NAVAL INVENTORY CONTROL POINT
Requisition Processing
Presented By Thomas P. Mullin
November 5, 2003
![Page 2: NAVAL INVENTORY CONTROL POINT Requisition Processing Presented By Thomas P. Mullin November 5, 2003.](https://reader036.fdocuments.in/reader036/viewer/2022082713/5697bfa41a28abf838c972cd/html5/thumbnails/2.jpg)
NAVAL INVENTORY CONTROL POINT
• DAASC Automated Message Exchange System (DAMES)
• Requisitions received twice daily
• Morning & after 1300
• Item Manager makes the decision on how to fill the requisition, if not filled automatically by the computer.
Requisitioning Processing
![Page 3: NAVAL INVENTORY CONTROL POINT Requisition Processing Presented By Thomas P. Mullin November 5, 2003.](https://reader036.fdocuments.in/reader036/viewer/2022082713/5697bfa41a28abf838c972cd/html5/thumbnails/3.jpg)
Customer GeneratesRequistion
DamesRequisition
Received by ICPGoes to IM Desk
ITIMP Reqmt NSN BV Status
Buyer’s Work Load
Twice a Day
Requisition goesInto BD Status
Issued fromStock
SPOT BUY
Backordered
BM to StockPoint1 Day
ITIMP BV Status
Reqn inBB Status
Issued fromStock Point1 to 2 days
Buyers WorkLoad
IM GeneratesProcurement
3 Days
Award Shipped
3 to 5 days Delivery 60 to 90 days
BA Status Shipped 1 to 7 days
Award Shipped
30 to 45days toaward
30 to 60days to
ship
Buyer’sWork Load
AwardedShipped to
StockReqn’s BM
To Stock PointBA Status
Once shipped
30 to 45days
30 to 60days
1 day 1 to 7 daysStatus Codes:
BM - Document forwarded to activity indicated in cc 67-79BA - Item being processed for release and shipment ESD cc 70--73
BB - Item back ordered against a due-in to stock ESD cc 70-73BV - Item procured and on contract for direct shipment to consignee ESD cc 70-73
![Page 4: NAVAL INVENTORY CONTROL POINT Requisition Processing Presented By Thomas P. Mullin November 5, 2003.](https://reader036.fdocuments.in/reader036/viewer/2022082713/5697bfa41a28abf838c972cd/html5/thumbnails/4.jpg)
NAVAL INVENTORY CONTROL POINT
Requisitioning Processing
• If the NSN is a Requirements Contract the IM spot buys the requirement. (Day One)
• Requisition then goes in to ITIMP (Integrated Technical Item
Management & Procurement System) that assigns an order number to the appropriate contract (Day Two)
• The Buyer releases the buy from ITIMP & the order goes electronically to the contractor. (Day Three)
• Status is automatically sent to the requisitioner with an estimated delivery date. ( 60 to 90 Days depending on the contract)
![Page 5: NAVAL INVENTORY CONTROL POINT Requisition Processing Presented By Thomas P. Mullin November 5, 2003.](https://reader036.fdocuments.in/reader036/viewer/2022082713/5697bfa41a28abf838c972cd/html5/thumbnails/5.jpg)
NAVAL INVENTORY CONTROL POINT
Requisitioning Processing
•If the NSN is an Agilent Requirements Contract item, the requirement is filled from stock or backordered if no stock available.
•Issued from stock, and stock is available, the requisition is BM to the stock point and a A condition assets is issued. Requisition goes to BA status and will ship in 1 to 7 days.
![Page 6: NAVAL INVENTORY CONTROL POINT Requisition Processing Presented By Thomas P. Mullin November 5, 2003.](https://reader036.fdocuments.in/reader036/viewer/2022082713/5697bfa41a28abf838c972cd/html5/thumbnails/6.jpg)
NAVAL INVENTORY CONTROL POINT
Requisitioning Processing
• Spot Buy, requisition goes to ITIMP (Integrated
Technical Item Management & Procurement System) Buyer goes out for quote, award is 30 to 45 days. Material will ship in 30 to 60 days direct to consignee.
• If there are no A condition assets on hand the IM will back-order the requirement and initiate a buy for stock.
![Page 7: NAVAL INVENTORY CONTROL POINT Requisition Processing Presented By Thomas P. Mullin November 5, 2003.](https://reader036.fdocuments.in/reader036/viewer/2022082713/5697bfa41a28abf838c972cd/html5/thumbnails/7.jpg)
NAVAL INVENTORY CONTROL POINT
Requisitioning Processing
•Backorder will be released in the following sequence.•Priority
•Joint Chiefs of Staff (JCS) Project Code
•CASREP
•Work Stoppage
•Numeric Required Delivery Date (RDD)
•Document Julian Date