NASA Saturn V Rocket Structural Elements - 1968
Transcript of NASA Saturn V Rocket Structural Elements - 1968
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
1/413
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
2/413
DOCUMENTNO. D5-15782
TITLE APOLLO/SATURN V SPACE VEHICLE SELECTEDSTRUCTURAL ELEMENT REVIEW REPORT, AS-503MODEL NO. APOLLO/SATURN V CONTRACTNO. NAS8-5608, SCHEDULE IVPART IV, TASK 1.0CHANGE ORDER MSFC IV-2
ORIGINA[. RELEASE - NOVEMBER 25, 1968
,ssoEo. j_ ISSUED TO ._._ -_ _ -. },t / s ,'7", _.,.__ " . "J _,C
THE _ItU_J_I_G COMPANY SPACE DIVISION LAUNCH SYSTEMS BRANCH
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
3/413
D5-15782
RE'V.SYM
REV i S IONSDESCR IPT ION DATE APPROVED
ii
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
4/413
OC
tI
_b
03
E
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
5/413
Oo I O0
OJOoO0
o
DO-._0
DO
PO
I_0
I_0ixODO
_
(0
P-_0
.
._
.
,_,_.
C r Z m r r c z m
-__
(X')
_mc-
"-rl_0_
c
-i_,-
L
_
t
C
'_
tmILI-JI
I_Y
03IL
L_m
"I
IJ__
,=_LC3LL
I00IIJtZ
>
O
(J_-
tO--
:E
9I(D
:>
O(O
(D
r_
r_O
._
L
E
'_
cI
CE>
O1
ELc
,_
v"rO
4
V-_9
rO_
(Dr_9
OO
((_.
P4
V
I
9
_
P(D
O
(D-
r_O
(O
EErJ
pr_
0
E
E4
,_O
EI_
.Pu(1I
(1_4L
(1(cO
(DIi
L(D_i
r_OC
Or_I'_
rO
O
_
rO
c
.
I
"O
O3E
rO
O
E
r_
rm
"O
Oc
4
L(D
__
_
_
_:_O
-
::3
-r-_'_
_Pr_
LcO
rE
O"
U
IL
L-J
(I
:3
E
,_O
_(1
rOc
_
I
(D_"
4
-Ev(_
r
.G
E(O
L>_
O
-
_E-r-
(_V
oOO_
(J
"_0
r
(_)
_-r-
r
(D_.r--
.
-
(.D
_E:-IJ'r-
(..)r_
_
_.
OO
_
crO
I0
O4
r_
.Jr_
I_r___
._r
E
c_
r_
(D,
(DD
>SC
_(1
S
(D
"_O
OO
-Ec
(-_Ji
OP
-J-Jr0
_(_
_
L
O_
-_-_O
_
I
r_
nJ
(D_I
LrDI
((Or
g_:Dr_
O
E
c
0
r0
_
(1
-J0-
_
(D
r
(D
O
>
>VP_
P_
E_
I
(DV
c_
c
_rr0
"_
O(DI"
-J
L_
r0
O
O3
_(1c
c
r-(D
r_r
r___o
CI
O
E
_D_
0
I
c_
C
Or_
0EL
t_tO
r_3C_J%
I
L
:_Or_I
r1O
o9OO
_r_
iIOc"s4cOOOIEI
r0r_1r_
LEOO
r___
>(1
r-J
">
CO
ED4V>(3r_>cS4r_Ocr_Op_
E
I
ie_
_(E
E_
C
__t
OcO
__.p4r_(
vOOO
4E
O_
_Lc
(Ur0
r_t
E_Oc
Pr3
-J,V
_(D
,OE
r_O"_
>LO
L_r_
c0
(D'_
E
__O
.r-_
0
:_O
>
_
.r-
-J
__
4
r3
IEE
_
_
E0
-r-
_c
-J_
-
0
r
_
(_
_
(D
.
r
(.-)CO
0
I
r_
Z
u
_,_
(D
Of
_
>
"m0
r
.LO
Q
,
4i
C(D
C_
E>
L
!
L.
L
I>O
I>
n3
!
L
I
(f)C
Z3
_JO
_r
.-oX
O
r
_
O
,
O
O
_
L
C
O_
C
r
O
P
O_
C
oJ
L
C
L
C
r
O
C
_
'_
0
O
0
0
_
r"
L
L
_0
c
O3
L
L
O
!
i
QD
(J
_
O
O3
r_
_
I
im
C
,_
L
L
L
L
_
L
r
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
15/413
rmZ--Z
00
O
I
ILl
LO
C._
r-_
ZLJLUr_
-1:3E0
%-sLO
_C0E
'
c-r_r_
Ic-c-O.r--
e-E.-e-e-r_
o'3
.X
0!0N
I
0
0
I
0
I
IrJ
_
_0
r
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
16/413
O4O0r_Lf_hrm
Z--(__
Dv-F--
Z
>
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
17/413
oOZ04
0
O0
_-_
m-
I---
UUO
L_
r-n
:
00
0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
18/413
r_
L$
0__
C
-
Z
.Qc
_
_0
ca
r_
0e,_
_
L
,__-Jc
X
0
0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
19/413
OCt
ewD
"0
c4-)4_
0
0
_.-I
,m.
C0i4I
o
o
e
o
o
_-ZN
(D
tOO_
O
OO-1_
O
_
%
c
00tOOtm
etO
ODoOtO
$OOt,
,O
-OO
_,
O_
cru_r5
OOO
c-0"_3-l.J
(Dc-
-hi(D
i-,
CJ
-I_0
0
O0
o0r
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
20/413
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
21/413
D5-15782
SECTION 1S-IC-3 LOX TANK LOWER BULKHEAD
SELECTED ELEMENT REPORT
I-I
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
22/413
O0LO
I
_t_
o1
r_
_c
r
0'I-r--O_
c0
.r-_-c-
-_-
-
_-r-
.
_
c-
c-0
c-n_(D
I
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
23/413
04COL'DC
Z0..)29
ILl,-%
r---
Ir
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
24/413
D5-15782
SKINSECTIONS-_x, x
UPPERBULKHEAD
VEHICLESTATION
909 ---
772 ---
IiMANTI-SLOSH
BAFFLES
POS I
POS I ]
POS IV
LOWER LOX BULKHEAD
PUS llI
FIGURE l-I S-IC LOWER LOX BULKHEAD
I-4
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
25/413
D5-1 57821.2 MANUFACTURING1.2.1 FabricationThe apex and base gores were fabricated in Wichita from2219-T37 aluminum sheets purchased per BMS 7-I05Co The seg-ments were sculptured and machine milled in the flat condi-tion. The milling provided a light structure with weldlands at the edges and integral membrane and stiffener con-figuration in the base gore segment to carry hoop compres-sion stresses.Following the milling operation, the segments were roughrolled to the approximate desired contour. The segmentswere then hydraulically bulge formed to the finish contour,rough trimmed, cleaned, and heat treated to the T87 condi-tion.The polar cap was machined from 2219 aluminum.The Y-ring was made at Michoud from 2219-T351 aluminumbillets which were rolled to a radius of sixteen and ahalf feet and then oven aged to T851 hardness. The threebillets were then butt welded to form a ring The MIGwelding was performed from both sides of the joints simul-taneously (each joint required approximately 112 weldingpasses). The completed 19,000 pound billet ring was thenplaced on a boring mill and turned to the finished Y-ringconfiguration, having a thirty-three foot diameter whichweighed approximately 3500 pounds.1.2.2 AssemblyFollowing receipt of the apex and base gore segments fromWichita, the edges of the segments were prepared for join-ing by trimming and fitting. The appropriate apex and basegores were joined using the TIG welding process. The eightassembled gores were joined by the same process to form thegore to gore assembly. Subsequently, the Y-ring was weldedto this gore assembly utilizing the TIG welding process.The final step was the TIG welding of the 54 inch polarcap into position to complete the ellipsoidal shaped bulk-head. See Figures I-2 thru I-5. The following MORTP'sdetail the operations on the foregoing steps of assembly:60B12200-I-904 thru 907, 949, 950, 960 and 970.In conjunction with the Y-ring to bulkhead weld, a certi-fication weld (per MORTPWC60BI2200-IB-970) of a partialY-ring to a partial base gore was made under the surveil-lance of the Boeing Welding Engineer and the NASA Certify-ing officer. This was for the purpose of certifying the
I-5
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
26/413
91
_
-H i,iI
1-11 I PO I 0 rn
-1I-rl
5_ f-q
Z -11
C_ --I
0 Z -r --I
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
27/413
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
28/413
GORE TRIM MERIDIAN WELD BULKHEAD TRIM
FIGURE I-4 S-IC BULKHEAD ASSEMBLY, MICHOUD
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
29/413
ON1N
ON0dOn
O,Xn
I_
Q!
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
30/413
CxJO0L
0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
31/413
D5-1 5782
1.3 QUALITY AND RELIABILITY ASSURANCE1.3.1 Receiving Inspection (Raw Material)The incoming raw material from Wichita was thoroughly in-spected for damage, and the identifying numbers were veri-fied and recorded. The VSD's which were received with theraw material were carefully reviewed to verify complianceof the material with the mechanical, chemical, dimensional,and configuration requirements. The VSD's included:Shipping Documents, Data Transfer and Certification Re-cord, Certified Inspection Report and Test Results (Alcoa-mechanical properties, chemical properties, and ultrasonicgird chart results), contour maps, and thickness maps.Following the visual inspection for damage, the materialwas cleaned, dye penetrant inspected, cleaned again, thenprotectively wrapped and/or stored in a controlled atmos-phere area till ready for assembly.1.3.2 In-Process InspectionThe following brief outline depicts the types of inspec-tion performed on the various bulkhead assembly operations,and is indicative of the thoroughness of the quality controlmeasures utilized: Instl. of
Y-Ring Assy. of Fittings Fittings ....Non-Destructive Non-Destructive
X-ra_enetran t-ra_enetrant DyeDyeDimensional DimensionalOptical MechanicalMechanical
Visual VisualMiscellaneous Miscellaneous
Non-Destructi veX-rayDye PenetrantDimensionalMechanical
VisualMiscellaneous
Apex toBase Assy. Bhd L. Assy.
Non-DestructiveX-rayDye PenetrantDimensionalMechanical
VisualMiscellaneous
Non-DestructiveX-rayDye PenetrantDimensionalMechanical
VisualMiscellaneous
Y-Ring to Bhd.Non-Destructive
X-rayDye PenetrantDimensionalMechanical
VisualMiscellaneous
I-II
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
32/413
0C7
o"(D
0E
ctO
04_
0
.%ter
e
4_0t_
t_
o_
r
I>_
r__
0
"_
oo
_4c
_
_
t__
_
'_
(_
4_fr_
0
ec
c
4_
_0c
r_
_r_.tO
,
cXr__
_
0
.
-1o
U0OO010Or0Cr
'T
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
33/413
OJCO
0(O
or)V
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
34/413
CCrLLr_
O0ItYi
t.
I_
,.r-
E
E
"E-E_
0
E_
_-J
O
.E__
C"_
r_.03_
JO-_E
V
._r__O_
.
9-E_-_O
0
(:_il:i.r-c
_--
o'_0
(--
_C_
u0_,'_-
5_
u5
I(I;0.,-
I.L_:_
E.r--rY>CLC_0mL
5
0
:3L
0
VE
40"P.
E
E
OU_E
(_.p
O_
IE
E(_
O
__iEo
.EOO-J
O-_.(
4Oc
X
L_
EP"3
eOpCCrlJ
L
40
0_
*.
r_0
r_cIE
o
O
E
0
E
-r-"_'_04J
-r-
(J
_::v
r_
i_,_
(_o,--t_C
tl--
.r-:_.r--L
0
C_
O_r"-Cr_I
7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
35/413
OOr
IZ_-_IJ00#"m
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
36/413
D5-15782
1.6 ON-SITE REVIEW SUMMARY1.6.1 GeneralThe on-site, selected element review was conducted duringthe period September 3-6 as a part of the JSAT effort, bya group of materials and stress engineers selected to re-view the AS-503 aft LOX bulkhead history, in regard tomanufacturing techniques and quality control procedures.This review encompassed a study of: manufacturing se-quences and processes; MRB actions; handling and storagetechniques; quality control procedures and results; manu-facturing drawings; and engineering planning documentation.The actual hardware being manufactured at the time, wasfor a much later flight effectivity. The differencesbetween the current methods of manufacturing and qualitycontrol, and the methods employed during the constructionof the AS-503 bulkhead were determined and noted. Themajor differences noted between the current and the 503effectivity methods of manufacture are as follows:
The AS-503 vehicle had the solid Y-ring. At a laterdate tee stiffeners were machined into the Y-ringas an integral part of the base of the Y.The TIG welding process was utilized on the bulkhead-to-Y-ring weld during assembly of AS-503. The MIGwelding process is currently employed on this operation.This process utilizes a much faster torch speed, thuslessening the heat buildup and thereby reducing dis-tortion of the bulkhead.On the AS-503 aft LOX bulkhead assembly, the polarcap was installed by welding the polar cap to theassembled bulkhead (gores and Y-ring) with the Y-ring,supporting the weight of the assembly. At a laterdate this operation was accomplished by draping thegore/Y-ring assembly over a center support therebystretching the bulkhead by its own weight. This methodminimized distortion in the bulkhead following thepolar cap weld. At a still later point in time thecurrently used method was evolved. That is - the gore/Y-ring assembly is placed over a central support andstretched in a positive manner by pulling the Y-ringtowards the floor, utilizing turnbuckles, prior toinstalling the polar cap.All of the fittings on the AS-503 aft LOX bulkheadwere welded on the bulkhead. Beginning with the AS-504,
1-16
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
37/413
D5-15782
the fittings were machined as an integral part of thebulkhead segments except for the four (4) outboard LOXsuction fittings. The configuration of these fittingsis such that it is impractical to make them an integralportion of the gore segments, therefore, they are stillbeing welded to the segments.
Deviations in contour on gore segments were often correctedby aging the part within a restrained aging fixture.During construction of the AS-503, manufacturing was stillin the process of developing fabrication and assembly pro-cesses that would eliminate or minimize problems that hadcaused particular difficulty to that point. It was clearlyevident from observation of defect charts posted at thevarious weld operation stations that considerable progresshad been made by the time the AS-503 was built and thatprogress has continued to this date.A number of X-ray films were reviewed by the group. Theparticular films selected were chosen so that a detailedanalysis could be made of certain UER's. These films wereof gore-to-gore welds, apex-to-base welds, Y-ring-to-bulk-head welds and tee stiffener welds.1.6.2 Documentation ReviewedThe documents of prime concern to the investigating groupwere those involving manufacturing, inspection, and MaterialReview Board actions. The principal document developedfor governing the former two items was the MORTP (Manu-facturing or Testing Procedure) which spells out in detailthe manufacturing and testing procedures used in fabricatingand inspecting the individual parts. Additional documen-tation reviewed, which was utilized in the manufacturing andinspecting operations, was as follows: engineering drawings;welding specs (ABMA-PD-W-45A, ABMA-PD-R-27A, 60B32032,60B32004, 60B32009, MSFC Spec 135, BAC 8401, MSFC Spec130, MIL-T-5021C, 60B32514); cleaning specs (60B32002A,BAC 5749, BAC 5750, BAC 5765, BAC 5786, BAC 5745, BAC 5744,MSFC Spec 164); protective and wrapping specs (BAC 5034,BAC 5703, MIL-C-5541); identification specs (BAC 5307,60B00015, 60B32059); penetrant inspection (BAC 5423); heattreat (BAC 5602); forming, straightening, and fitting(BAC 5300); and VSD'So A substantial number of UER's,UER summaries, and UER data printouts were also reviewed.The UER is the primary document of TBC/MICH dealing withMRB actions. The group also examined the S-IC AS-503 De-sign Certification Review and the Manufacturing Plan.1.6.3 Conclusions
1-17
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
38/413
OJCOLOr_
Oq
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
39/413
!
(_ m r
!
m
-
I
m
O
r
_
-
_
__
"_
_
0
.4
r_
"o
,_
o
.4
! (31 O
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
40/413
OIC
0
t_!U
cOcr
__Q"
Ec_r
o
Xc
O
crOu_
cc
cOr_0
c_
_1-
!
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
41/413
OOLLr_
0irccio
co
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
42/413
D5-15782
VEHICLESTATION
1541 --
1420--
SKIRT
FIGURE 2-I. S-IC FORWARD SKIRT
2-4
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
43/413
D5-1 5782
INTERMEDIATERING FRAME
TUBUL#STRUT
INTERMEDIATERING FRAME
INTERFACE RINGFRAME
INTERCOSTAL
HAT SECTIONSTRINGERS ACCESS & UMBILICAL DOORSKIN SEGMENT ASSY.
FIGURE 2-2 S-IC FORWARD SKIRT
2-5
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
44/413
OC
Z
0
CP
r
i
0rrOr
O
O
O
O
00t00p-o90-04>>*crOc-0_QoOorOotO._
0>
-0
o
rO
,_
_.
0
O
40
_0
nO0c
4nO
c4_.4>
oo0
ErO4>
___m
j
_-_
_
4-O04-_0-0
--._o_
0r-'-
c01
g
t_-
.,--t
O-
e
J
"0_--0
_-_-t0
00o
_Ot_0
o0
0c0
c
4>
(10e
t.1__
0
0
c
c
_
_Oc
OCr._-
c
,0_c
-_-P_
0.4>
-
t_00
_,
cSt1_
01c._
0
-r-._0
0
t
IO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
45/413
D5-15782
The following MORTP's detail the assembly and inspectionoperations performed on the foregoing steps of assembly:60BI4009-1A-910, thru 922, 924, 925, 952; 60BI4200-IA-900;60B14220-I; 60B14325-I; 60BI4400-IA-900; 901; 60BI4400-3A-900, 901, 902, 903; 60BI4600-IA-900 thru 905; 60BI4009-1A-990, 950, 951, 954, 955, 956; 60BI4600-IA-950.
2-7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
46/413
CCIO%9(Z
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
47/413
!
l-rl
rrl
O
__
_-m
__D
O
OX
_
_D
F
fD
--'_.-'--'.-S
_
fD
O _IO_ O
r
_
Oi
O
fD__
fD
fD__ fD
__
__ _O_
IX
I
I O_
fD
_O _
fD ._ O
m o
rrl
PO O0
--_0
-_
0
_
--_.
0
_.
.-_
_-0
fD
-_0
_
-_
rsfD_-I-
-_
_.
fD
o__
_.
_-_
_-I-"-_
-_.
-__-_-
0
-_.
0
-_
e-c-fD
c-h0000
0
0
!
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
48/413
D5-15782
2.5 ON-SITE REVIEW SUMMARY2.5.1 GeneralThe on-site selected element review was conducted duringthe period September 3-6 as a part of the JSAT effort, bya group of materials and stress engineers selected to re-view the AS-503 Forward Skirt history, in regard to manu-facturing and quality control procedures. The reviewcovered: manufacturing sequences and operations; MRBactions; handling and storage techniques; quality controlprocedures and test results; engineering drawings; andengineering planning documentation.The actual hardware being manufactured at the time of thereview, was for a later flight effectivity. The differencesbetween the current methods of manufacturing and qualitycontrol, and the methods employed during the constructionof the S-IC-503 forward skirt were determined and noted.The major differences noted were:
a Difficulties experienced on the AS-501 andAS-502 flights, with the umbilical door,necessitated a change in the design ofthe closing mechanism and latch assembly.The door interfered with the umbilicallanyard cable as the umbilical disconnected,and remained open during flight. The im-proved design was satisfactorily tested,Reference 2.1, and a decision was made toincorporate the change in design on AS-504rather than AS-503 slnce time was a factorand the problem presented an acceptablerisk.
b . Titanium fasteners currently used, wereinstalled on S-IC-AS-504 and on.2.5.2 Documentation ReviewedDocuments of primary concern to the investigative groupwere those dealing with manufacturing, inspection, and Ma-terial Review Board actions. The principal document generat-ed for controlling the first two items was the MORTP (Manu-facturing or Testing Procedure) which details in step-by-step fashion the manufacturing and testing procedures utilizedin fabrication and assembly of the individual components.Other documents which were reviewed and which were used inconjunction with manufacturing and inspection were: engineer-ing drawings; identification requirement specs (BAC 5307,60B-32059); protective covering and storage (BAC 5034);
2-10
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
49/413
(MCrrm
E
E
E
O
E
O'r-
QD
.r-
r
_J
_
c
E
(D--
r_
E
"
"
c
rL
_.r--_
('-_
_
-r--
I
_,_-r--
(Dn:i(]JE
D(D
Ice_
r_>
_
_J.
(v_
"1:3(-(D
.r-E
c-Ooc-O
C.DCO
0
C_J
r---?
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
50/413
D5-15782
THIS PAGE LEFT BLANK INTENTIONALLY
2-12
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
51/413
I
I_
I
I11
_
r
c_
C_ __
-
-
m
_
C
i1
:_ -
:_
I11
_
r
! O P
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
52/413
CLO
mm
_
,,
-_c
_
c-_3-_
_.,--
(
_I:_c"O_
0
c-
c-,--.r-._--
__c
0c"
(_
,_
o
.
c-_
_
"_c-.)
OCO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
53/413
D5-1 5782
3.1 DESCRIPTIONThe LOX tank girth weld is the circumferential weld thatjoins the common bulkhead to the aft LOX bulkhead, asshown in Figure 3-I. The gore segments of the aft LOXbulkhead and facing sheets of the common bulkhead are 2014-T6 aluminum alloy. The bulkhead shells are fabricated from12 gore segments, and fusion welded by the TIG process using2319 aluminum alloy filler wire. The common bulkhead isan adhesive-bonded sandwich assembly which employs a fiber-glass/phenolic honeycomb core. Figure 3-2 shows thephysical relationship of the LOX tank, bolting ring, aftskirt, and lower LH 2 tank cylinder.
3-3
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
54/413
D5-15782
BULKHEAD
GIRTH WELDAFT LOX BULKHEAD
FIGURE 3-I S-II LOX TANK GIRTH WELD
3.-4
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
55/413
STATION.m.---1863
ISIN
STATION1841
BOLTING RING
AFT $KIR_T_
::::::::::::::::::::::::::::::::::::::::::.....-.-.-.>:.:..
: .,....?+.:::'-'q"'_::+"
1:110COMMONBULKHEAD
FORWARD FACING SHEET- INSULATION
AFT FACING SHEET
HEAYY GORE SEGMENTS
AFT LOX BULKHEAO .._
0"1I
0"1
coI"0
FIGURE 3-2 S-II LOX TANK, AFT SKIRTAND LH 2 TANK CONNECTION
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
56/413
0CLLtn
tS(c
z
"
F
c
(
0
r
0
I
"_
c"
(.-)
('_
0
I
-r--
E
ZZ)
_
0
Z
-
(-.)
r
_-
b-.
C'X.I
(".I
C_I
o_
"
.L
_c_>c
co40t
(-"_'_._
cqu4
_
!cY_
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
57/413
COMMON BULKHEADFORWARD FACINGSHEET12 GORESEGMENTS &DOLLARSECTION
CQMMONBULKHEADINSULATION
GORE FRAME
25 CONSTA NT
.050CONSTANT
0SC
2014-T6 ALUMINUM ALLOYFACING SHEETSWITH FIBERGLASS PHENOLICHONEYCOMB CORE
E:J(,_!...iC.Vl"-400IO
FIGURE 3-3 S-II COMMON BULKHEAD CONSTRUCTION
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
58/413
2014-T6 ALUMINUM ALLOYEXPLOSIVE FORMED AND
WELDED __ __;_< :_ i
AFT LOX BULKHEAD12 GORE SEGMENTS
BOLTING RING12 SEGMENTS
E_(5"1I
(J1O3
FIGURE 3-4 S-II AFT LOX BULKHEAD
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
59/413
OCLr
(_o9
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
60/413
D5-15782
FIGURE 3-5 COLLAPSIBLE WORK PLATFORM AND SKATE SAW
3-10
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
61/413
D5-15782
/- VACUUM CUPS
C.L. OFWELD
/
FIGURE 3-6 BACKUP BAR AND OFFSET TOOL
3-11
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
62/413
O0rLr_
EE_
O
(U
EE"_I
cCO
oe(UO
PE
%L-J
u4EEO
l__LL-
0
0
"_
9_cOCJp
_
-J-__
-O(U
c(1+
"
-O_
E
LrO0_
-JrO
4
__
e_0
0_(0.,-__
E-LE"_(_(__
X'E_
E
5-_0c-.p
_-_.r-
0
U
-O
.:__p
_OP
Er_
"O
.E
-Oc_E
_v-_(UEi0_O
_.P,.E__
-P
(0V
,_0(__
_
_-_-r-
(i__-I_
I0r_4
4c
U(_(U
.r-_-"_--
0_-
L
_J
_D_
c(_
_
(J-JO
I_0EL
_U
rIO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
63/413
C_O07
o_
L_
r_
Z
S-
ty"Do
_-
oq>
e
I--
v
__]
c-
_-_
0.f--
-J','
O-
e
c-c-o
_--
>
-.J
0
D
_J
C
r_"r
e
cO7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
64/413
i
i
O0rLLr_
ODP:E
>U
IGE
I
EL
*PEP
__
o(n
_(
-J
nS
V(_
-
_O
(U
-_
E_c"E
(J
O._
-_
.
.E
>
4
_r_0
0X-_
:>
_
-O
_O(D
"
.
O(-_
_
:3OE_
m
_
_I_
E
_
u-JO
_
_
_(1P.P_O
(D
c
ro.EE
_O
4
.-J
Q_
(_
-J
(D._
_
E9EO
V
O
(UO
t_
cE
.L
_
"O
v
__
_
.
r
_,
*O_
-EJ
.,--
E_"E
-E
(1-
r_
U
(D'E_
,--
_-0
(D
_-
c-_.r-
_
O_L
-O
._
-_
X
_
r_u
=._O
(1c
_E
O
c
0-
r--I_
N-
-_
>
X
O-Jr___,.E
rCO
-E
r_E-_Q.J
c
c
_-EO
_
_>
(_._
"E-JJJ
O
D
.r-
-I__
_
_
r_
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
65/413
O(3Orl:t--
ZLILlU--
O-OO"1--LO
If')COt---
or--or--
_)(/)(D
"O
cO._,
rO_m
cI
-_0(OrO
q-
(1)
I
O
c-_
r
tO
Of--
O
"
_.
_-
O
CO
_D_C-O
GJ
O._J
_O-O
_-)-
O
-_E0_.4-
(D
O
c-r
O
_-X
_-
E(D
O
OO
(D
LOCO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
66/413
OLL
4ot_4Ct_0roO4_I040
_
"
D
r
111
r_
i
.
(
4
r
e
0
1
I_
_
_
nocO.0O
kO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
67/413
!
!
m I
!
-
P
0 -
r_
! O
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
68/413
0O7
O'd
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
69/413
COLOLO
CO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
70/413
D5-1 5782
FIGURE 4-I S-II FORWARD LH 2 BULKHEAD
4-4
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
71/413
OCrLID
ZED(JiD0
vI__
U'z_4zI
,rOUtc
Oq
_.r-
qE
E00-04J
0
_
,--c
443_(Dt_
_G%
cc
c
LO_
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
72/413
(i)D5-15782
POSITIONLH2 BHD IN SADDLESPACERS ALIGN CYL. POSITION I TO LH 2 BHD POSITION I LEVEL BHD FOR TRIM-INSPECT PER ITI INSTALL UPPER VACUUM DETAILS - WELD
BACKUP BAR & APPLY INITIAL PRESSURE
S TON HOOK II!i
LH2 BH
\CYLINDER---_
FWD LH 2
LH 2 CYLINDER #6 J
FIGURE 4-2 POSITION LH 2 BULKHEAD IN SADDLE SPACERS
4-6
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
73/413
D5-15782
Q_TRIM OPERATIONLH2BHD, POSITION SKATE SAW - MAKE ROUGH TRIM VACUUM CHIPS CHECK FOR PLANE MAKE NET TRIM INSPECT TRIM
SKATE TRACK -_T-7200039
Yi
FIGURE 4-3 TRIM OPERATION LH 2 BULKHEAD
4-7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
74/413
D5-15782
Q WELD PREPARATION DROP BACKUP BAR PRESSURE RAISE BULKHEAD USING VACUUM DETAILS RETRACT BACKUP BAR CLEAN & INSPECT
FWD LH 2 BHD.
FIGURE 4-4 WELD PREPARATION
4-8
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
75/413
D5-15782(i) WELD0PERATION REINSTALL BACKUP BAR ALIGN TO WELD POSITION BHD: FOR DRAW FILING VACUUM & INSPECT POSITION BHD. FOR WELDING IT] INSPECT, NASA INSPECT APPLY BACKUP BAR PRESS 6,000 LBS.
HYDRAULIC PRESSURE SCREW JACKS IN EXCESSIVE OFF SET AREAS
& START INTERMITTANT TACK WELD REMOVE SCREW JACKS PENETRATION PASS REMOVE BACKUP BAR SHAVE INTERNAL WELD BEAD MAKE CONTINUOUS TACK PASS
nil ._
FWD LH 2 BHD.,,..._w./
#6 CYL INDER_._
FIGURE 4-5 WELD OPERATION
4-9
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
76/413
WELD COVERPASSOPERATION MAKE IN-PROCESS REPAIRS AS REQUIRED CLEAN-UP SHARP EDGES OF PENETRATION PASS, X-RAY & INSPECT - REPAIR AS REQUIRED INSTALL BACKUP BARS,
APPLY 5000 LBS. HYDRAULIC PRESSURE RUN COVER PASS MILL COVER PASS, BEAR-TEX & CLEAN-UP AREA DYE PENETRANT, INSPECT ALL ACCEPTED X-RAYVIEWS & CHEM FILM
INSPECT, CLOSE FAIR BOOK
WELD SKATE-----'-ZT-7200040 /
SKATE TRACKT-7200039 I
FIGURE 4-6 WELD COVER PASS OPERATION
4-10
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
77/413
!
/ " " _\ _HD "_ _ /TAPED VINYL (TWO PLY/ / _ NER" I _ BAGsAL_LA_OUNDA Vll_A RETAI "_A J_ I _ .RAISE BHD AFTER CUT, TOOL _ .VACUUM
|, - STANDARDSKATE - -- i 1%I TRACK & SAW SETUP I _
SECTION A-A
NYLON '
_ STRAPS_ _TWO-PLY
R -/_I VINYLJ/ll ;_, PROTECTIVEBAG ,
6-WAY-,SPREADER
BAR
STEPFWD.BHD.
CYLINDER #6
LH 2 FWD.BHD
CYLo #6 '-_ / _.SAWDRILL JI .
STEP
i CYLINDER #6
ROUTER SKATE
CY
FIGURE 4-7 SEQUENCE OF OPERATIONS FORREMOVAL OF DAMAGED BULKHEAD
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
78/413
O_COL_Lr
%(._
or-
D
r_
O'3I--
v
__
c-
_JW
c-
r-_
_-_
Z
c-._
CD"
r_rCO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
79/413
LMCrLL
O3
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
80/413
0OL
FZL.JLL00O"
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
81/413
O400L_
>-D23L
vr
uO7.%-OCCO_D
L7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
82/413
D5-15782
THIS PAGE LEFT BLANK INTENTIONALLY
4-16
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
83/413
O1 !
I1 I
I
11
z_
-
I
I1
O
C_
ID
I_
-
m
O
"
rT
:_
5
ID
o1
- O
-
-
fD i o1 0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
84/413
CO1.0t
r_GI_0
I_
_-r-
_
n_O-r-
___0__
OJILO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
85/413
OJCOLOTr)r
Z0--CLr_(__
or)rLO
or)ILO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
86/413
D5-1 5782
RING FRAMES
J _ _LONGITUDINALli(l..- "- _-_- --. HIP, _STIFFENERSJlIi ::'_i
!_ i ![;
I_ ..... -/,,|l :! /-' /-k ' _', , i ll
j____; : .... L_. _ll!!
FIGURE 5-I S-II FORWARD SKIRT
5-4
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
87/413
OOrTC
_QEDC_C_J
L
04Cc
,
_-_-
_0
,__b
r_r_0
(1"C04
r_r_,I
@)-_
c_x
_C
LOLO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
88/413
!Oh
LOCATETRINGERSKIN-DRILLTACKRAW _OCK PANEL SKIN ROLL STORAGE TRIM STORAGE RIVET
RAW STOCK STORAGE STRINGER STOCK EXTRUSION STORAGE
I STORAGE
END TRIM & ROll
LOCATE FRAMES TOPANEL ASSY. DRILl,. &RIVET COMPLETE.
GI SHIPTOSEAL J
BEACH & |
.STORAGE _j
FIGURE 5-2 S-II FORWARD SKIRTFABRICATION SEQUENCE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
89/413
D5-15782
T',,,
FRAME SUBASSEMBLY
SKIN SUBASSEMBLY ANDFRAME ASSEMBLY
COMPLETE FORWARD SKIRT ASSEMBLY
FIGURE 5-3 S-ll FORWARD SKIRT ASSEMBLY
5-7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
90/413
O0TO
Q.)
_
Z
_-
I--"
v
._j
c-O
.-J
(D
,,,
__c
r
_-4
Z>
.z--
l
>._
CD"
r_
C
C
LO
LO
O0LO
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
91/413
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
92/413
O0
Z,IIJ-
0-
c-o_
0
0-
I--
Co_
-r-
_0
I/3
LO
n_0
4Je-
lI_.Q
o._
oOc
0_.1ct
,0c
Ice_
O-_
c0i_
0___
0nOoO"Or_
E_
_O
c0e
r_eO
O__
0._
_r__
r_
__
_IL0
0c
|
I0_
,__
It_0
Oc
I
_J_
_cc.p
t_04
"_>_
o
cr(_(_
n.Q0
(V.h._
c_3"_o
(__
I
.Jc9u
"_
I=
,E"E
_
c_e
(U"EE4
(_,
O(_14
J:33
{1V
(1
r_(_
c
:3'=E
o(_-1_
(_,_c-C
,_Ov
(1
"_-
O
c,
,
-__
c(n
_0
q0Ec
OUl0
0
(_-
0-(0(_
OPO
$
:3:3I-J
0QG(
cEI-J
Ir_O(
(
"_c
c1
E
"
EQ
c
0
c-
(0._-
n_
E
c
0
_-_
c-(
I0
(UX_-
QC
o"c
O"P
.E-J,
(_-
cU
45
-_-J
-Ec
v_r:3
EC
UOE
-_,
E.p"_
c(1
-_O-_
_r_U
PII
VrL
(_"_
E_
LE
-EE4
I_O
O
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
97/413
0C7ZrrOLtZJ
ILp0
C
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
98/413
D5-15782
FORWARDSKIRTLH 2 TANK
LH TANKCYLINDERCOMMON
BHD
AFTSKIRT
LOX DOMEFILLET WELD*THRUST STRUCTURE/AFT DOME JOINT*
INTERSTAGE
* STRUCTURAL JOINTS
THRUSTSTRUCTURE
REVIEWED
FIGURE 6-I S-IVB
6-4
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
99/413
D5-15782
6.2 MANUFACTURINGIn order to appreciate the complexities of the two jointsin question, a description of the manufacture of the threecomponents involved is outlined.6.2oi Fabrication6.2.1.I Common BulkheadThe common bulkhead assembly is a two inch thick sandwichhoneycomb structure, Reference 6_I. It consists of a fiber-glass reinforced phenolic honeycomb core adhesively bondedbetween two hemispherically shaped domes per DPS 31150-I.The forward and aft dome assemblies are produced from 2014aluminum material. Each assembly is fusion welded (MIGprocess, DPS 14052) and consists of a contoured centerplate, nine gore segments, and a circumferential ringassembly. Figure 6-2 shows the common bulkhead and aclose-up of the common bulkhead/aft dome joint.The ring assembly is composed of three identical ringsegments fabricated from an extruded angle, formed on astretch die, and heat treated by aging to T6 condition.The three segments are joined by fusion welding in a weldfixture, then machined in a large boring mill.The forward dome segments and center plate are fabricatedfrom 0.125 inch thick sheet aluminum, and the aft domesegments and center plate from 0.133 inch thick sheetaluminum. Figure 6-3 shows the manufacturing sequencefor the common bulkhead.The adhesive bonding sequence subjects the entire assemblyof aft dome, honeycomb and bonding tool to a vacuum of25" Hg. and the bond is cured with heat (330F) and pres-sure (I0 psi) in a large autoclave. When cure is com-plete, the forward surface of the honeycomb is carefullyfitted to the contour of the aft face of the forward domeThe bonding sequence is repeated, with vacuum, heat andpressure to achieve final cure The seal weld completesclosure of the common bulkhead, and the final finish stepsare taken as shown in Figure 6-3.6.2oi.2 Aft BulkheadThe aft bulkhead of the LOX tank is a hemisphericallyshaped aluminum structure consisting of nine gore seg-ments, and various flanges, fittings and elbow assembliesThe nine gore segments are fabricated from 0.280 inchthick 2014 sheet aluminum. Forming of individual segments
6-5
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
100/413
CONTOUREDCENTERPLATE
HEAT RESISTANTPHENOLICHONEYCOMB-- UPPERDOMESEAL WELD
LOWERDOME
IBLINDBOLT
LOX TANKSEAL WELD
SEAL WELD
HUCK BOLT
!
O0
GORE SEGMENTS(9 PLACES)
ATTACHANGLE
AFT DOMESTRUCTURE
FIGURE 6-2 S-IVB COMMON BULKHEAD ANDCOMMON BULKHEAD/AFT BULKHEAD JOINT
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
101/413
I-.j
RECEIVE FORM DOME HEAT TREAT FINALSHEET STOCK SEGMENTS TO A.Q. STRETCH"O'" FORSTRETCHING." 'T3" FORBULGEFORM ING
ROUGH AGETRIM TO T6
_. IWEIGH!.._._ _ ___WELD SEAMS. TRIMTRIM STATION SEGMENTSPLANE, X-RAY
DEEP. ETCHMILL_ ,_
C ECK AND TRIM STRETCH RING" WELD DOMES MACHINE RINGS STRAIGHTEN SEGMENTSTO RINGS, X-RAY SEGMENTS SEGMENTS
MACHINE CENTER X-RAYPLATE OPENING.WELD CENTER PLATE
CHECK HONEYCOMB. SEAL WELDII'WEIGHL _F_--- IP'-_,._ - BOND BETWEEN RINGSMOVE TO
LOX TANK 4 I _i1"_---" _ i--'_ASSEMBLYAREA LEAK CHECKMACHINE RINGS
E_(J1I
(J3COr,o
FIGURE 6-3 S-lVB COMMON BULKHEADMANUFACTURING SEQUENCE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
102/413
OJOLLr_
(3SU--JScI0_
ot,"_0r"(1_00_x
4"0
UN
_m
{0
0-4-0
4_
_c
4r
c0
I"_
It_
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
103/413
!
STRETCH FORMRECEIVE SHEET 9 SEGMENTSSTOCK C'O'" FORSTRETCHING."'r3""OR BULGEFORMING)
---'___ LI_J ____- .OO_R,.__ _ _'_11 ...... NTSTRESS RELIEVE AND _ n_m_ ETCH CLEAN
CON DITION TO ""A Q'" FINAL STRETCH
9
ROUT CUTOUTS
_
ANODIZE ETCH MILL STENCIL CUT CURE MASKi AND PEEL
WELD FITTINGONE SIDE INVERT. WELDOTHER SIDE
TRIM GOREMERIDIAN EDGES
SPRAY MASK AGE TO T6
MAKE MERIDIAN WELDS.TRIM STATION PLANEAT EQUATOR.ovSSEMBLY AREA
" TRIM OPENING.WELD OUTLETS. WELD JAMBSTU DS. CLIPS
.
FIGURE 6-4 S-IVB LOX TANK AFTBULKHEAD MANUFACTURING SEQUENCE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
104/413
ELDING HEAD
BAR INWELDING POSITION
CROSS SECTION SHOWINGWELDING OPERATION
Oh!
O
DOME
!
COr_
MERIDIAN WELDER
FIGURE 6-5 S-IVB WELDING GORE SEGMENTSAFT AND COMMON BULKHEADS
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
105/413
07!
FABRICATE DETAILSAT SANTA MONICA
DELIVER TO TOWER COMPLEX
!
_ HANDLING,-PLACE ON HANDLINGAND STORAGE DOLLY
E_(._I(._"MO3
FIGURE 6-6 S-IVB THRUST STRUCTUREMANUFACTURING SEQUENCE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
106/413
!
.-...-..-_
LOAD AFT DOMEINTO WELD FIXTURE
i
LOCATE & HUCKBOLT BAFFLEASSEMBLY, WEIGH & SHIP TOSPACE SYSTEMS CENTER
LOCATE & HUCKBOLT AI-rACH ANGLE.INSTALL BAFFLE. LOAD COMMON BULKHEAD.DRILL HOLES & HUCKBOLT COMMON BULKHEADTO AFT DOME
X-RAY WELDS
41
WELD AFT COMMONBULKHEAD RINGTO AFT DOME
!
0-WELDORWARD COMMONBULKHEAD RING TOAFT DOMEFIGURE 6-7 S-IVB LOX TANK
ASSEMBLY SEQUENCE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
107/413
!,,,=JC_
AFT DoME
CROSS SECTION SHOWING AFT WELD
e
O OWELDING TORCH
LOX TANK/"
TANKWELD FIXTURE
SPECIAL FIXTUREFOR MAKINGINSIDE WELD
E_j'l!,_J(.T"McoPO
FIGURE 6-8 S-IVB LOX TANK-JOINING COMMONBULKHEAD AND AFT BULKHEAD
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
108/413
YELDING TORCH
TORCH POSITIONER
COMMONBULKHEAD AFT DOME
/
! CROSS SECTION:SHOWING FORWARDWELD . FIXTURE INHORIZONTAL POSITIONAS SHOWN
!...a
coP_
LOX TANKWELD FIXTURE
FIGURE 6-9 S-IVB JOINING LOX TANK ASSEMBLYCOMMON BULKHEAD AND AFT BULKHEAD
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
109/413
!
_--..._l_JN _LOAD TRANSPORTATIO ,___ _FIXTURE ON LOW _ _ _-_J_t fl'__-_,BED TRAILER ! llL_ ___/ "| I _F |_-'_T_
j 7t(_ TRANSPORT TO SSC
FIGURE 6-10 S-IVB SHIPPING LOX TANKTO SPACE SYSTEMS CE_ITER
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
110/413
D5-15782
6.3 QUALITY AND RELIABILITY ASSURANCE"Quality Control shall be in accordance with NASA NPC200-3 and applicable portions of NASA NPC 200-2 as definedin the Douglas Reliability Control Specification," Ref-erence 6.2.6o3.1 Receiving Inspection (Raw Materials)Raw materials are inspected for identification, damage,dimensional characteristics and evidence of non-destructivetests. All receiving paper is reviewed for the supplierschemical and/or physical test reports, test certification,material certification, etc., to the applicable specifica-tions noted on the purchase order. In the absence ofacceptable suppliers test data, MDC tests as required bythe applicable specifications In addition to the fore-going testing, periodic testing is performed by Q&RA per-sonnel on a prescribed random basis to assure accuracy ofsuppliers' test resultsAll raw materials requiring test are withheld pending com-pletion of these tests. Reliability assurance verifiesthat the requirements of the specifications are met.632 In-Process InspectionInspection procedures for fabrication, assembly and testoperations are an integral part of the detail manufacturingdocuments (A.Oo'S). Both standard and special inspectionprocedures are issued and controlled by the ReliabilityAssurance Department.All tooling is optically inspected at regular intervals,and realigned as required.Etch baths, chem-mill solutions and anodizing solutionshave their composition and concentration verified beforeuse.Welding personnel are certified and must be recertifiedat regular intervals. All welding is done under rigid cleanroom conditions, under personal supervision of a weldingengineer, per DPS 41006. Every step of the welding proce-dure must be signed off by Q&RA inspectors.Bonding technicians undergo intensive training beforebeing allowed to work on the common bulkhead. Refreshertraining courses are also required. Adhesive bonding iscarried out under rigid clean room procedures. Adhesivebatches are checked before use to verify age and bond
6-16
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
111/413
D5-15782strength, per DPS 31150-I. All temperatures, pressuresand vacuums are recorded and monitored.As indicated in Figure 6-3, 6-5, and 6-7, 100% x-ray in-.spection is carried out on all welds as standard procedure(DPS 15200, QCM 0008). In addition, all welds are examinedvisually under white light, black light and by penetranttechniques (DPS 15101, DPS 15105). Weld settings aredetermined in advance of production welding by running pre-production sample welds on production weight metal. Pre-production weld samples are subjected to full inspectionand tensile testing before production welding may proceed(DPS 14052).After welding, but before final bolting of the commonbulkhead/aft bulkhead joint, the assembly is leak testedby pressurizing the area between the two welds.6.3.3 Final Checkout and InspectionFinal assembly of the tanks of the S-IVB is accomplishedin the Tooling Tower complex at the Huntington Beachfacility. The assembled tank is proof-pressure testedhydrostatically in this building (Figure 6-II) then allwelds are again checked by dye penetrant techniques, perReferences 6-3 and 6-4.Following insulation of the LH2 tank interior, the tankassembly is returned to the Tooling Tower complex forattachment of skirts, thrust structure, J-2 engine, elec-trical and hydraulic systems. The procedures followed,with checkout points noted, are shown in Figure 6-12o
6-17
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
112/413
D5-1 5782
BRIDGE CRANE,
WORK PLATFORM_WORK LEVEL
WATER TANK
TANK ASSEMBLY --
FIGURE 6-11 S.IVB HYDROSTATIC TESTING
6-18
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
113/413
I.-
1. LOCATE THRUST STRUCTURE2. LOCATE AFT SKIRT
1 . DETERGENT CLEANHYDROGEN TANK
2. LOCATE PROBES3. SEAL
1. LOWER TANK ASSEMBLY ()NAFT SKIRT AND ATTACH
2. RAISE THRUST STRUCTUREAND ATTACH TO LOX TANK
3. LOCATE AND ATTACHFORWARD SKIRT
4. CHECK TARGET ALIGNMENT5. COMPLETE INSTALLATIONS
I. LOCATE ASSEMBLY IN TOWERAND ATTACH AFT HOIST RING
2 . INSTALL ENGINE VERTICALLYTHROUGH BASE
3. COMPLETE INSTALLATIONSBETWEEN ENGINE AND .VEHICLE
4. INSTALL AUX IL IARY PROPULS IONMODULES
5. CHECKOUT
1. REMOVE FROM TOWER2. LOCATE ON TOOLING DOLLY
_FORWARD AND AFT HFH'S AREALSO ROLL RINGS FOR PAINTPOSmON)
INSTALL PROTECTIVECOVER AND SHIP
_m ,---LOAD ON REMOVE WEIGHING J/b,CK UP ASSEMBLY,TRANSPORTER ROLL RINGS AND LOWER ON LOADINSTALL G.S.E. ROLL CELLS. WEIGH
RINGS
!.- LIFT FROM DOLLY.2. INSERT CRADLE.3. LOWER VEHICLE4. INSTALL WEIGHING
ROLL R INGS
PAINT
C
.D
'FIGURE 6-,]12 S-,1WB..FINAL ASSEMBLY
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
114/413
060f,..IX)
r
Z_.)rn
o_O
Ir_
c
_
0
_O
__0c._
_._-"_0
,ct_
>_.r-
c-_J
(OS
S
>
-_c-
_
Q
"
_
_
(D_E
(D
O
_3-_
O_LF)_,J
O
,0
(1:3Iu
00
OO
c-(/)(j
_
C_JU
LOJ
r_(_
_1
40
0S,=E0
-J_"_
0e
0(P
._E
>
O
Z
O
f0r_
C
(_
(
:3
_I
_(1
E0
i
-_E
OSEO_J
r
S
S
_O
E
4
4e_
O
0
:_
0
E
E_
.r-O
____.r.-S
_/Ic-
,
Or--
_.._
O4OO
_
S
(1_0
_r_._
c
0__--
_-
0
_.r-
_
_c.J
_
_,-_
I
(3,;0
-t_O
0
r-4c
O
:3
S0
o_f
(
0
0_-
__c-
0
Q
04
E
L44
(_O
.L
(_EO_
O
.EO
O
o0Et3:P
O.4"O
L:3_1
,
tO
Or--
_rY
c-
.
Z
_
(__Z
-I--}'-D
I0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
156/413
D5-15782
I0.I GENERAL - Continuedfor most of the non-structural parts. A few vendorsupplied non-structural items have not been revieweddue to delays in obtaining drawings
b Twenty structural parts have been categorized as"Stress Corrosion possible" or "Stress Corrosionimprobable (but possible)" based on maximum adverseconditions of manufacture, assembly, and environmentthat could be expected. These are presented in tabularform (in the final report) together with a listing ofexamination which has been made of these parts onvarious spacecraft s.
C No evidence of stress corrosion has been found in anyitem examined. A report (SD6B-740) is currently inprocess of publication covering the details of thesurvey including a list of the 1501 drawings reviewed.
quality Control ProceduresThe quality control procedures that were stipulated for themanfuacture of AS-503 hardware were assessed and foundadequate Quality control requirements are incorporatedin all manufacturing specifications. This includes thevarious aspects of fabrication and assembly from the procure-ment of raw material to the final inspection of flight hard-ware. Evidence that the quality control requirementshave been met is found in the NR Fabrication and InspectionRecords (FAIR Books), wherein the disposition of discrepan-cies in the structure is described. These discrepancydispositions are the result of Materials Review (MR)actions which are described below. Provisions for AS-503quality assurance are typified in the descriptions of qualityassurance provisions for the CM and the SLA, presented in theappropriate sections which followThe assessment of the impact of Material Review Board (MRB)action on the selected critical elements is described inthe JSAT Spacecraft As-Built Capability Document, D5-15781.A report of a complete review of MR's that pertain to theAS-503 spacecraft structure is contained in Boeing/HoustonDocument D2-I18158-I, "AS-503 jSAT/ASSAT SpacecraftMaterial Review Assessment". This latter document is therecord of the Joint Structural Assessment Team (JSAT) andApollo Spacecraft Structural Assessment Team (ASSAT) reviewof the North American Rockwell Company (NR) Material Review(MR) documents that describe dispositions of discrepanciesthat were found in the AS-503 spacecraft structure
10-6
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
157/413
D5-15782I0.I GENERAL- ContinuedApproximately 2500 MR dispositions were contained in the787 MR documents that were reviewed. After assessing andevaluating each disposition, 2404 were determined to beadequate and 96 were determined to be questionable. These96 dispositions were referred to JSAT stress for in-depthanalysis and resolution. The stress analysis verified theadequacy of the 96 questionable dispositions. Thus, the2500 MR dispositions that were reviewed were all finallyassessed to be adequate.These MR review results were used by JSAT in the final assess-ment of the flight readiness of the AS-503 Spacecraft.The purpose of the review was to verify the adequacy of thedispositions of structural discrepancies that are describedin the MR documents. At the outset the intent was toassess only those MR's that pertained to primary structure.However, the review encompassed not only all of the pri-mary structure MR's but virtually all of the secondarystructure MR's as well. Particular attention was givento the potential impact of MR's on previously identifiedselected critical elements.The objective of the review was to assess the impact of theMR dispositions on the strength of the Spacecraft structure.The original configuration of the AS-503 spacecraft structurewas composed of five modules that included a SpacecraftLunar Module Adapter (SLA-II), a Service Module (SM-I03),a CommandModule (CM-I03), a Launch Escape System (LES),and a Lunar Module (LM-3). The plan was to assess theMR's that pertain to each of the above modules. Coincidentwith a change in the mission requirements for AS-503,a structure (LTA-B) which simulates the mass of a LunarModule was substituted for LM-3. The flight worthinessof LTA-B was assessed to be adequate by inspection methods.There are no MR documents pertaining to this simulatedspacecraft module. With the elimination of the require-ment to assess the LM, this AS-503 ASSAT/JSAT SpacecraftMaterial Review assessment was accordingly limited to theSLA, SM, CM, and LES.The MR review was conducted in three phases, as follows:Phase S/C ModuleI SM
II CM/LESIII SLA
LocationDowney, CaliforniaDowney, CaliforniaHouston, Texas
DatesSept. 3 - Oct. 4, 1968Oct. 15 - Oct. 18, 1968Oct. 22 - Oct. 26, 1968
10-7
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
158/413
_rT_
CO0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
159/413
CO1.0
G#oi--
>
..,-_,E_--_;_._.ATERIAL USAGE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
173/413
Inconel 718, 7075-T6BELL CRA!
Alclad 2014-T652 Outer Face5052-H39
2014-T651 Plate Inner F.Sand Built-Up Edge
COMMANDMODULE TUNNEL PRESSUREEQUALIZATION AND INDICATOR VALVE
7075-T6 Plate (Center)nd Bar (Support)
A-286 (Bushings)
Housing 2024-T351Gears Inconel 718GEAR BOX
Ti-6AI-4v
2024-T4Spring 17-7PH
7075-T6
Button Spring302 SS
A286 End Fittings(Typ)
7075-T6HANDLE IN STOWEDPOSITION2024-T4
PLUNGER 2024-T4Incl 718Spring 302 B Wire
ROD ASSY (Typ)2024-T3 Tubes (7)
!
CO
Figure lO-12 TYPICAL FORWARD PRESSURE HATCH MATERIALS
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
174/413
VENT P,ORTPURGEA-286
Corning 1723 Aluminosilicate GlassFrame 2024-T351, 7075-T651Retainer 2024-T351Flange 7075-T6BOOST COVERRELEASE FAIRING
(jm!
OoixJ
AblatorOutside
Inside Slab 2014-T6522014-T652 FG FRAME
HATCH DRIVE PENETRATIONFiberglass Honeycomb BetweenAluminum Slab and Ablator HINGE
BOOST COVER
Figure 10-13 TYPICAL UNIFIED HATC_ AND BOOST COVER MATERIALS
!
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
175/413
Shell StructurePHI4-8 Mo Face SheetsPHI4-8 Mo Honeycomb Core RING ASSEMBLY 321 Stainless Ann.
71 78-T,!
C_
HANDLE ASSEMBLY(OPEN POSITION)
HANDLE ASSEMBLY(STOWED POSITION)
Figure 10-14 TYPICAL ABLATIVE HATCH MATERIALS
Inc 718A-286
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
176/413
3
CC
Lr
9U
N3
9N
N
9U_
0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
177/413
DROGUEASSEMBLY.--,
_Inconel 718 Hook201 4_TR_B_ap\
DOCKING RING (CM)
Inconel 718Ti-6AI-4v
Latch Fittings A286Base 2024-T4Fiberglass
+Z17-4 PH PLATE
I0'3CO
2014-T6 CYb2014-T6Inconel 718
Inconel 7182014-T4 Collar-- .
l!JH SSEMBLIESInc l" 718 ShaftTi-6AI-4v Yoke
Figure I0-16 DOCKING SYSTEM MATERIAL USAGE
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
178/413
SEA RECOVERYCABLE
Cable 301 SSBar Inconel 718Plate 7075-T6
Y
DROGUE PARACHUTE MORTAR
LES TOWER ELECTRICALRECEPTACLE
Flower Pot Ti-6AI-4vBeams 7079-T652
PARACHUTERISER PROTECTOI
Mortar Supt.7075-T6PILOTMORTAR, Cap 7075-T6
MAIN LANDINGRetention Frame 7075-T6
RCS ENGINE PROTECTOR7075-T67075-T651
DYE MARKER AND SWIMMER UMBILICALHF RECOVERY ANTENNAUPRIGHTING BAGS
UNDER MAIN PARACHUTES (3 PLACES)Tiedown Fitting 7075-T651
!..=a
CO
Figure 10-17 LES- EQUIPMENT MATER!AL VSAGE
!,t
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
179/413
IMPREGNATEDFIBER GLASSLAMI NATEMBO130-O04V36-321278
f/
BONDEDAL HONEYCOMB\ 5052-H39 CORE
_---.- I NNER ML
17-4PH CRESSTEELMBOI60-018V36-321280
V36-310001 (REF)
" " "X_ OUTER-286CRES EELMB01_-029
\ V36-321279Ti-6AI-4VCOND. AV36-3212/5(REF)lO15-T651/QQ-A22519V36-211006
',_..-.--V36-320001REF}
ML
Figure 10-18 INNER TO OUTER SHELL ATTACHMENT MATERIAL USAGE
CZ_(31
C_COr,O
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
180/413
D5-15782
10.3.2 ContinuedAdhesive Bondin 9 (Continued)Tie Brackets, Doublers, Etc. to Apollo Spacecraft."0606-006 will be discussed first.
MA
The primers, adhesives, and fillers for use with MA 0606-006 are epoxy-based. The primers are MB 0120-032 (Pitts-burgh Plate Glass M-602 for -423 to 300F), MB 0120-047Type I (Am. Cyanamid HT-424B or Adhesive Engineering Aero-bond P-413 for -423 to 180F), and MB 0120-047 Type II(Am. Cyanamid HT-424F, or Adhesive Engineering AerobondP-413 for -300 to 300F. and short time to 500 F _.MA 0606-006 makes use of four adhesives. MB 0120-048, theprimary structural adhesive for honeycomb panel fabrication,is an epoxy-phenolic glass tape supported adhesive for-423 to 500F service (HT-424 or Aerobond 430). For core-to-core splicing and for core-to-edge member or insertbonds, a thixotropic HT-424 paste, MB 0120-026, is usedfor -423 to 300F, or short time to 500F service. Itis dyed blue to distinguish it from MB 0130-030. A foamingtype adhesive, MB 0120-030 (HT-424, Type I) is used insteadof the thixotropic paste where the core density is 4.4 lb.per cu. ft., or less, or where little or no pressure canbe obtained during cure. It is also used as a stiffeningmedium to prevent edgewise collapse of core cells wheninserting into channels, etc. As an alternate to thefoaming type adhesive, a mineral-filled epoxy, MB 0120-037(Epon 954, Reliabond 377), may be used to rigidize coreedges. It is room-temperature curing. Figure lO-19 showsexamples of adhesive selection.For filling exposed core edges or core cells, where speci-fied, three types of fillers are used: Type I consistingof lO0 pbw MA 0120-039 (Am. Cyanamid Corfil 615) and 14pbw Apco 320 hardener (Applied Plastics), Type II made upof 50 pbw LB 0120-012 (PPG Bondmaster M611/CH60) and 50pbw Buehler 15-57AB alumina powder with 7 pbw Apco 320,and Type Ill composed of lO0 pbw, MB 0120-039 with 7.5pbw red di-ethylene triamine.
Details are fabricated for bonded honeycomb sandwich perLA 0102-004; surfaces are prepared for bonding per MA 0110-024; and process controls such as solution control, ad-hesive validation, production peel tests, etc., are coveredin MQ Ol03-OOl. The specification itself, MA 0606-006,includes general requirements, detail requirements, andquality assurance provisions.
I0-30
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
181/413
D5=15782
ORE OUTERSKIN MB 0120-048 I (HT424, AEROBOND430, FILM)J CORE-EDGE-
__MBER/ ............ COREPL,CE'---"
INNER WELDEDSKIN WELDMB 0120-030 (HT424FOAM)
"MB 0120-026 (HT424THIXOTROPIC PASTE)ORMB 0120-030 (HT424FOAM} DEPENDNG ON
COREDENSITIES
Figure 10-19 EXAMPLES OF ADHESIVE & FILLER SELECTION BASED ONMA 0606-006 ADHESIVE BONDING SPECIFICATION
lO-31
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
182/413
CCI.
I.Ot
_IJ
c-
c-
E
--
(
0
0Or
c
O
(D
I
rO
uO_
l
0_
___c
.
_O
,
0
0
0
-
_'
_.,--C
4-__
0_0
c
,__.,--
-_J,oO_--_E_
0
C
,
c-(lJ0_
_c!
"00q.J
rOc
_.
c-
0
._
.
_
__
-0
0
c-
_I_
.,-_---I_
c-_"_
,
.,-
I0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
183/413
D5-15782
I0.3.2 Continued
InsulationThe insulation blanket installed between the inner andouter structure is an aluminum faced silica fibre matteknown as TG-15000. The heat shield ablative materialapplied to the surface of the PHI4-8Mo honeycomb sandwichof the outer structure, is AVCOAT 5026-39HCG. This isan epoxy-novolac with phenolic micro-balloons and randomsilica fibres in a phenolic fiberglass honeycomb. Thephenolic honeycomb is bonded to the brazed steel honey-comb sandwich prior to filling with ablative material.10.3.3 CM Quality AssuranceQuality Assurance covers process control specification,method of tool proofing, adhesive and filler evaluationprior to use (including peel and tensile strength require-ments and others for MB 0120-039, MB 0120-012, MB 0120-030,MB 0120-030, and MB 0120-026), production testing (includesrunning test coupons with each production part - lap shear,if only metal-to-metal bonds; both lap shear and honeycombpeel if honeycomb bonds present - placement of test couponsand minimum test strengths; however, test coupons for foamand thixotropic adhesives not required), visual inspection(including adhesive primed surfaces and bonded parts),ultrasonic inspection ("where practicable," includingrejection and drying requirements), sonic inspection (taptest where ultrasonic impracticable), X-ray inspection(core-to-core splices and core-to-edge member bonds singlestage only to check maximum foam splice line width, coresplice intersections, and repair of both), bondline thick-ness control, metal-to-metal adhesive defect inspection(visual for edge and corner lack of adhesive), and main-tenance of records for each production part.Radiographic inspection is controlled by NR specificationMQ 0501-007 and ultrasonic inspection by MQ 050-010. Oneof the most important of the quality specifications iscalled out by number on drawing MQ 0501-026, "ProductionQuality Verification (PQV) Testing of Apollo CommandModule Inner Structure Adhesive Bonds." This specificationpresents methods to locally destructive test productionhardware to determine the strength of primary adhesivebonds Four Block II tests are described: (I) face sheet-to-core tension (Tc) , (2) metal-to-metal tension (TM),(3) metal-to-metal shear (SM), and (4) metal-to-metalPorta Shear. In the first three types, small grip piecesare bonded to the test surfaces, the test areas are tre-panned by cutting through the skins and into the primary
10-33
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
184/413
D5-,15782
I0.3.3 Continuedbonds to isolate the areas, and the loads applied by suit-able calibrated equipment In the Porta Shear test a hollowcutter is used to cut through the metal and bond line andthe shear load is then applied directly to the remaining cir-cular piece of bonded metal. After testing the damagedareas are repaired.Sketches define the locations of all test areas on the CMinner structure. Tables define the specimen types, loca-tions, and loads required for the forward bulkhead, forwardsidewall, aft sidewall, aft bulkhead, and bellyband. Thenumber of tests to be performed are 16 TC, 4 Tm, 16 S , and21 Porta Shear, although current practice has eliminatedSm in favor of Porta Shear. These numbers are reduced to5, 2, 5, and 5, respectively, if two successive spacecrafthave met the P&V requirements of the more extensive testsequence.MA 060_014, "Secondary Bonding of Stringers, Tie Brackets,Doublers, Etc., to Apollo Spacecraft" makes use of boththe MB 0120-032 primer and the MB 0120-048 adhesive pre-viously mentioned plus the MB 0120-053 high peel adhesivefilm (Am. Cyanamid FM-123-2). All CM details are requiredto be primed except shims which do not have to be primedif they are bonded within 24 hours after cleaning. Processverification coupons are run with the assembly when re-quired by Quality Assurance This option of process verifi-cation coupon testing could be a weakness in the specification.The two quality specifications in MA 0606-014 are MO 0103-001 and MO 0501-024, the former being a general processcontrol specification and the latter being specificallydirected to the testing of MA 0606-014 bonded members.MQ 0501-024, "Verification Testing of Apollo SecondaryBonded Structures" is a 117 page document which shows indetail by means of sketches how each member such as chan-nels, tees, and brackets is tested by using appropriatetorque wrenches or tension scales with tools to grip themember under test. Test loads are those given on theengineering drawing.In summary, it is difficult to pick an obvious weak spotin the adhesive bonding procedures. The adhesives arewell known and acceptable. The specifications appear tobe complete in their requirements for handling bondingsurface preparation, validation procedures and storagelife, and temperatures for primers and adhesives, fitchecks, process validation test coupons, etc. The useof PQV (Production Quality Verification) testing (MQ 0501-026) of the honeycomb panels and the verification testing
10-34
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
185/413
D5-15782
10.3.3 Continuedof secondary bonded structural members (MQ 0501-024) de-notes the extent to which quality assurance checking hasbeen carried; although, of course, such tests are still inessence only sampling the structure to increase confidencein its reliability. PQV test reports for CM's No. I08,I09, and llO were reviewed. In general, the test resultswere excellent with only two material review actions beingrequired.The problem of degrading the strengths of some heat treatedaluminum alloys during bonding cure cycles was discussedwith NR M&P allowables people. They were aware of thepotential problem and claimed that necessary steps weretaken to keep the designers informed and that degradedallowables were issued where necessary. Also, they indi-cated that they survey repair or rework bonding thermalcycles for the same reason.Another potential problem area, that of the designer callingout the wrong specification for adhesive bonding (therebeing five MA 0606-XXX and five MA OI06-XXX specificationsfor adhesive bonding) was discussed with M&P. They indi-cated that the designer generally comes to the Project M&Pgroup for consultation. Also, the Project M&P group re-ceives one of four courtesy copies of all drawings forreview. However, M&P does not have drawing sign-off rightsand cases have occurred apparently where a drawing wasreleased before M&P had reviewed their courtesy copy.No amount of quality control nor sampling plans can sub-stitute for good workmanship. This may be a problem areawhich could cause some trouble inasmuch as it is understoodfrom NASA inspectors that (1) NR has no formal trainingprogram for shop bonding personnel and (2) periodic layoffsresult in "bumping" which permits less qualified personnelwith seniority to replace bonding shop personnel. Thislatter situation results in a measurable rise in bondedassembly rejections. It is conceivable that a greaternumber of marginal, or inadequate, parts are accepted des-pite the quality assurance provisions when "bumping"occurs,
One area of concern is the inadequate control over adhesivebonding process variables typified in the notes on drawingnumbered V36-311001. This drawing authorized options re-sulting in bondline thicknesses up to 0.024 inches. TheNR design allowables limit bondline thicknesses to 0.012inches maximum. The NR document QEL-NMP-103-98, datedOctober 31, 1963, titled "Results of Lap Shear Strength vs.Glueline Thickness Tests," concludes that "gluelines"
10-35
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
186/413
D5-1 5782I0.3.3 Continued
for the HT 424 adhesive system below 0.014 inches willgenerally produce adequate bond strengths, which is inagreement with the NR allowables. Figure I0-20 obtainedfrom the above document demonstrates that increasing thebondline thickness from 0o012 inches to 0.024 inches de-creases lap shear strength at room temperature by 30 percent and causes a 25 per cent reduction from design allow-able.AllowablesThe allowables used for the CM were obtained from MIL-HDBK-5, North American Rockwell (NR) Structures Manual, and NRMaterial Producibility Bulletins 16, 44, 45, 46, 48, and 49.The allowables used for the PHI4-8Mo brazed honeycomb werenot available for assessment of this structure since NRconsidered these data proprietary.
I0-36
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
187/413
D5-15782
4O
322824
201612S4
MINIMUM REQUIREMENTR.T.
'"
R.T,i2 4
i i8 I0 12 i4 16 18 20 22 24 26 28 30 32 34 36BONDLINE THICKNESS x 10-3 INCHES
Figure 10-2o HT-424 ADHESIVE SYSTEM
10-37
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
188/413
D5-15782
I0.4 CM LONGERONSlO.4.1 Design Adequacy Review
The reason for selecting the longerons was based on the lowfactor of safety reported in the NR analysis (F.S. = 1.53)coupled with the fact that the plastic bending part of theanalysis was incorrectly handled. The analysis erred incomputing the plastic bending section factor and in cal-culating a factor of safety based on stress allowablesrather than based on bending moment allowables as is therequired procedure for unsymmetrical sections (conserva-tive in this case).The longerons appear to be the controlling element ofXA I083 interface capability for both liftoff and engine-out loads. Using the same internal loads, the plasticbending analysis was corrected with the result being thatthe error in the conservative direction was over-ridingand that the factor of safety increased to 1.62. Thecorrected analysis demonstrates a higher factor of safetythan was reported in the stress analysis. A summary ofthe review is presented in Figure I0-24.
I0-38
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
189/413
D5-15782I0.5lO.5.1
CM/SM INTERFACE XA lOlODesign Adequacy Review
The X^ = lOlO interface is made up of six radial beamtrussBs, six truss load pads, and 3 CSMtension ties. Theoutboard leg of the Radial Beam #3 Truss was selected asthe critical element since the analysis indicated negativemargins-of-safety in that area. Both the load pads andtension ties have been adequately demonstrated by test.Boeing analysis is in close agreement with the NR analysis.The conclusions as to the criticality of the Radial Beam #3Truss are the same, both indicating an analytical factorof safety of about 1.47 for the AS-503 C-Prime flight loads.The comparison is shown in Figure I0-25.There has been no structural test performed which adequatelydemonstrates the ultimate capability of Radial Beam #3.However, because of the similarity between Radial Beams #1and #3, the ATR 222013 test demonstrates a Radial Beam #3factor of safety >l.4O for the AS-503 C-Prime loads.Radial Beams #2 and #5 will be tested for engine-outloads before the AS-503 flight, and since Radial Beams #3and #5 are similar, it will then be possible to determinea new test factor of safety for Radial Beam #3.I0.5.2 SM General Materials UsageThe SM outer structure is a one-inch thick, cylindrical,bonded aluminum honeycomb sandwich shell. This shell con-sists of four basic panels which are attached to sixradial beams and to the forward and aft bulkheads, plusfour smaller reaction control system panels. Except forthe radiator panels, the outer face sheets are 2024-T81,the radiator panels outer face sheets being 6061-T6.The inner face sheets are 7178-T6. The honeycomb coresare 5052-H39 in two sizes, i.eo, 3/16 x 0.0007 and 3/16 x0.0015. The structure is bonded with epoxy-phenolic adhesives.The inner structure consists of the six radial beams, forwardand aft bulkheads, equipment shelves in one bay, and thevarious hardware associated with engine support, tank support,etc. Except for the bulkheads and shelves, the materialused is generally 7075-T6, -T651. Some 2024-T3, -T4, -T42,and 2014-T6 are used also, but less extensively. The equip-ment shelves and forward and aft bulkheads are of bondedaluminum honeycomb structure.The radial beams are machined and chem-milled from singleplates of 2-I/2 inch thick 7075-T651 per NR specificationsMA 0103-005 and MA 0103-004, respectively, to webs as thin
I0-39
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
190/413
C_JCOPITrm
(_I
c--_3
c-i
c_c-
_-0
-
t_t'ML
"r-
(;j,--c-
r
c-0
t/1(_I
r_
-r-(I,)
r_
_n_
o
q-
,o
_
_.-
_o
E
_:L
_"
0
c(f_I_
_ID_
4
_"
O_
0
c-_,--
-_
%
O(1E
4O
'_
N(11_-E
O
E(D_
O
V_c
_
_cE
-a_
-D
EE
_EE
PUO_
O
--a-J
___C
>
r-J_
V9
O0
ODL.J"_
>cIM,11
I_4L-_e
c0cO
O
:
c-
(D
E.r-
,--(I,)
_J0
c-
,--.u
_
(I_v
(D_'13.r-
-C_
,---I::::__
U.r-_0
O-
_--
I_j
r_
_
,
E
E:D_
0
0
_
O
9_
,3(D
(0_
(1_.(_c-
,(_uO
_
O'_(_-_t_
tOc
Qt_>_
4T_-_cOM
_
(
t_I__0-c(
_
(_
00
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
191/413
D5-15782
OUTER SHELL PANELS(EXCEPTRAD IATORS)2024-TBIFACE SHEETS (OUTER)7178-T6FACE SHEETS (INNER)5052-H30CORES7075-T6CLOSEOUTS,.ETC.
BEAM NO. 2
FORWARD BULKHEAD (6PANELS)7178-T6FACE SHEETS5052-H39CORES7178-T6DOUBLERS2024-T3DOUBLERS 7075-T6CLOSEOUTS
BEAM NO. I
BEAMNO. 3
BEAM NO. 47075-T6, T651FRAMING (TYP)2024-T3DOORSCTYP)
"_'BEAM NO. 57075-T651(ALL BEAMS)
BEAM NO. 27075-T6
+ZBEAM NO. 3
BEAM NO.-Z 6
BEAM NO. 4
Figure
_y 1075-T652 I RINGSAFT BULKHEAD 7075-T6FITTINGS7178_T6FACE SHEETS5052-H39CORES7075-T6CLOSEOUTS, CAPS, ANGLES, FITTINGS,ETC.
10-21 TYPICAL SM MATERIAL USAGE
lO-41
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
192/413
3
Ioi
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
193/413
D5-1 5782
7075-T651 ' '7075-T6
2024-T3# II II I
HORIZONTAL ENGINEMOUNT WEB.ALL 7075-T6
RADIAL BEAM7075-T65!MACHINED &CHENFMILLED
\
7079-T652
X2 200.00ENGINEMOUNTASSY
BEAMNO 6
Figure 10-23 TYPICAL MATERIAL USAGEENGINE MOUNT ASSEMBLYIN THE SERVICE MODULE
10-43
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
194/413
ITEM OF COMPARISON
ENVIRONMENTLOADS
Limit Loads atXc I083 Interface
ALLOWA3LE
ASSUMPTIORSMINIMUM FACTOR OF SAFETYFAILURE NODE
COnTraCTOR
Room TemperatureM = 1,03 x 106 in-!bs.P = |22,0_0 Ibs.
JSAT
Room TemperatureH : 1,03 x 106 in-lbs.P : 122,000 ]bs.
FTU:60,000 #/inZFBU = 87,550 #/_n2Plastic b_n_ing
3.53Be_}ding & tension on _nner capat Sta. Xc = 71.5
FTU = 60,000 #1in 2" = 139,500 _n-lbs.'"ALL
Plastic b_nding1.62
Bending & Tension oninner cap at Sta. X c = 71.5
FIGURE 10-24 SELECTED _L_, ,ENT _,_ J_,_ DATA CO,, ,PA, ,IJON - CFI LONGERON
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
195/413
ITEr-! OF COZ:_PARISO_
ENVIRONME_LOADS (I MTE_NAL)
LIMIT
CONTRACTOR
Not applicableCompression Pad Load
Pc = 21060#Loads in Outboard LegP = -_4479=V = 871#M = 9281 in_Ib
JSAT
Not applicableCompression Pad Load
P _ = 21060#Loa_ in Outboard LegP : -24479#V = 871 #M = 9281 in-lb
ALLOt.tABLE
ASSUHPTIONS
M[RIMUM fACTOR OF SAFETYFAILURE NODE
Comp. Pad Allowable Pcu = 31000#Leg a]lowables
Fcc = 58390 psi,Fsu = 41000 psiMu = 37170 in-lb
1. P]astic bending in trussmembers2. Moments fro_ beam-colL_neccentricities neglected
1.47Interaction of shear, bending, andcompression stresses in outboardleg
Comp. Pad Allowable Pcu : 31200#Leg allo_cab]esFcc = 5_000 psiFsu = 42000 psi_ = 36900 in-lbI. Plastic bending in truss members2. Moments from beam-column
eccentricities neglected1.48
Interaction of shear, bending, andcompression stresses in outboard leg
.... FIGUEE 10-25 SELECTE_ ELEHENT _EV!EW DATA COHPAR!SOt: - CMISM [NTERFACE 1010
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
196/413
J
VVODVV9
oc
r
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
197/413
D5-15782
7075-T6
6061-T6
-Phenolic Laminate2024-T81
5052-H39 CoreSplice
Glass-Phenolic Laminate
--Glass-Phenolic Honeycomb CoreGlass-Phenolic Laminate
7075-T6Cork
?O7_2024
5052-H39 7178-T6
;-T67178-T6 Doubler'178-T6
5052-H39 Core
7178-T6
Figure 10-27 TYPICAL MATERIAL USAGE, FORWARD BULKHEAD -OUTER SHELL PANEL - CSM FAIRING AREA(ALL FASTENERS NOT SHOWN)
10-47
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
198/413
D5-15782
202h-T81
_052-H39 Core
7178-T6
7075-T6
5052-H39-Core
., iiI I, /:h ,,
I _.jl
Figure 10-28
Q
II
-_---- SLA
-- 7178-T6
_----7075-T6
-_---7075-T6
7178-T6
TYPICAL MATERIAL USAGE, AFT BULKHEAD -OUTER SHELL PANEL JOINT AREA (FASTENERSNOT SHOWN)
I0-48
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
199/413
D5-15782
I0.5.2 SM General Materials Usage - Continuedpeel process verification test coupons are run with pro-duction parts- honeycomb tensile specimens not being required.In general, the specification appears to be quite thoroughin its coverage, being similar to MA0606-006. Test couponsare required to be run simultaneously with each productionpart to verify the bonding process. Also, production qualityverification testing (a distinctive test of a small areaof an actual production part to determine adhesive bondstrength) is required. For example, the aft bulkhead draw-ing, V37-329810, requires eight Porta-Pull (tensilestrength of honeycomb to face sheet bond) and two Porta-Shear(shear strength of metal-to-metal bond) tests. A check ofother drawings shows single Porta-Pull tests usually arerequired for the various outer shell panels, although theforward bulkhead panels and shelves do not appear to requiresuch tests.FinishesPart finishes generally are called out on the drawing byreference to V14-000-24, "Finish Specification ApolloSpacecraft" The standard finish for most of the SM isa chromate conversion coating per MAOI09-O03, "Applicationof Chemical Films to Aluminum and Aluminum Alloys" (MIL-C-5541), followed by one coat of clear epoxy. The chemicalfilm constituents are either Iridite 14-2 or Alodine 1200S.Typically, this finish system is called out for the aftbulkhead, the forward bulkhead, the three shelves supportingthe fuel cells, etc., the radial beams, the inside surfacesof the outer shells, and the outside surfaces of the outershells except for the radiators and non-aluminum alloysurfaces. The radiators have a white inorganic temperaturecontrol coating, MB 0125-031, applied per MA 0108-022.Some of the smaller aluminum alloy parts, especially wherepainting would interfere with their function, are sulfuricacid anodized. The CM/SM tension-tie bolts (4340 steel)are given a nickel-tin plated finish per MB 0125-041which appears to have adequate hydrogen embrittlementrelief coverage. Where aluminum and titanium alloys arein contact, special precautions are taken, e.g., in theassembly of the main propellant tank it is noted that bothof the alloys contacting surfaces receive one coat ofMB 0125-012 white epoxy primer per MA 0108-013 before assembly.In general, the finishes appear to be adequate. The chromateconversion coatings were used successfully on the Boeing Lunar
I0-49
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
200/413
COL
00
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
201/413
D5-15782
I0.6 SM/SPS PROPELLANT TANK UPPER SUPPORTlO.6.1 Design Adequacy ReviewThe adequacy of the SPS Forward Tank Supports was questionedbecause of the presence of thrust-oscillation induced tankvibrations. The effect of these dynamic loads for AS-503was not considered in the design.The Tank Supports were checked for tank lateral loads,including dynamic effects, as given in D5-15778 (Loads andCriteria Document). At the time the check was being made,the tanks were tested in the CM/SM End-Boost Stack Test(SD 67-554) for a tangential tank mode.It was found that the Supports can be expected to show afactor of safety of at least 2.49, and thus are judgedto be adequate for AS-5O3, see figure I0-29.
lO-51
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
202/413
ITEM OF COt,IPARISON
ENVIRONI,_ENT
LOADS
_.LLOIIABLE
ASSU:_PTIONS
MINIIiUt.!ACTOR OF SAFETY
FAILURE NODE
CONTPJ_CTOR
Not applicableUltimate column load = ]560 Ibs.
Column bucklingAllo_vab]e = 3600#
Column load is determined fromSD 67-554 End Boost Test andtransverse accelerat ions
3.20
Colu,_1buckl ing
JSAT
SAME
Ultimate column load = 2020 Ibs.
SAI]E
S,_,_E
2.49
S_E
FIGURE IO-2-9 SELECTED ELEMENT ,REVIEW DATA CONPARISON --SM/SPS PROPELLANT TANK UPPER SUPPORT
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
203/413
0C
_Jr0-I-)0"04--
0
0_.iJ
.t-O._
_J0-1J_E
0_(I.)(I.)(I)
ue
(I;c-(I;
-I-)-IJ
I(I.)-,--
k_0
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
204/413
ITEM OF CO_,IPARISON
E_V IRON_,_E!ITLOADS @ XA lOlO
(LIHIT)
COI'ITPJ_CTOR
88 F.
SA = 25.430 lb.MA = 1.84 x 106 in-lb.
ALLOL_ABLE
ASSU_..T IOilS
HINII;IU;,IACTOR OF SAFETY
FAILURE F_)DE
P = -94,640 lb.T = 200,000 in-lb.
l .43
Compression yielding around cutout
JSAT
SA_E
FIGURE 10-30 SELECTED ELEMENT REVIEW DATA COHPARISON - SM SHELL
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
205/413
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
206/413
ITEM OF. CO_:IPARISO_I
ENVI RON:_IENT
LOADS
ALLO'._ABLEASSUI,IPTONS
MINIM_I FACTOR OF SAFETY!FAILURE MODE
CONTP_CTOR
Room temperature considered
Axial-Load Factor = 4.032 g (limitLateral toad Factor = 0.236 g "Values incluCz accelerations_ue to thrust oscillations.Inte_nal tank pressure =
230 psi (limit}
Fcc = 35,970 psiAxial peak!ng factor = 1.831_om_nt pea:_ing factor =I.42_Values de_e}_nne by 2-$2
structural test.1.40 (test)
Meridional compressive stresson inner surface of the Skirt.
JSAT
Room temperature considered
/Lxial Load Factor = 4,027 g (limit)|iLateral Load Factor = 0.150 gValues include accelerationsd._ to thrust oscillations.Internal t_nk pressure -230 psi (limit)
Fcc = 35,970 psi
Sa_e
l .42Same
FIGURE 10-31 SELECTEI)ELENENT REVIEW DATA COF_PARISON- SM SPS LOWERTANK SKIRT
-
8/14/2019 NASA Saturn V Rocket Structural Elements - 1968
207/413
D5-15782
10.9 SM AFT BULKHEAD10.9.1 Design Adequacy Review
The critical area for the SM Aft Bulkhead is in Bay #5. In-vestigation into this area was initiated by an analyticallyderived factor of safety of 1