NACE-2015-556511111111
-
Upload
andreea-patru -
Category
Documents
-
view
5 -
download
0
description
Transcript of NACE-2015-556511111111
-
Evaluation and Reform of Regional Cathodic Protection System Based on Numerical
Simulation
Guangchun Wu, Yanxia Du*, Minxu Lu, Zitao Jiang, Dezhi Tang
Institute for Advance Materials and Technology
Key Laboratory for Environmental Fracture (MOE)
University of Science and Technology Beijing
30 Insititute Road
Beijing, PR 10083
ABSTRACT
A 4-circuit impressed current cathodic protection system with flexible and high silicon cast-iron
shallow buried auxiliary anode bed is applied in Jinghe compressor station. In order to obtain the
protective effect of the regional cathodic protection system, detailed field tests have been carried out.
Based on the results of field tests, assessment of regional cathodic protection is conducted, then
reform programs for inadequate protective effect and interferences between pipelines outside and
inside the station is determined using numerical simulated computation and field experiments.
Keywords: regional cathodic protection, numerical simulation computation, effect assessment,
reform program
INTRODUCTION
Regional cathodic protection technique is an effective measure to prevent corrosion on buried metal
facilities in oil and gas transmission stations, which works depended on the reasonable layout of
anode ground bed, the distribution of protective current and the electric insulation with adjacent metal
facilities. Compared with the cahodic protection applied in long-distance pipelines, regional cathodic
1
Paper No.
5565
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
protection has the following characteristics: various protected objects, complicated protective circuits,
severe interference, and higher safety requirements1, and it was introduced into China in 1970s2-4.
However, there are a series of problems to be improved and solved in the processes of the design,
implementation and application because that it developed relatively late and it is still very immature
technically in China.
A 4-circuit impressed current cathodic protection system with flexible and high silicon cast-iron
shallow buried auxiliary anode bed is applied in Jinghe compressor station. The protected
objectscontain buried pipelines, including sewage pipelines, gas pipelines, fire pipelines, and
grounding, including horizontal grounding made by galvanized flat iron and vertical grounding made
by galvanized flat iron or grounding module. Detailed detection has been performed in Jinghe station
and the results reveal that: (1) some CP under-protection and over-protection areas existed; (2)
severe anode interference between cathodic protection systems inside (CP-1) and outside (CP-2)
the Jinghe station. To assure the safety of pipelines in station, the above problems should be solved
quickly and carefully. In this paper, the assessment of regional cathodic protection is conducted
based on field tests, then reform programs for inadequate protective effect and interferences
between pipelines outside and inside the station is determined using numerical simulated
computation and field experiments.
ASSESSMENT OF REGIONAL CATHODIC PROTECTION
A 30 ampere 50 volt PS-3F CP Transformer/Rectifier (T/R), designated as T/R-1, China, is applied
in Jinghe regional cathodic protection system. It has 4 circuits: 1# circuit provides protection to
grounding; 2# circuit provides protection to the buried pipelines around the area of process units, pig
receiver & launcher and vent; 3# circuit provides protection to the buried pipelines around the
compressor area; 4# circuit is standby. A HPS-1D CP T/R, designated as T/R-2, 15 ampere 40 volt
powering a shallow high silicon cast-iron anode bed which provides cathodic protection to the main
pipelines outside the Jinghe Station. The plan view of the station and main pipeline is shown as
Figure 1.
Trade Name.
2
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
Station
Upstream main
pipeline
Downstream main
pipeline
1# Insulation joint 2# Insulation joint
1# Test point
2# Test point 3# Test point
4# Test point171# CP Post
Crossover wire
Figure 1: Plan view of station and main pipeline
INITIAL OPERATINGSTATE OF CP T/R
The initial operating parameters of the CP T/R were listed in Table 1. It can be seen that: 2# circuit
(T/R-1) couldnt boot normally for the reason that the potential difference between the control
potential (0 VCSE) and protection potential (-750 mVCSE) exceeded the set value of T/R-1; the off
potential at contact points of 1# circuit, 3# circuit and T/R-2 were all positive than -850 mVCSE, thus
their outputs should be increased to meet the protection requirement.
Table 1
Initial Operating State of T/R-1 and T/R-2
Protective potential
(mVCSE)
Output voltage
(V)
Output current
(A)
Off potential
(mVCSE)
T/R-1
1# Circuit -1112 1.86 0.96 -680
2# Circuit Dont boot
3# Circuit -910 18.55 4.90 -720
4# Circuit Standby
T/R-2 -1277 4.14 1.49 -730
FIELD INVESTIGATION AND DISCUSSION
Operating parameters have been modified based on initial operating state and protected objects
self-potential, as shown in Table 2. In order to full reflect the protection effect of the regional cathodic
protection system, a detailed field investigation has been conducted in 9 part areas, a total of 169
different sites in Jinghe station. The distribution of the total 169 test sites are as follow: 28 sites in
distribution and regulating area; 38 sites in filtration and separation area; 4 sites in blow-down tank
area; 11 sites in 1# valve group area; 7 sites in pig receiver area; 6 sites in launcher area; 3 sites in
2# valve group area; 56 sites in compressor area and 16 sites near to compressor area. Detailed test
results were shown in Table 3. However, T/R-2 worked abnormally after the adjustment of the
operating parameters of T/R-1. It became clear after the special field investigation for the reason that
3
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
the anode-bed of 2# circuit placed close to the drain point and control reference electrode of the
CP-2, which caused the measured potential at the site of control reference electrode exceeded the
predetermined value. Hence, there was a severe anode interference existed between the 2# circuit
and the CP-2. In order to determine the main pipelines off potential whether seriously interfered by
the anode interference, potential tests have been carried out at upstream and downstream pipeline
(test point 1#, 2#, 3# and 4#, shown in Figure 1) through adjusting the control potential of the CP-2 to
keep the output of T/R-2 at non-interference level, then turning T/R-1 and T/R-2 on and off
simultaneously. Test results were present at Table 4.
Table 2
Initial Operating Parameters of T/R-1 after Adjustment
Control potential
(mVCSE)
Output voltage
(V)
Output current
(A)
T/R-1
1# Circuit -2600 4.36 4.49
2# Circuit -940 12.50 24.70
3# Circuit -910 30.53 6.70
4# Circuit Standby
Table 3
Test Result of Regional Cathodic Protection System in Jinghe Station
Test area
Number
of test
site
Off
potential
(VCSE)
Potential distribution
>-0.85 VCSE -0.85 VCSE-1.2 VCSE
-
Pig receiver area 7
-0.73
-0.84
7 100 0 0 0 0 6 85.7
Launcher area 6
-0.71
-0.88
5 83.3 1 16.6 0 0 5 83.3
2# valve group
area
3
-0.94
-1.02
0 0 3 100 0 0 3 100
Compressor area 56
-0.58
-1.00
40 71.4 16 28.5 0 0 49 87.5
Near to
compressor area
16
-0.54
-0.74
16 100 0 0 0 0 7 43.7
Total 169 105 62.1 63 37.3 1 0.6 143 84.6
Table 4
Pipeline Potential at Both Ends of Insulation Joints
Potential 1nside station (VCSE) Potential outside station (VCSE)
On potential
(VCSE)
Off potential
(VCSE)
On potential
(VCSE)
Off potential
(VCSE)
Downstream
pipeline
-1.67 (3# test
point)
-0.94 (3# test
point)
-2.22 (4# test
point)
-1.20 (4# test
point)
Upstream
pipeline
-1.13 (1# test
point)
-1.07 (1# test
point)
-1.60 (2# test
point)
-1.14 (2# test
point)
It can be seen from Table 3 that: (1) there are only one over-protection site placed in filtration and
separation area; (2) the pipelines off potentials in 1# valve group area are all more positive than -850
mVCSE, which dont meet the cathodic protection requirement; (3) the pipelines off potentials in
compressor area are more widely spread and the protection effect is poor. In general, the protection
effect of the CP-1 is not good, especially in the 1# valve group area and compressor area. Some
reform programs must to be conducted to prevent pipelines from corrosion in Jinghe station.
Table 4 presents that when placed the potential control point of CP-2 beyond the anode interference
zone and remained the output current of T/R-2 unchanged, off potential at 4# test point is -1.20 VCSE
5
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
which doesnt exceed the cathodic protection standard value, -0.85 VCSE -1.20 VCSE. Hence, the
anode interference can be mitigated by changing the location of the control reference electrode.
Moreover, in order to avoid over protection, CIPS test also need to be conducted near the Jinghe
station.
From the above content, two problems can be estimated in Jinghe regional cathodic protection
system: (1) Poor protection effect, some inadequate protective areas existed; (2) Severe anode
interference between 2# circuit and CP-2, which results in the abnormal operation of T/R-2.
RESEARCH ON REFORM PROGRAMS OF REGIONAL CATHODIC PROTECTION SYSTEM
Traditional CP reforms often depend on empirical evaluations. However, in many case, the reforms
would be found unreasonable or uneconomical after construction has been finished, adding the
workloads of the late-stage adjustment and in return limiting the further application and development
of CP techniques in station. With the development of computer techniques, a new method-numerical
simulation, as a good and convenient manner to obtain potential and current density distribution has
been widely used to study the CP system 5-10. Using numerical simulation technique, Bazzoni 8
calculated the potential distribution of tank bottom and analyzed the influence of soil resistance on
the potential distribution. Du 9 et al. applied numerical simulation techniques to predict the
performance of CP system and optimize the systems in several oil and gas transmission stations. Lu
10 et al calculated potential distribution on the surface of pipelines buried in discontinuous permafrost.
In this work, numerical simulation technique is applied to optimize the CP system in Jinghe station to
solve the above two problems.
COMPARISON OF RESULTS BETWEEN NUMERCIAL SIMULATION AND FIELD
INVESTGATION
After collecting required basis information and establish the CP model of metal structures, potential
distribution on the surface of buried pipelines and grounding in Jinghe station is calculated by
numerical simulation, as shown in Figure 2. It is clear that the potentials of the majority of pipelines,
horizontal grounding and vertical grounding distribute in the range of -0.85 VCSE -1.20 VCSE, -0.46
VCSE -0.9 VCSE and -0.26 VCSE -0.76 VCSE, respectively. Comparison of results between
numerical simulation and field tests was shown in Table 5. As can be seen, numerical simulation
result is perfectly consistent with field test.
6
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
Figure 2: Potential distribution of CP-1 using numerical simulation (unit: VCSE)
Table 5
Comparison Between Numerical Simulation and Field Test
Test Area Field Test Results
(VCSE)
Numerical Simulation Results
(VCSE)
Percentage of Error
10% (%)
Distribution and
regulating area -0.66-0.92 -0.62-0.89 100
Filtration and separation
area -0.57-1.25 -0.61-1.10 92.1
Blow-down tank area -0.86-1.20 -1.00-1.18 75
1# valve group area -0.61-0.75 -0.60-0.81 100
Pig receiver area -0.73-0.84 -0.74-0.86 100
Launcher area -0.71-0.88 -0.70-0.86 100
2# valve group area -0.94-1.02 -0.95-1.01 100
Compressor area -0.58-1.00 -0.64-0.95 96.4
Near to compressor area -0.54-0.74 -0.59-0.77 100
REFORM PROGRAMS FOR INADEQUATE PROTECTIVE EFFECT
According to the previous field investigation, the inadequate protective effect of CP-1 could be
illustrated by the following two reasons: (1) massive grounding grids which directly connected to the
pipelines consume a large part of the total CP current, especially when the grounding grids is made
by grounding module. In some case, current demand by the grounding may exceed 90% of the total
7
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
current output of the impressed current system 11; (2) mutual interference among each circuits of
CP-1. Considering the feasibility and economy of reform programs, the final reform program has
been determined which can be accomplished in two steps:
(1). Replace the grounding module with galvanized steel which is very compatible with CP system
12.
(2). Reform the anode beds inside the station, add distributed shallow anodes in under-protection
areas.
The reform target is to let the potential of pipelines all distribute in the range of -0.85 VCSE -1.20
VCSE.
STEP ONE
After replacement, potential distribution of pipelines and grounding is shown in Figure 3. As can be
seen, the potential of the majority of the buried pipelines is between -0.90 VCSE -1.30 VCSE, more
negative than the value before reform (-0.84 VCSE -1.30 VCSE). However, the extent of variation is
relatively small due to the less number of grounding module in station and some inadequate
protective areas also existed. Hence, further reform need to be conducted. In addition, after reform,
the potential distribution of horizontal grounding is in the range of -0.46 VCSE -0.92 VCSE, negative
shifting about 20 mV form the value before reform (-0.46 VCSE -0.90 VCSE). In the unreformed
areas, the potential of vertical grounding is between -0.57 VCSE -0.84 VCSE which is negative
shifting 60 mV from the value before reform (-0.52 VCSE -0.76 VCSE). Due to grounding
replacement, the potential of vertical grounding changes from -0.26 VCSE to -0.96 VCSE in the reform
areas.
Figure 3: Potential distribution of CP-1 using numerical simulation after reform step 1 (unit: VCSE)
8
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
STEP TWO
After reform step one, potential anomaly also existed in some areas in station, as shown in Figure 4.
Herein, the potential in 1# area is more negative, -1.30 VCSE -1.35 VCSE; the potential in 2# area,
4# area and 5# area are -0.77 VCSE -0.82 VCSE, -0.81 VCSE -0.85 VCSE and -0.79 VCSE -0.83
VCSE, respectively, all under the required protection level.
Optimized anode beds in the above potential anomaly areas in which added 12 distributed shallow
anodes in the location shown in Figure 5. The potential of pipelines and grounding after reform step 2
is shown in Figure 6. As can be seen, the potential of buried pipelines distribute in the range of -0.89
VCSE -1.20 VCSE, obtained good protection effect.
Figure 4: Potential anomaly areas after reform step 1
9
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
Figure 5: Location of added anodes in reform step 2
Figure 6: Potential distribution of CP-1 using numerical simulation after reform step 2 (unit:
VCSE)
10
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
REFORM PROGRAMS FOR INTERFERENCE BETWEEN CP-1 AND CP-2
Based on the above content, the anode interference between 2# circuit and CP-2 can be mitigated
by changing the location of the control reference electrode, in other words, placed the potential
control point of CP-2 beyond the anode interference zone.
DETERMINATION OF INTERFERENCE ZONE
To determine inference zone using numerical simulation, firstly, calculated the potential distribution of
the main pipeline outside the station without interference, shown in Figure 7. It can be seen that the
potential is about -1.0 VCSE, reached a good protection effect. When the interference existed, the
potential of the upstream and downstream main pipelines are shown in Figure 8 and Figure 9. As can
be seen, the potential of the main pipeline near the station shift toward negative direction due to
anode interference, but dont exceed the limit, -1.20 VCSE, in other words, without over-protection.
Regarded -1.0 VCSE represented by light green color as standard potential, the interference zone of
the anode interference could reach 200300m in the light of Figure 8 and Figure 9.
Figure 7: Potential distribution of the main pipeline without interference (unit: VCSE)
11
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
Figure 8: Potential distribution of the downstream main pipeline near the station, under
interference (unit: VCSE)
Figure 9: Potential distribution of the upstream main pipeline near the station, under
interference (unit: VCSE)
Meantime, in order to verify the accuracy of the interference zone calculated by numerical simulation,
field experiment has been conducted through measuring the potential of the main pipeline along
downstream direction when keep the T/R-1 in the on-off operation state. The result of field test is
12
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
shown in Table 6. It is clear that when the portable reference electrode is 350m away from 2#
insulation joint, the potential of the main pipeline dont interfere by the current from CP-1, hence, the
interference zone is about 350m which is consistent with the result of numerical simulation.
Table 6
Result of Field Test for Interference
Number
Distance between
the portable
reference electrode
and 2# insulation
joint (m)
Potential of the main
pipeline, T/R-1 on (VCSE)
Potential of the main
pipeline, T/R-1 off
1 2 -1.36 -1.27
2 20 -1.32 -1.27
3 50 -1.34 -1.29
4 100 -1.30 -1.26
5 150 -1.33 -1.31
6 200 -1.35 -1.33
7 250 -1.30 -1.28
8 300 -1.30 -1.28
9 350 -1.26 -1.26
REFORM PROGRAM
According to the above content, the reform program for the interference between CP-1 and CP-2 is
as follow: It can be mitigated by moving the control reference electrode of CP-2 to 171# CP post
500m away from 2# insulation joint due to the interference zone is about 300m, which reduces the
workload of building a new marks post for the long-term reference electrode and further prevents the
main pipeline from interference. Of course, a new closer post can be established by further field test,
but the effect of the change of CP-1 current with time must be taken into account fully. It is worth
noting that although changing the location of the control reference electrode can mitigate the
interference of T/R-2, the potential of the pipelines suffering interference whether meet the protection
requirement entirely need to be tested further by keeping CP-1 and CP-2 under the on and off
condition in the same time. If the interference hasnt been completely eliminated, reform must to be
carried out on the anode beds in station.
13
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
CONCLUSIONS
(1). The protection effect of CP-1 is not good and some inadequate protective areas existed in
station according to the field test at 169 sites. In addition, there is a severe anode interference on
CP-2 generated by 2# circuit of CP-1, which caused the abnormal operation of T/R-2.
(2). After the replacement of grounding module by galvanized steel and the reform of anode beds in
station, the potential of all buried pipelines predicted by numerical simulation are between -0.89
VCSE-1.20 VCSE, meeting the protection requirement.
(3). Through changing the location of the control reference electrode can mitigate the interference of
T/R-2. However, to eliminate the interference completely, further test and research need to be
conducted.
14
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.
-
REFERENCES
1. Du Y. X, Lu M. X, Sun J. M, Problems and Solutions Concerning Cathodic Protection in Oil
and Gas Transmission Station, Gas & Heat 31, 11 (2011): pp.1.
2. Du Y. X, Zhang G. Z, Regional Cathodic Protection in Pump Station, Corrosion & Protection
27, 8 (2006):pp.417.
3. Sun X. G, Wang Z. F, Regional Cathodic Protection for DongYing Crude Oil Tanks, Oil &
Gas Storage and Transportation 11, 3 (1992): pp.57.
4. Ge A. T., Tu M. Y., Application of Regional Cathodic Protection in ShanJing Pipeline Station,
Corrosion & Protection 30, 5 (2009): pp.343.
5. Qiu F, Xu N.X., Potential and Current Distribution on Pipelines Cathodically Protected with
Ribbon Sacrificial Anodes, J. Chin. Soc. Corros. Prot. 17, 1 (1997): pp.12.
6. Brichau F, Deconinck J., A numerical Model for Cathodic Protection of Buried Pipes,
Corrosion 50, 1 (1994): pp.39.
7. Telles J. C. F., Mansur W. J., Wrobel L. C., et al. Numerical Simulation of a Cathodically
Protected Semisubmersible Platform Using the Procat System, Corrosion 46, 6 (1990): pp.513.
8. Bazzoni B, Current and potential distribution modeling for cathodic protection of tank
bottoms, Corrosion 2008, paper no. 08059 (Houston, TX: NACE, 2008).
9. Du Y. X, Lu M. X, Dong L, Study on the Cathodic Protection Scheme in Oil and Gas
Transmission Station Based on Numerical Simulation, Corrosion 2011, paper no. 11057 (Houston,
TX: NACE, 2011).
10. Du Y. X, Lu M. X, Dong L, Cathodic Protection Potential Distribution Simulation for Pipeline
buried in Discontinuous Permafrost, Corrosion 2009, paper no. 09070 (Houston, TX: NACE,
2009).
11. Gummow R. A., Cathodic Protection Current Requirements for Electrical Grounding
Materials, Corrosion 2004, paper no. 04562 (Houston, TX: NACE, 2004).
12. Kirkpatrick E. L., Shamim M. L., Copper Grounding Systems Have a Negative Effect on
Cathodic Protection in Production Facilities, Corrosion 2000, paper no. 00743 (Houston, TX:
NACE, 2000).
15
2015 by NACE International. Requests for permission to publish this manuscript in any form, in part or in whole, must be in writing to NACE International, Publications Division, 15835 Park Ten Place, Houston, Texas 77084. The material presented and the views expressed in this paper are solely those of the author(s) and are not necessarily endorsed by the Association.