Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013.
-
Upload
myrtle-allison -
Category
Documents
-
view
218 -
download
2
Transcript of Muon Campus AIP Review MC-1 Building GPP Update Russ Alber FESS Engineering January 23, 2013.
MC-1 Building GPP Milestone Schedule
MILESTONE DEFINITION BASELINE PERCENT COMPLETE
Start Project Directive signed April 2012 100%
Start Engineering Engineering work for the project starts when a task is entered into the Task Database
May 2012 100% Site Prep90% Building
Begin Construction Notice To Proceed/Purchase Order Issued
January 2013 NTP Site PrepJanuary 10, 2013
Construction Complete Final acceptance of all work September 2014 0%
Engineering Complete Completion of Close-out Documents
December 2014 0%
Project Complete Project Closed March 2015 0%
MC-1 Building GPP Scope
Construction split into two packages to expedite construction:
Package A – MC-1 Building Site Prep ($742.5K FY13)Goal is to 1) relocate all utilities out of building excavation, and
2) perform all shutdown work during current
shutdown Relocate/tap into utilities:
Chilled Water Supply & Return (CHWS, CHWR)
Domestic Water Supply (DWS)
Gas (GAS)
Industrial Cooling Water (ICW)
Sanitary Sewer and new lift station (SAN)
Electrical ductbank and manholes
Communication ductbank and handholes
Relocate Well Pond Road (shutdown work)
Install cryo line supports and under-road piping (shutdown work)
MC-1 Building GPP Scope
Package A – MC-1 Building Site Prep – CURRENT STATUS
Cost Estimate: $1.096M – Low Bid: $742.5K Whittaker Construction Construction documents are located here:ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/6-10-20A - Issued for Bids/
Notice of Intent & Storm Water & Pollution Prevention Plan (NOI & SWPPP) has been submitted to Illinois Environmental Protection Agency (IEPA) on November 1, 2012. Construction can begin December 1, 2012.
• Revision No. 1 to incorporate entire Muon Campus including Mu2e approved.
ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/NOI & SWPPP/
Radiation Safety Drawings created for all work within the vicinity of the 8 GeV beamline. Reviewed by AD/Radiation Safety and awaiting final approval for construction.
ftp://fess-ftp.fnal.gov/public/Projects/MC-1 Building/Radiation Drawings/
MC-1 Building GPP Scope
Package B – MC-1 Building ($4.0M FY13, $0.8M FY14)
60% Review completed October 24, 2012
95% Review (Lab Wide) – February 1, 2013 (est.)
Issue for Bids – March 2013 (est.)
Pre-procurements (FY13) 1,500 kVA Transformer - $125K
(pad installed under building package for current and future transformers)
15 kV Switch - $20K
30 Ton Building Crane - $175K