National Communications Support Programme
NCSP UNDP/UNEP/GEF
Martha PerdomoGlobal Manager, NCSP
George ManfulSenior Task Manager, UNEP
United Nations Development Programme
Programme Objectives
1. To facilitate preparation of NCs 2. To prepare and disseminate technical and policy-
relevant materials, including training3. To sustain capacity building efforts through:
– knowledge networks – best practices– communications and outreach
Collaboration with regional institutions will be actively promoted
NCSP Implementation Strategy
• Provide support to all NAI Parties for the preparation of their NC
• Consult with NC project coordinators on a regular basis• Flexible scheme to address changing priorities during
preparation of NCs• Core thematic areas to be addressed by the NCSP
– GHG inventories, vulnerability and adaptation, abatement
– Technology transfer and needs assessments– Integration of climate change issues into national
development plans• Cooperate with CGE for technical assistance • Web-based training materials, where appropriate• Provide assistance for preparation of mitigation and
adaptation projects for funding
NCSP: Communications Strategy
• Website– Updated monthly– Hosts Knowledge Networks– Expanded library of resources
• Email list-server– Monthly information updates (e.g. project results,
lessons learned, general climate news)
• Quarterly Newsletter– Informing on NCSP and UNDP, UNEP, GEF climate
change activities
• UNFCCC side events to inform on progress
NCSP Support Activities
• During project implementation:– Identify and share good practices on the basis of
countries’ experiences
– Provide technical feedback on draft NCs and sectoral technical reports
– Provide guidance on methodological issues and resource materials, addressing gaps where relevant
– Conduct regional thematic workshop in coordination with the CGE
– Conduct sub-regional, targeted training activities
NCSP Current Activities
• NCSP activities were initiated in June 2005
• A workplan was prepared
• A listserv is being updated on national project coordinators
• A questionnaire on technical needs is being prepared
• An initiation workshop is being organized for countries already starting the NC work
• Preparations for a KN on GHG inventories are underway
• Participation in training workshops of CGE
• A meeting of the Advisory Committee is planned
KN on GHG Inventories and V&A
• Purpose: to provide an online facility for NAI experts:
- to exchange information
- ask questions
- share expertise
There is currently no such facility
KN on GHG Inventories and V&A
• Description:– It will take the form of a moderated email listserv
– Moderator will function as expert and as gatekeeper for listserv submissions
– Substance of exchanges will be: information dissemination, questions and answers
– Will engage regional Centres of excellence/organizations
– Annual report to be produced, including lessons learned
Status of preparation of NCs
• 102 countries have received funds ($15,000) for the stocktaking exercise and stakeholders consultations to prepare their NC project proposals under expedited procedures:
• 6 countries are preparing their SNC without accessing stocktaking funds:– Argentina, Brazil, India and Peru (full cycle projects)– Morocco, Tunisia (followed expedited procedures)
• 2 countries are preparing their TNC without accessing stocktaking funds:– Mexico, Uruguay (followed expedited procedures)
• TOTAL NUMBER OF COUNTRIES PREPARING NATIONAL COMMUNICATIONS: 110
– SNC: 103– TNC: 2– INC: 5
Status of approval of projects
• Albania• Armenia• Azerbaijan• Bolivia• Cote d’Ivoire• Democratic Rep. of Congo• Georgia• Haiti• Kazakhstan• Kenya• Kyrgyzstan• Lebanon• Liberia (INC)
• Macedonia• Mauritania• Mexico (TNC)• Moldova• Morocco• Nicaragua• Niue• Samoa• Tajikistan• Tunisia• Turkey (INC)• Uruguay (TNC)• Uzbekistan
• Countries with project proposals approved, under full cycle procedures: Argentina, Brazil, India, Peru
• 16 countries have submitted their proposals to IAs for approval
• Countries with project proposals approved, under expedited procedure:
Antarctica
China
Brazil
CanadaRussian Federation
Australia
India
Greenland
/
LEGEND1. SNC Approved by IA and Preparing National Communication
2. Submitted SNC Draft for approval to the IA
3. Self Assessment to prepare their SNC proposal
N C S P W O R L D W I D E A C T I V I T I E SN C S P W O R L D W I D E A C T I V I T I E SI M P L E M E N T A T I O N S T A T U S O F S N CI M P L E M E N T A T I O N S T A T U S O F S N C
0 6,800,000 13,600,000 20,400,000 27,200,0003,400,000Meters