National Governors Association Meeting LM: Ensuring a Smooth Transition – Procedures and Examples
description
Transcript of National Governors Association Meeting LM: Ensuring a Smooth Transition – Procedures and Examples
National Governors Association Meeting
LM: Ensuring a Smooth Transition – Procedures and Examples
June 21-22, 2005Dave Geiser
Office of Legacy Management
2
Current Sites in Legacy Management
3
Worker Activities
Worker Activities During Remediation
Worker Activities After Remediation
4
Environmental Management/Legacy Management Transition
5
Transition Goals
• Achieve zero service disruption for critical activities
• Achieve zero negative impact to closure mission or LM mission
• Identify programs and activities requiring transition versus termination
• Bring together separate EM and LM organizational initiatives• Identify schedule drivers and develop an action plan for each
transition element• Manage actions and logic ties as a project• Actively engage stakeholders in transition• Complete transfer of functions as logically and early as
possible
6
LM Transition Approach
• Establish early communications
– DOE to DOE
– Expand to contractor to contractor, as appropriate
• Site visit by LM team
• Establish transition plan that includes scope, cost, and schedule
– An integrated EM–LM effort to the greatest extent possible
– Flexible along the way, but firm end points
• RUN THE TRANSITION AS A PROJECT!
7
Legacy Management Transfer Tasks for “Complex” Sites
8
Weldon Spring Site – In the 1950s during Full Scale Operations
9
Weldon Spring: Disposal Cell, Interpretive Center, Prairie, and University Campus - 2004
10
Rocky Flats: Recent aerial view - prior to Final Remediation
11
Rocky Flats– Conceptual End State as the Rocky Flats National Wildlife Refuge
12
Fernald – Recent Aerial Photo (2004) during Active Remediation
Fernald – Conceptual aerial view after active remediation including GW P&T is complete.
14
LM will be ready for the EM Closure Sites to Transfer
• Post-closure work scope is generally within LM’s current capabilities, i.e., cell maintenance, ground water and surface water monitoring, and limited pump and treat.
• EM and LM have agreed to the amount of funds currently expected for post-closure operation.
• Management of records and information (environmental data in particular) is a significant aspect of transition and post-closure operation.
• Post-closure regulatory agreements and CERCLA O&M plans are tailored to the needs of the individual sites and regulators.
• Everyone needs to make the transition: post-closure operation means a greatly reduced workforce, fewer and less important decisions, and opportunity for controlled beneficial reuse.