicative analyses (67%). Only a few clients (8%) requested

to use only detailed analyses during the commissioning test. However, because the results of detailed

analyses prevail over those of indicative analyses, most clients agreed that detailed analyses should

be carried out in cases where indicative analyses showed a likelihood of non-compliance. In 67% of

the tests, the analyses were stopped after the indicative analyses, and in 25% of the tests, additional

detailed analyses were carried out after the indicative tests showed likely non-compliance (Figure 7).

Figure 7. Analysis approaches.

2https://www.globaltestnet.org/getattachment/Discussions/GloBal_TestNet_Methodology_Comparison_Tables.pdf, EPA Environmental Technology Verification Program (ETV) Generic Protocol for the Verification of Ballast Water Treatment Technology, Version 5.1 (EPA, 2010).

67%

8%

25%

Indicative analyses only

Detailed analyses only

Indicative + detailed analyses

Page 32: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

11/13

When this occurred, in 54% of the cases, the detailed analyses provided data to refute the results from

indicative testing, therefore proving compliance of the ship with the discharge standard. This result

clearly indicates that there is a great value in considering detailed analyses in commissioning

testing—even if it is used as a secondary testing approach—to ensure that the owner does not

have to carry out a second, separate sampling event. The limitation of indicative testing during

commissioning testing may not be solely due to the adequacy of the analytical method but also to the

fact that many BWMS are approved with no minimum holding time, allowing discharge sampling to be

carried out immediately after the intake.

Overall, combining all testing approaches, 21% of the installations did not meet the D-2

performance standard of the Convention, and all failures were found in the largest size class of

organisms (≥50 µm). In many respects, the resistance of the larger organisms to treatment is not

surprising, and it has been discussed that this is the most likely size class to generate non-compliance.

Testing this size class illustrates to need to ensure that the filtration step (which is present on nearly all

BWMS) is well functioning (e.g., the integrity of the filter must be assured).

On quite a few occasions, the total residual oxidant (TRO) level in treated, discharged water from

BWMS using active substances was higher than the limit of 0.1 mg/L used by the Joint Group of

Experts on the Scientific Aspects of Marine Environmental Protection (GESAMP) to evaluate basic and

final approvals of BWMS. SGS is now in the process of compiling these data. High TRO values in

treated, discharged ballast water are an emerging issue for ballast water management, because while

high TRO concentrations likely ensure that the D-2 standard is met, the concentrations may be in

violation of local, state, or federal requirements and may have a negative impact on the environment

where the treated water is discharged.

6. ADDITIONAL OBSERVATIONS

Considering the data and experiences gained during the commissioning testing event, the following

potential issues should be considered:

- A relatively large number of crew members reported receiving limited training in the use of the

BWMS. In fact, the commissioning itself was often the only training given to the crew prior to

sailing.

- A relatively high number of installations had no information on the probe design and its

installation.

- The tanks may not have been cleaned prior to installation, float off water may contaminate

clean tanks, and other sources of cross contamination may occur.

Page 33: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

12/13

- In some cases, the installation did not allow the BWMS to work according to its specification

(e.g., the distance between the TRO sensors and the injection of neutraliser was not

appropriate).

- Inconsistencies between the flow meter reading and actual flow rate were observed on multiple

occasions. Here, the ship’s flow meter reading differed greatly from the real flow rate (which

was calculated from the tank capacity and the time to fill it); this could affect the isokinetic

sampling.

- In some the cases following a failure to meet the D-2 standard, after an investigation by the

classification society was performed, issues were corrected, and the ship passed when tested

again. Therefore, classification societies are managing to verify and ensure compliance to the

D-2 Standard at the time of commissioning.

7. CONCLUSIONS

At this stage, the causes for the failures observed in 21% of the tests are not evident. Overall, the work

performed to date points to the circumstances that should be considered during commissioning testing,

e.g., the value of two stage (indicative, detailed) analysis. The failures noted—while not providing a

clear picture of the source of failure—indicate that installation can affect the performance of BWMS

shown to be effective during type approval testing. If not corrected, this pattern of failures will

continue to be seen during compliance assessments by port State control authorities during

the life of the ship, resulting in an ongoing compliance risk to the vessel as well as risk to the

environment.

8. ACKNOWLEDGEMENTS

SGS would like to thank the crew members onboard the vessels that were sampled for their support,

commitment to “get it right”, and openness to discuss environmental issues. Additionally, thanks are

due to the surveyors from classification societies and manufacturers’ representatives who supported

the planning of the testing events.

9. TERMS AND CONDITIONS

http://www.sgs.com/en/Terms-and-Conditions.aspx. Attention is drawn to the limitation of liability,

indemnification and jurisdiction issues defined therein.

Page 34: Navigating the BWMS Part of Ballast Water system ......Navigating the BWMS system selection maze 19 May 2020 • 09:00-09:45 BST Part of Ballast Water Webinar Week 18-22 May 2020 Presentation

13/13

Any holder of this document is advised that information contained hereon reflects the Company’s

findings at the time of its intervention only and within the limits of Client’s instructions, if any. The

Company’s sole responsibility is to its Client and this document does not exonerate parties to a

transaction from exercising all their rights and obligations under the transaction documents. Any

unauthorized alteration, forgery or falsification of the content or appearance of this document is

unlawful and offenders may be prosecuted to the fullest extent of the law.