Muskrat Falls Project Oversight Committee
Transcript of Muskrat Falls Project Oversight Committee
Muskrat Falls Project Oversight Committee
Quarterly Project Update
Period Ending December 31, 2019
February 26, 2020
2
Table of Contents
1. Q4 2019 Cumulative Project Progress
2. Performance Summaries
3. Oversight Committee Reporting
4. Nalcor Reporting
Annex A - Project Capital Budget and Project Milestone Schedule
Annex B - Project Expenditures
Annex C - Earned Progress
Annex D - Project Milestone Schedule Forecast
3
1. Q4 2019 Cumulative Project Progress
Note: Planned Progress Baselined in June 2016
4
2. Q4 2019 Performance Summary
Note: Planned Progress Baselined in June 2016
5
3. 2019 Performance Summary
Note: Planned Progress Baselined in June 2016
6
2. 2019 Performance Summary - Power Development
Activity Status
Powerhouse and Intake• Turbine and Generator (T&G)
• Units 1 - 4
• Balance of Plant Installation
• Intake Gates
Reached Pit Free by May 2019
Assembly and installation ongoing; Unit 1 assembly
complete; Ready for operation expected in Q1 2020
Approximately 90% complete; commissioning ongoing;
systems to support Unit 1 Ready to Turn complete
Complete and intake impounded
Civil Scope Base scope substantially complete in powerhouse and
spillway
Impoundment Impoundment to full supply level completed on
September 4, 2019
7
2. 2019 Performance Summary - Power Supply
Activity Status
Labrador Island Transmission Link
• Overland Transmission Line and Strait of
Belle Isle Cable Crossing
• HVdc Specialties – Muskrat Falls and
Soldiers Pond Converters
• HVdc Specialties – Soldiers Pond
Synchronous Condensers
• Energization and Power Transfer
Assets turned over and under the control of Power
Supply since 2018
Pole 1 complete in 2018; Only remaining work on Pole
2 is installation of interface transformers at Soldiers
Pond for electrode line fault locator
Rotor lift, lube oil contamination and hydrogen piping
contamination complete in July 2019; dynamic
commissioning and root cause investigations into
vibrations and binding ongoing
Pole 1 power transfer commenced in December 2018;
commissioning and energization of monopole
concluded in June 2019; static versions of bipole
software released to site in 2019 to advance static
commissioning
Labrador Transmission Asset (LTA) Construction and commissioning 100% complete and
turned over to Power Supply in June 2019
8
3.0 Oversight Committee Reporting
3.1 Overview
3.2 Committee Activities
3.3 Independent Engineer Activities
3.4 Risks and Issues Being Monitored by the Committee
3.5 Subsequent Events to Q4
9
3.1 Overview
• The Oversight Committee (Committee) receives details on project costs
incurred, schedule progress, changes in costs and milestone schedule, the
status of construction, and manufacturing and installation contracts.
• The Committee identifies risks and issues and follows up with Nalcor to obtain
more detail and explanation.
• This report covers the October to December 2019 period (Q4) and includes
information on other notable project activity up to the date of drafting of this
report.
• Section 3 of this report contains information developed by the Committee.
Section 4 contains project cost and schedule information provided by Nalcor.
The Annexes contain a more detailed accounting of the information provided in
this report.
• The next Committee Report will cover the period January 2020 – March 2020.
10
3.2 Committee Activities
• The Committee met on three occasions during the period to receive project
updates and conduct other Committee business. Committee meeting minutes
and reports are available on the Committee website @ Click here and Click
here.
• The Department of Natural Resources Associate Deputy Minister and Director
participated in site project visits and meeting with the Independent Engineer
(IE) and Natural Resources Canada (NRCan) during November 19-21, 2019.
• The Committee Chair participated as an observer in two monthly calls on
Nalcor project reporting to the IE and NRCan and one call with the IE and
NRCan to discuss Nalcor monthly project reporting and site visits. The
Department of Natural Resources Director also participated in two calls with
the IE and NRCan.
11
3.3 Independent Engineer Activities
• The IE and NRCan held project site visits and meetings during September and November
2019 and visited GE Grid’s Stafford, UK HVdc protection and controls software
development site in December 2019. Reports from these visits can be found on the
Committee’s website @ Click here.
• In these reports:
• September 15-18, 2019 Site Visits and Meetings
• Status update. No concluding comments.
• November 2019 Project Site Visits and Meetings
• Action Items and Recommendations
• With respect to delays in Unit #1 commissioning, IE request more details on the issues facing theAndritz team.
• IE request a copy of Andritz NCR (non-compliance report) for the Unit #4 elevation anomaly.
• IE request a copy of updated Unit #1 Ready-To-Turn scope document.
• HVAC line faults on the rectifier side may cause loss of HVDC power loss; HVAC faults on theinverter side may cause commutation failure and loss of power flow. Nalcor may wish to verifycapability of LIL converters to ride through AC faults by staged ‘close-in’fault tests on the parallelHVAC lines.
• Regarding design of programming sequences for operation in ‘Overload” mode, failed monopolepower may be replaced from other sources such as the Maritime Link. If that is acceptable, S/Wdesign for operation in ‘Overload’ may be temporarily deferred to free up design resources.
• Completion team appears to have all the requisite specialties and chain of command. Respectivesite responsibilities, sign off process, overall responsibility for the Commissioning andAcceptance, and final approval process for the ITP’s (Inspection and Test Plans) meritclarification and further discussion.
12
3.3 Independent Engineer Activities
• December 2019 Stafford, UK Visit
• Comments and Conclusions
• There is a cautious optimism that overall quality is improving.
• While the plan still shows expected completion of the factory acceptance tests (FAT)
by June 9th, 2020, there is little confidence that the target will be met. Progress
velocity remains in risk category ‘red’.
• If available, addition of qualified resource with knowledge of coding and the HVDC/
electric utility industry is recommended.
• Number of outstanding bugs that will be identified/ remedied at later stages presents
an unknown risk to Project schedule and S/W performance.
• GE’s project plan does not include full regression testing of the completed software
release or provides time allowance for bug fixes between the project phases. That
raises a question if that approach will ensure full functionality of this critical
component.
• NALCOR and Amplitude site representatives monitor and provide helpful feedback to
both NALCOR and GE.
• The IE is planning to visit the Muskrat Falls powerhouse in Q1 2020.
13
3.4 Risk and Issues being Monitored by the Committee
• In its project reporting, Nalcor identifies risks which may impact project cost and schedule.
The Committee reviews these and other project information to assess project risks. These
risks can be found on pages 14-17 of this report.
• Over the reporting period the Committee noted:
• Reservoir rim stability remained consistent over the Quarter;
• Pennecon (replacement contractor for Astaldi) has largely demobilized from the
powerhouse and spillway as work is largely complete;
• Litigation and Arbitration proceedings are ongoing with Astaldi;
• Document discovery ongoing;
• Protection and Controls (P&C) software completion for the HVdc system and
schedule remains a key project risk. P&C software completion has placed the LITL
on the critical path for the overall project schedule and there continues to be schedule
milestone adjustments;
• Soldiers Pond synchronous condensers vibration and binding issues root cause and
remediation activities are ongoing. Schedule milestone changes are continuing to
occur;
• Forecast completion of key milestones under Power Development changed during
the period; Nalcor has reported little improvement in Andritz Hydro’s productivity; and
• Nalcor/NLH preparedness for interconnection and operations following transfer of
power and final completion of bipole remains a key focus area.
14
3.4 Risk and Issues being Monitored by the Committee
• The project is now largely in the installation, integration and static and dynamic
commissioning phases which inherently carry associated risks.
• Risks that are being tracked by the Committee include:
A) Safety Performance
• Risk associated with simultaneous operations across multiple work
sites, impact on project delivery particularly in the powerhouse,
energized yards and other assets. This risk will continue through
construction into operations.
B) Contractor Management and Productivity
• Nalcor ability to manage contractors and contractor ability to meet
schedule;
• Contractor management and performance in the powerhouse;
• Potential commercial negotiations to settle claims; and
• Potential for new claims as construction nears completion.
15
3.4 Risk and Issues being Monitored by the Committee
C) Phased Commissioning
• Completion of P&C system to enhance functionality and reliability;
associated warranty considerations with early asset handover during
commissioning and completion;
• Final completion and testing of HVdc system under low and full
power, in-service system reliability, and timing of contractor release
and effective warranty period; and
• P&C software delivery and final commissioning completion to
maintain project critical path and power delivery.
D) Astaldi
• Astaldi arbitration/litigation outcomes and potential impact on projectcosts.
E) Synchronous Condensers
• Remediation of vibration (Unit 3) and binding (Units 1 and 2) issuesand potential impact on project schedule.
16
3.4 Risk and Issues being Monitored by the Committee
F) Insurance Claims and Coverage
• Coverage: Lube oil contamination within the Synchronous
Condensers – As of December 2019, remedial work complete on all
three units and eligible GE and Nalcor costs has been recovered.
• Potential coverage: Preservation/re-preservation of Turbine and
Generator parts - investigations ongoing.
• Potential coverage: Spillway secondary concrete and gate guide
heater tubulars repairs – investigations ongoing and repair work
suspended until after winter 2019-2020.
G) Powerhouse Commissioning
• Commissioning of powerhouse generation Units 1 through 4 withinthe project schedule.
H) Reservoir Rim Stability
• Impact of reservoir full supply level on reservoir shoreline/slope
stability.
I) Project Integration and Operations Readiness
• Nalcor/NLH readiness to connect the Muskrat Falls Project to theIsland and North American electricity grid and operate facilitieseffectively.
17
3.4 Risk and Issues being Monitored by the Committee
J) Project Delivery Team Retention
• Project Team personnel departures and potential impact on project
completion.
K) Additional Risks (above the June 2017 Project Budget)
• Astaldi arbitration/litigation; and
• Alternate HVdc P&C software development.
• Funds are not held within the June 2017 Project Budget for these
additional risks.
18
3.5 Subsequent Events to Q4 2019
• In Nalcor’s February 6, 2019 reporting update which included the January 2020 reporting period under
development, Nalcor advised:
• Power Supply (Transmission)• Is expecting at least a six week delay to Factory Acceptance Tested (FAT) interim bipole software
being delivered to site and corresponding impact on subsequent milestones at a minimum.
• Given the status of bipole software development, a new delivery schedule from GE Grid is
required; discussion are ongoing and new schedule is expected in the coming weeks; and
• Based on GE Grid’s historical and current performance, Nalcor is assessing all options to
mitigate further schedule slippage to low power and high power versions of software.
• Power Development (Generation)• In January 2020, a generator and rotor torque key issue was identified during Unit 2 installation.
Fabrication of new keys and change out is ongoing on Units 2, 3 and 4. Repairs to Unit 1,
including manufacturing of replacement parts, delivery, and installation, will require 4 to 6 weeks
to conclude. Other commissioning on Unit 1 is still proceeding. This repair will impact Unit 1 first
power milestone dates by at least 4-6 weeks; and
• Progress on Units 2,3, and 4 continues to trend behind plan and Andritz Hydro’s performance is
lagging behind their estimates. An overall consolidated recovery plan as of February 6, 2020, has
not been received by Nalcor. Andritz Hydro’s schedule dates for Units 2, 3 and 4 are uncertain.
Nalcor is developing revised schedule dates which will be reflected in its January 2020 project
reports. Looking forward it is very likely that Units 3 and 4 may not be commissioned by
September 1, 2020.
• Collectively, project teams are focused on delivery of quality assets rather than advancing with possible asset
deficiencies in order to meet schedule milestone dates. Objectives at this time include delivering necessary
power to Newfoundland and Labrador Hydro under the Power Purchase Agreement (PPA) to offset oil-fired
generation from Holyrood and pass on savings to ratepayers and meeting electricity commitments to Emera
under the project agreements by September 1, 2020. Nalcor will be engaging project stakeholders to advise
accordingly.
19
3.5 Subsequent Events to Q4 2019
• On February 20, 2020 Nalcor provided Construction Reports for the period ending January 2020 and
including recent events up to February 20, 2020. In these reports Nalcor advised:
• Power Supply (Transmission)
• Contractual dates as agreed with GE Grid in the November 2019 8th Amending
Agreement for the LITL Protection and Controls software delivery remain in effect,
however Nalcor had adjusted the project’s Integrated Project Schedule (IPS) to reflect
GE Grid’s slower than planned progress. The new schedule forecast is as follows:
• Risk for further Interim FAT Software release to site milestone change is high and has
potential to impact the Final Software Delivery schedule.
• Due to GE Power’s synchronous condenser vibration and binding root cause
investigations and ongoing remediation, commissioning of all three synchronous
condenser units is now forecasted for May-June-August for Units 3,2, and 1
respectively. Pending the outcome of root cause investigations and the resolution, there
is a risk that schedule may extend beyond August 2020.
Milestone Date
Interim Bipole Software release to site April 20, 2020
Interim Low Load Dynamic Commissioning Complete May 30, 2020
Final Software release to site July 29, 2020
Dynamic Commissioning Complete August 31, 2020
20
3.5 Subsequent Events to Q4 2019
• Power Development (Generation)• Unit 1 First Power from Muskrat Falls is now forecasted for March 15, 2020.
• Progress on Units 2,3, and 4 continues to trend behind plan as Andritz Hydro’s performance is
lagging behind their estimates. Nalcor has updated the remaining Muskrat Falls generation
milestone dates based on its assessment of Andritz Hydro’s demonstrated performance to date
and potential for parallel work on Units 3 and 4. The new schedule forecast is as follows:
• Overall, the estimated Commissioning Date of September 1, 2020, set forth in the Labrador Island
Transmission Link and Muskrat Falls Project Schedule is under review, however Nalcor does not anticipated it
to extend past Date Certain (February 28, 2021).
• The Committee will report any changes to schedule and risk in reference to slides 18-20, following review of
project materials over the reporting period in preparation of the Committee’s Q1, 2020 report.
Milestone Date
First Power from Muskrat Falls March 15, 2020
Powerhouse Unit 1 Commissioned – Ready for Operation April 15, 2020
Powerhouse Unit 2 Commissioned – Ready for Operation June 20, 2020
Powerhouse Unit 3 Commissioned – Ready for Operation September 17, 2020
Powerhouse Unit 4 Commissioned – Ready for Operation November 18, 2020
Full Power from Muskrat Falls November 18, 2020
Commissioning Complete – Commissioning Certificate
Issued
September 1, 2020 - Under Review
Date Certain February 28, 2021
21
4.0 Nalcor Reporting
4.1 Summary - Quarter Ending December 2019
4.2 Project Expenditures
4.3 Contingency
4.4 Earned Progress
22
4.1 Summary – Quarter Ending December 2019
• December 2019 Summary:• Overall construction progress is at 99.3%;
• $9,560 Million in incurred costs; and
• $9,626 Million in committed costs.
• Overall, the project is tracking in compliance with the June 2017 budget and schedule,
however there have been continued schedule milestone adjustments for Power Supply
and Power Development.
• As of December 2019, the June 2017 budget final forecast cost remains unchanged.
• While the overall budget and final forecast cost remains unchanged, variances
between the project budget and final forecast costs have occurred within and among
expenditure categories. Most variances are related to the transfer of budget between
allocations from the contingency budget to the procurement and construction budget.
As well, there are transfers of unused budget from procurement and construction to
the contingency budget to be used in other areas of the project.
• Does not include costs for Additional Risks as reported on slide 17, which at the end
of December 2019 totaled approximately $550 Million.
• The current forecast contingency budget at December 2019 is $134.7 Million, a decrease
of $18.1 Million from the previous Quarter. For further detail see Section 4.3.
• In the November 2019 reporting period, the LTA contingency budget was reduced by $15
Million and funds were reallocated to the Project’s Other Costs - Transition to Operations
(TTO) Category. With this adjustment the project capital budget is now reset to $10,102
Million. See Annex A for the project capital budget.
23
4.1 Summary – Quarter Ending December 2019
Quarterly Planned vs Incurred Cost Variances:
• Planned expenditure by month was set in June 2017.
• During Q4 2019, the variance in planned vs. incurred cost is primarily due
to more than planned expenditure under Contract CH0031 for the Supply
and Install Mechanical and Electrical Auxiliaries, Contracts
CH0007/CH0011-002 for the Intake, Powerhouse, Transition Dams and
Spillway, and Supply and Installation of Hydro-Mechanical Equipment
under Contract CH0032.
• See Section 4.2 and Annex B for further detail.
MFGen
Cumulative Planned: $5,367M Q4 2019 Planned: $70M
Cumulative Incurred: $5,127M Q4 2019 Incurred: $95M
Variance: -$240M (-4.5%) Variance: $25M (35.7%)
24
4.1 Summary – Quarter Ending December 2019
Quarterly Planned vs Incurred Cost Variances:
• The planned expenditure by month was set in June of 2017.
• During Q4 2019, incurred was higher than planned due to extension of
work scope into 2019, whereas work scope was planned to be
substantially complete in 2018.
• See Section 4.2 and Annex B for further detail.
LITL
Cumulative Planned: $3,714M Q4 2019 Planned: $0M
Cumulative Incurred: $3,568M Q4 2019 Incurred: $13M
Variance: -$146M (-3.9%) Variance: $13M
LTA
Cumulative Planned: $889M Q4 2019 Planned: $0M
Cumulative Incurred: $865M Q4 2019 Incurred: $1M
Variance: -$24M (-2.7%) Variance: $1M
25
4.1 Summary – Quarter Ending December 2019
Planned vs Earned Progress:
• MFGen
• Cumulative progress as of end Q4 2019 was 98.5% vs. a plan of 99.8%(variance of -1.3%). Quarterly progress for Q4 2019 was 0.9% vs. a planof 0.6% (variance of 0.3%).
• During the Quarter, the cumulative variance decreased from 1.6% to1.3% behind plan.
• As noted above, progress was higher than planned during the Quarter.Rollways were completed, and progress on the Turbine and Generatorunits are progressing, however trending behind plan.
• LITL
• > 99% complete.
• LTA
• Complete.
• See Section 4.2 and Annex C for further detail.
26
4.1 Summary – Quarter Ending December 2019
Power Development:
• Overall, the project is tracking in compliance with the June 2017 budget and
schedule.
• Power Development’s project milestone schedule dates remain the same as
reported in the Committee’s Q3 2019 reporting Subsequent Events section. See
Annex D for further detail.
• As of January 24, 2019 Andritz Hydro’s progress continues to trend behind plan and
a full recovery plan has not been received by Nalcor.
• Power Development has not provided a December 2019 summary schedule
forecast as it is developing and finalizing a new forecast schedule for Units 2, 3, and
4 which will be included in period ending January 2020 Construction Reports.
• Arbitration with Astaldi continues; payment of Astaldi related liens against the
project continues; Nalcor intends to recover any costs associated from Astaldi or the
contract’s securities; responses to statements of claims and counterclaims and
document discovery ongoing.
• Other project residual contingency, funds are not held within the June 2017 budget
should net damages be awarded in Astaldi’s favour.
27
4.1 Summary – Quarter Ending December 2019
• Intake Powerhouse Transition Dams and Spillway - Remaining Construction
• Finalization of handover documentation ongoing;
• Demobilization ongoing throughout January 2020; and
• Reviewing remaining punch list scope to be completed in Summer 2020.
• Hydro Mechanical Installation
• Base Spillway scope is complete;
• Previously reported repair work associated with spillway guide and spillway
secondary concrete defects are on hold for the winter season;
• Work necessary to enable spillway operation during the spring freshet 2020 is
to be completed prior to April 1, 2020; and
• Remaining work and repair to be completed post the spring freshet.
• Balance of Plant
• Mechanic completion and commissioning activities ongoing;
• Systems to support Ready to Turn Unit 2 ongoing as work fronts from Andritz
Hydro are made available; and
• As of the end of January 2020, overall work scope is approximately 90%.
28
4.1 Summary – Quarter Ending December 2019
• Turbines and Generators
• Focus areas for Q1 2020 include commissioning of Unit 1 and ongoing installation
of Units 2-4. Forecast expenditure for Q1, 2020 is estimated at approximately $81.7
Million.
Unit % Complete (December 2019)
Status
1 96% Water Up is complete; wet commissioning commenced January 28,
2020 and Powerhouse Unit 1 Commissioned - Ready for Operation is
forecasted for March 2020.
2 78% Upper bracket assembly; installation of servo manifolds, and
fabrication/installation of oil head piping ongoing.
3 56% Rotor and runner assembly; installation of rim plates and
measurement of rotor and preparing for runner flip ongoing.
4 28% Stator piling complete; commenced installation of stator winding and
runner assembly; installation of filler strips and wedging on stator
ongoing.
29
4.1 Summary – Quarter Ending December 2019
Power Supply:
• Overall, the project remains on budget; however further schedule milestone adjustments
have occurred. The LITL Protection and Controls (P&C) bipole software remains critical
path for the overall project schedule.
• Protection and Controls (P&C) Transmission Bipole Software Status
• Software development is currently in the Factory System Test (FST) Phase;
• GE Grid started FST on December 9, 2019; as of end of January 2020 approximately only
60% of test cases have passed;
• Factory Acceptance Test (FAT) for interim bipole software scheduled for February 2, 2020
has been delayed as a result of the FST outcome as GE Grid is currently fixing
outstanding software bugs;
• Power Supply see further schedule slippage risk as high based on historical and current
performance of GE Grid;
• Progress at the Stafford software development site is slower than GE Grid planned
putting pressure on schedule milestone dates;
• GE Grid has indicated that schedule for final bipole software will slip due to resource
constraints; and
• Power Supply has a continuous presence in Stafford overseeing GE Grid’s work.
• Power Supply has not provided a December 2019 summary schedule forecast or software
milestone dates due to uncertainties in bipole software delivery schedule. Power Supply is
in discussion with GE Grid on a revised software and commissioning schedule. This
schedule will be included in period ending January Construction Reports. Existing project
schedule milestone dates can be found in Annex D.
30
4.1 Summary – Quarter Ending December 2019
Synchronous Condensers (SC)
• Vibration Root Cause Investigation
• Ontario Power Generation (OPG) concluded their Operation Deflection Shape
(ODS) test in December 2019;
• FZA (GE Power consultant) concluded their Soil Structure Interaction Analysis
in December 2019;
• Final reports are pending and GE Power will determine path forward based on
final results;
• Early observations from consultants indicated axial vibration is associated with
the Unit’s half-moon support and lateral vibration is associated with the Unit’s
foundation;
• A half-moon stiffener platform for Unit 3 has been installed; GE Power is
running the machine to test vibration levels at various start-up and operating
regimes; and
• Conceptual design for resolution of lateral vibration related to foundation is
expected in early February and includes possible attachment of the existing
synchronous foundation to the base floor slab of the synchronous condenser
building.
31
4.1 Summary – Quarter Ending December 2019
Synchronous Condensers (SC)• Binding Root Cause Investigation
• Lift Oil Twin Orifice Design• Manufacturer refused to modify lift oil orifice design of SC bearing. The manufacturer’s
opinion is that the design is sound; and
• A spare bearing has been redesigned from a twin oil orifice to a single oil pocket; installation
of the spare bearing is pending the outcome of Unit 2 testing with the modified bearing
housing circumferential slot as referenced in paragraph below.
• Bearing/Housing Apex Point• Bearing housing for Unit 2 has been modified to include a circumferential slot; re-installation
is underway; testing planned for February 2020; and
• Bearing modification for Unit 1 is complete; installation subsequent to installation and testing
of Unit 2.
• Schedule• Commissioning of all three units has moved out by a month; November schedule was
March and May 2020, current schedule is March, April and June 2020; correspondingly the
Soldiers Pond Synchronous Condenser Ready for Operation schedule milestone has
moved from May to June 2020 since the last quarterly reporting period; and
• Synchronous Condensers are not currently on the critical path and not required for low
power commissioning, however further schedule slippage remains a risk.
• For further details on schedule milestone dates see Annex D.
• The focus for Q1 2020 remains on continued completions, commissioning and
integration of operations; and the forecast expenditure for Q1 2020 is estimated at
approximately $34.2 Million.
32
4.2 Project Expenditures
Columns in tables may not total due to rounding
December 2019 ($000)
Project Budget June
2017 AFE amended
November2019
Cumulative $ Cumulative %
Plan Incurred Variance Plan Incurred VarianceDescription A B C C-B D=B/A E=C/A E-D
NE-LCP Owners Team, Admin and EPCM Services $1,115,235 $1,109,460 $1,035,990 ($73,470) 99.5% 92.9% -6.6%
Feasibility Engineering $37,072 $37,072 $35,846 ($1,226) 100.0% 96.7% -3.3%
Environmental & Regulatory Compliance $42,699 $42,509 $39,198 ($3,311) 99.6% 91.8% -7.8%
Aboriginal Affairs $17,478 $16,642 $44,553 $27,911 95.2% 254.9% 159.7%
Procurement & Construction $8,475,290 $8,681,018 $8,326,263 ($354,755) 102.4% 98.2% -4.2%
Commercial & Legal $90,423 $82,706 $78,165 ($4,541) 91.5% 86.4% -5.0%
Contingency $324,162 $0 $0 $0 0.0% 0.0% 0.0%
TOTAL $10,102,328 $9,969,406 $9,560,015 ($409,391) 98.7% 94.6% -4.1%
December 2019 ($000)
Project Budget June 2017 AFE amended
November 2019
Incurred Cumulative Costs
Project Final Forecast Cost
Variance PFC from BudgetDecember 2019 December 2019
Description A B C D=A-C
NE-LCP Owners Team, Admin and EPCM Services $1,115,235 $1,035,990 $1,164,522 ($49,287)
Feasibility Engineering $37,072 $35,846 $35,847 $1,225
Environmental & Regulatory Compliance $42,699 $39,198 $40,409 $2,290
Aboriginal Affairs $17,478 $44,553 $50,960 ($33,482)
Procurement & Construction $8,475,290 $8,326,263 $8,567,460 ($92,170)
Commercial & Legal $90,423 $78,165 $108,452 ($18,029)
Contingency $324,162 $0 $134,679 $189,483
TOTAL $10,102,328 $9,560,015 $10,102,328 $0
33
4.3 Contingency
Columns in tables may not total due to rounding
Q4 December 2019 ($000)Project Budget June 2017 AFE
March 2018 AFE
Adjustment
March 2018 AFE
Adjustment
Project Forecast Cost
Project Forecast
Cost Change from Previous Quarter
Variance PFC from Budget
September 2019
December2019
A - B C C - B C - A
Total Project $339,162 $339,162 $324,162 $152,733 $134,679 ($18,054)* ($189,483)
.
* (Includes $15 Million contingency adjustment to LTA as noted on slide 22)
34
4.4 Earned Progress
Cumulative to end of December 2019
Weight
Factor %
December 2019 Cumulative % September
2019 VariancePlanned Earned Variance
Sub-Project A B C D = C - B E
Muskrat Falls Generation (MFGen) 46.3% 99.8% 98.5% -1.3% -1.6%
Labrador Island Transmission Link (LITL) 43.9% 100.0% 99.97% -0.03% -0.1%
Labrador Transmission Asset (LTA) 9.8% 100.0% 100.0% 0.0% 0.0%
Muskrat Falls Project - Overall 100.0% 99.9% 99.3% -0.6% -0.7%
December 2019 Period
Weight
Factor %
Period %
Planned Earned Variance
Sub-Project A B C D = C - B
Muskrat Falls Generation (MFGen) 46.3% 0.2% 0.0% -0.2%
Labrador Island Transmission Link (LITL) 43.9% 0.0% 0.03% 0.03%
Labrador Transmission Asset (LTA) 9.8% 0.0% 0.0% 0.0%
Muskrat Falls Project - Overall 100.0% 0.1% 0.0% -0.1%
Columns in tables may not total due to rounding
35
Annex A
I. Project Capital Budget
II. Project Milestone Schedule
Columns in tables may not total due to rounding
36
I. Project Capital Budget
Contingency Budget (in $ thousands) November 2019 AFE
Sub-Project:
Muskrat Falls Generating Facility $226,400
Labrador-Island Transmission Link $92,750
Labrador Transmission Assets $5,012
Total Project $324,162
Muskrat Falls Generating Facility (in $ thousands) June 2017 AFE
Expenditure Category
NE-LCP Owners Team, Admin and EPCM Services $655,850
Feasibility Engineering $17,543
Environmental & Regulatory Compliance $27,125
Aboriginal Affairs $16,395
Procurement & Construction $4,501,984
Commercial & Legal $54,760
Contingency $226,400
Muskrat Falls Generation Total $5,500,056
Labrador-Island Transmission Link (in $ thousands) March 2018 AFE
Expenditure Category
NE-LCP Owners Team, Admin and EPCM Services $322,101
Feasibility Engineering $19,167
Environmental & Regulatory Compliance $14,726
Aboriginal Affairs $1,003
Procurement & Construction $3,233,690
Commercial & Legal $30,280
Contingency $92,750
Labrador-Island Transmission Link Total $3,713,716
Labrador-Transmission Assets (in $ thousands)November 2019
AFE
Expenditure Category
NE-LCP Owners Team, Admin and EPCM Services $137,284
Feasibility Engineering $363
Environmental & Regulatory Compliance $817
Aboriginal Affairs $80
Procurement & Construction $739,617
Commercial & Legal $5,383
Contingency $5,012
Labrador Transmission Assets Total $888,556
Muskrat Falls Capital Cost Budget Total $10,102,328
37
II. Project Milestone Schedule
Labrador-Island Transmission Link
June 2017 Planned Dates
SOBI Cable Systems Ready Dec-16
Soldiers Pond Switchyard Ready to Energize Aug-17
Ready for Power Transmission (LTA) Dec-17
Muskrat Falls Converter Station Ready to Energize (Pole 1) Jun-18
HVdc Transmission Line Construction Complete Dec-17
Soldier's Pond Converter Station Ready to Energize (Pole 1) Jun-18
1ST Power Transfer (Pole 1) Jul-18
Soldiers Pond Synchronous Condenser Ready for Operation Jun-18
Ready for Power Transmission (Low Load Testing Complete Pole 1) Dec-18
Muskrat Falls and Soldiers Pond Converter Stations -Bipole Dynamic Testing Complete Mar-19
Commissioning Complete -Commissioning Certificate Issued Sep-20
Labrador Transmission Assets
June 2017 Planned
Dates
HVac Transmission Line Construction Complete May-17
Churchill Falls Switchyard Ready to Energize Nov-17
Muskrat Falls Switchyard Ready to Energize Nov-17
Ready for Power Transmission Dec-17
Commissioning Complete -Commissioning Certificate Issued Sep-20
Muskrat Falls Generating Facility
June 2017 Planned Dates
North Spur Works Ready for Diversion Oct-16
River Diversion Complete Feb-17Reservoir Impoundment Complete Nov-19
Powerhouse Unit 1 Commissioned - Ready for Operation Dec-19First Power from Muskrat Falls Nov-19
Powerhouse Unit 2 Commissioned - Ready for Operation Mar-20Powerhouse Unit 3 Commissioned - Ready for Operation Jun-20Powerhouse Unit 4 Commissioned - Ready for Operation Aug-20
Full Power from Muskrat Falls Aug-20Commissioning Complete - Commissioning Certificate Issued Sep-20
38
Annex B
Project Expenditures
I. Muskrat Falls Generation
II. Labrador Island Transmission Link
III. Labrador Transmission Assets
Columns in tables may not total due to rounding
39
I. Muskrat Falls Generation
December 2019 ($000)Project Budget June
2017 AFE
Incurred Cumulative Costs
December 2019
Description A B
NE-LCP Owners Team, Admin and EPCM Services $655,850 $551,983
Feasibility Engineering $17,543 $16,865
Environmental & Regulatory Compliance $27,125 $26,828
Aboriginal Affairs $16,395 $43,759
Procurement & Construction $4,501,984 $4,438,831
Commercial & Legal $54,760 $48,846
Contingency $226,400 $0
TOTAL $5,500,056 $5,127,113
December 2019 ($000)Project Budget June 2017 AFE
Cumulative $ Cumulative %
Planned Incurred Variance Planned Incurred Variance
Description A B C C-B D=B/A E=C/A E-D
NE-LCP Owners Team, Admin and EPCM Services $655,850 $637,725 $551,983 ($85,742) 97.2% 84.2% -13.1%
Feasibility Engineering $17,543 $17,543 $16,865 ($678) 100.0% 96.1% -3.9%
Environmental & Regulatory Compliance $27,125 $26,965 $26,828 ($137) 99.4% 98.9% -0.5%
Aboriginal Affairs $16,395 $15,559 $43,759 $28,200 94.9% 266.9% 172.0%
Procurement & Construction $4,501,984 $4,622,299 $4,438,831 ($183,468) 102.7% 98.6% -4.1%
Commercial & Legal $54,760 $47,043 $48,846 $1,803 85.9% 89.2% 3.3%
Contingency $226,400 $0 $0 $0 0.0% 0.0% 0.0%
TOTAL $5,500,056 $5,367,134 $5,127,113 ($240,021) 97.6% 93.2% -4.4%
40
II. Labrador Island Transmission Link
December 2019 ($000)Project Budget
March 2018 AFE
Incurred Costs
Cumulative December 2019
Description A B
NE-LCP Owners Team, Admin and EPCM Services $322,101 $353,243
Feasibility Engineering $19,167 $18,679
Environmental & Regulatory Compliance $14,726 $11,557
Aboriginal Affairs $1,003 $625
Procurement & Construction $3,233,690 $3,160,924
Commercial & Legal $30,280 $22,748
Contingency $92,750 $0
TOTAL $3,713,716 $3,567,777
December 2019 ($000)Project Budget
March 2018 AFE
Cumulative $ Cumulative %
Plan Incurred Variance Plan Incurred Variance
Description A B C C-B D=B/A E=C/A E-D
NE-LCP Owners Team, Admin and EPCM Services $322,101 $332,101 $353,243 $21,142 103.1% 109.7% 6.6%
Feasibility Engineering $19,167 $19,167 $18,679 ($488) 100.0% 97.5% -2.5%
Environmental & Regulatory Compliance $14,726 $14,726 $11,557 ($3,169) 100.0% 78.5% -21.5%
Aboriginal Affairs $1,003 $1,003 $625 ($378) 100.0% 62.3% -37.7%
Procurement & Construction $3,233,690 $3,316,440 $3,160,924 ($155,516) 102.6% 97.7% -4.8%
Commercial & Legal $30,280 $30,280 $22,748 ($7,532) 100.0% 75.1% -24.9%
Contingency $92,750 $0 $0 $0 0.0% 0.0% 0.0%
TOTAL $3,713,716 $3,713,716 $3,567,777 ($145,939) 100.0% 96.1% -3.9%
41
III. Labrador Transmission Assets
December 2019 ($000)
Project Budget November 2019 AFE
Cumulative $ Cumulative %
Plan Incurred Variance Plan Incurred Variance
Description A B C C-B D=B/A E=C/A E-D
NE-LCP Owners Team, Admin and EPCM Services $137,284 $139,634 $130,764 ($8,870) 101.7% 95.3% -6.5%
Feasibility Engineering $363 $363 $303 ($60) 100.0% 83.5% -16.5%
Environmental & Regulatory Compliance $817 $817 $812 ($5) 100.0% 99.4% -0.6%
Aboriginal Affairs $80 $80 $168 $88 100.0% 209.7% 109.7%
Procurement & Construction $739,617 $742,279 $726,508 ($15,771) 100.4% 98.2% -2.1%
Commercial & Legal $5,383 $5,383 $6,571 $1,188 100.0% 122.1% 22.1%
Contingency $5,012 $0 $0 $0 0.0% 0.0% 0.0%
TOTAL $888,556 $888,556 $865,126 ($23,430) 100.0% 97.4% -2.6%
December 2019 ($000)
Project Budget November 2019
AFE
Incurred Costs
Cumulative December 2019
Description A B
NE-LCP Owners Team, Admin and EPCM Services $137,284 $130,764
Feasibility Engineering $363 $303
Environmental & Regulatory Compliance $817 $812
Aboriginal Affairs $80 $168
Procurement & Construction $739,617 $726,508
Commercial & Legal $5,383 $6,571
Contingency $5,012 $0
TOTAL $888,556 $865,126
42
Annex C
Earned Progress
I. Overall Construction
II. Muskrat Falls Generation
III. Labrador Island Transmission Link
IV. Labrador Transmission Assets
Columns in tables may not total due to rounding
43
I. Overall Construction
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
May
-13
Jun
-13
Jul-
13
Au
g-1
3
Se
p-1
3
Oct-
13
No
v-1
3
Dec-1
3
Jan
-14
Fe
b-1
4
Mar-1
4
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Se
p-1
4
Oct-
14
No
v-1
4
Dec-1
4
Jan
-15
Fe
b-1
5
Mar-1
5
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Se
p-1
5
Oct-
15
No
v-1
5
Dec-1
5
Jan
-16
Fe
b-1
6
Mar-1
6
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Se
p-1
6
Oct-
16
No
v-1
6
Dec-1
6
Jan
-17
Fe
b-1
7
Mar-1
7
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct-
17
No
v-1
7
Dec-1
7
Jan
-18
Fe
b-1
8
Mar-1
8
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Au
g-1
8
Se
p-1
8
Oct-
18
No
v-1
8
Dec-1
8
Jan
-19
Fe
b-1
9
Mar-1
9
Ap
r-1
9
May
-19
Jun
-19
Jul-
19
Au
g-1
9
Se
p-1
9
Oct-
19
No
v-1
9
Dec-1
9
Jan
-20
Fe
b-2
0
Mar-2
0
Ap
r-2
0
May
-20
Jun
-20
Cu
mu
lati
ve
Pro
gre
ss
Pe
rio
d P
rog
ress
OVERALL CONSTRUCTION/COMMISSIONING PROGRESS CURVE
Overall Period Planned
Overall Period Earned
Overall Period Forecast
Overall Cuml Planned
Overall Cuml Earned
Overall Cuml Forecast
44
II. Muskrat Falls Generation
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
May
-13
Jun
-13
Jul-
13
Au
g-1
3
Se
p-1
3
Oct-
13
No
v-1
3
Dec-1
3
Jan
-14
Fe
b-1
4
Mar-1
4
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Se
p-1
4
Oct-
14
No
v-1
4
Dec-1
4
Jan
-15
Fe
b-1
5
Mar-1
5
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Se
p-1
5
Oct-
15
No
v-1
5
Dec-1
5
Jan
-16
Fe
b-1
6
Mar-1
6
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Se
p-1
6
Oct-
16
No
v-1
6
Dec-1
6
Jan
-17
Fe
b-1
7
Mar-1
7
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Se
p-1
7
Oct-
17
No
v-1
7
Dec-1
7
Jan
-18
Fe
b-1
8
Mar-1
8
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Au
g-1
8
Se
p-1
8
Oct-
18
No
v-1
8
Dec-1
8
Jan
-19
Fe
b-1
9
Mar-1
9
Ap
r-1
9
May
-19
Jun
-19
Jul-
19
Au
g-1
9
Se
p-1
9
Oct-
19
No
v-1
9
Dec-1
9
Jan
-20
Fe
b-2
0
Mar-2
0
Ap
r-2
0
May
-20
Jun
-20
Jul-
20
Jul-
20
Jul-
20
Cu
mu
lati
ve
Pro
gre
ss
Pe
rio
d P
rog
ress
MFG CONSTRUCTION/COMMISSIONING PROGRESS CURVE
MFG Period Planned
MFG Period Earned
MFG Period Forecast
MFG Cuml Planned
MFG Cuml Earned
MFG Cuml Forecast
45
II. Muskrat Falls Generation
December 2019Weight
Factor %
December 2019 Cumulative % September 2019
VariancePlan Earned Variance
Sub-Project A B C D = C - B E
MFG Road/Camp/Constr. Power 8.9% 100.0% 100.0% 0.0% 0.0%
MFG Reservoir Preparation 5.8% 100.0% 100.0% 0.0% 0.0%
MFG Spillway & Gates 12.2% 100.0% 100.0% 0.0% -1.8%
MFG North Spur Stabilization 3.9% 100.0% 100.0% 0.0% 0.0%
MFG North Dam 5.7% 100.0% 100.0% 0.0% 0.0%
MFG Powerhouse & Intake 61.3% 99.7% 97.6% -2.1% -2.1%
MFG South Dam 1.1% 100.0% 100.0% 0.0% 0.0%
MFG Misc:Eng/ 315kV/Site Rest./logistic 1.1% 97.0% 99.1% 2.1% -4.3%
MFGen - Overall 100.0% 99.8% 98.5% -1.3% -1.6%
* Adjusted for MFGen rollway installation schedule N/A N/A N/A N/A
46
III. Labrador Island Transmission Link
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
May
-13
Jun
-13
Jul-
13
Au
g-1
3
Sep
-13
Oct
-13
No
v-1
3
Dec
-13
Jan
-14
Feb
-14
Mar
-14
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Sep
-14
Oct
-14
No
v-1
4
Dec
-14
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Oct
-15
No
v-1
5
Dec
-15
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Jan
-17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
Dec
-17
Jan
-18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Au
g-1
8
Sep
-18
Oct
-18
No
v-1
8
Dec
-18
Jan
-19
Feb
-19
Mar
-19
Ap
r-1
9
May
-19
Jun
-19
Jul-
19
Au
g-1
9
Sep
-19
Oct
-19
No
v-1
9
Dec
-19
Jan
-20
Feb
-20
Mar
-20
Ap
r-2
0
May
-20
Jun
-20
Cu
mu
lati
ve
Pro
gre
ss
Pe
rio
d P
rogr
ess
LITL CONSTRUCTION/COMMISSIONING PROGRESS CURVE
LITL Period Planned
LITL Period Earned
LITL Period Forecast
LITL Cuml Planned
LITL Cuml Earned
LITL Cuml Forecast
47
III. Labrador Island Transmission Link
December 2019Weight December 2019 Cumulative % September 2019
VarianceFactor % Plan Earned Variance
Sub-Project A B C D = C - B E
LITL Muskrat Falls Converter 6.1% 100.0% 99.9% -0.1% -0.3%
LITL Soldiers Pond Converter 5.5% 100.0% 99.6% -0.4% -0.6%
LITL HVdc Transmission Line Seg 1/2 26.8% 100.0% 100.0% 0.0% 0.0%
LITL HVdc Transmission Line Seg 3/4/5 34.2% 100.0% 100.0% 0.0% 0.0%
LITL Electrode Sites 0.8% 100.0% 100.0% 0.0% 0.0%
LITL Transition Compounds 1.7% 100.0% 100.0% 0.0% 0.0%
LITL SOBI Cable Crossing 17.7% 100.0% 100.0% 0.0% 0.0%
LITL Soldiers Pond Switchyard 2.7% 100.0% 100.0% 0.0% 0.0%
LITL Soldiers Pond Sync. Condensors 3.1% 100.0% 99.9% -0.1% -0.1%
LITL Misc 1.4% 100.0% 100.0% 0.0% 0.0%
LITL- Overall 100.0% 100.0% 99.97% -0.03% -0.06%
48
IV. Labrador Transmission Assets
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
May
-13
Jun
-13
Jul-
13
Au
g-1
3
Sep
-13
Oct
-13
No
v-1
3
Dec
-13
Jan
-14
Feb
-14
Mar
-14
Ap
r-1
4
May
-14
Jun
-14
Jul-
14
Au
g-1
4
Sep
-14
Oct
-14
No
v-1
4
Dec
-14
Jan
-15
Feb
-15
Mar
-15
Ap
r-1
5
May
-15
Jun
-15
Jul-
15
Au
g-1
5
Sep
-15
Oct
-15
No
v-1
5
Dec
-15
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
Dec
-16
Jan
-17
Feb
-17
Mar
-17
Ap
r-1
7
May
-17
Jun
-17
Jul-
17
Au
g-1
7
Sep
-17
Oct
-17
No
v-1
7
Dec
-17
Jan
-18
Feb
-18
Mar
-18
Ap
r-1
8
May
-18
Jun
-18
Jul-
18
Au
g-1
8
Sep
-18
Oct
-18
No
v-1
8
Dec
-18
Jan
-19
Feb
-19
Mar
-19
Ap
r-1
9
May
-19
Jun
-19
Jul-
19
Au
g-1
9
Sep
-19
Oct
-19
No
v-1
9
Dec
-19
Cum
ula
tive
Pro
gres
s
Per
iod
Pro
gres
s
LTA CONSTRUCTION/COMMISSIONING PROGRESS CURVE
LTA Period Planned
LTA Period Earned
LTA Period Forecast
LTA Cuml Planned
LTA Cuml Earned
LTA Cuml Forecast
49
IV. Labrador Transmission Assets
December 2019
Weight December 2019 Cumulative %September
2019 VarianceFactor % Plan Earned Variance
Sub-Project A B C D = C – B E
LTA HVac Transmission Line Seg1/2 - MF to CF 62.8% 100.0% 100.0% 0.0% 0.0%
LTA Churchill Falls Switchyard 21.7% 100.0% 100.0% 0.0% 0.0%
LTA Muskrat Falls Switchyard 13.4% 100.0% 100.0% 0.0% 0.0%
LTA Misc 2.1% 100.0% 100.0% 0.0% 0.0%
LTA - Overall 100.0% 100.0% 100.0% 0.0% 0.0%
50
Annex D
Project Milestone Schedule Forecast
I. Muskrat Falls Generation
II. Labrador Island Transmission Link
III. Labrador Transmission Assets
51
I. Muskrat Falls Generation
December 2019
Planned Date
June 2017December 2019
Actual/Forecast
Project Sanction 17-Dec-12 Complete
North Spur Works Ready for Diversion 31-Oct-16 Complete
River Diversion Complete 15-Feb-17 Complete
Reservoir Impoundment Complete 1-Nov-19 Complete
Powerhouse Unit 1 Commissioned - Ready for Operation 19-Dec-19 215-Mar-2020
First Power from Muskrat Falls 2-Nov-19 115-Feb-20
Powerhouse Unit 2 Commissioned - Ready for Operation 3-Mar-20 316-April-2020
Powerhouse Unit 3 Commissioned - Ready for Operation 9-Jun-20 9-Jun-20
Powerhouse Unit 4 Commissioned - Ready for Operation 14-Aug-20 14-Aug-20
Full Power from Muskrat Falls 14-Aug-20 14-Aug-20
Commissioning Complete - Commissioning Certificate Issued 1-Sep-20 1-Sep-20
1 > 3 month forecast date adjustment beyond the June 2017 planned date as reported in Committee Q3 2019 reporting Subsequent Events.2 < 3 month forecast date adjustment beyond the June 2017 planned date as reported in Committee Q3 2019 reporting Subsequent Events.3 > 1 month forecast date adjustment beyond the June 2017 planned date as reported in Committee Q3 2019 reporting Subsequent Events.
52
II. Labrador Island Transmission Link
December 2019
Planned Date
June 2017
December 2019
Actual/forecast
Project Sanction 17-Dec-12 Complete
SOBI Cable Systems Ready 9-Dec-16 Complete
Soldiers Pond Switchyard Ready to Energize 31-Aug-17 Complete
Ready for Power Transmission (LTA) 31-Dec-17 Complete
Muskrat Falls Converter Station Ready to Energize (Pole 1) 1-Jun-18 Complete
HVdc Transmission Line Construction Complete 31-Dec-17 Complete
Soldier's Pond Converter Station Ready to Energize (Pole 1) 1-Jun-18 Complete
1ST Power Transfer (Pole 1) 1-Jul-18
Completion of 45
megawatt heat run
Soldiers Pond Synchronous Condenser Ready for Operation 1-Jun-18 1 30-June-2020
Ready for Power Transmission (Low Load Testing Complete Pole 1) 1-Dec-18 Complete
Muskrat Falls and Soldiers Pond Converter Stations - Bipole Dynamic Testing Complete 31-Mar-19 215-July-20
Commissioning Complete - Commissioning Certificate Issued 1-Sep-20 1-Sep-20
1 = 1month forecast date adjustment since Committee Q3 2019 reporting Subsequent Events. 2 < 1month forecast date adjustment as reported in Committee Q3 2019 reporting Subsequent Events.
53
III. Labrador Transmission Assets
December 2019
June 2017 Budget
Planned Date
December 2019
Actual/Forecast
Project Sanction 17-Dec-12 Complete
HVac Transmission Line Construction Complete 31-May-17
Complete: Turnover of HVac TL
and all subsystems complete
Churchill Falls Switchyard Ready to Energize 30-Nov-17 Complete
Muskrat Falls Switchyard Ready to Energize 30-Nov-17 Complete
Ready for Power Transmission 31-Dec-17 Complete
Commissioning Complete - Commissioning Certificate Issued 1-Sep-20 1-Sep-20
54
End of Report