NACE-2015-556511111111

15
Evaluation and Reform of Regional Cathodic Protection System Based on Numerical Simulation Guangchun Wu, Yanxia Du*, Minxu Lu, Zitao Jiang, Dezhi Tang Institute for Advance Materials and Technology Key Laboratory for Environmental Fracture (MOE) University of Science and Technology Beijing 30 Insititute Road Beijing, PR 10083 ABSTRACT A 4-circuit impressed current cathodic protection system with flexible and high silicon cast-iron shallow buried auxiliary anode bed is applied in Jinghe compressor station. In order to obtain the protective effect of the regional cathodic protection system, detailed field tests have been carried out. Based on the results of field tests, assessment of regional cathodic protection is conducted, then reform programs for inadequate protective effect and interferences between pipelines outside and inside the station is determined using numerical simulated computation and field experiments. Keywords: regional cathodic protection, numerical simulation computation, effect assessment, reform program INTRODUCTION Regional cathodic protection technique is an effective measure to prevent corrosion on buried metal facilities in oil and gas transmission stations, which works depended on the reasonable layout of anode ground bed, the distribution of protective current and the electric insulation with adjacent metal facilities. Compared with the cahodic protection applied in long-distance pipelines, regional cathodic 1 Paper No. 5565 ©2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

description

articol

Transcript of NACE-2015-556511111111

  • Evaluation and Reform of Regional Cathodic Protection System Based on Numerical

    Simulation

    Guangchun Wu, Yanxia Du*, Minxu Lu, Zitao Jiang, Dezhi Tang

    Institute for Advance Materials and Technology

    Key Laboratory for Environmental Fracture (MOE)

    University of Science and Technology Beijing

    30 Insititute Road

    Beijing, PR 10083

    ABSTRACT

    A 4-circuit impressed current cathodic protection system with flexible and high silicon cast-iron

    shallow buried auxiliary anode bed is applied in Jinghe compressor station. In order to obtain the

    protective effect of the regional cathodic protection system, detailed field tests have been carried out.

    Based on the results of field tests, assessment of regional cathodic protection is conducted, then

    reform programs for inadequate protective effect and interferences between pipelines outside and

    inside the station is determined using numerical simulated computation and field experiments.

    Keywords: regional cathodic protection, numerical simulation computation, effect assessment,

    reform program

    INTRODUCTION

    Regional cathodic protection technique is an effective measure to prevent corrosion on buried metal

    facilities in oil and gas transmission stations, which works depended on the reasonable layout of

    anode ground bed, the distribution of protective current and the electric insulation with adjacent metal

    facilities. Compared with the cahodic protection applied in long-distance pipelines, regional cathodic

    1

    Paper No.

    5565

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • protection has the following characteristics: various protected objects, complicated protective circuits,

    severe interference, and higher safety requirements1, and it was introduced into China in 1970s2-4.

    However, there are a series of problems to be improved and solved in the processes of the design,

    implementation and application because that it developed relatively late and it is still very immature

    technically in China.

    A 4-circuit impressed current cathodic protection system with flexible and high silicon cast-iron

    shallow buried auxiliary anode bed is applied in Jinghe compressor station. The protected

    objectscontain buried pipelines, including sewage pipelines, gas pipelines, fire pipelines, and

    grounding, including horizontal grounding made by galvanized flat iron and vertical grounding made

    by galvanized flat iron or grounding module. Detailed detection has been performed in Jinghe station

    and the results reveal that: (1) some CP under-protection and over-protection areas existed; (2)

    severe anode interference between cathodic protection systems inside (CP-1) and outside (CP-2)

    the Jinghe station. To assure the safety of pipelines in station, the above problems should be solved

    quickly and carefully. In this paper, the assessment of regional cathodic protection is conducted

    based on field tests, then reform programs for inadequate protective effect and interferences

    between pipelines outside and inside the station is determined using numerical simulated

    computation and field experiments.

    ASSESSMENT OF REGIONAL CATHODIC PROTECTION

    A 30 ampere 50 volt PS-3F CP Transformer/Rectifier (T/R), designated as T/R-1, China, is applied

    in Jinghe regional cathodic protection system. It has 4 circuits: 1# circuit provides protection to

    grounding; 2# circuit provides protection to the buried pipelines around the area of process units, pig

    receiver & launcher and vent; 3# circuit provides protection to the buried pipelines around the

    compressor area; 4# circuit is standby. A HPS-1D CP T/R, designated as T/R-2, 15 ampere 40 volt

    powering a shallow high silicon cast-iron anode bed which provides cathodic protection to the main

    pipelines outside the Jinghe Station. The plan view of the station and main pipeline is shown as

    Figure 1.

    Trade Name.

    2

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • Station

    Upstream main

    pipeline

    Downstream main

    pipeline

    1# Insulation joint 2# Insulation joint

    1# Test point

    2# Test point 3# Test point

    4# Test point171# CP Post

    Crossover wire

    Figure 1: Plan view of station and main pipeline

    INITIAL OPERATINGSTATE OF CP T/R

    The initial operating parameters of the CP T/R were listed in Table 1. It can be seen that: 2# circuit

    (T/R-1) couldnt boot normally for the reason that the potential difference between the control

    potential (0 VCSE) and protection potential (-750 mVCSE) exceeded the set value of T/R-1; the off

    potential at contact points of 1# circuit, 3# circuit and T/R-2 were all positive than -850 mVCSE, thus

    their outputs should be increased to meet the protection requirement.

    Table 1

    Initial Operating State of T/R-1 and T/R-2

    Protective potential

    (mVCSE)

    Output voltage

    (V)

    Output current

    (A)

    Off potential

    (mVCSE)

    T/R-1

    1# Circuit -1112 1.86 0.96 -680

    2# Circuit Dont boot

    3# Circuit -910 18.55 4.90 -720

    4# Circuit Standby

    T/R-2 -1277 4.14 1.49 -730

    FIELD INVESTIGATION AND DISCUSSION

    Operating parameters have been modified based on initial operating state and protected objects

    self-potential, as shown in Table 2. In order to full reflect the protection effect of the regional cathodic

    protection system, a detailed field investigation has been conducted in 9 part areas, a total of 169

    different sites in Jinghe station. The distribution of the total 169 test sites are as follow: 28 sites in

    distribution and regulating area; 38 sites in filtration and separation area; 4 sites in blow-down tank

    area; 11 sites in 1# valve group area; 7 sites in pig receiver area; 6 sites in launcher area; 3 sites in

    2# valve group area; 56 sites in compressor area and 16 sites near to compressor area. Detailed test

    results were shown in Table 3. However, T/R-2 worked abnormally after the adjustment of the

    operating parameters of T/R-1. It became clear after the special field investigation for the reason that

    3

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • the anode-bed of 2# circuit placed close to the drain point and control reference electrode of the

    CP-2, which caused the measured potential at the site of control reference electrode exceeded the

    predetermined value. Hence, there was a severe anode interference existed between the 2# circuit

    and the CP-2. In order to determine the main pipelines off potential whether seriously interfered by

    the anode interference, potential tests have been carried out at upstream and downstream pipeline

    (test point 1#, 2#, 3# and 4#, shown in Figure 1) through adjusting the control potential of the CP-2 to

    keep the output of T/R-2 at non-interference level, then turning T/R-1 and T/R-2 on and off

    simultaneously. Test results were present at Table 4.

    Table 2

    Initial Operating Parameters of T/R-1 after Adjustment

    Control potential

    (mVCSE)

    Output voltage

    (V)

    Output current

    (A)

    T/R-1

    1# Circuit -2600 4.36 4.49

    2# Circuit -940 12.50 24.70

    3# Circuit -910 30.53 6.70

    4# Circuit Standby

    Table 3

    Test Result of Regional Cathodic Protection System in Jinghe Station

    Test area

    Number

    of test

    site

    Off

    potential

    (VCSE)

    Potential distribution

    >-0.85 VCSE -0.85 VCSE-1.2 VCSE

  • Pig receiver area 7

    -0.73

    -0.84

    7 100 0 0 0 0 6 85.7

    Launcher area 6

    -0.71

    -0.88

    5 83.3 1 16.6 0 0 5 83.3

    2# valve group

    area

    3

    -0.94

    -1.02

    0 0 3 100 0 0 3 100

    Compressor area 56

    -0.58

    -1.00

    40 71.4 16 28.5 0 0 49 87.5

    Near to

    compressor area

    16

    -0.54

    -0.74

    16 100 0 0 0 0 7 43.7

    Total 169 105 62.1 63 37.3 1 0.6 143 84.6

    Table 4

    Pipeline Potential at Both Ends of Insulation Joints

    Potential 1nside station (VCSE) Potential outside station (VCSE)

    On potential

    (VCSE)

    Off potential

    (VCSE)

    On potential

    (VCSE)

    Off potential

    (VCSE)

    Downstream

    pipeline

    -1.67 (3# test

    point)

    -0.94 (3# test

    point)

    -2.22 (4# test

    point)

    -1.20 (4# test

    point)

    Upstream

    pipeline

    -1.13 (1# test

    point)

    -1.07 (1# test

    point)

    -1.60 (2# test

    point)

    -1.14 (2# test

    point)

    It can be seen from Table 3 that: (1) there are only one over-protection site placed in filtration and

    separation area; (2) the pipelines off potentials in 1# valve group area are all more positive than -850

    mVCSE, which dont meet the cathodic protection requirement; (3) the pipelines off potentials in

    compressor area are more widely spread and the protection effect is poor. In general, the protection

    effect of the CP-1 is not good, especially in the 1# valve group area and compressor area. Some

    reform programs must to be conducted to prevent pipelines from corrosion in Jinghe station.

    Table 4 presents that when placed the potential control point of CP-2 beyond the anode interference

    zone and remained the output current of T/R-2 unchanged, off potential at 4# test point is -1.20 VCSE

    5

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • which doesnt exceed the cathodic protection standard value, -0.85 VCSE -1.20 VCSE. Hence, the

    anode interference can be mitigated by changing the location of the control reference electrode.

    Moreover, in order to avoid over protection, CIPS test also need to be conducted near the Jinghe

    station.

    From the above content, two problems can be estimated in Jinghe regional cathodic protection

    system: (1) Poor protection effect, some inadequate protective areas existed; (2) Severe anode

    interference between 2# circuit and CP-2, which results in the abnormal operation of T/R-2.

    RESEARCH ON REFORM PROGRAMS OF REGIONAL CATHODIC PROTECTION SYSTEM

    Traditional CP reforms often depend on empirical evaluations. However, in many case, the reforms

    would be found unreasonable or uneconomical after construction has been finished, adding the

    workloads of the late-stage adjustment and in return limiting the further application and development

    of CP techniques in station. With the development of computer techniques, a new method-numerical

    simulation, as a good and convenient manner to obtain potential and current density distribution has

    been widely used to study the CP system 5-10. Using numerical simulation technique, Bazzoni 8

    calculated the potential distribution of tank bottom and analyzed the influence of soil resistance on

    the potential distribution. Du 9 et al. applied numerical simulation techniques to predict the

    performance of CP system and optimize the systems in several oil and gas transmission stations. Lu

    10 et al calculated potential distribution on the surface of pipelines buried in discontinuous permafrost.

    In this work, numerical simulation technique is applied to optimize the CP system in Jinghe station to

    solve the above two problems.

    COMPARISON OF RESULTS BETWEEN NUMERCIAL SIMULATION AND FIELD

    INVESTGATION

    After collecting required basis information and establish the CP model of metal structures, potential

    distribution on the surface of buried pipelines and grounding in Jinghe station is calculated by

    numerical simulation, as shown in Figure 2. It is clear that the potentials of the majority of pipelines,

    horizontal grounding and vertical grounding distribute in the range of -0.85 VCSE -1.20 VCSE, -0.46

    VCSE -0.9 VCSE and -0.26 VCSE -0.76 VCSE, respectively. Comparison of results between

    numerical simulation and field tests was shown in Table 5. As can be seen, numerical simulation

    result is perfectly consistent with field test.

    6

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • Figure 2: Potential distribution of CP-1 using numerical simulation (unit: VCSE)

    Table 5

    Comparison Between Numerical Simulation and Field Test

    Test Area Field Test Results

    (VCSE)

    Numerical Simulation Results

    (VCSE)

    Percentage of Error

    10% (%)

    Distribution and

    regulating area -0.66-0.92 -0.62-0.89 100

    Filtration and separation

    area -0.57-1.25 -0.61-1.10 92.1

    Blow-down tank area -0.86-1.20 -1.00-1.18 75

    1# valve group area -0.61-0.75 -0.60-0.81 100

    Pig receiver area -0.73-0.84 -0.74-0.86 100

    Launcher area -0.71-0.88 -0.70-0.86 100

    2# valve group area -0.94-1.02 -0.95-1.01 100

    Compressor area -0.58-1.00 -0.64-0.95 96.4

    Near to compressor area -0.54-0.74 -0.59-0.77 100

    REFORM PROGRAMS FOR INADEQUATE PROTECTIVE EFFECT

    According to the previous field investigation, the inadequate protective effect of CP-1 could be

    illustrated by the following two reasons: (1) massive grounding grids which directly connected to the

    pipelines consume a large part of the total CP current, especially when the grounding grids is made

    by grounding module. In some case, current demand by the grounding may exceed 90% of the total

    7

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • current output of the impressed current system 11; (2) mutual interference among each circuits of

    CP-1. Considering the feasibility and economy of reform programs, the final reform program has

    been determined which can be accomplished in two steps:

    (1). Replace the grounding module with galvanized steel which is very compatible with CP system

    12.

    (2). Reform the anode beds inside the station, add distributed shallow anodes in under-protection

    areas.

    The reform target is to let the potential of pipelines all distribute in the range of -0.85 VCSE -1.20

    VCSE.

    STEP ONE

    After replacement, potential distribution of pipelines and grounding is shown in Figure 3. As can be

    seen, the potential of the majority of the buried pipelines is between -0.90 VCSE -1.30 VCSE, more

    negative than the value before reform (-0.84 VCSE -1.30 VCSE). However, the extent of variation is

    relatively small due to the less number of grounding module in station and some inadequate

    protective areas also existed. Hence, further reform need to be conducted. In addition, after reform,

    the potential distribution of horizontal grounding is in the range of -0.46 VCSE -0.92 VCSE, negative

    shifting about 20 mV form the value before reform (-0.46 VCSE -0.90 VCSE). In the unreformed

    areas, the potential of vertical grounding is between -0.57 VCSE -0.84 VCSE which is negative

    shifting 60 mV from the value before reform (-0.52 VCSE -0.76 VCSE). Due to grounding

    replacement, the potential of vertical grounding changes from -0.26 VCSE to -0.96 VCSE in the reform

    areas.

    Figure 3: Potential distribution of CP-1 using numerical simulation after reform step 1 (unit: VCSE)

    8

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • STEP TWO

    After reform step one, potential anomaly also existed in some areas in station, as shown in Figure 4.

    Herein, the potential in 1# area is more negative, -1.30 VCSE -1.35 VCSE; the potential in 2# area,

    4# area and 5# area are -0.77 VCSE -0.82 VCSE, -0.81 VCSE -0.85 VCSE and -0.79 VCSE -0.83

    VCSE, respectively, all under the required protection level.

    Optimized anode beds in the above potential anomaly areas in which added 12 distributed shallow

    anodes in the location shown in Figure 5. The potential of pipelines and grounding after reform step 2

    is shown in Figure 6. As can be seen, the potential of buried pipelines distribute in the range of -0.89

    VCSE -1.20 VCSE, obtained good protection effect.

    Figure 4: Potential anomaly areas after reform step 1

    9

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • Figure 5: Location of added anodes in reform step 2

    Figure 6: Potential distribution of CP-1 using numerical simulation after reform step 2 (unit:

    VCSE)

    10

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • REFORM PROGRAMS FOR INTERFERENCE BETWEEN CP-1 AND CP-2

    Based on the above content, the anode interference between 2# circuit and CP-2 can be mitigated

    by changing the location of the control reference electrode, in other words, placed the potential

    control point of CP-2 beyond the anode interference zone.

    DETERMINATION OF INTERFERENCE ZONE

    To determine inference zone using numerical simulation, firstly, calculated the potential distribution of

    the main pipeline outside the station without interference, shown in Figure 7. It can be seen that the

    potential is about -1.0 VCSE, reached a good protection effect. When the interference existed, the

    potential of the upstream and downstream main pipelines are shown in Figure 8 and Figure 9. As can

    be seen, the potential of the main pipeline near the station shift toward negative direction due to

    anode interference, but dont exceed the limit, -1.20 VCSE, in other words, without over-protection.

    Regarded -1.0 VCSE represented by light green color as standard potential, the interference zone of

    the anode interference could reach 200300m in the light of Figure 8 and Figure 9.

    Figure 7: Potential distribution of the main pipeline without interference (unit: VCSE)

    11

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • Figure 8: Potential distribution of the downstream main pipeline near the station, under

    interference (unit: VCSE)

    Figure 9: Potential distribution of the upstream main pipeline near the station, under

    interference (unit: VCSE)

    Meantime, in order to verify the accuracy of the interference zone calculated by numerical simulation,

    field experiment has been conducted through measuring the potential of the main pipeline along

    downstream direction when keep the T/R-1 in the on-off operation state. The result of field test is

    12

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • shown in Table 6. It is clear that when the portable reference electrode is 350m away from 2#

    insulation joint, the potential of the main pipeline dont interfere by the current from CP-1, hence, the

    interference zone is about 350m which is consistent with the result of numerical simulation.

    Table 6

    Result of Field Test for Interference

    Number

    Distance between

    the portable

    reference electrode

    and 2# insulation

    joint (m)

    Potential of the main

    pipeline, T/R-1 on (VCSE)

    Potential of the main

    pipeline, T/R-1 off

    1 2 -1.36 -1.27

    2 20 -1.32 -1.27

    3 50 -1.34 -1.29

    4 100 -1.30 -1.26

    5 150 -1.33 -1.31

    6 200 -1.35 -1.33

    7 250 -1.30 -1.28

    8 300 -1.30 -1.28

    9 350 -1.26 -1.26

    REFORM PROGRAM

    According to the above content, the reform program for the interference between CP-1 and CP-2 is

    as follow: It can be mitigated by moving the control reference electrode of CP-2 to 171# CP post

    500m away from 2# insulation joint due to the interference zone is about 300m, which reduces the

    workload of building a new marks post for the long-term reference electrode and further prevents the

    main pipeline from interference. Of course, a new closer post can be established by further field test,

    but the effect of the change of CP-1 current with time must be taken into account fully. It is worth

    noting that although changing the location of the control reference electrode can mitigate the

    interference of T/R-2, the potential of the pipelines suffering interference whether meet the protection

    requirement entirely need to be tested further by keeping CP-1 and CP-2 under the on and off

    condition in the same time. If the interference hasnt been completely eliminated, reform must to be

    carried out on the anode beds in station.

    13

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • CONCLUSIONS

    (1). The protection effect of CP-1 is not good and some inadequate protective areas existed in

    station according to the field test at 169 sites. In addition, there is a severe anode interference on

    CP-2 generated by 2# circuit of CP-1, which caused the abnormal operation of T/R-2.

    (2). After the replacement of grounding module by galvanized steel and the reform of anode beds in

    station, the potential of all buried pipelines predicted by numerical simulation are between -0.89

    VCSE-1.20 VCSE, meeting the protection requirement.

    (3). Through changing the location of the control reference electrode can mitigate the interference of

    T/R-2. However, to eliminate the interference completely, further test and research need to be

    conducted.

    14

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.

  • REFERENCES

    1. Du Y. X, Lu M. X, Sun J. M, Problems and Solutions Concerning Cathodic Protection in Oil

    and Gas Transmission Station, Gas & Heat 31, 11 (2011): pp.1.

    2. Du Y. X, Zhang G. Z, Regional Cathodic Protection in Pump Station, Corrosion & Protection

    27, 8 (2006):pp.417.

    3. Sun X. G, Wang Z. F, Regional Cathodic Protection for DongYing Crude Oil Tanks, Oil &

    Gas Storage and Transportation 11, 3 (1992): pp.57.

    4. Ge A. T., Tu M. Y., Application of Regional Cathodic Protection in ShanJing Pipeline Station,

    Corrosion & Protection 30, 5 (2009): pp.343.

    5. Qiu F, Xu N.X., Potential and Current Distribution on Pipelines Cathodically Protected with

    Ribbon Sacrificial Anodes, J. Chin. Soc. Corros. Prot. 17, 1 (1997): pp.12.

    6. Brichau F, Deconinck J., A numerical Model for Cathodic Protection of Buried Pipes,

    Corrosion 50, 1 (1994): pp.39.

    7. Telles J. C. F., Mansur W. J., Wrobel L. C., et al. Numerical Simulation of a Cathodically

    Protected Semisubmersible Platform Using the Procat System, Corrosion 46, 6 (1990): pp.513.

    8. Bazzoni B, Current and potential distribution modeling for cathodic protection of tank

    bottoms, Corrosion 2008, paper no. 08059 (Houston, TX: NACE, 2008).

    9. Du Y. X, Lu M. X, Dong L, Study on the Cathodic Protection Scheme in Oil and Gas

    Transmission Station Based on Numerical Simulation, Corrosion 2011, paper no. 11057 (Houston,

    TX: NACE, 2011).

    10. Du Y. X, Lu M. X, Dong L, Cathodic Protection Potential Distribution Simulation for Pipeline

    buried in Discontinuous Permafrost, Corrosion 2009, paper no. 09070 (Houston, TX: NACE,

    2009).

    11. Gummow R. A., Cathodic Protection Current Requirements for Electrical Grounding

    Materials, Corrosion 2004, paper no. 04562 (Houston, TX: NACE, 2004).

    12. Kirkpatrick E. L., Shamim M. L., Copper Grounding Systems Have a Negative Effect on

    Cathodic Protection in Production Facilities, Corrosion 2000, paper no. 00743 (Houston, TX:

    NACE, 2000).

    15

    2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.