NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
description
Transcript of NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
MONTHLY PROGRESS REPORT on
NTDC DEVELOPMENT PROJECTSfor
February, 2013
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Ongoing Development Projects
Projects Ready for Implementation
Cross Border Interconnection Projects
1
ACTIVITIES
Ongoing Projects of NTDC
2
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of Work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
1-Extension at 500 kV Sheikh Muhammadi
Addition of 500/220 kV 1x450 MVA T/F
1,03817 21-01-2010 ADB Tranche-I Project
Completed 100 % Commissioned in June, 2012
Addition of 220/132 kV 1x160 MVA T/F
2- Extension at 500 kV Dadu
Addition of 500/220 kV 1x450 MVA T/F
1,05017 21-01-2010 ADB Tranche-I
Project Completed 100 % Commissioned in
June, 2012
Addition of 220/132 kV 1x160 MVA T/F
Project Completed 100 % Commissioned in
December, 2012
3-In/out of 220kV Ghazi Barotha – Shahi Bagh at Mardan
220 kV D/C T/L(30 km)
5339 30-11-2006 ADB Tranche-I Project
Completed 100 % Commissioned in December, 2012
3
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
4- 220 kV GIS Bandala
220 kV substation with two 220/132 kV 160 MVA T/Fs along with allied equipment.
1,95032 30-11-2006 ADB Tranche-
I
Civil & electrical works in progress.
75 % June, 2013
In/Out of 220 kV Gatti-KSK Transmission Line at Bandala (5+5 km)
Project Completed. 100 % Commissioned on 16-
05-2012
5- 220 kV Rohri
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
4,84778 06-02-2008 ADB Tranche-
II
Civil and electrical works in progress.
73.35 % June, 2013
•220 kV Dharki-Rohri New D/C T/L (115 km)•220kV D/C Rohri New-Shikarpur T/L (50km)•220 kV D/C T/L for In/Out of Fauji Mari-Rohri New at Engro Chemical CCPP (5+5km)
Project Completed. 100 % Commissioned in
June, 2012
4
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No. Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected Commissioning
6- 220 kV Khuzdar
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,90050 27-07-2004 JICA
Civil and electrical works in progress.
77 %
September, 2013220 kV Dadu-Khuzdar D/C T/L (274 km) Erection and
stringing work in progress
82 %
7- 220 kV Kassowal
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,06736 02-02-2005 World Bank
Civil and electrical works in progress.
57 % September, 2013
Two 220 kV D/C T/L for In/out of 220 kV Vehari-Yousafwala D/C T/L at Kassowal (45+45km)
Project Completed. 100 % T/L commissioned
on 06-08-2012
8- 220 kV GIS Shalamar
220 kV gas insulated substation with three 220/132 kV 160 MVA T/Fs and allied equipment
3,61759 22-10-2007 JICA
Civil and electrical works in progress.
75 % June, 2013
Project Completed. 100 %
T/L commissioned on 20-11-2012220 kV D/C T/L for In/Out
of one circuit of 220 kV Ravi-KSK T/L at Shalimar (9 km)and under ground cable (3+3 km)
5
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
9- 220 kV Okara
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,88431 06-02-2008 ADB Tranche-
II
Civil and electrical works in progress.
86 % June, 2013
In/out of 220 kV Yousaf Wala-Sarfraz Nagar D/C T/L at Okara (5+5 km)
Project Completed. 100 % T/L ready for
commissioning.
10- 220 kV T.T. Singh
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,75929 06-02-2008 ADB Tranche-
II
Installation in progress. 86 %
June, 2013In/Out of 220 kV Faisalabad-Multan D/C T/L at T.T Singh (1+1 km)
Civil works completed.
Erection and Stringing in
progress
75 %
6
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
11- 220 kV Loralai
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
5,08883 06-02-2008 ADB Tranche-
II
Civil and electrical works in progress.
70%
June, 2013
220 kV D.G Khan-Loralai D/C T/L (200 km)
Erection and stringing in progress.
95 %
12-500 kV Rahim Yar Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment 4,936
81 22-10-2007 JICA
Civil and electrical works in progress.
64 %
December, 2013
500 kV S/C T/L for In/Out of 500 kV Guddu-Multan 3rd Circuit at R.Y Khan (30+30 km)
Civil and Electrical works in progress.
57 %
7
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
13-Ext. at 500 kV Ghazi Barotha
Addition of one 500/220 kV 600 MVA T/F with allied equipment.
1,65427 06-02-2008 ADB
Tranche-IICivil works in
progress. 37 % December, 2013
14- 220 kV Gujrat
220 kV substation with three 220/132 kV 250 MVA T/Fs with allied equipment.
1,96632 22-10-2007 JICA
Contract agreement signed
with M/S HYOSUNG Cooperation
Korea on 3-1-2013
3 % 2013-14220 kV D/C T/L for In/Out of 220 kV Mangla-Ghakkar D/C T/L at Gujrat (2+2 km)
15-220 kV Ghazi Road, Lahore
220 kV substation with three 220/132 kV 160 MVA T/Fs and allied equipment
2,59243 25-02-2005 KfW
Bidding documents as prepared by
Design has been vetted by M/S Lahmayer and sent to KfW for concurrence
1 %2013-14
220 kV D/C T/L for In/Out of 220 kV NKLP-S/Nagar S/C at Ghazi Rd (30 km)
220 kV D/C T/L for In/Out of 220 kV Ravi-KSK S/C at Ghazi Road (50 km) Ready for
commissioning 100 %
8
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
16- 220 kV Chishtian
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
2,63343 22-10-2007 JICA
Contractor mobilized and
started civil work.
18.75 %
December, 2013
220 kV Chishtian-Vehari D/C T/L (65 km) Foundation
and Erection work in
progress35 %
Extension at 220 kV Vehari Grid Station
17- 500 kV D.G Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment
4,46773 06-02-2008 ADB
Tranche-II
Civil works in progress. 23 %
December, 2013
Erection and stringing in progress
79 %In/Out of 500 kV Guddu-Multan 2nd Circuit at D.G Khan (20+20 km)
9
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusExpected
Commissioning
18
Augmentationof existing Grid Stations
Name of Grid Stations
No. of
T/FsVoltage
(kV)Capacity
(MVA)
3,90046
21-01-2010 ADB Tranche-II
Bids under evaluation December, 2013
500 kV Rewat 1 500/220 750
500 kV Sheikh Muhammadi
4 220/132 250
220 kV Mardan 2 220/132 250
220 kV Burhan 4 220/132 250
220kV Bund Road 4 220/132 250
220 kV Bahawalpur 2 220/132 250
220 kV Quetta Industrial
2 220/132 250
10
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
19- SVC at NKLP Static Var Compensators of 450 MVA
2,08734 30-11-2006 ADB
Tranche-I
Contractor mobilized and
started the work.
10 % December, 2013
20- 220 kV Dera Murad Jamali
220 kV substation with 220/132 kV 1x160 MVA & 1x100 MVA T/Fs and allied equipment
88011 07-04-2011 NTDC own
resources
Contractor mobilized and civil works in
progress10 %
June, 2014
220 kV D/C single conductor T/L for In/Out of 220 kV Uch-Guddu S/C at Dera Murad Jamali (5 km)
T/L profile and Plan Tabling approved. 10 %
11
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
21-500 kV Lahore (South)
500 kV substation with two 500/220 kV 750 MVA T/Fs and allied equipment
12,524150 09-12-10 JICA
Works awarded to the contractor M/S
CNEEC-FNEPCC (Joint
Venture), agreement signed on
12-06-2012.Contractor not yet mobilized.
3 % June, 2014
Two 500 kV S/C T/Ls for In/Out of 500 kV Sahiwal-Lahore S/C at Lahore New (15+15km)
Two 500 kV S/C T/Ls for In/Out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km)
220 kV D/C T/L for In/Out of 220 kV NKLP- Ghazi Road S/C at Lahore New (50km)
220kV D/C T/L for In/Out of 220 kV NKLP- Wapda Town S/C at Lahore New (45 km)
12
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
22- SVC at Quetta Static Var Compensators of 450 MVA
2,08734 06-02-08 ADB Tranche-
IINot yet started. N/A December, 2014
23- 500 kV Shikarpur
500 kV substation with two 500/220 kV 600 MVA T/Fs and allied equipment
8,04996 09-12-10 JICA
Contract agreement signed, L/C opened and contractor mobilized.
5 % June, 2014
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu -Guddu Cct # 1 (20+20 km)
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu – Guddu Cct # 2 (22+22 km)
220 kV D/C T/L for In/out of 220 kV Guddu – Sibbi S/C at Shikarpur(50 km)
13
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by ECNEC Financing Project Status Expected
Completion
24-Power Dispersal from 747 MW CCPP Guddu
500kV Guddu-Muzaffargarh S/C T/L (256 km)
7,85691 29.07.2011 Buyer’s Credit
BasisTender opened on
08.10.2012 and are under evaluation.
2013-14Two 500 kV T/L for In/Out of 500 kV Guddu-Multan S/C T/L at 500 kV Muzaffargarh (10 +10 km)
Extension at 500kV Muzaffargarh
25-Power Dispersal from Uch-II
•220 kV Uch-II – Sibbi D/C T/L (125 km)•220 kV D/C T/L for In/Out of 220 kV existing Uch-I to Shikarpur New S/C T/L at Uch-II (0.5 km)•Reconductoring of 220kV T/L Uch-I to Uch-II (1 km) 2,508
30 16.08.2012 ADBTranche-III
Tenders opened on 12.12.2012,
Evaluated by C.E Design and has been sent to GM Projects
for approval.
2013-14
Extension at 220kV Sibbi substation
Tenders opened on 18-10-2012 and are under evaluation.
2013-14
14
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Expected
Completion
26-Power Dispersal from Neelum Jhelum HPP
Package-I• 500 kV D/C T/L from Neelum Jhelum to Gujranwala (270 km)•500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Karot (5 km)•500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Azad Pattan (5km) 22,582
251PC-I cleared by
CDWP on 18-06-2012
Buyer’s Credit Basis
Tender opened on 09-08-2012, evaluated and submitted for
approval on 16-10-2012 2015-16
Package- IIExtension at 500 kV Gujranwala
Draft Bidding documents submitted to NTDC on Nov. 29,2012
Total 107,8081,483
15
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 500kV Projects
Sr. No. Description Addition in T/L & T/F Capacity
1- 500 kV S/C Transmission Lines Length 1150 km
2- 500/220 kV Transformation Capacity (New Projects) 5100 MVA
3- 500/220 kV Transformation Capacity (Extension) 1500MVA
4- 500/220 kV Transformation Capacity(Augmentation) 300MVA
500/220 kV Transformation Capacity(Grand Total) 6900MVA
16
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 220kV Projects
Sr. No. Description Addition in T/L & T/F
Capacity
1- 220 kV Transmission Line 1224.5 km
2- 220/132 kV Transformation Capacity(New Projects) 6930 MVA
3- 220/132 kV Transformation Capacity(Extension) 320MVA
4- 220/132 kV Transformation Capacity(Augmentation) 1620MVA
220/132 kV Transformation Capacity(Grand Total) 8870MVA
17
Projects Ready for Implementation
18
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Approval byECNEC/CDWP Financing Project Status Expected
Completion
1-3rd Circuit from Jamshoro to Rahim Yar Khan
500 kV Jamshoro - R.Y.K (535 km)
24,831285
PC-I Cleared by CDWP on 21.10.2011
ADBTranche-III
Tender scrapped due to technical
and administrative reasons by MD
NTDC.
2015-16500 kV Moro-Dadu (55 km)500 kV Switching Station at Moro
Extension at 500 kV Jamshoro, Dadu & R.Y.K Grid Stations.
2-Power Dispersal from Chashma Nuclear (C3 & C4)
220 kV Chashma Nuclear – Bannu D/C T/L (125 km)220kV D/C T/L for In/Out of existing C1 &C2 at C3 & C4 (2 km) 3,103
35
PC-I is under scrutiny in Planning
Commission
Buyer’s Credit Basis
Route under checking. 2015-16
Extension at 220kV Bannu
19
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No. Name of the Projects Scope of work Est. Cost
(MUS$)Approval by
ECNEC/CDWP Financing Project Status Expected Completion
3-Power Dispersal from 1200 MW Thar Coal Based Power Plant
500 kV Thar – Matiari D/C T/L (250 km)
20,053233
PC-I Approved by ECNEC on 16.08.2012
Buyer’s Credit Basis
T/L Plan and Profile
Drawings completed.
2015-16500 kV Switching Station at Matiari
4- 220 kV Nowshera
220kV sub station with 3x250 MVA T/Fs along with allied equipment
1,87631
Approved by ECNEC on 06.02.2008
Proposed in ADB
Tranche-IV
Hiring of project preparatory
consultants in process.
2015-16In/Out of 220 kV Ghazi Barotha – Shahi Bagh D/C T/L at Nowshera (5+5 km)
20
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Approval byECNEC/CDWP Financing Project Status Expected
Completion
5- 220 kV Lalian New
220kV sub station with 3x250 MVA T/Fs along with allied equipment
1,58118
Approved by ECNEC on 11.11.2011
Proposed in ADB
Tranche-IV
Hiring of project preparatory consultants in process.
2015-16Two 220 kV D/C T/L for In/Out of 220 kV Gatti – Ludewala D/C T/L at Lalian New (4+4 km)
6- 220 kV Mansehra
220kV sub station with 2x250 MVA T/Fs along with allied equipment
90511
Approved by ECNEC 07.04.2011
ADBTranche-III
Construction of boundary wall completed.Bidding documents are on sale and tenders opened on 26-02-2013 and are under Evaluation
2015-16Two 220 kV D/C T/L for In/Out of 220 kV Alai Khawar – Islamabad Peshawar Road D/C at Mansehra (0.5+0.5 km)
21
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Approval byECNEC/CDWP Financing Project Status Expected
Completion
7- 220/132 kV D.I.Khan
220kV sub station with 2x250 MVA T/Fs along with allied equipment
3,74444
Approved by ECNEC 09.12.2010
Proposed in ADB
Tranche-IV
Land for G/S acquired.
Construction of boundary wall in
progress.
2015-16220 kV D/C T/L for In/Out of 220 kV Chashma Nuclear-Ludewala S/C T/L at D.I Khan (100km)
Total 56,093
657
22
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Projects Ready for Implementation
Sr. No. Description Addition in T/L & T/F Capacity
1- 500kV S/C Transmission Lines Length 1090 km
2- 220kV Transmission Line 246 km
3- 220/132 kV Transformation Capacity 2500 MVA
23
Cross Border Interconnection Projects
24
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
1- Import of 100MW Power from Iran.
220 kV Pak Iran Border-Gwadar D/C T/L (100km)
44
Survey work in progress.
Iranian Bank June, 2013
Work awarded to contractor.
220KV GIS at Gwadar with 2x160MVA T/Fs
2-Import of 1000MW Power from Iran.
500kV HVDC Bipolar Transmission Line from Pak - Iran Border to Quetta (585km).
413
MoU signed between Pakistan & Iran on
31.05. 2012 to implement the
project.
Not yet committed 2015-16
500 kV Convertor Station at Quetta.
25
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
3-Import of 1000MW Power from Tajikistan.
500kV HVDC Bipolar Transmission line from Pak-Afghan Border to Peshawar (71km).
189 Feasibility Study completed.
Positive response from
World Bank and IDB
2015-16
500 kV Converter Station at Peshawar
4-Import of 200-500 MW Power from India.
Different options for Interconnection are under study. -
World Bank has offered to sponsor pre-feasibility study
for the project
Positive response from
World Bank-
Total 646
26
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Report Prepared by: Designation Contact No.
Maqsood Ahmad Qureshi
Additional ManagerProjects Planning
0347-4447720 042-99202609
Fahmeeda Shafi Dy. Manager Projects Planning
042-99202609